testing goals and notes - indico-fnal (indico)...testing goals & plans • we cannot do a full...
TRANSCRIPT
![Page 1: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/1.jpg)
Testing Goals and Notes
Sarah Lockwitz, FNAL
![Page 2: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/2.jpg)
Mini-Review Planned for July 28, 2016• Tentative Charge:
• 1. Is the proposed setup and test plan sufficient for evaluating the proposed ProtoDUNE-SP field cage design with regard to high voltage?
• 2. Are there any electrical or mechanical problems with the design of the test apparatus?
• 3. Are there any safety issues to be addressed?
• 4. Does the TSW contain the needed resources to do this?
• Tentative Schedule:
• 1. Overview and Motivation for the Test (20 min+10)
• 2. Plan for ProtoDUNE-SP HV (20+10 min) (Bo or Francesco)
• 3. Technical Review: Mechanical Specifications (Jeff) (25+15 min)
• 4. Technical Review: Electrical Specifications (Glenn) (25+15 min)
• 5. Cryogenics and plan for instrumentation (Alan with input from WM on camera)
• 6. Phase II Plans (Cheng-Ju) (20 min)
2
![Page 3: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/3.jpg)
Goals of Testing: Ensure that the ProtoDUNE design is a success
• Expose any weaknesses so that we can fix them
• Test the high voltage features of the ProtoDUNE design
• The beam plug is a challenging feature of the design
• Beam plug must be tested in the field cage
• There are enough untested features of the field cage that testing everything at once would make it difficult to determine the source of instabilities (if they arise)
• Test the field cage without the beam plug first. Characterize performance.
• Test the field cage with the beam plug to understand the beam plug performance.
3
![Page 4: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/4.jpg)
Testing Goals & Plans• We cannot do a full size test of ProtoDUNE
• We will do a partial & scaled test in 35t. (Size effects?) • Cathode at full voltage (-180 kV), 10 TPC stages at correct voltage, anode plane at -47 kV, resistor chain to ground.
• TPC has 4 parallel chains of 5.5 GΩ (11 stages x 500 MΩ. The 500 MΩ is from 2 1 GΩ resistors in parallel between each profile)
• Resistors will have surge protection. The last stage beyond the TPC is under development. • Test interfaces.
4180171162153147 171 162 153 147
• Really want to evaluate these edges. • First one is at 177 kV • To get that voltage w/o the tail of resistors, one
really gets into large tube to tube ΔVs (~20 kV)
![Page 5: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/5.jpg)
What is a successful test?
• We want the HV+TPC design to not adversely affect data-taking at ProtoDUNE
• TPC should be robust (no breakage of field cage from HV)
• We shouldn’t have instabilities that affect data-taking
• HV system should not create troublesome noise for the DAQ (filter can be tested separately)*
• System should not create light that adversely affects data-taking
• Have not found this to be an issue in a non-broken TPC
• Might want to put a PMT in the cryostat
• Should not have freq. breakdowns (relative term, aim for zero).
5
Let’s think about this…it
would be good to have an
answer by the review
![Page 6: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/6.jpg)
Rough Schedule• July:
• Complete design of field cage components including TPC circuit (resistors & varistors)
• Order long lead time materials
• Mini-Review week of July 25th
• Fabricate parts
• August:
• Remove 35t TPC
• Continue fabrication
• Test fit?
• Clean pieces
• September: Install PhaseI HV Test
• October: Purge, cool down & fill cryostat
• November: Perform Test
• December: Transfer LAr to LAPD. Warm up cryostat. Takes a little over 1 month
• January: Install Phase II
• February: Purge cooldown & fill
• March: Test Phase II
6
![Page 7: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/7.jpg)
Monitoring Ideas• Toroid: Polarity of first pulse tells you where the
voltage drop was
• Pick off/Field cage termination (required port)
• HV Supply: Heinzinger offers much better current readout ability (~100 nA vs 10s uA with a Glassman)
• Camera: M. Kordosky & group (required window(s) and/or feedthrough ports)
• PMT/SiPMs? (required ports)
• Any other ports needed?
• Not planned at the moment: Antenna, microphones
7
Blips: Toroid and FCT signals while running • Do not cause trips • Can affect data-taking (shield plane reduces this) • 35t and another experiment have seen them
• Both positive & negative polarities • Small test stand has not. Not a deal breaker at this time, but something to be aware of.
![Page 8: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/8.jpg)
Membrane Performance?
• The proposed test does not evaluate the effect of the TPC+cryostat membrane performance. This should be a low risk (40 cm away).
• The 35t was done by a Japanese company and has a different profile than what Proto-DUNE will have (GTT).
• We have some GTT profile onsite. We have some that people are willing to allow us to test.
• If there’s a strong motivation, we can test them in a small test vessel we have onsite with access to TPC-quality argon. Would only be able to test up to ~100 kV at the moment (likely < 1 inch). We would have to pay for the argon.
8
![Page 9: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/9.jpg)
A Note on Cable Terminations
• I saw Bo has requested DS 2134 cable.
• I am sure people already have ideas about cable terminations.
• If anyone would like an additional idea, we’ve used this technique for cable terminations at FNAL. Tevatron used them for decades.
• I’m willing to share parts, help with drawings, etc. if anyone wants to use this.
9
![Page 10: Testing Goals and Notes - INDICO-FNAL (Indico)...Testing Goals & Plans • We cannot do a full size test of ProtoDUNE • We will do a partial & scaled test in 35t. (Size effects?)](https://reader033.vdocuments.mx/reader033/viewer/2022051904/5ff69d872b442916970a14b9/html5/thumbnails/10.jpg)
Cleaning G10/FR4
• An option for cleaning the G10/FR4 parts is an ultrasonic bath the TD at FNAL has
• The parts in the photo are ~2.5 m in length
• On the G10, the cleaner used was Elba-Clean 65 (total cost to arrive at the lab was ~$1k)
• If there’s interest, I can ask if this is available to use at the end of the summer.
10
From T. Strauss