Telescope Integration and Tests

Tuesday Afternoon

2

Status: Document LTS-104 describes the Telescope integration and tests Plan

This coming year, this plan will be reviewed and updated:- Using vendor schedule input- Include software

development

WBS 4-14

Service Building

Coating Plant Installation

M2 Inspection

M2 coating

M2 integration in Cell

M1/M3 inspection

M1/M3 integration

in Cell

M1/M3 coating

Mount Integration

Mount Testing

M1/M3 integration in

MountM3 Tests

M2 integration on Top End

3-Mirror Telescope

Testing

Mount Science Camera

Lower Enclosure

Completion

Dome Installation

FACILITIES

MOUNT

M2 M1/M3

TELESCOPE INTEGRATION

CAMERA

Integrating Structure

Installation

SHWFS Installation

TCS(Pointing,

Mount, Alignment, Operator)

TCS(Active Optics)

OCS(Main

Controller, Sequencer, Operator)

Commission Camera Utilities

Base Facility& Fiber Network

DM Infrastructure at Base Facility

DM Network Mountain to Base

DM End-To-End Test from

Mountain to Base

Support Building

Control Room

DM NETWORK

Camera Testing in

Lab

Camera Lab Facility

Camera Inspection

Calibration telescope

Calibration Screen

commission

CALIBRATION

Facility Alignment System

M1M3 Surrogate Mirror integration

in Mount

Calibration Screen

Installation

M1M3 Cell dismounted from

the Mount

ComCam Commissioning

Final System Commissioning

DOME

COMMISSIONING

Integration sequence in phase with subsystems delivery

Integration and Test Plan (LTS-104) describes the general strategy, includes the integration and test sequence and provides a summary for all major key activities.Three Major Phases:Phase 1 (P1): Heavy ConstructionPhase 2 (P2): Mirrors Coating and IntegrationPhase 3 (P3): Alignment Phase

START

ENDP1

P2P3

Phase 1 Heavy Construction• Summit Facility construction (lower enclosure, support building, platform lift, AT lower enclosure)• Provide early access for Dome Installation (lower enclosure and pier ready) and Coating Plant

installation• Crane + Manpower to build Dome included in I&T WBS (supervisory from dome contractor). Mount

and Coating Plant Installation on site included in contract.• Dome Light/Wind Screen installation finalized after Mount installation for shutter door access

Laser Tracker used during Integration

6 months

11 months

P1

Mount Testing Milestones:•Mount Acceptance Tests•Refine positioning look-up tables•First Pointing on Sky•Refine TCS Pointing Model on sky with small alignment telescope

6 months

Total:1year 5months

Service Building

Coating Plant Installation

M2 Inspection

M2 coating

M2 integration in Cell

M1/M3 inspection

M1/M3 integration

in Cell

M1/M3 coating

Mount Integration

Mount Testing

M1/M3 integration in

MountM3 Tests

M2 integration on Top End

3-Mirror Telescope

Testing

Mount Science Camera

Lower Enclosure

Completion

Dome Installation

FACILITIES

MOUNT

M2 M1/M3

TELESCOPE INTEGRATION

CAMERA

Integrating Structure

Installation

SHWFS Installation

TCS(Pointing,

Mount, Alignment, Operator)

TCS(Active Optics)

OCS(Main

Controller, Sequencer, Operator)

Commission Camera Utilities

Base Facility& Fiber Network

DM Infrastructure at Base Facility

DM Network Mountain to Base

DM End-To-End Test from

Mountain to Base

Support Building

Control Room

DM NETWORK

Camera Testing in

Lab

Camera Lab Facility

Camera Inspection

Calibration telescope

Calibration Screen

commission

CALIBRATION

Facility Alignment System

M1M3 Surrogate Mirror integration

in Mount

Calibration Screen

Installation

M1M3 Cell dismounted from

the Mount

ComCam Commissioning

Final System Commissioning

DOME

COMMISSIONING

M1M3 Cell with Surrogate Mirror

Mount sections installed through the dome shutter doors using outside crane

1- Azimuth Track Integration 2- Azimuth Bearing Installation 3- Elevation Pier Installation

4- Center Section Integration5- Top End Ring Integration

Welded in place

Az drives installed and Tested

1st Elevation balance

6- Platform , Surrogate Mass Installation

M1M3 Cell Reception Sequence1 2

34

M1M3 Mirror Cart M1M3 Cell Reception

Cell Installed on CartM1M3 Surrogate Mirror

From Integration and Test Plan (LTS-104)

Service Building

Coating Plant Installation

M2 Inspection

M2 coating

M2 integration in Cell

M1/M3 inspection

M1/M3 integration

in Cell

M1/M3 coating

Mount Integration

Mount Testing

M1/M3 integration in

MountM3 Tests

M2 integration on Top End

3-Mirror Telescope

Testing

Mount Science Camera

Lower Enclosure

Completion

Dome Installation

FACILITIES

MOUNT

M2 M1/M3

TELESCOPE INTEGRATION

CAMERA

Integrating Structure

Installation

SHWFS Installation

TCS(Pointing,

Mount, Alignment, Operator)

TCS(Active Optics)

OCS(Main

Controller, Sequencer, Operator)

Commission Camera Utilities

Base Facility& Fiber Network

DM Infrastructure at Base Facility

DM Network Mountain to Base

DM End-To-End Test from

Mountain to Base

Support Building

Control Room

DM NETWORK

Camera Testing in

Lab

Camera Lab Facility

Camera Inspection

Calibration telescope

Calibration Screen

commission

CALIBRATION

Facility Alignment System

M1M3 Surrogate Mirror integration

in Mount

Calibration Screen

Installation

M1M3 Cell dismounted from

the Mount

ComCam Commissioning

Final System Commissioning

DOME

COMMISSIONING

Phase 2 Starts after end of heavy construction for safe handling of mirrors

• M2 Coating during Mount Testing (overlap with Phase 1)• M2 is first installed on Telescope Mount• M1M3 Mirror Reception and Integration in cell• M1M3 coating and assembly (Mount locked at Zenith)• Calibration Screen installed on Dome during M1M3 coating• M1M3 integration on Telescope

P2

3 months

2 months1 month

1 month3 months

2 months

Total:10 months

M1M3 Cell and M1M3 Mirror Assembly

1 2

34

M1M3 Lifter StagingM1M3 Mirror Reception

M1M3 Container Open

M1M3 Mirror Installation in Cell

M1M3 Cell PreparationM1M3 Cell under coating chamber

Phase 3 starts with M3 tests for 3-Mirror Telescope testing

• Repeat M3 Mirror System performance tests under full active control at zenith pointing (with interferometer)

• Install Integrating Structure with wavefront sensor (WFS)

• On-axis 3-Mirror Telescope Alignment (take advantage of diffraction-limited image on-axis by design)

• Perform Calibration Equipment Tests

P3

Total: 8 months

M3 Interferometer

Service Building

Coating Plant Installation

M2 Inspection

M2 coating

M2 integration in Cell

M1/M3 inspection

M1/M3 integration

in Cell

M1/M3 coating

Mount Integration

Mount Testing

M1/M3 integration in

MountM3 Tests

M2 integration on Top End

3-Mirror Telescope

Testing

Mount Science Camera

Lower Enclosure

Completion

Dome Installation

FACILITIES

MOUNT

M2 M1/M3

TELESCOPE INTEGRATION

CAMERA

Integrating Structure

Installation

SHWFS Installation

TCS(Pointing,

Mount, Alignment, Operator)

TCS(Active Optics)

OCS(Main

Controller, Sequencer, Operator)

Commission Camera Utilities

Base Facility& Fiber Network

DM Infrastructure at Base Facility

DM Network Mountain to Base

DM End-To-End Test from

Mountain to Base

Support Building

Control Room

DM NETWORK

Camera Testing in

Lab

Camera Lab Facility

Camera Inspection

Calibration telescope

Calibration Screen

commission

CALIBRATION

Facility Alignment System

M1M3 Surrogate Mirror integration

in Mount

Calibration Screen

Installation

M1M3 Cell dismounted from

the Mount

ComCam Commissioning

Final System Commissioning

DOME

COMMISSIONING

Shack-Hartmann WFS

Commissioning camera (ComCam) for initial off-axis alignment

1. 3-Lenses FOV Corrector (2 lenses + dewar window)

2. 40-arcmin Focal Plane Composed of one CCD raft (3x3 CCD Detectors)

3. Intra and Extra focal images used for Wavefront Analysis (on and off-axis)

FiltersWindow

374 mm

309 mm

Rotator

Hexapod

Camera Support Assembly with ComCam ComCam installed on Surrogate Mass

Integration Milestones with Dependence on Main Subsystems Delivery

Dependent on following milestones:1. Dome Ready for Installation 03 Jan 172. TMA Ready for Installation 12 Jul 173. Support Facility ready for Coating Chamber 06 Oct 174. M1M3 arrives on site 24 Jan 185. M2 arrives on site 10 Apr 18

1. Dome Installation Finished (Ph1) 19 Jun 172. Telescope Mount Installation Finished (Ph1) 03 Jan 183. Coating Chamber ready for use (Ph1) 18 May 184. Telescope Mount Testing Finished (Ph1) 11 Jun 185. Major Exterior Handling Operations Complete (Ph1) 14 Dec 186. Telescope ready for 3-mirror testing (Ph2) 25 Jan 197. T&S ATP Complete (Ph3) 30

Sept 19

FDR Schedule in Primavera

Team

Equipment

Activities

Y3 Y4 Y5 Y6

Rental