stem project renewable energy is it the right decision for your business? october 1 st 2013
TRANSCRIPT
STEM Project
Renewable EnergyIs it the right decisionfor your business?
October 1st 2013
Agenda
Introduction The risk finance journey Resource Grid Planning Finance Technology considerations & information sources Summary
STRATEGY SUSTAINABILITY SAVINGS
Chemical energy (gas, oil, biomass etc):
• Can be burned to produce electricity or heat
• Can be transported and stored easily
Electricity:
• Can use it for anything
• Easy to transport in a wire, hard to store
Low grade heat:
• Can only use it for heat
• Not very transportable, possible to store
Introduction - Energy
STRATEGY SUSTAINABILITY SAVINGS
Max Fordham Consulting Engineers
Impact on energy Cost
Free? Dull
Interesting Bolt-on
Perception
Integrated Design
Expensive
Cheap
Energy Management
Energy Efficiency
Cheap Renewables
Expensive Renewables
Fuel Cells etc
Introduction - Technology Perception
STRATEGY SUSTAINABILITY SAVINGS
Carbon Trust
Introduction - Carbon Abatement
STRATEGY SUSTAINABILITY SAVINGS
Verifiable Resource
Planning Permission
Grid Connection
Construction
Operation
Revenue
RISK RETURN
Fundable or saleable project
The Risk Finance Journey
STRATEGY SUSTAINABILITY SAVINGS
Wind – wind speed (@10m @ hub height) Hydro – hydrology, hydraulic head, abstraction Biomass – feedstock security and quality Anaerobic Digestion - feedstock security and
quality Solar – insolation and shading
Banks and funders will want to know…
Available resource and incentive thresholds…
Resource, Resource, Resource
STRATEGY SUSTAINABILITY SAVINGS
Scale – 11kV or 33kV Nearest connection Who else is on the line Who else is in the queue Distance to substation Likely connection costs Elapsed time to connection agreement
Grid
STRATEGY SUSTAINABILITY SAVINGS
Substation
11 kV
11kV33kV
11kV£70k
£150k
£4m
£ ???
£500k
£120k
Grid
STRATEGY SUSTAINABILITY SAVINGS
PPS 18 in NI DOE RE Planning Statistics
Scale of project Impacts - EIA Ecology
Agents and consultants
Costs
Planning
STRATEGY SUSTAINABILITY SAVINGS
Business Case USP Financial Models - RETScreen?
Funders – perceived risk, redundancy
funding for some RE projects is very challenging due to risk perception
Finance
STRATEGY SUSTAINABILITY SAVINGS
Republic of Ireland- Renewable Energy Feed-in-Tariff
(REFIT)
Northern Ireland- Renewable Obligation Certificates- Renewable Heating Incentive
(RHI)
Policy creepGreat Britain- Feed In Tariffs – Degression!- ROCS- Contracts for difference incoming- Renewable Heating Incentive
(RHI)
Timing!
Incentives
STRATEGY SUSTAINABILITY SAVINGS
• There have been three separate schemes known as REFIT 1(2006) REFIT 2(2012) and REFIT 3(2012)
REFIT 1• officially launched on 1st May 2006.
• The fixed price tariffs can be seen below:- Wind (Large scale) >5MW: 5.7 cent/kWh- Wind (Small scale) <5MW: 5.9 cent/kWh- Biomass landfill gas: 7.0 cent/kWh- Hydro & other Biomass: 7.2 cent/kWh
• In 2009 additional Categories (other than Hydro, wind & biomass)were added to the established 2006 REFIT.
• The reference prices for the additional technologies were as follows:
- Anaerobic Digestion: €0.12/kWh- High Efficiency CHP: €0.12/kWh (only for High Efficiency)- Ocean Energy: €0.22/kWh- Offshore Wind: €0.14/kWh
ROI – Renewable Energy Feed in Tariff (REFIT)
STRATEGY SUSTAINABILITY SAVINGS
Officially launched in March 2012
• Incentives are given to the generators of selected renewable technologies which have been commissioned between 01/01/2010 - 31/12/2015.
• Available for 4,000MW of onshore wind, hydro & landfill gas.
• The reference price for each technology is shown below:- Onshore Wind (>5MW): €66.35/MWh- Onshore Wind (<5MW): €68.68/MWh- Hydro (<5MW): €83.49/MWh- Biomass (Landfill gas): €81.49/MWh
• The support for any particular project cannot exceed 15 years and may not extend beyond 31/12/2030
• REFIT 2 is not payable for electricity generation consumed onsite
REFIT 2
STRATEGY SUSTAINABILITY SAVINGS
Officially opened in February 2012
• Incentives are given to the generators of selected renewable technologies which have been commissioned between 01/01/2010 - 31/12/2015
• Available for 310MW of anaerobic digestion, biomass CHP & biomass combustion
• Technology limits to the incentives under REFIT 3 are; 50MW for AD (including CHP), 100MW for Biomass CHP and 160 MW for Biomass Combustion.
• The reference price for each technology is shown below:- AD CHP (K500kW): €0.15/kWh- AD CHP (>500kW): €0.13/kWh- AD Non CHP (K500kW): €0.11/kWh- AD Non CHP (>500kW): €0.10/kWh- Biomass CHP (K500kW): €0.14/kWh- Biomass CHP (>500kW): €0.12/kWh
• Biomass Combustion Technologies (non CHP) which use energy crops will get 9.5cent/kWh and all other biomass will get 8.5cent/kWh.
REFIT 3
STRATEGY SUSTAINABILITY SAVINGS
• The main support mechanism for renewable energy generation in the UK
• First introduced in GB in April 2002
• Adopted by Northern Ireland in April 2005 as the NIRO.
• Prior to 1st April 2009 all renewable electricity generation technologies received 1 ROC/MWH generated
• However, banding of the RO was introduced in April 2009 to allow different levels of support for different technologies depending on their stage of development and their costs, with reviews of banding levels set to be undertaken every four years.
• Certificates can then be sold to electricity suppliers who are legally required to purchase ROCs to show that a specified quantity of electricity supplied can be accounted for by generation of renewables.
NI Renewables Obligation (NIRO)
STRATEGY SUSTAINABILITY SAVINGS
Technology Current (2012/ 13)
Confirmed ROC Levels 2013/14 2014/15 2015/16 2016/17
Anaerobic digestion (≤ 500kW)
4
4
4
4 4
Banding levels from 2015/16 subject to further review
Anaerobic digestion (500kW – 5MW)
3
3
3
3 3
Banding levels from 2015/16 subject to further review
Anaerobic digestion (above 5MW)
2 2 2 1.9 1.8
Hydro (≤ 20kW)
4 4 4 4 4 Banding levels from 2015/16
subject to further review Hydro (>20kW – 250kW)
3
3
3
3 3 Banding levels from 2015/16
subject to further review Hydro (>250kW – 1MW)
2
2
2
2 2 Banding levels from 2015/16
subject to further review Hydro (>1MW – 5MW)
1
1
1
1 1 Banding levels from 2015/16
subject to further review Hydro (>5MW)
1 0.7 0.7 0.7 0.7
Onshore wind (≤ 250kW)
4 4 4 4 4 Banding levels from 2015/16
subject to further review Onshore wind (>250kW – 5MW)
1
1
1
1 1 Banding levels from 2015/16
subject to further review Onshore wind
Sample of ROC/MWh Levels from 1st May 2013
DETI, 2013
STRATEGY SUSTAINABILITY SAVINGS
Onshore wind (Above 5MW)
1
0.9
0.9
0.9
0.9
Banding levels from 2014/15 subject to further review
Offshore wind
2
2
2
1.9
1.8
Solar photovoltaic (up to 50kW)
4
4
4
4 4 Banding levels from 2015/16 subject to
further review Solar photovoltaic (>50kW to 250kW)
2
2
2
2 2 Banding levels from 2015/16 subject to
further review Solar photovoltaic – Ground mounted >250kW
2
1.6
1.4
1.3
1.2
Solar photovoltaic –Building mounted >250kW
2
1.7
1.6
1.5
1.4
Sample ROC levels – 1st May 2013
STRATEGY SUSTAINABILITY SAVINGS
• In May 2012 the Renewable Heat Premium Payment scheme was launched as an interim scheme to the RHI
• Phase 1 of the RHI was Launched in NI in November 2012 with a budget of £25 million up to 2015
• Phase 1 concerns Non-domestic installations of renewable heat
• Phase 2 (Domestic installations) launched in Autumn 2013
The technologies that are to be covered under phase 1 of the RHI are:
- solid biomass and solid biomass contained in municipal waste (including CHP)
- ground and water source heat pumps,- geothermal (including CHP) - solar thermal (at capacities of less than 200 kWth) - biogas combustion (except from landfill gas but including CHP; at
capacities of less than 200 kWth)- biomethane injection.
NI Renewable Heating Incentive (RHI)
STRATEGY SUSTAINABILITY SAVINGS
Tariff Name Eligible Technology
Size Range (kW)
NI RHI Tariff (p/ kWh)
Length of Tariff
Biogas I njection
Biomethane injection & biogas combustion (except landfill gas)
Biomethane all scaled; Biogas combustion less than 200kWth
3.0 20 years
Biomass Boilers
Solid Biomass; Municipal Solid Waste (inc.CHP)
Less than 20kWth
6.2 20 years
20kWth and above up to but not including 100kWth
5.9 20 years
100kWth and above up to but not including 1000kWth
1.5 20 years
Ground Source Heat Pump
Including water source heat pumps and deep geothermal
Less than 20kWth
8.4 20 years
20kWth and above up to but not including 100kWth
4.3 20 years
100kWth and above
1.3 20 years
Solar Thermal
Below 200kWth
8.5 20 years
NI RHI Tariffs
STRATEGY SUSTAINABILITY SAVINGS
Technologies
CTG011www.carbontrust.co.uk/publications
http://www.seai.ie/Publications/
Renewables_Publications_/
STRATEGY SUSTAINABILITY SAVINGS
Technologies - Wind
Considerations:
• Scale
• Noise
• Flicker
• Visual Impact
• Ecology
• Transportation
• Grid connection
STRATEGY SUSTAINABILITY SAVINGS
Site electrical generation and consumption
0
500
1000
1500
2000
2500
3000
3500
04/1
2/20
03
01/0
1/20
04
29/0
1/20
04
26/0
2/20
04
25/0
3/20
04
22/0
4/20
04
20/0
5/20
04
17/0
6/20
04
15/0
7/20
04
12/0
8/20
04
09/0
9/20
04
07/1
0/20
04
04/1
1/20
04
DAYS
kW
h p
er
da
y
Building consumption
Net wind generation
Technologies - Wind
STRATEGY SUSTAINABILITY SAVINGS
Considerations:
• High head low flow
• Low head high flow
• Turbine type
• Ecology
• Civil costs
• Resource
Technologies - Hydro
STRATEGY SUSTAINABILITY SAVINGSCarbon trust images
Considerations:
• PV or Thermal
• Insolation
• Shading
• Roof structure
• Matching demand
• Cleaning
• Guarantees
Technologies - Solar
STRATEGY SUSTAINABILITY SAVINGS
Solar thermal Photovoltaic
Technologies - Solar
STRATEGY SUSTAINABILITY SAVINGS
Technologies - Biomass
Considerations:
• Size
• Pellet or chip or other
• Water, Steam, Gasification
• Fuel supply
• Contract terms
• WID
STRATEGY SUSTAINABILITY SAVINGS
Technologies - Biomass
STRATEGY SUSTAINABILITY SAVINGS
Technologies – Anaerobic Digestion
Considerations:
• Advanced
• All revenue streams
• Blend of feedstock
• Feedstock security
• Long term commitment
• Operation and maintenance
• Grid
STRATEGY SUSTAINABILITY SAVINGS
Technologies – Anaerobic Digestion
STRATEGY SUSTAINABILITY SAVINGS
• Prioritise the business case for all your options
• Exhaust all more cost effective alternatives
• Identify, verify and secure your resource
• Identify the most cost effective technology
• Produce project finance model
• Minimise your risk finance journey
• Get planning permission and any other consents
• Get a grid connection
• Secure equipment guarantees and maintenance costs for the lifetime of the project
Summary
STRATEGY SUSTAINABILITY SAVINGS
Facilities and Energy Management Ltd250 Ravenhill RoadBelfastBT6 8GJ T: +44 (0) 8456 891 257M: +44 (0) 7513 994 936F: +44 (0) 2890 466509E: [email protected]: www.fandem.co.uk
Thank youfor listening