sub_dwg_00_221210
DESCRIPTION
DrawingsTRANSCRIPT
12/22/10
Bharat Heavy Electricals Limited Bhopal
TRE BLOCK-3 EASTERN ANNEXE, BHEL, PIPLANI, BHOPAL 462021
Page 1 of 3
Transformer Engineering Department
Sub: Submission of Customer Drawings for 340 MVA 420/16.5 kV 3 Phase Generator transformer
for M/S Abhijit Infra Ltd. (AINL) against WO 69071-Q-512-01 & 60036-Q-512-01
Dear Sir,
With reference to subject please find enclosed herewith the 3 sets of the following drawings/documents for
further submission to Customer/PEM/DCPL
Sl. No. Description Drawing No. Rev.No.
1 OGA 34600000717 01
2 OGA Part List 34600000718 01
3 Foundation Plan 34600000719 01
4 HV Bushing 34600000720 00
5 LV Bushing 34600000721 00
6 HV Neutral Bushing 34600000722 00
7 Bus Duct Mounting flange details 34600000724 00
8 320 Dia Twin Bi Directional Roller 34600000723 00
9 Shipping Diagram 34600000725 00
10 Rating & Diagram Plate 34600000726 00
11 Valve Schedule Plate 34600000727 00
12 Technical Data Sheet TRE/69071/GTP 01
13 Customer Inspection Test Schedule TRE/69071/CITS 00
Please also note that the Sl. No. 1-3 has been revised as per customer comments dtd: 23.11.10.
Our point wise reply is as below:
Sl. No. Customer point BHEL Reply
1 Provide necessary Shut off valves for
detachable cooler units
Indicated as item no. 123
2 Confirm that all valves are made of Gun Metal. Please note that valves upto 50 NB
shall be of Gun metal. All valves
above 50 NB shall be of Cast steel
with Gun metal fittings. This is our
standard practice and followed for all
projects of NTPC/POWERGRID and
also the earlier supplies to JINDAL.
3 Confirm that all gasketed joints are with earth
continuity through copper strips.
Please note that the Copper strips are
provided at Tank, turret joints etc.
Other joints get the earth continuity
through nut-bolts etc.
Our Ref: TRE/69071/GKL
Date- 22-12-2010
Shri P.K Sharma
CMG
12/22/10
Bharat Heavy Electricals Limited Bhopal
TRE BLOCK-3 EASTERN ANNEXE, BHEL, PIPLANI, BHOPAL 462021
Page 2 of 3
This is our standard practice and
followed for all projects of
NTPC/POWERGRID and also the
earlier supplies to JINDAL.
4 Confirm that all drain valves shall be with
threaded adopter.
We have provided two nos. sampling
valves at Top & Bottom with
threaded adopter.(Item no. 25 & 25a)
5 Indicate the size of Earthing Connection for
item no. ‘212a” and “110”.
Indicated in the revised OGA
drawing(Sht-03)
6 Indicate “Transformer Marshalling Box”. Indicated as item no. 34
7 Item no. “181” (HV Terminal Connector) shall
be suitable for TWIN Moose ACSR.
Confirmed. Please confirm that the
conductor spacing shall be 450mm.
8 Provide Pressure Relief device with trip contact. Confirmed
9 Confirm Explosion Vent shall be double
diaphragm type.
Please note that Explosion vent is
not applicable as PRV is provided.
10 Correct the Name of the Project. -
11 Indicate breather. Indicated as item no. 17
12 Submit other drawings as listed. Submitted as per list above
13 Direction of Transformer Withdrawal will be
opposite left hand side to Cooling Bank. Change
the foundation plan accordingly.
Indicated in revised Foundation plan
drawing.
14 Indicate item no. “007”: Pump Support on
foundation plan.
Indicated in revised Foundation plan
drawing.
15 Indicate “Oil Filling Instruction Plate” on OGA
Part List.
Indicated in revised OGA and OGA
Part list
The Technical data sheet has been revised as per Customer comments dtd 05.08.10. Please find below the
point wise reply for your comments on GTP.
Sl.
No.
Customer point BHEL Reply
1 Transformer rated out put for ONAN as well as ONAF Not applicable with OFAF type
unit coolers.
2 Winding insulation level with impulse and power frequency Indicated in Cl.5.1.
3 No load current referred to HV (%) Indicated in Cl. 10.1 to 10.5
4 Rated voltage of tap changer Indicated in Cl.18.3
5 BHEL shall specify no of cooling units required for full load
operation
Indicated in Cl.14.8
6 For secondary resistance (5 ohms) in the CT data sheet shall
be rechecked
It may please be noted that CT
secondary resistance is indicated
as per Customer Specification
Annexure E.
Other drawings are fresh submission for customer approval.
Please arrange the approval of the above drawings/documents at the earliest.