sunzia southwest transmission project february 27 · pdf file · 2017-02-28euci...
TRANSCRIPT
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 0
SunZia Southwest
Transmission
Project
September
2011
EUCI 2017 Western Transmission SummitSunZia Project Case StudyFebruary 27, 2017
SunZia Southwest Transmission Project
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 1
Project Summary
515 mile transmission project in New Mexico and Arizona
Two 500 KV AC lines providing 3,000 MW of transfer capacity to AZ and CA
Brings high-quality renewable energy to western markets
Pattern Energy was selected as the anchor customer for the first 500 kV transmission line
Obtained Declaratory Order from FERC in May 2011 for negotiated rate authority
WECC granted SunZia an Accepted Rating of 3,000 MW for two 500kV AC lines in March 2011; rating was re-confirmed in January 2015
Executed ROW Grant Agreement with BLM September 2016
Plan of Development in being prepared; NTP from BLM expected December 2017
Construction Start 1Q 2018
Commercial operation by 4Q 2020
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 4
Central NM
Wind Region
Proposed SunZia
Transmission Line
Pinal CentralSunZia East
Willow
SunZia South
3rd Party
Transmission Service
SunZia Target Market and Delivery Options
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 5
Project Owners
Shell Wind Energy
Salt River Project Tri-State G&T
SouthWestern Power/ MMR Group Tucson Electric Power
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 6
SouthWestern Power Group
Independent developer of utility-scale generation and transmission in the Desert Southwest
Project Manager/Developer of SunZia
Based in Phoenix, staff of ten: 175 years of experience, in business for 17 yrs
Major References:
» 2,400 MW CCGT Panda Gila River power plant (in operation)
» 1,000 MW CCGT Bowie Power Station (permitted)
» 600 MW Lignite CFB Rockdale Power Plant (in operation)
» 200 MW (DC) Solar PV power project (in operation)
Owned by MMR Group of Baton Rouge, LA
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 7
MMR Group
Construction services firm based in Baton Rouge, LA
22 offices in USA, Canada & overseas
In business +25 years; owned by senior management
Approximately 5,000 employees
One of the largest electrical contractors in the US
Industrial markets only: power, oil & gas, process, etc.
Built over 40,000 MWs of generation
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 8
Project Concept to Operation: 15 Years
Concept emerges in regional planning Starting 2006
Sponsors sign MOA April 2008
Submit BLM SF-299 ROW Application Sept 2008
Initiate Scoping May 2009
Draft EIS May 2012
Final EIS June 2013
Record of Decision Jan 2015
AZ CEC Permit Feb 2016
NM Location Control Permit Q2 –Q3 2017
Final Design & Engineering, Q4 2017Plan of Development, and NTP
Financial Close Q1 2018
Engineering, Procurement & Construction 2018-2020
Commercial Operation Q4 2020
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 9
Upcoming Activity
2022 2023 2024 20252015 2016 2017 2018 2019 2020
Commercial Operation
2021
BLM issued Record of Decision
Arizona Corporation Commission issued Certificate of Environmental Compatibility
BLM-SunZia executed ROW Grant
ROW Acquisition: Private & State Trust
Interconnection Agreements
Engineering, Design and Plan of Development
Financial Close
Engineering, Procurement & Construction
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 11
New Mexico Transmission Line Location Approval
The location of all transmission lines capable of voltage of at least 230 kV that are: (1) connected to “large capacity” generation plants – i.e., plants with a capacity of 300,000 kW or more; and (2) that are proposed by “persons” and “public utilities.” (NMSA 1978 § 62-9-3(C); NMAC 17.9.592.7 (A))
“Transmission Line” is defined as “any electric transmission line and associated facilities designed for or capable of operations at a nominal voltage of two hundred thirty kilovolts or more, to be constructed in connection with and to transmit electricity from a new plant for which approval is required.” NMSA 1978 § 62-9-3(C))
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 12
The Location Approval Process applies to transmission lines providing electric service within or outside of New Mexico.
Location Approval is obtained by filing an application with the PRC.
SunZia plans Application filing in February - March 2017 time frame.
The PRC may deny or approve the application within 6 months.
The PRC may not act unless notice and public meeting(s) are held.
The PRC may approve without a meeting if no protests are filed within 60 days of the notice date. (NMSA 1978 § 62-9-3).
New Mexico Transmission Line Location Approval
13SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017
SunZia Southwest Transmission Project
Plan of Development
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 14
Final Plan of Development Outline
1. Introduction2. Project Management3. Project Components4. Project Construction5. Operation and Maintenance6. Mitigation of Environmental Concerns
Appendix A - Construction ConsiderationsAppendix B - Biological ConsiderationsAppendix C - Cultural and Paleontological ConsiderationsAppendix D - Other Special Resource Considerations and Mitigation MeasuresAppendix E - Stormwater Pollution and Prevention PlanAppendix F - Right-of-Way Preparation, Reclamation, and Monitoring Framework Plan
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 15
POD Implementation Plan
Project Initiation Project Kick-off Meeting – September 29, 2016 Initial Engineering – October 2016 to January 2017
Resource Surveys Cultural Resources Class III – October 2016 to March 2017 Biological Resources – October 2016 to February 2017 Paleontological Resources – November 2016 to January 2017 Jurisdictional Delineation – October 2016 to February 2017 BLM and Agencies Review Resource Survey Reports – February to August 2017
Plan Of Development Update Preliminary POD, Prepare Draft POD (Volume I) – April to June 2017 Prepare Draft POD (Volume II) – April to August 2017 BLM Review Draft POD – May to August 2017 BLM Review Draft Final POD – September to October 2017 BLM Approve Final POD – December 6, 2017
Notice to Proceed: December 29, 2017
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 16
Resource Surveys
Cultural Resources – Class III Pedestrian Survey
Biological Resources – ESA/Sensitive Species, Eagle Nests,
Native Plants, Noxious Weeds
Paleontological Resources – Pedestrian Survey of Fossil
Localities
Jurisdictional Delineations – Clean Water Act, Section 404
(ACOE)
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 20
2,000+ Miles of Routes Studied(2009-2013)
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 21
BLM Cooperating Agencies in EIS
1. Arizona State Land Department
2. Arizona Game and Fish Department
3. Arizona Department of Transportation
4. Department of the Army, Fort Huachuca
5. Department of Defense, Energy Siting Clearinghouse
6. Department of the Army, Fort Bliss Army Installation Base
7. Department of the Army, White Sands Missile Range
8. U.S. Air Force, Holloman Air Force Base
9. U.S. Fish & Wildlife Service
10. U.S. Army Corps of Engineers
11. Bureau of Indian Affairs
12. National Park Service
13. New Mexico State Land Office
14. New Mexico Spaceport Authority
22SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017
Certificate of Environmental Compatibility from the Arizona
Corporation Commission
SUNZIA SOUTHWEST TRANSMISSION PROJECT FEBRUARY 27, 2017 23
Arizona CEC
September 2, 2015: Filed an application for an Arizona Certificate of Environmental Compatibility (CEC) from the AZ Power Plant & Line Siting Committee (LSC)- case No. 171
» 13 days of LSC hearings held in Willcox, Tucson, Casa Grande and Florence
» Two field tours
» One minor route change to avoid SaddleBrooke Ranch residential development
November 19, 2015: LSC issued CEC by unanimous vote
February 22, 2016: ACC issued Decision No. 75464 approving CEC