THE DEVELOPMENT OF THE BRONKHORSTSPRUIT BIOGAS PROJECT
MARCH 2015
CONTACT:
Sean Thomas, CEO
+27 (0) 79 496 6725
+27 (0) 11 067 4747
First deal of its kind in South Africa
PROJECT SUMMARY• Bio2Watt, is a Waste to Energy Project Development Company which owns, develops
and builds the projects it is involved in.
Bronkhorstspruit Biogas Project (Pty) Ltd (“BBP”) is a Renewable Energy IPP:
• 4.4MW installed electrical capacity and further 3MW available for greenhouse farming
• Electricity will be sold to BMW in Pretoria, roughly 60kms from the site.
• Total project costs amount to R150m, broken down as follows: R36m equity, R16m dti
(SA govt) grant, R98m loan from the Industrial Development Corporation
• The project is structured as a limited recourse finance transaction. Equity investors
include Norfund, the EPC contractor, two impact funds and Bio2Watt.
• Project will officially start evacuating power in April 2015
THE BRONKHORSTSPRUIT BIOGAS PROJECT
WASTE REDUCTION
JOB CREATIONMORE
RENEWABLE ENERGY
DEVELOPING LOCAL EXPERTISE
FLARE
MIXER
FOOD PRODUCERS
DIGESTORFERTILISER
OFF-TAKER
3MW
GAS ENGINES
POWER PURCHASING AGREEMENT
BIOGAS
ORGANIC WASTE
WASTE
BENEFITS
AVOID WATER POLLUTION
BYPASS LANDFILLS
AVOID GHGEMMISSIONS
23-04-18 Confidential
Anaerobic Digestion
SOME INTERESTING FACTOIDS
1,5001,5001,5001,500
R8MR8M
7 years7 years7 years7 years From when project was started to Financial Closure March 2014
Pages of Legal documents – Typically agreements would lapse
… spent in legal fees
BBP – PROJECT TIMELINE
PPA negotiations PPA negotiations
Environmental Impact AssessmentEnvironmental Impact Assessment
Supply AgreementsSupply Agreements
Pre-feasibility study
Pre-feasibility study
Jan 2007 Jan 2008 Jan 2009 Jan 2010 Jan 2011 Aug 2012 Mar 2013 Feb 2014 Apr 2015
Connection and Wheeling AgreementsConnection and Wheeling Agreements
Licenses & Permits Licenses & Permits
Debt/Loan Agreement - IDCDebt/Loan Agreement - IDC
EPC AgreementEPC Agreement
O&M Agreement
O&M Agreement
Equity InvestorsEquity Investors
ConstructionConstruction
PROJECT TIMELINE
Environmental Impact Assessment
Environmental Impact Assessment
Supply AgreementsSupply Agreements
Pre-feasibility study
Pre-feasibility study
Start 6 months 12 months 18 months 24 months 30 months 36 months 42 months 48 months
Connection and Wheeling Agreements
Connection and Wheeling Agreements
Licenses & Permits Licenses & Permits
Debt/Loan Agreement - IDC
Debt/Loan Agreement - IDC
EPC AgreementEPC Agreement
Operations Operations
Equity InvestorsEquity Investors
ConstructionConstruction
PPA negotiations PPA negotiations
23-04-18 Confidential
Challenges specific to SA
- Manure has to be at most 4 weeks old
-Mechanism to control stones from the manure
-Manure alone is not sufficient to make the plant viable
-Support from farm is critical e.g. grey water is required ±300m3/day
-At this stage Electricity price will be higher than municipality or Eskom
-The plant will require an off-taker that operates baseload
-Returns are low and drawn out - requires patient investors
-A very long list of licenses required
23-04-18 Confidential
Licenses required for biogas project
LICENSES: - EIA
- WULA
- Waste License
- Air Emission License
- SALA
MUNICIPALITIES: - Building Plan approval
- By Laws
- Consent of Use
DOE, NERSA & ESKOM: - Generation License
- Letter from DOE
- Access to grid
23-04-18 Confidential
Opportunities for large SA feedlots
- Though the power is not sold to the feedlot owner it will be used in the vicinity
of the plant – offering security of supply & possibility to access additional
capacity which is valuable in current power constrained context
- Availability of a higher grade fertiliser both liquid and solid on site
- Access to a source of heat and carbon dioxide which could allow Farm to
diversify
- Lease of land
- Better management of waste supported by Department of Environmental
Affairs
How was this possibleFarm:
-Buy-in & support from Farm is critical
-Extensive amount of input required e.g. banks even request access to books to
ensure Farm’s sustainability
Funding
-Patient investors
-Development Finance Institution providing attractive loan
Off-taker
- Willing to pay a premium for Green Electricity
23-04-18 Confidential