telescope integration and tests tuesday afternoon
TRANSCRIPT
2
Status: Document LTS-104 describes the Telescope integration and tests Plan
This coming year, this plan will be reviewed and updated:- Using vendor schedule input- Include software
development
WBS 4-14
Service Building
Coating Plant Installation
M2 Inspection
M2 coating
M2 integration in Cell
M1/M3 inspection
M1/M3 integration
in Cell
M1/M3 coating
Mount Integration
Mount Testing
M1/M3 integration in
MountM3 Tests
M2 integration on Top End
3-Mirror Telescope
Testing
Mount Science Camera
Lower Enclosure
Completion
Dome Installation
FACILITIES
MOUNT
M2 M1/M3
TELESCOPE INTEGRATION
CAMERA
Integrating Structure
Installation
SHWFS Installation
TCS(Pointing,
Mount, Alignment, Operator)
TCS(Active Optics)
OCS(Main
Controller, Sequencer, Operator)
Commission Camera Utilities
Base Facility& Fiber Network
DM Infrastructure at Base Facility
DM Network Mountain to Base
DM End-To-End Test from
Mountain to Base
Support Building
Control Room
DM NETWORK
Camera Testing in
Lab
Camera Lab Facility
Camera Inspection
Calibration telescope
Calibration Screen
commission
CALIBRATION
Facility Alignment System
M1M3 Surrogate Mirror integration
in Mount
Calibration Screen
Installation
M1M3 Cell dismounted from
the Mount
ComCam Commissioning
Final System Commissioning
DOME
COMMISSIONING
Integration sequence in phase with subsystems delivery
Integration and Test Plan (LTS-104) describes the general strategy, includes the integration and test sequence and provides a summary for all major key activities.Three Major Phases:Phase 1 (P1): Heavy ConstructionPhase 2 (P2): Mirrors Coating and IntegrationPhase 3 (P3): Alignment Phase
START
ENDP1
P2P3
Phase 1 Heavy Construction• Summit Facility construction (lower enclosure, support building, platform lift, AT lower enclosure)• Provide early access for Dome Installation (lower enclosure and pier ready) and Coating Plant
installation• Crane + Manpower to build Dome included in I&T WBS (supervisory from dome contractor). Mount
and Coating Plant Installation on site included in contract.• Dome Light/Wind Screen installation finalized after Mount installation for shutter door access
Laser Tracker used during Integration
6 months
11 months
P1
Mount Testing Milestones:•Mount Acceptance Tests•Refine positioning look-up tables•First Pointing on Sky•Refine TCS Pointing Model on sky with small alignment telescope
6 months
Total:1year 5months
Service Building
Coating Plant Installation
M2 Inspection
M2 coating
M2 integration in Cell
M1/M3 inspection
M1/M3 integration
in Cell
M1/M3 coating
Mount Integration
Mount Testing
M1/M3 integration in
MountM3 Tests
M2 integration on Top End
3-Mirror Telescope
Testing
Mount Science Camera
Lower Enclosure
Completion
Dome Installation
FACILITIES
MOUNT
M2 M1/M3
TELESCOPE INTEGRATION
CAMERA
Integrating Structure
Installation
SHWFS Installation
TCS(Pointing,
Mount, Alignment, Operator)
TCS(Active Optics)
OCS(Main
Controller, Sequencer, Operator)
Commission Camera Utilities
Base Facility& Fiber Network
DM Infrastructure at Base Facility
DM Network Mountain to Base
DM End-To-End Test from
Mountain to Base
Support Building
Control Room
DM NETWORK
Camera Testing in
Lab
Camera Lab Facility
Camera Inspection
Calibration telescope
Calibration Screen
commission
CALIBRATION
Facility Alignment System
M1M3 Surrogate Mirror integration
in Mount
Calibration Screen
Installation
M1M3 Cell dismounted from
the Mount
ComCam Commissioning
Final System Commissioning
DOME
COMMISSIONING
M1M3 Cell with Surrogate Mirror
Mount sections installed through the dome shutter doors using outside crane
1- Azimuth Track Integration 2- Azimuth Bearing Installation 3- Elevation Pier Installation
4- Center Section Integration5- Top End Ring Integration
Welded in place
Az drives installed and Tested
1st Elevation balance
6- Platform , Surrogate Mass Installation
M1M3 Cell Reception Sequence1 2
34
M1M3 Mirror Cart M1M3 Cell Reception
Cell Installed on CartM1M3 Surrogate Mirror
From Integration and Test Plan (LTS-104)
Service Building
Coating Plant Installation
M2 Inspection
M2 coating
M2 integration in Cell
M1/M3 inspection
M1/M3 integration
in Cell
M1/M3 coating
Mount Integration
Mount Testing
M1/M3 integration in
MountM3 Tests
M2 integration on Top End
3-Mirror Telescope
Testing
Mount Science Camera
Lower Enclosure
Completion
Dome Installation
FACILITIES
MOUNT
M2 M1/M3
TELESCOPE INTEGRATION
CAMERA
Integrating Structure
Installation
SHWFS Installation
TCS(Pointing,
Mount, Alignment, Operator)
TCS(Active Optics)
OCS(Main
Controller, Sequencer, Operator)
Commission Camera Utilities
Base Facility& Fiber Network
DM Infrastructure at Base Facility
DM Network Mountain to Base
DM End-To-End Test from
Mountain to Base
Support Building
Control Room
DM NETWORK
Camera Testing in
Lab
Camera Lab Facility
Camera Inspection
Calibration telescope
Calibration Screen
commission
CALIBRATION
Facility Alignment System
M1M3 Surrogate Mirror integration
in Mount
Calibration Screen
Installation
M1M3 Cell dismounted from
the Mount
ComCam Commissioning
Final System Commissioning
DOME
COMMISSIONING
Phase 2 Starts after end of heavy construction for safe handling of mirrors
• M2 Coating during Mount Testing (overlap with Phase 1)• M2 is first installed on Telescope Mount• M1M3 Mirror Reception and Integration in cell• M1M3 coating and assembly (Mount locked at Zenith)• Calibration Screen installed on Dome during M1M3 coating• M1M3 integration on Telescope
P2
3 months
2 months1 month
1 month3 months
2 months
Total:10 months
M1M3 Cell and M1M3 Mirror Assembly
1 2
34
M1M3 Lifter StagingM1M3 Mirror Reception
M1M3 Container Open
M1M3 Mirror Installation in Cell
M1M3 Cell PreparationM1M3 Cell under coating chamber
Phase 3 starts with M3 tests for 3-Mirror Telescope testing
• Repeat M3 Mirror System performance tests under full active control at zenith pointing (with interferometer)
• Install Integrating Structure with wavefront sensor (WFS)
• On-axis 3-Mirror Telescope Alignment (take advantage of diffraction-limited image on-axis by design)
• Perform Calibration Equipment Tests
P3
Total: 8 months
M3 Interferometer
Service Building
Coating Plant Installation
M2 Inspection
M2 coating
M2 integration in Cell
M1/M3 inspection
M1/M3 integration
in Cell
M1/M3 coating
Mount Integration
Mount Testing
M1/M3 integration in
MountM3 Tests
M2 integration on Top End
3-Mirror Telescope
Testing
Mount Science Camera
Lower Enclosure
Completion
Dome Installation
FACILITIES
MOUNT
M2 M1/M3
TELESCOPE INTEGRATION
CAMERA
Integrating Structure
Installation
SHWFS Installation
TCS(Pointing,
Mount, Alignment, Operator)
TCS(Active Optics)
OCS(Main
Controller, Sequencer, Operator)
Commission Camera Utilities
Base Facility& Fiber Network
DM Infrastructure at Base Facility
DM Network Mountain to Base
DM End-To-End Test from
Mountain to Base
Support Building
Control Room
DM NETWORK
Camera Testing in
Lab
Camera Lab Facility
Camera Inspection
Calibration telescope
Calibration Screen
commission
CALIBRATION
Facility Alignment System
M1M3 Surrogate Mirror integration
in Mount
Calibration Screen
Installation
M1M3 Cell dismounted from
the Mount
ComCam Commissioning
Final System Commissioning
DOME
COMMISSIONING
Shack-Hartmann WFS
Commissioning camera (ComCam) for initial off-axis alignment
1. 3-Lenses FOV Corrector (2 lenses + dewar window)
2. 40-arcmin Focal Plane Composed of one CCD raft (3x3 CCD Detectors)
3. Intra and Extra focal images used for Wavefront Analysis (on and off-axis)
FiltersWindow
374 mm
309 mm
Rotator
Hexapod
Camera Support Assembly with ComCam ComCam installed on Surrogate Mass
Integration Milestones with Dependence on Main Subsystems Delivery
Dependent on following milestones:1. Dome Ready for Installation 03 Jan 172. TMA Ready for Installation 12 Jul 173. Support Facility ready for Coating Chamber 06 Oct 174. M1M3 arrives on site 24 Jan 185. M2 arrives on site 10 Apr 18
1. Dome Installation Finished (Ph1) 19 Jun 172. Telescope Mount Installation Finished (Ph1) 03 Jan 183. Coating Chamber ready for use (Ph1) 18 May 184. Telescope Mount Testing Finished (Ph1) 11 Jun 185. Major Exterior Handling Operations Complete (Ph1) 14 Dec 186. Telescope ready for 3-mirror testing (Ph2) 25 Jan 197. T&S ATP Complete (Ph3) 30
Sept 19