team a pm600 working plan :: jennifer brower pmp :: naperville, il
DESCRIPTION
PM600 Masters projectTRANSCRIPT
Working Plan
8/23/2009PM 600 Section C
Tina Finch
Team A:Jennifer BrowerTom Menning
Fred ParlinThomas Rampley
Table of Contents
1.0 Executive Summary............................................................................6
1.1 Project Baseline........................................................................6
........................................................................................................
1.2 Project Variance........................................................................7
1.3 Project Expansion......................................................................8
2.0 Technical Information........................................................................10
2.1 Project Purpose.......................................................................10
........................................................................................................
2.2 Project Benefits.......................................................................10
2.3 Statement of Work (SOW)........................................................11
2.3.1 Scope.........................................................................11
2.3.2 Applicable Documents.................................................12
2.3.3 Tasks (Level 2 WBS)....................................................13
2.3.4 Deliverables & Acceptance Criteria..............................16
2.4 Project Plan.............................................................................17
2.4.1 Technical Description..................................................17
2.4.2 Project Schedule.........................................................19
2.4.3 Project Resource Loading............................................20
2.4.4 Specific Challenges.....................................................21
2.5 Project Completion Plans.........................................................24
2.5.1 Deliverables................................................................24
2.5.2 Acceptance and Sign-Off..............................................24
3.0 Initial Management Plan....................................................................26
3.1 Corporate Organizational Structure..........................................26
3.2 Project Organizational Plan......................................................26
3.2.1 Work Breakdown Structure (Level 3 WBS)....................26
3.2.2 Project Team...............................................................28
4.0 Management Systems.......................................................................29
4.1 Monitoring Cost and Schedule .................................................29
4.1.1 Overview ...................................................................29
4.1.2 Earned Value Report ...................................................29
4.1.3 Major Cost and Schedule ............................................30
4.2 Risk Management ...................................................................30
4.2.1 Overview ...................................................................30
Page 2 of 56
4.2.2 Risk Inventory and Contingencies................................32
4.2.3 Risk Ranking and Re-Evaluation Procedures.................34
4.2.5 Risk Escalation Procedures..........................................34
4.3 Project Communications Management .....................................35
4.4 Environmental, Worker Safety, and Health...............................36
4.4.1 Environmental............................................................36
4.4.2 Worker Safety.............................................................37
4.4.3 Occupational Health....................................................38
5.0 Cost Working Plan............................................................................40
5.1 Project Cost ............................................................................40
5.1.1 Total Project Cost .......................................................40
5.1.2 Breakdown of Project Costs ........................................40
5.1.3 Progress Payments.....................................................45
5.2 Customer-Provided Resources.................................................45
5.3 Terms and Conditions.............................................................46
6.0 Unexpected Event ............................................................................49
6.1 Problem Description and Current Status..................................49
6.2 Alternative Solutions & Evaluation ..........................................49
6.3 Proposed Action.....................................................................50
7.0 Added Work.....................................................................................52
7.1 Project Description.................................................................52
7.2 Initial Planning.......................................................................53
7.3 Scope......................................................................................53
7.4 Schedule................................................................................54
7.5 Budget....................................................................................56
Appendix A: List of Figures.....................................................................58
Figure 1 Gantt Chart (Level 3).....................................................59
Figure 2 Organization Chart for Customer....................................60
Figure 3 Work Breakdown Structure (Level 3)..............................61
Figure 4 Organization Chart for Project.......................................63
Appendix B: List of Tables.......................................................................64
Table 1 Acceptance Criteria.......................................................65
Table 2 Breakdown of Total Project Cost.....................................67
Page 3 of 56
This page intentionally left blank.
Page 4 of 56
1.0 Executive Summary
1.1 Project Baseline
The City of Loganville Emergency Response Plan project began officially after the
proposal was accepted on August 9, 2009. Overall, the project has stayed on
time and budget through today, November 9, 2009. The project has gone very
well and the City of Loganville has gone out of its way to work with the project
team.
Here is an overview of the project status so far:
Deliverable Complete In-progress Not Yet StartedRisk Identification, Level, and Response X
Warning System and Signals X
Emergency Plan Documentation X
Disaster/Hazard Supply X
Shelters X
Communications Plan X
Community Plan X
Practicing and Maintaining Plan X
Food Safety X
All project deliverables have been started and are to be completed according to
the Gantt Chart. The deliverables are all on time and at budget. The following list
shows the status of existing Work Breakdown Structure items:
1. Hire Director of Emergency Response: $50,000/Year. Complete
2. Subject Matter Expert Conference: $7,500. Complete
3. Emergency Response Center of Operations: $245,000 Approx 40%
Complete
4. Setup of Shelter Network. Complete
5. Communication Plans. Approx 40% Complete
6. Volunteer Selection/Training. Complete
7. Emergency Notification System. Complete
8. Emergency Response Test. Incomplete
The following progress payments were made:
Page 5 of 56
1. Upon Project Initiation – 20% - Paid
2. Upon Completion of SME Conference – 20% - Paid
3. Upon Completion of Shelter Network Setup – 20% - Paid
4. Upon Completion of Emergency Notification System – 20% - Paid
1.2 Project Variance
There were two unexpected items that required extra work:
1. Asbestos Abatement (Unexpected Event) - $125,000
2. Food Safety Program (Added Work) - $10,000
The cost of both items were not disputed and were able to run parallel to the
project schedule. These items also fit into the project scope.
The total project proposal was originally offered at a price of $735,000. Due to
additional costs incurred by unexpected events/work, the total project costs are
now $870,000. This is shown in Appendix B - Table 2 Breakdown of Project Cost.
Here is the status of the two additional items were added to the Work
Breakdown Structure. The complete WBS is shown in Appendix A -Figure 3:
1. Asbestos Abatement (Unexpected Event). Complete Next Week
2. Food Safety Program (Added Work). Complete
1.3 Project Expansion
Overall, the project has gone very well up to this point in time. The project has
remained on time, on budget, and in scope. However, there were two items that
required additional work. It is fortunate that these items were brought to the
forefront early in the project.
First, the team learned that the largest of the buildings slotted to be used as a
shelter turns out to contain asbestos and must be decontaminated before the
plan can be implemented. There are no alternative buildings, so the costs and
time required to carry out the decontamination, has been added to the overall
cost. The City of Loganville understands that it will bear these additional costs
and we have revised the project to reflect the impact of this event.
Page 6 of 56
Second, the team learned of a food safety program offered by the Department of
Homeland Security. This program This program permits municipalities to apply
for a grant to introduce a proactive food product safety program for all foods
sold locally. The project received the grant on November 9, 2009.
Any negative impact the items had on the overall project is limited to extra
costs. The asbestos removal project required extra labor resources while the
food safety program required the use of existing city resources.
However, these items also had a positive impact on the project. The asbestos
removal program helped improve environmental factors while the food safety
program brought peace of mind that food supplies will be safe if an emergency
occurs. Also, the food safety program will bring an extra $350,000 each year to
the community for safe food.
The positives, however, outweighed the negatives. Both items resulted in adding
value to the project with very little interruption to the project.
Page 7 of 56
2.0 Technical Information
2.1 Project Purpose
Preparedness refers to the state of being prepared for specific or unpredictable
events or situations; and that is ultimately the primary goal of this project -
preparedness.
The need to prepare for disasters, as well as, food safety is real. Being prepared
can reduce anxiety, fear, and the losses that typically accompany disasters.
The purpose of this project is to create a comprehensive disaster recovery and
food safety plan that will leave Loganville, South Carolina much better positioned
and prepared to respond to the needs of its citizens in the event of catastrophe
than it was prior to the creation of a disaster recovery response plan.
2.2 Project Benefits
Disaster preparedness is literally a matter of life and death. A litany of benefits
large and small, tangible and intangible will be the resulting payback from the
successful completion of this project, not the least of which will be a significant
reduction in the potential for loss of life in the event of a disaster.
Additionally, the food safety portion of this project will provide for the
development of local food safety policies, laws and activities that parallel
pending federal reforms with the intent of empowering the local agencies to
cooperate with state and federal agencies in a far more coordinated manner.
This project will provide many benefits to the city's visitors and inhabitants.
1. The emergency response plan will improve the quality of life by providing a
safe, healthy, beautiful and harmonious place to live and work.
2. The plan will help provide peace of mind to the community as it grows. The
city must be safe and provide a haven to its citizens in order to promote
growth.
3. This project will facilitate communication during a desperate situation. Help
will be delivered to those who need it. And those who provide help in cases of
Page 8 of 56
emergency will be able to act with precision and confidence while proving
information to the federal response team that will take over afterward.
4. In the unfortunate event of emergency, the community will have peace of
mind and have the ability to obtain food, shelter, and safety from the
elements and individuals who wish to harm others. In these times of great
danger in the world, it is the responsibility of the City of Loganville to offer
peace of mind and the ability to provide intelligence to federal responders.
The community will be able to immediately step into action via first
responders.
2.3 Statement of Work (SOW)
2.3.1 Scope
We intend to develop and administer an emergency response
preparedness plan for the City of Loganville, South Carolina. The
Team's intention is to ensure that local officials are adequately
prepared to provide immediate assistance to the community in the
event of a disaster until outside agencies are able to respond.
Additionally, the project scope includes the utilization of a government
grant for the development of a proactive food product safety program
for food items sold locally.
This plan will ensure that local officials and volunteers are adequately
prepared and able to provide immediate assistance to their community
in the event of a disaster until outside agencies are able to respond.
This disaster response plan calls for the decontamination of one of the
buildings slotted to be used as a shelter as the building contains
asbestos.
2.3.2 Tasks (Level 2 WBS)
Think of a Work Breakdown Structure as a decomposition of the work
that needs to be completed in order to accomplish the project’s
objectives. There are a number of milestones which are significant
events in a project. Milestones help to organize and define the scope of
the project. Each of these milestones is subsequently subdivided into
Page 9 of 56
an increasingly detailed definition of the project work. The WBS is
shown below in the following chart:
WBS Code Initiative
1.0
1.1 Director of Emergency Response
1.2 Subject Matter Expert Conference
1.3 Emergency Response Center of Operations
1.4 Shelter Setup
1.5 Communication Plans
1.6 Volunteers/Training
1.7 Emergency Notification System
1.8 Emergency Response Test
1.9 Asbestos Abatement
1.10 Food Safety Program
2.3.3 Deliverables
Hazard Identification, Risk Level, and Risk Response Plan
This deliverable involves identifying all potential hazards along with
an assessment that rates the likelihood and the impact of each
one.
For hazards identified as being high risk, the scope of work calls for
the creation of a full documented risk mitigation plan detailing
methods meant to lower the impact or reduce the risk of each
hazard.
For hazards identified as being medium risk, a risk mitigation plan
will be created for each hazard, but to a lesser degree of detail
than that of the high risk hazards.
For hazards identified as being low risk, the scope of work calls for
a simple statement explaining the best way to mitigate the risk of
each hazard.
Warning System and Signals
This deliverable involves detailing how the plan intends to provide
for the initial warning of both the community, as well as, local
public officials of the existence of a hazard.
Page 10 of 56
The scope of work calls for a tiered system causing the higher risk
hazards have higher priority in the communication plan.
Emergency Plan Documentation
This deliverable requires that the plan provide local officials with
easily understood documentation to aid them in implementing the
emergency response plans. These documents (checklists) are to be
accessible to local officials online for review. The scope calls
specifically for the following:
1. Updated area maps
2. Escape routes (a plan to manage highway traffic)
3. Communications plans, shutting off utilities, handling those
with special needs (such as the elderly).
4. Handling animals (pets)
5. Basic safety skills
Disaster/Hazard Supply
This deliverable calls for the creation of a method for educating the
general public and local officials concerning how to prepare
themselves for hazards and providing for their own basic needs for
a period of several days. Basic needs are defined as water, food,
first aid, clothing and blankets. The scope calls for the development
of lists of emergency supplies people should have in their
workplaces, homes, schools, and cars.
Shelters
To meet the scope of this deliverable, the plan must identify
several community buildings to be used as mass care shelters. In
addition to identifying these locations, the project is expected to
provide for the abatement of the asbestos contamination at the
largest of the identified buildings and deliver a method for the
stockpiling and dispensing of basic supplies at each shelter: water,
Page 11 of 56
food, first-aid and sanitary facilities, as well as, addressing security
concerns.
Communications Plan
The communications plan is two-fold.
First, this deliverable requires the development and testing of a
method for local officials to use to communicate with one another
during a disaster.
The second piece of this deliverable calls for the development of a
means of informing the community of actions to take during a
disaster rather than merely informing them that a disaster is
occurring. In addition, the scope declares that the plan instruct the
community to go to a website that will have further instructions for
them, as well as links to other pertinent government websites.
Community Plan
This deliverable requires that the plan detail a method for the
creation and operation of a group of community volunteers that will
report to a designated city official. This group and their city official
will create a community emergency response plan.
Practicing and Maintaining Plan
This deliverable calls for the development of methods for practicing
the emergency response plan for each of the various disaster
scenarios. These methods should be created such that emergency
communications methods and equipment are tested to assess their
functionality.
In addition, this deliverable requires that the plan include a process
for maintaining and updating the emergency response plan going
forward as the needs of the city change and to communicate those
changes to the appropriate parties.
Page 12 of 56
Food Safety
This deliverable calls for the development of a proactive food
product safety program for all food items sold locally. Utilizing a
federal grant we will develop a proactive food product safety
program that links local food safety activities with state and federal
efforts and parallels federal reforms.
2.3.4 Acceptance Criteria
The criteria and requirements that the project must meet before the
Customer will accept delivery are as follows:
All deliverables and work performed are subject to Customer’s
written approval.
All deliverables and work performed will be provided in a manner
consistent with and on the dates detailed in the proposal.
During acceptance testing, the project team will make themselves
reasonably available to the customer.
During acceptance testing, if the customer determines that any
deliverable does not meet the requirements agreed upon in writing,
the customer will notify the project team in writing with specifics.
The project team has ten (10) business days to correct the
deficiencies. Then, acceptance testing will once again resume. This
will continue until the deliverable is accepted. However, the
customer may terminate the agreement after two (2) successive
acceptance failures. If the agreement is terminated, the project
team must refund within thirty (30) days all monies paid by the
customer at that point and the customer must return all
deliverables in their possession.
2.4 Project Plan
2.4.1 Technical Description
Project Management is the art and the science of applying certain
skills, tools, techniques and knowledge to project activities in order to
meet project requirements. This is accomplished through the
integration of the project management processes of initiating,
Page 13 of 56
planning, executing, monitoring and controlling and closing. The
Team's approach to this project includes identifying requirements,
establishing clear achievable objectives, balancing the demands for
scope, cost, time and quality and adapting the plans and approach to
best meet the city's needs and concerns.
The technical approach the team intends to take is to utilize generally
accepted project management best practices and principles as defined
by the Project Management Institute (PMI). The project will follow the
processes and philosophies of PMI as described in Project Management
Body of Knowledge (PMBOK), 4th Edition.
The team will incorporate a traditional phased approach to the project;
i.e. the project will begin with the initiation phase. At that time, the
new project’s existence will be formally recognized. Also, a Project
Charter will be created and the Project Manager will be named.
Next, the development phase will be done. This phase will include
project planning. A Project Plan will be created with the help of the City
of Loganville via team interviews, etc.
The implementation phase will follow the development phase. During
this phase, the project plan will be executed, monitored and controlled.
Monitoring will require that pertinent data be routinely acquired and
analyzed so that action can be taken when progress fails to match
plans and meet objectives. Additionally, a Change Management board
will be formed to handle requests for changes related to scope,
schedule, and cost.
The final phase of the approach to the project will be the closing phase.
At that time, all outstanding contractual issues will be completed and
documented in preparation for turning over the end result to the
clients for acceptance and sign-off. The team will also request
customer input for the lessons learned document.
2.4.2 Project Schedule
Page 14 of 56
2.4.3 Project Resource Loading
Initiative Team Lead Doc. Lead Comm.
Page 15 of 56
Coordinator
Tech. Expert
Facilitator
Director of Emergency Response 1 1 Subject Matter Expert Conference 1 1 1 Emergency Response Center of Operations 1
Shelter Setup
Communication Plans 1 1
Volunteers/Training 1 1 1 Emergency Notification System 1 1 Emergency Response Test 1 1
Asbestos Abatement
Food Safety Program 1 1 1 1 Resources Scheduled 1 1 1 1Resources Available 1 1 1 1
Initiative Tech. ExpertQ.A. Analyst
Team Member
Dev. Manager
App. Manager
Director of Emergency Response Subject Matter Expert Conference 2 Emergency Response Center of Operations 4 1 1
Shelter Setup 1 1 6
Communication Plans 1 1
Volunteers/Training 1 6 Emergency Notification System 2 1 1Emergency Response Test 2 1 1
Asbestos Abatement 2 1
Food Safety Program 1 1 1 Resources Scheduled 2 1 6 1 1Resources Available 2 1 6 1 1
2.4.4 Specific Challenges
In order to maximize the probability of success there are a number of
specific project challenges that must be overcome; they are detailed
as follows:
Standup of a local emergency coordinator position: This position is
designed to manage and coordinate responses and functions as the
local Director or Commander. All information flows to and from this
Page 16 of 56
position. This is the top priority to ensuring effective
communication.
Response effectiveness: Bi-annual exercises will improve
cooperation and allow all agencies to work together to strengthen
response actions.
Complete identification of all resources available: There are local
resources which when made available will render the project
successful. Notification and education of all emergency responders
will ensure all resources are available.
Buy in of local community: Education is the only way to improve
the likelihood the community will stand by the plan. We will provide
information to the community via Television, Radio and the local
news. Additionally, town hall meetings will take place to ensure the
community has the ability to share their concerns and field
questions.
Create a Command (Emergency) Response Center: which will act as
the hub for an emergency or natural disaster in a time of need. This
is the major part of the plan and drives a successful response. The
project's main focus will be to ensure all appropriate and most
accurate data is represented in checklists and plans developed.
Representatives from the following agencies would be present and
consist of:
1. Director of Emergency Response (typically the Emergency
Coordinator)
2. Security
3. Environmental
4. Fire
5. Civil Engineering
6. Medical
7. Manpower
8. Safety
Page 17 of 56
9. Chaplain/Pastor/Preacher
10. Red Cross
11. Salvation Army
12. Communications
13. Vehicle Dispatch Perhaps Department of Transportation
(DOT)
Coordination: Coordination is extremely important. When multiple
agencies are responding to a scenario, it must be ensured that
everyone is speaking to each other effectively. Proper training will
reduce confusion and increase awareness.
Communication: Communication (internally/externally) is a must!
To ensure communication takes place routine meetings must take
place. Outside agencies are encouraged to attend. Once again,
proper training will reduce confusion and increase awareness.
Low annual cost requirements: In this small community, cost is a
major concern and utilizing resources already available will reduce
costs. Additionally, regular maintenance and repairs will increase
the longevity of resource.
Preparedness: The community has to be able to respond to
emergencies and disasters efficiently and effectively. Training will
ensure they are prepared for the situation and understand how to
act and respond accordingly and are in a position of readiness.
Continuity: The customer must ensure proper guidance is
maintained for those responding. This must try to always be done
similarly to reduce confusion and increase effectiveness. Those
managers who would run response teams and hold positions of
authority must all be trained to the same level of understanding to
reduce confusion.
Volunteers: With any emergency those who volunteer are the ones
who ensure the response is a success. There are almost no paid
Page 18 of 56
positions in this scenario. Therefore encouraging the community to
stick together and form a bond is a must. Education will improve
community awareness and proved information in case of a disaster.
2.5 Project Completion Plans
2.5.1 Deliverable Status
The follow chart details deliverable status twelve (12) weeks into the
project:
Deliverable Complete In-progress Not Yet StartedRisk Identification, Level, and Response X
Warning System and Signals X
Emergency Plan Documentation X
Disaster/Hazard Supply X
Shelters X
Communications Plan X
Community Plan X
Practicing and Maintaining Plan X
Food Safety X
2.5.2 Acceptance and Sign-Off
The criteria and requirements that the project must meet before the
Customer will accept delivery are as follows:
All deliverables and work performed are subject to Customer’s
written approval.
All deliverables and work performed will be provided in a manner
consistent with and on the dates detailed in the proposal.
During acceptance testing, the project team will make themselves
reasonably available to the customer.
During acceptance testing, if the customer determines that any
deliverable does not meet the requirements agreed upon in writing,
the customer will notify the project team in writing with specifics.
The project team has ten (10) business days to correct the
deficiencies. Then, acceptance testing will once again resume. This
Page 19 of 56
will continue until the deliverable is accepted. However, the
customer may terminate the agreement after two (2) successive
acceptance failures. If the agreement is terminated, the project
team must refund within thirty (30) days all monies paid by the
customer at that point and the customer must return all
deliverables in their possession.
Page 20 of 56
3.0 Initial Management Plan
3.1 Corporate and Project Organizational Structure
The Project Management Team consists of 15 members, each with a unique set
of skills capable of delivering high quality project outcomes to customers. Each
member is responsible for specific work which spans across the entire project
related to a specific end product or deliverable.
The Project Team members have the ability and are capable of executing
focused implementation business concepts using a high level of operational,
technical and strategic engagements. Additionally, the successful combination of
innovative spirits and business concepts offers the financial power of venture
capitalists and strategic investors.
3.2 Project Organizational Plan
3.2.1 Work Breakdown Structure (Level 3 WBS)
WBS Code Initiative
1.0 Loganville Project
1.1 Director of Emergency Response
1.1.1 Create Job Opening - Director Of Emergency Response
1.1.2 Collect Resumes
1.1.3 Conduct Interviews of Qualified Candidates
1.1.4 Hire Director of Emergency Response
1.2 Subject Matter Expert Conference
1.2.1 Identify SME to invite to Conference
1.2.2 Plan for Conference. Food/Hotels
1.2.3 Conduct Conference with SMEs
1.2.4 Collect SME Feedback.
1.2.5 Create Emergency Response Plans
1.3 Emergency Response Center of Operations
1.3.1 Hire Architect
1.3.2 Hire Real Estate Agent
1.3.3 Locate Land for Operations Center
1.3.4 Purchase Land for Operations Center
1.3.5 Design Operations Center
1.3.6 Build Operations Center
1.3.7 Emergency Leadership moved into Operations Center
1.4 Shelter Setup
1.4.1 Select Community Buildings to double as Emergency Shelters
1.4.2 Stock Shelters with Emergency Supplies
Page 21 of 56
(Medical/Food/Communication)
1.4.3 Create signage for shelters (i.e. Emergency Shelter)
1.4.4 Post Signage in front of Shelters
1.4.5Install Emergency communication (radio system) to Operations Center
1.5 Communication Plans
1.5.1 Hire Web Site Designer
1.5.2 Create Emergency Response Website
1.5.3Setup Automated Emergency Response information line (Where to go, What to do)
1.5.4 Conduct Town hall Meetings at New Operations Center.
1.5.5Radio notifications of Town hall Meetings and Emergency Response Website/Phone Line
1.5.6TV notifications of new Emergency Response Plan and Website/Phone Line
1.6 Volunteers/Training
1.6.1 Draft of Volunteer Incentive Program
1.6.2 Collect List of Volunteers
1.6.3 Train Volunteers
1.6.4 Assign Volunteers to Shelter Locations
1.7 Emergency Notification System
1.7.1 Work with TV Stations to Issue Alert Notification
1.7.2 Work with Radio Stations to Issue Alert Notification
1.7.3 Set up Alert Sirens throughout Community
1.8 Emergency Response Test
1.8.1 Select 100 Community Members (From Volunteers)
1.8.2 Trial Alert issued
1.8.3 Measurement of Emergency Response Plan Effectiveness
1.9 Asbestos abatement
1.9.1 Hire asbestos abatement firm
1.9.2 Asbestos materials removed
1.9.3 Replacement removed materials with substitute materials
1.10 Food Safety Program
1.10.1 Develop local food safety laws that parallel federal reforms
1.10.2Identify POC for linking local activities with state and federal system
3.2.2 Project Team
The Project Team is shown in the Organization Chart below:
Page 22 of 56
Page 23 of 56
4.0 Management Systems
4.1 Monitoring Cost and Schedule
4.1.1 Overview
Cost and schedule for the project is being calculated based upon
project completion up to November 9, 2009. The Earned Value Report
up to this date is given below. Due to the extended period required for
construction of the operations center, the unexpected event (asbestos)
and additional work fit into the project schedule without causing any
delays as can be seen in Section 4.1.2. (Schedule Variance = 0)
4.1.2 Earned Value Report
4.1.3/4 Major Cost and Schedule
Up to this point, much of the total project costs have already been
incurred. Of the original $735,000 proposed amount; $530,297 has
been spent. Some of the major expenditures up this point include:
Page 24 of 56
1. Purchase of Land for the new Operations Center: $50,000
2. Construction costs to date on Operations Center: $32,083
(Total $175,000).
3. Install emergency communication systems in shelters:
$75,000
4. Siren System: $100,000
5. (New) Asbestos Abatement to make largest shelter usable:
$100,000
6. (New) Food Safety Program: $10,000
4.2 Risk Management
4.2.1 Risk Management
Risk management considers risk assumptions, the roles and
responsibilities, risk rating/scoring techniques, establishes risk
thresholds, risk communication, and the development of a risk tracking
process or system.
The risk management process is adjustable to ensure the correct level,
type, and visibilities of risk management are commensurate with both
the risk and the importance of the project.
There are eight risk management levels which collectively comprise
the Risk Management Plan:
1. Risk Identification – Risks will be identified by using a risk
assessment questionnaire and include project risks and operational
risks as appropriate.
2. Categorize Risks – Once identified risks will be categorized based
on their severity and specific task or section of the project.
3. Risk Impact Assessment – For each of the risks identified, the
risk will be assess in terms of the likelihood of the risk occurring.
The results will be prioritized using established criteria.
4. Prioritize Risks – Risks will be recorded in a Risk Response Plan.
Page 25 of 56
5. Risk Response Planning – For each risk identified in the Risk
Response Plan, determine the actions to reduce the likelihood or
consequences of impact to the overall project objective,
considering cost, mitigation, and contingency planning. Assign
responsibilities, due dates, and incorporate this information into the
Risk Response Plan.
6. Risk Response Tracking – Document dates and the action taken
when the risk occurred and any subsequent additional actions.
Incorporate this information into the Risk Response Plan.
7. Risk Monitoring – Establishment of reviews scheduled into the
project schedule including risk response tracking and
communication to ensure:
All the requirements of the plan are being implemented
Assess defined risks
Evaluate effectiveness of actions taken
Status of actions to be taken
Validate likelihood and impact
Validate previous assumptions
Identify new assumptions
8. Controlling Risks
Validate mitigation strategies and alternative actions
Take corrective actions when events occur
Assess the impact on the project (Cost, Time, Resources)
Identify new risks
Ensure the project plan is maintained
Ensure change control addresses risks associated with the
proposed change
Revise the Risk Response Plan
Communication
4.2.2 Risk Inventory and Contingencies
Page 26 of 56
The following chart outlines the risks associated with this specific
project and the plan of action to reduce or eliminate those risks:
Risks Likelihood Impact Contingency PlanFinancial Obligation Low High $735,000 has been set aside
for this project. Budgeting for shortfalls / maintenance may
be necessaryCommunication
BreakdownLow High Regularly scheduled
meetings will reduce breakdowns
Community Acceptance
Moderate Moderate Promote and educate the community on the
importance of this project via town hall meetings and
advertisingLogistics Moderate High Continual coordination and
maintenance of resources. Additionally, planning and
training are keyTechnical Support Low Moderate Seek assistance from
Emergency Managers from nearby cities
Coordination Low Moderate Notifications and communication requirements through training will reduce
thisResource
Availability (Personnel)
Moderate Moderate Create a large list of city employees assigned to
positionsChecklist Accuracy Low Moderate Checklists continually evolve.
Conduct annual reviews to ensure most current
informationContingency
PlanningLow Moderate Train using exercise
scenarios. This allows the identification of shortfalls and
operational problemsLiabilities (Risk Management)
Moderate Low Ensuring all parties are insured and documents are in place to protect the citizens
and the communityLong Term RisksLack of Equipment Low High Allocate monies over time
within the budget to acquire necessary equipment
Lack of Training Low Moderate Initial and continual contingency training will ensure responder and community readiness
Mobilization (timeliness)
Moderate High A checklist will be developed to outline specific mobilization needs
Activation Deficiencies
Low Moderate Within the checklists, activation notifications will be
step oneLack of Roles and Low Moderate Training and checklist will
Page 27 of 56
Responsibilities provide responders with knowledge of the Command Response Center (CRC) and will be trained to manage all
aspects of a responseConfusion in Long
Term Planning (post response)
Low Low Following emergencies create an after action reports and utilize available technical resources. For instance the
EPA is a free phone callOperations Control Low Moderate Teach to maintain open
channel of communication
4.2.3 Risk Ranking and Re-Evaluation Procedures
The Project Risk Management Plan will help alleviate any confusion on
ranking risks. It outlines specific procedures on the process or ranking
them. Each risk is unique and presents specific hazards or concerns
with the overall project and in some cases must be evaluated
independently.
Re-evaluation procedures are also covered in the Risk Management
Plan under controlling risks. Using the Risk Management Plan will
reduce any likelihood of future risks or the reassurance of previously
identified risks.
4.2.4 Risk Escalation Procedures
As stated above, Risks will be identified using a risk assessment
questionnaire and include project risks and operational risks as
appropriate. These risks cannot always be identified via this process.
Identification of additional unnoticed or unforeseen risks throughout
the project is done through personal identification. These risks will be
added to the Risk Management Plan and will also be channeled up the
chain of command for review. A Quality Assurance Representative will
evaluate each risk personally and outline procedures to eliminate or
reduce the given risk. These specific risks will be tracked as all other
risks are tracked, which is through the Risk Management Plan.
Escalation is important to the success of mitigating risks. The sooner
they are escalated, the greater chance of eliminating the risk.
4.3 Project Communications Management
Page 28 of 56
As indicated in the Terms and Conditions of the Proposal, all communications
related to the project are to be directed to the Project Leader, Tom Menning. In
the event that communication with the project leader is not possible, only the
new Director of Emergency Response will have the authority to make decisions
that directly change the original scope of the project plan. In the event this
occurs, the city of Loganville will pay any costs incurred over and above any
costs already outlined in this audit. Regular communications from the project
team will (and currently) are available to the City of Loganville for the purpose of
project status clarity. These communications include:
1. Project Gantt chart updated as progress is made. An updated Gantt chart
is attached to this audit.
2. Earned Value Table: A table that tracks project performance related to the
original budget. An updated table is included in section 4.1.2.
3. Monthly Meetings: A monthly status update meeting is held every month
with the project leader as well as any interested parties. These meetings
are currently being held in City Hall.
4.4 Environmental, Worker Safety and Health
The Project's ultimate goal is to reduce occupational safety and health
mishaps through education and avoidance.
4.4.1 Environmental
Maintaining or preserving the environment is extremely important and
must be considered at all times with one exception - if harming the
environment means saving a life! Once environmental accidents occur,
it is difficult, or even impossible in some cases, to reverse the long
term effects. When the work is performed for the project, even during
responses it is important to be coherent of the environment and
ensure we maintain or preserving land, air, and water.
During emergencies there is a high likelihood that environmental
catastrophes will occur and cause emergency responders to respond
differently according to the scenario. Most natural disasters are going
to increase the chances of an environmental disaster occurring.
Page 29 of 56
Understanding those risks and knowing how to reduce them while
removing oneself from the given hazard is an important part of the
responder's role.
Post emergencies create a unique concern in relation to environmental
hazards. While responding, it is important to ensure that the project's
footprint on the environment is reduced. However, post emergencies
are equally important as we have a responsibility as a society and as a
community to return the area as close to its original state as possible.
Most environmental problems associated with disasters are
unpreventable. However, we have the ability to reduce or minimize
additional stress on the environmental.
Environmental Engineers offer a great wealth of knowledge during
responses. Their expertise and background provides them the ability to
make decisions reducing the environmental effects created by
disasters. Utilizing this knowledge in their efforts can be an enormous
asset to the future of the community.
4.4.2 Worker Safety
During contingency operations worker safety is most important! As
part of any emergency response a local safety manager will be part of
the response both on the ground and in the command and control
center. This will allow for maximum safety of the personnel responding.
If at any time responders are put in harm’s way and would risk injuring
themselves and causing additional casualties the safety manager has
the right to stop the response and ensure all precautions are being
taken or eliminate that part of the response all together. They have the
authority to halt all personnel from entering a certain area and
ensuring responders enter only areas deemed safe.
Prior to any response proper training would be conducted utilizing the
safety manager to properly training all responders on local procedures
and notification instructions. This will help reduce the likelihood of
additional casualties and increase mission successfulness.
Page 30 of 56
At the end of the day if the responders become casualties themselves,
the project has failed its emergency responders.
4.4.3 Occupational Health
The occupational health of emergency responders will be evaluated on
a case by case basis. Each officially designated responder will be asked
to provide baseline blood work and perform occupational health
studies. This information will be maintained at the local hospital and
will be updated on a biannual basis. The rationale behind the baseline
studies is so in the event of an emergency post blood work and
evaluations can be conducted to verify personal exposures to
hazardous chemicals and agents during a response. This information
along with potential sampling results at the scene will allow medical
personnel to properly treat responders and will give the city and its
responders a legal stance in an unfortunate event.
Continual education and training along with the proper Personal
Protective Equipment (PPE) will allow responders to reduce the
likelihood of exposure and improve responder confidence in procedure
and actions taken. The training must be an annual occurrence to
improve responder knowledge and awareness. This training will allow
responders to see what hazards are potentially present and providing
recommendations for reducing their exposures. The PPE training is
important and must be maintained properly to ensure personnel
understand the use of specific PPE for specific situations. For instance
Nitrile gloves can be used to offer superior resistance too many types
of chemicals, whereas Butyl Rubber gloves provide superior resistance
to highly corrosive acids and are excellent for handling keytone and
esters. Butyl rubber gloves also provide the highest permeation
resistance to gases and vapors. Understanding this information and
responding correctly reduces the risk of occupational health injuries.
Page 31 of 56
5.0 Cost Working Plan
5.1 Project Cost
This section will discuss the various costs involved in the project for project cost
clarity. The purpose of this section is to itemize all costs so the customer may
have the ability to customize their cost where possible.
5.1.1 Total Project Cost
The total project proposal was originally offered at a price of $735,000.
Due to additional costs incurred by unexpected events/work, the total
project costs are now $870,000. Terms and Conditions for payment
are described in later sections of this document.
5.1.2 Breakdown of Project Costs
A breakdown of project costs is provided for cost clarity in the event
the customer wishes to alter the cost structure if possible by
adding/subtracting pieces of the proposal. The project consists of 8
major milestones as well as a 9th unexpected event all with varying
costs. These milestones are outlined in order below along with their
corresponding costs.
1. Hire Director of Emergency Response: $50,000/Year. Complete
This is a re-occurring salaried position which is deemed a
necessary. The most successful processes have process
champions therefore successful implementation and continuity is
dependent upon maintaining a process champion. The salary is
estimated using freely available salary databases of persons with
similar title and responsibilities.
2. Subject Matter Expert Conference: $7,500. Complete
This is a onetime project expense deemed necessary to formulate
the best possible Emergency Action Plans to be utilized by the
Shelter Network. At times of crisis; its highly possible
communication plans will be cut between a Shelter and the
Operations Center necessitating Emergency Action Plans to guide
Shelter leaders of appropriate actions during times of lost
communication. The $7,500 cost essentially pays lodging and
Page 32 of 56
travel expenses incurred by Subject Matter Experts. It also pays for
a modest conference style forum with food and beverage provided.
3. Emergency Response Center of Operations: $245,000 (Approx
40% Complete)
a. This is a onetime project expense which is deemed optional
however highly recommended by the project team. Times
of crisis call for clear leadership and the construction of a
new Operations Center accomplishes this. It would also
increase communication efficiencies across the already
established emergency response teams in Loganville by
centrally locating the heads of those functional areas all in
one place. These costs are estimates based on previously
constructed Operations Centers in other communities
nearby Loganville. The breakdown of these costs are as
follows:
i. Hire Architect: $10,000
ii. Hire Real Estate Agent: $5,000
iii. Purchase of Land for Operations Center: $50,000
iv. Construction of Operations Center: $175,000
v. Moving Expense: $5,000
b. All but $5,000 of the above expense could be avoided by
designating an existing town building to service this need.
The moving expense would still remain since functional
heads should still move into this existing building. Also, by
utilizing an existing town building, as much as 60 days may
be cut out of the total project duration. Possible Optional
Savings: $240,000. Savings not adopted.
4. Setup of Shelter Network. Complete
This is mostly a one time necessary expense with the exception of
emergency supplies. The Shelter Network will consists of several
pre-existing buildings spread throughout the community which will
act as “safe zones” for community members. Since not all
Page 33 of 56
community members can fit within the Operations Center, the
Shelter Network is of extreme importance. The breakdown of costs
are as follows:
i. Stock shelters with emergency supplied: $50,000
Yearly replenishment costs of $10,000 will apply
ii. Signage to indicate shelter location: $1,500
iii. Emergency Communication Radio Systems: $75,000
5. Communication Plans. ( Approx 40% Complete)
a. These costs relate mostly to the communication process of
the new Emergency Response System. Most of the cost will
be upfront “marketing” type cost which are deemed
necessary by the project team. If community members are
not aware of the new Emergency Response System, it
ceases to have any value. Communications will be made in
all media types.
i. Create Website: $7,500
ii. Automated Emergency Response Telephone Hotline:
$5,000
iii. Townhall Meetings: $10,000
iv. Radio Notifications: $2,000
v. TV Notifications: $4,000
b. The website, automated telephone hotline, radio, and TV
notifications are considered necessary. The town hall
meetings are optional but suggested since many people will
appreciate the person approach which more easily
facilitates 2 sides question and answers. Possible
Optional Savings: $10,000 – Savings not adopted.
6. Volunteer Selection/Training. Complete
These costs are re-occurring yearly since the project team believes
volunteers will require certain incentives in order to volunteer. The
Page 34 of 56
project team suggest yearly tax breaks given to volunteers for
service.
i. Volunteer incentive program: $10,000/Year.
ii. Volunteer Training: $0 to be facilitated by Director of
Emergency Response and existing Loganville emergency
response teams (Police, Fire Dept, Etc).
7. Emergency Notification System. Complete
These costs are a necessary onetime expense. All the advertising
in the world will not inform a bystander on the street of an
impending emergency.
Setup Emergency Sirens throughout the community: $100,000
8. Emergency Response Test. Incomplete
This will accomplished at no cost since all preceding costs are
necessary to accomplish this step.
9. Asbestos Abatement (Unexpected Event). Complete Next Week.
The removal of asbestos from the primary shelter in the shelter
network will occur concurrently with the construction of the new
operations center. The complete removal of asbestos cost
$125,000; this was not part of the original proposal.
10. Food Safety Program. Complete.
The Department of Homeland Security offered a grant of $350,000
annually to create a food safety program. The complete cost was
$10,000; this was not part of the original proposal.
The final cost of the project proposal consists of the Project Premium to
deliver the project. This cost essentially covers the projects teams’
cost to deliver the proposal over 8 months as well as a reasonable
return. Total Project Premium: $167,500.
Total Project Cost: $870,000
Page 35 of 56
5.1.3 Progress Payments
Proposed payments are to follow progress of the rollout of the new
Emergency Response Plan. Proposed payments are as follows:
1. Upon Project Initiation – 20% - Paid
2. Upon Completion of SME Conference – 20% - Paid
3. Upon Completion of Shelter Network Setup – 20% - Paid
4. Upon Completion of Emergency Notification System – 20% -
Paid
5. Upon Completion of successful Emergency Response Test – 20%
- Not Paid
6. Upon Completion of Asbestos Abatement - $125,000. – Not Paid
5.2 Customer-Provided Resources
The customer will make available existing emergency response personnel as
well as town leadership to provide support for volunteer training as well as
communication plans necessary to socialize the existence of the new
Emergency Response Plan. Primary examples include (but are not limited to):
1. Police Department
2. Fire Department
3. Loganville Mayor
The newly hired Director of Emergency Response will work and utilize
necessary town resources which includes essentially any person whom is
directly compensated by the city of Loganville. In order to ensure
cooperation, the project team recommends dotted line reporting to the
Director of Emergency Response in all things related to the new Emergency
Response system.
5.3 Terms and Conditions
Limits
The delivery date of proposal is given as 8/9/09 with proposal expiration 60
days thereafter, or 10/9/09. After 10/9/09, the proposal will no longer be
valid. Upon acceptance of the proposal, Project Initiation will commence 7
Page 36 of 56
days later which is also the same time the customer must pay the first
progress payment of 20%. The project initiation date will mark the beginning
of the project schedule and will be communicated to the customer by the
project team upon acceptance of the proposal.
Contact
All inquiries both before and during (should the proposal be accepted)
concerning the proposal should be directed to Tom Menning; Project Team
Lead.
Completion Metric
A successful implementation of the Emergency Response plan will be
determined by the following criteria:
1. Milestones 1-7 outlined above in section 4.1.2 Breakdown of Project
Costs are completed.
2. 50% Success Rate of test subjects in milestone 8; Emergency
Response Test. A success rate is defined simply as whether or not
a test subject responds to the emergency test by going to the
correct shelter in the shelter network.
Customer Default of Payments
In the event the city of Loganville does not make payment within two weeks of
a scheduled progress payment, the project team reserves the right to cancel
the remainder of the proposal and require an additional 20% surcharge of
whatever monies are yet unpaid. If such problems are foreseen by the
customer, excess communication is requested by the project team in order to
avoid such measures by adding additional flexibility by both the customer and
the project team. If customer remains in default, the project team will pursue
other necessary modes of collection to be paid by the customer with the
primary mode of collection including civil court with all fees (including
attorney and court) to be covered by the customer.
Project Extension
In the event the project extends beyond its original timeline, an additional
payment equal to one tenth of the total project costs will be due on the first of
Page 37 of 56
each additional month. As an example, If total projects costs equal $735,000,
a payment of $73,500 will become due on the first day of each month beyond
the original timeline. This is done only to provide cost coverage for the
project team during unplanned work time. The one tenth payment does not
provide the project team with any premium payment whatsoever so incentive
to complete at or ahead of schedule is still high. Note: Unexpected Event did
not increase the project duration therefore there will not be any necessary
extended cost coverage.
Page 38 of 56
6.0 Unexpected Event
6.1 Problem Description and Current Status
The largest of the buildings slotted to be used as a shelter turns out to contain
asbestos and must be decontaminated before the plan can be implemented.
There are no alternative buildings, so the costs and time required to carry out
the decontamination, has been added to the overall cost. The City of Loganville
understands that it will bear these additional costs and we have revised the
project to reflect the impact of this event.
6.2 Alternative Solutions & Evaluation
With no other buildings available, the removal of the Asbestos Containing
Material (ACM) is the only solution. After an extensive asbestos survey of the
building, it was deemed to contain 300 linier feet of amphibole Thermal System
Insulation (TSI). TSI is asbestos found as insulation on boilers, water and steam
pipes elbows, fittings, and pipe runs. Additionally, miscellaneous material was
found throughout the main level of the building. Miscellaneous material is all
material containing asbestos, which is not classified as sprayed/troweled-on
material or in the TSI classes. In this case the miscellaneous material was found
to be chrysotile floor tile. Roughly half of the asbestos was found in a friable
state, which means the material can be crushed or crumbled by hand. This
required the removal of the asbestos as opposed to covering or working with it in
place.
As an important notice, the city of Loganville is responsible for the removal of
the contaminated waste generated from the removal process. This removal
would be contracted out to ensure it is being handled properly, but we want to
stress the importance of this process. ACM can only be taken to approved
landfills and is heavily scrutinized by the Environmental Protection Agency (EPA).
6.3 Proposed Action
The actions we propose are to hire an asbestos team certified to conduct the
removal of ACM in the State of South Carolina. We propose creating a bid for the
work to be completed and putting it on the market short notice and for only a
period of 30 days. We would notify all known certified contractors to review the
bid and provide feedback in the form of a formal bid to this office for the final
selection process for this work. In the statement of work the removal of ACM
would need to start within 30 days of the formal notification of the contractor
Page 39 of 56
selected. This will allow the project to continue on schedule and result in no loss
of time to the overall project timeline. The anticipated time frame for this work to
be completed is roughly 4 weeks. This would allow time for the preparation, the
removal process and the air sampling to be completed. The turnaround time of
the air sampling results is expected to be roughly 1 week.
Throughout the removal process we would hire an independent contractor,
preferably a Certified Industrial Hygienist, to conduct quality control of this
section of the project. The Industrial Hygienist would also conduct the final
clearance air sampling, send the samples to a certified laboratory and publish a
letter outlining the results of the air sampling. This would provide the City of
Loganville a certified document validating the removal was completed according
to Occupational Safety and Health Administration, published standards and the
air sampling results are below the permissible or occupational exposure limit
(PEL/OEL).
Once clearance sampling is completed and results indicate the removal of the
ACM was successful the renovation of the building could begin. The renovation
would include all predetermined design mortifications to improve the working
space of the building to fit the needs desired during an emergency response. The
focal point of the building would include the shelter and its need to hold the
maximum number of people safely. Additionally, as determined in the
preliminary plan, we would like to see this building be used as the Emergency
Response Center. Modification to improve the building for that use could also be
determined at that time.
Page 40 of 56
7.0 Added Work
7.1 Project Description
An additional task was added to the project shortly after the proposal was
accepted in August, 2009. It was started as soon as possible.
It was brought to the team's attention that the Department of Homeland Security
will provide funding for a special program to promote food safety. This program
permits municipalities to apply for a grant to introduce a proactive food product
safety program for all foods sold locally. This program will cover all food products
sold within the city limits; i.e. groceries for personal use, restaurants, schools,
and hospitals. The Department of Homeland Security will give the City of
Loganville - upon approval - up to $350,000 each year that this program is in
place.
The project team needs to do the following as needed so that the work fits
sensibly into the master project schedule:
1. Create a preliminary plan for the added work.
2. Create a preliminary budget for the added work.
3. Adjust the overall project schedule.
4. Adjust the project resource allocations.
The additional task was approved via the established project change control
process on Friday, August 21, 2009. The Personal Assistant of the Mayor of the
City of Loganville applied for the funds from the Department of Homeland
Security on August 21. Filing for the funds is considered part of her regular
duties, thus incurring no additional cost to the project for her time. Also, there
was no filing fee. The application process took approximately 10 weeks. On
November 9, 2009, the City of Loganville received a grant of $350,000 from DHS
to cover costs for a food safety program.
7.2 Initial Planning
The first topic to consider when planning this task is to list what exactly needs to
be done by this project team and how it fits into the scope of the project. Also,
an implementation plan for the City of Loganville is needed that will describe the
Page 41 of 56
processes the city will need to manage that are out of scope for the Emergency
Recovery Plan project.
Then, it needs to be determined how this addition to the project will fit into the
master project schedule. At first glance, it appears that this task can easily run
parallel to the existing schedule.
Last, analysis needs to be done to determine if there are any additional costs
and resource needs. However, resource allocations need to be made and if there
are any extra resources that need to be added to the project.
7.3 Scope
The scope of this task as it relates to the project is rather limited. This program
will permit municipalities to apply for a grant to introduce a proactive food
product safety program for all foods sold locally. This program will cover all food
products sold within the city limits; i.e. groceries for personal use, restaurants,
and schools. It will not impact WBS item 1.4.2. Stock Shelters with
Emergency Supplies (Medical/Food/Communication) for this year since the
supplies have already been purchased. However, subsequent purchases will be
covered by the program that occur after the DHS funding was received on
November 9, 2009.
This program does not cover vending machines and food purchased prior to
receiving funds from the Department of Homeland Security. Also, it is entirely
out of scope to discuss aspects of this program that do not relate to the
Emergency Response Plan that the team has been hired to create. This would
include every day safety concerns when an emergency does not exist and
prevention of food safety emergencies from occurring.
Several items do fall into scope for the Emergency Response Plan project:
1. Apply for funds from the Department of Homeland Security. - Completed
on August 21, 2009; Received approval on November 9, 2009
2. Provide a list of recommendations for local food safety laws that parallel
federal reforms. This would include encouraging the city to meet with
Page 42 of 56
local grocers, food suppliers, and restaurant owners to find ways to avoid
additional costs during times of crisis.
3. Identify a point of contact for linking local activities with state and federal
system.
7.4 Schedule
The addition of the task will not cause a conflict with any of the items currently
listed in the Work Breakdown Structure.
Here is the additional items added to the Work Breakdown Structure for the food
safety program:
1.10 Food Safety Program
1.10.1Provide a list of recommendations for local food safety laws that parallel federal reforms
1.10.2Identify POC for linking local activities with state and federal system
1.10.1 - Provide a list of recommendations for local food safety laws
that parallel federal reforms.
Start Date: August 21, 2009
End Date: September 10, 2009 - On time
The team met with local officials, grocers, food suppliers, and restaurant owners
to find ways to avoid additional costs during times of crisis. Then, a list of
recommendations was given to the City Council. It was then up to the City
Council to write and pass those laws. The local food safety laws are contingent
on being approved by DHS to receive the funds. Also, the laws will not go into
effect until the funds are received. Additionally, the team encourages the City
Council to determine what actions will be taken to prevent food safety
emergencies from occurring - which is out of scope for this project.
On time completion of this task was mandatory. It ran parallel to a huge
emergency response plan open house public relations event held by the city on
September 11, 2009. It was open to all members of the community. The new
food safety laws were also introduced within the City Council on September 11
and passed on September 18.
Page 43 of 56
1.10.2 - Identify POC for linking local activities with state and federal
system
Start Date: July 1, 2009
End Date: July 31, 2009
The team began to process of identifying the point of contact to work with state
and federal officials concerning food and other supplies. On July 31, the team
selected Thomas Rampley to head up that portion of the project contingent upon
acceptance of the proposal.
7.5 Budget
The addition of the task cost the project an additional $10,000. This cost will be
refunded to the City of Loganville by the Department of Homeland Security.
Again, here is the additional items added to the Work Breakdown Structure for
the food safety program:
1.10 Food Safety Program
1.10.1Provide a list of recommendations for local food safety laws that parallel federal reforms
1.10.2Identify POC for linking local activities with state and federal system
1.10.1 - Provide a list of recommendations for local food safety laws that
parallel federal reforms.
The team met with local officials, grocers, food suppliers, and restaurant owners to
find ways to avoid additional costs during times of crisis. Then, a list of
recommendations was given to the City Council. It was then up to the City Council to
write and pass those laws. This process ended with a huge emergency response plan
open house public relations event held by the city on September 11, 2009. It was
open to all members of the community.
The cost of lobbying city officials, holding meetings, and the final September 11
event totalled $10,000.
1.10.2 - Identify POC for linking local activities with state and federal
system
Page 44 of 56
Start Date: July 1, 2009
End Date: July 31, 2009
The team began the process of identifying the point of contact to work with state and
federal officials concerning food and other supplies while creating the Preliminary
Plan. On July 31, the team selected Thomas Rampley to head up that portion of the
project contingent upon acceptance of the proposal. Since Mr Rampley is a member
of the team, no additional costs were incurred.
Page 45 of 56
Appendix A: List of Figures
Page 46 of 56
Figure 1 Gantt Chart
Page 47 of 56
Page 48 of 56
Figure 2 Organization Chart for Customer
Page 49 of 56
Mayor
Fire Chief Police Chief Director of Emergency Response
Food Safety Liaison
Community Liaison
Lieutenant Lieutenant
SGT SGT
LieutenantLieutenant
SGTSGTSGT SGT SGTSGT
City of Loganville Emergency Response
Org ChartAppendix A: Figure 3
Figure 3 Work Breakdown Structure (Level 3)
WBS Code Initiative
1.0 Loganville Project
1.1 Director of Emergency Response
1.1.1 Create Job Opening - Director Of Emergency Response
1.1.2 Collect Resumes
1.1.3 Conduct Interviews of Qualified Candidates
1.1.4 Hire Director of Emergency Response
1.2 Subject Matter Expert Conference
1.2.1 Identify SME to invite to Conference
1.2.2 Plan for Conference. Food/Hotels
1.2.3 Conduct Conference with SMEs
1.2.4 Collect SME Feedback.
1.2.5 Create Emergency Response Plans
1.3 Emergency Response Center of Operations
1.3.1 Hire Architect
1.3.2 Hire Real Estate Agent
1.3.3 Locate Land for Operations Center
1.3.4 Purchase Land for Operations Center
1.3.5 Design Operations Center
1.3.6 Build Operations Center
1.3.7 Emergency Leadership moved into Operations Center
1.4 Shelter Setup
1.4.1 Select Community Buildings to double as Emergency Shelters
1.4.2Stock Shelters with Emergency Supplies (Medical/Food/Communication)
1.4.3 Create signage for shelters (i.e. Emergency Shelter)
1.4.4 Post Signage in front of Shelters
1.4.5Install Emergency communication (radio system) to Operations Center
1.5 Communication Plans
1.5.1 Hire Web Site Designer
1.5.2 Create Emergency Response Website
1.5.3Setup Automated Emergency Response information line (Where to go, What to do)
1.5.4 Conduct Town hall Meetings at New Operations Center.
1.5.5Radio notifications of Town hall Meetings and Emergency Response Website/Phone Line
1.5.6TV notifications of new Emergency Response Plan and Website/Phone Line
1.6 Volunteers/Training
1.6.1 Draft of Volunteer Incentive Program
1.6.2 Collect List of Volunteers
1.6.3 Train Volunteers
Page 50 of 56
1.6.4 Assign Volunteers to Shelter Locations
1.7 Emergency Notification System
1.7.1 Work with TV Stations to Issue Alert Notification
1.7.2 Work with Radio Stations to Issue Alert Notification
1.7.3 Set up Alert Sirens throughout Community
1.8 Emergency Response Test
1.8.1 Select 100 Community Members (From Volunteers)
1.8.2 Trial Alert issued
1.8.3 Measurement of Emergency Response Plan Effectiveness
1.9 Asbestos abatement
1.9.1 Hire asbestos abatement firm
1.9.2 Asbestos materials removed
1.9.3 Replacement removed materials with substitute materials
1.10 Food Safety Program
1.10.1 Apply for Department of Homeland Security Funds.
1.10.2 Develop local food safety laws that parallel federal reforms
1.10.3Identify POC for linking local activities with state and federal system
Page 51 of 56
Figure 4 Organization Chart for Project
Page 52 of 56
Appendix B: List of Tables
Page 53 of 56
Table 1 Acceptance Criteria
Deliverable Criteria Standard
Hazard Identification, Risk Level, and Risk Response
Plan
Identify all potential hazards along with an assessment that rates the likelihood, impact and a course of action
for each.
For hazards identified as being high risk, the scope of work calls for the creation of a full documented risk mitigation plan detailing
methods meant to lower the impact or reduce the risk of each hazard. For hazards identified as being medium risk, the scope of work calls for the development of a risk mitigation plan
for each hazard - but to a lesser degree of detail than that of the high risk hazards. For
hazards identified as being low risk, the scope of work calls for a simple statement
explaining the best way to mitigate the risk of each hazard.
Warning System and
Signals
Provide for the initial warning of the
community and local public officials of the
existence of a hazard.
A tiered system where the higher risk hazards have higher priority in the communication
plan.
Emergency Plan Documentation
This deliverable requires that the plan provide
local officials with easily understood
documentation to aid them in implementing
the emergency response plans.
These documents (checklists) are to be accessible to local officials online for review. The scope calls specifically for the following:
updated area maps, escape routes, communications plans, shutting off utilities, handling those with special needs, handling
animals, basic safety skills.
Disaster/ Hazard Supply
Educating the general public and local officials
concerning how to prepare themselves for hazards and provide for their own basic needs for a period of several
days.
Basic needs are defined as water, food, first aid, clothing and blankets.
Shelters Identify several community buildings to be used as mass care
shelters. Address a method for the stockpiling and
dispensing of basic supplies at each shelter.
Specifically: Water, food, first-aid, sanitary facilities, security.
Page 54 of 56
Communications Plan
Develop and test method local officials
are to use to communicate with one
another during a disaster. Develop means
of informing the community at large of
actions to take during a disaster.
Direct community to website with further instructions.
Community Plan
Create group of community volunteers
that will report to a designated city official.
This group and their city official will create a community emergency response plan for
small business owners.
Practicing and Maintaining
Plan
Create a process for practicing the
emergency response plan for each disaster
scenario. Also, create a process for maintaining
and updating the emergency response
plan.
The practicing/testing process should be created such that emergency communications
methods and equipment are tested for functionality. The maintaining and updating
process should be created such that changes are communicated to the appropriate parties.
Asbestos Abatement
Provide for the abatement of asbestos contamination at the
largest of the buildings identified to be used as
a shelter.
Remove contaminates, replace with appropriate materials.
Food Safety Program
Develop a proactive food product safety program for all food items sold
locally.
Utilizing a federal grant we will develop a proactive food product safety program that
links local food safety activities with state and federal efforts and parallels federal reforms.
Table 2 Breakdown of Total Project Cost
Milestone Description Cost Emergency Response Initiative $702,500.00 1 Director of Emergency Response $50,000.00 Create Job Opening - Director Of Emergency Response $0.00 Collect Resumes $0.00 Conduct Interviews of Qualified Candidates $0.00 Hire Director of Emergency Response $50,000.00 2 Subject Matter Expert Conference $7,500.00 Indentify SME to invite to Conference $0.00 Plan for Conference. Food/Hotels $0.00 Conduct Conference with SMEs $7,500.00
Page 55 of 56
Collect SME Feedback. $0.00 Create Emergency Response Plans $0.00 Complete SME Conference $0.00 3 Emergency Response Center of Operations $245,000.00 Hire Architect $10,000.00 Hire Real Estate Agent $5,000.00 Locate Land for Operations Center $0.00 Purchase Land for Operations Center $50,000.00 Design Operations Center $0.00 Build Operations Center $175,000.00 Emergency Leadership moved into Operations Center $5,000.00 Complete New Operations Center $0.00 4 Shelter Setup $126,500.00 Select Community Buildings to double as Emergency Shelters $0.00 Stock Shelters with Emergency Supplies (Medical/Food/Communication) $50,000.00 Create signage for shelters (ie. Emergency Shelter) $1,500.00 Post Signage in front of Shelters $0.00 Install Emergency communication (radio system) to Operations Center $75,000.00 Complete Shelter Setup $0.00 5 Communication Plans $28,500.00 Hire Web Site Designer $7,500.00 Create Emergency Response Website $0.00
Setup Automated Emergency Response information line (Where to go, What to do) $5,000.00
Conduct Townhall Meetings at New Operations Center. $10,000.00
Radio notifications of Townhall Meetings and Emergency Response Website/Phone Line $2,000.00
TV notifications of new Emergency Response Plan and Website/Phone Line $4,000.00 Complete Communication Plans $0.00 6 Volunteers/Training $10,000.00 Draft of Volunteer Incentive Program $10,000.00 Collect List of Volunteers $0.00 Train Volunteers $0.00 Assign Volunteers to Shelter Locations $0.00 Complete Volunteer Gathering $0.00 7 Emergency Notification System $100,000.00 Work with TV Stations to Issue Alert Notification $0.00 Work with Radio Stations to Issue Alert Notification $0.00 Set up Alert Sirens throughout Community $100,000.00 Complete Emergency Notification System $0.00 8 Emergency Response Test $0.00 Select 100 Community Members (From Volunteers) $0.00 Trial Alert issued $0.00 Measurement of Emergency Response Plan Effectiveness $0.00 9 Asbestos Abatement $125,000.00 Hire Asbestos abatement firm $100,000.00 Asbestos Material Removed $0.00 Replace Removed Materials $25,000.00
10 Food Safety Program $10,000.00 Develop local Food Safety Laws $10,000.00 Identify POC $0.00