standard costing technique 1

36
1 STANDARD COSTING TECHNIQUE AND VARIANCE ANALYSIS BY PROFESSOR T.O. ASAOLU

Upload: matthew-ishiekwene

Post on 20-Jun-2015

144 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: Standard costing technique 1

1

STANDARD COSTING TECHNIQUE AND VARIANCE ANALYSIS

BY

PROFESSOR T.O. ASAOLU

Page 2: Standard costing technique 1

2

• The technique known as standard costing consists of setting of predetermined estimate of costs and the comparison of this with actual cost as they are incurred. The difference between the actual cost and standard cost is termed the VARIANCE. Variance analysis is used to attribute variances to the various causes.

Page 3: Standard costing technique 1

3

Standard cost can be defined as “a predetermined cost of how much costs should be under specified work and conditions (CIMA).”

Page 4: Standard costing technique 1

4

TYPES OF STANDARD

Page 5: Standard costing technique 1

5

(1) Basic Standards:

This is defined by the CIMA as a standard established for use over a long period from which a

current standard can be developed.

Page 6: Standard costing technique 1

6

They are established for use unaltered over the years. Its variance report helps the management to highlight trends (i.e. over material, prices, labour, efficiency). They are not very useful for preparation of budgets as basic standards are not up to date.

Page 7: Standard costing technique 1

7

The information they provide for cost control in terms of various analysis cannot be used as a basis for actual control nor can there be any motivational effect from the use of basic standard. They cannot be used to highlight current efficiency or inefficiency.

Page 8: Standard costing technique 1

8

(2) Ideal Standards: This is a standard which can be

attained under the most favourable conditions. i.e. no breakdowns, no material wastage, no stoppages or idle time, in short, there is perfect efficiency. It will be revised periodically in the light of development of technology improvements in materials. Clearly, ideal standard would be unattainable in practice accordingly, it is rarely used.

Page 9: Standard costing technique 1

9

However, their uses could be considered worthwhile for investigation and development purposes, but not for normal day to day control activities. Ideal standards will be used where management believes that it would provide the best type of standard needed for motivation and cost control.

Page 10: Standard costing technique 1

10

In some cases, it will be reasonable to expect that no wastage of material will occur however, in terms of labour efficiency, ideal standards will assume no inefficiency, no breakdown, no loss of efficiency due to fatigue, may lie no more than a dream. Ideal standard is not widely used in practice because it may influence employee motivation adversely. It is otherwise known as the Alice in the wonderland Standard.

Page 11: Standard costing technique 1

11

(3) Currently Attainable Standards:This can be defined as a standard

which can be attained if a standard unit of work is carried out efficiently (CIMA), a machine properly operated or a material properly used. It will show the cost to be incurred under the normal efficient operation condition and allowances are made for normal wastage of material, machine breakdown loss of efficiency from

fatigue.

Page 12: Standard costing technique 1

12

Although, currently attainable standard should be possible to achieve, it should also represent a high standard of performance. Standard cost determined in this way can be used for a variety of purposes, e.g. for budget preparation, for cost control by mean of variance analysis, for product costing and for motivation.

Page 13: Standard costing technique 1

13

(4) Current Standards: This is a standard established for use

over a short period of time to reflect current conditions (CIMA). Where stable conditions of prices exist, the current standard is equivalent to an attainable standard but where for example a temporary problem exists with material quality or there is an unexpected inflation, then a current standard could be set for a limited period to deal with the temporary problem.

Page 14: Standard costing technique 1

14

It is useful in inflationary circumstances where current standards could be set, perhaps on a monthly basis.

Page 15: Standard costing technique 1

15

(5) Expected Standard: This is the standard which is

anticipated can be attained during a future specific budget period and based on current or prevailing conditions. Standards set are on a short-term basis and it is often revised as may be necessary.

Page 16: Standard costing technique 1

16

• Advantages of Standard Costing

(i) It helps in preparation of annual budget, i.e. Planning.

(ii) It is useful in setting prices in advance, mostly in making tender.(iii)It is useful in motivating employees, labour efficiency.

(iv) It helps in determining various standard of actual costs for future planning.

Page 17: Standard costing technique 1

17

(v) It helps management in planning for the future.

(vi) It is useful for cost control.

• Disadvantages of Standard Costing

(i) It may be expensive and time consuming to install and maintain the system.

(ii) In an inflationary period or improving technological environment, standards quickly become obsolete and consequently lose their control and motivational effects.

Page 18: Standard costing technique 1

18

VARIANCE ANALYSIS

Page 19: Standard costing technique 1

19

A variance is the difference between standard cost and actual cost. Variance analysis therefore is the process whereby the difference between standard cost and actual cost is sub-analyzed into their constituent parts.

Page 20: Standard costing technique 1

20

A variance could be favorable or adverse. It would be favorable where the actual cost is less than the standard or where actual revenue is higher than the budgeted revenue. It would be an adverse variance where the actual cost is higher than the standard cost or where actual revenue is less than the budgeted revenue.

Page 21: Standard costing technique 1

21

METHODS OF CALCULATING VARIANCES

There are two methods of calculating variances. These are:

(1) Formulae method and

(2) Narrative method.

The formulae method will only be mentioned in passing and our discussion will focus on the narrative method.

Page 22: Standard costing technique 1

22

Page 23: Standard costing technique 1

23

DIRECT MATERIAL VARIANCES:

Direct Material Total Cost Variance:

This is the addition of the usage variance and the price variance. The CIMA officially defines it as "the differences between the standard production material cost of the actual production volume and the actual cost of direct material".

Page 24: Standard costing technique 1

24

Direct Material Price Variance:

The CIMA officially defines this as "the difference between the standard price and the actual purchase price for the actual quantity of material." It can be calculated at the time of purchase or the time of usage. Its formula is given as the:

"Actual purchase quantity x Actual price minus Actual purchase quantity x Standard Price"

Page 25: Standard costing technique 1

25

Direct Material Usage Variance:

The CIMA officially defines this as "the difference between the standard quantity specified for the actual production and the actual quantity used, at the standard purchase price." Its formula is given as the:

“Actual quantity used for actual production x Standard Price minus Standard quantity for actual production x Standard Price"

Page 26: Standard costing technique 1

26

ILLUSTRATION 1 Material Cost Variances

A product (A) has a standard direct material cost as follows:

5 kilograms of material M @ N2 = N10 per unit of A. During April 1995, 100 units of the product are manufactured, using 520 kilograms of material M which cost N l,025.

Required: Calculate the:

(a) Total direct material cost variance.

(b) Material price variance.

(c) Material usage variance.

Page 27: Standard costing technique 1

27

Page 28: Standard costing technique 1

28

DIRECT LABOUR VARIANCES Direct Labour Total Cost Variance:

This is defined as "the difference between the standard direct labour cost and the actual direct labour cost incurred for the actual production level achieved" - CIMA Terminology.

Direct Labour Rate/Wage Variance: The CIMA officially defines this as "the difference between the standard and actual direct labour hour rate per hour for the total hours worked". Its formula is given as:

Actual labour hours x Actual rate minus Actual labour hours x Standard rate.

Page 29: Standard costing technique 1

29

Direct Labour Efficiency Variance:

The CIMA officially defines this as "the difference between the standard hours for the actual production achieved and the hours actually worked, valued at the standard labour rate". Its formula is given as:

"Actual labour hours x Standard rate" minus "Standard labour x Standard rate".

Page 30: Standard costing technique 1

30

ILLUSTRATION 2

Direct Labour VarianceThe standard direct labour cost of product B is 4 hours of grade S labour at-N3 per hour = N12 per unit. During May 1995, 200 units of product B were made, and the direct labour cost of grade S was N2,440 for 785 hours of work.

You are required to calculate the :(a) Total direct labour cost variance.(b) Direct labour rate variance.(c) Direct labour efficiency (productivity)

variance.

Page 31: Standard costing technique 1

31

Page 32: Standard costing technique 1

32

• Idle Time Variance

This is the non-productive hours recorded in a costing system. Idle time is usually caused by machine breakdowns, bottlenecks in production, shortage of orders from customers or for any reason, the company cannot productively engage its labour force even though they are ready to work and at any rate, they would be paid for the unproductive hours.

Page 33: Standard costing technique 1

33

Unproductive hours paid for is inefficiency and therefore, idle time is always an adverse efficiency variance.

An idle time variance can be calculated by multiplying the hours of idle time by the standard rate.

Page 34: Standard costing technique 1

34

ILLUSTRATION 3 Direct Labour Variances (with Idle Time)

The direct labour cost of product C is as follows: 3 hours of Grade T labour @ N2.50 per hour = N7.50 per unit. During June 1995, 300 units of product C were made and the labour cost of grade T was N2,200 for 910 hours. During the month, there was a machine breakdown, and 40 hours were recorded as idle time.

You are required to calculate the:

(a) Direct labour total cost variance.(b) Direct labour rate variance.(c) Idle time variance.(d) Direct labour efficiency variance

Page 35: Standard costing technique 1

35

solution

Page 36: Standard costing technique 1

36