suggestions, explanations and guidance for the ... · pdf filesuggestions, explanations, and...
TRANSCRIPT
1
Suggestions, Explanations and Guidance for the Implementation of the Requirements of the ISO/TS 16949:2009* in the Chemical Industry
October 2009
* Technical specification ISO/TS 16949:2009, third edition 2009-06-15 Quality management systems - Particular requirements for the application of ISO 9001:2008 for automotive production and relevant service part organizations This document was prepared by a work group of QM experts of the Verband der Chemischen Industrie e.V. (VCI). Copyright for this text is held by VCI. Dr. Harmut Lardon, BASF SE Dr. Ilka Beuermann, LyondellBasell Industries Norbert Dolezal, Dow Corning GmbH Thomas Kirsch, Albis Plastic GmbH Dr. Karl Moser, Evonik Degussa GmbH Herr Hermann Köhler Verband der Chemischen Industrie e. V. (VCI) Abt. Wissenschaft, Technik und Umwelt Bereich Produktsicherheit Mainzer Landstraße 55 60329 Frankfurt am Main, Deutschland Tel.: +49 069-2556-1400 Fax: +49 069-2556-2400 E-Mail: [email protected]
2
Preface
This brochure may not be used as a basis for certification.
It should provide - from the perspective of experts in the chemical industry, who have
already gained experience in working with the automotive industry requirements –
suggestions, explanations, and guidance for the implementation of the requirements
of ISO/TS 16949:2009 – even if a corresponding certification is not intended.
If a customer does not require a certification based on ISO/TS 16949, e. g. when
supplying raw materials, and if the customer accepts instead a certification according
to ISO 9001:2008 as well as a verification on meeting requirements from ISO/TS
16949, it is recommended to get a clear agreement on the extent of meeting the
automotive requirements.
The ISO/TS 16949 was developed for a QM system for automotive production, and
relevant service part organizations (see ISO/TS 16949:2009, chapter 0.5).
The character and requirements of the procedures and processes in the chemical
industry, however, are in some essential aspects different from those of most of the
automotive suppliers, who provide finished components "just in time" for assembly.
Understandably, the examples, mentioned in this brochure, can not cover the
complexity and diversity of the chemical industry, and therefore do not claim to be
complete.
3
Table of contents
Suggestions, explanations and guidance for the ISO/TS 16949:2009
1 Scope
Page
5
2 Normative references 5
3 Terms and definitions 5
4 Quality management system 7
5 Management responsibility 9
6 Resource management 11
7 Product realization 14
8 Measurement, analysis, and improvement 27
A Explanations for the ISO/TS 16949:2009 annex A 37
B Supplementary literature for the ISO/TS 16949:2009 40
4
1 Scope
1.1 General
The extent and contents of the QM system monitoring (corporate
headquarters, design and development labs, sales units) are to be
agreed upon, in detail, with the respective certification company or
the respective customer. While doing so, the current IATF
certification rules must be taken into account. For example: It is
possible to reduce the effort of external auditing, by using a
corporate audit scheme, or by extending an already existing ISO
9001 certification. Furthermore, not all processes must be audited
during each external audit.
1.2 Application
Customer specific requirements of the respective customers on the
QM system of their suppliers are to be considered in many cases, in
addition to the application of the ISO/TS 16949:2009. Such
customer specific requirements are included in the certification
audits, too.
2 Normative references
No need for further explanation in regard to ISO/TS 16949:2009.
3 Terms and definitions
In the German version of the ISO/TS 16949:2009, published by
VDA-QMC, the terms were re-sorted in alphabetical order, in
contrast to the DIN version, published by the Beuth publishing
company, which maintained the order of the original English version.
It is therefore important to be extra careful when citing term
numbers.
3.1 Terms and definitions for the automotive industry
Some ISO/TS 16949:2009 definitions were explained in the provided
VCI interpretations, additional terms were added as of chapter
section 3.1.13.
3.1.1 Laboratory scope
No need for further explanation in regard to ISO/TS 16949:2009.
3.1.2 Special characteristic
No need for further explanations in regard to the ISO/TS
16949:2009; a more detailed definition can be found in PPAP, 4th
edition, March 2006, annex F7.1
5
3.1.3 Remote location
Remote locations in the chemical industry could be, for example:
corporate headquarters, design and development laboratories, sales
units, logistics units and marketing units, which could be performed
by external enterprises as “outsourced processes” as well.
3.1.4 Error proofing
Tools to prevent errors are risk assessments (e.g. FMEA, risk
analyses, statistical planning of experiments – DOE), corrective and
preventive measures.
3.1.5 Laboratory
No need for further explanation in regard to ISO/TS 16949:2009.
3.1.6 Design responsible organization
No need for further explanation in regard to ISO/TS 16949:2009.
3.1.7 Manufacturing
According to the current interpretation, production materials are
processed materials or semi-finished products, which will become
parts of the automobile with the end customer.
3.1.8 Control plan
No need for further explanation in regard to ISO/TS 16949:2009,
see annex A1.
3.1.9 Site
No need for further explanation in regard to ISO/TS 16949:2009.
3.1.10 Predictive maintenance
Condition-based maintenance, including planned revision shut off
and maintenance activities based on machine-aided diagnosis (e.g.
vibration measurement, temperature monitoring, cooling water
analysis).
3.1.11 Preventive maintenance
Time controlled maintenance; it’s based on statistical experience
concerning the life expectancy of equipment parts, or based on
manufacturers’ recommendations.
3.1.12 Premium freight
No need for further explanation in regard to ISO/TS 16949:2009.
6
3.1.13 Effectiveness
The extent in which planned activities are realized and planned results
are achieved.
3.1.14 Efficiency
The relationship between the result achieved and the resources used.
3.1.15 Verification
Confirmation, through the provision of objective evidence, that
specified requirements have been fulfilled (according to ISO 9000).
3.1.16 Validation
Confirmation, through the provision of objective evidence, that the
requirements for a specific intended use or a specific intended
application have been fulfilled (according to ISO 9000).
3.1.17 Nonconformity elimination
Correction of an acknowledged nonconformity without affecting the
error cause of the nonconformity.
3.1.18 Corrective action
Elimination of the cause of an acknowledged nonconformity with the
goal to prevent the nonconformity from recurring.
3.1.19 Preventive action
Elimination of possible causes of potential nonconformities.
3.1.20 Continual improvement
Recurring activities in order to increase the ability to fulfill
requirements.
4 Quality management system
4.1 General requirements
The control of outsourced processes should include that process
audits are conducted (comp. ISO 9001:2008, last section in chapter
4.1, in combination with chapter 8.2.2).
4.1.1 General requirements – supplemental
If an organization has outsourced a process, which affects the ability
to deliver products, which meet requirements of customers, laws or
regulations, this process cannot just be ignored or be excluded from
the QM system of the organization. On the contrary, the organization
has to prove that this process is being sufficiently monitored, to
7
ensure that the requirements of ISO 9001:2008 or any other
requirements of the implemented QM system are fulfilled.
This monitoring should, if possible, be performed by means of a
contractual agreement with the provider of the outsourced process,
e.g. by documenting:
a) QM system requirements, including process monitoring,
measurement methods, performance indicators, reports on results
b) specifications and performance check, compliance check of
regulatory and statutory requirements
c) On-site inspections, verifications, audits.
Examples of outsourced processes, of which the requirements
have influence on the product conformity:
Logistics: filling, packaging, disposition, shipment, transport
Service: Maintenance, repairs, IT-support
Production or production steps: re-works, refining stages like the
coloring of plastics, acquisitions
Product inspection in external test laboratories: analyses,
analysis certificates
4.2 Documentation requirements
4.2.1 General
The quality policy of an organization may be included in a statement
of the whole company policy. The policy may be broken down into
different levels of the organization.
The quality objectives should be broken down into different levels of
the organization.
4.2.2 Quality manual
The quality manual may be included in a general or comprehensive
management manual, in which other system requirements are
described, too, e.g. safety management, environmental management,
risk management, etc.
In addition to the six documented procedures, required by ISO
9001:2008, (procedures for the control of documents, control of
records, internal audit management, control of nonconforming
products, corrective actions, preventive actions), at least one further
procedure must be documented for the ISO/TS 16949:2009 (training).
It is important to display the interaction between the processes in an
appropriate way.
8
4.2.3 Control of documents
No need for further explanation in regard to ISO 9001:2008.
4.2.3.1 Engineering specifications
The prescribed interval of 2 working weeks for checking the
specifications, can not always be kept in the chemical industry,
particularly because the interdisciplinary communication channels
may be very different in regard to the sources and the relevant
organization units, e.g. in regard to:
Disclaimers in orders
Internet sources, partly with restrictive access
QM agreements with specifications, liability clauses, etc.
In critical cases, an alternative time schedule must be agreed upon
with the customer.
4.2.4 Control of records
No need for further explanation in regard to ISO 9001:2008 and
ISO/TS 16949:2009.
4.2.4.1 Records retention
Customers’ requirements relating to records, which go beyond statutory
requirements, must be agreed upon in an appropriate way.
5 Management responsibility
5.1 Management commitment
The "top management" is explained in the IATF guidelines for ISO/TS
16949, chapter 5.1.1 and must be clearly defined in each case, to
guarantee that the actual top management will be involved adequately.
5.1.1 Process efficiency
Explanations can be found in the IATF guidelines for the ISO/TS 16949,
chapter 5.1.1
5.2 Customer focus
It is a good practice that top management defines indicators, which
make it possible to measure the customer satisfaction.
5.3 Quality policy
No need for further explanation in regard to ISO 9001:2008.
9
5.4 Planning
5.4.1 Quality objectives
No need for further explanation in regard to ISO 9001:2008.
5.4.1.1 Quality objectives – upplemental
A business plan is a document of top management, which contains short-
term, mid-term, and long-term strategies, plans, and overriding objectives;
the business plan may be one document or several individual documents.
5.4.2 Quality management system planning
No need for further explanation in regard to ISO 9001:2008
5.5 Responsibility, authority and communication
5.5.1 Responsibility and authority
No need for further explanation in regard to ISO 9001:2008
5.5.1.1 Responsibility for quality
Related to the specific shifts all production processes have personnel in
charge (e.g. shift supervisor), who, in case of quality problems, will trigger
the pre-defined shift overlapping information chain.
Due to the process design or for safety reasons, in the chemical industry,
it is usually not possible to stop a production immediately. For example: it
takes several days to shut down high pressure or polymerization
processes. Some discontinuous processes can not be stopped until the
chemical conversion has been completed.
Products that do not meet the specifications, as they were produced
during a malfunction, are locked out. Then they are either reworked,
brought back to production or treated as waste.
5.5.2 Management representative
No need for further explanation in regard to ISO 9001:2008
5.5.2.1 Customer representative
Usually, the customer representative is located in Sales, Technical
Support, Marketing, Design and development, or Product Management.
For more information see IATF guidelines for ISO/TS 16949, chapter
5.5.2.1.
5.5.3 Internal communication
The communication regarding the effectiveness of the quality
10
management, can, for example, be accomplished by adequate
visualization of trends of meaningful indicators with reference to the own
working environment.
5.6 Management review
5.6.1 General
Management reviews are usually performed once a year, if possible
coupled with the business planning. The management review may also be
performed more frequently, if required.
5.6.1.1 Quality management system performance
Advanced explanations can be found in the IATF guidelines for the
ISO/TS 16949, chapter 5.6.1.1.
5.6.2 Review input
No need for further explanation in regard to ISO 9001:2008.
5.6.2.1 Review input - supplemental
In addition to the inputs listed in ISO 9001:2008, chapter 5.6.2 under a) -
g), other inputs, as mentioned elsewhere in ISO/TS 16949:2009, are
useful for the review:
Continuous adequacy of the quality policy (5.3)
Performance in comparison to quality objectives (5.4.1)
Quality related losses (costs of poor quality) (5.6.1.1)
Actual and potential failures (FMEA) during the stage of use (5.6.2.1)
Additional freight costs (8.2.1.1)
Design and development indicators (7.3.4.1)
Maintenance objectives (7.5.1.4)
5.6.3 Review output
No need for further explanation in regard to ISO 9001:2008.
6 Resource management
Chapter 6 is a logical supplemental of chapter 5; here top management is
asked to decide on the resources needed. There are two main
requirements for an effective management system:
Active participation of top management
Provision of adequate resources
6.1 Provision of resources
No need for further explanation in regard to ISO 9001:2008.
11
6.2 Human resources
6.2.1 General
The required personnel criteria "education, training, skills and
experience", as listed in the ISO 9001, do not only refer to activities,
which have a direct influence on the quality of products or services, but
also refer to all activities of personnel that have an influence on the
functionality of the quality management system.
An adequate provision of human resources, works best when based on:
Job and function descriptions
Quality plans
Qualification matrices
Shift and superiors' plannings
Evaluations of the general and individual workloads
6.2.2 Competence, training and awareness
No need for further explanation in regard to ISO 9001:2008.
6.2.2.1 Product design skills
In the chemical industry, product design is performed by qualified
personnel like chemists, engineers, lab technicians. Ensuring the
qualification of personnel with product design responsibility, can be
supported by means of, e.g.:
Qualification matrices
Job and function descriptions
6.2.2.2 Training
6.2.2. a, b, c) The procedure of the qualification matrix is widespread in
the industry. In the qualification matrix, the required competences are,
according to the job description, subdivided into several levels,
e.g.:
1. Level: Competent to complete an assignment under supervision
2. Level: Competent to complete an assignment independently
3. Level: Competent to train others
6.2.2 c) Suitable methods for evaluating the effectiveness of the adopted
measures are in parts included in the Kirkpatrick Model, e.g.:
Self-assessment of the training measures by the participants
Measuring the increase of knowledge by taking a test before and after
the training
12
Changes in behavior – usually 6-12 months after training
Management review of the added value based on the training
measures of the past 12-18 months.
Internal and external audits
Appraisal interviews
Interactive kinds of training
6.2.2.3 Training on the job
In the chemical industry, on-the-job training for all personnel (permanent
and contracted) is usually the state of the art. Training records are to be
kept.
6.2.2.4 Employee motivation and empowerment
The motivation of employees can be promoted and, to some extent, be
measured by instruments like e.g. information, appraisal interviews,
regular staff meetings, employee surveys, social benefits, target settings'
and bonus system, premiums, empowerment, recognition, employee
suggestion system of the company.
6.3 Infrastructure
No need for further explanation in regard to ISO 9001:2008.
6.3.1 Plant, facility and equipment planning
In the chemical industry, the plant, facility and equipment planning is
usually exactly defined by means of authority approvals. The IATF
guidelines for ISO/TS 16949 contain methods for the evaluation of the
productivity and effectiveness of existing operations.
6.3.2 Contingency plans
In the chemical industry, it is customary to create plans for unexpected
events. This includes for example an early-warning system for chemicals
that are to be classified differently in the future (e.g. carcinogenic,
reprotoxic, etc.), possible supply shortfalls in the availability of raw
materials, as well as strike, power blackout, logistical problems, IT-
availability, fire, facility breakdowns, missing spare parts, pandemics. In
the chemical industry, it is customary to appoint a crisis management
team, which is responsible for leading to decisions in cases of
emergency.
6.4 Work environment
An adequate work environment is usually part of the facility design.
6.4.1 Personnel safety to achieve conformity to product requirements
This issue is especially affected by legal specifications regarding permits
13
and employer's liability insurance associations. Explanations can be found
in the IATF guidelines for the ISO/TS 16949.
6.4.2 Cleanliness of the premises
Examples can be found in the IATF guidelines for the ISO/TS 16949. A
systematic procedure is the Japanese 5S method.
7 Product realization
7.1 Planning of product realization
In the chemical industry, the product realization usually consists of
several phases, like e.g.:
defining the product requirements as well as verification and validation
criteria
product design
production process design
product introduction, including product validation, initial production,
etc.
Some companies already have a standardized procedure, which has
been adapted to the technology of the chemical industry, including project
check lists and project milestones. Companies that, for example, plan and
manufacture chemical engineering equipment, usually have a customized
project plan.
Further details can be found in section 7.3.1 Design and development
planning. Detailed realization suggestions can be found, for example, in
the reference manual Advanced Product Quality Planning and Control
Plan (APQP) or the VDA volume "Entwicklungsabläufe" (design and
development courses).
Quality management plan
The sum of all documents that ensure that the requirements for the
product to be designed and its production process, defined by the
customers as well as by the own organization, may be called "quality
management plan". For example, it could contain a project plan (including
critical path), check lists and breakpoints, as well as summaries and
minutes of management reviews and business plans regarding the
product to be realized (resource management).
Concrete requirements regarding the design of the quality management
plan are not existing in the ISO/TS 16949.
Note 2 is not required in the ISO/TS 16949, because concrete
specifications are listed in chapter 7.3.
14
7.1.1 Planning of product realization – supplemental
Technical customer specifications not only refer to product properties, but
also, for example, specifications regarding the release procedure, test
criteria, test procedures, material exclusion lists, packing specifications,
special labels ("VDA tag ", barcode, customer part number),
communication systems that are to be used, (EDI, CAD, etc.), as well as
entries into the IMDS (International Material Data System).
These documents must be controlled, just as any other document with
instructions.
7.1.2 Acceptance criteria
Acceptance criteria are understood to be detailed specifications, which
are used to monitor the product properties, e.g.: Reference samples
(master samples), transition samples, sampling plans, test frequency,
based on the – perhaps preliminary - process capability.
Attributive data sampling means that a random sample from an entity is
inspected on the existence of one characteristic, e.g. the decision if the
sample characteristic corresponds with the characteristic of the master
sample (e.g. is the sample a white free-flowing powder, without any
impurities). The result of such an inspection can be: present / not present,
or good / bad.
Acceptance criterion "zero defects", means that all inspected samples
must have the attribute "good". In case of batch operation, usually a
100% inspection is performed, inspecting a representative sample from
each batch. In case of continuous production, the location of the sampling
and the inspection frequency must be determined (also see section
8.2.3.1 Monitoring and measurement of production processes).
7.1.3 Confidentiality
How to deal with confidential information should be defined in a contract
in an individual case. Confidential electronic data should be encrypted
when exchanged between contractual partners. The organization should
have a procedure for securing confidential information.
7.1.4 Change control
The changes that are to be controlled in the context of this chapter are
only changes that affect the quality of the product. Other process changes
or document changes are to be taken into account in chapter 4.1 and 4.2.
Changes that affect the quality of the product probably exist when in this
context the content of the control plan has to be changed. Further
explanations can be found in the IATF guidelines for the ISO/TS 16949.
Criteria for the obligation to notify changes can be included in customer-
15
agreed approaches or - as often applied in the chemical industry – in the
specification agreements. Examples can also be found in the PPAP
(Production Part Approval Process) reference manual, especially in
section 3, "Customer notification and submission requirements”.
Within the organization, protected development results (e.g. product
formulations) are classified as confidential. Since the customer purchases
quasi a black box, the changes should be validated jointly with the
customer.
Each change must be documented – in line with chapter 4.2. – with the
implementation date and, if possible, with the batch number. The change
history must include all changes up to product termination, and perhaps
beyond that. The archiving requirements of the customer and the
legislator are decisive. In addition, the VDA volume 1 "Nachweisführung"
(verification management) should be regarded.
NOTE 1: The word “agreement” in note 1 of the English original version
has been translated into German by “Genehmigung” which may possibly
not be completely appropriate. As to the general usage “agreement” could
also be translated by “Einvernehmen mit dem Kunden”. This means it’s
expected that the customer participates in the evaluation of changes, and
that an agreement is reached.
7.2 Customer-related processes
7.2.1 Determination of requirements related to the product
It is also necessary to define requirements which were not explicitly stated
by the customer, but which are needed – as far as known – for the
intended use. Users of chemical products often do not exactly know the
interactions that make the product “function”. Contrary to the production of
parts, the customer often transforms chemical products in an additional
process step, e.g. from a liquid starting material to a hard film (paint or
adhesive) or, by letting temperature and pressure work on the material,
form a molding with particular properties (see PPAP, 4. edition, chapter
F14).
Therefore it is absolutely useful when the organization – based on their
product knowledge – determines certain handling requirements, of which
the customer has not thought of or could not know of, and adds these to
the specification or the technical data sheet. However, this must not be
mixed up with a recommendation for a certain application.
"Any additional requirements considered necessary by the organization"
16
may be understood to refer to, for example, possible incorrect use, as well
as correct and safe product disposal (see note 2).
NOTE 3: Please note that also the statutory and regulatory requirements
of the country, in which the product is manufactured and marketed, must
be met.
7.2.1.1 Customer-designated special characteristics
If special characteristics were designated with the customers, these
characteristics must be marked in those documents that are used to
control these characteristics. Such documents could, for example, be:
Quality management plan
Product specification
FMEA
Control Plan
Formulation
Test instruction
In customer specific requirements, it can be defined which symbol has to
be used at what point (see IATF guidelines).
7.2.2 Review of requirements related to the product
This includes the review of non-documented customer requirements (e.g.
brought forward verbally or assumed to be self-evident), regarding
whether or not they can be met.
7.2.2.1 Review of requirements related to the product - supplemental
It may be that the customer renounces a formal review of these
requirements. It is possible that this renunciation is included in the
contract conditions in case of internet purchases.
7.2.2.2 Organization manufacturing feasibility
This means a check whether the product can be manufactured in the
required quantity and in the defined quality and be delivered on the
wanted date and price. In doing this possibly arising risks must be
estimated. Further advices can be found in the APQP reference manual
under "Team feasibility commitment and management support”.
For products from the organization's standard program (catalogue
products), it’s only necessary to review the manufacturing feasibility with
regard to the delivery date. Further explanations can be found in the IATF
guidelines for the ISO/TS 16949.
7.2.3 Customer communication
17
The responsibility for the communication with the customers must be
clearly defined. In special cases, it may be useful to agree on a fixed
contact person on both sides, e.g. key account manager, integration
champion, QM representative.
7.2.3.1 Customer communication - supplemental
The CAD data compatibility requirement is usually not relevant for
chemical industry manufacturers. It is more important to set up a network
with the planning departments of some customers, e.g. by means of EDI
as well as entering data into the IMDS (International Material Data
System).
Customers are also beginning to put their technical specifications and
customer specific standards on the internet.
Many customers assume that their requirements (e.g. on their homepage
or on the order confirmations) have been accepted, as long as the
supplier does not contradict in writing, e.g. by means of a business letter
referring to own equivalent standards.
7.3 Design and development
No need for further explanation in regard to ISO/TS 16949:2009.
7.3.1 Design and development planning
The design and development planning should be appropriate to the
complexity of the organization and of the product. APQP or VDA 4.3
describe examples of an adequate review, verification and validation of
detailed phase models.
The development phases may absolutely overlap, e.g. first considerations
regarding the production process design may already be started, even
though the formulation of the product has not yet been completed (so-
called simultaneous engineering).
7.3.1.1 Multidisciplinary approach
Multidisciplinary approach generally means that collective knowledge,
needed to fulfill a complex task, is pooled. It has been proven successful
to have multi-functional teams, with a leader who is responsible for the
product realization, from project start until the successful commercial
launch. In individual cases, it may be useful to involve specialists, like
toxicologists and legal staff, as well as customers, or strategically
important suppliers with their knowledge into the team.
7.3.2 Design and development inputs
Here, the conversion of the requirements into objectively verifiable
specifications for the developer is meant, thus that the customer
18
requirements are converted into the language of the organization. For this
purpose, the so-called Design Matrix (see PPAP – appendix F.4) or the
QFD method may be used. While doing so, requirements are
distinguished, regarding:
Shape, color, appearance
Processibility,
Function of the completed product in the product of the customer
Statutory and regulatory requirements and environmental aspects.
In the chemical industry, a detailed and specific determination of the
design and development inputs is not always possible in the early stage
of the product realization, because important product properties often only
will appear when the product will be used in the (planned) customer
product (validation).
7.3.2.1 Product design input
The requirements, regarding the product design inputs, must be
documented. For this, a list of duties, specification, graph, requirements’
profile, etc. may be used. It is recommended to record the results of the
review, too.
7.3.2.2 Manufacturing process design input
The requirements regarding the manufacturing process design input must
be documented. The four listed bullet points are mandatory inputs (for
process capability, also see 8.1, 8.2, ff.). A review must be performed.
7.3.2.3 Special characteristics
The organization is obliged to systematically check, if and to which extent
their products have special characteristics. Further explanations can be
found in the IATF guidelines for the ISO/TS 16949.
Special characteristics, which were determined by the organization itself,
could, for example, affect the processing properties, performance
characteristics or recyclability.
7.3.3 Design and development outputs
Information regarding the purchase, production and providing service,
could, for example, include the following elements:
Product specification
Physical properties
Packaging and durability
Approved raw materials sources
Sampling plans, test equipment and test methods
19
Personnel safety and environmental factors, disposal
Specifics regarding facilities, procedures, and process control
Error prevention measures and reaction plan in case of malfunctions.
It is also important to consider that the design and development outputs
are to be released. Usually, this release is performed by the responsible
design and development leader.
7.3.3.1 Product design outputs - supplemental
In accordance with the ISO/TS 16949 requirements, the terms listed in
this section are - as far as applicable - to be regarded as mandatory. If
individual listings do not apply, like for example reliability tests,
diagnostics guidelines, etc., it must be possible to account for this.
The design and development outputs should be the result of a process,
which includes measures regarding simplification, optimization, innovation
and waste reduction. Further explanations can be found in the IATF
guidelines for the ISO/TS 16949.
7.3.3.2 Manufacturing process design output
The manufacturing process design also includes the development of the
required measurement and test methods, and concludes with the
determination of the preliminary process capability. For chemical
processes, a statement on the preliminary process capability is often only
possible in a restricted extent; it is therefore allowed, with due caution, to
rely on experiences with similar processes.
The outputs listed in this section are also – if applicable - to be regarded
as mandatory. If individual listings do not apply, this must be accounted
for.
The manufacturing process design should be the result of a process,
which includes measures regarding optimization, waste reduction, lean
production and innovation. There are several helpful tools for this, like e.g.
ANDON (electronic control system of the production line), KANBAN,
SMED (Single Minute Exchange Die), Lean Manufacturing and 5S-
method. Further explanations can be found in the IATF guidelines for the
ISO/TS 16949.
7.3.4 Design and development review
Design and development reviews should be performed according to the
phase model of the design and development process. Minutes with
actions and timing are sufficient as verification.
7.3.4.1 Monitoring
Like any other process, the design and development process must also
be reviewed by means of measurement parameters / indicators in regard
20
to its effectiveness and efficiency (see section 5.6.2 "review input"). Part
of these indicators are, amongst others, risk assessment data, e.g. of the
FMEAs (also see 7.3.3.1 and 7.3.3.2), and other possible success factors.
7.3.5 Design and development verification
The goal of design and development verification is to ensure that the
design and development outputs comply with the inputs according to
section 7.3.2. This usually concerns the physical and chemical properties
of the product (e.g. density, purity, melting point, color, etc.)
Usually, lab analyses, tests, development output comparisons with similar
product formulations or record reviews are used for verifications.
The results of the verifications must ensure the conformity of the product
with the specification and must be based on controlled processes.
7.3.6 Design and development validation
Validation is one step further than verification. It can be performed as
processing tests (pilot production), simulation of specific conditions in the
lab or test field, as well as often by the customer, e.g. as field tests. This
experimental phase should be, if possible, completed before regular
ordering starts.
NOTE 2: Since the production process also with new products usually
does not change in the chemical industry, experiences from the
production of other, similar products are used. If products are
manufactured according to a new or a significantly changed process, this
process is validated regarding its ability to meet the product requirements
of the customer.
7.3.6.1 Design and development validation – supplemental
It may be necessary to adjust the own development plan to the schedule
of the customer by mutual agreement.
7.3.6.2 Prototype program
In the chemical industry, instead of prototype programs, it is custom to
perform sample production. The required facilities and tools can be
provided by the customer (e.g. robots, injection molding machine or mold,
etc.).
7.3.6.3 Product approval process
By means of the production process approval and product approval
procedure, verification shall be provided, which shows that products can
be manufactured in the required quality and quantity.
Production process approval and product approval – also first sample
approval – of chemical engineering products are understood to be in the
21
automotive industry: testing a batch, which is manufactured under
production conditions, in connection with individual verification
documents, which shall prove that the agreed specification or required
product properties are met.
The production process approval and product approval should follow the
verification of the production process (see 7.3.5 design and development
verification).
The production process approval and product approval are usually based
on the PPF – procedure (VDA, volume 2, 4th edition, 2004) or the PPAP
procedure (4th edition, 2006, mainly required in the USA). The PPF
procedure includes a process audit by the customer, according to a
regular standard or a checklist from the customer. The advantage of this
is that it is meaningful and field-proven, however, does not regard specific
features of the process engineering in the chemical industry.
The PPAP procedure takes into account the concerns of the chemical
industry. The amount of verification documents has been reduced,
because only relevant fields have to be filled out on the "bulk materials
checklist" appendix F (many fields with "NR= Not Required").
To avoid misinterpretations, some organizations in the chemical industry,
point out that the presented first sample is a product, which is subject to
fluctuations caused by raw materials and manufacturing conditions, and
which may not be considered as purchase according to sample (used to
be legally handled according to §494 BGB).
If products are already approved or listed by the OEM, a production
process approval and product approval by the customer is no longer
required. In case of catalogue products a customer's requirement for a
production process approval and product approval should be questioned
critically.
A procedure for production process approval and product approval, which
is already established within the own organization, may also be used in
regard to suppliers, if the customer does not object.
7.3.7 Control of design and development changes
Changes could be:
Change of raw materials
Product formulation
Test procedure
Specifications
Design / development changes may be required due to, for example:
Revalidation of the toxicity of a part of the formulation
Change in the statutory terms and regulations
22
Change in the applicable standards.
In general you can orientate yourself on the statement, that a change
must be reported if essential design and development documents have to
be changed.
7.4 Purchasing
7.4.1 Purchasing process
Suppliers may be selected and evaluated based on criteria like:
Certificate according to ISO 9001/ISO 14001
Satisfactory delivery performance
Creditworthiness
Price
Positive sampling result
Customer approval, if required
Availability, flexibility, delivery capability.
The delivery availability is often secured by framework agreements.
7.4.1.1 Statutory and regulatory conformity
It should be kept in mind that, when fulfilling the respective statutory and
regulatory requirements, the requirements of the country of destination
have to be met as well. In case of doubt, legal advice should be sought.
7.4.1.2 Supplier quality management system development
According to the requirement of the ISO/TS 16949 all suppliers must be
certified on the basis of ISO 9001: 2008. Unless something else was
arranged with the customer.
Otherwise, in case of a missing ISO 9001: 2008 certification of a supplier,
other measures must be taken, like e.g. supplier audits, quality assurance
agreements, or looking for alternative suppliers.
Further guidelines can be found in the IATF Sanctioned Interpretations:
SI 5 06 ISO/TS 16949:2002 7.4.1.2
http://www.iatfglobaloversight.org/docs/English%20NEW%20%20IATF
%20TS%20SIs%20Non%20Table%20Version.pdf
7.4.1.3 Customer-approved sources
This rarely applies to the chemical industry.
7.4.2 Purchasing information
In the statement of a) “requirements for approval of product, …” the
23
English word “approval” is understood as “release”.
7.4.3 Verification of purchased product
No need for further explanation in regard to ISO 9001:2008.
7.4.3.1 Incoming product conformity to requirements
No need for further explanation in regard to ISO/TS 16949:2009.
7.4.3.2 Supplier monitoring
If the customer experiences disruptions, which are caused by
nonconforming products from suppliers, which then lead to special
customer requirements (e.g. special notifications), the disruptions’ data
have to be collected and will be integrated into the supplier evaluation. On
time delivery performance and premium freight cases are further criteria
for the supplier evaluation. The costs are not the prime issue here, but
rather the kind and causes related to the incidents with premium freights.
A promotion of "supplier monitoring of the performance of their
manufacturing processes" could be performed by the organization, for
example, by providing feedback to the supplier, concerning their supplier
monitoring results. If necessary, the organization could point out
improvement potentials and motivate the supplier to take improvement
measures.
7.5 Production and service provision
7.5.1 Control of production and service provision
No need for further explanation in regard to ISO 9001:2008.
7.5.1.1 Control plan
For a definition see 3.1.8 in the ISO/TS 16949:2009. A respective form
can be found in the APQP reference manual, 2nd edition.
7.5.1.2 Work instructions
The level of detail of work instructions should fit the education level of the
employees. It is not necessary to describe standard activities, which a
skilled worker has learned during his education (e.g. titrations by a lab
worker, welding by a metal worker). Apart from that, we refer to the
detailed remarks in the IATF guidelines.
7.5.1.3 Verification of job set-ups
Job set-ups apply in the chemical industry (if applicable at all) to major
maintenance, product change, reconstruction, initial release of new
facilities, new equipment. Order changes have no meaning in chemical
24
processes, as far as job set-ups are concerned.
In case of maintenance, reconstruction or new equipment, the facility is
released after having been inspected; after a product change, the
cleanliness is attested e.g. in the cleaning protocol. The cleaning method
may depend on the type of product change.
Statistical methods usually cannot be used for job set-ups in the chemical
industry.
7.5.1.4 Preventive and predictive maintenance
see definitions in 3.1.10 and 3.1.11.
7.5.1.5 Management of production tooling
Usually does not apply to the chemical industry.
7.5.1.6 Production scheduling
In the chemical industry, production scheduling is based on orders as well
as on storage management. Due to the processes, a campaign-type of
operation can be often found in the chemical industry.
7.5.1.7 Feedback of information from service
In the chemical industry, members of the commercial or application
engineering external service gather information or customers’ problems,
e.g. in visit reports, which are then forwarded to the responsible authority.
Usually, an IT based process is used for this. This supports the fulfillment
of the statutory product monitoring obligation.
7.5.1.8 Service agreement with customer
Usually not applicable in the chemical industry.
7.5.2 Validation of processes for production and service provision
In the chemical industry, the validation of a production process is often
obtained by the verification and/or validation of the product. Compare also
7.3.6.3
7.5.2.1 Validation of processes for production and service provision –
supplemental
No need for further explanation in regard to ISO/TS 16949:2009.
7.5.3 Identification and traceability
In the chemical industry, a physical traceability is often only possible up to
the hand over point (pipework system, tank or silo). Special problems
arise in case of several reactors connected in series, as well as large
tanks, where the assignment of the raw material (batch or date) can only
25
be assured roughly, due to mixing effects during passage. Often, the link
to the respective data can only be made by means of the position
number, date and time.
7.5.3.1 Identification and traceability – supplemental
No need for further explanation in regard to ISO/TS 16949:2009.
7.5.4 Customer property
No need for further explanation in regard to ISO 9001:2008 and ISO/TS
16949:2009.
7.5.4.1 Customer-owned production tooling
Usually does not apply to the chemical industry.
7.5.5 Preservation of product
No need for further explanation in regard to ISO 9001:2008.
7.5.5.1 Storage and inventory
No need for further explanation in regard to ISO/TS 16949:2009.
7.6 Control of monitoring and measuring equipment
To prove that the monitoring and measurement requirements have been
met, it makes sense to consult the results of the statistical inspections
according to 7.6.1.
Provided that there is no traceable standard for test methods, the
following adapted procedure can be used in the chemical industry:
Calibration measurements according to the calibration schedule using
a product that serves as standard of the operation.
Creating a control chart for evaluation of the operation’s course.
Determination of the mean value and the standard deviation and
comparison with the respective specification tolerance (determination
of the Cg value).
7.6.1 Measurement system analysis
The methods that must be used for the measurement system analysis
can, for example, be found in the MSA reference manual, 3rd edition, or
in the guidelines for "Capability verification of measurement systems" (Q-
DAS). They have to be adjusted to the requirements of the test
procedures in the chemical industry.
Provided that tests are performed according to the defined test
procedures as listed in standards (e.g. ASTM, AMS, ISO), the accuracy,
linearity, stability and R&R variation of the measurement system do not
26
have to be verified again by the organization (comp. PPAP 4th edition,
appendix F, number 9).
R&R studies (Gauge Repeatability and Reproducibility Calculations of the
measurement equipment / measurement system) may be helpful for
further tests when determining the influence of tester, test method, test
equipment and test location. Similar test equipment can be grouped.
7.6.2 Calibration/verification records
It makes sense to document all calibration parameters which were
determined, also those within the tolerance limits.
7.6.3 Laboratory requirements
7.6.3.1 Internal laboratories
No need for further explanation in regard to ISO/TS 16949:2009.
7.6.3.2 External laboratories
The verification of the qualification of external commercial laboratories is
performed in a meaningful way by means of an accreditation according to
DIN EN ISO/IEC 17025. The verification of the qualification by means of a
customer audit or by a customer approved audit, which is possible
according to ISO/TS 16949, must be agreed upon individually with each
customer. This approach is often not accepted by the customer and is,
with the huge number of customers, hardly to accomplish. Customers are
usually not interested in qualifying the commercial laboratories by audits
or in approving these audits.
8 Measurement, analysis and improvement
8.1 General
The planning and implementation for demonstrating the product
conformity, requires that the inspections are defined based on
documented specifications according to inspection plans. The product
conformity is demonstrated, for example, by means of analysis certificates
or inspection documents, e.g. according to DIN EN 10204 (test report,
inspection certificate).
8.1.1 Identification of statistical tools
In the chemical industry, statistical tools are used for quality control and
for continual improvement. The SPC manual and the MSA manual of the
American OEMs, or the VDA volumes 4 or 5 can be used as reference
manuals.
27
The need for the use of statistical methods must be fundamentally
determined. This includes all processes, defined in the quality planning. If
required, statistical methods have to be used to plan and evaluate
experiments, in design and development, for quality inspections on
supplies, for process control and optimization, and for the final inspection.
In most cases the mean value and the standard deviation of the
measurement parameters are determined.
8.1.2 Knowledge of basic statistical concepts
The applicable statistical basic concepts must - if applicable in the
respective functions - be known, defined and documented. In marketing
these are, for example, tabular comparisons of sales, proceeds, costs and
deviation analyses of costs.
8.2 Monitoring and measurement
8.2.1 Customer satisfaction
No need for further explanation in regard to ISO 9001:2008 and ISO/TS
16949:2009.
8.2.1.1 Customer satisfaction – supplemental
Several methods must be applied:
a) The review of the "delivered part quality performance", required in the
ISO/TS 16949:2009, usually contains a statistical collection and
evaluation of the quality of the products delivered. The percentage ratio of
1A quality deliveries or, if applicable, ratios of minor qualities, can be
appropriate indicators for this.
The "ppm nonconformities" indication, which is often used and required in
the automotive industry, is not suitable, as these indicators usually cannot
be determined for process engineering products. The number of
manufacturing batches per year is usually in the range of dozens or some
hundreds, however not thousands or even millions. With one data point
per batch, the population for calculating ppm nonconformities is too low.
Especially in case of contaminations (e.g. rust particles), which often
occur very inhomogeneously, the relation to ppm is not obvious, since it
may apply to rejected quantity, number of particles or number of
deliveries.
b) An evaluation of the "customer disruptions, including field returns"
according to ISO/TS 16949:2009 may also be relevant for the chemical
industry. Customer problems regarding chemical industry products,
usually lead to customer complaints, or claims, which should be seen as
an opportunity and an important feedback from the market and which
28
should be controlled actively. Based on the documented claims, it should
be analyzed according to the claim reason, cause, products and
customers. It should be aimed for the use of an electronic system, which
would also make it easier to analyze complaints’ main areas and to verify
successful corrective actions.
c) The review of the "delivery schedule performance", required according
to ISO/TS 16949:2009, should contain analyses of the delivery reliability
statistics at short intervals, e.g. monthly. Delivery reliability means that the
agreed dates and quantities must be kept. Within the company, it should
be defined in detail, what "agreed date" means (e.g. date desired by the
customer, date confirmed by the own organization, shipment date, date of
arrival with the customer).
If a premium shipment is necessary to enable an in-time-delivery –
usually leading to additional costs – this must be registered and
evaluated. When the cause of the problem has been found, appropriate
corrective measures should follow shortly after.
d) “Customer notifications (formal rebukes by the customers) related to
quality or delivery problems" may include product claims or special status
notifications. The first may for example imply a special release of a time
or quantity limited delivery, the stop of design and development activities
or the exclusion from future business. Special status notifications could
lead to a revocation of the certificate. Further details can be found in the
certification rules of the automotive industry for ISO/TS 16949:2009, 3rd
edition, chapter 8.
e) In addition to the methods, which are directly required in the ISO/TS
16949:2009, an analysis may be carried out on those supplier reviews,
which customers periodically mail or post in the internet. This includes in
most cases the evaluation, if deadlines and product quality have been
met. The result usually leads to a classification as being an A, B, or C
supplier, or to similar ratings.
If the specifications are not met, the supplier (the organization) is required
to take corresponding improvement measures and to provide proof of the
realization of these measures. If the rating of the customer falls beneath a
defined limit, immediate actions must be taken. The realization and
effectiveness of the measures are to be followed up and reviewed.
Customer satisfaction analyses can also be based on periodical customer
surveys, e.g. by field staff members or by external institutes. The survey
results, as well as derived improvement measures should be recorded
systematically and should be made available within the company for
analyses (Customer Relationship Management).
29
A lack of customer feedback should not automatically be regarded as an
indication of customer satisfaction.
8.2.2 Internal audit
No need for further explanation in regard to ISO 9001:2008.
8.2.2.1 Quality management system audit
System audits, according to VDA QMC or IATF, must definitely be
conducted in a process-orientated manner. In doing this, approved
customer specific requirements must be audited as well.
8.2.2.2 Manufacturing process audit
No need for further explanations in regard to the ISO/TS 16949:2009.
Helpful instructions for performing process audits can be found in VDA
volume 6.3.
8.2.2.3 Product audit
During a product audit, it will be checked whether the product
requirements for a defined production process step are met. This may
also include checking those features that are not inspected during a
regular approval inspection, or a combination with a layout inspection and
functional testing (see also 8.2.4.1).
In most cases a product audit (dock audit) is performed on a ready-for-
shipment product.
Key aspects of an audit could be:
The labelling of the packed product
packing method
shipping documents
delivery documents
product inspection results
product approval status
data traceability
special customer requirements
further product sample inspections
8.2.2.4 Internal audit plans
In the annual audit plan the system audits, the audits of all important
processes and the product audits have to be planned. While doing so, the
system requirements, as well as possible customer specific requirements
must be taken into account. This should be updated continuously.
30
8.2.2.5 Internal auditor qualification
The qualification, according to the ISO/TS 16949:2009 requirements,
includes that all internal auditors must have passed an auditor training in
line with ISO 19011 for auditing according to ISO/TS 16949:2009. This
ensures that they have and also can prove the required knowledge
regarding the preparation, execution and post-processing of internal
ISO/TS 16949 audits.
The ISO 19011 expects both an adequate auditor training and audit
experience. Therefore all ISO/TS 16949 auditors of a company should
have records, which contain information on when and with whom the
auditor training has been attended (with or without exam?), the validation
date of the auditor certificate, when the auditor attended a refresher
training and to which extent the auditor performed internal ISO/TS16949
audits during the past years.
The auditor qualification specifications may be expanded by customer
specific requirements (e.g. from FORD).
8.2.3 Monitoring and measurement of processes
All management system relevant processes and important indicators for
monitoring of the processes are to be identified.
8.2.3.1 Monitoring and measurement of manufacturing processes
The reference manuals of the automotive industry expect machine and
process capability index inspections, in association with SPC methods
(Statistical Process Control). Identifying process capabilities is often a
long-winded process, because usually only one data point is available per
batch or per time (comp. section 8.1.1 and PPAP, 4th edition, section
F.10), and does therefore not always apply to chemical processes.
Since sampling and testing of in-process samples are also time-
consuming processes (hours until days), quality control charts for
important process features can only be used in time-delay. They are
therefore not suited for process control. According to the technology of
chemical procedures, adapted appropriate statistical methods are used.
The verification of the process performance of new manufacturing
processes is usually performed by means of production tests in various
operational states (pressure, temperature, volume flow, product variants).
The results of these tests slip into the determinations in the manufacturing
control plan.
In the chemical industry, there is a distinction between continuous and
discontinuous production:
31
Discontinuous production in the chemical industry
When a product is manufactured in a discontinuous procedure, the
process parameters (e.g. pressure, temperature) and the product
properties are subject to a continuous change. It is not meaningful to use
SPC here. Instead, information about the course of the process can in this
case be taken from a graphical presentation of the parameters with
indications of the control limits.
The examination of product characteristics is often used to evaluate the
process capability.
Continuous production in the chemical industry
Basically, when manufacturing a product in a continuous procedure, the
process parameters are controlled in such a way, that the process
parameters are continuously kept constant, within specified limits, as
close to the mean value as possible (continuous process control, CPC).
Usually, an automated diagram and a statistical analysis are available,
which replace the manual control charts that were used previously.
To control and monitor the processes, electrical measuring and controlling
instrumentation as well as controlling techniques are used. Those
electrical measuring and controlling devices whose measurement
parameters are linked to the predetermined and to be maintained target
value of a quality characteristic for a product in a chemical process, and
which are therefore listed in the control plan, are regarded as quality
relevant.
A statistical normal distribution of the process and product characteristic
parameters is not existing if the production process is controlled actively,
e.g. in closed control loops. A constant intervention prevents a random
distribution. SPC methods for process controlling can not be used here.
The calculation of cp values or cpk values is methodically wrong and does
not provide correct information. In such cases, a 100% inspection is
required (see 8.2.4). A diagram with specification limits and/or warning
limits based on experiences is useful here.
The processes are conducted and monitored according to the production
control plan. In case of deviations the available reaction plans must be
followed. (compare PPAP, 4th edition).
8.2.4 Monitoring and measurement of product
A sample of the finished product is taken and inspected either after
having reached a specified reaction step, but usually from the final
reaction product. This is then representative for the batch. This approach
32
is called a 100%-inspection (comp. PPAP, 4th edition, section 2.2.11.6,
note 2).
Products of the same quality, but from different batches of a campaign,
can be merged in one lot. If, for example, the products from the
discontinuous production are collected in closed silos or tanks, a sample
may be drawn from the silo or tank after the production period (marked by
the different batches), to measure and evaluate the characteristic
parameters of such a lot.
In case of processes which respond relatively slowly to external
influences, a test frequency is justifiable, e.g. per ton, per palette, per 20
sacks, which is lower than appropriate for processes that change quickly.
If the test frequency was agreed upon with the customer, it may be
decreased upon approval by the customer.
8.2.4.1 Layout inspection and functional testing
Inspection plans must be created when products are to be monitored
during an extended period of time. This could concern, for example,
inspections that are elaborate and are therefore not performed on each
batch or lot (e.g. specifications in the technical data sheet). Examples are
ignition testing or monitoring, which has to be performed by independent
third parties.
If and as far as agreed upon with the customer, inspections regarding the
regular requalification of the products (e.g. according to PPAP or PPF)
may thus be performed.
8.2.4.2 Appearance items
No need for further explanation in regard to ISO/TS 16949:2009.
8.3 Control of nonconforming product
The following control measures are possible:
Application as intended
If it has been detected that the existing nonconforming state has no
negative influence on the quality when processed by the customer,
"application as intended" can be issued.
Downgrading or reclassifying
It is possible to downgrade or reclassify products with different quality
requirement levels if the quality level is marked. If a nonconforming
product has already been delivered, the customer must be informed
immediately.
Extraordinary release
33
If the customer agrees on a delivery of off-spec-grade product, an
extraordinary release, meaning a written consent, must be obtained from
the customer.
Post-processing or reworking
Post-processing or reworking is performed, if it is technically possible and
commercially reasonable to change the product concerning the deviant
product characteristics in a way to meet the requirements. The post-
processed product must be re-inspected and re-classified.
Disposal
Non-applicable product is labeled as waste and disposed of in an
appropriate way.
Rejection
If a raw material does not comply with the raw material specifications, the
material is sent back to the supplier.
8.3.1 Control of nonconforming product – supplemental
No need for further explanation in regard to ISO/TS 16949:2009.
8.3.2 Control of reworked product
No need for further explanation in regard to ISO/TS 16949:2009.
8.3.3 Customer information
No need for further explanation in regard to ISO/TS 16949:2009.
8.3.4 Customer waiver
Provided that customer-approved production control plans are available,
the customer must be informed about non-compliant process courses or
about reworking of the product prior to release for delivery.
Analogously, a decision must be taken regarding the whereabouts of
products that no longer meet the specifications or are under the suspicion
of being non-conforming, are non-labeled or are taken back from the
customer after claims (retour shipments), because of external influences
during storage or shipment after the product release.
8.4 Analysis of data
No need for further explanation in regard to ISO 9001:2008.
8.4.1 Analysis and use of data
The data is analyzed and used within the company by means of regular
reports, trend analyses and comparisons to the competition (comp. IATF
guidelines for ISO/TS 16949:2002) The individual functions or process
34
owners (e.g. Controlling, Marketing, QM) are responsible for the collection
and analysis of the data, and they have to report, in the Management
Review, to the management team.
Often a Balanced Scorecard Report is used in this context.
In line with the data analysis, it must be reported on the observation of the
product on the market, too (e.g. product observation obligation; for
products that circulate in the USA, the TREAD Act may be relevant).
8.5 Improvement
8.5.1 Continual improvement
No need for further explanation in regard to ISO 9001:2008.
8.5.1.1 Continual improvement of the organization
No need for further explanation in regard to ISO/TS 16949:2009. Further
examples can be found in the IATF guidelines.
8.5.1.2 Manufacturing process improvement
The general approach is based on the principle of the Plan-Do-Check-Act
quality cycle. In regard to a continual improvement of the manufacturing
process it is especially important to reduce variation and waste. In this
context the Six-Sigma-Method is an appropriate approach.
The initiation and planning of improvement measures can be performed
by interdisciplinary teams during meetings, supported by common
problem solving methods. Examples of such teams are design and
development teams, product teams, process improvement teams, or Six
Sigma teams. The implementation of the improvement measures and
their effectiveness should be reviewed in periodic follow-up meetings.
8.5.2 Corrective action
Corrective actions usually run through the following stages: analysis,
measure, execution, and review.
8.5.2.1 Problem solving
Examples of problem solving methods can be found in the IATF
guidelines for the ISO/TS 16949, chapter 8.5.2.4.
The 8D method is often used as a structured approach for solving
problems (see file on the VDA-QMC homepage). Customers often require
explicitly that this method is used - sometimes also in a refined manner.
35
The assumed cause should be validated, to ensure that the measure is
effectively working on the right place.
8.5.2.2 Error prevention
Error prevention should be preferred to error detection.
Examples of error prevention methods would be the Ishikawa cause and
effect diagram, Poka-Yoke, the FMEA and the fault tree analysis (also
see IATF guidelines for ISO/TS 16949).
8.5.2.3 Corrective action impact
No need for further explanation in regard to ISO/TS 16949:2009.
8.5.2.4 Rejected product test/analysis
To reach an objective result regarding the claimed non-conformity, a
product test/analysis may be performed on the material, which has been
sent back by the customer, or on own reference samples. By doing so, it
should be determined, if there is really a non-conformity and - if this is
correct - the cause of the mistake should be determined and solved, to
prevent recurrence.
The processing time of such a procedure may be used as measurement
parameter for customer satisfaction (see 8.2.1), but the quality of the
investigation should have the first priority.
8.5.3 Preventive action
The FMEA (Failure Mode and Effects Analysis) is a good method for the
preventive detection of potential mistakes and their causes, as well as the
evaluation of the need of actions to possibly avoid the appearance of
mistakes (also see the FMEA reference manual, 4th edition and VDA
volume 4). This method is in many cases required by customers
In addition, a self assessment could be performed, e.g. based on the
EFQM Excellence Model, a Toyota Self Assessment, or, for Ford
suppliers, by a Q1 Manufacturing Assessment.
36
A Interpretations of the ISO/TS 16949:2009 annex A
Control Plan
A.1 Phases of the control plan
The control plan must contain, if applicable, three phases for prototype, pre-
launch, and production. The column on the right explains the ISO/TS 16949
terms in regard to the conditions of the chemical industry.
ISO/TS 16949:2009 requirements Explanation, interpretation
a) Prototype
a description of the dimensional
measurements, material and
performance tests that will occur
during building of the prototype. The
organization shall have a prototype
control plan, if required by the
customer.
Laboratory tests, technical center
tests (if available)
Lab- preparation procedure
Technical center – production
procedure
Test plan for a lab product
Test plan for a technical center
product
b) Pre- launch
a description of the dimensional
measurements, material and
performance tests that occur after
prototype and before full production.
Pre-launch is defined as a production
phase in the process of product
realization, which may be required
after prototype build.
Plant tests
Production procedure for plant test,
incl. Q-relevant measurements / lab
tests
Test plan for test product
(often expanded or fully or partly
identical to the production procedure
or inspection plan of the finished
product.)
Geometrical dimensional checks are
usually not applicable in the chemical
industry.
c) Production
Documentation of product/process
characteristics, process controls, tests
and measurement systems that occur
during mass production.
Each part shall have a control plan
but, in many cases, family control
plans may cover a number of similar
parts produced using a common
process. Control plans are an output
of the quality plan.
(Routine) Production
Production procedure incl. Q-relevant
measurements and lab tests
Test plan for finished product
Quality inspection manual
37
A.2 Elements of the control plan
The organization shall develop a control plan. The requirements for this plan
are, in regard to the chemical industry, explained in the right column.
a) General data
ISO/TS 16949:2009 requirements Explanation, interpretation
Control plan number Number of the: production procedure,
test plan, quality assurance/inspection
manual and/or the operating manual,
etc.
Issue date and revision date, if any Issue date or revision date of the
documents with instructions listed
above
Customer information (see customer
requirements)
Requirements for the development of
a new product, specification
agreement, quality assurance contract
or list of duties.
Organization's name / site designation No need for further explanations
Part number(s) Product number
Part name / description Product name / description
Engineering change level Version number of the product
description
Phase covered (prototype, pre-launch,
production)
Lab tests or technical center tests,
production tests or (routine)
production
Key contact No need for further explanations
Part/process step number Number of the process step
Process name / operation description Name / short description of the
production process
b) Product control
ISO/TS 16949:2009 requirements Explanation, interpretation
Product-related special characteristics Special product characteristics
according to specification or quality
agreement with the customer
Other characteristics for control
(number, product or process)
Other Q-relevant product
characteristics or measurement
parameters / lab tests according to
production procedure
Specification / tolerance Product specification
38
c) Process control
ISO/TS 16949:2009 requirements Explanation, interpretation
Process parameters No need for further explanations
Process-related special
characteristics
Quality relevant production process
measurements
Machines, jigs, fixtures Production facility, equipment,
machines
Tools for manufacturing Tools, etc. are not applicable
d) Methods
ISO/TS 16949:2009 requirements Explanation, interpretation
Evaluation measurement technique No need for further explanations
Error-proofing Outputs of the Measurement System
Analysis (e.g. gRR values)
Sample size and frequency Size and frequency of the
measurements or tests
Control method Method for monitoring measurement
and test data (e.g. type of used
control chart)
e) Reaction plan
ISO/TS 16949:2009 requirements Explanation, interpretation
Reaction plan
(include or reference)
Cross-references to test-, work- or
operating instructions
Corrective action Cross-references to test-, work- or
operating instructions
39
B Supplementary literature for the ISO/TS 16949:2009
1 IATF guidelines for ISO/TS 16949:2002, 1st edition 2002
2 Certification Rules of the automotive industry for ISO/TS 16949:2002,
3rd edition, October 2008
3 AIAG Publication Catalogue,
(www.aiag.org)
4 ISO/TS 16949:2002 Implementation Guide, AIAG, 2003
5 The ISO/TS 16949 Answer Book, Radley M. Smith et al, Paton Press LLC
Chico, California 2004, ISBN 1-932828-00-1
6 Various VDA volumes
(www.vda-qmc.de)
7 PPAP-manual, 4th edition, June 2006
8 FMEA-reference manual, 4th edition, June 2008
9 MSA-reference manual, 3rd edition, March 2002
10 SPC-reference manual, 2nd edition, July 2005
11 APQP-reference manual, 2nd edition, July 2008
12 Balanced Scorecard, Burkhard Rüth, WEKA-publishing, 2004,
ISBN 3-8276-2919-5
13 The Six Sigma Way, Peter S. Pande et al, Mc Graw-Hill, 2000,
ISBN 0-07-135806-4
14 The Six Sigma Handbook, Thomas Pyzdek, Mc Graw-Hill, 2003,
ISBN 0-07-141015-5
15 Seven-Step Problem-Solving Process for Truck And Heavy Equipment,
AIAG, 2000