Stage 2 - Planning & Procurement
(a) Evaluation of Fee Tender Submissions by Technical Consultants
Consultant Tender Evaluation Report Comment
Tender chosen or invited. Refer to tendering
procedures in Department of Finance guidelines.
Name of consultants invited to tender and who
actually tendered. Also include name of
successful tender and the organisational structure.
Contract for fees
Indicative programme
Schedule A & B of the Consultants Contract
detailing scope of services
Procurement/tender process Procurement process whether open, selective or
negotiated. EU or National. Call for a specific
project or restricted to an existing framework.
Ranking of submitted and valid tenders; include
copy of successful tenderer opening page and
recommendation for award of contract with
VFM explanation
In terms of criteria ranking in ascending order of
submitted tenders.
Please note: The information provided here
may be commercially sensitive.
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
26
Tender Award Criteria used (MEAT)
For Most Economically Advantageous Tender
(MEAT) indicate the quality to price ratio as well
as ranking of quality criteria.
Other comments about successful tender
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
27
Stage 2- Planning & Procurement
(a) (i) Pre- Statutory Planning and Design Submission to Local Authority
Having received appraisal approval in principle for the project from the local authority, the
following planning/design and cost plan information is required for the detailed planning & design
stage. The Approved Housing Body (AHB) will appoint a Design Team in accordance with public
procurement requirements and New Forms of Contracts to carry out this work.
Planning/Design Submission to local authority prior to statutory planning
application
REQUIREMENTS COMMENTS AND GUIDE
Ordnance survey map showing
location of site.
Also provide information on the wider site context. And
confirmation that the site is satisfactory for the proposed housing
project.
1:500 site plan indicating
boundary and adjoining lands.
1:200 site layout identifying
external works, boundary
treatments, site contours, paving,
hard and soft landscaping.
1:100 floor plans of all dwelling
types, room areas and
dimensions.
1:100 section and elevation
drawings of individual units.
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
28
1:200 apartment block or street
elevations showing context of
proposed buildings to
surrounding buildings.
General commentary The commentary should demonstrate how the proposed project
relates to the local context as well as how the project itself will
operate. This information is required to support the designs/ plans
listed above. It should include housing management aspects, future
maintenance e.g. implications for window cleaning and painting,
layout, any demolitions, access to buildings, public and open space,
boundaries, security measures and environmental aspects e.g. solar
panels, insulation and have regard to DoEHLG Delivering Homes-
Sustaining Communities.
Design Brief as issued to
technical consultants
Design brief to be prepared in accordance with Best Practice
Guidelines with reference to DoEHLG Delivering Homes
Sustaining Communities.
Schedule of House Types having
regard to DoEHLG Guidelines
for dwelling designs and room
sizes
Supply list of house/apartment types (one, two, three bedroom) and
floor area sizes etc. for compliance purposes.
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
29
Stage 2 - Planning and Procurement
(b) Detailed Cost Plan
REQUIREMENTS COMMENTS AND GUIDE
Cost Plan documentation. Submit along
with HCA1 and HCA 2 forms.
Details on proposed costs (including abnormal costs)
Site acquisition cost (if any). Include any abnormal site works and associated costs.
Building acquisition (if any).
Indicate if building cost includes site costs.
Construction cost (including VAT).
Agreed Technical fees (including VAT)
List all Technical consultants
Employer’s Agent / Architect
Quantity surveyor
Engineer(s)
Valuer
Other.
In the case of Part Vs or turnkey projects include cost
for Employers’ Agent who would act on behalf of and
protect the interests of the Approved Housing Body.
Under the new forms of government contracts a lump
sum fee is required.
Where independent valuation is required for Part Vs,
turnkey, design and build, site acquisition the cost of a
qualified Valuer should be included.
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
30
Legal fees and costs (including VAT). Include both the Approved Housing Body’s legal costs
as well as that of the Local Authority.
Capital Application forms (CAS 1, and
LSS1) should also be submitted providing a
summary of the project.
Approval to proceed to be given to AHB and the Local
Authority.
Project cost summary See separate templates for the ‘Project Cost Summary’
for projects by building contracts, design and build, Part
Vs & Turn Key projects.
Date completed by AHB: Day_______________ Month_______________ Year______________
ACTION
Local Authority Approval to proceed to Statutory Planning
Day_______________ Month_______________ Year______________
AHB may wish to take a note of the initial meeting and send a copy of it to the Local Authority.
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
31
Stage 2 - Planning and Procurement
(b)(i) Project Cost Summary
Traditionally Procured Scheme Stage: Initial Appraisal / Pre Planning / Pre Tender / Post Tender (delete as appropriate)
Scheme:
Number of Dwellings:
Proposed Commencement Date:
Estimated Construction Period:
Scheme Details Current Budget Previous Department
Application Approval (if relevant) Use Only
1 Construction Costs
2 VAT @ xxx%
3 Bond
4 Capital Contributions (if not included in 1)
5 sub total
6 Planning Contributions
7 Site Investigation (Inclusive of VAT)
8 Site Purchase
9 Other
10 sub total
11 Architects Fees
12 QS Fees
13 M&E Engineer
14 C&S Engineer
15 PSDP
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
32
Note 1: Net Construction costs
Note 2: VAT at applicable rate applied to net construction costs - currently 13.5%
Note 3: Cost of performance bond that contractor is required to be put in place - Not subject to VAT
Note 4: Contributions to ESB for unit connections, ESB supply for public lighting, Bord Gais supply etc.
Note 6: LA planning contributions levied under xxx should be excluded
16 Other
17 Total Professional Fees
18 VAT on fees
19 sub total
20 Approved Body Legal Fees
(Inclusive of Vat if applicable)
21 Legal Disbursements
22 Legal Fees LA
(inclusive of VAT if applicable)
23 Approved Body Development Allowance
24 Clerk of Works (incl VAT if applicable)
25 Per Cent for Art (if applicable)
26 Other
27 Other
28 sub total
29 Total (5, 10, 19, 28)
30 Average Unit Cost
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
33
Note 7: Actual / anticipated costs associated with geotechnical and topographical survey
Note 8: Cost of site acquisition inclusive of VAT @ 13.5% if relevant
Note 9: Include here for planning notice fees, tender advert fees, valuations etc.
Note11: Agreed architect's fee on a fixed price lump sum basis
Note 12 Agreed QS fee son a fixed price lump sum basis
Note 13 Agreed Engineer's fee on a fixed price lump sum basis
Note 14 Agreed Engineer's fee on a fixed price lump sum basis
Note 15 Agreed fee for PSDP on a fixed price lump sum basis
Note 16 Could include for landscape or environmental consultants etc.
Note 17 Total net professional fees agreed with consultants
Note18: VAT on fees at appropriate rate - currently 21%
Note 20 Voluntary Body legal fee normally charged as a percentage of items 1 and 8
Note21: Disbursements associated with registering title, stamp duty etc. (normally allow for 1,200)
Note22: Extent of legal fees to be agreed with LA
Note23: Allowance calculated at 1.5% of item 1 up to a maximum of 127,000
Note24: To cover the cost of Client supervision on site.
Note25:
Note30: Total costs (item 29) divided by the number of units within the scheme
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
34
Stage 2 - Planning and Procurement
(b)(ii) Project Cost Summary
Design and Build Scheme Stage: Initial Appraisal / Pre Planning / Pre Tender / Post Tender (delete as appropriate)
Scheme:
Number of Dwellings:
Proposed Commencement Date:
Estimated Construction Period:
Scheme Details Current Budget Previous Department
Application Approval (if relevant) Use Only
1 Construction Costs 2 VAT @ xxx% 3 Bond 4 Capital Contributions (if not included in 1) 5 Planning Contributions 6 Site Investigation (Inclusive of VAT) 7 Site Purchase 8 Developer's Design Fee 9 VAT on design fees
10 sub total
11 Employer's Agent
12 VAT on fees
13 Approved Body Legal Fees (Inclusive of Vat if applicable)
14 Legal Disbursements
15 Legal Fees LA
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
35
(inclusive of VAT if applicable)
16 Approved Body Development Allowance
17 Clerk of Works (incl VAT if applicable)
18 Per Cent for Art (if applicable)
19 Other
20 Other
21 sub total
22 Total (10 and 21)
23 Average Unit Cost
Note 1: Net Construction costs Note 2: VAT at appropriate rate should be applicable if land sale linked to building contract
Note 3: Cost of performance bond that contractor is required to be put in place - Not subject to VAT
Note 4: Contributions to ESB for unit connections, ESB supply for public lighting, Bord Gais supply etc. Note 6: LA planning contributions levied under xxx should be excluded Note 7: Actual / anticipated costs associated with geotechnical and topographical survey Note 8: Cost of site acquisition inclusive of VAT @ 13.5% if relevant Note 9: Include here for planning notice fees, tender advert fees, valuations etc. Note10: Total Design and Build Contract Note11: Agreed EA fee on a fixed price lump sum basis Note12: VAT on fees at appropriate rate - currently 21%
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
36
Note 13 Voluntary Body legal fee normally charged as a percentage of items 1 and 8 Note14: Disbursements associated with registering title, stamp duty etc. (normally allow for 1,200)
Note15: Extent of legal fees to be agreed with LA
Note16: Allowance calculated at 1.5% of item 1 up to a maximum of 127,000
Note17: To cover the cost of Client supervision on site. Note18: Note23: Total costs (item 22) divided by the number of units within the scheme
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
37
Stage 2 - Planning and Procurement
(b)(iii) Project Cost Summary
Part V Scheme Stage: Initial Appraisal / Pre Planning / Pre Tender / Post Tender (delete as appropriate)
Scheme:
Number of Dwellings:
Proposed Commencement Date:
Estimated Construction Period:
Scheme Details Current Budget Previous Department
Application Approval (if relevant) Use Only
1 Construction Costs 2 Builders Profit on 1 @ xxx% 3 Attributable Development Costs 4 sub total 5 Developers Profit on 4 6 Site Purchase 7 sub total 8 VAT on 7 @ xxx% 9 Developer's Design Fee
10 VAT on design fees
11 sub total
12 Employer's Agent
13 VAT on fees
14 Approved Body Legal Fees (Inclusive of Vat if applicable)
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
38
15 Legal Disbursements
16 Legal Fees LA (inclusive of VAT if applicable)
17 Approved Body Development Allowance
18 Clerk of Works (incl VAT if applicable)
19 Per Cent for Art (if applicable)
20 Other
21 Other
22 sub total
22 Total (10 and 21)
23 Average Unit Cost
Note 1: Net Construction costs excl Vat and Profit Note 2: Builder entitled to claim reasonable profit on cost of construction Note 3: To include Bond, planning contributions, capital contributions, site investigation etc. Note 4: Developer entitled to claim reasonable profit on net development costs Note 6: Cost of site acquisition as calculated under Part V procedures Note 8: VAT at appropriate rate - currently 13.5% Note 9: Reasonable costs incurred by the developer during design and construct phases Note10: Total Cost of Units to be Acquired under Part V agreement between LA and Developer Note12: Agreed EA fee on a fixed price lump sum basis Note13: VAT on fees at appropriate rate - currently 21%
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
39
Note 14 Voluntary Body legal fee normally charged as a percentage of items 1 and 6
Note15: Disbursements associated with registering title, stamp duty etc. (normally allow for 1,200)
Note16: Extent of legal fees to be agreed with LA Note17: Allowance calculated at 1.5% of item 1 up to a maximum of 127,000 Note18: To cover the cost of Client supervision on site. Actual costs to be evidenced Note19: Note23: Total costs (item 22) divided by the number of units within the scheme
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
40
Stage 2 - Planning and Procurement (b)(iv) Project Cost Summary
Turn Key Scheme Stage: Initial Appraisal / Pre Planning / Pre Tender / Post Tender (delete as appropriate)
Scheme:
Number of Dwellings:
Proposed Commencement Date:
Estimated Construction Period:
Scheme Details Current Budget Previous Department
Application Approval (if relevant) Use Only
1 Purchase Price 2 Cost of Additional works 3 VAT on works
4 Total Cost of Units
5 Deduct Allowance for site value 6 Net Value of Construction
7 Approved Body Legal Fees (Inclusive of Vat if applicable) 8 Legal Disbursements 9 Legal Fees LA (inclusive of VAT if applicable)
10 Approved Body Development Allowance
11 Survey Fees (inclusive of VAT if applicable)
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
41
12 Valuation Fees (inclusive of VAT if applicable)
13 Other
14 Other
15 sub total (7 to 14)
16 Total (4 and 15)
17 Average Unit Cost
Note 1: Net Construction costs excl Vat and Profit
Note 2: Additional works required on the properties as per detailed schedule
Note 3: VAT on 2 at appropriate rate
Note 5: To allow for deduction in costs for land when calculating development allowance
Note 7 Voluntary Body legal fee normally charged as a percentage of items 4 Note 8: Disbursements associated with registering title, stamp duty etc. (normally allow for 1,200) Note 9: Extent of legal fees to be agreed with LA
Note10:
Allowance calculated at 1.5% of item 6 up to a maximum of 127,000
Note11: To cover the cost of Client survey's, snagging etc necessary to confirm suitability of units to be acquired Note12: Independent valuation obtained to confirm purchase price represents value for money Survey to be carried out for each house type, not necessarily each unit to be acquired.
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
42
Note17: Total costs (item 16) divided by the number of units within the scheme
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
43
Stage 2 - Planning and Procurement
(c) Project Plan Checklist
The following information should be submitted with each Project Plan
1 Original project brief and design brief
2 General project commentary explaining how design of scheme has evolved from original project
brief (based on approved template)
3 Cost estimate summary sheet(s) based on approved templates
4 Cost plan and elemental cost analysis based on HCA2 format
5 Space standards and floor area analysis based on “Quality Housing for Sustainable Communities”
6 Confirmation of proposed form of works contract and copies of completed schedule
7 Confirmation of public procurement compliance in relation to the commissioning of project
consultants
8 Amended / updated programme and timeframe for completion of the works
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
44
9 1:500 site plan outlining boundary of site in red and identifying types and site numbers of all
proposed dwellings
10 1:200 (or suitably scaled) site layout identifying types and site numbers of all proposed dwellings
11 1:200 (or suitably scaled) site layout identifying external works, boundary treatments, site
contours, paving and landscaping details, etc
12 1:50 or 1:100 floor plans of all dwellings, showing furniture layouts, room areas, dimensions,
sections and elevations of individual units
13 1:100 or 1:200 block or street elevations indicating relationship to adjoining buildings (if relevant)
14 Project Management Plan- Contract Administration: Who is going to be the Employers
Representative?
15 Financial Profile- cash drawdown, cash flow projections
16 Other
Date Completed by AHB: …………Month……………..Year………
AHB may wish to take a note of the initial meeting and send copy of it to the local authority
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
45
Action:
Local authority to facilitate pre-planning application consultation with Planning Department/Section
Local authority to issue approval to AHB to proceed to submit statutory application for planning
permission
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
46
Stage 2 – Planning & Procurement
(d) Post Planning Permission Cost Review
Following statutory planning permission, the Local Authority will review the cost plan and
check if the planning conditions impact on the project/budget.
The following information is required to be submitted to the Local Authority by the approved
housing body:-
1. Copy of Planning Permission
2. Planning conditions that have implications for the cost of the project or its re- design - list out significant design changes.
3. How does it deviate from the Project plan?
4.
Review of Cost Plan. Is it in line with the cost plan? What are the variances?
Note: if design has changed and increased cost significantly - reapply for additional funding.
Date submitted by AHB………………………
ACTION
Local Authority approval to proceed to tender in writing based on sanction of funding by the DoEHLG
for pre-tender cost plan
Approved Housing Body prepares Contract construction drawings, specifications and documents in line
with public procurement procedures for building works contracts.
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
47
Stage 2- Planning & Procurement
(e) Approved Housing Body’s Record of Tender Opening for Works
Contracts
Scheme: Date and Time of Opening:
Main Contract / Mechanical Sub Contract / Electrical Sub Contract / Lift Sub Contract / Other:
………………………………..………………………………………………………………..…..
Contractor
Tender
Sum
VAT Incl
/Excl
Programme Compensation
Events
Ranking Bond
Comment
1
2
3
4
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
48
5
6
7
8
To be supplied with consultant quantity surveyor’s evaluation report and HCA Form
Opened in the presence of: ……………………………………… (for and on behalf of Housing
Association)
Name of Witness 1: ………………………………. Signature of Witness 1:
……………………………….………….…………….
Name of Witness 2: ………………………………. Signature of Witness 2:
……………………………….………….…………….
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
49
Stage 2 - Planning & Procurement
(f) Tender Evaluation Report-report following receipt of Price Tenders for
Building Works Contract
Consultant Evaluation Report Comment
Procurement/tender process.
Identify procurement procedure used.
Procurement process whether open, selective or
negotiated. EU or National. Call for a specific
project or restricted to an existing framework.
List of contractors who submitted tender prices
Name of successful tender and the organisational
structure
Ranking of submitted and valid tenders; include
copy of tender opening page, which includes
recommendation and states this represents VFM
Refer back to re-tender and highlight any
discrepancies i.e. why there are any differences,
changes to price if outside a particular margin.
In terms of ranking criteria, ranking in ascending
order of submitted tenders
Note the information provided here may be
commercially sensitive
Pre-selection criteria is preferable
Indicative programme Indication of elements of building programme
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
50
Criteria used (MEAT)
For Most Economically Advantageous Tender
(MEAT) indicate the quality to price ratio as well
as ranking of quality criteria.
Additional Requirements from successful
tenderer
Tax Clearance, insurance requirements,
professional indemnity, health and safety etc.
Other comments about successful tender
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
51
Stage 2 - Planning & Procurement
(g) Post Tender Funding Submission Checklist
The following information should be submitted with each post tender funding application
1.
Completed application forms
2.
Scheme Commentary Identifying how scheme has progressed from Project Plan
approval
3.
Copy of Planning / Fire Cert Approval
4.
Cost Estimate Summary sheet(s) based on approved templates
5.
Tender Report and Cost Analysis based on HCA2 format
6.
Contractor Cash Flow Analysis
VOLUNTARY & CO-OPERATIVE HOUSING CAPITAL FUNDING SCHEMES
Templates for Application, Appraisal and Approval Stages
52
7.
Confirmation of public procurement compliance in relation to the commissioning of the
Works
8.
Additional Site Layout and Floor Plans if drawings significantly different from those
submitted as part of the Project Plan
NB: Circular N7/2007 [Link to circular] stresses that even once a scheme has been included on the SHIP,
changing circumstances in specification or costs of a project may require a fresh assessment.