the echowater project leveraging technology to enhance ... … · 05/06/2019 · bim modeler...
TRANSCRIPT
![Page 1: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/1.jpg)
© 2017 HDR, Inc., all rights reserved.
The EchoWater
Project
Leveraging Technology to Enhance Project DeliveryChristina Romano, PE, PMP, Brown and Caldwell
Ron Perkins, PE, CCM, HDR Engineering, Inc.
![Page 2: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/2.jpg)
What is the EchoWater Project
Implementing 3D/4D/5D
Benefit: Issue Visualization
Benefit: Project/Operations Coordination
Benefit: Asset Data Transfer
Summary - Results
Benefit: Schedule Analysis
![Page 3: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/3.jpg)
What is the EchoWater Project
![Page 4: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/4.jpg)
Service Area
![Page 5: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/5.jpg)
Regional San is California’s Largest Inland Discharger
It serves approximately
1.4 million residents
in the greater
Sacramento Region
SRWTP began operating in 1982; it replaced 22 separate treatment systems
The plant discharges to the Sacramento River, which flows to the Delta and the San Francisco Bay
It is responsible for major interceptors
and the Sacramento Regional
Wastewater Treatment Plant
(SRWTP)
![Page 6: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/6.jpg)
• Required significantly higher treatment to remove ammonia, nitrates, and
further reduce pathogens in the treated water
• Ammonia removal MUST be completed and operational by May 2021;
filtration/disinfection by May 2023
• 2011 – 2012 – Initial Studies, Design, and Build 0.5-mgd Pilot Plant
• February 2012 – Commissioned Program Management Office
• Late 2014 – Environmental Document Complete
2010 Discharge Permit (NPDES)
![Page 7: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/7.jpg)
EchoWater Project Stats
• Original Program cost estimate: $2.1 billion
• Current Program cost estimate:$1.735 billion
• Number of discrete projects: 24
• Peak month spending: $35 million
• Estimated daily workers at site: 500 at peak
![Page 8: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/8.jpg)
8
![Page 9: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/9.jpg)
Return Activated Sludge
Tertiary Treatment Facilities
Flow Equalization
BNR/PEPS
Miscellaneous
Site Buildings
Main Electrical Substation Expansion
Nitrifying Sidestream Treatment
Miscellaneous Site Buildings
Bufferlands Building
Disinfection Chemical Storage
![Page 10: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/10.jpg)
Implementing 3D/4D/5D
![Page 11: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/11.jpg)
3D 4D 5DVISUALIZATION SCHEDULING ESTIMATING
• Existing Conditions
• Animations
• Renderings
• Walkthroughs
• Project Phasing
• Visual Validation
• Interproject
Coordination
• Cost Phasing
• Quantity
Extractions
• Funding
Projections
![Page 12: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/12.jpg)
• Established
CAD/BIM
standards for all
designers
• Established
processes for
updating files
from design
through
construction
Establish BIM Standards
Step ADesigner BIM modeler places
file sets into a DropBox folder
under their project
Step BBIM modeler copies link to
shared folder into existing
PMWeb deliverable record
Step CBIM modeler sends
PMWeb notification to
PMO, designers, and
schedulers as new files
are posted. Include
a description of changes
DropBox notifies PMO and
designers of new files posted
Step EBIM administrator posts clash
detection results on comments page in
a) PMWed deliverables record if formal or
b) PMWeb Document Manager if informal
Step DBIM administrator copies DWG,
NWD, RVT files to Z drive and
merges into master model
for analysis
BIM Modeler (Designer)
BIM Administrator (PMO)
BIM
Model
(Designer)
PMWeb
BIM
Model
(Master)
![Page 13: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/13.jpg)
• Established
scheduling
standards for all
designers and
contractors
• Established
processes for
updating schedules
design through
construction
Establish Scheduling/4D/5D Standards
![Page 14: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/14.jpg)
Benefit: Issue Visualization
![Page 15: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/15.jpg)
Pre-Construction Use of BIM
Effective Project Planning
Visualization of design
options/studies
Site utilization planning
![Page 16: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/16.jpg)
Primary Effluent Pumps 3D Rendering
![Page 17: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/17.jpg)
BIM-Clash Detection
![Page 18: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/18.jpg)
Inter-Project Connections
![Page 19: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/19.jpg)
Benefit: Schedule Analysis
![Page 20: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/20.jpg)
4D and 5D BIM
• Synchro Model, P6 Schedule,
and Cost Integration
![Page 21: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/21.jpg)
![Page 22: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/22.jpg)
Baseline Schedule Scope Gap
![Page 23: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/23.jpg)
Visual Schedule Variance Analysis (VSVA)
![Page 24: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/24.jpg)
Benefit: Project/Operations Coordination
![Page 25: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/25.jpg)
Brown and Caldwell 25
![Page 26: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/26.jpg)
• Inter-Project ConflictsConstruction Use of BIM
![Page 27: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/27.jpg)
Brown and Caldwell 27
![Page 28: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/28.jpg)
Benefit: Asset Data Transfer
![Page 29: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/29.jpg)
Leveraging Smart P&ID and BIM Data Transition to Operations:
![Page 30: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/30.jpg)
• Asset Management Design Database (AMDD) serves as the hub for design and construction data capture
• AMDD interfaces with design models and construction phase inputs for assets, spare parts, warrantees, and maintenance requirements for export to CMMS
• AMDD includes tracking and controls tools for quality and completeness of data being transferred to CMMS
Timely data is always a challenge. CM and Designer review of BIM as-built data keeps pressure on contractor and aids commissioning processes.
Capturing Asset Data for Migration to Plant CMMS
![Page 31: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/31.jpg)
Summary - Results
![Page 32: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/32.jpg)
• No unplanned operational impacts to date
• Program is on schedule for meeting discharge permit deadlines
• Program total cost $1.7B versus initial $2.1B estimate
• Future recycled water project in planning phase
EchoWater Project Progress and Results
![Page 33: The EchoWater Project Leveraging Technology to Enhance ... … · 05/06/2019 · BIM modeler copies link to shared folder into existing PMWeb deliverable record Step C BIM modeler](https://reader033.vdocuments.mx/reader033/viewer/2022050506/5f97ec2996778a425947f79b/html5/thumbnails/33.jpg)
Presenter Contact Information
• Christina Romano, PE, PMP [email protected]
• Ron Perkins, PE, CCM [email protected]
Questions