technical requirements.pdf

Upload: sorry2qaz

Post on 14-Apr-2018

235 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    1/49

    Part E (Technical Requirements) Page - 1

    PART E

    ___________________

    TECHNICAL REQUIREMENTS

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    2/49

    Part E (Technical Requirements) Page - 2

    Table of Contents

    1 EXECUTIVE SUMMARY ................................................................................................................................................................4

    2 SCOPE OF WORK S..........................................................................................................................................................................42.1 DESIGN SCOPE OF WORKS............................................................................................................4

    2.1.1 General Design Requirements..................................................................................................52.1.2 Architectural / Civil / Structural Design...................................................................................62.1.3 Electrical Design.......................................................................................................................8

    2.2 DESIGN MATTERS .......................................................................................................................112.2.1 Engineering Design Management Procedures........................................................................11

    2.3 TECHNICAL REVIEW...................................................................................................................132.3.1 Detail Design Review..............................................................................................................13

    2.4 DELIVERABLES............................................................................................................................132.4.1 Detailed Design.......................................................................................................................13

    2.5 SCOPE OF CONSTRUCTION WORKS............................................................................................16

    2.5.1 Extent of Work.........................................................................................................................162.5.2 Application of Standards.........................................................................................................182.5.3 Project Plan............................................................................................................................182.5.4 Access to Site...........................................................................................................................182.5.5 Site Compound........................................................................................................................182.5.6 Temporary Demarcation Fence..............................................................................................192.5.7 RailCorps Access to its facilities...........................................................................................192.5.8 Working Hours........................................................................................................................192.5.9 Works Programme and Staging..............................................................................................192.5.10 Subsurface Conditions........................................................................................................202.5.11 Protection of Existing Infrastructure..................................................................................202.5.12 Coordination of Works with Others ...................................................................................202.5.13 Railway Worksite Protection..............................................................................................20

    2.5.14 Setting out the Works..........................................................................................................202.5.15 Services Search..................................................................................................................202.5.16 Occupational Health & Safety...........................................................................................212.5.17 Protection of the Environment...........................................................................................212.5.18 Signage...............................................................................................................................222.5.19 Hot Work Authority............................................................................................................222.5.20 Electrical Permits...............................................................................................................222.5.21 Documentation and As-Built Drawings..............................................................................222.5.22 Quality Standards...............................................................................................................222.5.23 Concrete Works..................................................................................................................222.5.24 Drainage Works.................................................................................................................232.5.25 66kV Structures..................................................................................................................232.5.26 High Voltage Electrical Work............................................................................................23

    2.5.27 Low Voltage Electrical Work.............................................................................................242.5.28 RailCorp Standards and Specifications..............................................................................262.5.29 Civil ....................................................................................................................................262.5.30 Electrical : High and Low Voltage.....................................................................................262.5.31 Detailed Site Survey (DSS) Procedures.............................................................................26

    3 QUALITY REQUIREMENTS........................................................................................................................................................273.1 DESIGN STANDARDS....................................................................................................................273.2 SELECTION AND USE OF AUSTRAL IAN AND INTERNATIONAL STANDARDS...............................273.3 RAILCORP STANDARDS ..............................................................................................................273.4 STANDARD OF COMPLETED DESIGN...........................................................................................28

    3.4.1 Design Verification.................................................................................................................283.4.2 Technical Reviews...................................................................................................................293.4.3 Reference Standards...............................................................................................................31

    3.4.4 Access to RailCorp Standards.................................................................................................323.4.5 Access to RailCorp drawings..................................................................................................32

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    3/49

    Part E (Technical Requirements) Page - 3

    3.5 DESIGN DRAWINGS .....................................................................................................................323.5.1 Drawing Format.....................................................................................................................323.5.2 Cross Referencing...................................................................................................................323.5.3 Drawing Compatibility...........................................................................................................333.5.4 Drawing Revisions..................................................................................................................33

    3.6 DESIGN APPROVAL .....................................................................................................................33

    3.7 ENVIRONMENTAL MATTERS ......................................................................................................333.7.1 Review of Environmental Factors...........................................................................................33

    4 FUNCTIONALITY REQUIREMENTS........................................................................................................................................344.1 RAIL SAFETY AND SITE VISITS...................................................................................................344.2 CONSTRUCTION HAZARDS AND RISKS .......................................................................................344.3 HAZARDRISKANDHUMAN FACTORSANALYSIS ......................................................................344.4 RELIABILITY ...............................................................................................................................35

    4.4.1 Functional Item Reliability.....................................................................................................354.4.2 Fixed Mechanical Items/Structures.........................................................................................354.4.3 Maintainability........................................................................................................................364.4.4 Availability..............................................................................................................................36

    4.5 INTERFACE MANAGEMENT.........................................................................................................364.5.1 With Existing Systems.............................................................................................................364.5.2 Interfaces with other Engineering service providers and other entities and or stakeholderswho access the site. ...............................................................................................................................37

    Attachments

    ATTACHMENT 1LAWSON CONCEPT DESIGN PACKAGE.............................38ATTACHMENT 2-DRAWING FORMAT ...........................................................40

    ATTACHMENT 3: SCADASYSTEM .............................................................41ATTACHMENT 4CONCEPT PROTECTION DETAILS.....................................44ATTACHMENT 5: DEFINITI ON OF CABLE NUMBERING...............................45ATTACHMENT 6: EXAMPLE CABLE SCHEDULE ..........................................46ATTACHMENT 7VOLTAGE REGULATOR REQUIREMENTS..........................47

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    4/49

    Part E (Technical Requirements) Page - 4

    1 Execut ive Summary

    RailCorp NSW is responsible for the operation and maintenance of train services and railinfrastructure in metropolitan and regional New South Wales.

    Fire damage recovery has made it necessary to upgrade the LV and HV facilities withinthe Lawson Traction Substation.

    This Technical Specification is for the detailed design and construction of facilities withina spare bay of the Lawson Traction Substation, including AC switchgear, transformerrelocations and all associated works. The detailed design and construction will be carriedout on the basis of a concept design provided by RailCorp and in accordance withRailCorp Engineering Standards. The designs will be required to incorporate majorplant items nominated by RailCorp which will be supplied from supply agreements thatRailCorp has in place. The substation must remain live and in operational service for the

    duration of the works.

    There are a number of items that have been identified that may impact on futureexpansions and/or works where it may be prudent to perform these works within thisproject. These have been requested as items to be included with tender; they are to betreated as separable components for the purpose of works scope.

    2 Scope of Works

    2.1 Design Scope of Works

    The Contractor shall provide in relation to the scope of work:

    1) Hazard, Risk and Human factors analysis2) Reliability, Availability and Maintainability analysis3) Design of the 66 kV outdoor switchyard, generally in accordance with Attachment 1

    Lawson Concept Design Package.4) Design of all associated cable routes within the substation boundary including 11kV

    cables.

    5) Design of the 66 kV AC outdoor transformer and regulator arrangements, completewith bunding, drainage and retention as applicable to the scope.

    6) Design of protection schemes in accordance with the concept protection scheme.7) Design of control and indication cabling and cable routes.8) Design of commissioning & test plan, including detailed commissioning & test

    procedures. The plan shall demonstrate that the designer has fully understood themanagement of the interfaces, both with existing systems and other engineeringdisciplines, which the commissioning and test plan will affect.

    9) Design of 11kV switchboards, distribution boards and protection equipment inaccordance with the Lawson Concept Design Package. See Attachment 1.

    The design of the below ground earthing installation does not form part of this RFThowever the Contractor shall manage the interface between the above ground and belowground earthing installations.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    5/49

    Part E (Technical Requirements) Page - 5

    The detail design shall include, but not necessarily be limited to, the following elements:

    2.1.1 General Design Requirements

    2.1.1.1 Definitions

    For purposes of Design, Design Verification and Design Approval:

    Contractor shall be a person or organisation that has been accredited by RailCorp to carryout design works on the RailCorp electrical distribution infrastructure.

    Contractors Designer shall be a qualified engineer who has been duly accredited byRailCorp to carry out electrical design of the Design works.

    Contractors Verifier shall be a qualified engineer who has been duly accredited byRailCorp to carry out electrical design verification and validation of the Design works.

    Accreditedshall be as defined by Division 1 of Part 2 of the Rail Safety Act 2002 No 96.The Designer and Verifier are required to be accredited for the separate sections of works:

    1. Distribution Design: HV switchgear and regulators; LV switchgear and cables2. Power Systems: Protection and Earthing Design3. Main: 11kV cables and Aerials

    RailCorp Electrical Design refers to the RailCorps Electrical Engineering Standards andServices

    2.1.1.2 Bui lding Code of AustraliaThe final design must comply with the relevant Parts of the BCA.

    Refer to Parts C, D and E in the BCA.

    2.1.1.3 Existing Services

    The design documents shall indicate the existing services, using a RailCorp ServicesSearch and other Dial before You Dig methods to locate the position of any existingservices. As listed RailCorp will provide a services search, however it is to be treated asinformation only as it may not include all cabling and or services be they live or redundantwithin the works site.

    2.1.1.4 Environmental Management Plan

    The Contractor shall prepare and submit an Environmental Management Plan. TheContractor shall demonstrate that the design complies with the EnvironmentalManagement Plan to address areas of potential environmental impact.

    2.1.1.5 Compliance

    Comply with Acts, Ordinances, Regulations, By-laws and Proclamations of theCommonwealth, State of New South Wales and relevant Local Government and theaccepted EMP.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    6/49

    Part E (Technical Requirements) Page - 6

    2.1.1.6 Bunding Considerations

    Refer to the Department of Environment & Climate Change (DECC) for guidelines for thedesign, construction and maintenance of bunds to minimise the risk of pollution fromspills and leaks. Electrical transformers containing oil shall comply with requirements ofthe DECC. The Contractor must design the bund to comply with Australian Standard AS

    1940: The Storage and Handling of Flammable and Combustible Liquids. Designdocuments are to include, an erosion control map and notification requirements to theDECC prior to commencement of work on site.

    2.1.2 Architectural / Civil / Structural Design

    2.1.2.1 General Requirements

    1) Design shall comply with the BCA, Australian Standards, Local Authorities andRailCorp Standards;

    2)

    Design shall include relocation of existing services including structures (i.e. polesand buildings etc);

    3) The colours and materials shall be chosen with due consideration given to existinggraffiti issues;

    4) All fill material specified for cable trenches shall be inorganic, non-perishablematerial of the types specified and free of sulphur content;

    5) All general filling material specified shall be: Granular material, maximum particle size 75mm Percentage passing .075 sieve 25% maximum Plasticity Index, not greater than 15% and not less than 2%

    6) All sub-grade fill specified shall be such that material in the top 150 mm shall have amaximum size of 75mm.

    7) The Contractor shall provide an Architectural / Civil / Structural Report to determinethe as found bearing capacity of existing foundations that are to be reused. AGeotechnical Engineer must certify that the foundation design is suitable. A copy ofthe report and certificate must be included in the final design report.

    8) The Contractor shall ensure that all testing is carried out by a NATA approvedlaboratory in accordance with the requirements of AS 1289 series. Methods of

    Testing Soils for Engineering Purposes.

    2.1.2.2 Particular Requirements1. The design shall include all incidental works and equipment, not specifically

    mentioned herein, necessary for the operation and performance of the systems.

    2. Provision of a geo-technical report enabling the suitable design of all foundationsand civil works;

    3. Design shall include excavation for new pits and underground trenching;4. Design to include reinforced concrete cable trenches, pits, footings and slabs to the

    extent indicated on the drawings (non-slip finish to trafficable areas);

    5. Design all reinforced concrete plinths for the 66/11kV transformer and voltageregulator equipment as required where not existing and useable;

    6. Detail design of 66 kV Circuit Breaker support structure and foundations;RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    7/49

    Part E (Technical Requirements) Page - 7

    7. Detail design 66 kV Air Break Switch support structure and foundations;8. Design to allow for galvanized metal gratings over service trenches. Design

    required for grating types, size and locations.

    9. Provide Operating and Maintenance Instruction manuals.10.

    Design to include the safely capping off by suitable means for the located unearthedservice of all redundant services where found.

    11. Applications and fees to local councils and other authorities shall be included as apart of the designers deliverables.

    12. Provide an adequacy report for bunding oil retention and disposal system;13. Provide an adequacy report for drainage/storm water retention and disposal;14. Provide adequacy report for fire detection and control.2.1.2.3 Optional Addi tional Works

    The following design and construction tasks are requested to be included with the tender:

    15. All external and internal doors are solid-core timber doors. The Tender shall providecosting for replacement and or retro fitting the doors with louvers;

    16. Design to allow for 150mm thick wool insulation (similar to CSR Glasswool andRockwool) to whole of the roof space, all in accordance with the manufacturersinstructions;

    17. Provide detailed design for the relocated battery room to an agreed location. Thedesigner shall ensure that the battery room is of sufficient size to adequately allowall equipment to function as intended. Design to include eyewash stands, which shallbe located on the design drawings.

    18. Design required for a system to ventilate the interior of the building (new controlroom and battery rooms only). The design may allow for a make-up air-intake,fixed-metal, Louvre panel systems to walls and nominated doors to supply air to theinterior ventilation system. The ventilation and make up air shall provide a minimumof 15 air changes per hour, at a wind speed of 6km/hr, and ensure an inside/outsidetemperature difference of 8 degrees for an ambient temperature of 40 degrees. All tobe in accordance with the requirements of AS1668.2:1991 - Mechanical Ventilationfor Acceptable Indoor Quality, Clause F5.4, Health and Amenity Light andVentilation Ventilation of Rooms. AS/NZS3666.1:2002 Clause F 4.5, Health andAmenity Light and Ventilation Ventilation of Rooms. Design of Class A rainresistant roof ventilation system employing turbine ventilators. The number ofventilators in the design shall be determined by substation internal air volume.

    19. Design of replacement or augmentation of the existing proposed 66/11kVtransformer foundation.

    20. Demolition, dismantling and disposal off site of redundant structures and associatedfoundations where necessary.

    21. Design associated with the relocation of the 66/11kV transformer from its presentlocation to the proposed location.

    RailCorp might delete any or all of Items 15 to 21 from the Contract.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    8/49

    Part E (Technical Requirements) Page - 8

    2.1.3 Electr ical Design

    2.1.3.1 General Requirements

    The Contractor shall:

    1.

    Provide safety clearances as detailed in AS 2067:1984, Switchgear Assemblies &Ancillary Equipment for Alternating Voltages above 1 kV, clause 10.2;

    2. For any component of design where required and specific details are omitted, theContractor shall provide design to the minimum standard as required by the relevantRailCorp and Australian Standards;

    3. Provide a detailed Electrical Hazard and Risk assessment. See Section 4.3 HazardRisk and Human Factors Analysis of this document;

    4. Provide a detailed Reliability, Maintainability and Availability analysis. See Section4.4, Section 4.4.3, and Section 4.4.4 respectively of this document;

    5. Provide a detailed Designers Risk and Hazard Analysis in accordance withOccupational Health and Safety Regulation 2001, Regulations 86-97 and RailCorpEngineering Design Management Plan ED0008P Clauses 6.3.2, 6.3.3 and 7.2;

    6. Provide all low voltage switchboards and miscellaneous marshalling or controlcubicles with a minimum 20% spare capacity;

    7. Provide design generally as detailed in RailCorps Standard EP 99 00 00 01 SP Substation Minimum Construction Standards; and

    8. Cable numbering shall be as detailed in Attachment 5 Definition of CableNumbering.

    2.1.3.2 Particular Requirements

    The Contractor shall provide:1. System Operating Diagrams concurrent with the project stage for the proposed

    arrangements to be submitted and approved prior to implementation;

    2. Electrical design details for the 66 kV outdoor dual busbar arrangements, showingRLs for the new air break switches (isolators);

    3. Electrical design details for the 66 kV outdoor isolator switchgear arrangements,showing RLs;

    4. Electrical design details for the 66 kV ACCB arrangements, showing RLs;5. Electrical design details for the 66/11 kV Transformer and 11kV regulator general

    arrangements, showing RLs;

    6. Electrical design details for 66 kV ACCB Protection and Control Switchboard inaccordance with the concept design. See EP 19 00 00 02 SP Protection SystemRequirements for the High Voltage Network;

    7. Electrical design details for 66 kV Feeder 865 ACCB Protection and Controlincluding pilot wire and over-current protection schemes. Design shall be inaccordance with concept design documents. See EP 19 00 00 02 SP ProtectionSystem Requirements for the High Voltage Network. Pilot Wire transformer(s) tobe located within the 66kV Protection Panel;

    8. Electrical design details for 66 kV Feeder 871 ACCB Protection and Controlincluding pilot wire and over-current protection schemes. Design shall be in

    accordance with concept design documents. See EP 19 00 00 02 SP Protection

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    9/49

    Part E (Technical Requirements) Page - 9

    System Requirements for the High Voltage Network. Pilot Wire transformer(s) tobe located within the 66kV Protection Panel

    9. Electrical design details for 66 kV Feeder 877 ACCB Protection and Controlincluding pilot wire and over-current protection schemes. Design shall be inaccordance with concept design documents. See EP 19 00 00 02 SP Protection

    System Requirements for the High Voltage Network;10. Electrical design details for 66 kV Feeder 878 ACCB Protection and Control

    including pilot wire and over-current protection schemes. Design shall be inaccordance with concept design documents. See EP 19 00 00 02 SP ProtectionSystem Requirements for the High Voltage Network;

    11. Electrical design details for 66 kV Busbar (Blue and Yellow) ACCB Protection andControl including buszone protection scheme. Design shall be in accordance withconcept design documents. See EP 19 00 00 02 SP Protection System Requirementsfor the High Voltage Network;

    12. Electrical design details for 66/11 kV Transformer ACCB Protection and Controlincluding transformer differential and overcurrent protection schemes. Design shallbe in accordance with concept design documents. See EP 19 00 00 02 SP ProtectionSystem Requirements for the High Voltage Network;

    13. Electrical design details for the eight (8) off 11kV ACCBs switchboard, plus theassociated VTs and Protection and Control. EP 19 00 00 02 SP Protection SystemRequirements for the High Voltage Network;

    14. Detailed design of cable routing arrangements within the Protection Panels andswitch-room building, as required;

    15. Detailed electrical design of 220V AC, 240V AC, 415V AC, 120V and 50V DCauxiliary supply panels;

    16. Detailed design for the 11kV cable termination and route between the 11kVregulator and the 11kV switchboard. See attachment for suggest routes;

    17. Detailed design of control cable routes between external equipment and the switch-room building including cable penetrations and all cable support systems necessarywithin the building;

    18. Detailed design of cable routing arrangements within the building, this shall includeall necessary rerouting and repair necessary to perform the task;

    19. Detailed design of cable routing for all high voltage cabling nominally (Feeders 659,680, and H403 also the new No.1 transformer, and the 2 auxiliary transformers)arrangements within and external to the building, this shall include all necessary

    rerouting and repair necessary to perform the task. Note: 680 feeder cable wasinstalled in 2007 and should be able to be rerouted rather than a new cable. Concept11kV cable routes provided in Attachment 1 Lawson Concept Design Package;

    20. A cable schedule including details of conduit allocation for all works included in thisscope. The schedule shall be in an approved MS Excel spreadsheet format andRailCorp Standards;

    21. detailed design for the marshalling of connections of control and indication wiringbetween equipment and the SCADA system. See attachment 3 SCADA System ifnecessary;

    22. A detailed site survey of all new equipment and cables installed or relocated in thevertical and horizontal planes for all services relating to the scope or within thedefined scope boundaries;

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    10/49

    Part E (Technical Requirements) Page - 10

    23. No provision for the augmentation or evaluation of the existing earthing system isrequired, however design shall incorporate earthing and bonding details for all newand or modified structures / equipment or foundations as is required in the applicableRailCorp Standard; and

    24. Electrical design details for Rectifier No.1 and 2, ACCBs protection and control.The design shall be in accordance with concept design documents. See EP 19 00 0002 SP Protection System Requirements for the High Voltage Network, for details.

    2.1.3.3 Optional Addi tional Works

    The following design tasks are requested to be included with the tender:

    25. Design of Emergency Lighting for works under this scope, nominally control room,battery room and egress routes from such.

    26. Detailed design of battery systems including sizing calculations, as defined by theconcept design. Battery capacity shall be sufficient to maintain auxiliary supplies forseven days after loss of 415V AC. Design shall be as detailed in RailCorp StandardEP 06 00 00 01 SP System Substation Battery. It is expected that the 7 dayrequirement will realise a large system battery. For these reasons the tender will alsobe required to provide pricings for a 3 day capacity system.

    27. Detailed design of optical fibre communications cable route between existingconnections and newly installed equipment where necessary.

    28. Detailed design of copper communications cable route between existing connectionsand newly installed equipment where necessary. Provide electrical design details for66/11kV Transformer general arrangement.

    RailCorp might delete any or all of Items 25 to 28 from the Contract.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    11/49

    Part E (Technical Requirements) Page - 11

    2.2 Design Matters

    2.2.1 Engineering Design Management Procedures

    The RailCorp design process is controlled by Engineering Design ManagementProcedures which are detailed individually in documents ED 0001 to ED0019. Thesedocuments are available on RailCorps extranet.

    2.2.1.1 Design Reviews

    Appropriate RailCorp personnel will participate in the Technical Review process and,when approved accept the design on behalf of RailCorp. Design review presentations willbe required.

    In accepting the Appointment under this Contract the Contractor is acceptingresponsibility and accountability as the designer and design verifier and will verify,

    validate, and sign off that the completed design complies with best engineering practice,standards, regulations, codes, guidelines and statutes applicable to the works.

    Design documents presented to RailCorp for review shall be packaged so that theapplicable RailCorp Principal Engineer can complete design reviews independently, thefollowing document groups shall be submitted:

    Principal Engineer Power Systems shallll review documents containing design forthe RailCorp High Voltage Network and for Earthing, Bonding and ProtectionSystems.

    Principal Engineer Mains shall review documents containing design for HighVoltage Aerial lines and Underground Cabling Systems. Principal Engineer Distribution shall review documents containing design for High

    Voltage and Low Voltage Distribution Substation and Power Supply upgrade.

    Senior Design Officer, Electrical Systems shall review drawings for drafting and CADacceptance.

    2.2.1.2 Acceptance of Design Responsibili ty

    The Contractor shall accept full accountability for their design detailing the configuration

    change and verifying its compliance with applicable standards, statutory requirements,regulations, guidelines and engineering best practices.

    The Contractor shall supply a comprehensive set of engineering calculations, drawings,specifications, schedules and written documentation, in sufficient detail to enableverification of that compliance.

    The Final Design Documentation Package shall be endorsed as Approved by theContractors approval authority. The verification and validation shall endorse that thedesign is complying and able to be accepted by the RailCorp Electrical Design for directinclusion in the construction works.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    12/49

    Part E (Technical Requirements) Page - 12

    2.2.1.3 Design Approval Responsibili ty

    The Contractors accredited Designer and Design Verifier shall accept responsibility fordesign approval. RailCorp will review all design documents submitted for conformitywith RailCorp requirements only. Following acceptance by RailCorp of all drawings the

    Contractor shall submit an A4 sheet, or sheets, in tabular form listing the documentnumber and revision letter, description and date. The sheet shall identify the name of theContractors organisation and carry a statement to the effect that the drawings referencedon the sheet are Approved for Construction by the Contractors Designer and DesignVerifier signatories whose original signatures shall appear on the sheet.

    2.2.1.4 Design Verifier

    The Contractor shall nominate their design verifier prior to acceptance of the designprocess and shall ensure that their nominated design verifier maintains compliance withthe following requirements throughout the duration of the design:

    Holds the necessary qualifications to check design work for the disciplineconcerned;

    Has been duly accredited by RailCorp. For external contractors, design authorityis delegated by the General Manager Engineering to the person(s) nominated bythe Contractor; and

    Has not been directly responsible for producing the design.Upon completion of the Final Detailed Design documentation the Contractors designverifier shall complete, sign and date a Design Verification and Approval Checklist.

    2.2.1.5 Design Verification

    The Contractors design verifier shall carry out the verification of the designdocumentation according to the RailCorp Engineering Design Management ProcedureED 0011 P prior to submitting for review. Verification shall proceed progressivelythroughout the design process. Progress of the verification shall be reported at the

    Technical Review meetings by presentation of a Design Verification and ApprovalChecklist signed by the Contractors design verifier for the stage of the design covered bythe meeting.

    2.2.1.6 Design Validation

    The Contractors design verifier shall carry out the validation of the design documentationon behalf of the Contractor according to the RailCorp Engineering Design ManagementProcedure ED 0012 P, prior to submitting for review.

    2.2.1.7 Design Programme

    A detailed design and interface management plan, including the design programme, shallbe developed and submitted to indicate major project milestones. Milestones will formhold points for the design process, for which RailCorp acceptance and approval will berequired before progress. Design progress beyond hold points (unapproved) which upon

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    13/49

    Part E (Technical Requirements) Page - 13

    approval requires change shall not be reason or cause for claim of additional designconsultancy fees based on unproductive use of engineering time.

    2.2.1.8 Designers Responsibilities

    The Contractor shall provide a design which is fully fit for purpose and provide a

    comprehensive set of engineering drawings showing sufficient detail for the work to becompleted as designed. The design shall make allowance for the methods of constructionlikely to be used during installation. The Contractor shall note that any or allresponsibilities incumbent with the design shall remain with the Contractor.

    2.3 Technical Review

    The primary objective of Technical Reviews is risk reduction, to ensure that anydepartures from the intent of the design tasks are recognised and reviewed as early aspossible in the design process and to enable corrective action to be implemented withminimal schedule and cost impacts. See3.4.2Technical Reviewsfor details of the review

    process.

    2.3.1

    2.4.1

    Detail Design Review

    The review will comprise three types of meetings at a nominated RailCorp location. TheContractors representative shall attend these meetings as required during the design andreview process. Meeting categories are as follows:

    1. Project Initiation Review2. Detailed Design Review3. System Verification Review2.4 Deliverables

    Detailed Design

    2.4.1.1 Technical Specification.

    Presented in an A4 size hard covered folder with sections separated by numbered dividersand one MSWord 97 compatible copy of the completed report on a CD. The followingsections shall be included:

    1. Document Control page2. Introduction detailing the project scope and contributors to the project.3. Technical specifications for the equipment proposed for the installation including

    sufficient information to allow construction to be completed without furtherreference to the designer.

    4. References specifically related to the installation phase.5. Drawing Index6. Cable Schedule7. Commissioning Documentation. The commissioning plan and associated

    documentation shall form part of the Technical Specification. The Commissioning

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    14/49

    Part E (Technical Requirements) Page - 14

    Plan shall demonstrate that due attention has been paid to the local operatingconditions which will prevail at the time of commissioning.

    8. Product information.9. Civil works specification.

    2.4.1.2 Design Report.

    Presented in an A4 size hard covered folder with sections separated by numbered dividersand an MSWord copy of the completed report on a CD. The following sections shall beincluded:

    1. Document control page.2. Introduction detailing the project scope, statement of responsibilities and a

    discussion of the observations noted.

    3. Equipment proposed.4.

    Design parameters, including sources.

    5. References specifically used in the design.6. Interface management plan.7. System Operating Diagrams concurrent with the project stage for the proposed

    arrangements.

    8. Hazard, Risk and Human factor analysis.9. Reliability, Maintainability & Availability analysis.10. List of RailCorp documents supplied for reference.11. Drawing index.12.

    Design Calculations. The report shall include copies of all design calculationcompleted (copies of hand written sheets are acceptable. All hand written sheetsmust be clearly legible, cursive text not to be used.).

    13. Product Information.14. Civil design verification documents.15. Detailed Project Construction Plan, including staging in accordance with hold

    points.

    2.4.1.3 Schedule of drawings.

    The schedule of drawings shall include drawing title, location, drawing description,drawing type, drawing size, in an approved format to which the designer can add theapproved RailCorp drawing number.In some cases the requirement for particular drawings may be covered by the OEMdrawings for the major electrical plant. In such cases it is acceptable that these drawingsbe incorporated into the drawing set by reference rather than being re-drawn, unlessdirected otherwise by RailCorp.

    The table below lists the minimum number of drawings anticipated for the project. Actualnumbers may vary dependant upon the complexity of the design task.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    15/49

    Part E (Technical Requirements) Page - 15

    DRAWINGNUMBER

    TITLE COMMENT

    TBASite Plan showing a survey layout including all RLs., accessgate, ramps, fencing etc.

    TBA Substation outside arrangement, Floor Plan, section, elevationand details.

    TBA Foundation layout PlanTBA Foundation layout sections and detailsTBA Major cable routes plan & sections.TBA Conduit Layout Plan & Detail.TBA Conduit ScheduleTBA Conduit Layout - Plan & Details.TBA 66kV Feeders AC SchematicTBA 66kV Bus Bar Interconnection AC Schematic

    TBA 66kV Feeders Wiring diagramTBA

    66kv Switchboard protection, metering and control - singleline diagram

    TBA 11kV Circuits AC SchematicTBA 11kV Circuits DC SchematicTBA 11kV Feeders Wiring DiagramTBA AC Board General ArrangementTBA AC Board SchematicTBA Light & Power LayoutTBA DC Board General ArrangementTBA DC Board schematic

    TBA SCADA Equipment general arrangementTBA SCADA I/O listTBA RTU marshalling panel termination diagramTBA Miscellaneous EquipmentTBA Miscellaneous equipment panel Termination diagram

    2.4.1.4 Full size paper copy of each drawing.

    1. Three copies of each drawing shall be submitted for review, dated and markedPRELIMINARY . All preliminary drawings shall be marked for their relevant

    revision date and description.2. Following acceptance by RailCorp, three full size copies of each drawing dated and

    marked FOR CONSTRUCTION, shall be submitted, accompanied by a separatecopy dated and signed in red ink as approved by the person responsible for the design.

    2.4.1.5 Electronic copy of each drawing.

    1. The following electronic copies of drawings are required: A copy of each FORCONSTRUCTION drawing in Microstation version 8 or AutoCAD version 2000.

    2. A copy of each FOR CONSTRUCTION drawing dated and signed by the approvingperson, as detailed in 2.4.1.4 above, in TIFF MSB, Monolithic CCIT Group IV file

    format, non colour drawings - resolution 300dpi in both X & Y directions. Markeduncontrolled when printed.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    16/49

    Part E (Technical Requirements) Page - 16

    3. Note: A process incorporating digital signatures on documents is at present beingformulated. The requirements of this section may be simplified should this process beincorporated by the time design drawings are submitted to RailCorp.

    2.5 Scope of Construction Works2.5.1 Extent of Work

    Works under this Contract comprise the supply of all labour, materials and equipment(except free issued items as detailed in Section 2.5.11) to complete the necessaryupgrading of the Lawson Electrical Substation. The works include all specificallyreferenced and incidental works necessary to ensure a fully functioning installation inaccordance with design documentation and RailCorps requirements. They include thefollowing items that are to be carried out in accordance with this RFT Document:

    2.5.1.1 Provis ion of Free Issue Equipment

    a) 66/11KV Transformer. (Onsite to be disconnected and relocated)b) 66kV Circuit Breaker (RailCorp to deliver to site)c) Air Break Switches (2) (RailCorp to deliver to site)d) 11kV voltage Regulator (RailCorp to deliver to site)

    All other equipment shall be supplied by the Contractor.

    2.5.1.2 General Work

    Preparation, implementation and management of an integrated and comprehensiveProject Plan with fully detailed hold points during the project including OHS&RPlan, Environmental Management Plan, Quality Plan, Traffic Management Plan,

    Demolition Plan and Daily Works Programme;

    Establishment and maintenance of Hazard Log for duration of works; Site establishment and provision of amenities; Setting out of the works; Supervision of all activities on site, this shall include the successful management of

    works and staff movements within a live and operational substation;

    Supply of railway worksite protection, when required; Preparation and submission of as built drawings; Interface management for daily works as approval by RailCorp for the duration of the

    works. RailCorp shall be responsible where appropriate for the issue of all accesspermits as required;

    Site clean-up and de-establishment;2.5.1.3 Civil Work

    Earthworks including excavation and disposal off-site of all excavated material to anapproved disposal site;

    Construction of bund;

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    17/49

    Part E (Technical Requirements) Page - 17

    Construction of new busbar, strung bus support structures and equipmentfoundations;

    Demolition works including removal of redundant drainage, electrical structures,cable pits, retaining wall and foundations; and

    Building works including roofing, ventilation and insulation.2.5.1.4 High Voltage Electr ical Work

    Modifications to outdoor busbars at Lawson substation; Construction of new 66kV dual busbar, strung bus and equipment support structures; Construction of new 66kV rigid and strung bus sections; Relocation and Installation of existing 66/11kV transformer, new 11kV regulator, 2

    air breaks switches / isolators and ACCB.

    Installation of modified 11kV cable routes and new 11kV cable routes. Supply and installation of 11kV switchboard. Installation of all necessary earthing and bonding as applicable to this scope of work. Supply, installation and termination of 11kV cables.

    2.5.1.5 Low Voltage Electrical Work

    Supply and installation of underground c abling;

    Supply and installation of new miscellaneous switchboards / panels;

    40V, 240V, 220V, 120VDC

    mented battery systems as required by

    on of all necessary earthing and bonding as applicable to this scope of work.2.5.1.6 Testing and Commissioning

    T d equipment. A test and commissioning plan

    2.5.1.7 Produce Records

    ocumentation, including ITPs and check sheets;

    service

    Supply and installation of 66kV Protection switchboard. Supply and installation of all new or augmented 415V, 2

    and 50VDC systems as required by design.

    Supply and installation of all new or augdesign.

    Installati

    esting & commissioning all construction an

    including records sheets with proposed pass/fail criteria shall be submitted for approvalduring design in the technical specification. Test and commissioning plans complete withminimum test requirements shall generally be in accordance with RailCorp Standards andsubmitted at least 6 weeks prior to the tests being required and accompanied with therelevant operational drawings that will be required.

    Submit test reports and QA d

    Produce and submit records and surveys of all equipments cables andlocations for the new installation under this scope to the DSS standard;

    Produce and submit as-built drawings;

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    18/49

    Part E (Technical Requirements) Page - 18

    2.5.2 Appl ication of Standards

    The Contractor m rks comply with the requirements of all currentAustralian and industry accepted Standards to the extent that they are relevant and that

    ite, the Contractor shall prepare and submit to RailCorp foracceptance Project Plan, incorporating but not limited to the following

    oremen, worksite protection officers, 24/7 contact person etc.). Information to be

    2.3. procedures, hold points and witness points;

    ding Safe Work Method Statements (SWMS and SWIs) and

    6. ;;

    g areas required for construction, storage of materials and staff

    ct Plan.

    The be submitted to the Principal for review and acceptance six (6)eeks prior to work commencing on site. No site work will be permitted to commence

    the rail line via Loftus Street.Access to the worksite is via a gate at the eastern end of the substation at this location.

    the

    site compound and amenities on land asmay be a lly agreed between the Principal and the Contractor. The

    ust verify that all Wo

    they are not exceeded by other Contract requirements.

    .5.3 Project Plan2

    Prior to commencing work on san integrated

    details:1. Names and contact details for key personnel (i.e. project manager, project engineer,

    site fprovided shall at minimum include qualifications relevant to the position, experiencein the position, relevant tickets and licenses including RISI, electrical contractorslicense. Note the requirement for only RailCorp issued RISI tickets from July 08. Thisinformation will be used to assess competence and subsequent approval by RailCorp

    of key staff for that position;Works Programme;Quality Plan including quality

    4. OHS&R Plan incluemergency procedures;

    5. Environmental Management Plan;Worksite Protection Plan

    7. Demolition Plan;8. Power outage requirements9. Site Plan showin

    amenities.

    10.Approved stage operating diagrams should be mentioned as hold points or milestoneson the Proje

    Project Plan shall

    wuntil the Principal has accepted the Plan.

    2.5.4 Access to Site

    Access to th le from Northern side of e Substation is availab

    Access to site is only permitted with the attendance of a RailCorp Substation Technician.

    A substation technician will be required to be in attendance for the duration of all dailyworks. The substation will remainLIVE and operational for the duration of the works.

    Note: The site is also a shared site with Integral Energy (IE) and as such total access to thewhole site may not be able to be given. This should not impinge on this contract butContractor needs to be aware of this situation.

    2.5.5 Site Compound

    The Contractor will be p lish hisermitted to estabvailable and mutua

    Contractor is to provide all site facilities and amenities as covered by the relevantindustrial awards including site sheds, toilet and ablution facilities, power, water andcommunications. Responsibility for security, protection from theft and vandalism willremain with the Contactor for all their amenities, tools and equipment.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    19/49

    Part E (Technical Requirements) Page - 19

    2.5.6 Temporary Demarcation Fence

    The Contractor must ensure that the security of the substation, and public safety are notcompromi

    ay require access to its facilities at times. Accordingly, the Contractor must be

    able to cle

    s) willbe:

    Saturday: 0700 to 1300 hours, for works on Saturday if required, a minimum 2 weeks

    of th ilCorp substation technician.

    ssary a comprehensiveworks programme for the works. The programme may be in the form of a bar chart but

    l ensure that a works programme is submitted for these

    sed.The Contractor shall prevent inadvertent encroachment of personnel into the substation. Ifnecessary a demarcation barrier may be erected at the periphery of the work site.

    The Contractor must provide and maintain fences, to preclude public access and trespassinto the substation where their arrangement or configuration is altered.

    The Contractor shall remove and dispose of all rubbish they generate on the site. TheContractor must keep all gates that might allow trespassers to access the substation lockedat all times, unless they are attended by a responsible person and are in immediate use.

    The Contractor must lock the gates at the end of its daily activities.On completion of the work, the Contractor is to fully restore the area to its previouscondition.

    2.5.7 RailCorp s Access to its facili ties

    RailCorp m

    ar the area to give access;The Contractor must keep clear access to the substation during non working times.

    2.5.8 Working Hours

    Permissible working hours on site (with the exception of the full track closedown

    Monday to Friday: 0700 to 1530 hours

    notice in writing must be given.

    Any work outside these hours including the delivery of materials is subject to the approval

    e Principal and availability of Ra2.5.9 Works Programme and Staging

    The Contractor is required to prepare, monitor and update as nece

    must show any critical dependencies etc. Daily work sheets must be submitted to RailCorp24hours prior to the proposed day of work for approval. Relevant risk assessments andsafe work method statements must accompany works programme. This requirement isinflexible and must be strictly adhered to ensure safety in a live and operational substation.

    Access for modification and or connections to the 66kV bus will be restricted to outage

    eriods only. Outage periods occur during possessions for the Blue Mountains region ofpwhich there are four per year. Outages outside possession times can some times beorganised with sufficient notice given, especially individual feeders. The Contractor shallprogramme the works to take advantage of these outages. This shall be shown in theproject plan. Also approved stage operating diagrams shall be shown as hold points ormilestones on the project plan.

    Notification from RailCorp of occasional night outages will be provided as soon asossible. The Contractor shalp

    outages a minimum of 12 weeks prior to the outage should they be required by theContractor.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    20/49

    Part E (Technical Requirements) Page - 20

    2.5.10

    2.5.11

    2.5.12

    2.5.13

    2.5.14

    2.5.15

    Subsurface Conditions

    It is the Contractors responsibility to assess for himself from this and any other data thathe may obtain the nature of the subsoil conditions across the site.

    Protection of Existing Infrastructure

    Construction of the Work under this Contract shall proceed without any disturbance to theexisting railway infrastructure (other than the nominated demolition works) and adjacentpublic and private property.

    The Contractor shall ensure that the stockpiling of materials and storage of plant on siteshall not interfere with the rail infrastructure including track, signalling and electricalequipment. The Contractor and Principal shall agree on the locations for stockpiling beforeequipment and materials are delivered to site.

    Coordination of Works with Others

    The Contractor will be required to co-ordinate his work with the Principal and anyauthorities whose services may require temporary or permanent relocation.

    If the Contractors work requires some prior work to be completed by the Principal orothers, he shall advise his requirements to the Principal not less than thirtydays beforesuch completion is needed.

    Railway Worksite Protection

    The Contractor shall provide Worksite Protection Services (WPS) for the works under theContract as and when required. It should be noted that the works under this contract arenot expected to require extensive access to the rail corridor.

    The WPS are to be obtained from any of the organisations approved to provide WPS byRailCorp.

    The requirement that the Contractor provide worksite protection personnel extends to anyperiods of full track possession and while working within the Danger Zone.

    Setting out the Works

    The Contractor shall arrange all survey and setting out of the works in accordance with theApproved for Construction Drawings. The following stages of the setting out are to becertified by a registered surveyor engaged by the Contractor and constitute Hold Pointsunder the Contract: 66 kV Structure and Equipment Foundations; Transformer Foundation; Regulator Foundation; Cable pits and trenches; and Penetrations into the substation.

    Services Search

    The Contractor shall confirm the location of all services within the work area, includingcontact and receipt of information from Dial Before You Dig and potholing as deemednecessary. Damage by the Contractor to known services that are located in the generalvicinity as identified in the services search will be at the Contractors risk and cost.Completion of the services search shall constitute a Hold Point under the Contract Quality

    System.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    21/49

    Part E (Technical Requirements) Page - 21

    2.5.16

    2.5.17

    Occupational Health & Safety

    The Contractor shall implement OHS&R practices and procedures in accordance withrelevant government legislation and the Special Conditions of Contract.

    The Contractor is to note that other contractors may be on site during the works.

    Protection of the EnvironmentThe Contractor shall prepare and implement a comprehensive Environmental ManagementPlan (EMP) for the performance of the works. The EMP shall be prepared and submittedto the Principal for acceptance prior to the Contractor commencing work on site.All work shall be carried out in such a manner as to avoid nuisance and/or damage to theenvironment or disturbance to adjoining landowners.

    The Contractor shall comply with the requirements of the Environmental Planning andAssessment Act, 1979, associated legislation and all requirements of relevant statutorybodies. No extensions of time or variation to costs will be considered due to theserequirements.

    The Contractor shall arrange for all necessary approvals required by the DECC and other

    bodies to enable the work to proceed. Further, the Contractor shall provide and maintainthroughout the construction period, all necessary environmental protection measuresrequired by the DECC.

    The Contractor shall mitigate the impact on the environment and the community at andnear the work site that might arise from dust, contaminated soil, debris, noise, obstruction,vibration, attraction of vermin, and all other effects, irrespective of whether these effectsare identified by RailCorp.In particular, the Contractor shall observe the following requirements: The whole of the works are to be planned and implemented to avoid erosion,

    contamination, and sedimentation of the site, surrounding country, watercourses andstreams;

    The Contractor shall not cause any unnecessary or excessive noise or smoke; The Contractor shall protect any watercourses from the ingress of sediments disturbed

    during construction work. Where necessary, sediment collection barriers and damsare to be provided;

    The washing down of concrete mouldings and agitators shall be carried out in an areathat drains into a collection pond or in some other location where pollution of waterscannot occur;

    Fuel and oil stored on site shall be stored in an area designed to hold 120% of thevolume of the largest tank within the bund. Such storage facility must not be located

    within a flood-prone area;

    Any vehicle maintenance, servicing or refuelling shall be carried out in an area whereany spillage of fuel, oil and other lubricants cannot pollute waters;

    No material shall be burnt on site other than that considered necessary for safetypurposes;

    The sites shall be cleaned regularly and left in a tidy condition on completion of thework;

    The Contractor shall rectify any damage resulting from the Contractor not observing theabove requirements.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    22/49

    Part E (Technical Requirements) Page - 22

    2.5.18 Signage

    2.5.19

    2.5.20

    2.5.21

    2.5.22

    2.5.23

    The concrete works shall be constructed in accordance with relevant sections ofRailCorps Standard TMC304 Structures Construction Manual.

    The Contractor shall provide safety construction signs conforming to the OH&S SafetyRegulation 2001, Part 8, and as otherwise required by the Contract. The general signage must include the Contractors and RailCorps logos, Danger Construction site sign; Notice sign, including RailCorps compulsory PPE requirements for construction site; Contractors Site Manager details; RailCorps contact details; and After hour emergency contact telephone number.

    The sign shall be made from corflute with minimum dimensions of 1200mm x 900mm.

    Hot Work Author ity

    The Contractor shall note that in the event of a Total Fire Ban, any work that has thepotential to cause a fire will be prohibited. This restriction includes all welding with theexception that the work is being undertaken during a closedown or major track possessionand the welding is essential for the continuance or restoration of rail services. In this event,

    it will be necessary for the Contractor to apply for a Hot Work Authority in accordancewith the procedures detailed in RailCorp Engineering Manual TMC 501 Bushfire HazardManagement Manual.

    Electrical Permits

    The Contractor shall provide an accredited electrical permit holder whenever necessaryunder RailCorps standards and safety procedures.

    Documentation and As-Built Drawings

    The Contractor shall prepare and submit one hard copy set of the construction drawings,marked-up to indicate work-as-executed (WAE). Any variations to the detail as specifiedon the contract drawings are to be clearly shown on the WAE set.

    The Contractor shall mark-up the WAE drawings as the various items of the workprogress and are completed. The Contractor shall submit WAE drawings for review ateach of the progress review meetings.

    The Contractor must accurately document the location of all new services installed by theContractor in accordance with RailCorps Detailed Site Survey (DSS) procedures.

    The Contractor must prepare and complete inspection test plans (ITPs) for new works andor equipment.

    Quality Standards

    The Work under this Contract shall be undertaken in accordance with RailCorp StandardTMC 304.

    The Contractor shall allow RailCorp to perform regular audit of the work. The Contactorshall make available all documentation to RailCorp for work audit.

    Concrete Works

    The scope of concrete works by the Contractor includes: Foundations for new busbar (strung and rigid) support structures. All necessary

    equipment (free issue or otherwise) whether specifically mentioned or which formspart of the detailed design;

    The above concrete works are to be treated as Witness Points under the Contract QualitySystem.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    23/49

    Part E (Technical Requirements) Page - 23

    2.5.24 Drainage Works

    The scope of drainage work by the Contractor includes: Provide an adequacy report for the existing drainage lines where shown on the

    Drawings or identified in the services search with the works scope boundary.

    ent;

    ing all associated

    rfere with construction of new structures, the. Such trimming shall not extend anyodating the new footing. This shall extend

    tions to be grade 350).

    lvanised to A.S.4680 unless noted otherwise on

    e Contractor for approval. Fabrication

    ise specified all welds shall be 6mm cfw in accordance to AS1554 Part

    shall be supervised by anengine to ensure that all requirements of the designare me

    The

    Connection of existing 66kV Dual Busbar to the new wiring structures / equipment;

    Installation and connection of two new air break switches;

    The Contractor shall maintain the existing drainage system to its best capacity duringconstruction.

    2.5.25 66kV Structures

    The scope of work on 66kV Bus Structures by the Contractor includes: Construction of footings for new 66kV equipm

    Fabrication and delivery to site of new steel structures, includholding down bolts and fastenings;

    Installation and erection of new structures;If existing redundant footings inte

    footings may be trimmed to suit, by saw cuttingdeeper than the minimum required accommto demolition and removal if required.

    Fabrication and protective treatment of the new structures;

    All workmanship to be in accordance with A.S.4100 and A.S.1554.1

    Unless otherwise noted, all steel to be grade 300 (hollow sec All connection and stiffener plates to be minimum 10mm thick u.n.o. All welds to be continuous fillet special purpose welds u.n.o.

    All bolts to be M20 and no connection to have less than 2 bolts u.n.o. All bolts to be grade 8.8/tc u.n.o. All holding down bolts to be grade 4.6/s u.n.o. All structural steel items to be fully ga

    the drawing.

    Shop drawings to be submitted in triplicate to thnot to commence until approval has been given.

    Unless otherw1, Category SP. The extent of weld inspections shall be:

    a. 100% visual examination; andb. Minimum 10% non destructive testing.

    The fabrication and erection of the structural steelworker experienced in such supervisiont.

    2.5.26 High Voltage Electr ical Work

    scope of high voltage electrical work by the Contractor includes:

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    24/49

    Part E (Technical Requirements) Page - 24

    Reloc of the existing 66/11kV transformer to the

    Installation and connection of the new 11kV voltage regulator;

    kV switchboard

    ard.

    wn on the Drawingswitches, surge arrestors, earth

    s design

    ngineering Standards, Specifications and manuals:

    System Substation Battery

    ltage

    r

    & Disposal of Material

    tions and Joints

    equirements

    The l certified by a qualifiedelec c eCon tion / commissioning stage for new

    wiring; and

    he scope of low voltage electrical work by the Contractor includes:

    ation, installation and connectionnew location ;

    Installation and connections for the new 66kV ACCB; Supply and installation and necessary connection of new 11 Relocation and augmentation of existing 11kV feeder cables as necessary to terminate

    at new switchbo

    Supply and installation of all electrical components as shoincluding all cabling, cable trays, fastenings, isolating sconnections necessary to perform the works detailed by this scope of workand construct contract.

    All high voltage electrical works shall be undertaken in accordance with thefollowing RailCorp E

    EP 99 00 00 01 SP Substations Minimum Construction StandardsEP 99 00 00 02 SP System Substation Commissioning Tests

    EP 99 00 00 04 SP Base Safety & Operating Standards

    EP 06 00 00 01 SP

    EP 19 00 00 03 SP Commissioning of Translay Pilot Wire Protection Scheme

    EP 19 00 00 02 SP Protection System Requirements for the High VoNetwork

    orme EP 16 00 00 02 SP Outdoor Ground Type Distribution Transfding EP 00 00 00 02 SP Electrical Technical Maintenance Co

    EP 00 00 00 07 SP Requirements for Handlingcontaining PCB

    EP 21 00 00 01 SP Insulation Co-ordination & Surge Arrester EP 20 00 00 03 SP Above Ground Cable Installation Systems Selection Guide EP 20 00 04 05 SP Cable Pits EP 20 00 04 01 SP Cable Route Selection Guide EP 20 00 04 04 SP Ground Entry Arrangements

    EP 20 10 00 02 SP High Voltage Cable Selection Guide

    EP 20 00 03 01 SP Requirements for Cable Polymeric Termina EP 20 00 00 20 SP Testing of High Voltage Cables EP 12 10 00 20 SP Earth Mat r

    fo lowing stages of the high voltage electrical works are to betri al engineer engaged by the Contractor and constitute Hold Points under thtract Quality System:

    At each 66kV structure and equipment termina

    High voltage power supply switchgear commissioning.2.5.27 Low Voltage Electrical Work

    T

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    25/49

    Part E (Technical Requirements) Page - 25

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

    nstall new protection and miscellaneous power main switchboard;ling to allow for completed

    installation and function in the intent of the design;

    inclu

    n of Cables AS3008

    The Building Code of Australia

    Earthing

    Distribution

    lating Transformer

    e low voltage electrical works shall be certified by a qualifiedelec c r and constitute hold points under theCon

    The o as a Hold Point under the

    Supply and i

    Supply and install all necessary and or incidental cab

    Supply and install power cabling including trenching, conduits and backfilling;Supply and install access pits; and

    Supply all necessary luminaries, fittings and fixtures.All low voltage electrical works are to be undertaken in accordance with the specifications

    ded on the Drawings and the following standards:

    Electrical Work AS/NZE 3000.2007 (Wiring Rules)

    Electrical Installations Selectio

    Quality Assurance AS 9000 Series New South Wales Local Government Act

    RailCorp Standards:

    EP 17000006SP Installation Inspection EP 12100010SP System Substation EP 95300002SL Isolation of Low Voltage EP 17000011SP Low Voltage Iso

    The following stages of thtri al engineer engaged by the Contractotract Quality System:Low voltage power supply; and

    Low voltage cable route to lighting.

    f llowing item of low voltage work shall be treatedContract Quality System: Commissioning and Test of Protection Switchboard.

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    26/49

    Part E (Technical Requi rements) Page - 26

    2.5.28 RailCorp Standards and Specif ications

    The following RailCorp Standards, Specifications and Manuals are also referred to in this documentand are available in soft copy on request to registered customers.Please contact [email protected] for a registration to receive these documents.

    Tenderers must allow sufficient time to effect their registration.

    2.5.29 Civil

    No. TITLETMC 501 Bushfire Hazard Management Manual

    TMC304/S01 Quality Assurance & ControlTMC304/S03 Miscellaneous EarthworksTMC304/S04 Excavation & Foundations for StructuresTMC304/S10 Concrete WorksTMC304/S22 Miscellaneous SteelworkTMC304/S25 Protective Galvanised Coating of SteelworkTMC304/S41 Demolition of Existing Structures

    2.5.30 Electrical : High and Low VoltageNo. TITLE

    EP 99 00 00 01 SP Substations Minimum Construction StandardsEP 99 00 00 02 SP System Substation Commissioning TestsEP 99 00 00 04 SP Base Safety & Operating StandardsEP 00 00 00 02 SP Electrical Technical Maintenance CodingEP 00 00 00 07 SP Requirements for Handling & Disposal of Material containing PCBEP 06 00 00 01 SP System Substation BatteryEP 12 00 00 01 SP High Voltage & 1500VDC System Earthing References & DefinitionsEP 12 10 00 10 SP System Substation EarthingEP 12 30 00 01 SP Electrolysis from Stray DC CurrentEP 16 00 00 02 SP Outdoor Ground Type Distribution TransformerEP 19 00 00 03 SP Commissioning of Translay Pilot Wire Protection SchemeEP 19 00 00 02 SP Protection System Requirements for the High Voltage NetworkEP 21 00 00 01 SP Insulation Co-ordination & Surge ArresterEP 20 00 00 03 SP Above Ground Cable Installation Systems Selection GuideEP 20 00 04 05 SP Cable PitsEP 20 00 04 01 SP Cable Route Selection GuideEP 20 00 04 04 SP Ground Entry ArrangementsEP 20 10 00 02 SP High Voltage Cable Selection GuideEP 20 00 03 01 SP Requirements for Cable Polymeric Terminations and Joints

    EP 20 00 00 20 SP Testing of High Voltage Cables

    2.5.31 Detailed Site Survey (DSS) Procedures

    No. TITLEEP 0491 to EP 0497 Detailed Site Survey Data Capture Procedure

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

    mailto:[email protected]:[email protected]
  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    27/49

    Part E (Technical Requi rements) Page - 27

    3 Quality Requirements

    3.1 Design Standards

    All design work performed by the Contractors Designer shall conform to standards stated.

    In the event of any ambiguity, inconsistency or discrepancy with the requirements of any referencedocumentation the designer must detail the ambiguity, inconsistency or discrepancy found, assessthe impact and advise RailCorp.

    3.2 Selection and Use of Australian and International Standards

    The Contractors Designer shall be responsible for the selection and use of the appropriateAustralian and/or International standards for individual design tasks, including:

    The requirements of Lawson Concept Design Packages provided by RailCorp, and Requirements for compliance with NSW State and Federal Legislation and Regulations,

    including NSW Occupational Health and Safety Regulations 2001, Environmental Legislationand Regulations, Electricity Legislation and Regulations, and

    Additional requirements included in RailCorp Standards that limit or otherwise amplify theuse of other standards for RailCorp applications.

    3.3 RailCorp Standards

    RailCorp has adopted a series of internal Standards for use within the design of rail infrastructure.These include Standards prepared by, or on behalf of, predecessor organisations (RSA, RAC, andSRA) that have had responsibility for design and maintenance of the NSW rail systeminfrastructure.

    The set of RailCorp Standards applicable to design tasks comprises two general types ofdocuments, as follows:

    1. Standard Specifications. These generally cover physical and functional performancerequirements and limitations for items and materials used in infrastructure design andmaintenance. Standard specifications also include details of items or products that have beentype approved for use within the RailCorp system as well as limitations on the use of typeapproved products.

    2. Standard Designs. These generally cover type approved designs that have been developedfor use in appropriate applications within the RailCorp Infrastructure.

    The RailCorp Standard Documents referenced above may be used by the Contractor however theresponsibility for provision of a design which is fit for purpose remains with the Contractor.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    28/49

    Part E (Technical Requi rements) Page - 28

    3.4 Standard of Completed Design

    3.4.1 Design Verif ication

    Design verification ensures that the output from an individual design stage meets or is likely tomeet the verified inputs to that stage. Design verification is part of the process whereby designoutputs are progressively reviewed before the design is released for construction. The designershall note that any review undertaken by RailCorp will not transfer design ownership to RailCorp.

    The design and any or all responsibilities incumbent with such design will remain with thedesigner. Verification of design output shall be achieved as specified below:

    3.4.1.1 Design Verifier

    The Contractor shall nominate their design verifier prior to acceptance of the design process andshall ensure that their nominated design verifier maintains compliance with the following

    requirements throughout the duration of the design:

    Holds the necessary qualifications to check design work for the discipline concerned, and hasbeen duly accredited by RailCorp. For external Contractors, design authority is delegated bythe General Manager Engineering to the person(s) nominated by the Contractor.

    Has not been directly responsible for producing the design. Design checks shall be performedby the design engineer supervising the design tasks performed by members of that team butcan be performed by any competent and properly authorised engineer meeting the foregoingcriteria.

    Upon completion of the Final Detailed Design documentation the Contractors design verifier shall

    complete, sign and date a Design Verification and Approval Checklist to sign off their verificationof the final design.

    3.4.1.2 Design Verification

    The Contractors design verifier shall carry out the verification of the design documentationaccording to the RailCorp Engineering Design Management Procedure ED 0011 P prior tosubmitting for review. Verification shall proceed progressively throughout the design process.Progress of the verification shall be reported at the Technical Review meetings by presentation of aDesign Verification and Approval Checklist signed by the Contractors design verifier for the stageof the design covered by the meeting.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    29/49

    Part E (Technical Requi rements) Page - 29

    3.4.1.3 Design Validation

    The Contractors design verifier shall carry out the validation of the design documentation on

    behalf of the Contractor according to the RailCorp Engineering Design Management Procedure ED0012 P, prior to submitting for review.

    3.4.2 Technical Reviews

    3.4.2.1 Project Init iation Review

    A Project Initiation Review (PIR) will be carried out as early as possible after the award of thecontract. The main purpose is to ensure that the design brief fully defines the requirements for thetask and that any inconsistencies or omissions are identified and resolved.

    The PIR should take place after the design brief has been reviewed in detail by all applicablediscipline groups and following initial requirements analysis and allocation.

    Submission of a Design Management Plan is required at the PDR including provisions for interfacemanagement.

    RailCorps Authorised Person will convene the PIR.

    Project Initiation Reviews shall be attended by representatives of the Contractors design staff, theRailCorp Delivery Manager, Stakeholders and representatives from RailCorp Design Section(s)appropriate to the scope of the task. The Delivery Manager will be responsible for chairing all

    such reviews, in conjunction with the Head of the applicable design section(s).

    3.4.2.2 Preliminary Design Review Meeting

    The purpose of Preliminary Design Reviews (PDR) is to assess whether the proposed approach forthe design is consistent with the functional and performance requirements of the design brief.

    PDRs will take place when the preliminary design has progressed to a level of detail that will allowthe intended approach to be assessed for compliance with the design intent of the design brief. ThePDR may be conducted in one session or in several sessions to consider individual parts of thedesign.

    PDRs conducted with the designer will be attended by the RailCorp Design Delivery Manager,Stakeholders and the Section Head or a Team Leader from each discipline involved. RailCorp staffnominated to attend PDRs will have reviewed information delivered by the designer prior to themeeting.Minimum levels of information necessary to conduct an effective review include: Preliminary design and layouts drawings, including interface definitions, A summary of key assumptions made by the designer, Initial selection of major components and materials. The results of preliminary risk, hazard and human factors analysis, Preliminary reliability models and predictions available.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    30/49

    Part E (Technical Requi rements) Page - 30

    Design reports and calculations may be required in support of the review process but are notnormally delivered in advance of the review.

    3.4.2.3 Detailed Design ReviewThe Detailed Design Review (DDR) will take place at or close to the completion of the detaileddesign phase. The primary purpose is to ensure that the design appears to be suitable in all respectsto proceed with construction and fabrication.

    In this Contract construction is involved, the DDR will form a major input for determining whetherthe requirements of the design contract has been met.

    In addition drawing reviews will be completed as detailed in Electrical Standard EP 00 00 00 15 SPCommon Requirements for Electrical Power Equipment Paragraph B3.3 Drawings. Drawingreview will be an iterative process until design is considered complete, following which all

    documentation as detailed in Section2.4above shall be submitted by the to RailCorp.

    The scope of the DDR is similar to the PDR, but addresses the proposed design in more detail. Thisincludes detailed drawings and supporting design information (design report and technicalspecification), safety and hazard analysis and final reliability models and predictions for the design.

    The Design Delivery Manager is responsible for convening the DDR stage, by agreement with theContractors Design Manager, as applicable. Wherever possible the DDR shall be attended byRailCorp Stakeholders as well as RailCorp Section Heads or Team Leaders from each disciplineinvolved in the project.

    3.4.2.4 System Verification Review

    A System Verification Review shall be carried out to ensure all verification and validationrequirements of the contract have been met, including testing to the extent that it is appropriate tothe contract task.

    3.4.2.5 Design Checking

    Upon contract award design authority shall be deemed to be transferred to the Contractorsdesigner, being the appointed design consultant. Design checking will also be the soleresponsibility of the Contractors designer.

    Design checking shall include the systematic review of design assumptions, calculations,methodology, use of standards and compliance with mandatory requirements as part of the designprocess by an engineer who:

    a) Holds the necessary qualifications to check design work for the discipline concerned,b) Is properly authorised. For external service providers (Contractors designer) design authority

    is delegated by the General Manager Engineering to the person(s) nominated by the externalservice provider, as having responsibility for Design Approval; and

    c) Has not been directly responsible for producing the design.Design checks shall be performed by the design engineer supervising the design tasks performedby members of that team but can be performed by any competent and properly authorised engineer

    meeting the foregoing.

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    31/49

    Part E (Technical Requi rements) Page - 31

    3.4.3 Reference Standards

    The documents listed below are a representative list of applicable standards. The list is notcomprehensive and it remains the responsibility of the designer to ensure compliance with allrelevant standards.

    Number Revision/Date of Issue Title

    EP 99 00 00 01 SP Ver. 2 November 2001Substations minimum construction standards

    EP 99 00 00 04 SP Ver. 2 November 2001Substations Base safety and operating standards

    EP 99 00 00 02 SP Ver. 2 November 2001 System Substation Commissioning Tests

    EP 12 10 00 10 SP Ver. 2.1 September 2002System Substation Earthing

    EP 12 00 00 01 SP Ver. 2 November 2001 High Voltage & 1500 System Earthing References &Definitions

    EP 00 00 00 01 TI Ver. 2 November 2001 RailCorp Electrical system general descriptionEP 90 10 00 01 SP Ver. 2 November 2001 Electrical phase relationshipsEP 90 30 00 01 SI Ver 1.0 June 1997 Polarity of AC Signalling SuppliesEP 21 00 00 01 SP Ver. 2.0 November 2001 Insulation Coordination & Surge Arrestor SelectionEP 20 10 00 02 EP Ver. 1.0 October 2002 High voltage cable selection guideEP 90 10 00 02 SP Ver 2.0 November 2001 Standard Voltage Tolerances.EP 03 02 00 01 SP. Ver 1.0 July 2004 Control and Protection for Rectifier EquipmentEP 95 00 00 10 TI Ver 1.0 22 June 2001 DefinitionsEP 95 00 00 00 TI Ver 1.0 22 June 2001 Electric Power systems Safety AspectsEP 95 00 30 06 SP Ver 1.0 September 2003 Electrical Network Management Plan.EP 20 00 04 01 SP Ver 1.0 October 2002 Cable Route Selection Guide

    EP 00 00 00 13 SP Ver 1.0 January 2004Electrical Power Equipment Design Ranges ofAmbient Conditions

    EP 00 00 00 12 SP Ver 1.1 November 2003Electrical Power Equipment- Integrated SupportRequirements.

    EP00 00 00 15 SP Ver 1.0 July 2004Common requirements for Electrical PowerEquipment

    EP 19 00 00 02 SP Ver 3.0 July 2004Protection System Requirements for the HighVoltage Network

    ED0001 ED0019 Ver 1.1 June 2004 Engineering Design Management Procedures

    AS/NZS 3000 2007Electrical Installations (known as the Australian/NewZealand wiring rules)

    AS 2067 1984Switchgear assemblies and ancillary equipment foralternating voltages above 1 kV.

    AS 4680 1999Hot-dip galvanised (zinc) coatings on fabricatedferrous articles.

    EP 95 00 00 10 TI Ver 1.0 22 June 2001 DefinitionsEP 95 00 00 00 TI Ver 1.0 22 June 2001 Electric Power systems Safety AspectsEP 95 00 30 06 SP Ver 1.0 September 2003 Electrical Network Management Plan.EP 20 00 04 01 SP Ver 1.0 October 2002 Cable Route Selection GuideEP 00 00 00 13 SP Ver 1.0 January 2004 Electrical Power Equipment Design Ranges of

    RFT No. 08/08056Design and Construction of Upgrading Worksfor Lawson Electrical Substation

  • 7/30/2019 TECHNICAL REQUIREMENTS.pdf

    32/49

    Part E (Technical Requi rements) Page - 32

    Number Revision/Date of Issue Title

    Ambient Conditions

    EP 00 00 00 12 SP Ver 1.1 November 2003Electrical Power Equipment- Integrated Support

    Requirements.

    EP00 00 00 15 SP Ver 1.0 July 2004Common requirements for Electrical PowerEquipment

    EP 19 00 00 02 SP Ver 3.0 July 2004Protection System Requirements for the HighVoltage Network

    ED0001 ED0019 Ver 1.1 June 2004 Engineering Design Management Procedures- - City Rail Sign Types Manual.

    3.4.4

    3.4.5

    3.5.1

    3.5.2

    Access to Rai lCorp Standards

    Copies of all RailCorp Standards are located on the RailCorp Extranet. These can be madeavailable to the Contractor if requested.

    Access to Rai lCorp drawings

    Copies of all RailCorp and/or SRA original drawings can be obtained from the RailCorp plan roomafter RailCorp authorisation has been granted. RailCorp authorisation will be arranged by theDesign Delivery Manager after written request by the Contractors designer. Drawings are beingprogressively scanned into the drawing database and where this has occurred the scanned copy maybe made available electronically.

    It shall be the Contractor designers responsibility to ensure that the information contained on thedrawi