tab 5 operational impacts-v3.1

Upload: pao-lema

Post on 13-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    1/50

    2012 Siemens Industry Inc. All rights reserved

    Tab 5: Wind Integration Operational Impacts

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    2/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Siem

    ensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-2

    In this section we will explore:

    Frequency Control Impacts

    Load frequency Control

    Governor action and droop control

    Wind impacts on frequency regulation

    Major Challenges

    Load Following Impacts or Economic Dispatch

    Definition of economic dispatch

    Characteristics of hydro units

    Characteristics of wind units

    Dispatch of Wind units

    Load following

    Impact of wind units on assignment of load following units

    Unit Commitment Impacts

    Wind Integration Operational Impacts

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    3/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Siem

    ensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-3

    Introduction

    The growth of wind power have complicated the way optimizedpower system operation is carried out

    The main activities of power system operations:

    Voltage control

    Real Time

    frequency control (regulation)

    Real Time

    Load following

    Economic dispatch, and

    Unit commitment

    System Reliability

    Resource and Capacity Planning

    now involve different behaviors (than conventional generation)more variability and uncertainties

    introduced by wind and otherrenewable generation technologies (e.g. solar)

    The impact of the variability and uncertainties will increase as

    the penetration increases and can lead to substantial integrationcosts if not treated properly.

    Fortunately there are ways of dealing with this effects.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    4/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Siem

    ensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-4

    Time Line for Operational Control Activities

    Source: NERC IVGTF Report

    ELCC

    Wind reducedELCC (EffectiveLoad Carrying

    Capability)

    Winduncertainty

    Wind Variability& uncertainty

    Wind Variability& controllability

    Impact

    Impact

    Impact

    Impact

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    5/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Siem

    ensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-5

    Time Line for Operational Control Activities

    (continued)

    VoltageRegulation

    FrequencyRegulation

    Load followingand Economic

    Dispatch

    Scheduling andUnit

    commitment

    Real time Short time frames tomaintain systembalance

    Dispatch of bothenergy and capacity(reserves) services

    Ensure sufficientgeneration is therewhen needed

    Seconds -

    Minutes

    Maintain voltageprofiles & PreventVoltage collapse

    Initial:

    GovernorAction

    seconds Several minutes to afew hours Normally Day AheadHours Ahead provideadjustments.

    Week, Month, YearAhead ensureavailability.

    Then:

    Provided bygenerators on AGC

    With wind:

    Greater regulation, load-following, and quick-start capabilityrequired from the remaining generators.

    Function of balancing area size, the size and geographicaldispersion of Wind Plants, the capabilities of the WTG

    & the

    flexibility of other generators and load.

    Greatest source ofcosts. Windforecasting crucial tomanage this and therisk associated with

    the uncertainty in theday-ahead time frame

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    6/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Siem

    ensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-6

    Frequency Events in Power Systems

    When a generator output is lost the frequency immediatelybegins to fall.

    The remaining generator governors, to a varying extent, see

    the lower frequency and increase the amount of powergenerated via governor action

    Some loads are naturally frequency dependent. Simple ACmotors slow down and consume less power. For some types ofloads this power reduction is much more than a directproportion.

    A new equilibrium point is reached, in a few seconds, and the

    frequency decline is arrested. The system is off-nominalfrequency

    When a block of load is suddenly lost, frequency immediatelybegins to rise, governors decrease the generator output,

    frequency dependent loads consume more power, and a newequilibrium is reached.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    7/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-7

    Frequency Deviation in the U.S.

    For the Northeast interconnected system

    Frequency generally remains between 59.85 Hz and 60.15 Hz

    During major events the deviation is still small

    During the blackout of 2003 frequency only deviated within +/-

    0.3 Hz.

    Loss of the largest single unit in the interconnection (1300 MW)

    produces a frequency decline of about 0.04 Hz; No Problem.

    Huge Inertia

    For the Eastern Interconnection:

    Response of about -3300 MW/0.1 Hz, i.e. the loss of 1000 MW ofgeneration will cause a frequency deviation of -0.0303 Hz.

    Usually, rate of frequency change is low:

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    8/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-8

    550

    70

    500

    450

    400

    140

    210

    280

    Frequency Deviation in the U.S.

    An Example

    The figure below shows the impact in ERCOT system when WTG (QSE)

    almostinstantaneously ramp up and down causing frequency deviations and RapidResponse Reserve (RRS) to be deployed

    Eventually, a 10% ramp rate was agreed upon by ERCOT and the wind

    community taking into consideration the economical impact a smaller ramprate could have on the WTGs (more on this later)

    Impact

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    9/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-9

    Frequency Control

    When there is disturbance the system responds intwo time frames:

    Primary Control

    System Inertial Response

    Load Response

    Prime Mover Governing Response

    Primary frequency response (10 sec)

    Secondary frequency response (30 sec)

    Supplementary Control

    Speed changer -

    local level (Load reference set-point);

    Instruction to operators from the control center.

    Automatic Generation Control (AGC) -

    system level

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    10/50

    20

    12SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-10

    Initial Line of Defense

    Inertial Response / Load Response

    Inertia comes from thelarge mass in therotors and turbines of

    conventionalgenerators.

    Load can contribute

    significantly to arrest theinitial drop in frequencyworking together with thesystem inertia.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    11/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-11

    Next Line of Defense

    Response of Machines Governors

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    12/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-12

    But

    Frequency Response is Affected by WTG Impac

    t

    WTG have less inertia and traditionally did notparticipate in frequency control: e.g. rotor speed

    constant philosophy for the DFIG

    This produced:

    Increased rate of change of system frequency for the samedisturbance (drop large generator unit)

    Need to increase the up-regulation / down-regulationspinning reserve in the system

    More acute for relatively small isolated systems: increased

    risk of under-frequency load shedding and cascadingoutages

    Gets worse for greater levels of penetration

    WTG could ramp up and down very rapidly makingthe situation worse.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    13/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-13

    However

    Modern WTG Generation Addressed This

    Modern Larger WTG

    have greater inertia

    The inertia stored in the rotating mass tends to increase slightlymore than linear with the rated power of the turbine

    Deliberately use the control to extract stored inertial energyby decelerating the machine rotor

    Provide incremental energy contribution during the firstseveral seconds of grid events

    Do not go too far down with the rotor speed to avoid stalling awind turbine

    Can provide Governor like response by spilling

    wind if thisis the most economic way of providing regulation

    Have ramp controls.

    Solution

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    14/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-14

    Modern WTG Generation Addressed ThisSiemens Netconverter

    The output of the WTG is controlled so it is frequency

    sensitive.

    The energy is extracted from both slowing the turbine and thewind that is spilled.

    This gives time for the system to recover.

    Solution

    Turbines at reduced power

    Increase in turbine output power

    Reduction in turbine output powerTurbines at reduced power

    Increase in turbine output power

    Reduction in turbine output power

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    15/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-15

    ERCOT LOAD SHED LEVELS

    Three steps are considered in ERCOT

    A Typical response shown

    Frequency Threshold Load Relief

    59.3 Hz 5% of the ERCOT System Load(Total 5%)

    58.9 Hz An additional 10% of the ERCOT System Load

    (Total 15%)

    58.5 Hz An additional 10% of the ERCOT System Load

    (Total 25%)

    Recorded, Initial, Adjusted

    59.2

    59.3

    59.4

    59.5

    59.6

    59.7

    59.8

    59.9

    60

    60.1

    60.2

    60.3

    0 5 10 15 20 25

    Seconds

    Hz

    recorded

    initial

    adjusted

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    16/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-16

    Modern WTG Generation Addressed ThisGE WindINERTIA

    1

    WindInertia increases electric power during the initial stages ofa significant downward frequency event by issuing a commandfrom the special frequency control

    Usually it is enough to provide response within several secondsuntil governors of larger conventional machines start their work

    WTG electric power drops to allow recovery of rotational speed

    Solution

    Source: N. Miller et al., GE Energy. CanWEA, Vancouver, BC, October 20, 2008

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    17/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-17

    Modern WTG Generation Addressed ThisRamp Control

    ISOs are imposing limits on the ramping of WTG (e.g. 10%/minfor ERCOT)

    Modern WTG have the capability to respond.

    Below to examples one from Siemens and another from GE

    Solution

    Source: N. Miller et al., GE Energy. CanWEA, Vancouver, BC, October 20, 2008

    Ramp Rate Control

    0

    50

    100150

    200

    250

    300

    350

    0 5 10 15 20

    t, min

    P,MW

    Output Available Output

    Curtailment to 100 MW

    @ 15 MW/min

    Curtailment released;

    ramp to max power @

    10 MW/min

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    18/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-18

    Final Line of Defense

    AGC

    Governor control is proportional and will leave an error inthe frequency.

    As shown before the final line of defense after a major

    perturbation is the Automatic Generation Control (AGC).

    Units on AGC can change outputquickly to track minute byminute load variations and anyvariations in generation.

    Units in AGC are usually themarginal units in the network

    (e.g. GTs. CCPs, etc) or storage

    hydro.

    WTG are never the marginal unitand would not be on AGC.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    19/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-19

    Background of Other Operational Concepts

    Load Following

    Load following takes place in the same time frame as economicdispatch discussed next, usually defined in the intra-hour timeframe.

    Load following is defined as the response to changes in systemload and as we will see to changes in wind output.

    The composition of units assigned to load following depend onboth of utility company operational practices, economicdispatch regime and on the physical capabilities of generators

    (such as ramp rates) that follow load.

    Larger control areas typically have several units that provide a

    fraction of total output and

    that can be called upon to eitherincrease or decrease output.

    When this load following capability is spread among several units,

    the ramp rate becomes less of a constraint

    than if only a smallnumber of units adjust to changing load conditions.

    It is generally nor economic to use WTG to provide loadfollowing.

    WTG is modeled as a reduction in load in operational studies.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    20/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-20

    Background of Other Operational Concepts

    Economic Dispatch (ED)

    Problem Definition

    Given a set of generating units, synchronized and underdispatch control, and given the total net Load demand to besupplied by the units;

    Determine the output of each unit so that the totalproduction cost is minimized

    and the sum of the outputs

    equals the total net demand. Also

    no unit can violate its minimum or maximum dispatch

    limit.

    The flows in the system cannot violate transmission limits

    andcreate potentially unsecure conditions (security constrained

    solution)

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    21/50

    2012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-21

    Background of Other Operational Concepts

    Generator Models for Economic Dispatch

    Thermal Units

    Input-Output characteristics of a thermal generation unit is defined in termsof gross input: Heat rate (H) in (MBtu/hr) versus net generator MW output(P).

    Heat Rate

    (H)

    Is the amount of heat added, usually in Btu per hour, to produce a unit amount of work kWh. Heat

    rate thus has units of Btu/kWh.

    Hydro Units

    Production function of flow, head and efficiency

    Value of water is a function of expected (stochastic) futureproduction cost savings versus producing today

    Value is zero if the plant is spilling water or is a run-of-river

    Value is very high if levels are low and it is likely that in the future veryhighly priced thermal (or load rationing) would have to be incurred.

    Wind Units

    Function of the Cp and cube of the wind speed.

    Detailed hour by hour mesoscale wind models used to defineproduction

    Modeled usually as a negative load

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    22/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-22

    Background of Other Operational Concepts

    Economic Dispatch Solution

    The goal is to dispatch all the available synchronized units tomeet the load demand at minimum cost.

    For a a system with N thermal units, this is achieved under the

    condition that at optimal dispatch all units have equalincremental (marginal cost), where F(Pi

    ) is the Fuel input

    power output characteristic of each unit.

    All units are either at itsmaximum/minimum output or aremarginal units (within unconstrainedareas)

    Tool: Security Constrained EconomicDispatch (SCED)

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    23/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-23

    Background of Other Operational Concepts

    Unit Commitment (UC)

    Why Unit Commitment?

    Cyclic nature of power system loads.

    Load changes and the operation of an electric power system.

    Committing enough units and having them on line is one ofeconomics and security (reserves)

    Many constraints can be placed on the unit commitmentproblem such as;

    Generating unit constraints and status

    Reserve constraints

    Minimum up-time and down-time

    Crew constraints

    Ramp rate limits

    Transmission Constraints

    Generation-Load balance constraint

    Tool: Security Constrained Unit Commitment (SCUC)

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    24/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-24

    The ISOs functions include the administration of the UCand ED according to various timeframes

    Day-ahead security-constrained

    unit commitment once aday

    Real-time (short-term) security-constrained unitcommitment every 15-minutes

    with a 30-minute reactiontime

    Real-time security-constrained economic

    dispatch every 5minutes

    with a 10-minute reaction time

    Automatic generation control every 6 seconds

    Supplementary, computer-assisted manual intervention as

    needed

    Other functions of the ISOs are

    Operating the high-voltage transmission system and

    Administer, monitor, and settle the electricity markets

    Background of Other Operational Concepts

    Functions of the ISO

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    25/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-25

    Background of Other Operational Concepts

    Spinning Reserve Constraints

    Spinning reserve

    is the term used to describe the total amountof generation available from all units synchronized (i.e.,spinning) on the system, minus the present load and losses

    being supplied.

    Spinning reserve must be carried so that the loss of one or more

    units does not cause too far a drop in system frequency. If one

    unitis lost, there must be ample reserve on the other units to make up

    for the loss in a specified time period.

    Spinning reserve

    must be allocated to obey certain rules,usually set by regional reliability councils (in the united States)that specify, how the reserve is to be allocated to various units.

    Typical rules specify

    that reserve must be a given percentage of forecasted peakdemand, or

    that reserve must be capable of making up the loss of the mostheavily loaded unit in a given period of time.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    26/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-26

    Background of Other Operational ConceptsSpinning Reserve Constraints (continued)

    Beyond spinning reserve, the unit commitment problem may involve

    various classes of scheduled reserves

    or off-line

    reserves.

    These include:

    quick-start diesel or

    gas-turbine units

    hydro-units

    pumped-storage hydro-units

    that can be brought on-line, synchronized, and brought up to fullcapacity quickly.

    As such, these units can be counted

    in the overall reserve assessment,as long as their time to come up to full capacity is taken into account;Rapid Response Reserves (RRS)

    Finally, Reserves must be spread around the power system;

    to avoid transmission system limitations (often called bottling

    of reserves)and

    to allow various parts of the system to run as islands, should they becomeelectrically disconnected.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    27/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-27

    Background of Other Operational ConceptsResource Adequacy

    This refers to the procurement of enough installed generation in

    the system to be able to attend the forecasted peak load,schedule the required maintenances and account for forced

    unavailability while maintaining a desired level of reliability;

    usually measured in LOLP in % or LOLE in days per ten years

    One key component to represent the value of a unit is its ELCC or

    Expected Load Carrying Capability.

    For conventional generation it is approximately equal to Maximum

    Demonstrated Capacity (MW) * (1-FOR)

    For WTG we will see later.

    Yearly the ISO must ensure that there is enough capacity in thenetwork including firm imports less firm exports.

    Now we will see how WTG affects all of this!

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    28/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(Sie

    mensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-28

    The Nature of WTG

    Variability & Uncertainty

    Variability

    are changes in the WTG output due to weatherpatterns and are unavoidable, but can be mitigated.

    Geographic Dispersion reduces Variability

    Wind mesoscale models demonstrate that it is not credible that in alarge area all wind speed will experiment the same variation.

    The larger the geographical dispersion of Wind Plants the smaller thevariability of the generation

    Impact

    Source: DOE 2008 Report

    Solution

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    29/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-29

    The Nature of WTG

    Variability

    The size of the Wind Generation reduces the variability

    More WTG imply that it is less likely that they all see simultaneouslythe same change in wind speed resulting in soothing effects

    More WTG generation is likely to also imply greater geographical

    diversity.

    Also, shorter time frames are subject to less variability.

    Sudden changes in wind speed are less likely and thing localized.

    Solution

    Source: DOE 2008 Report

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    30/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-30

    The Nature of WTG

    Variability (continued)

    Based on the observations above we conclude that makingthe balancing areas larger

    reduce variability and as we willsee also the uncertainty.

    Virtual arrangements though reserve sharing, ACE sharing anddynamic scheduling of wind plants from smaller to larger areas.

    Source: Avista Wind Integration Study

    Solution

    Increase inGeographicaldiversity

    Cost is reduced as

    the Balancing Areasincreases (largerareas.

    Wind resources were evaluated in the Columbia Basin, in Eastern Montana, as a 50%/50% mix of Columbia Basin and EasternMontana wind, and as a multi-state diversified

    mix with many smaller sites combined.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    31/50

    2

    012SiemensIndustryInc.,SiemensP

    owerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-31

    The Nature of WTG

    Uncertainty

    Uncertainty are errors in the estimation of production due toerror in the wind speed forecast

    The errors in wind speed are magnified in the power output due

    to the cube dependency.

    10% error in wind speed results in 33% error in power.

    Costs can be substantial, particularly for over commitments of capacity.

    Impact

    Source: Avista Wind Integration StudyLevel ofPenetration

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    32/50

    2

    012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-32

    The Nature of WTG

    Uncertainty (continued)

    The errors in wind speed are magnified as the time horizonincreases. This means that on one extreme day ahead unitcommitment it has the greatest impact and on the other loadfollowing has the least.

    Impact

    Source: NERC IVGTF Report 041609

    This has an impact onmarkets, the sooner theday ahead closes

    the

    greater the error in theforecast and the higher thecost

    Same applies for hour

    ahead and

    This is a case for lateclosing of day aheadmarkets and intra-hour

    markets.Solution

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    33/50

    2

    012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-33

    The Nature of WTG

    Uncertainty (continued)

    Wind forecasting technology has improved substantially over theyears, lead by countries like Germany that have large levels ofwind integration.

    Better data collection / larger areas / faster computers

    Use of multi-model approaches for forecast; statistical models using forexample Artificial Neural Networks, mixture of experts, nearest neighborsearch and support vector machines

    Use of mutischeme forecasting based on different assumptions/methods in

    numerical weather models

    Source: Predicting the Wind, IEEE

    Solution

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    34/50

    2

    012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-34

    The Nature of WTG

    Uncertainty (continued)

    These methods and efforts have resulted in a continuedreduction in the forecasting error

    Source: Predicting the Wind, IEEE

    Solution

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    35/50

    2

    012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-35

    The Nature of WTG

    Uncertainty (continued)

    Larger areas result in a reduced forecasting error for the region.

    This results in less impact on scheduling and therefore lower integrationcosts,

    Source: Predicting the Wind, IEEE

    Solution

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    36/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-36

    Modeling Wind as a Load Resource

    for System Operations

    WTG is normally treated as a negative load resource and the netload forecast

    is used to commit and dispatch non-windgeneration:

    Since wind has no fuel cost per se, it is always called to run, whenever

    available in the dispatch; same as load

    It is treated as non dispatchable unit

    by most utilities and electricity markets;same as loads

    Wind generation is variable and has errors in its forecast; same

    as loads

    Load and WTG are independent and the combination of errors is :

    Example if the load forecast error for a 5,000 MW peak load is 2% = 100 MWand the WTG error for a total of say 1000 MW, with an output of 500 MWduring the peak is 25% = 125 MW, then the total expected error is 160 MW..

    Wind forecast error and variability increases ancillary services for

    regulation control

    2

    generationwind

    2

    loadtotal

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    37/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-37

    Wind Impacts on Load Following

    Wind generation canhave significant Impacton load following.

    Wind adds variability tothe to the rampingrequirements.

    The figure to the left

    shows the increase inrequirements for Xcelenergy North, with andwithout wind

    Impact

    Source: Grid Impacts of Wind Power Variability: RecentAssessments from a Variety of Utilities in the UnitedStatesB. Parson et. al.

    Ramp uprequirementsincreased bywind

    Ramp down

    requirementsincreased bywind

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    38/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-38

    Unit Commitment of Wind Generation

    The use of wind generation, due to the variable nature of wind,can lead to operational uncertainty:

    How much generation will be necessary

    to serve the net load (load

    WTG)?

    How much spinning reserve will be necessary

    to maintain reliabilitylevels?

    What load following reserves and ramping capabilities

    are

    required?To allow regulation, i.e. the minute by minute changes insystem load

    Some utilities when committing or dispatching wind

    generation, use a generation output that is discounted by acertain percentage of the forecast value

    to hedge againstuncertainties in wind forecasting.

    Remember that errors in the forecast have maximum impact the

    longer the time

    are maximum in the day ahead unitcommitment.

    Impact

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    39/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-39

    Effect of the Nature of Other Generation

    The impact of the variability and uncertainty of wind generation

    is minimizedwhen the rest of the generation is flexible and the LOAD!

    SolutionImp

    act

    Technology Impact

    Nuclear Power

    Plants Very inflexible slow to change

    Run-of-river hydro Limited flexibility without wasting water

    Large Coal FiredSlow to start and ramp, better at base

    load

    Combined Cycle

    Plants

    Faster to start, fast to ramp; high

    efficiency at close to nominal

    Conventional CT Fast to start and ramp; costly

    Advanced CCPFast to start and ramp; very efficient at

    many load levels FlexPlant 10

    Pump storageFaster to start, fast to ramp; need low

    cost energy

    Storage HydroFast to start and ramp; can virtual

    store

    worst

    better

    Best

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    40/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Si

    emensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-40

    Summary of Impacts and Solutions

    The table below summarizes the main operation impacts and theirmitigations/solutions

    Not all systems are the same with respect of the quality of the WTG,the flexibility of the generation and the level of penetration but this is a

    good indication

    Impact

    INCREASING COSTS

    Regulation

    Load following

    Economic Dispatch

    Unit Commitment

    short term

    Unit Commitment

    Day Ahead

    ImpactVery LowSmallest errors in

    forecast

    Limited Variability

    LowSmaller errors in forecast

    Subject to Variability

    MediumSome errors in forecast

    Important Variability

    HighSignificant errors in

    forecast

    Important Variability

    Mitigation- WTG Controls

    - Flexible Generation

    - WTG Controls

    - Flexible Generation

    - Geographical Diversity

    - Large Balancing Areas

    - Flexible Generation

    - Geographical Diversity

    - Large Balancing Areas

    - Flexible Markets

    - Flexible Generation

    - Geographical Diversity

    - Large Balancing Areas

    - Flexible Markets- Improved forecasting

    Effectiveness High High Improving Need to improve

    Activi ty

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    41/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Si

    emensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-41

    Summary of Impacts and Solutions

    (continued)

    The table below summarizes the results of various integration studiesto date.

    It is largely in agreement with the observations made

    Impact

    INCREASING COSTS

    Date Study WindCapacity

    Penetration(%)

    RegulationCost

    ($/MWh)

    LoadFollowing

    Cost($/MWh)

    UnitCommit-

    mentCost

    ($/MWh)

    Gas SupplyCost

    ($/MWh)

    TotOper.Cost

    Impact($/MWh)

    May 03 Xcel-UWIG 3.5 0 0.41 1.44 na 1.85

    Sep 04 Xcel-MNDOC

    15 0.23 na 4.37 na 4.60

    2005 PacifiCorp 20 0 1.6 3.0 na 4.60

    April 06 Xcel-PSCo 10 0.20 na 2.26 1.26 3.72April 06 Xcel-PSCo 15 0.20 na 3.32 1.45 4.97

    Jul 07 APS 14.8 0.37 2.65 1.06 na 4.08

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    42/50

    2012SiemensIndustryInc.,SiemensPowerTechnologiesInternational(Si

    emensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-42

    A larger number of Studies

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    43/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-43

    Using Economic Dispatch Simulation to Evaluatethe Cost Impact of Wind Generation

    The costs impacts of sub hourly load following that includedispatched wind generation can be evaluated by running aSecurity Constrained Economic Dispatch (SCUD) simulationsoftware .

    With wind profiles / mesoscale models / forecasts calculate wind

    productionby plant in 15 minutes increments and its expected error (introduced asprobability)

    Run the SCUD and calculate the dispatch for other units and reserves.

    For comparison purposes a case with uniform capacity and energy equal tothat produced by the wind resources can be assessed.

    This cost incurred due to using wind during this period, islargely due to factors such as;

    Sudden loss or increase of wind power

    Slow changes in wind power output (i.e. ramp rates)

    Units at their minimum.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    44/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-44

    Using Unit Commitment Simulation to Evaluate theEconomic Impact of Wind Generation (continued)

    The economic impact of wind generation in the unitcommitment can be done as follows;

    With wind profiles / mesoscale models / forecasts calculatewind production by plant in hourly increments. Expectedcase can be used or historical series. Account for errors inthe forecast.

    Run the SCUC and calculate the commitment for other unitsand reserves. Calculate the cost.

    This cost can be compared with a benchmark case that has a

    unit commitment with no wind capacity scheduled, butinstead an uniform block of generation that produces thesame energy of the wind is included.

    A case where wind and corresponding load is removed from

    the runs.

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    45/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-45

    Summary of Operational Impacts of Wind Integration

    Carrying of additional reserves,

    both spinning andnon spinning to meet intra hour load following.

    Additional energy costs incurred for intra hour loadfollowing due to greater variability

    Possible additional costs of frequency regulationresources or regulation reserves

    Found by evaluating the impact of wind fluctuations on thestandard measures such as area control error etc.

    Increased reserves for safe operation.

    Important for older WTG less so with new designs

    Additional cost for Unit commitment costs

    due toforecast inaccuracies

    in Wind generation outputs

    The cost of rescheduling generation to account for short fall

    of wind output

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    46/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-46

    A Case Study of a WPG in High Penetration Denmark(19.3%)

    A typical day on the Horns Rev Offshore wind plant in Denmark

    Plant spilling windso it has spinningreserve available

    Manual orders

    to reduceoutput

    Fast Reductionto counteractfrequencyincrease

    Source: European Balancing Act, IEEE

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    47/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-47

    The Capacity Value of Wind

    While wind is largely an energy resource it does have somecapacity value; i.e. Effective Load Carrying Capability (ELCC)

    There are several methods for determining this value for WTG

    Source: M. Milligan and K. Porter, Determining the capacity value of wind: A survey of methods and implementation,

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    48/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-48

    The Capacity Value of Wind (continued)

    As can be observed in the figure below in average about 25%ELCC is assigned to WTC across different companies.

    Source: Wind Plant Integration-

    Cost Status & Issues IEEE

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    49/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    Siemens Power Academy TD-NA Power System Studies for Wind Integration 5-49

    The Capacity Value of Wind (continued)

    However, this value may change season to season as Avistafound:

    Source: Avista Wind Integration Study

  • 7/26/2019 Tab 5 Operational Impacts-V3.1

    50/50

    2012SiemensIndustryInc.,Siemens

    PowerTechnologiesInternational(SiemensPTI)

    The Capacity Value of Wind (continued)

    At the end of the day the ELCC of wind is the additional loadthat one can serve when wind is added without degrading thetarget reliability level

    Source: Avista Wind Integration StudySource NREL The Capacity Value of Wind