summer construction projects update august 2, 2012
TRANSCRIPT
Summer Construction Projects UpdateAugust 2, 2012
Summer Construction Projects UpdateAugust 2, 2012
Capital Project Team
Mike Mollica, Capital Projects Coordinator and Facilities Development Division Manager
Scott Hendrix, Project Manager and Small Capital Projects Manager
Capital Project Costs Summary
Total Project Budgets - Large Cap $2,725,000
Total Project Budgets - Small Cap $ 425,000
$3,150,000
Facilities DevelopmentLarge Cap Projects
Burnley-Moran Elementary: Building Envelope Restoration CHS Stadium: Bleacher Replacement CHS Stadium: Field Lighting Replacement MLK-PAC Smoke Doors CATEC: Civil Rights Compliance Schools ADA Improvements – Drinking Fountains CHS Site Lighting Improvements, Phase II
Burnley-Moran ElementaryBuilding Envelope Restoration
Project Budget: $405,000
SCOPE:Correct deficiencies in the exterior building envelope of the school. The scope of work includes:
• Brick, concrete, cast stone & soapstone repairs • Masonry re-pointing & cleaning• Mortar joint repairs at window & door headers• Limestone repairs at main entry• Masonry expansion joint repairs• Exterior sealants, caulking, & painting• Site retaining wall repairs
SCHEDULE & STATUS:•Contractor Mobilization: Mon, June 11
•Lintel repair is approximately 90% complete.•NE entry canopy – requires complete demolition and re-build.
•Substantial Completion: October 12•Final Completion: November 9
A/E: Facilities DevelopmentCM: Piedmont Development Group (C’ville)
Contractor: Eastern Waterproofing & Restoration (Toano, VA)
CHS StadiumBleacher Replacements
Project Budget: $1.2M
SCOPE:
This project will provide replacement stadium bleachers, for both the home and visiting teams, at the new artificial turf field.
The project includes:• Bleacher seating for approx. 3,500 spectators.• A new press box.• Full ADA and building code compliance.• Pedestrian-scale site lighting improvements at
the stadium main entry stair.
STATUS & SCHEDULE:
•Preliminary design: COMPLETE
•Design & spec development: in progress
•Albemarle County review – submitted June 19• Stormwater: approved• Site Plan (includes E&S): pending
•Construction: late fall 2012 – April 2013
A/E: Timmons Group (Charlottesville, VA)
CHS Stadium Field Lighting Replacement
Project Budget: $150,000
SCOPE:This project will provide replacement stadium lighting at the new artificial turf field.
The existing lighting fixtures (6 pole locations) are at the end of their functional life (approx 40 years old). The fixtures do not provide sufficient field lighting to meet the VHSL standard of 50 fc (average level). The current level is 18 fc.
All new lighting shall be “dark sky” compliant.
Alb County review and approval may be required.
STATUS & SCHEDULE:
•Preliminary project scoping: COMPLETE
•Structural evaluation of existing poles: COMPLETE
•Design & spec development: in progress
A/E: Timmons (Charlottesville, VA)
MLK - Performing Arts CenterSmoke Door Replacements
Project Budget: $125,000
SCOPE:The scope of work includes removal of the existing smoke vents and installation of (8) new smoke vents over the stage at the MLK Performing Arts Center on the Charlottesville High School campus.
All roofing and electrical work is included.
STATUS:•Construction contract: COMPLETE
•Notice to Proceed: ISSUED
•Contractor now awaiting delivery of materials.
SCHEDULE:•Construction to commence: early Aug, 2012
•Substantial Completion: August 17, 2012
A/E: Facilities Development in-houseContractor: W.A. Lynch Roofing (Charlottesville, VA)
CATECCivil Rights Compliance
Project Budget: $340,000
SCOPE:The purpose of this project is to implement improvements required as a result of a recent DOE on-site audit and evaluation (ADA and Title IX).
STATUS:•Preliminary design & cost estimate: COMPLETE
•Final design (bid documents): now underway…..with an anticipated completion of Nov 1.
SCHEDULE:•Final design – Nov 1, 2012•Construction – proposed funding is FY’14 (July 1, 2013), and is contingent upon capital budget approvals.
FUNDING:This project is jointly funded by the City of
Charlottesville and Albemarle County (50/50 split).
A/E: Train & Partners Architects (Charlottesville, VA)
Schools ADA ImprovementsDrinking Fountains
Project Budget: $130,000
SCOPE:This project will replace selected water fountains (35) at City school facilities (all campuses), with water fountainsmanufactured and installed in compliance with 2010 ADA (Americans with Disabilities Act) Regulations andGuidelines.
STATUS & SCHEDULE:
•Final design: COMPLETE
•Bid Opening: June 22, 2012• W.E. Brown is the low bidder.
•Contract Execution: COMPLETE
•Contractor Mobilization: August, 2012
•Substantial Completion: April 5, 2013•Final Completion: April 5, 2013
A/E: Facilities Development in-houseCM: Facilities Development in-houseContractor: W.E. Brown (Charlottesville, VA)
CHS – Site Lighting Improvements (Phase II)
Project Budget: $375,000
Phase 1Phase 2
Phase 3
Scope:Install modern LED exterior lighting system for project area designated as Phase II on the approved site plan.Repave after installation of new lighting.
Status:
•Phase I work is complete•Phase II design and bidding is complete; work has been awarded•Phase II work is underway
Schedule:•On-site work began: July 16 •Boring, base construction and most disruptive work to be completed by August 21•Final Completion: September 28
A/E: AMT Engineering Consultants (Richmond, VA)CM: Ted Horn, Martin-Horn CMContractor: B&B Electric (Charlottesville/Ashland)
Facilities DevelopmentSmall Cap Projects
Buford Cafeteria Sound System Burnley-Moran Serving Line Replacement CCS Bells & Intercom Upgrades, Phase I CHS Boys Locker Room Renovation CHS Penthouse Door Replacement CHS Post Grad (Parkside) Building Clark Main Sign Johnson Admin Renovation Johnson Misc. Classroom Carpet Replacement MLK-PAC Stage Curtain Replacement MLK-PAC Rigging Maintenance Venable Stage Floor Restoration
Buford Cafeteria Sound/PA System
Scope:Modify existing wall opening to accommodate new sound rack and equipmentInstall new PA sound system for cafeteria; integrate existing TV monitors
Status:Contracts have been awarded
Schedule:Millwork modifications are completePA equipment and commissioning scheduled for August 13 - 17
A&E: FD Staff
CM: FD Staff
Contractor: Heinz Musitronics/Pro AV & Blue Ridge Millwork
Scope:Modify existing wall opening to accommodate new sound rack and equipmentInstall new PA sound system for cafeteria; integrate existing TV monitors
Status:Contracts have been awarded
Schedule:Millwork modifications are completePA equipment and commissioning scheduled for August 13 - 17
A&E: FD Staff
CM: FD Staff
Contractor: Heinz Musitronics/Pro AV & Blue Ridge Millwork
Project Cost $5,000
Burnley-Moran Serving Line
Scope:
Replace existing cafeteria buffet serving line Modify electrical service as required
Status:
Scope development is complete Client and Health Dept review is complete Contract has been awarded
Schedule:
August 2: Demo of existing equipment August 2-15: Window for custodian to clean/wax
floor; and, for City electricians to re-work electrical August 16-17: Installation and commissioning of
new equipment
A/E: FD StaffCM: FD StaffContractor: Hooten Equipment Co.
Scope:
Replace existing cafeteria buffet serving line Modify electrical service as required
Status:
Scope development is complete Client and Health Dept review is complete Contract has been awarded
Schedule:
August 2: Demo of existing equipment August 2-15: Window for custodian to clean/wax
floor; and, for City electricians to re-work electrical August 16-17: Installation and commissioning of
new equipment
A/E: FD StaffCM: FD StaffContractor: Hooten Equipment Co.
Project Cost $20,000
CCS Elementary Schools – Intercom & Bell System
Upgrades Phase IScope:Systematically replace bell and intercom systems in all CCS elementary schools
Status:Contract is in placeWork has been completed at Greenbrier, Johnson, & Venable
A&E: FD Staff and CCS Staff
CM: CCS IT Staff
Contractor: Telecor/Hudson-Payne
Scope:Systematically replace bell and intercom systems in all CCS elementary schools
Status:Contract is in placeWork has been completed at Greenbrier, Johnson, & Venable
A&E: FD Staff and CCS Staff
CM: CCS IT Staff
Contractor: Telecor/Hudson-Payne
Project Cost $ 50,000 (Phase I)
CHS Boys Locker Room Restroom
Scope: Renovate restroom
– Replace ceramic tile– Install new toilet compartment partitions– Re-paint– Install select new toilet accessories
Reconfigure fixtures to improve ADA compliance
Status: Design and IFB is complete IFB has been issued & work has been awarded Work is underway…approximately 80% complete
Schedule: Work Started: June 25 Substantial Completion: August 10 Final Completion: August 17
A/E: FD StaffCM: Ted Horn, Martin-Horn CMContractor: Snow’s
Scope: Renovate restroom
– Replace ceramic tile– Install new toilet compartment partitions– Re-paint– Install select new toilet accessories
Reconfigure fixtures to improve ADA compliance
Status: Design and IFB is complete IFB has been issued & work has been awarded Work is underway…approximately 80% complete
Schedule: Work Started: June 25 Substantial Completion: August 10 Final Completion: August 17
A/E: FD StaffCM: Ted Horn, Martin-Horn CMContractor: Snow’s
Project Cost $30,000
CHS Mechanical Penthouse Door Replacement
Scope:
Have all exterior door sets for each of the six mechanical penthouses replaced
Replace all hardware and paint new doors
Status:
Scope development is complete Contract has been awarded
Schedule:
Demolition is complete Doors have arrived on site and installation is
beginning All work is scheduled to be complete by August 10
A/E: FD StaffCM: Ted Horn, Martin-Horn CMContractor: Stonehaus Construction (Charlottesville)
Scope:
Have all exterior door sets for each of the six mechanical penthouses replaced
Replace all hardware and paint new doors
Status:
Scope development is complete Contract has been awarded
Schedule:
Demolition is complete Doors have arrived on site and installation is
beginning All work is scheduled to be complete by August 10
A/E: FD StaffCM: Ted Horn, Martin-Horn CMContractor: Stonehaus Construction (Charlottesville)
Project Cost $22,000
CHS Post High Facility
Scope: Provide/construct space for new post-grad program Utilize available CATEC modular building shell;
move to CHS site Finish out the building Modify the building for universal design / ADA
compliance
Status & Schedule: Work is complete The project has been turned over and they have
begun installation of furniture, appliances, etc.
A/E: Anhold/Gaines Group (Charlottesville, VA)CM: Martin-Horn CM Contractor(s): Building Prep & ADA Ramp Packages: Northstar LLCWaterproofing & Electrical: Harrisonburg ConstructionMoving: Snead’s Mobile Home ServiceExterior & Trim: Studio D AssociatesHVAC: Clyde E SmithInterior and Insulation: StonehausPlumbing: AP PlumbingPaint: Piedmont Paint and Finish
Scope: Provide/construct space for new post-grad program Utilize available CATEC modular building shell;
move to CHS site Finish out the building Modify the building for universal design / ADA
compliance
Status & Schedule: Work is complete The project has been turned over and they have
begun installation of furniture, appliances, etc.
A/E: Anhold/Gaines Group (Charlottesville, VA)CM: Martin-Horn CM Contractor(s): Building Prep & ADA Ramp Packages: Northstar LLCWaterproofing & Electrical: Harrisonburg ConstructionMoving: Snead’s Mobile Home ServiceExterior & Trim: Studio D AssociatesHVAC: Clyde E SmithInterior and Insulation: StonehausPlumbing: AP PlumbingPaint: Piedmont Paint and Finish
Interior – Main Room Interior - Kitchen
Project Cost $165,000
Clark Main Sign
Scope:
Design and have fabricated/installed a new monument sign for the site; maintain consistent brand imaging with the other CCS elementary schools
Coordinate with CCS and the Belmont Neighborhood Association
Coordinate with NDS regarding code allowances and BAR requirements
Status: Preliminary design is complete and was approved
by CCS and stakeholders; however, P&R review determined likely risk to roots of nearby Elm
Re-design of concept has been completed and is under review by Neighborhood Association
Schedule: TBD…contingent upon client, stake-holder, and
NDS approvals
A/E: FD StaffCM: FD StaffContractor: TBD
Scope:
Design and have fabricated/installed a new monument sign for the site; maintain consistent brand imaging with the other CCS elementary schools
Coordinate with CCS and the Belmont Neighborhood Association
Coordinate with NDS regarding code allowances and BAR requirements
Status: Preliminary design is complete and was approved
by CCS and stakeholders; however, P&R review determined likely risk to roots of nearby Elm
Re-design of concept has been completed and is under review by Neighborhood Association
Schedule: TBD…contingent upon client, stake-holder, and
NDS approvals
A/E: FD StaffCM: FD StaffContractor: TBD
Project Cost $10,500
Johnson Misc. Interior Upgrades
Scope:
Replace floor finish in Main Office suite Replace stair finishes Modify select pieces of millwork in Main Office suite
Status & Schedule:
Design is complete Contract award is complete All work is complete
A/E: FD StaffCM: FD StaffContractor(s):
Casework: Blue Ridge MillworkFlooring: B&L Floorcovering
Scope:
Replace floor finish in Main Office suite Replace stair finishes Modify select pieces of millwork in Main Office suite
Status & Schedule:
Design is complete Contract award is complete All work is complete
A/E: FD StaffCM: FD StaffContractor(s):
Casework: Blue Ridge MillworkFlooring: B&L Floorcovering
Project Cost $16,500
Johnson Misc. Classroom Carpet
Scope:
Replace failing carpet in two classrooms
Status:
Work has been bid and awarded Installation is scheduled for August 7
A/E: FM Staff CM: FM StaffContractor: B&L Flooring, Richmond, VA
Scope:
Replace failing carpet in two classrooms
Status:
Work has been bid and awarded Installation is scheduled for August 7
A/E: FM Staff CM: FM StaffContractor: B&L Flooring, Richmond, VA
Project Cost $7,000
MLK-PAC Stage Curtain Replacement
Project Cost $50,000
Scope:
All curtains have exhausted useful life and must be replaced in order to maintain proper operation and safety of the facility.
Status & Schedule:
Draft IFB and drawings have been developed and are nearly ready for issuanceWork should occur early Fall 2012
A&E: FD Staff
CM: FD Staff
Contractor: TBD
MLK-PAC Rigging Maintenance
Project Cost $45,000
Scope:Replace/upgrade stage rigging components identified in 2009 study as being deficient or inappropriate for the intended use.
Status:In-House – by MLK-PAC staff:
– Replacement purchase line rope is complete– Replacement of all rope locks is complete
Out-sourced – Most work is to be out-sourced as contracted services; a draft IFB scope has been defined and sent to the PAC manager for review and comment.
Schedule:TBD (pending client review and approval of scope)
A&E: FD Staff
CM: FD Staff/PAC Staff
Contractor: PAC Staff and TBD
Venable Stage Floor Renovation
Scope:
Restore and refinish wooded T&G floor at the stage
Status:
Work has been bid and awardedWork has not yet begun
Schedule:
To be completed by August 14, 2012
A&E: FD Staff
CM: FD Staff
Contractor: DuPrey’s Fine Floors
Scope:
Restore and refinish wooded T&G floor at the stage
Status:
Work has been bid and awardedWork has not yet begun
Schedule:
To be completed by August 14, 2012
A&E: FD Staff
CM: FD Staff
Contractor: DuPrey’s Fine Floors
Project Cost $ 4,000
Questions…Discussion…Feedback