tcf task 242 – managed motorway ground investigation process improvement lean project improvement...
TRANSCRIPT
TCF Task 242 – Managed Motorway Ground Investigation Process Improvement
Lean Project Improvement Presentation Slides
Objectives
Understand how Ground Investigations are currently undertaken
Develop an improved process with realistic timescales Ultimate deliverable would be a best practise guide
(beyond the scope of this commission)
Original Commission and Appraisal Work
Ground Investigation (GI) surveys on Tranche 1 Managed Motorway schemes were perceived to be costly in terms of budget and programme. These issues were perceived to be related to the procurement and delivery mechanism utilising the MAC.
Jacobs was originally commissioned to prepare a business case for setting up a national ground investigation framework
Ground Investigation Framework Study Findings
Jacobs collected and collated data following request for information covering: Procurement route Scope of work Programme Costs Traffic Management Other comments
Data was received from 4 managed motorway schemes, 3 other motorway schemes, 2 highway schemes and 2 existing frameworks
Ground Investigation Framework Study Findings
Single occurrence GI costs Since GI is conventionally
undertaken as a phased process, in some instances, this is just the cost so far
Time M4 / M5 anticipated 67 shifts,
actual 75 shifts MMM anticipated 10 weeks,
actual 20 weeks Not all schemes provided
data!!!!
£0
£100,000
£200,000
£300,000
£400,000
£500,000
£600,000
£700,000
£800,000
£900,000
M1 J10 to13 MM
M4 / M5 M40 M62 J18to 20 MM
M60 J15to 12
M60 J8 to12 MM
Other
Traffic Management
GI Works
Supervision
Ground Investigation Framework Study Findings
Procurement routes: Many routes are currently implemented No single option presented itself as an ideal solution Framework:
Advantages include one-off procurement and greater consistency / visibility of rates
Disadvantages include: Initial set-up time / costs, may not overcome traffic management issues Lack of integration with the MAC and other network operations Cost and programme could still be key issues if not procurement related.
MAC Advantages include knowledge of the site, TM, quicker mobilisation
(operational planning expertise, integration with other network occupancy, etc)
Disadvantages include perceived excessive costs, programme overruns lack of ownership and under resourcing management of the GI
Ground Investigation Framework Study Findings
Cost and programme comparison: Little evidence that rates are inconsistent or unreasonable
across procurement routes Procurement route has little effect on programme
Traffic Management: Greater control and flexibility of TM if GI procured through MAC Undertaking TM flexibly, managed by short-term programming
and effective communication improves efficiency In some instances, TM costs were approaching half the cost of
the investigation Technical scope for the GI can significantly affect cost &
programme if change is required during the works.
Ground Investigation Framework Study Findings
Outcome: Large quantity of factual and anecdotal evidence collected Procurement is not necessarily the issue – jumped to a
solution without fully understanding the problem Findings relate to issues around:
Traffic Management Planning Process Appropriate technical scoping and specification
Measure
What generally happens:
Prepare Desk Study &
Scope Initial GI
Procure GI
Undertake GI
Testing & Reporting
Design Development (during Stage 2) Detailed Design (during Stage 5)
Scope Detailed GI
Procure GI
Undertake GI
Testing & Reporting
Construction (design may change further)
Scope Supplementary
GI
Procure GI
Undertake GI
Testing & Reporting
GI data is used to manage the geotechnical risks associated with the construction of infrastructure and is used to inform the design. The ultimate objective is to produce a safe
design that is technically and commercially efficient.
Traditionally GI is a phased process aimed at reducing uncertainty and risk as a scheme develops. Initial GI undertaken based on “initial design” and used to gain a general
understanding of the ground conditions, design develops, detailed GI required, design possibly changes further, supplementary GI required, etc, etc
PRE-CONSTRUCTION CONSTRUCTION
Is known to have occurred
more than once in Stage 2
Is known to have occurred
more than once in Stage 5
M62 J25-30
£400,000
M62 J25-30
£95,000
M62 J25-30
£200,000
Measure
Manchester Managed Motorway Value Stream Mapping exercise
Key issues encountered: Adverse Weather Discovery of Services CDM Co-ordination Scope Quality MAC Pricing Landowner Objections Great Crested Newts
Measure
What went well: No accidents / incidents Weekly GI progress meetings Consultants came together
for a common approach Management of network
occupancy AOne+ and Costain flexibility
What could’ve gone better: Too many designers / CDMCs Technical specification more
appropriate to the operating environment
Insufficient on-site management Project Sponsor unfamiliar with
the process Greater time and effort required
in the preparation for the works (planning of shifts, access and network occupancy)
Lack of permanent site ecologist Time of year – weather,
embargos
Summary of Manchester Managed Motorway GI
Measure
NVA elements identified: CDM Role Consideration Specification submission to MAC Mobilisation TA process to approve the use of Sonic Borehole Technology Discovery of Services Pegging Out Services Great Crested Newts Landowner Objections
Measure
Failure Modes and Effects Analysis Workshop held on 14 February, key failure modes and causes: Failure to do boreholes in planned locations due to services in
the verge found during GI (see next slide) Delay appointing single CDM-C role – too many CDM-Cs /
Designers, lack of appreciation Reworking of GI scopes due to design changes and additions GI design – change in GI technique to reflect operating
environment during the works
Measure
Services located in the verge are “pegged” out by the TechMAC using similar images / information
On site the GI Contractor has no indication where exactly the services (cables) are or how many
The number of services in the verge and the inability to work around them forced the GI Contractor to move to the hardshoulder during the night
Improve
Improvement Workshop held on 22 March 2011 to: Validate the current situation Validate occurrences on Manchester Managed Motorway Test macro improvement options Test process improvement options
Why do we need to do GI on Managed Motorway schemes? To manage the risks to obtain a safe and economic design To obtain a level of confidence in ground condition
GI very rarely affects the gantry locations
Improve
Current situation validated: M62 Junction 25 to 30 about to undertake third GI – attributed to
design changes Birmingham Box Phase 3 about to undertake second GI – design
changes and need to determine foundation (pile) solution
Manchester Managed Motorway GI validated against occurrences on Birmingham Box: Programme pressures lead to limited planning time Competition on network for road space booking (TM) The GI design / work scope didn’t properly understand and reflect the
constraints of the operational environment
Improve
Macro Improvement Options – no pre-construction GI Contractor undertakes GI during Construction Phase. The
key differences between current situation are: No GI pre-construction Would require more designer input during construction Potential saving on TM duplication, i.e. during options then
construction Significant reduction in the chance of service strikes and the
ongoing need to re-position exploratory holes Potential lack of appreciation of major geology features / issues Dependence on site environment Could increase risk allocation leading to issues with target cost
Improve
Macro Improvement Options – no pre-construction GI What would we do?
Set out and agree approach to GI and geotechnical certification (Statement of Intent).
Desk Study – Preliminary Sources Study Report Isolated GI to target key risk areas, i.e. 1 or 2 boreholes during pre-construction to
augment PSSR. Challenge the need for GI at this stage and require rigorous justification.
Prepare matrix of foundation solutions for Deliver Partner to undertake Target Cost including risk allocation
During construction: TM established on site Verges cleared (services, barriers, etc) Undertake GI at exact locations Testing and interpretation Select foundation solution Structural and geotechnical certification Construction Feedback report to capture GI data
Improve
For / Benefits: The perfect “pull” project Design fixed and GI undertaken with
certainty Significant pre-construction cost saving GI only undertaken once – cost savings Efficiency – TM, verge clearance, site
welfare Stakeholder interface more controlled Standard solutions deliver potential
efficiency Potentially forces Designer / Delivery
Partner to value manage the GI
Against / Disbenefits: Potential to impact duration of
construction period Increased pre-construction risk The AIP (structures certification) process GI in construction could be blocking the
site Conservative foundation solutions Greater designer input during
construction (good or bad – undecided!!) Implications on perceived rigid structure
of PCF
Macro Improvement Options – no pre-construction GI
Macro Improvement Options
Macro Improvement Options – Single pre-construction GI Designer / Delivery Partner has one opportunity to undertake
GI. The key differences between current situation are: The need for GI is challenged Undertake GI once Undertake GI as late as possible during Stage 5 detailed design Greater chance of design fixity during detailed design
Improve
Macro Improvement Options – Single pre-construction GI What would we do?
Agree approach – prepare Statement of Intent Prepare Preliminary Sources Study Report Prepare strategy, scope and specification and challenge the need for GI Procurement Move into Phase 5 – Delivery Partner appointed Undertake GI The GI would then be used during Detailed Design and Target Cost
preparation with the objective is to reduce / manage risk allocation
Improve
For / Benefits: Cost saving by undertaking once GI results / findings can inform
the detailed design Should reduces risk (time / cost)
during preparation of Target Cost
Follows the current PCF process Fewer site visits, potentially
reduces impact on stakeholders Potentially forces Designer /
Delivery Partner to value manage the GI
Against / Disbenefits: The GI is still undertaken before
target cost design freeze, i.e. the design may change
Potential inflexibility of undertaking single GI
Potential to over scope GI if it’s only undertaken once
Still has many of the potential disadvantages of the current approach in terms of potential costs / delays / TM / conflicts in network occupancy
Macro Improvement Options – Single pre-construction GI
Improve
Further points to consider from the workshop: GI is only undertaken during construction stage of Network
Rail’s electrification schemes Design the GI (techniques and scope of work) with the
operating environment in mind Don’t assume GI needs to be undertake immediately Two hit GI is the traditional way for green-field schemes We are not Value Managing GIs Agreed by Designers and TAA at the workshop that no GI in
pre-construction phase should be the starting point
Improve
Lessons learned: Agree roles and responsibilities at the start Understand the constraints, embargos, working times, etc Write the specification for the GI with due regard for the site constraints Recognise all constraints include services, working space, barrier, fencing, lane
restrictions, etc Get to know and liaise with the MAC and Network Operations Managers Resource the site works adequately (day to day project management) Engage with the Environmental Coordinator early Agree GI Scope / Specification with TAA around a table Agree format of the pricing schedule early (inc. level of detail) Undertake GI as late as possible in the programme
Improve
High-level process: Undertake GI during construction should be the default route Project Sponsors, Project Managers and TAA would need to be
convinced to undertake GI earlier
PCF Stage 2 – Options PCF Stage 5 – Pre-Construction PCF Stage 6 – Construction
Data Gathering
Preliminary
Sources Study
Report
Undertake GI
during
construction
Yes
No
Undertake isolated
GI for key risks if req
Scheme Concept and Outline
DesignPreliminary Design
Environmental and Economic
AssessmentsDetailed Design Target Cost Construction
Prepare strategy,
scope &
specification
Undertake
single stage GI
Testing &
Reporting
Prepare strategy,
scope &
specification
Undertake GITesting &
ReportingKey decision
This is the default route
This is the non-preferred route