the applicable legal requirement

Upload: nishit-rupapara

Post on 04-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 The Applicable Legal Requirement

    1/21

    REGISTER

    OF

    LEGAL AND OTHER

    REQUIREMENTS

  • 7/29/2019 The Applicable Legal Requirement

    2/21

    List of applicable laws and regulations

    01 The Air (Prevention and Control of Pollution) Act, 1981 A

    02 Environmental (Protection) Act, 1986 A

    03 The Environmental (Protection) Rules, 1986, amended up to 2008 A

    04 Notification on Control of noise from DG sets A

    05 The Hazardous Waste (Management & handling) Rules, 1989,

    amended up to 2008 A

    06 Manufacture, storage and Import of hazardous chemicals Rules,

    1989, amended up to 2002. A

    07 The Noise pollution (Regulation & Control) rules, 2000 A

    08 The Central Motor vehicles Rules, 1989. A

    09 Th P l A 1934 A

  • 7/29/2019 The Applicable Legal Requirement

    3/21

    LEGAL PROCEDURAL REQUIREMENTS

    S.No Act/Rules Regulation / Obligations Relevant

    Documents

    Current Status Responsibility Remarks

    01 The Air (Prevention and Control

    of Pollution) Act, 1981/82/83

    To Comply with the Conditions in the

    consent to establish or consent to

    operate.

    Follow the Ambient Air QualityStandards for SPM, SOx, NOx, CO

    etc.

    Furnish information to the HPCB of

    any accident or unforeseen act or

    event.

    Allow entry to the HPCB to ascertain

    that provisions of the Act are being

    complied with.

    Provide access to the HPCB for taking

    samples.

    To comply with the directions issued

    in writing by the HPCB

    Dust level

    Noise Level

    last checked

    on

    To take consent

    CLIENT

    On site working

    and follow up by

    contractor

    On site follow up

    and documentation

    by contractor

    Complied

  • 7/29/2019 The Applicable Legal Requirement

    4/21

  • 7/29/2019 The Applicable Legal Requirement

    5/21

    S.No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    02 Environment

    (Protection) Act, 1986,

    Rules, 1986

    To prevent discharges or emissions

    in excess of the prescribed

    standards.

    To furnish information of any

    accidental or unforeseen event.

    An Environmental Statement is to

    be submitted in the prescribedformat by 30th September every

    year

    To comply with the directions of

    the MoEF/ HPCB. The directions

    may include:

    i) Closure, Prohibition or regulation

    of any activity of CLIENT; or

    ii) Stoppage or regulation of thesupply of electricity, water or any

    other service.

    Allow entry and inspection to

    ascertain compliance.

    Allow samples to be taken.

    Air Monitoring

    Noise Monitoring

    Water Testing etc.

    Environmental

    Statement

    Water Pollution

    and Air Pollution

    Standards

    Monthly

    report on

    Env status

    sent to

    Client

    On site

    documentation to be

    maintained by

    contractor and

    supervision by

    CLIENT shouldprepare

    EnvironmentalStatement on basis of

    documentation

    submitted by

    contractor and submit

    it to HPCB

    Sent by 7th of

    every month

    03 Notification for Noise

    levels for diesel

    generator sets

    DG sets (above 15kw) should be

    provided with acoustic enclosures.

    The insersion loss should be at least

    25 dB (A) or the ambient noise

    level whichever is maximum

    D.G. Sets, & other

    Plant Machinery

    Relevant

    Notification

    DGs with

    Accoustic

    Enclosure

    s provided

    Enclosures for

    generators should be

    constructed byContractor All Legal

    Permissions to be taken

    by CLIENT

    Complied

  • 7/29/2019 The Applicable Legal Requirement

    6/21

    S.No Act/Rules Regulation / Obligations Applicable area Relevant Documents Current

    Status

    Responsibility Remarks

    04 The Hazardous Waste

    Management &

    Handling) Rules,

    1989;

    To identify the wastes generated and

    cover under the regulation (by

    referring Schedule 1 & 2)

    Obtain Authorization for the

    collection, storage, treatment anddisposal of hazardous wastes

    Generate inventory of hazardous

    wastes in the Form N0.3. Return on

    the generated waste is to be filed in

    the Form No.4

    Follow a Manifest system (according

    to the Form 9) for off-site disposal of

    hazardous wastes

    Labelling and packaging of wastecontainers should be as per Motor

    Vehicle Act, Rules for transportation

    of haz. Waste

    Oil, Grease, Epoxy

    & Resin,

    Admixture,

    Lead/Acid Batteries

    etc.

    Contractor shouldsubmit bentonite

    proper handling &

    disposal procedure

    and consent should

    be taken by

    CLIENT.

    Being

    disposed

    off through

    CPCB

    approved

    vendorsonly

    Copy of

    Form 9

    being recdfrom the

    vendor.

    Legal/Written:

    CLIENT. On site

    implementation by

    contractor

    Complied

    05 Manufacture, Storage

    and Import of

    Hazardous chemical,1989,

    To identify the chemicals covered

    under schedule 1, 2 and 3 of the

    regulation (updated monthly)

    To identify hazards associated with

    CLIENT activity and take adequate

    steps for prevention and control.

    To provide information, training and

    PPEs to the persons handling

    hazardous chemicals

    . Diesel, Paints etc.

    Emergency

    Procedure and Plan

    MSDS

    Safety report.

    Onsite emergencyplan

    Legal/Written:

    CLIENT. On site

    implementation bycontractor

  • 7/29/2019 The Applicable Legal Requirement

    7/21

    To provide relevant information to

    persons liable to be affected by a

    major accident.

    To submit written report regarding

    Notification of Site at least 3months before commencing any

    activity (if Schedule 3 is applicable)

    To develop information in the formof a Material Safety Data Sheet

    (MSDS)

    To notify the concerned authorities

    within 48 hours of the occurrence of

    a major accident.

    To label the specified information on

    every container of a hazardous

    chemicals

    To prepare upto date on -siteemergency plan before commencing

    a new industrial activity involving

    specified chemicals

    To conduct mock-drill at least once ina month and report be submitted to

    the concerned authorities

    Contractor

  • 7/29/2019 The Applicable Legal Requirement

    8/21

    S.No Act/Rules Regulation / Obligations Applicable area Relevant Documents Current

    Status

    Responsibility Remarks

    06 The Motor Vehicle

    Act, 1988.

    Central motor

    Vehicle Rules

    To ensure that transportation of

    hazardous materials is taken place

    in accordance with the regulation

    - Manner of display of class

    labels

    - Safe transfer of hazardous goods

    - Driver to report to the police

    station about accidents

    Cover the truck &

    Vehicle

    PUC certificates,

    Permission to

    transport hazardous

    Material or trump

    card with vehicle.R.C. book , T.C.

    Book & insurance

    Certificate of the

    vehicle

    PUC

    certificates

    for all

    vehicles by

    AdmnDept.

    ContractorComplied

    07 The Petroleum

    Act, 1934.

    To obtain a permit under the

    regulation from the CCE for thequantities of petroleum product (s)

    stored

    The permit is renewable.

    Follow the conditions provided in the

    permit

    Diesel Storage , Oil

    & Grease Storage

    NAOil storagebeing less

    than 2500litres, no

    license

    reqd

    Contractor

    N.A

    08 Regulation on

    Recycling of waste

    oil, spent lead-acidbatteries and non-

    ferrous scrap

    These materials to be auctioned to

    only those recyclers who are

    registered with the Ministry ofEnvironment & Forests

    Traders should not be involved in

    such auctioning/ contract

    Oil, Grease, Epoxy

    & Resin, Admixture,

    Lead/Acid Batteriesetc.

    Contractor: On site

    implementation and

    legal requirement withCLIENT.

    Complied

    09 Batteries

    (Management &

    Handling) Rules,

    2001

    Old batteries need to be returned to

    the OEMs

    Spent Batteries on

    site

    Will be sold to

    suppliers

    Being

    returned to

    the battery

    supplier

    Contractor: On site

    implementation andlegal requirement with

    CLIENT.

    Complied

  • 7/29/2019 The Applicable Legal Requirement

    9/21

    LEGAL PROCEDURAL REQUIREMENTS

    Building and Other Construction Workers (Regulation of Employment and

    Conditions of Service) Act, 1996.S. No Act/Rules Regulation / Obligations Applicable area Relevant

    Documents

    Current

    Status

    Responsibility Remarks

    1. Registration ofEstablishment

    a) Manner Of Making Application

    The application shall be made in triplicate, as

    per the standard format.

    Every application should be accompanied by a

    demand draft of the fees.Application either personally delivered or sent

    by post.

    On receipt of the application, the registering

    officer shall, after noting the date of receipt, grant

    an acknowledgement to the applicant.

    b) Grant of certificate of registration - afterreceiving the application, The Registering Officer

    shall issue a certificate to the applicant within 15

    days.

    c) Payment of additional fees and amendment of

    register etc. when the registering officer is

    satisfied that an amount higher than the amount,which has been paid by the employer as fees, he

    shall require such employer to pay additional

    sums, which together would be equal to the such

    amount which is payable for the registration.

    d) Condition of registration it shall be non-

    transferable, the number of workmen shall not

    exceed the maximum limit, the employer shall

    submit a written notice to the inspector about the

    commencement or completion of work.

    e) Fees A fees to be paid for the grant of a

    certificate of registration as per the rule.

    Admn Head (ADMN)

    2. Display Of A copy of the certificate shall be displayed at the Site Office Head(ADMN)

  • 7/29/2019 The Applicable Legal Requirement

    10/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    RegistrationCertificate AtWorkplace

    premises where the construction work is being

    carried out.

    3. Hours of Work No worker shall be required or allowed to work

    for more than nine hours a day or 48 hours aweek. Not allowed to work for continuously 5hours.

    Site Office Head(ADMN) Complied

    4. Register of Overtime

    A register of overtime, for recording therein the

    number of hours of, and the wages paid for

    overtime work.

    ADMN Deptt Head(ADMN) Complied

    5. Weekly Rest AndPayment At Rest

    No building worker employed in building or

    other construction work shall be required or

    allowed to work on the rest day unless the will of

    the worker or a substitute rest day.

    ADMN Deptt Head(ADMN) Complied

    6. Night Shift The hours after midnight during which the

    worker has worked shall be counted towards the

    previous day.

    ADMN Deptt Complied

    7. Intimation OfCommencementAnd Completion

    Every employer shall intimate the inspector in

    written, before 30 days, about the commencement

    of the work.

    ADMN Deptt Complied

    8. MaintenanceCommencementAnd Completion

    If any change is occurs in any of the particulars

    furnished the employer shall intimate such

    changes to the employee

    ADMN Deptt Complied

    9. Register OfPersonsEmployed AsBuildingWorkers

    Employer shall maintain in respect of each

    registered establishment, where he employs

    building workers.

    ADMN Deptt Complied

    10. Payment of Wages

    if less than 1000 workers are employed then all

    wages shall be paid before the expiry of the 7th

    day or in other case before the expiry of 10th day.

    ADMN Deptt Complied

  • 7/29/2019 The Applicable Legal Requirement

    11/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    11. Display OfNotice Of Wagesregarding

    The date, place and time of wages to be paid shall

    be displayed at the working area in Hindi,

    English and local language.

    ADMN Deptt Complied

    12. Register OfDamage AndLoss

    A register of deduction, damage or loss, register

    of fines and register of advance shall be

    maintained by the employer.

    ADMN Deptt Complied

    13. Issue of WagesBook

    When the wage period is 1 week or more, the

    employer shall issue the wage book to each

    worker.

    ADMN Deptt Complied

    14. ServiceCertificate ForEach Workers

    Employer shall issue the service certificate to

    each of building worker on termination of theservice on account of completion of work or any

    other reason.

    ADMN Deptt Complied

    15. Display AnAbstract OfBOCWA And

    BOCWR

    Every employer shall display at the conspicuous

    places of the work site, an abstract of the Act and

    the rules in Hindi, English and local language

    understood by the workmen.

    ADMN Deptt Complied

    16. Annual Return employer shall send annually a return relating to

    the establishments to the registering officer so as

    to reach him no later than 15th February

    following the end of each calendar year with a

    copy to the inspector.

    ADMN Deptt Complied

    17. Drinking Water employer shall provide the sufficient supply ofwholesome water, provided and maintain at

    suitable locations for all persons, with properly

    marked as Drinking Water.

    ADMN Deptt Complied

    18. Latrines & Urinals employer shall provide sufficient latrine andurinal accommodation of prescribed type with

    properly marked as For Men and For Women

    at the suitable locations.

    ADMN Deptt Complied

    19. Accommodation employer shall provide free of charge with in the

    work site or near to it, temporary living

    accommodation to the workers for such period till

    the construction work in progress.

    ADMN Deptt Complied

    20. Creches every place wherein more than 50 female workers

    are employed, the employer shall provide and

    ADMN Deptt Complied

  • 7/29/2019 The Applicable Legal Requirement

    12/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    maintained the room or rooms for the use of

    children below the age of 6 years.21. First-Aid Boxes sufficient number of first aid boxes are provided

    and maintained, which shall be properly named as

    First-Aid, for the workers.

    ADMN Deptt Complied

    22. Canteens employer shall provide and maintain a canteen inevery place wherein not less than 250 building

    workers are ordinarily employed.

    ADMN Deptt Complied

    23. Food Stuff AndOther ItemsServed In TheCanteen

    The food items served in the canteen shall be in

    conformity with the normal dietary habits of the

    workers.

    ADMN Deptt Complied

    24. Supply Of TeaAnd Snacks InWork Place

    at a work place, situated at a distance of more

    than 0.2 Km from the canteen, the arrangements

    shall be made by the employer for serving tea and

    light snacks at these places.

    ADMN Deptt Complied

    25. Food ChargesOn No Profit NoLoss Basis

    The charges for food and beverages and otheritems served in the canteen should be on no profit

    no loss basis and the price list of such items

    should be properly displayed.

    ADMN Deptt Complied

    26. Safety Committee establishments wherein 500 or more workers are

    ordinarily employed, there shall be a safety

    committee constituted by the employer with such

    number of executives as prescribed by the state

    government. The main function of the committee

    would be to identify the probable cause of

    accident and unsafe practices at the work place

    and suggest remedial measures.

    Safety Deptt Complied

    27. Safety Off icer officers of the safety committee shall be

    appointed as per the scale, and shall be assisted

    by suitable and adequate staff.

    Whenever the workers employed are less than

    500, such employer may form a group and

    appoint a common safety for such groups, with

    prior permission of Director General.

    Safety Deptt Complied

    28. Reporting OfAccidents And

    the injured worker shall be providing first aid Safety Deptt Complied

  • 7/29/2019 The Applicable Legal Requirement

    13/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    DangerousOccurrences

    facility and immediately thereafter be transferred

    to the hospital for medical treatment. Where any

    accident results to death, the notice of such deaths

    shall be communicated to the authorities in

    written. In case of the failure of any machinery,

    which can lead to an accident, shall be keptundisturbed until inspected by the inspector.

    29. Procedure ForInquiry In To TheCause OfAccidents

    the enquiry shall commence as early as possible

    or within 15 days of getting the notice of

    accident. The authority may conduct the enquiry

    either by himself or by an enquiry officer

    appointed by such authority.

    Safety Deptt Complied

    30. Responsibi li ty ofOfficer

    employer shall be responsible for providing

    constant and adequate supervision of any building

    or other construction work as to ensure thecompliance with the provision of this act relating

    to safety and for taking all practical stepsnecessary to prevent accidents.

    Projects Manager Complied

    31. ResponsibilityOf Architect,Project EngineerAnd Designers

    it shall be the duty of them to ensure any

    consideration is given while considering the

    safety and health aspects of the workers who are

    involved in the erection, operation and execution

    of such projects.

    Safety Deptt Complied

    32. ResponsibilitiesOf Workmen

    it shall be the duty of every building worker to

    comply with the requirement of the rules relate to

    him, and act and co-operate in carrying out the

    requirements of these rules. It shall be theresponsibility of the workers to keep the welfare

    facilities provided by the employer in a clean and

    hygienic condition.

    All deptts Complied

    33. ResponsibilityOf Payment OfWages AndCompensation

    the employer shall be responsible for payment of

    wages and compensation to the worker employed

    by him on or before the due date as may be

    applicable.

    ADMN Deptt Complied

    34. Penalties andProcedures

    whoever contravenes any other provision of this

    act or who fails to comply with any provision of All depttsComplied

  • 7/29/2019 The Applicable Legal Requirement

    14/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    this act, where no express penalty is elsewhere

    provided for such contravention or failure, be

    punishable with fine.35. Excessive Noise,

    Noise Etcemployer shall ensure to protect the workers

    against the harmful effect of excessive noise or

    vibration at the construction site and the noiselevel in no case exceeds the limits laid down.

    Safety Deptt Complied

    36. Fire Protection the construction sites shall be provided with

    suitable fire extinguisher, adequate water supply

    with ample pressure and the trained persons. The

    fire fighting equipment should be properly placed

    and inspected at regular interval.

    Safety Deptt Complied

    37. Emergency ActionPlan

    employer shall ensure at a construction site,

    where more than 500 workers are employed,

    proper emergency action plan is maintained.

    Safety Deptt Complied

    38. Fencing of Motors the employer shall ensure that all motors, gears

    shafts and moving part of machinery are securelyfenced of lagged. The fencing of such parts shall

    not be removed while such machinery is inmotion.

    Safety Deptt Complied

    39. Lifting AndCarrying OfExcessiveWeight

    no building worker lifts by hand or carries over-

    head any material, tool or appliances exceeding in

    weight the maximum limits set out as follows:

    All deptts Complied

    40. Health, SafetyAndEnvironmentPolicy

    every establishment 50 or more building workers

    shall prepare a written statement of policy in

    respect of health and safety of the workers and

    submit the same for the approval of the directorgeneral.

    Safety deptt Complied

    41. Dangerous AndHarmfulEnvironment

    when an internal combustion engine exhaust into

    a confined space, suitable measures are to be

    taken at such places. No worker is allowed to

    enter such places that are likely to bring injuries

    to the worker.

    All deptts Complied

    42. OverheadProjection

    the employer shall ensure that the overhead

    protection is erected along the periphery of every

    All deptts Complied

  • 7/29/2019 The Applicable Legal Requirement

    15/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    building under construction, which shall be of 15

    meters in height.43. Slipping,

    Tripping,Cutting,Drowning And

    Falling Hazard

    all passageways, platforms and other places of

    construction work shall be kept free from any

    such materials which can harm the workers.

    All deptts Complied

    44. Dust, Gases,Fumes Etc.

    the employer shall prevent concentration of dust,gases or fumes by providing suitable means to

    control their concentration within the permissible

    limit so that they may not cause the health hazard

    to any worker.

    All deptts Complied

    45. CorrosiveSubstance

    employer shall ensure that the person, who is

    handling the corrosive substances like acids and

    alkalis, is provided with suitable protective

    equipment. In case of spillage the employer shalltake immediate remedial measures.

    All deptts Complied

    46. Eye Protection suitable personal protective equipment shall be

    provided by the employer to the worker which are

    engaged in welding, cutting, chipping or similar

    operations.

    All deptts Complied

    47. Head ProtectionAnd OtherProtectiveApparel

    every building worker require to pass through or

    working within the areas where there is hazard of

    his being struck by falling objects shall be

    provided by the safety helmets. If the worker is

    working in water or wet concrete, he should be

    provided by the water - proof boots.

    All deptts Complied

    48. Electrical Hazard shall take adequate measure to prevent the workerto directly come into contact with any electrical

    equipment or live electrical circuit. The employer

    shall display and maintain suitable warning

    signals.

    All deptts Complied

    49. Vehicular Traffic whenever the construction work is being carried

    on or is near the proximity of a road, the

    employer shall ensure that the construction work

    place is barricaded and suitable warning signalsare displayed.

    All deptts Complied

  • 7/29/2019 The Applicable Legal Requirement

    16/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    50. Illumination Employer shall ensure that all workplaces where excavation work is doneshall be illuminated according to thenational standard.

    Civil Deptt Complied

    51. Stacking of

    Material

    Shall ensure that all building materials

    are stored or stacked in a safe andorderly manner to avoid obstruction ofany passageway or place or work.

    Civil Deptt Complied

    52. Disposal of Debris Debris are handled and disposed of bya method, which does not causedanger to the safety of a person. Debrisare not allowed to concentrate.

    Civil Deptt Complied

    53. Lif ting Appl iancesand Gears

    Construction and maintenance oflifting appliances: all appliancesincluding their parts, whether fixed ormovable shall be of sound materialand adequate strength.

    Test and periodical examination oflifting appliances

    Automatic safe load indicators:proper warning signal shall be there.

    Installation: shall be by trainedperson and such appliances cannotbe displaced by the load, vibration orother influences.

    Winches: shall not be used if control

    levers operate with excessive frictionor play.

    Buckets: tip-up buckets shall beequipped with a device thateffectively prevents accidentaltipping.

    Identification and marking of safeworking load: every lifting applianceshall be marked with its safe working

    Crane SupplyingAgencies

    Complied

  • 7/29/2019 The Applicable Legal Requirement

    17/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    load capacity.

    Loading of lifting appliances andlifting gears: no lifting appliancesshall be used in an unsafe mannerand shall not be operated beyond

    their loading capacity. Operators cab or cabin: shall be

    made up of fire resistant materialwith a comfortable seat withadequate view.

    Operation of lifting appliances: theoperator posses adequate skill andtraining in the operation.

    Hoists: hoist tower shall be designedaccording to the national standard.

    Fencing of and means of access tolifting appliances: the operatorsplatform on every appliance issecurely fenced and is provided withsafe means of access.

    Rigging of derricks: every derrickshall have current and relevantrigging plans for safe rigging of suchderricks.

    Securing of derrick foot: appropriatemeasures shall be taken to preventthe foot of a derrick being lifted outof its socket or support.

    Construction and maintenance oflifting gear: shall be of good design,adequate strength and soundmaterial to perform the work.

    Test and periodical examination oflifting gear

    Ropes: shall be of good strength and

  • 7/29/2019 The Applicable Legal Requirement

    18/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    free from patent defects.

    Hear treatment of lifting gear.

    Certificate to be issued after actualtesting and examination etc.

    Register of periodical test,

    examination and certificates thereof Vacuum and magnetic lifting gear:

    no such gear or any other such gearshall be used which uses adhesivepower, is used while workers areworking beneath such gear.

    Knotting of chains and wire ropes: nochain or wire rope shall be used witha knot in it.

    Carrying on persons by means of

    lifting appliances, etc.: no buildingworker shall be raised, lowered orcarried by a power driven liftingappliance.

    Hoists carrying persons: a hoistcarries no worker unless it isprovided with a cage.

    Attachment of loads: when a sling isused to hoist long material, a liftingbeam is used to space the sling legsfor proper balance.

    Qualification of operator of liftingwinches and of signaler, etc.: shall beabove 18 yrs. of age and possess theknowledge of the inherent riskinvolved in the operation.

    54. TransportEquipment

    Earth moving equipment andvehicles: all vehicles shall be of goodmaterial and proper design and ofsufficient size to carry the containers.

    Civil Deptt

  • 7/29/2019 The Applicable Legal Requirement

    19/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    All such vehicles are inspected atleast once a week.

    Power shovels and excavators: ashovel or an excavation used forwork is constructed, installed,

    operated, tested and examined asrequired under the law.

    General safety: every vehicle or earthmoving equipment shall be equippedwith silencer, tail lights, power andhand brakes, reversing alarm, etc.

    55. Ladders and StepLadders

    Construction and safe use: shall be ofadequate strength and of soundmaterial and constructed accordingto the national standard. These

    ladders shall not slip. Rungs: no ladder is used which has a

    missing or defective rung or a rungwhich solely depends upon nails.Spikes or other similar fixing.

    Material for ladder: are constructedupright of adequate strength and aremade of straight-gained wood, freefrom defects and having the grains ofsuch wood running lengthwise.

    Concerned Deptt

    56. Stacking and

    Unstacking

    Stacking and unstacking of material

    and articles: stacking of material ismade on firm foundation not liable tosettle and deviate such material anddoes not overload the floor on whichsuch stack is made. Stacks, whichmay lean heavily or becomeunstable, shall be barricaded.

    Stacking of cement and othermaterial bags: such stack pile shall

    Concerned Deptt

  • 7/29/2019 The Applicable Legal Requirement

    20/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    not be more than ten bags in heightunless a support is provided. Bagscontaining cement or lime should bestored in dry place.

    57. Medical

    Examination forBuilding andOtherConstructionWorker, CraneOperator andTransport VehicleDrivers

    Medical examination shall be done by

    such medical officers or at suchhospitals, which are approved bycentral/state government.

    Safety Deptt

    58. Charging of Worker forMedicalExamination

    No worker shall be charged for medicalexamination and the cost of suchexaminations shall be borne by theemployer.

    Admn Deptt

    59. Ambulance Vanand Room If 500 or less workers are employed theemployer shall provide the ambulanceroom at construction site or anarrangement with the nearby hospital.In case of more than 500 employees,the employer shall provide anambulance.

    Safety Deptt

    60. Stretchers The employer shall ensure that sufficientnumbers of stretchers are provided atthe construction site.

    Safety Deptt

    61. Occupational

    Health Service forBuilding Workers

    A special medical service or an

    occupational health shall be availableat the construction site and suchservice shall provide first aid andemergency treatment, periodicalmedical examinations and training tothe workers.

    Safety Deptt

    62. Emergency CareService andEmergencyTreatment

    The employer shall ensure that speciallife saving aids and appliances areprovided to handle the emergency

  • 7/29/2019 The Applicable Legal Requirement

    21/21

    S. No Act/Rules Regulation / Obligations Applicable area RelevantDocuments

    CurrentStatus

    Responsibility Remarks

    conditions.63. Power of

    Inspectorsthe inspector may examine theconstruction site, take photographs,video clips, samples as he mayconsider necessary for

    the purpose of any enquiry. He mayhold an enquiry into the cause of anyaccident and may file in a court having

    jurisdiction, a complaint or otheroffence.

    Client Requirements

    64. Monthly Report Monthly Report on SHE Statistics to be sent by 7

    th of every month

    Complied Safety Deptt

    65. Report ofDangerous

    Occurence

    Report of Dangerous occurrence to be sent to

    Client/Local Concern Authority within 24 hrs

    NA Safety Deptt