the effects of arbitration on the building industry
TRANSCRIPT
-
7/29/2019 The Effects of Arbitration on the Building Industry
1/83
1
CHAPTER ONE
1.0 INTRODUCTION
1.1 BACKGROUND
The construction industry plays a very important role in contributing
significantly to the Gross Domestic Product (GDP) of any country. And it accounts
for around one-tenth of the worlds GDP, seven percent of employment, half of all
resource usage and up to 40 percent of energy consumption (United Nations
Environment Programme, UNEP report, 1996). This industry has a profound
impact on our daily lives: the buildings we live and work in, the roads and bridges
we drive on, the utility distributions systems we use, the railways, airports and
harbours we travel and trade from are all products of this vital industry. Sometimes,
in this developmental process, certain disputes are bound to arise in the
construction industry.
Construction industry based disputes are technically complex more often
than not, meaning that their investigations will be much more fact intensive than
other types of disputes. Arbitration is dispute resolution process in which the
disputing parties present their case to a third party intermediary (or a panel of
arbitrators) that examine all the evidences and then make a decision for the
parties. This decision is usually binding.
According to David Musil, (2008), The Construction industry is dynamic
and competitive environment. Relationship within construction, between clients,
contractors, sub-contractors and suppliers, are often adversarial. The
-
7/29/2019 The Effects of Arbitration on the Building Industry
2/83
2
presentations are made to prove one side right, the other wrong. Thus the parties
assume they are working against each other, not cooperatively. Arbitration is
generally not as formal as court adjudication, however, and the rules can be
altered to some extent to meet the parties needs.
Arbitration is the referral of a dispute to one or more impartial persons for final
and .economical. Parties can exercise additional control over the arbitration process
by adding specific provisions to their contract's arbitration clause or, when a
dispute arises, by modifying certain of the arbitration rules to suit a particular
dispute.
1.2 STATEMENT OF THE PROBLEM
Great concern has been expressed in recent years regarding the dramatic in
conflict and disputes in the construction industries of many countries and the
attendant high cost both in terms of direct cost (lawyers, claims consultants,
management time, delays to project completions) and indirect/ consequential
costs (degeneration of working relationships, mistrust between participants, lack
of teamwork and resultant poor standard of workmanship) Koh Cheo Poh, 2005.
There exist several parties in the construction industry and this most times
open up to many problems such as misunderstanding, different opinion and
controversy, regarding the construction work and the contract agreement. If the
disputes/ problems are not resolved in a proper manner, they (the parties
-
7/29/2019 The Effects of Arbitration on the Building Industry
3/83
3
involved) will experience serious problems such as delay in work, financial
losses and endless disputes (Aberra Bekele, 2005).
When construction disputes cannot be resolved informally, disputes may lead to
arbitration. If the construction disputes not able to reach the agreement between
two parties or more, it will be litigation case. Construction disputes may end up
involvement of high stakes such as multi-million Naira investments,
professional reputations and even business survival of the owner. As to which
method or technique is popularly accepted in the Nigerian construction industry,
this paper tends to focus on establishing the cause or causes of these disputes
and how they affect output, productivity and profitability of the construction
industry and how arbitration can be employed in resolving these disputes.
1.3 AIM AND OBJECTIVES OF STUDY
The aim or purpose of this project is to reveal useful and practical
information on the concept of arbitration and the acceptance and
implementation of arbitration as one of the methods of dispute resolution in the
Nigerian construction industry.
In order to achieve the above aim, objectives of this project have been
formulated. The primary objectives of this project are:
a) To study the nature of disputes and the resolution techniques in theNigerian Construction Industry.
b) To study the process and procedures of arbitration in the NigerianConstruction Industry.
-
7/29/2019 The Effects of Arbitration on the Building Industry
4/83
-
7/29/2019 The Effects of Arbitration on the Building Industry
5/83
5
d) The survey of local (Nigerian) contractors to gain information about theuse of arbitration and its acceptance in the local construction industry.
The project will highlight the implementation of arbitration and how it can
contribute to the Nigerian construction industry, the advantages and
disadvantages of arbitration. And also other alternative methods besides
arbitration that can be employed to ensure the success of the settlement process
of disputes.
1.6 ABBREVIATIONS
FIDICInternational Federation of Consulting Engineers.
RIBARoyal Institute of British Architects.
NIANigerian Institute of Architect.
ADR - Alternative Dispute Resolution
DRA - Dispute Review Advisor
DRB - Dispute Review Board
DRE - Dispute Review Expert
IPImportant Index
-
7/29/2019 The Effects of Arbitration on the Building Industry
6/83
6
CHAPTER TWO
2.0 INTRODUCTION
This chapter will provide general information about the nature of disputes,
definition and causes that can lead to disputes, what arbitration is, and also how
arbitration can be employed in resolving various construction disputes. At the
end of this chapter, construction disputes are categorised according to their
characteristics. This chapter will also fulfil the first objective of this project.
It is pertinent here, as general background information, to briefly describe or
refer to the various types of building contract that are normally employed in the
building and engineering industry. Quite commonly, standard forms of
agreement are used when letting out a building or engineering contract. A
standard form is an agreement that has been drafted and or approved by a body
such as Architects, Engineers, Contractors or other international association
or professional institution. It is generally accepted and used by these bodies or
institution with or without amendments. The obvious advantage of using such
standard forms is convenience and familiarity, as all parties concerned would
have had experience and knowledge of the conditions contained in such forms.
Also, it would cut down the cost of drafting a special agreement and avoid the
loss of time that would usually be required to draft an agreement afresh. The
usual standard forms of agreement used in Nigeria (and quite commonly in
other Commonwealth countries its equivalent standard form) are the NIA
-
7/29/2019 The Effects of Arbitration on the Building Industry
7/83
7
(Nigerian Institute of Architect) standard form of Contract, FIDIC
(International Federation of Consulting Engineer), & ICE forms of contract
(Nor Azim, 2003).
The FIDIC form of agreement is usually used in an international contract
such as those let out by the World Bank, Asian Development Bank or by the
government departments, which are under certain obligation to use the FIDIC
form of agreement. Another standard form of agreement is the ICE form of
contract, which is introduced by the institute of Engineers and is usually used in
a contract involving engineering works. The other standard form of agreement
is the PAM contract, which is based on the RIBA (Royal Institute of British
Architects) form of agreement and is used for building works.
Where standard forms of agreements are not used, then specifically drafted
contract will be used incorporating terms and the parties involved may agree to
conditions as. Some owners or employers prefer to use a specifically drafted
agreement to cater to the special circumstances that may be involved or that
may arise in the course of the work.
Under prevailing circumstances, building and engineering contract have
become more difficult to administer or execute due to increase in complexity
and magnitude of such works. Added to this there is a tendency to amend or add
to the standard forms of contract without proper advice or consideration as to
the consequences of such amendment or addition. Where a specific situation
requires certain provision or omitted from the usual terms and conditions, it
-
7/29/2019 The Effects of Arbitration on the Building Industry
8/83
8
would be far more prudent to seek proper legal advice and if necessary to have a
contract specially drafted to cover such situation rather than attempt a do-it-
yourself amendment or alteration of the contract which may lead to ambiguity
or confusion giving rise to disputes.
One of the most common causes of disputes is the misinterpretation or
misunderstanding of the powers, duties and responsibility of the parties. It is not
usual to find that both the administrating party (i.e. the Architect or the
Engineer or the Superintending officer) and the contractor are quite vague
regarding the extent of their obligations, powers and responsibilities. This is
exacerbated by their reluctance to seek advice to ascertain the exact position in
any given situation in relation to the contract (Koh Cheo Poh, 2005).
However, in the event that the parties cannot come to an amicable settlement on
disputes then the only course of action remaining would be to submit such
dispute for resolution by a third party which normally in a building or
engineering contract would usually provide the proper procedures for the
reference of any matter or differences arising from the contract for arbitration.
In this respect, it is necessary to ascertain when a dispute has taken place and
when such dispute has come within the scope of the arbitration clause. But it
should be borne in mind that arbitration is normally the ultimate course in a
building or engineering contract after all efforts to resolve any disputes have
failed.
-
7/29/2019 The Effects of Arbitration on the Building Industry
9/83
9
2.1 DISPUTES IN CONSTRUCTION
Disputes can be defined, according to the Law Encyclopaedia, as a conflict
or controversy; a conflict of claims or rights; an assertion of a right, claim, or
demand on one side, met by contrary claims or allegations on the other. Dispute
is the process of expressing dissatisfaction, disagreement, or unmet expressions.
Conflict is ongoing, amorphous and intangible (Costantino and Merchant
1996).
Disputes can arise from the interpretation and or application of any part of
the contract documents and at any time during the execution of the contract. If
the contract documents are ambiguous, unplanned and conflicting they will
most certainly lead to disputes. In addition to disputes, conflict can manifest
itself in a variety of other ways- sabotage, lack of productivity, low morale, and
withholding information are some examples. Such situation can be further
aggravated if numerous additions and omissions are made to the contract and
the persons responsible for the administration of the contract on both sided are
badly equipped to understand and apply the contract documents, (including
instructions to tenderers, agreement and conditions of contract, specifications,
drawings and bills of quantities and with annexure which form part of the
contract). It can be said that the seeds of disputes are sown right from the outset
if the above-described situation exist in any contract. Where ambiguous or
conflicting provisions do exist and disputes do arise, there is a need to ascertain
-
7/29/2019 The Effects of Arbitration on the Building Industry
10/83
10
if a dispute has arisen or whether the dispute can be amicably resolved before
referring such disputes to arbitration.
2.2 CAUSES OF CONSTRUCTION DISPUTES
There is a great deal in the literature, as to the causes of conflict and
disputes. There is also a profusion of key terminology. Some writers refer to
causes of conflict, others sources reasons, or triggers.
The following are identified as causes of disagreements from literature survey:
(Aberra Bekele, 2005)
a) Misunderstandings usually occur because of poor communication.
b)Values differ between people, professionals and skills,
c) People often have unrealistic expectations. The client wants speedy
completion and a quality building at a low price. The contractor may
want more time, a more reasonable quality and maximum price.
d)Emotions play a role, the ability to handle stress causes conflict. A
persons selfesteem (or lack of it) can cause also conflict. Factors under
this heading include languages, dynamics, geography, childhood
experiences, upbringing and religion.
e) Education levels, both structured and unstructured learning can have an
influence on conflict.
f) Many things are different between projects. There are different teams,
different funders and designers.
-
7/29/2019 The Effects of Arbitration on the Building Industry
11/83
11
g)Not all people are equally skilled to visualize two-dimensional drawings
in a three dimensional way.
h)Changes to plans, deadlines, payment dates, and so on, can cause conflict.
i) It does not matter whom or what one must blame for a delay. It could be
the weather, a subcontractor, the bank or whoever. The mere fact that
there is a delay could cause conflict.
j) Parties often inadequately define quality. High quality may mean
different things to a plasterer and to the project director or project
manager. One must use objective standards to define materials and
workmanship. One must precisely describe what one requires. A client
may specify a much higher standard than what he really wants while
wanting a lower price.
k)A sub-contractor may misunderstand the actual requirements and may
quote a lower price than other contractors may, then when he realizes his
mistake, conflict results.
2.3 TYPES OF CONSTRUCTION DISPUTES
Sundra Rajoo, 2010, identified the various disputes which are brought for
resolution in arbitration which is equally applicable in Nigeria. They are as
follows:
(A)Determination of Agreement
Disputes caused by the determination of the agreement are as follows:
-
7/29/2019 The Effects of Arbitration on the Building Industry
12/83
12
(1) The failure of the contractor or sub-contractor to proceed in a competent,
diligent and satisfactory rate
(2) The contractor or sub-contractor ceasing work on site.
(3) The employer repudiating the contract by denying contractor access to site,
not making progress payment, being insolvent or claiming to determine the
contract.
(B) Payment and Time
Disputes caused by the payment issues are as follows:
(1) Non-payment of variation claims by contractor or sub-contractor.
(2) Non-payment of progress claims by contractor or sub-contractor.
(3) Non-payment of amount certified in final account.
(4) Extension of time costs claims by contractor or sub-contractor.
(5) Liquidated and ascertained damages charged against the contractor or sub-
contractor.
(6) Retention monies not held in separate account by contractor.
(7) Validity of final account and certificate.
(8) Contractor claim sums for fluctuation of prices.
(C) Execution of Works and Delay
Execution of work issues are as follows:
(1) Changes in sub-structure design and lack of temporary support during
excavations
-
7/29/2019 The Effects of Arbitration on the Building Industry
13/83
13
(2) Defective materials and claims of negligent manufacture and supply
(3) Poor quality of workmanship including defects in brickworks, tiling, footing
and wall construction.
(4) Delays and extension of time due to local authorities requirements.
(5) Negligence and nuisance.
2.4 AREAS THAT CAN GENERATE CONSTRUCTION DISPUTES
There are some specific areas of the design and construction process that can
generate conflict. Aberra Bekele (2005), identified five (5) of them and they
include the following:
2.4.1. THE DESIGN
An incomplete, inaccurate or poorly coordinated design inevitably will
produce a project with conflicts and unanticipated costs and delay. Conversely,
nothing diminishes the risk of misunderstanding and litigation, and provides
more protection for the owner, than an accurate and complete design. The
traditional single prime contract can succeed only if, when the contract is
priced, the plans and specifications are reasonably detailed and complete.
Otherwise, the contract sum becomes an unreliable figure subject to changes
and claims for delays and impact damages.
However, in order to obtain a complete and accurate design, the owner must
give its architect/engineer a reasonable period to develop a complete set of plans
and specifications, and provide a fair fee for that service. The owner who
-
7/29/2019 The Effects of Arbitration on the Building Industry
14/83
14
pinches pennies with its architect and sets an unreasonable schedule invites
substandard plans/specifications, and time and cost overruns. The owners
failure to pay fairly for adequate design and engineering will drive its design
team to use off-the-shelf specifications and uncoordinated drawings, requiring
the contractor and the design team to design the project as construction
progresses. For similar reasons, fast-track construction increases the risk of
misunderstanding and litigation. While commencing construction before a
complete design is in place may be justified by the owners economic needs, the
costs and risks of that approach should be considered when estimating cost and
projecting completion dates.
2.4.2. SITE CONDITIONS
Views differ on whether, and to what extent, a contract should provide
additional compensation for differing site conditions. Some forms of contracts
include a differing site conditions clause, which entitles the contractor to
additional compensation for unexpected subsurface conditions meeting certain
criteria. Some owners (public and private) model their contracts on these forms.
Other owners utilize contracts that are silent on the issue, or expressly prohibit
recovery for differing site conditions while placing all of the risk of the
unknown on the contractor.
The assurance of equitable compensation for differing site conditions
encourages cautious contractors to submit lower bids, unencumbered by
-
7/29/2019 The Effects of Arbitration on the Building Industry
15/83
15
contingencies for unknown conditions. Perhaps just as importantly, a differing
site conditions clause helps protect prudent contractors against being underbid
by competitors who are either too careless or too reckless to include such a
contingency. Because hidden conditions can make the difference between a
profitable contract and a financial disaster, competent contractors often insist on
an equitable adjustment clause before submitting a bid on a job with significant
risk of differing site conditions. No matter which approach is taken, the wise
owner will make a thorough subsurface investigation so that as much can be
known about the site as possible. That information should be shared with the
contractor whether performing under a differing site clause or as a part of a
contract with exculpatory language. Reliable structural engineering and design,
and realistic pricing by the contractor, cannot be generated in the absence of
such knowledge. A good exploratory program by a competent engineering firm
will diminish misunderstandings and disputes resulting from extra work and
foundation failures. The quality of this investigation, as much as an exculpatory
clause, will diminish disagreements leading to litigation.
2.4.3. SITE SERVICES
Generally, the owner has no contractual obligation to provide for inspection
or site monitoring. The contractor has the obligation to provide its work in
accordance with the plans and specifications, and free from defect.
Nevertheless, the cautious owner will provide on-site representatives for
-
7/29/2019 The Effects of Arbitration on the Building Industry
16/83
16
significant projects. That representative may be from the consultants office or
he/she may be a permanent employee of an owner who does major construction
work. Unfortunately, some owners, even on large projects, attempt to avoid
overhead costs by cutting corners here. Even if the owner ultimately proves that
the contractor made a bad pour or connected the steel improperly, it is infinitely
better that discover the defect early rather than well into the construction stage,
where litigation is usually the result. A good inspection is the contractors and
owners best friend. It is just common sense for the owner to protect itself from
the catastrophic consequence of others failures.
2.4.4. WHO IS IN CHARGE?
A careful reading of some construction contracts makes it difficult to find
anyone in charge. The architect/engineer often provides generic specifications,
pushing true design responsibilities for specialty items down through the prime
contractor to various sub-levels of subcontractors and suppliers. There might be
conflict when no one was in charge, with each of the parties attempting to shift
the risk to another. The owner and its architect/engineer, whatever their
approach to exculpatory and risk-shifting provisions, should carefully review
technical data to make certain that the project will function, that means even if
an owner has to employ outside consultants or experts during the construction
stages. The contractor also should not allow its subcontractors work to be
performed and integrated into the project without careful observation. The
-
7/29/2019 The Effects of Arbitration on the Building Industry
17/83
17
contractor is responsible for its subcontractors. He is in charge for their work,
and needs to assure that it is properly done.
2.4.5. CONTRACTOR SUBMITTALS
The shop drawing process seeks to avoid failures and misunderstandings by
allowing the contractor to demonstrate the detailed application of the
architect/engineers design. It is here that the prime contractor, the owner and
architect have the best opportunity to avoid nonconforming products or
defective work. Unfortunately, prime contractors are often approving
subcontractors or supplier submittals while relying on the architect/engineer for
final approval or disapproval.
Although the architect has final legal responsibility to approve or reject shop
drawings, a contractor who does not give time and attention to this area
substantially increases the risk of failure and litigation. Contractors have a
substantial self-interest in making sure that material and equipment suppliers
conform to the design plans, and that unauthorized changes have been made. In
short, all parties who have the opportunity to review shop drawings bear the
responsibility to do so in order to assure successful project completion, no
matter what the contract provides.
-
7/29/2019 The Effects of Arbitration on the Building Industry
18/83
18
2.5.0 DISPUTE RESOLUTION
Dispute resolution is the process of resolving disputes between parties. The
legal system provides a necessary structure for the resolution of many disputes.
However, some disputants will not reach agreement through a collaborative
process. Some disputes need the coercive power of the state to enforce a
resolution. Perhaps more importantly, many people want a professional
advocate when they become involved in a dispute, particularly if the dispute
involves perceived legal rights, legal wrongdoing, or threat of legal action
against them.
The most common form of judicial dispute resolution is litigation. Litigation
is initiated when one party files suit against another. In the Nigeria, litigation is
facilitated by the government within federal, state, and municipal courts. The
proceedings are very formal and are governed by rules, such as rules of
evidence and procedure, which are established by the legislature. Outcomes are
decided by an impartial judge and/orjury, based on the factual questions of the
case and the application law. The verdict of the court is binding, not advisory;
however, both parties have the right to appeal the judgment to a higher court.
Judicial dispute resolution is typically adversarial in nature, e.g., involving
antagonistic parties or opposing interests seeking an outcome most favourable
to their position.
http://en.wikipedia.org/wiki/Party_%28law%29http://en.wikipedia.org/wiki/United_Stateshttp://en.wikipedia.org/wiki/Judgehttp://en.wikipedia.org/wiki/Juryhttp://en.wikipedia.org/wiki/Juryhttp://en.wikipedia.org/wiki/Judgehttp://en.wikipedia.org/wiki/United_Stateshttp://en.wikipedia.org/wiki/Party_%28law%29 -
7/29/2019 The Effects of Arbitration on the Building Industry
19/83
19
2.5.1 TYPES OF DISPUTE RESOLUTION METHODS
The two most popular and most common types of alternative dispute
resolution are mediation and arbitration. All other forms of dispute resolution
are highlighted below:
1. Litigation
Litigation (used when all other venues failed) is a dispute resolution
method that is inquisitorial and adversarial, where by the disputant initiates
legal action against the other party by going to court. It has a win/lose outcome
and rarely satisfies both parties. It is costly and results into much delay for the
disputants and may not do justice to the parties. However, the benefit of
litigation is that the court has authority to find out the truth from the parties
and the enforcement of the order or judgment is supported by other law
enforcement agencies. It is also used when parties have low resources and need
an umpire or when they cannot agree to other forms of dispute resolution.
2. Convening
Convening identifies the issues in dispute and selects the personnel
responsible for resolving the matter. The neutral, called a convenor, helps to
bring the parties together in order to begin negotiating a solution. Once the
parties have convened, they may use other ADR techniques to resolve the issues
in dispute.
-
7/29/2019 The Effects of Arbitration on the Building Industry
20/83
20
3. Conciliation
Conciliation involves a third party (conciliator) that may or may not be
neutral to the dispute. Conciliation is used when parties are unwilling, unable,
or unprepared to come to the bargaining table. The conciliator may begin by
carrying initial messages between the two parties and providing a neutral
meeting place in an effort to help establish communications. He or she attempts
to promote openness, build or re-build the relationship and clarify
misperceptions between the two parties. A conciliator must be able to deal with
strong emotions and build trust for cooperative problem solving. The conciliator
helps the parties repair the relationship. After conciliation, the parties may use
other ADR techniques to resolve the issues in dispute.
4. Facilitation
Facilitation uses a third party or facilitator to improve the flow of
information between two parties or within a group. The facilitator may or may
not be neutral to the dispute. The facilitators emphasis is on providing an
efficient procedure to continue dialog and move towards an agreement. His or
her role is not to interpret factual issues or make recommendations like a
mediator. Therefore, a facilitators role is more limited than a mediators.
5. Mediation
Mediation is the most common and most popular form of ADR. Mediation
requires a third party neutral or mediator who assists the parties in reaching an
-
7/29/2019 The Effects of Arbitration on the Building Industry
21/83
21
agreement. Mediators need not be subject matter experts. The mediator will
meet with each side individually or with both sides together as needed.
Mediators do not have any decision-making authority and cannot impose a
solution on the parties; the parties make the decision themselves. However, the
mediator, like a facilitator, serves as the supporter of the process to keep
discussions going so that the parties can resolve their dispute.
6. Settlement Judge
Settlement Judge is a form of ADR available with the Armed Services Board
of Contract Appeals. If parties elect to use a settlement judge they first draft an
agreement on the procedures that will be used to carry out the proceedings. The
agreement is drafted according to the circumstances of the case. Settlement
judges primarily act as mediators and use a variety of techniques to resolve the
dispute. The judge acts as a third party neutral to facilitate settlement
negotiations. He or she will meet privately with both sides, as in Early Neutral
Evaluation, and advise them on the merits of the case. Cases that are factually
and legally complicated are well suited for the settlement judge procedure.
7. Early Neutral Evaluation
Early Neutral Evaluation uses a third party neutral to provide an evaluation
to both sides of a dispute. The neutral is usually an expert on the issue being
disputed. Both sides informally present their case to the neutral who then
advises each side individually on the strengths and weaknesses of their cases.
-
7/29/2019 The Effects of Arbitration on the Building Industry
22/83
22
The evaluation may be binding or non-binding. Early neutral evaluation is an
excellent alternative when there are many technical issues that need to be
interpreted. It is also useful when decision makers or supervisors of one or both
parties need clarification on the value of their cases.
8. Peer Review Panel
Peer Review Panels, Dispute Panels and Dispute Resolution Panels use a
single third party neutral, or a panel to help resolve disputes as soon as they are
discovered in order to avoid traditional litigation. For workplace disputes, the
panel will be composed of fellow employees and supervisors. The panel will
review the conflicting data, fill in missing information, assess the issues, and
clarify the facts to both sides. The panel helps to resolve conflicts by assessing
the issues and making procedural or factual recommendations.
For contracting disputes, the panel will be composed of subject matter
experts that are selected by the disputing parties. The decision of the panel may
or may not be binding, depending on the agreement made by the two parties
beforehand.
9. Ombudsman
Ombudsman, Ombudsperson or Ombuds are advocates designated by the
company to confidentially investigate and resolve sensitive complaints. The
ombudsman does not normally have the authority to enforce a solution.
-
7/29/2019 The Effects of Arbitration on the Building Industry
23/83
23
Ombudsmen often work as advisors to management and a focal point for
employees to help identify problems and recommend solutions.
10. Fact-Finding
Fact-Finding and Neutral Fact-Finding involve the investigation of facts by
an impartial expert or group. The fact-finder investigates, evaluates and reports
the facts to both sides of the case. He or she is not permitted to resolve or decide
any issues of law but his or her expertise is expected to carry significant weight
with both sides. Fact-finding is successful if both parties resolve the dispute but
it is also useful if negotiations fail. The information can still be used in
traditional litigation.
11. Mini-Trial
Mini-Trial is not a small trial. Its not a trial at all. It is a process where
both sides of a dispute make brief presentations of their arguments to senior
executives in their organizations. The most important requirement is that the
senior executives have the authority to settle the dispute. After hearing the
evidence, the senior executives will privately discuss the case. A third party
neutral usually facilitates the process by helping with the presentation of
evidence and acting as a mediator in order to reach a settlement. This technique
is available mostly in the private sector.
-
7/29/2019 The Effects of Arbitration on the Building Industry
24/83
24
12. Mediated Arbitration
Mediated Arbitration (Med-Arb) is a combination of mediation and
arbitration. Med-Arb uses a neutral mediator to resolve as many of the issues as
possible. After reaching an impasse, the mediator or a new neutral then
arbitrates the remaining issues in dispute. His or her decision can be binding or
non-binding. Med-Arb allows both sides to quickly resolve simple issues so that
efforts can now be placed on the more difficult issues.
13. Summary Jury Trial
The Summary Jury Trial is a formal but abbreviated trial involving a
presentation by the disputing parties to a panel of jurors. This process reality
tests the case with a non-binding verdict to encourage the parties to negotiate
for a settlement based upon their new assessment of litigation risk. The
summary jury trial should not be confused with a mini-trial, an entirely different
process.
14. Arbitration
Arbitration is the second most popular type of ADR. It has been used
extensively in recent years to resolve labor/management and commercial
disputes. In arbitration, both parties present their issues to a third party neutral
or panel. Generally, both sides have a role in selecting the arbitrator. The
arbitrator is usually a subject matter expert. The rules of evidence are relaxed.
Both sides can agree before hand on the amount of evidence allowed and the
-
7/29/2019 The Effects of Arbitration on the Building Industry
25/83
25
time limits. The arbitrator makes a decision that has the full force and effect of
law and is not open for appeal. The decision is usually binding but is kept
private and does not set a precedent.
15. Private Judging
Private Judging is a technique that falls between arbitration and litigation in
terms of formality and control of the parties. The parties present their case to a
judge in a private courtroom. Private Judges are usually retired judges who are
experts in the matter under review.
2.5.2ADVANTAGES OF ALTERNATIVE DISPUTE RESOLUTION
The biggest advantage of ADR over litigation is it can provide the best
solution with the least amount of resources. ADR techniques are extremely
flexible. They allow parties to choose the amount of control they maintain and
the amount of authority given to the third party neutral. Additionally, ADR is a
non-adversarial process that helps to preserve the relationship between the two
parties by making the communication cooperative vice combative. This
cooperative atmosphere is attainable due to the confidential nature of the
proceedings. Parties are more open to discussion if their statements are not
available for public scrutiny.
-
7/29/2019 The Effects of Arbitration on the Building Industry
26/83
26
2.5.3 DISADVANTAGES OF ALTERNATIVE DISPUTE RESOLUTION
When agreeing to ADR, there is always an inherent lack of finality. Another
inherent weakness is the lack of enforcement authority given to the neutral. The
biggest disadvantage to ADR is that there is no guarantee that the dispute will
be resolved. Because of these doubts, parties may feel that ADR is a waste of
time and that ADR will only increase litigation costs by providing the other side
with information that makes them vulnerable. To some parties, agreeing to
ADR may be viewed as a weakness by the other side.
Using ADR depends on the willingness and the good-faith of the other
party. If one party acts in bad-faith they could merely be delaying action,
which will cause further damage to the relationship.
There is often a lack of information or lack of training on ADR on one or both
sides. The lack of rules may lead lawyers to recommend against using ADR.
Lastly, ADR lacks due process, procedural safeguards and does not set a
precedent.
2.6 THE ORIGIN OF ARBITRATION
It is not known exactly when formal non-judicial arbitration first began but it
can be said with some certainty that arbitration, as a way of resolving disputes
predates formal courts. Records from ancient Egypt attest to its use especially
with high priests and their interaction with the public. Arbitration was popular
both in ancient Greece and in Rome.
http://en.wikipedia.org/wiki/Ancient_Egypthttp://en.wikipedia.org/wiki/Ancient_Greecehttp://en.wikipedia.org/wiki/Ancient_Romehttp://en.wikipedia.org/wiki/Ancient_Romehttp://en.wikipedia.org/wiki/Ancient_Greecehttp://en.wikipedia.org/wiki/Ancient_Egypt -
7/29/2019 The Effects of Arbitration on the Building Industry
27/83
27
UnderEnglish law, the first law on arbitration was the Arbitration Act 1697,but
when it was passed arbitration was already common. The first recorded judicial
decision relating to arbitration was in England in 1610. The noted Elizabethan
English legal scholarSir Edward Coke refers to an earlier decision dating from
the reign of Edward IV (which ended in 1483). Early arbitrations at common
law suffered from the fatal weakness that either party to the dispute could
withdraw the arbitrator's mandate right up until the delivery of the award if
things appeared to be going against them (this was rectified in the 1697 Act).
The Jay Treaty of 1794 between Britain and the United States sent
unresolved issues regarding debts and boundaries to arbitration, which took 7
years and proved successful (Wikipedia, 2010).
In the first part of the twentieth century, many countries (France and the
United States being good examples) began to pass laws sanctioning and even
promoting the use of private adjudication as an alternative to what was
perceived to be inefficient court systems.
The growth of international trade however, brought greater sophistication to
a process that had previously been largely ad hoc in relation to disputes between
merchants resolved under the auspices of the lex mercatoria. As trade grew, so
did the practice of arbitration, eventually leading to the creation of a variant
http://en.wikipedia.org/wiki/English_lawhttp://en.wikipedia.org/wiki/Edward_Cokehttp://en.wikipedia.org/wiki/Edward_IV_of_Englandhttp://en.wikipedia.org/wiki/Common_lawhttp://en.wikipedia.org/wiki/Common_lawhttp://en.wikipedia.org/wiki/Jay_Treatyhttp://en.wikipedia.org/wiki/Francehttp://en.wikipedia.org/wiki/United_Stateshttp://en.wikipedia.org/wiki/Law_merchanthttp://en.wikipedia.org/wiki/Law_merchanthttp://en.wikipedia.org/wiki/Law_merchanthttp://en.wikipedia.org/wiki/United_Stateshttp://en.wikipedia.org/wiki/Francehttp://en.wikipedia.org/wiki/Jay_Treatyhttp://en.wikipedia.org/wiki/Common_lawhttp://en.wikipedia.org/wiki/Common_lawhttp://en.wikipedia.org/wiki/Edward_IV_of_Englandhttp://en.wikipedia.org/wiki/Edward_Cokehttp://en.wikipedia.org/wiki/English_law -
7/29/2019 The Effects of Arbitration on the Building Industry
28/83
28
now known as international arbitration, as a means for resolving disputes under
international commercial contracts.
In the United States, the so-called "forced arbitration" or mandatory binding,
arbitration has recently been strongly criticized by Public Citizen, a
Washington-based public interest advocacy group, which points out a tendency
of arbitrators to rule against consumers and in favour of corporations or
institutions.
Today, arbitration also occurs online, in what is commonly referred to as
Online Dispute Resolution, or ODR. Typically, ODR proceedings occur
following the filing of a claim online, with the proceedings taking place over the
internet, and judgment rendered on the basis of documentation presented.
2.7 HISTORICAL ANTECEDENTS OF ABITRATION IN NIGERIA
According to Akin Akinbote 2008, the Arbitration Ordinance 1914, which
was predicated on the English Arbitration Act 1889, is the first formal statute on
Arbitration in Nigeria and dates back to the colonial times. Nigeria had its first
set of Laws of the Federation in 1958, two years before independence in 1960.
The Arbitration Ordinance 1914 was re-enacted as the Arbitration Ordinance
Act Cap 13, Laws of the Federation of Nigeria and Lagos, 1958. By virtue of
paragraph 2 of Section 1 of the Arbitration Ordinance Act 1958, the Act was
applicable to the Northern, Western and Eastern Regions, Federal Territory of
http://en.wikipedia.org/wiki/International_arbitrationhttp://en.wikipedia.org/wiki/Online_Dispute_Resolutionhttp://en.wikipedia.org/wiki/Online_Dispute_Resolutionhttp://en.wikipedia.org/wiki/International_arbitration -
7/29/2019 The Effects of Arbitration on the Building Industry
29/83
29
Lagos; and interestingly or coincidentally, the then Southern Cameroons. It is
interesting that this conference is taking place on the Cameroonian soil. It will
equally be interesting to find out if the Law is still applicable today in an
adopted or assimilated form. In any event, delving into this will certainly be
hors sujet.
The provisions of the 1958 Act was limited to domestic arbitration only as
no reference was made to international commercial arbitration. One is not
certain if there was any international commercial arbitration involving Nigerian
parties or foreign parties either in Nigeria or abroad, prior to Independence in
1960. If there was, Nigeria then a colony of Britain would probably have been
covered by the 1958 New York Convention. It is not clear whether Britain,
being a signatory to the Convention, in the exercise of its sovereignty over the
former colonies, could rightly have made the Convention applicable to Nigeria.
It will be a subject of further research for one to reach a conclusion that
Recognition and Enforcement of Foreign Arbitral Awards (The York
Convention) was ever put into practice in Nigeria prior to Nigeria becoming a
signatory to the Convention in 1988.
The first indigenous Statute on Arbitration and Conciliation was enacted in
1988, by a military Decree. It was known as the Arbitration and Conciliation
Decree 1988 (ACA1988) and came into effect on 13th
March, 1988.
-
7/29/2019 The Effects of Arbitration on the Building Industry
30/83
30
2.8 ARBITRATION IN CONSTRUCTION
Arbitration has become recognized as the dispute settlement mechanism in
the construction industry. It is seen as the final mode of dispute resolution
which is beyond the usual attractions of arbitration, such as privacy, speed,
flexibility and choice of the arbitrator. In the construction industry, arbitration is
the norm because firstly, the prevalence of arbitration clauses in standard forms
of contract; secondly, the technical content of disputes, leading to the use of
arbitrators skilled in technical disciplines; and finally the need in many disputes
for the arbitrator be empowered to open up, review and revise decisions or
certificates, rising from the architects orengineers judgment in administering
the building contract.
The construction industry generates disputes that arise from matters of
considerable scientific or technical difficulty. Two points working in
combination increase the technical content and the utilization of technically
qualified arbitrators in their resolution which are further enhanced by the
consultants discretion in the various standard forms of building contracts.
Firstly, the various standard form of building contracts instead of determining
matters of uncertainty by prior contractual arrangements, tend to postpone them.
The architect or engineer is given the discretion to decide on them later. This at
times gives rise to uncertainty as regard to the scope of work to be undertaken,
the time or schedule it should be completed, and the payment due to be paid on
it. The architect or engineer when administrating the contract may make
-
7/29/2019 The Effects of Arbitration on the Building Industry
31/83
31
evaluations. The disputes that arise from such determination are normally
technical in nature although they may involve legal and contractual issues.
Secondly, nowadays these ex post facto technical evaluations involve not only
the consultants but also claim consultants. The latter are involved in promoting,
preparing, arguing, defending, appealing claims and disputing technical
evaluations. Eventually, given the frequency and experience of participants in
such disputes encourages them to be more specialists in their resolution, and
make their careers in construction arbitration.
2.9 ADVANTAGES AND DISADVANTAGES OF ARBITRATION
Parties should consider whether or not to provide for arbitration as the
chosen method of dispute resolution every time they enter into a contract. It is
particularly important to do so where the parties or their assets are in different
countries or where disputes give rise to complex technical issues. The most
important advantages and disadvantages of arbitration that should be considered
(according to Advocates for International Developments Guide to
Arbitration), when deciding whether to provide for arbitration as the dispute
resolution methods in a contract are listed below:
(A) ADVANTAGES
1. Enforceability: Due to international conventions, the potential forenforcing arbitral awards worldwide is much greater than that for court
judgements. As there is little point in obtaining a court judgment which
-
7/29/2019 The Effects of Arbitration on the Building Industry
32/83
32
cannot be enforced against suitable assets, this feature often conclusively
determines the choice of arbitration over litigation for international
contracts. The most important enforcement convention is the New York
Convention which provides for the enforcement of arbitral awards in over
140 countries.) There is no such wide-ranging convention providing for
the enforcement of court judgements (the closest being the Brussels
Regulation, which is limited to parties in Europe).
2. Flexibility: Arbitration rules are generally simpler and more flexible thanthose of court proceedings. They are relatively easy to understand for
parties of different nationalities, and the parties can adapt the dispute
resolution process to suit their relationship and the nature of their dispute.
In many cases, parties (or tribunals exercising discretion left to them by
the parties) choose to follow a procedure that is similar to court
proceedings. In some cases, the parties make significant changes to court
procedure. For example, they may decide that their dispute should be
determined on the basis of documents only, without a hearing.
3. Neutrality: Frequently, one party will not wish to submit to the localcourts of another party. For example, party A may not be familiar with
the language, legal culture or court procedure in party B's country or may
fear that the courts in party B's country are not impartial. This will be a
particular worry to party A where party B is a sovereign state, e.g. where
A, a company based in Austria, has entered into a contract with B, the
-
7/29/2019 The Effects of Arbitration on the Building Industry
33/83
33
Republic of Bolivia. Arbitration can provide politically neutral dispute
resolution. The parties can select a neutral venue in a third country for the
arbitration (e.g. London, England), appoint a multinational tribunal,
request that international procedural rules be applied and choose a
language for the proceedings with which they are comfortable (very
frequently English).
4. Technical expertise and experience: Parties may select arbitrators withthe appropriate expertise or experience in the subject matter of the
dispute. Although some jurisdictions have very good specialist courts,
parties run the risk of their dispute being decided by a judge with little or
no relevant experience.
5. Choice of arbitrators: Unlike court proceedings, where parties generallyhave no input into the choice of judge for their case, the parties to an
arbitration usually appoint, nominate or at least have some input into the
selection of the tribunal. Most developed international arbitration laws
require that all the arbitrators be impartial. However, a party can use its
input into the selection process to help ensure that, as far as possible, the
tribunal will understand the commercial context, the relevant issues and
the parties' procedural preferences.
6. Cost / Speed / Finality: Lawyers' fees generally account for the majorityof costs of proceedings (whether litigation or arbitration). The cost of the
proceedings therefore generally depends on the complexity of the dispute,
-
7/29/2019 The Effects of Arbitration on the Building Industry
34/83
34
the way the proceedings are conducted and their length. Arbitration can
be speedier and less costly than litigation because of the finality of the
award. Whereas a court judgment can often be appealed (prolonging
matters by months and years), parties to international contracts normally
agree that there is no right of appeal on the merits from any award. In
many countries, awards may only be reviewed in strictly limited
circumstances. Arbitration costs initially can be higher than those of court
proceedings because the parties have to pay for arbitrators, any
administering institution and the hiring of hearing venues. Arbitration can
also take longer if the tribunal fails to impose strict deadlines. However,
there are no court fees, and the parties can agree on streamlined or "fast-
track" procedures. Moreover, it is increasingly common for a successful
party to be awarded all or part of its costs of the arbitration whereas this
is not the norm in litigation in many countries.
7. Privacy: Although national laws and arbitration rules vary as to thedegree of confidentiality afforded to arbitration, there can be no doubt
that arbitration provides greater privacy and confidentiality than litigation
(which is often public). The parties can expect that there will be no public
right of access to the hearings and can provide for the required degree of
confidentiality in their arbitration agreement, subject to any mandatory
reporting obligations imposed by law, for example where there is a
requirement to record any potential exposure to liability in the context of
-
7/29/2019 The Effects of Arbitration on the Building Industry
35/83
35
financial reporting. Any confidentiality might come to an end or at least
be put at risk if enforcement through the courts becomes necessary.
8. Commencement of proceedings: Arbitration proceedings can often becommenced more quickly than court proceedings. A party need generally
only submit a short document to the appropriate arbitral institution and /
or the other party to start the arbitration. The commencement of court
proceedings can be more complicated, e.g. requiring a party to seek leave
to serve process on the other party if that other party is abroad.
(B)DISADVANTAGES
The disadvantages of arbitration stem from the same characteristics.
Arbitration is adversarial, thus it generally does nothing to create win-win
solutions or improve relationships. Often it escalates a conflict; just as court-
based adjudication is likely to do. In addition, arbitration takes decision making
power away from the parties. This results in a resolution of the current conflict,
but does nothing to help the parties learn how to resolve their own conflicts
more effectively in the future, as does mediation. Other people also fault
arbitration for being too informal and potentially unjust. Only the courts, with
their carefully regulated procedures can provide justice, some researchers
believe.
Some of the disadvantages summarized include:
1.
Arbitration may become highly complex
-
7/29/2019 The Effects of Arbitration on the Building Industry
36/83
36
2. Arbitration may be subject to pressures from powerful law firmsrepresenting the stronger and wealthier party
3. Arbitration agreements are sometimes contained in ancillary agreements,or in small print in other agreements, and consumers and employees
sometimes do not know in advance that they have agreed to mandatory
binding pre-dispute arbitration by purchasing a product or taking a job
4. If the arbitration is mandatory and binding, the parties waive their rights toaccess the courts and have a judge or jury decide the case
5. In some arbitration agreements, the parties are required to pay for thearbitrators, which adds an additional layer of legal cost that can be
prohibitive, especially in small consumer disputes
6. In some arbitration agreements and systems, the recovery of attorneys'fees is unavailable, making it difficult or impossible for consumers or
employees to get legal representation; however most arbitration codes and
agreements provide for the same relief that could be granted in court
7. If the arbitrator or the arbitration forum depends on the corporation forrepeat business, there may be an inherent incentive to rule against the
consumer or employee
8. There are very limited avenues for appeal, which means that an erroneousdecision cannot be easily overturned
-
7/29/2019 The Effects of Arbitration on the Building Industry
37/83
37
9. Although usually thought to be speedier, when there are multiplearbitrators on the panel, juggling their schedules for hearing dates in long
cases can lead to delays
10.In some legal systems, arbitral awards have fewer enforcement optionsthan judgments; although in the United States arbitration awards are
enforced in the same manner as court judgments and have the same effect
11.Arbitrators are generally unable to enforce interlocutory measures againsta party, making it easier for a party to take steps to avoid enforcement of
an award, such as the relocation of assets offshore
12.Unions may only make a weak effort to defend one member or a smallgroup of members in arbitration due to increasing legal fees, without
explaining to the members the adverse consequences of an unfavourable
ruling
13.Rule of applicable law is not necessarily binding on the arbitrators,although they cannot disregard the law
14.Discovery may be more limited in arbitration or entirely nonexistent15.The potential to generate billings by attorneys may be less than pursuing
the dispute through trial
16.Unlike court judgments, arbitration awards themselves are not directlyenforceable. A party seeking to enforce an arbitration award must resort to
judicial remedies, called an action to "confirm" an award
-
7/29/2019 The Effects of Arbitration on the Building Industry
38/83
38
17.Although grounds for attacking an arbitration award in court are limited,efforts to confirm the award can be fiercely fought, thus necessitating
huge legal expenses that negate the perceived economic incentive to
arbitrate the dispute in the first place.
2.10 ARBITRATION AGREEMEMENT
In theory, arbitration is a consensual process; a party cannot be forced to
arbitrate a dispute unless he agrees to do so. In practice, however, many fine-
print arbitration agreements are inserted in situations in which consumers and
employees have no bargaining power. Moreover, arbitration clauses are
frequently placed within sealed users' manuals within products, within lengthy
click-through agreements on websites, and in other contexts in which
meaningful consent is not realistic. Such agreements are generally divided into
two types:
Agreements which provide that, if a dispute should arise, it will beresolved by arbitration. These will generally be normal contracts, but they
contain an arbitration clause
Agreements which are signed after a dispute has arisen, agreeing that thedispute should be resolved by arbitration (sometimes called a "submission
agreement")
http://en.wikipedia.org/wiki/Contracthttp://en.wikipedia.org/wiki/Arbitration_clausehttp://en.wikipedia.org/wiki/Arbitration_clausehttp://en.wikipedia.org/wiki/Contract -
7/29/2019 The Effects of Arbitration on the Building Industry
39/83
39
The former is the far more prevalent type of arbitration agreement.
Sometimes, legal significance attaches to the type of arbitration agreement. For
example, in certain Commonwealth countries, it is possible to provide that each
party should bear their own costs in a conventional arbitration clause, but not in
a submission agreement.
The courts have also upheld clauses which specify resolution of disputes other
than in accordance with a specific legal system. These include provision
indicating:
that the arbitrators "must not necessarily judge according to the strict lawbut as a general rule ought chiefly to consider the principles of practical
business"
"internationally accepted principles of law governing contractualrelations".
Agreements to refer disputes to arbitration generally have a special status in
the eyes of the law. For example, according to the Arbitration and Conciliation
Act (Chapter 19, Laws of the Federation of Nigeria, 1990), this stipulates;
1) Every arbitration agreement shall be in writing contained-
(a) in a document signed by the parties; or
http://en.wikipedia.org/wiki/Commonwealth_of_Nationshttp://en.wikipedia.org/wiki/Commonwealth_of_Nations -
7/29/2019 The Effects of Arbitration on the Building Industry
40/83
40
(b) in an exchange of letters, telex, telegrams or other means of communication
which provide a record of the arbitration agreement; or
(c) in an exchange of points of claim an of defence in which the existence of an
arbitration agreement is alleged by one party and denied by another.
(2) Any reference in a contract to a document containing an arbitration clause
constitutes an arbitration agreement if such contact is in writing and the
reference is such as to make that clause part of the contract.
2. Unless a contrary intention is expressed therein, an arbitration agreement
shall be irrevocable except by agreement of parties or by leave of the court or
judge.
3. An arbitration agreement shall not be invalid by reason of death of any party
thereto but shall, in such an event, by enforcement by or against the personal
representative of the deceased.
4. (1) A court before which an action which is the subject of an arbitration
agreement is brought shall, if any party so request not later than when
submitting his first statement on the substance of the dispute, order or stay of
proceedings and refer the parties to arbitration.
(2) Where an action referred to in subsection (1) of this section has been
brought before a court, arbitral proceedings may nevertheless be commenced or
-
7/29/2019 The Effects of Arbitration on the Building Industry
41/83
41
continued, and an award may be made by the arbitral tribunal while the matter
is pending before the court.
5. (1) If any party to an arbitration agreement commences any action in any
court with respect to any matter which is the subject of an arbitration agreement
any party to the arbitration agreement may, at any time after appearance and
before delivering any pleadings or taking any other steps in the proceedings,
apply to the court to stay the proceedings.
(2) A court to which an application is made under subsection (1) of this section
may, if it is satisfied-
(a) That there is no sufficient reason why the matter should not be referred to
arbitration in accordance with the arbitration agreement; and
(b) That the applicant was at the time when the action was commenced and still
remains ready and willing to do all things necessary to the proper conduct of the
arbitration, make an order staying the proceedings.
2.11 APPOINTMENT OF ARBITRATOR
According to the Arbitration and Conciliation Act (Chapter 19, Laws of the
Federation of Nigeria, 1990), the parties can agree on a procedure for
appointing the arbitrator or arbitrators. If they are unable to agree, each party
will appoint one arbitrator and the two appointed arbitrators will appoint the
-
7/29/2019 The Effects of Arbitration on the Building Industry
42/83
42
third arbitrator who will act as a presiding arbitrator. [section 11(3)]. If one of
the parties does not appoint an arbitrator within 30 days, or if two appointed
arbitrators do not appoint third arbitrator within 30 days, the party can request
Chief Justice to appoint an arbitrator. [section 11(4)]. The Chief Justice can
authorise any person or institution to appoint an arbitrator. [Some High Courts
have authorised District Judge to appoint an arbitrator]. In case of international
commercial dispute, the application for appointment of arbitrator has to be made
to Chief Justice of India. In case of other domestic disputes, application has to
be made to Chief Justice of High Court within whose jurisdiction the parties are
situated. [section 11(12)].
2.11.1 CHALLENGES TO APPOINTMENT OF ARBITRATOR
An arbitrator is expected to be independent and impartial. If there are some
circumstances due to which his independence or impartiality can be challenged,
he must disclose the circumstances before his appointment. [section 12(1)].
Appointment of Arbitrator can be challenged only if (a) Circumstances exist
that give rise to justifiable doubts as to his independence or impartiality (b) He
does not possess the qualifications agreed to by the parties. [section 12(3)].
Appointment of arbitrator cannot be challenged on any other ground.. The
challenge to appointment has to be decided by the arbitrator himself. If he does
not accept the challenge, the proceedings can continue and the arbitrator can
make the arbitral award. However, in such case, application for setting aside
-
7/29/2019 The Effects of Arbitration on the Building Industry
43/83
43
arbitral award can be made to Court. If the court agrees to the challenge, the
arbitral award can be set aside. [section 13(6)]. Thus, even if the arbitrator does
not accept the challenge to his appointment, the other party cannot stall further
arbitration proceedings by rushing to court. The arbitration can continue and
challenge can be made in Court only after arbitral award is made (Arbitration
and Conciliation Act, Chapter 19, Laws of the Federation of Nigeria, 1990).
2.12 PROCEDURE PROIR TO HEARING
The Arbitral Tribunal should treat the parties equally and each party should
be given full opportunity to present his/ her case. The Arbitral Tribunal is not
bound by Code of Civil Procedure, that is, the parties to arbitration are free to
agree on the procedure to be followed by the Arbitral Tribunal. If the parties do
not agree to the procedure, the procedure will be as determined by the arbitral
tribunal.
Arbitral Tribunal has full powers to decide the procedure to be followed,
unless parties agree on the procedure to be followed. The Tribunal also has
powers to determine the admissibility, relevance, materiality and weight of any
evidence. Place of arbitration will be decided by mutual agreement. However, if
the parties do not agree to the place, the same will be decided by tribunal.
Similarly, language to be used in arbitral proceedings can be mutually agreed.
Otherwise, Arbitral Tribunal can decide.
-
7/29/2019 The Effects of Arbitration on the Building Industry
44/83
44
2.13 ARBITRATION HEARING
Participation in a professional standards hearing - arbitration or ethic - can
be an intimidating experience for first time participants, witnesses and even new
panel members. Knowing what will likely happen can make it a less stressful
experience.
Although the arbitration hearing process is based on the judicial model of a
civil trial, there are important differences between a trial and an arbitration
hearing. While parties to any professional standards proceeding are entitled to
fundamental due process, technical rules of evidence and procedure do not
apply in an arbitration hearing. While the burden of proof rests with the parties,
arbitration panel members can ask questions (directly or through the chair) to
ensure that they have a clear understanding of relevant issues and facts. This is
key to rendering a fair decision.
Parties are entitled to have legal counsel present but must respond to
questions asked by panel members - or asked by other parties or their counsel
when directed to respond by the chair.
Prior to the hearing, parties have the opportunity to challenge potential panel
members for cause. While there are no preemptory or "automatic" challenges,
boards/associations make all reasonable efforts to ensure that panel members
will be impartial, unbiased, and fair.
-
7/29/2019 The Effects of Arbitration on the Building Industry
45/83
-
7/29/2019 The Effects of Arbitration on the Building Industry
46/83
-
7/29/2019 The Effects of Arbitration on the Building Industry
47/83
47
particulars. All relevant documents must be submitted. Such claim or defence
can be amended or supplemented any time.
After submission of documents and defence, unless the parties agree
otherwise, the Arbitral Tribunal can decide whether there will be oral hearing or
proceedings can be conducted on the basis of documents and other materials.
However, if one of the partys requests, the hearing shall be oral, sufficient
advance notice of hearing should be given to both the parties. [Thus, unless one
party requests, oral hearing is not compulsory].
It is permissible for parties to arrive at mutual settlement even when arbitration
is proceeding. In fact, even the Tribunal can make efforts to encourage mutual
settlement. If parties settle the dispute by mutual agreement, the arbitration shall
be terminated. However, if both parties and the Arbitral Tribunal agree, the
settlement can be recorded in the form of an arbitral award on agreed terms.
Such Arbitral Award shall have the same force as any other Arbitral Award.
2.15 THE MAKING AND FORM OF AN AWARD
Decision of Arbitral Tribunal is termed as 'Arbitral Award'. Arbitrator can
decide the dispute ex aequo et bono (In justice and in good faith) if both the
parties expressly authorise him to do so. [section 28(2), Arbitration and
Conciliation Act]. The decision of Arbitral Tribunal will be by majority. The
arbitral award shall be in writing and signed by the members of the tribunal.
[section 29]. The award must be in writing and signed by the members of
-
7/29/2019 The Effects of Arbitration on the Building Industry
48/83
48
Arbitral Tribunal. [section 31(1)].. It must state the reasons for the award unless
the parties have agreed that no reason for the award is to be given. [section
31(3)]. The award should be dated and place where it is made should be
mentioned. Copy of award should be given to each party. Tribunal can make
interim award also. [section 31(6)].
Arbitration act has over-riding effect; this is because, the act clarifies that
notwithstanding anything contained in any other law for the time being in force,
in matters governed by the act, the judicial authority can intervene only as
provided in this act and not under any other act.
2.16.1 ENFORCEMENT OF FOREIGN AWARD
The foreign awards which can be enforced in Nigeria are as follows: -
(a) New York convention Award (made after 11th October, 1960)
(b) Geneva convention Award - made after 28th July, 1924.
Since most of the countries have signed New York convention, normally, New
York convention awards are enforceable in Nigeria. New York convention was
drafted and kept in United Nations for signature of member countries on 21st
December, 1958. Each country became party to the convention on the date on
which it signed the convention.
-
7/29/2019 The Effects of Arbitration on the Building Industry
49/83
49
Party which intends to enforce a foreign award has to produce the arbitral award
and agreement of arbitration [original or its certified copy] to the district court
having jurisdiction over the subject matter of the award. The enforcement of
award can be refused by court only in cases specified. Otherwise, the foreign
award is enforceable through court as if it is a decree of the court. If the court
declines to enforce the arbitral award, appeal can be made to the court where
appeal normally lies from the district court. However, no further appeal can be
made (except appeal to Supreme Court). [Probably, the aggrieved party may be
able to approach International Court of Justice, as the convention is an
international convention, signed by many of the member countries].
One advantage of foreign award, according to foreign parties, is that Nigerian
courts come into picture only at the time of implementation of award. The
courts can refuse to implement the award only on limited grounds.
2.1. SUMMARY OF CHAPTER
Construction is an amalgam of complex activities requiring a careful
allocation of resources and preparation. The lack of such allocation and
preparation can bring about workmanship and quality control problems. It may
arise from personality clashes and differing goals espoused between various
parties and members of the consultant team. This can poison the atmosphere
without proper communication between the parties. The consultants may end up
-
7/29/2019 The Effects of Arbitration on the Building Industry
50/83
50
issuing unclear and/or late instructions. Parties may lack good faith to resolve
disputes on an amicable basis thus leading on to arbitration.
-
7/29/2019 The Effects of Arbitration on the Building Industry
51/83
51
CHAPTER THREE
3.0 RESEARCH METHODOLOGY
This chapter discusses data collection process in order to achieve the aim and
objectives of this study. The following are the necessary steps during data
collection:
1. Data on the causes of construction disputes and its impact on clientorganizations.
2. Questionnaire development3. A sample selection.4. Responses to Questionnaire Survey.
The way in which research is conducted may be conceived of in terms of the
research philosophy subscribed to, the research strategy employed and so the
research instruments utilised (and perhaps developed) in the pursuit of a goal
the research objective(s) - and the quest for the solution of a problem - the
research question. For any research to be successfully carried out, relevant data
should be clearly defined and the informal investigation should show that the
project is economically feasible, the next important step is to develop the most
efficient plan for gathering the needed information. This means the researcher
would design a plan as to where and how to get the desired relevant data.
-
7/29/2019 The Effects of Arbitration on the Building Industry
52/83
52
3.1 RESEARCH DESIGN
Research design is the overall operational pattern framework of the project.
It stipulates the information to be collected, from which source or sources and
by what procedure through which the information will be collected and also the
nature of analysis required to analyse the collected information.
Research design provides the glue that holds the research project together. A
design is used to structure the research, to show how all of the major parts of the
research project - the samples or groups, measures, treatments or programs, and
methods of assignment - work together to try to address the central research
questions (William M. Trochim, 2006).
3.2 DATA SOURCES
The term data refers to groups of information that represent the qualitative or
quantitative attributes of a variable or set of variables. Data are typically the
results of measurements and can be the basis ofgraphs, images, or observations
of a set of variables. Data are often viewed as the lowest level of abstraction
from which information and knowledge are derived (Wikipedia, 2010).
Literature review in Chapter II helps to identify the problems of the research.
The details study on the role of clients, designers and contractor in construction
process were carried out to identify the potential causes of dispute. Besides, the
impact of construction dispute was also been identified. A standard
questionnaire was prepared to ensure all relevant information is gathered. Pilot
http://en.wikipedia.org/wiki/Variable_%28mathematics%29http://en.wikipedia.org/wiki/Graph_%28data_structure%29http://en.wikipedia.org/wiki/Imagehttp://en.wikipedia.org/wiki/Abstractionhttp://en.wikipedia.org/wiki/Abstractionhttp://en.wikipedia.org/wiki/Imagehttp://en.wikipedia.org/wiki/Graph_%28data_structure%29http://en.wikipedia.org/wiki/Variable_%28mathematics%29 -
7/29/2019 The Effects of Arbitration on the Building Industry
53/83
53
survey and discussion with industry professional were carried out with the aim
to test the prepared questionnaire.
3.2 THE QUESTIONNAIRE
The questionnaire survey shown in the appendix A was formulated to access
the collective perceptions of arbitration from clients, consultants and
contractors, as to identify the causes of dispute and the effects of arbitration on
construction projects in Nigeria.
The questionnaire consisted of four sections, which are:
Section A; which asked questions about the general information of respondents
and types of organization.
Section B; this collects the views of respondents with regards the significance
of each cause of dispute and classified into 3 categories where category 1 is
causes contributed by clients, category 2 is causes contributed by designers and
category 3 is causes contributed by contractors.
Section C, is to collect the views of the respondents with regards to the most
significance of each impact of the poor construction documentation on clients
organizations.
Section D, is to examine the level of understanding ofArbitration and source
of disputes encounter by respondent, best solution to resolve dispute at site and
lastly precaution methods to avoid disputes occurring.
-
7/29/2019 The Effects of Arbitration on the Building Industry
54/83
54
The questionnaire has been designed in such as way that to preserve the
overview and provide unambiguous picture due to the cross flows between the
groups and preventing any biases of group ratings and rankings. The ratings
were assigned by each respondent on a scale from 1 to 5, where 1 represents
very insignificant, 2 represents insignificant, 3 represents average, 4 represents
significant and 5 represents very significant.
3.3.1 RESPONSE TO QUESTIONNAIRES
Thirty- Five (35) questionnaires were sent to randomly selected numbers of
Construction companies, which are mainly based in Abuja. This included the
following:
a)Bullet International Nig. Limited.b) Sazak Acres Biloque Company Limited.c)Julius Berger Nig. Limited.d) S.C.C Limited.e)Acres Limited.
f) Cachez Nig. Limited.
Out of the 35 questionnaires sent out, 27 were sent back, which equates to
77% response rate. The composition of respondents that returned their
questionnaires were clients (15.0%), designers (41.0%) contractors (41.0%) and
others (3.0%).
-
7/29/2019 The Effects of Arbitration on the Building Industry
55/83
55
The results provide a breakdown of valid responses by the respondent type as
shown below:-
Table 3.1: Detail Breakdown of Respondents
Type of Samples Return Percentage
Client Oriented 4 15
Designer (Architect, Quantity Survey,Structural Engineer & Services Engineer)
11 41
General Contractors 11 41
Others (Specialist contractors & Suppliers) 1 3
TOTAL 27 100%
(Researchers Survey, 2010)
The response rate in this survey is ok, although some companies refused to
answer the questionnaire and gave various excuses. Among the most common
reasons were:
1) The suitable person to fill the questionnaire is not available
2) You better ask someone there,Im not suitable for this
3) Im busy with my works now, can youcome back later?
4) Sorry, I dont understand, look for someone else
5) Can u come again tomorrow, my boss / superioris not in
6) Company policy..cant answer any questionnaire
-
7/29/2019 The Effects of Arbitration on the Building Industry
56/83
56
3.3.2 DATA SUMMARY/ RESPONDENTS POINT OF VIEW
Data summary was important step to provide data for analysis. In order to
achieve the study objectives, the data collected from questionnaire survey was
categorized into 4 sections as below;
1) General profile
2) Respondents point of views
3) Others point of views
4) Additional questions on dispute issues.
3.3.2.1 SUMMARY OF RESPONSES
The total questionnaires collected in the questionnaire survey were 27
numbers. The Questionnaire responses for overalls points of views were
summarized as per below;
1. General Profile
This section shows the job description of the respondents and their general job
profile.
Fig 3.1: Bar chart showing the Respondents years of experience
0
2
4
6
8
10
1214
16
Less than 2 years 2-5 years 5-10 years 10-15 years 15 yr above
No.ofRepondents
Years of Experince
-
7/29/2019 The Effects of Arbitration on the Building Industry
57/83
57
Fig 3.2: Pie chart showing the breakdown of Respondent.
2. Respondents Point of Views
In the subsequent tables below, the indicators; 1,2,3,4 & 5 represents the
following;
1 = frequency ofthe very insignificant response.
2 = frequency of the insignificant response.
3 = frequency of the average response.
4 = frequency of the significant response.
5 = frequency of the very significant response.
Client Oriented
15%
Designer
41%
Contractor
41%
Others
3%
-
7/29/2019 The Effects of Arbitration on the Building Industry
58/83
58
(A) Disputes leading to Arbitration (Category 1)
Table 3.2.1: Respondents view on Disputes leading to Arbitration (Category 1)
INDICATORS 1 2 3 4 5
Response to Q1 2 6 11 7 1
Response to Q2 - 4 16 5 2
Response to Q3 1 - 9 15 2
Response to Q4 1 2 9 9 6
Response to Q5 - 3 5 12 7
Response to Q6 - 7 12 4 4
Response to Q7 2 3 10 7 5
(Researchers Survey, 2010)
(C)Disputes leading to Arbitration (Category 2)
Table 3.2.2: Respondents view on Disputes leading to Arbitration (Category 2)
INDICATORS 1 2 3 4 5
Response to Q1 1 9 13 4 -
Response to Q2 - 2 10 13 2
Response to Q3 - 7 8 10 2
Response to Q4 2 6 10 8 1
Response to Q5 - 4 9 11 3
Response to Q6 1 2 9 13 2
(Researchers Survey, 2010)
-
7/29/2019 The Effects of Arbitration on the Building Industry
59/83
59
(D)Disputes leading to Arbitration (Category 3)Table 3.2.3: Respondents view on Disputes leading to Arbitration (Category 3)
INDICATORS 1 2 3 4 5
Response to Q1 - 3 10 11 3
Response to Q2 - 2 8 11 6
Response to Q3 1 3 13 7 3
Response to Q4 2 5 10 10 -
Response to Q5 - 5 11 10 1
Response to Q6 1 8 8 9 1
Response to Q7 1 8 9 8 1
(Researchers Survey, 2010)
(E)The impact of Construction Disputes (Section C)Table 3.2.4: Respondents view on impact of Construction Disputes (Section C)
INDICATORS 1 2 3 4 5
Response to Q1 - 7 14 4 4
Response to Q2 5 6 7 7 2
Response to Q3 6 7 3 6 5
Response to Q4 4 8 9 2 4
Response to Q5 1 8 6 7 5
Response to Q6 - 8 10 7 2
Response to Q7 1 10 11 5 -
-
7/29/2019 The Effects of Arbitration on the Building Industry
60/83
60
Response to Q8 - 8 12 7 -
Response to Q9 - 2 19 5 1
Response to Q10 2 6 9 6 4
(Researchers Survey, 2010)
4. Additional Questions on Dispute (Section D)
In this section D, the questions aim to find out the opinions of the
respondents about the level of understanding the term Arbitration, kinds of
construction disputes encountered based on their working experiences, best
solutions and methods to resolve disputes at construction site and precautions
and avoidances to be taken account as to avoid disputes occurring at
construction site.
3.3.3 PRELIMINARY ANALYSIS
After collecting the information from the respondents, the next step is to
analyze the information and available data. The method used in analyzing the
information in the next chapter is the Important Index. The method used in
ranking of causes of dispute and impacts on clients organization is by adopting
the likert scale with 5- point scale. The formula of important index is shown
below;
Important Index = (ai Xi) x 100
b
-
7/29/2019 The Effects of Arbitration on the Building Industry
61/83
61
Where,
ai = Constant expressing the weight given each response (1-5)b = Number of option for weighting, if 5point scale of response is
assigned, then b = 5
Xi = n / N Where,
N = Total of responses
ni = Frequency of the response,
i = 1,2,3,4,5 and illustrated as below.
n1 = frequency ofthe very insignificant response and corresponding to a1 =
1.
n2 = frequency of the insignificant response and corresponding to a2 = 2.
n3 = frequency of the average response and corresponding to a3 = 3.
n4 = frequency of the significant response and corresponding to a4 = 4.
n5 = frequency of the very significant response and corresponding to a5 = 5.
-
7/29/2019 The Effects of Arbitration on the Building Industry
62/83
62
CHAPTER FOUR
4.0DATA ANALYSIS
This chapter discusses how the data will be analyzed, interpreted and
presented as to achieve the objectives of identifying the causes of construction
dispute according to its nature of occurrence during the construction process
which results in arbitration and to identify its impact on clients organizations. It
also evaluates and determines the significance of each cause and impact of
construction disputes on clients organizationsbased on point of views of major
parties involved in construction process.
Moreover, the analysis would help in deriving the conclusion on the major
contributor that causes the construction dispute as well as the most appropriate
measures to overcome the disputes occurrences that leads to arbitration. The
data obtained from the questionnaire survey were analyzed.
4.1 ANALYSIS OF DATA AND DISCUSSION
The logical step after collecting all information and data needed from
questionnaire and unstructured interviewed with industry professionals is to
analyze the gathered data. Although the causes of construction dispute and its
impact on clients organization were researched and investigated by many
researchers but the cases here in Nigeria maybe quite different from those
abroad. Researches in Nigeria did not cover much, thus most of the information
are from overseas. Causes of construction dispute are identified by more
-
7/29/2019 The Effects of Arbitration on the Building Industry
63/83
63
developed countries and are important to identify the causes of construction