technical specification for mechanical integration of

12
Technical specification for mechanical integration of chiller loop and skid for sCO2 rig components I. Scope of work The tender broadly includes the following: 1. Fabrication and supply of a portable skid for mounting the components ofthe CO2 loop in accordance with ASME B 31 standards. 2. The complete mechanical integration of the chiller system with the CO2loop in accordance with ASME 31.3 standards II. Technical specifications This document provides the technical specification required for successful integration of the components present in the chiller loop, the CO2 cylinder of the sCO2 loop and skid for sCO2 pump, precooler, condenser& pressure vessel. Below tables provide the detail requirements of this tender which need to be quoted/provided by the bidders/vendors. Sr. No. Spec Remark 1 All the hardware to be procured/fabricated by vendor should be capable of sustaining high pressure of 3100 psi and operating temperature of min -10 0 C and max of 50 0 C 2 All the components should meet the ASME standard for design, material, assembly, operation and integration, specifically piping (including pipe bends), valves, fittings, joints, etc. should meet ASME B31 standard 3 All the integration hardware when assembled with the rig components should provide leak-proof working and vendor should demonstrate the leak test as per ASME 31.3 4 The skid should be capable of taking 2 times the weight of all the components and the transient loading due to operation 5 The skid should be designed to withstand the vibrations coming from rotating component (sCO2 pump) without failure for continuousdaylong operation of the plant 6 The skid should be portable and should have leveling casters with required locking mechanism so that it should not vibrate or move during the operation 7 Skid should have sufficient extra space (minimum of 300 mm) between all the components to provide accessibility for connection, inspection and repair

Upload: others

Post on 25-May-2022

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Technical specification for mechanical integration of

Technical specification for mechanical integration of chiller loop and skid

for sCO2 rig components

I. Scope of work

The tender broadly includes the following:

1. Fabrication and supply of a portable skid for mounting the components of the CO2 loop in

accordance with ASME B 31 standards.

2. The complete mechanical integration of the chiller system with the CO2 loop in accordance with

ASME 31.3 standards

II. Technical specifications

This document provides the technical specification required for successful integration of the

components present in the chiller loop, the CO2 cylinder of the sCO2 loop and skid for sCO2 pump,

precooler, condenser& pressure vessel. Below tables provide the detail requirements of this tender

which need to be quoted/provided by the bidders/vendors.

Sr. No. Spec Remark

1

All the hardware to be procured/fabricated by vendor should be

capable of sustaining high pressure of 3100 psi and operating

temperature of min -100 C and max of 50

0 C

2

All the components should meet the ASME standard for design,

material, assembly, operation and integration, specifically piping

(including pipe bends), valves, fittings, joints, etc. should meet ASME B31 standard

3

All the integration hardware when assembled with the rig components

should provide leak-proof working and vendor should demonstrate the leak test as per ASME 31.3

4 The skid should be capable of taking 2 times the weight of all the

components and the transient loading due to operation

5

The skid should be designed to withstand the vibrations coming from

rotating component (sCO2 pump) without failure for continuous daylong

operation of the plant

6

The skid should be portable and should have leveling casters with

required locking mechanism so that it should not vibrate or move during the operation

7

Skid should have sufficient extra space (minimum of 300 mm) between

all the components to provide accessibility for connection, inspection and repair

Page 2: Technical specification for mechanical integration of

8

Skid should have space to put test coupon of 600 mm by 600 mm and

other accessories like sensors, back pressure relief valves, electrical circuits, etc. Refer to the CO2 loop schematic

9

The skid is expected to have slotted holes to assemble the components

tightly. And it should have necessary connections/connectors/hooks for

packaging, transportation and lifting to avoid damage to components and to the skid itself

10 The skid components should be painted to have corrosion resistance properties

11

All the components should be tested before integration. Perform

calibration & provide test certificate for thermal sensors. Comply with

ASME B31 standard wherever applicable

12 Vendor should demonstrate the working of all the components by

working electrical connection through DAQ and control panel

13

Vendor is also expected to demonstrate emergency shutdown of the

circuit and its effect on the mechanical integration components and skid

14 All the components should at least have 1 year warranty

15 All the components (wherever possible) should be made of Stainless Steel only

16 Vendor shall have the manufacturing facility (steel cutting, welding,

testing etc) required for the execution of the project. (Proof of having

the manufacturing facility to be attached)

17

Vendor must have experience and must provide the proof of executing

super critical CO2 system with the operating pressure of 3100 psi and

operating temperature of min -100 C and max of 50

0 C

18 All the components should be well insulated to avoid any heat transfer

between the system and the surrounding.

III. Material/components Provided by IITM:

SR. No. Items Quantity

1 Precooler 1

2 Condensor 1

3 Chiller 1

4 CO2 cylinder 2

5 sCO2 pump with motor 1

6 Test coupon 1

7 Pressure vessel 1

Technical Specifications for materials supplied by IIT Madras

Page 3: Technical specification for mechanical integration of

1. Precooler: Heat Exchanger of 10KW

The heat exchanger unit should be capable of handling the hot fluid of the pressure up to 200 bar and at a

maximum flow rate of 0.1 kg/s and at a maximum inlet temperature of 100o C. The heat exchanger

is expected to behave like an unit to cool of super critical CO2. The heat exchanger shall accept water /

Refrigerant / MEG as one of the cold fluids. The cold fluid operating pressure shall not exceed 4 bar and

maximum operating temperature of 400 C. The heat exchanger unit can be made of SS316L meeting

ASME standards of 200 bar pressure application on the side while 4 bar maximum pressure on the cold

side. The unit can be diffusion bonded multiple channel type compact heat exchanger type specially built

for super critical CO2 application purpose. The Unit shall be specifically meant for handling gaseous CO2 or

liquid CO2 or super critical CO2 as hot fluid. The cold and hot fluid ports must meet standard BSP flange

connections to be able connect a 1-inch pipeline in the layout. The heat exchanger is expected to have an

outer insulation to minimize the ambient temperature effects in the closed operation. The construction of

the HX should comply the ASME design code for meeting the maximum operating pressure and

temperature requirements. The units should have been pretested for any leak using the standard water

leak test procedures.

Thermal requirements

Parameter Hot Side Cold Side

Heat load 10 KW @

max flow

10 KW @

max flow

Inlet Temperature ( C ) 100 10

Outlet Temperature ( C ) 50 46.8

Design Temperature Max 2000C 50

0 C

Flow Requirements

Parameter Hot Side Cold Side

Pressure Drop < 0.5 bar < 0.5

Inlet Pressure 200 bar Max 4 bar Max

Inlet Flow (kg/s) 0.2 0.5

Mechanical requirements

Parameter Hot Side Cold Side

Material (Nozzle, Flange, Header &

Pipe)

SS316L SS316L

Welding No No

Bonding Diffusion Diffusion

Inlet Flange Size

Requirement

To connect to a 1- inch SS

pipeline

To connect to a 1-inch SS pipeline

Outlet Flange Size

Requirement

To connect to a 1- inch SS

pipeline

To connect to a 1-inch SS pipeline

Additional Requirements

Parameter

Insulation Yes for outside surface of the HX

Inbuilt Strainer for

both fluids Yes

Fouling Allowance Not needed

Page 4: Technical specification for mechanical integration of

Fluid

Properties for Sizing

the HX

Use Refprop of NIST database (https://www.nist.gov/srd/refprop)

2. Cooling Heat Exchanger of 10 KW Rated / Condenser

The heat exchanger unit should be capable of handling the hot fluid of the pressure up to 200 bar and at a

maximum flow rate of 0.1 kg/s and at a maximum inlet temperature of 40o C.The heat exchanger is

expected to behave like a condenser unit to cool of liquid/gaseous CO2 so that it turns in to complete

liquid state before being pressurized to super critical state. The working hot fluid is CO2from the standard

gas bottle. The heat exchanger shall accept MEG as one of the cold fluids. The cold fluid operating

pressure shall not exceed 4 bar and maximum operating temperature of 400 C. The heat exchanger unit

can be made of SS316L meeting ASME standards of 200 bar pressure application on the side while 4 bar

maximum pressure on the cold side. The unit can be diffusion bonded multiple channel type compact

heat exchanger type specially built for super critical CO2 application purpose. The Unit shall be

specifically meant for handling gaseous CO2 or liquid CO2 or super critical CO2 as hot fluid. The cold and

hot fluid ports must meet standard BSP flange connections to be able connect a 1-inchpipeline in the

layout. The heat exchanger is expected to have an outer insulation to minimize the ambient temperature

effects in the closed operation. The construction of the HX should comply the ASME design code for

meeting the maximum operating pressure and temperature requirements. The units should have been

pretested for any leak using the standard water leak test procedures.

Thermal requirements

Parameter Hot Side Cold Side

Heat load ~10 KW @

max flow

~10 KW @ max

flow

Inlet Temperature ( C ) 40 5

Outlet Temperature ( C ) <10 xx

Design TemperatureMax 2000C 50

0 C

Flow Requirements

Parameter Hot Side Cold Side

Pressure Drop < 0.25 bar < 0.3

Inlet Pressure 200 bar Max 4 bar Max

Inlet Flow (kg/s) 0.33 0.5

Mechanical Requirements

Mecha Parameter Hot Side Cold Side

Material (Nozzle, Flange, Header &

Pipe)

SS316L SS316L

Welding No No

Bonding Diffusion Diffusion

Inlet Flange Size

Requirement

To connect to a 1- inch SS

pipeline

To connect to a 1-inch SS

pipeline

Outlet Flange Size

Requirement

To connect to a 1- inch SS

pipeline

To connect to a 1-inch SS

pipeline

Additional Requirements

Parameter

Page 5: Technical specification for mechanical integration of

Insulation Yes for outside surface of the HX

Inbuilt

Strainer for

both fluids

Yes

Fouling Allowance Not needed

Fluid Properties for

Sizing the HX

Use Refprop of NIST database (https://www.nist.gov/srd/refprop)

3. Chiller Unit of 20KW

The chiller unit shall be expected to provide coolant at a minimum temperature of -100 C and to a

maximum temperature of 400 C. The Chiller should be a closed loop integrated system that works

automatically on a digitally controlled set point temperature at a required mass flow of the coolant.

The chiller unit is expected to have easily accessible digital panel to control the flow and temperature

requirement. There should be additional options to be able control the unit operation through a PC as

well. The coolant ports should meet up with BSP piping standards. The chiller unit shall be a quiet unit

adhering to the sound level up to 60 DBA. The unit shall be expected to have zero leakage of the coolant

and if happens should have an automatic tripping system.

Operational Specifications

S.No. Description

1. Cooling Capacity at a minimum coolant temperature 20 KW

2. Minimum Temperature -10oC

3. Maximum Temperature 400 C

4. Coolant Flow 0 to 40 GPM at a pressure of 4 bar

5. Temperature Stability Within + 0.10 C

6. Control Automatic

7. Condenser Type Air or Water Cooled

8. Coolant Type MEG

9. Nominal Coolant Connection Ports Inlet 1 inch BSP standard connection port

10. Nominal Coolant Connection Ports Outlet 1 inch BSP standard connection port

11. Automatic Tripping Yes

12. Control System Integrated with digital display

13. Communication RS232/RS485

14. Operation Mode Through PC as well as on the Panel

15. Coolant Refilling Automatic

16. Tripping system Automatic tripping for coolant leakage

Electrical Specifications

S.No. Description

1. Voltage 3 Phase – 220- 240 V

2. Power Up to 20 KW

3. Current 10 - 15 A

4. Frequency 50-60 Hz

Page 6: Technical specification for mechanical integration of

4. CO2 cylinder

CO2 Gas (HSN CODE – 2811 2190) – 2.0 Grade in 47ltr W.C

Carbon Steel cylinder confirms to IS 7285 fitted with RH threaded Valve confirms to IS 3224. Filling

pressure – 60 kg/cm2

Gas capacity – 31 kg, Gas Purity – 99%

5. High Pressure sCO2 Pump with motor

The pump is expected to deliver super critical CO2 at a pressure of 200 bar with no pulsation in the flow.

The expected maximum mass flow outlet from the pump is 0.05 kg/s at a maximum discharge pressure of

200 bar. The pump should have the in-built cooling system to protect from overheating issues. The pump

needs to have full protections against burst protection with appropriate burst protection disc and

pressure regulating valves. The motor associated with the pump needs to be electrically driven with the

capacity of up to 30 KW rating. The electrical motor shall have a small fan to electrically cool it.

The pump should have noise levels less than 60 DB, if exceeds, the system needs to have an appropriate

noise protection cabinet. The pump shall have required protection for handling back pressures and

Cavitation. The inlet and exit ports of the pump shall meet the standard BSP norms. The pump shall be

quoted along with the back-pressure regulator to regulate the feed pressure to the pump.The pump shall

be associated with adequate control systems to be built as auxiliary units and shall be quoted along with

the quotation. The expectation is to deliver the flow at a given set point flow and discharge pressure

without any flow fluctuations using Feedback loop control system that uses PID controller along with the

Coriolis flow meter. The motor VFD unit should be coupled with the PID controller as well to control the

flow appropriately. The motor shall be controlled from the location outside the lab through a personal

computer. Hence the final system shall encompass required software interface to be used from a lab PC.

Detailed technical specifications for the requirements are listed below.

Operational Specifications

Description

Mass flow 0 – 0.05 kg/s or 0 to 180 kg/h

Discharge Pressure Max 200 bar

Discharge Temp (C) 70 degree C

Power Rating 30 KW

Operating Mode Set Pressure and Mass Flow Control Modes

Control System Yes. Include accessories for a fully automated PID control system to achieve steady mass

flow at a set pressure

Pump Cooling In built lubricant cooling system

Electrical Motor 30 KW

Electrical Motor Cooling Fan 2 HP blower fan for cooling the

motor

Inlet Pressure Up to 60 bar

Communication RS232/RS485

Mode of Operation Continuous & Closed Loop System

Page 7: Technical specification for mechanical integration of

VFD Suitable for CO2 pump at the specified power rating of 30

KW

Fluid Condition at the Pump Inlet Liquid CO2 at 100 C and 50 to 60 bar pressure

Back Pressure Regulation Valve Rated up to 400 bar

Pump Base Frame Made of Mild Steel

Motor to Pump Shaft Coupling Yes

Burst Protection Disc (Explosion protection) Yes

Pulsation Damper Yes

Controller (Mass flow and Discharge pressure based set point)

PID controller unit for feed

back from the flow meter to the VFD of the motor

Software Interface Software to be installed in the PC to control the pump

Back pressure regulator One unit at the inlet of the pump to regulate the back

pressure with range of 300 bar

Electrical Specifications

Description

Voltage 3 Phase – 220- 240 V

Power Up to 30 KW

Current 10 - 15 A

Frequency 50 – 60 Hz

6. Test coupon

As per the size provide in the tender specifications sheet.

7. Pressure vessel

The pressure vessel is expected to store liquid CO2 at a maximum pressure of 100 bar and at a minimum

temperature of 50 C. The purpose of this vessel is expected to act a phase separator to be able to supply

liquid CO2 to the downstream pump. it can expect a maximum withdrawal liquid flowrate of 0.05kg/s

while there might be a 30% volume fraction of uncondensed vapour of CO2 might exist in the feed line.

The unit is intended to supply only liquid CO2 to the downstream high pressure pump while the input to

the unit is coming from a condenser. The output line shall be from the bottom of the vessel. The unit

is expected to have a rupture disc for burst protection and a self-regulating valve for maintaining the

pressure within 100bar. It should have the provision for venting CO2 out during the restart operation for

depressurizing the system. The unit shall have digital level sensor whose output should be monitored

through the system. The vessel should also have the pressure and temperature sensors embedded in it

whose output also must be data logged. The vessel should have proper insulation to minimize the losses

to ambient. The maximum ambient temperature expected is 420 C. The make shall be of SS316L material

complying with ASME codes of standard pressure vessel manufacturing.

System Operational specifications

Parameter

Pressure 100 bar

Temperature Min of5 deg C

Equipment Make SS316 L

Page 8: Technical specification for mechanical integration of

Pressure Sensor In-built range 150 bar

Pressure Safety Valve 100 bar capacity

Temperature RTD + 0.1 deg C accuracy

Liquid Level Digital with RS232/485 connection

Self- Regulating Valve Made of SS316Lbody for maximum of 300 bar pressure

Vapour volume Maximum 30% of

volume

the liquid

Total Vessel

Capacity

To be designed as

separator by Vendor

a phase

Inlet line Feed 1” inch BSP (above

level)

the liquid

Output Line 1” inch BSP (from the bottom)

Drain Line 1” inch BSP

Insulation Outer walls to be covered to

maintain temperature 5 deg C

Sight Glass No

Wall Thickness Meeting ASME codes

Liquid Residence Time 15 mins

Withdrawal liquid

rate

0.05 kg/s

Fluid Properties Use Refprop of NIST database

(https://www.nist.gov/srd/refprop)

Electrical Requirement

Voltage 220 to 240 V

Current 15 amps / 3 Phase supply

IV. Material/components to be procured by fabricator/vendor:

SR. No. Items Quantity

1 Manual needle type valve for CO2 cylinder discharge (50-70 bar) 1

2 Pneumatic operated on-off automated valve (fail-open type) 1

3 Manual needle type Valves 2

4 Thermocouple temparature sensor (RTD temperature range-100 C to50

0 C) 4

5 3/8'' tube 20m

6 Male connecter 3/8'' for HX 4

7 Tee connector 3/8" 4

8 3/8'' union 20

9 3/8'' Nut and ferrule 15

10

Skid for Pump (minimum size: LXBXH (height from ground) : 2000 mm X 900 mm X 200 mm)

1 unit

Page 9: Technical specification for mechanical integration of

11

Noise Arrester for Pump to restrict noise level to less than 60 dbs

(perforated acoustic cover; galvanized sheet metal with adequate foam

packing; minimum size: 2100 mm (L) x 1000 mm (B) x 700 mm (H)

1 unit

12

Skid for assembling pressure vessel, condenser and precooler (minimum size: 2000 mm (L) x 2400 mm (B) x 1000 mm (height from ground)

1 unit

V. Mechanical Integration Schematic:

1. sCO2 test loop with only key components:

2. Chiller Loop:

1. Chiller Circuit(MEG fluid)

a. 21-24 line

i. Pipe connecting chiller exit to condenser inlet

ii. Pipe connecting condenser exit to chiller inlet

iii. Both the pipes require a temperature sensor (T5&T6)each.

b. 21-18 line

i. Pipe connecting chiller to pre-cooler inlet with temp sensor (T7) in b/w

ii. Pipe connecting precooler exit to chiller with temp sensor (T5) in b/w

Use engineering judgments and calculations whenever required such that the components withstand

the operating condition of 3100 psi pressure and temperature of min -100 C and max of 50

0 C.

Page 10: Technical specification for mechanical integration of

VI. Training:

Vendor shall demonstrate to the IIT M staff the operation of the complete system via a

working DAQ and control system. The vendor shall also provide a complete operating manual

outlining the steps in operation and procedures for emergency shutdown.

For technical clarifications, contact

Dr. Anandu Surendran

Mob: 7550160214

[email protected]

Technical compliance sheet Vendors are required to submit their bids along with this duly filled technical compliance sheet

Sr.No. Specification/requirements Complied/Not Complied

Catalogue Page No /reference

Remarks (if any)

1

All the hardware to be procured/fabricated by vendor should be capable of sustaining high pressure of 3100psi and operating temperature of min-10

0C and max of 50

0C

2

All the components should meet the ASME

standard for design, material, assembly,

operation and integration, specifically

piping(including pipe bends), valves, fittings,

joints, etc. should meet ASMEB31 standard

3

All the integration hardware when assembled

with the rig components should provide leak-

proof working and vendor should demonstrate

the leak test as per ASME31.3

4 The skid should be capable of taking 2 times the

weight of all the components and the transient

loading due to operation

5

The skid should be designed to withstand the vibrations coming from

Rotating component(sCO2pump)without failure

for continuous day long operation of the plant

6

The skid should be portable and should have

leveling casters with required locking mechanism

so that it should not vibrate or move during the

operation

Page 11: Technical specification for mechanical integration of

7

Skid should have sufficient extra space (minimum

of 300mm) between all the components to

provide accessibility for connection, inspection And repair

8

Skid should haves pace to put test coupon of

600mm by 600mm and other accessories like

sensors, back pressure relief valves, electrical circuits, etc. Refer to the CO2 loop schematic

9

The skid is expected to have slotted holes to

assemble the components tightly. And it should

have necessary connections/connectors/hooks for

packaging, transportation and lifting to avoid

damage to Components and to the skid itself

10 The skid components should be painted to have corrosion resistance properties

11

All the components should be tested before integration. Perform

Calibration & provide test certificate for thermal

sensors. Comply with ASMEB31 standard

wherever applicable

12 Vendor should demonstrate the working of all the

components by working electrical connection

through DAQ and control panel

13

Vendor is also expected to demonstrate emergency shutdown of the

Circuit and its effect on the mechanical

integration of components and skid

14 All the components should at least have 1 year warranty

15 All the components(wherever possible) should be made of Stainless Steel only

16 Vendor shall have the manufacturing facility (steel

cutting, welding, testing etc)required for the

execution of the project. (Proof of having the

manufacturing facility to be attached)

17

Vendor must have experience and must provide the proof of executing

Supercritical CO2 system with the operating

pressure of 3100 psi and operating temperature

of min-100C and maxof50

0C

Page 12: Technical specification for mechanical integration of

18 All the components should be well insulated to

avoid any heat transfer between the system and

the surrounding.