the economic weekly letter from punjab beas … economic weekly january 7, 1961 beas-sutlej power...
TRANSCRIPT
T H E E C O N O M I C W E E K L Y January 7, 1961
Beas-Sutlej Power Complex P U N J A B is threatened w i t h acute
power shortage once again. The current flow in the Sutlej is so poor that i t is feared that if the Bhakra reservoir is not replenished in t ime, its water level may soon fal l below the penstock gates. This w i l l put the newly-commissioned uni t of the Left Bank Power House out of act ion. A cut in power consumption of 10 per cent has, therefore, been imposed from mid-December. I t is against this background of addit ional power load continually outpacing addi t ional power supply that-the proposed Beas Scheme has to be viewed.
The Beas project w i l l consist of two units. The first of these, the Beas-Sutlej L i n k envisages the construct ion of a darn at Pandoh in K u l u Valley to divert the waters of the r iver Beas to the Bhakra reservoi r t h rough tunnels and open conduits. The ' l i n k ' w i l l consist of the 5-mile Pandoh-Suketi tunnel, the 14-mile Suketi Val ley hydel channel and, f inally, the 9-mile Suketi-Dehar tunnel. ft w i l l have a natural fa l l of 1,000 feet at Debar where a power plant w i l l be installed. The m i n i m u m flow through the ' l ink' w i l l be 7,500 cusecs. except du r ing the dry months .when il w i l l be 1,800 eusecs. The power plant at Dehar w i l l supply about 600 mW of f i rm power. Further, the conduct ion of Mink' w i l l ease pressure on the Gobind Sagar and therefore, make possible addi t ional power generation al Bharka and extension of i r r i ga t ion facilities to Southern Punjab.
Long-term Project
Pre l iminary work on this part of the Beas Scheme was scheduled to begin in 1960-61 w i t h an allocation of Rs 50 lakhs. Out of the total cost of Rs 80 crores, Rs 13.5 crores ( i nc lud ing Rs 7 crores in foreign exchange) w i l l be incurred d u r i n g the t h i r d Plan.
The second par t of the Beas project w i l l cover a 325-feet h igh earth and rock fill dam at Pong in Kangra Dis t r ic t w i t h a ' l i ve ' storage capacity of 5.55 m i l l i o n acre-feet and a power house w i t h a capacity of 122 mW of firm power at 100 per cent load factor. Water stored in the dam w i l l be released to the Rajasthan Canal and the S i r h i n d
Feeder du r ing the winter months. Construction of the dam w i l l be undertaken j o i n t l y by Rajasthan and Punjab and its i r r i ga t i on benefits w i l l accrue mainly to the former while Punjab w i l l benefit chiefly f r o m the new power generated. A detailed project report fo r this un i t has been prepared and the total cost is estimated at Rs 87 crores of which Rajasthan w i l l meet about Rs. 70 crores. A sum of Rs 60 lakhs is expected to be spent du r ing 1060-61 on p re l imina ry work. The t h i r d Plan includes an allocation of Rs 10.1 crores. i nc lud ing Rs 12.38 crores in foreign exchange for this part of the project. It must he noted, however, that though tin-t h i rd Plan contains a sizeable alto-cation for both units of the project, no benefits are l ikely to accrue du r ing this per iod.
Power from Bhakra
The overall feasibili ty of the two-unit Beas project has been established. But in view of the fact that the Pong Dam lies in a seismic area, the axis on which its foundations w i l l rest remains to be ascertained. For this purpose a tunnel is proposed to be dug below the river bed at Pong. The General Manager of the Bhakra project has been given charge of the Beas project and so the transfer of men and equipment f rom Bhakra to the new sites w i l l be faci l i ta ted. The control and supervision of the Beas project is l ike ly to he entrusted to an auto nomous hoard w i t h representatives of the Central Government and the two State Governments associated w i t h the project. The Uni ted States and the W o r l d Bank have offered $33 m i l l i o n and $23 m i l l i o n respectively as loans to meet the foreign exchange costs of the proj e c t
The Beas project w i l l in due course be dovetailed to the Bhakra system to become one of the largest power systems in the w o r l d . The Bhakra system itself is made up of two units—the Bhakra Dam proper and the power stations on the Nan-gal Hydel channel at Kotla and Ganguwal which have an installed eapacitv of 48 mW each. An addit ional uni t with a capacity of 20 mW
is being installed at both Kot la and Ganguwal. These units w i l l he ready by March and June 1961 respectives
But the much bigger power generat ing units are at Bhakra. The Left Bank Power House, the first unit of which was commissioned in November last, w i l l have five generating units of S3 to 00 mW capacity each, depending on the water level in the reservoir. A l l these units are expected to be commissioned during 1961. Only four of them, however, w i l l work at a l ime and so the f i rm power capacity of the Power House w i l l he 212 mW in al l .
The Right Bank Power House of the Bhakra Project is estimated to cost Rs. 26.4-3 crores of which Punjab w i l l contribute about Rs 21 crores. Dur ing the t h i rd Plan a total of Rs. 21.11 crores w i l l be spent on it. wi th Punjab contributing 18.71 crores. W i t h the construction of this Power House, the total cost of the Bhakra-Nangal Project w i l l come to Rs 196.43 crores of which Rs 96.66 crores w i l l be accounted for by power schemes. In i t i a l l y four units of 70 to 120 mW capacity each wi l l be installed and a f i f th wi l l be added later when the Beas-Sutlej "link' is completed.
Thermal and Diesel Units
The entire power complex can. however, be put out of gear if rainfall is inadequate or late, Except when rainfal l is so poor that the water level in the reservoir falls below the penstocks, the working head available at Bhakra w i l l vary from 268 feet in May-June to 512 feet immediately after the monsoons in October. Now, the same quantity of water can generate more power if released f rom a higher head than f rom a lower head or, conversely, to venerate a given quanti ty of power more water has to be released from a lower head than f rom a higher one. Water level being high dur ing October-November less water w i l l have to be. released to generate power. Dur ing this period, however. more water has to be released for Rabi sowing and so the advantage of the h igh water level for power generation may not be ful ly realised in practice.
Letter from Punjab
15
January 7, 1961 T H E E C O N O M I C W E E K L Y
A p a r t f r o m this difficulty, w h i c h is characteristic of a l l Bhakra- type mul t i -purpose projects i n I n d i a , there is the fur ther uncertainty about r a i n f a l l . However, i t is proposed to firm up Bhakra hydro-power w i t h thermal and diesel sets. A nucleus one-unit scheme w i t h a capacity of 50 mW is to be in i t i a ted near D e l h i . Smal l diesel stations w i t h capacity up to 25 mW w i l l be set up at var ious load centres l ike Chandigarh , Sangrur , etc at a to ta l cost of Rs 2 crores.
Seasonal Load V a r i a t i o n in water level introduces
the p rob lem of developing adequate seasonal power load . Since, as mentioned above, water level in the Bhakra reservoir w i l l va ry f r o m about 270 feet in May-June to about 510 feet in October, generat i o n of secondary power above the f i rm capacity w i l l be possible on ly for 6 to 8 months f r o m October. Seasonal industries must,, therefore, be started to consume this secondary power w h i c h w i l l not be avai l able a l l th rough the year. Cane crushing, cotton g inn ing , and processing of ag r i cu l tu ra l produce in general are some such industries.
Load centres in Punjab are growing r a p i d l y . Besides, D e l h i w h i c h now consumes for 60 mW of Bhakra power, w i l l take away another 40 mW of the power generated by the Right Bank Power House. At the same t ime a l l towns w i t h a populat ion of 10,000 and over have been electrified. F ina l ly , of the 20,000 villages in Punjab , 3,000 are to be electrified by the end of the second Plan and another 3,000 d u r i n g the t h i r d P lan . As against this r a p i d g r o w t h im load , targets of increase in power generat ion are as fo l lows:
Ins ta l led F i r m ( i n m W )
Firs t Plan 96 84 Second Plan 652 373 T h i r d Plan 1229 680
The present power shortage may not be relieved t i l l mid-1961 when the new uni ts at K o t l a and Gangu-wal are com missioned. Even this add i t ion to capacity is l ike ly to be soon outs t r ipped by increase in load. U l t i m a t e l y , Punjab can expect to have a sound power base only when the Righ t Bank Power House is commissioned by 1964-65. The Beas Scheme, as ment ioned above, is a long-term project , In the meant ime, extension of the o ld U h l River ( Jogindernagar) Scheme, exploita
t i on of the power potential of the water fal ls in Uppe r B a r i Doab and Western Jamuna Canals and the i n stallation of thermal and diesel sets, discussed above, are expected to alleviate the power shortage in the State.
was 369,072 metr ic tons, according
to the I n d i a n Bureau of Mines. Th i s
represents an increase of about 9 per
cent as compared to the output of
338,512 metr ic tons in the correspond
i n g per iod of the preceding year.
The entire product ion was reported
f rom Singhbhum dis t r ic t o f B i h a i
State.
Copper Ore Production T H E produc t ion o f copper ore
d u r i n g January-October, 1960