the big dig team summit topic presentation april 19 th, 2005 tommy nguyen & candace pederson
TRANSCRIPT
![Page 1: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/1.jpg)
The BIG DIG
Team Summit Topic Presentation
April 19th, 2005
Tommy Nguyen & Candace Pederson
![Page 2: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/2.jpg)
Problem
• Boston, Massachusetts’ main highway - the 6 lane Central Artery - (built in 1959) along with the harbor crossings could not predict the exponential growing Boston community that it would have to support in the years to come…
![Page 3: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/3.jpg)
Conditions will only worsen…
• High congestion at least 10 hours/day• Has 4x’s the national accident rate average• Deteriorating and becoming unstable and unsafe• Environmental concerns • Wasted fuel from idling and late deliveries cost
drivers 500 million dollars/year• this elevated highway cuts off communities from
Boston – severing them from economic culture
![Page 4: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/4.jpg)
Boston’s Future
• By 2010, it is predicted that the Central Artery will be completely congested with a permanent traffic jam that lasts all day and all night.
![Page 5: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/5.jpg)
SolutionCA/T (Central Artery/Tunnels Project or The “Big Dig”)
• 8-10 lane UNDERGROUND expressway underneath the existing structure
• Merging as a 14 lane two bridge crossing over the St. Charles river
• Central Artery will be demolished and space used for other developments (such as park space)
![Page 6: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/6.jpg)
Challenges
“To put these highway improvements in the ground in a city like Boston proved to be one of the largest, most technically difficult and environmentally challenging infrastructure projects ever undertaken in the United States.” (http://www.masspike.com/bigdig/background/index.html#problem
![Page 7: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/7.jpg)
Predicted Solution Benefits
• Less time in traffic!
• 12% reduction in carbon monoxide levels
• Connect communities that were once severed
• 260 acres of open land – much of it used for new parks
• Capped off old dumps with dirt from project
![Page 8: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/8.jpg)
Project SCOPE Management
• Replace the 6 lane elevated highway with an 8-10 lane underground expressway– 14 lane/2 bridge crossing over St. Charles River– Old highway used for parks/developments
• Add extension of I-90 (Mass Turnpike) will be a tunnel beneath South Boston & the Boston Harbor – First link will be the Ted Williams Tunnel under the
harbor
![Page 9: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/9.jpg)
Project TIME management
• Project started in 1991 (design began in 1980s)
• Summer 2004, 94% complete
• Entire project will be finished mid-2005
![Page 10: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/10.jpg)
• 1983: Work begins on Final Environmental Impact Statement/Report • 1987: Congress approves funding and scope of Project.
Building acquisition and business relocation process begins.• 1990: Congress allocates $755 million to project. Construction begins on
Ted Williams Tunnel and South Boston Haul Road. • 1992: More than $1 billion in design and construction contracts under way.
Dredging and blasting for the Ted Williams Tunnel ongoing. Archaeologists find 17th and 18th century artifacts at a North End dig.
• 1993: South Boston Haul Road opens. All 12 tube sections for Ted Williams Tunnel are placed and connected on harbor floor.
• 1994: Charles River Crossing design approved. New set of loop ramps open in Charlestown.
• 1998: Enter peak construction years, including Charles River Crossing. • 1999: Overall construction 50 percent complete.
New Broadway Bridge opens. 2000: Nearly 5,000 workers employed on the Big Dig
• 2001: Overall construction 70 percent complete. • 2004: Dismantling of the elevated Central Artery (I-93). Looking Ahead . . . • 2005: 96% complete. Issues are popping up…
Timeline
![Page 11: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/11.jpg)
Project COST management
• Construction: $9,120 Million
• Force Accounts: $596 Million
• Right of Way Settlements: $572 Million
• Design: $996 Million
• Project Management: $1962 Million
• Insurance: $572 Million
• Contingency: $258 Million
![Page 12: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/12.jpg)
Project Management Monthly (PMM)
• CA/T established this report to publicly document scope, schedule, and cost progress.
• Posted on website for anyone to view
• Lists all project management details that are discussed
![Page 13: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/13.jpg)
Current Problems
• Cost overruns!
• Leaky tunnel walls
• Tuesday April 5th: Dirt/debris fall and hit motorists (damage cars/ambulance)
![Page 14: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/14.jpg)
The Big Dig
![Page 15: The BIG DIG Team Summit Topic Presentation April 19 th, 2005 Tommy Nguyen & Candace Pederson](https://reader036.vdocuments.mx/reader036/viewer/2022072006/56649f455503460f94c665e3/html5/thumbnails/15.jpg)
References
• Official website: http://www.masspike.com/bigdig/index.html
• CNN.com: http://www.thebostonchannel.com/news/4351211/detail.html?subid=22100410&qs=1;bp=t
• Boston News: http://www.boston.com/news/traffic/bigdig/
• Photos: http://www.csmonitor.com/slideshows/durableSlideshows/bigdig/slide7.html