“Success in Offshore Wind & Marine” Michael Cowie, Technical Director

Presentation Overview

• ESS Ethos • ESS Financials and Growth • Ecosse Subsea Systems – Business Overview • Who We Work With

• Utilising Existing Knowledge

• Success in Offshore Wind & Marine • Successful Projects • Conclusions

ESS Ethos

Subsea Services that are focused on being:

• Client focused • Safe • Simple • Robust • Off-the Shelf Components • Negate the requirement for specialist vessels • Installable by local people and vessels • Recoverable, recyclable

ESS has been described as a ‘Pseudo’-Contractor – A business that not only undertakes subsea services but is continually re-investing in new technology and innovation – quite unusual! Utilising their ‘technology advantage’ ESS perform most of the services that huge Contractors provide at a fraction of the cost. Cable Lay, Pipelay, Trenching, Lifting.

ESS Financials and Growth

ESS provide a specialist personnel and resourcing support business service across the full spectrum of offshore requirements. Today more than £350 million of subsea projects are managed by ESS personnel resource for and on behalf of our clients.

Personnel

ESS offer bespoke engineering and design solutions with a team combining a vast experience curve, specialist subsea expertise, coupled with procurement, fabrication, and installation know-how.

Engineering Consultancy

ESS Technologies comprises of innovative patented offerings specifically developed over more than 25 years to address subsea operational challenges. These include trenching,cable/pipelay, and lifting applications

Pipelay Technologies

ESS’s patented subsea lifting and positioning technologies Ambient lifting is a flexible mechanism using incompressible gas which facilitates control of the accent, decent and underwater positioning of offshore structures

Ambient Lifting

A wide range of equipment is available for hire to support and deliver subsea installation projects. Including 800-2000Te Carousel, 10Te Hydraullic Tensioners, SCAR Plough in its four configurations and PREP (Plastic Reeled Elastic Pipelay System).

Equipment Hire

Ecosse Subsea Systems

Who We Work With…

Utilising Existing Knowledge

• ESS combined Oil and Gas with Renewables Market

• Transferable skills and tools

• Success from projects is reinvested into the development of new technologies and innovation

• Variety of project work supports the retention of personnel

Success in Offshore Wind & Marine

• Researching and Targeting the Market

• International Approach

• Conferences and Exhibitions

• PR and Marketing

• Strong Sales Approach • Projects We’ve Worked On

SCAR Seabed Trenching System: Track Record

Date Project Title Project Description

March-April 2012

Laggan-Tormore Boulder Clearance Project

Boulder clearance along a single 67km corridor over 6 days, 2,000 large boulders were cleared. Water depths up to 640m. Client; TOTAL.

December 2012

Humber Gateway SCAR Demonstration Project

Demonstration project by SCAR was deployed in each of its current configurations (boulder clearance, first pass, multi-pass pre-cut trenching and backfill modes) in order to perform passes within several dedicated trial locations. Soils were soft, stiff and hard clays with shear strengths in excess of 300kPa in sections. Site featured many boulders and cobbles. Client; E.On C&R.

March-June 2013

Baltic 2 Offshore Wind Farm Project

Boulder clearance and pre-cut trenching of 86 array cable routes within the Baltic 2 site. Pre-cut trenching entailed two passes on each of the array routes, trenching to 1.5m Soils varied from soft clays, to stiff sands, to glacial till. Client; Siem Offshore Contractors. Total ploughing distance of some 240km and a total of >250 individual passes.

October-November 2013

Humber Gateway Export Cable Boulder Clearance Project

Boulder clearance on 2 x 7km Export Cable lines on the Humber Gateway Offshore Wind Farm project. Client; E.On C&R.

June – August 2014

Westermost Rough Offshore Wind Farm Project

Multi-pass Boulder Clearance operations on 37 inter array routes on Westermost Rough Offshore Wind Farm, Client; Dong Energy. 50,000 targets cleared

A $7.5 million boulder clearing and pre-lay trenching project which has been one of the most successful ever conducted for the wind energy sector. 86 boulder clearing passes followed by 172 first and multi-passes over a 90km route during a 13-week boulder clearing and trenching campaign on the EnBW Baltic 2 offshore wind farm project. The project was on schedule and on budget. Mobilisation on the 86 cable route work scope started in Gdansk/Poland, with ESS transporting its SCAR® ploughing technology by road from Aberdeen. Mobilisation aboard the Siem Topaz took 48 hours with demobilisation being completed in only 12 hours. Several thousand boulders ranging up to 4m in size were cleared from the individual cable routes and ESS performed 260 individual route passes in varying and sometimes challenging soil conditions. Reliability of the plough equipment was excellent as expected with more than 95% uptime.

Baltic 2 OWF Project

Humber Gateway OWF

Humber Gateway site is located is extremely tidal, with the current predominantly running north to south, frequently in excess of 3 knots. Route clearance and multi-pass trenching modes demonstrated Effective trenching achieved in hard clays and boulders Shallow water operation (11-17m) Higher than anticipated progress rates (360-720m/hour) and lower than expected tow forces (average 42Te) Turn radius of <50m achieved with trenching plough Boulder clearance run performed in stiff clays

A $10 million boulder clearing project for Dong Energy 33 routes cleared in high currents on spring as well as neap tides 20m corridor required Generally 5 passes per string, Centre line, 2 x Wing lines (accuracy essential) and lay downs at either end (accuracy essential) Campaign was 72 days to include - Ploughing, Surveying, Transiting, Port calls Mobilisation in 47 hours in Aberdeen Demobilisation in 24 hours Within the 20m wide corridors between the 35 towers towers there were 48,000 on seabed target boulders 0.35m and above. The project was on schedule and on budget.

Westermost Rough OWF

13 11

Displaced Boulder

SCAR Seabed Trenching System: Anticipate work Scopes 2015 / 2016

Date Up coming Projects Q1 – Q4 2015 European Oil & Gas Project - Trenching, Pipelay & Backfill

Q2 - 2015 North Sea Oil & Gas Boulder Clearing Project

Q2 - 2015 North Sea Oil & Gas Pre cut trenching and backfill Project

Q2 - 2015 North Sea - Installation of Tidal Turbines using Ambient Lifting

Q2 /Q3 2016 European – Offshore Wind Farm Inter array and Pre cut Installation of Wind Turbines using Ambient Lifting

Q2/Q3 2016 UK Offshore – Boulder clearing Pre – cut / Post lay and backfill

International Approach

PR and Marketing

Strong Sales Message

• Keep to your business ethos and Values • Value Proposition

• Versatility

• Flexibility

• Speed

• Robust

• Simple

• Cost Effective

Conclusions To be successful in the offshore wind and marine market ESS believe: • Export our skills, expertise and solutions • Attend/participate at key events • Establish a flexible sales approach • Publish track record • Network with the relevant parties