  • 7/27/2019 TE040 PO Plan to Replenish

    1/23

    Plan to Replenish

    Flow Script

    12.0 GB PH v3.0

    This document provides step-by-step instruction coinciding with the Plan to Replenish business flow. It

    may be useful for validation of this specific transaction; therefore the steps should not be modified.

    Copyright 2005, 2007, Oracle. All rights reserved

    Business Scenarios Test Sequences

    Tests Test Name Tester1

    Tester2

    Tester3

    Date Notes

    00 Prerequisite Steps10 Establish Inventory

    Planning Policies(PF1960)

    20 Manage InventoryPlanning (PF0033)

    30 Manage InventoryPlanning (PF0033)

    40 Generate Requisitions(MM0912)

  • 7/27/2019 TE040 PO Plan to Replenish

    2/23

    Testing Notes

    SummaryThis flow script provides the steps for inventory planning.

    Assumptions

    It is assumed that the on hand quantity of the Item RUBMNT is below the minimum level of planning at

    subinventory Stores.

    It is assumed there is no open purchase order exists for the item RUBMNT.

  • 7/27/2019 TE040 PO Plan to Replenish

    3/23

    00 Test Specification Prerequisite Steps

  • 7/27/2019 TE040 PO Plan to Replenish

    4/23

    BusinessProcess:Open Current

    Period

    Business Flow:Pre-requisite steps for Plan to Replenish

    Summary Process:

    Event: Description: Open current period in Purchasing, Inventory, General Ledger

    Step #

    ProcessStep

    Description

    Path and Action Input Data Expected Result Actual Results

    00.01

    Logon to ApplicationSelect the appropriateresponsibility.

    ENGINEERING/welcomeOU100_PurchasingSuper User

    Purchasing SuperUser Navigatordisplays

    00.02

    VerifyCurrentPurchasingPeriod is

    Open

    (N) Setup > Financials >Accounting > Control PurchasingPeriods

    00.03

    Search the current period (theperiod that contains todays date).Verify the Status.If current period is not Open, openperiod by selecting Open fromPeriod Status LOV.

    Current PeriodStatus shouldOpen

    00.04

    VerifyCurrent

    Click on Home.Switch Responsibility.

    Inventory

  • 7/27/2019 TE040 PO Plan to Replenish

    5/23

    InventoryPeriod isOpen

    Select the appropriateresponsibility.

    00.05

    (N) Accounting Close Cycle >Inventory Accounting Periods

    Scroll down to the current period(the period that contains todaysdate).Verify the Status.If period is not opened, click on therow for the current period. Click onthe Change Status buttonClick (B) OK to the caution note.

    Org = 101

    Current PeriodStatus shouldOpen

    00.06

    VerifyGeneralLedgerperiod isopen

    File > Close formSwitch responsiblity(N) Setup > Open/Close

    Click: FindVerify / Change the Status for thecurrent period to Open

    PL100_GeneralLedger Super UserLedger: PL100Status: AnyPeriod:

  • 7/27/2019 TE040 PO Plan to Replenish

    6/23

    BusinessProcess:Check On-hand

    quantity

    Business Flow:Pre-requisite steps for Plan to Replenish

    Summary Process:

    Event: Description: Check on-hand quantity of min-max planned item.

    Step #

    ProcessStepDescription

    Path and Action Input Data Expected Result Actual Results

    01.01

    ChooseResponsibility

    Switch to appropriate responsibility. Inventory

    01.02

    Verify on-handquantity foritem

    (N) On-hand Availability > On-handQuantity

    Click (B) Find

    Ensure the on hand quantity of theItem RUBMNT is below theminimum level of planning, i.e 50nos.Otherwise perform a miscellaneoustransaction to bring the on handavailability below this minimumlevel of planning.

    Org = 101Item = RUBMNTSubinventory =Stores

    01. Log out Log out of Application

  • 7/27/2019 TE040 PO Plan to Replenish

    7/23

    03

  • 7/27/2019 TE040 PO Plan to Replenish

    8/23

    BusinessProcess:Create Blanket

    PurchaseAgreement

    Business Flow:Pre-requisite steps for Plan to Replenish

    Summary Process:

    Event: Description: Create Blanket Purchase Agreement for Re-order Point Planned and Min-max planneditem

    Ste

    p #

    Process

    StepDescription

    Path and Action Input Data Expected Result Actual Results

    02.01

    Login toapplication

    Login to Oracle E-Business Suite

    Select the appropriateresponsibility.

    User=PROCUREMENTPassword=welcomeOU100_PurchasingSuper User

    OU100_PurchasingSuper UserNavigator displays

    02.02

    (N) Purchase Orders > PurchaseOrders

    Purchase Ordersform displays.Type shoulddefault toStandardPurchase Order.

    02.03

    Enter POHeader

    Enter / Verify Operating UnitNavigate to Type field and Input

    Operating Unit =OU100

  • 7/27/2019 TE040 PO Plan to Replenish

    9/23

    (Select a value from the List ofValues)

    Blanket PurchaseAgreement

    02.04

    Navigate to the Supplier field andinput

    EASTERNINDUSTRIALPRODUCTS

    Site should defaultto EIP Main_PH

    02.05

    Navigate to the Ship-to field andverify/change

    HQ

    02.06

    Navigate to the Bill-to field andverify/change

    HQ

    02.07

    Navigate to Amt Agreed and input 1,000,000,000.00

    02.08

    Enter POLine 1

    Navigate to Type field and enter Goods

    02.09

    Navigate to Item field and input Item = RUBMNT

    Category shoulddefault toDEFAULT.DEFAULT

    02.10

    Navigate to UOM field andinput/verify

    Each

    02.11

    Navigate to Price field andinput/verify

    50

    02.12

    Click on Save Icon. A blanket ordernumber will bedisplayed in PO,Rev field andApprove buttonshould beenabled.

    02.13

    Enter POLine 2

    Navigate to Type field and enter Goods

    02.14

    Navigate to Item field and input Item = BA0401

    Category shoulddefault toDEFAULT.DEFAULT

    02.15

    Navigate to UOM field andinput/verify

    Each

  • 7/27/2019 TE040 PO Plan to Replenish

    10/23

    02.16

    Navigate to Price field andinput/verify

    100

    02.17

    Click on Save Icon

    02.

    18

    Click on Approve Button Approval Form

    displays.

    02.19

    Uncheck Email (if checked)Click on OK ButtonClose the form and return tonavigator

    Blanket PO statusis changed toApprovedNote down the PONumber

  • 7/27/2019 TE040 PO Plan to Replenish

    11/23

    BusinessProcess:Update Approved

    Supplier List

    Business Flow:Pre-requisite steps for Plan to Replenish

    Summary Process:

    Event: Description: Update Approved Supplier List for Re-order Point Planned and Min-max planned item

    Step #

    ProcessStepDescription

    Path and Action Input Data Expected Result Actual Results

    03.01

    Navigate toApprovedSupplier Listform

    (N) Supply Base > ApprovedSupplier List

    Select OrganizationClick on OK Button

    101

    Approved SupplierList (101) form isdisplayed.Type shoulddefault to Item.

    03.02

    Query forASL Details

    Query for Item

    Item = RUBMNT Approved SupplierEASTERN

    INDUSTRIALPRODUCTS will bedisplayed

    03.03

    EnterAttributesforthe Supplier

    Place the cursor in the line item andClick on Attributes button

    Supplier-ItemAttributes (101)form displayed.

    03.04

    Navigate to Purchasing UOM fieldand input

    Each

    03.05

    Navigate to Release Method fieldand verify / input

    Automatic Release

  • 7/27/2019 TE040 PO Plan to Replenish

    12/23

    03.06

    Navigate to Source Documents Tab.

    03.07

    Navigate to Type field and Input(Select from List of Values)

    Blanket

    03.

    08

    Navigate to Number field and Input

    (Select from List of Values)Navigate to Lines field and inputline no.

    Enter the Blanket

    PO generatedearlierEnter line no. = 1

    03.09

    Click on Save iconClose the Supplier Item Attributesform

    03.10

    Query forASL Details

    Query for Item Item = BA0401

    03.11

    EnterAttributes

    for theSupplier

    Place the cursor in the line item andClick on Attributes button

    Supplier-ItemAttributes (101)

    form displayed.

    03.12

    Navigate to Purchasing UOM fieldand input

    Each

    03.13

    Navigate to Release Method fieldand input

    Automatic Release

    03.14

    Navigate to Source Documents Tab.

    03.15

    Navigate to Type field and Input(Select from List of Values)

    Blanket

    03.16

    Navigate to Number field and Input(Select from List of Values)Navigate to Lines field and inputline no.

    Enter the BlanketPO generatedearlierEnter line no. = 2

    03.17

    Click on Save icon

    03.18

    Close forms Purchasing SuperUser Navigatordisplays.

    03. Logout of Oracle Apps.

  • 7/27/2019 TE040 PO Plan to Replenish

    13/23

    19

  • 7/27/2019 TE040 PO Plan to Replenish

    14/23

    10 Test Specification Perform Inventory Planning

    Business Process:Establish Inventory PlanningPolicies (PF1960)

    Business Flow:Plan to Replenish Summary Process:

    Event: Description:

    Step#

    ProcessStepDescription

    Path and Action Input Data ExpectedResults

    Actual Results

    10.01

    Login toApplication

    Username =ENGINEERINGPassword =welcomeSelect the

    Inventoryresponsibility

    10.02

    VerifyPlanningparametersfor ReorderPointplanned Item

    (N) Items > Organization ItemsItem = BA0401Click: FindNavigate to General Planning tab

    SelectOrganization =101

    Inventory PlanningMethod = ReorderPoint

  • 7/27/2019 TE040 PO Plan to Replenish

    15/23

    Navigate to Lead Times tab

    PreprocessingLead Time = 10

    10.

    03

    Verify

    Planningparametersfor Min-Maxplanned Item

    Query for Item = RUBMNT

    Navigate to General Planning tab

    Close Form

    Inventory PlanningMethod = Min-Max

    Min-Max Quantity:Minimum: 50Maximum: 500

    10.04

    Verify /Update

    Forecastquantitiesexists forItems withRe-orderpointreplenishment

    (N) Planning > Forecasts > Entries

    Query for Forecast:

    Manually enter a new forecast:Item:Bucket:Date:End Date:Quantity Current:Click: Save

    Close the Item Forecast Entriesform

    Forecast =REORDER

    BA0401Weeks100

    ForecastQuantities shouldexist for ItemBA0401.

    10.05

    GenerateSafety StockLevels

    (N) Planning > Safety Stock UpdateEnter parameters for requestReload safety stocks:

  • 7/27/2019 TE040 PO Plan to Replenish

    16/23

    Selection:Item:Method:Forecast:

    Safety stock %:(Accept all other defaults)Click:Click: (B) SubmitSubmit another request?Make Sure the request completes

    normally

    Specific InventoryItemBA0401

    User-definedPercentageREORDER10

    OK

    No

    10.06

    Verify /UpdateSafety StockLevels

    (N) Planning > Safety StocksClick: (B) Find

    Update any fractional safety stockquantity to the next higher integer

    Item: BA0401

    System CalculatedSafety stock levelsfor BA0401 shouldbe displayed forthe forecastedperiodNote down theSafety stock (S)calculated for date< First Mondayafter today>For a 5days week,S = (100/5) X10% = 2

    10. Close the form

  • 7/27/2019 TE040 PO Plan to Replenish

    17/23

    07

  • 7/27/2019 TE040 PO Plan to Replenish

    18/23

    Business Process:Manage Inventory Planning(PF0033)

    Business Flow:Plan to Replenishment

    Summary Process:

    Event: Description:

    Step#

    ProcessStepDescription

    Path and Action Input Data ExpectedResults

    Actual Results

    11.01

    Run theReorderPointPlanningReport

    (N) Planning > Reorder Point PlanningEnter parameters for requestReorder Point Report:Item Selection:Restock:Forecast:Items From:

    Items To:(Accept all other defaults)Click:Click:Submit another request?

    All reorder pointplanned itemsYes

    REORDERBA0401BA0401

    OKSubmit

    Note down theConcurrent

  • 7/27/2019 TE040 PO Plan to Replenish

    19/23

    Make Sure the request completesnormally

    No

    Request number______

    11.02

    ReviewReorder

    PointPlanningReport

    (N) View >Requests

    Enter the Request ID noted aboveClick (B) View OutputClose the form

    The reportshould contain anon-zero re-order quantityfor BA0401.Note down thisReorder Qty.

    11.03

    PerformMin-MaxPlanningRun the Min/ MaxPlanningReport

    Navigation: Planning > Min-MaxPlanning

    Press the button Press the button Note 1: This process needs to be run /scheduled for all subinventories.

    Org = 101Run the requestwith the followingparameters:Planning Level =SubinventorySub-inventory =Stores (See note1)Restock =Yes(Accept Defaultvalues for otherParameters)Click No in theDecision Box.

    Note down theConcurrentRequest number______Concurrentprocess issuccessfullycompleted: Go

    to View MyRequest; verifyconcurrentrequest is

  • 7/27/2019 TE040 PO Plan to Replenish

    20/23

    successfullycompleted

    11.04

    Review theMin-Maxreport

    (Online)

    Navigation: Menu: View >RequestsEnter the Request ID noted above

    Click (B) View OutputLogout of oracle apps.

    Check the Min-Max ReportVerify that thequantity shownin the Re-orderQuantity =Maximum

    Quantity (OnhandQuantity +Supply Quantity+ DemandQuantity)

  • 7/27/2019 TE040 PO Plan to Replenish

    21/23

    20 Test Specification Generate Requisitions

    Business Process:Generate Requisitions

    (MM0912)

    Business Flow:Plan to Replenish

    Summary Process:

    Event: Description:

    Step#

    ProcessStepDescription

    Path and Action Input Data ExpectedResults

    Actual Results

    20.01

    Run theRequisitionImportprocess

    Login as Purchasing Superuser.

    Navigation: Reports> RunSingle Request

    Press the button Press the button Click on No for submititng anotherrequest

    Username =PROCUREMENTPassword =welcomeSelect theOU100_Purchasing Super Userresponsibility

    Request Name =Requisition ImportOperating Unit =OU100Parameters:ImportSource = INVGroup By = ItemMultiple

    If the Min-Maxprocess wassuccessful, theImport SourceLOV will containINV.After therequisition

  • 7/27/2019 TE040 PO Plan to Replenish

    22/23

    Menu: View >Requests

    Distributions = NoInitiate Approvalafter Req Import =Yes

    importconcurrentprocess hascompleted, theoutput will

    display thenumber ofrequisitionscreated

    20.02

    ReviewPurchaseRequisitions for Re-ordereditem

    Navigation: Purchasing Super User>Requisitions > RequisitionSummary

    Press the button

    Operating Unit =OU100Item, Rev =BA0401

    Get RequisitionNumber

    Close RequisitionLines SummaryWindow

    At theRequisition LinesSummary form:RequisitionInformationshould bepopulated

    NOTE: If there ismore than oneline, then thetopmost row isthe requisitioncreated now.Also theRequisitionquantity shouldbe the same asthe ReorderQuantity notedbefore.

    20.03

    ReviewPurchaseRequisition

    Navigation: Purchasing Super User>Requisitions > RequisitionSummary

    At theRequisition Lines

  • 7/27/2019 TE040 PO Plan to Replenish

    23/23

    s for Min-MaxplannedItem

    Press the button

    Operating Unit =OU100Enter Item, Rev =RUBMNT

    Get RequisitionNumber

    Close RequisitionLines SummaryWindow

    Summary form:

    RequisitionInformationshould bepopulatedNOTE: If there ismore than oneline, then thetopmost row isthe requisitioncreated now.

    Also theRequisitionquantity shouldbe the same asthe Min-MaxOrder qty notedbefore.

    20.04

    AutomaticRelease forMin-Maxplanned

    Item

    Navigation: Purchasing Super User >Purchase Orders > Releases

    Query for Supplierand Date:Supplier =EASTERN

    INDUSTRIALPRODUCTSCreated =Ensure Item =RUBMNT

    Latest Releasedetails will bedisplayed.

    Ensure that there-orderQuantitymatches withthe releaseQuantity