$ssolhg 3urmhfw &rqwurov · schedule status at the end of week 2: • activity a started on...
TRANSCRIPT
PAPERBACK BOOK - STANDING
www.PhotoshopActionScripts.com
Project ControlsTraining Manual
Applied
Your Ultimate Guide to Successin Project Control and Management
Table of Contents
Module 5-‐ Execution of Project Controls
Record Schedule Status ............................................................................................................................................. 6
Record Cost Status ................................................................................................................................................... 14
Measure Earned Value Key Components .................................................................................................. 16
Exercise # 1-‐ Calculating the key components of Earned Value ................................................................. 34
Performance Measurement Methods ....................................................................................................... 41
Fixed Formula .................................................................................................................................. 45
Percent Complete ............................................................................................................................ 48
Weighted Milestone ........................................................................................................................ 50
Apportioned Effort .......................................................................................................................... 53
Level of Effort (LOE) ......................................................................................................................... 57
Review of Module 5 ................................................................................................................................................. 60
Page: 1 2014 © Project Control Academy, All rights reserved
By the end of this module, you will learn: The elements of schedule and cost status recording. The steps involved in schedule upda;ng process. Three key components ( PV, AC, EV) of cost status recording in applying the Earned Value Management technique. The difference between the Tradi;onal Management and Earned Value Management. Various techniques available to calculate Earned Value.
Page: 2 2014 © Project Control Academy, All rights reserved
In previous modules, three major elements of planning; Scope Planning, Time Planning, and Cost planning were discussed. Through the integrated scope, ;me, and cost planning, the project “baseline” is established. ANer establishing the project’s Baseline and freezing the Baseline, we are ready to execute the work. The execu;on stage is covered in this module.
Page: 3 2014 © Project Control Academy, All rights reserved
Execu&on of Project Controls Record Schedule Status
Record / Measure Cost Status
Do
The role of Project Controls in the execu;on stage of the project is to accurately and regularly record and measure the project progress against the frozen baseline.
The role of planner/scheduler during the execu;on stage is to record the schedule progress.
The role of a cost controller during execu;on stage is to capture actual costs, physical progress, and changes to the BL.
The above figures will be used for monitoring and controlling performance against the frozen project’s baseline.
Page: 4 2014 © Project Control Academy, All rights reserved
Measure EV Key Components
(PV, AC, EV)
Select EV Measurement
Method
Record Cost Status
In execu;ng a project, to determine the status of projects, three key components are examined:
Cost and Schedule Baseline (What is Planned) Actual expenditures (What is done) Recorded accomplishment or “Earned Value” (What is earned)
To measure progress (“physical” accomplishments), we will review various Earned Value methods.
Page: 5 2014 © Project Control Academy, All rights reserved
WBS Schedule Budget
Scope Planning
Time Planning
Cost Planning
Planning
PMB PV
EV Methods
AC
Physical% Complete
EV
Financial Accounting
Sys.
Cost Control System
Execution
Schedule Updates Schedule
Software
Page: 6 2014 © Project Control Academy, All rights reserved
Record Schedule Status Record Cost Status
Page: 7 2014 © Project Control Academy, All rights reserved
Change is inevitable and every project will experience it. Change can occur simply by:
Work progressing more quickly or slowly than planned, Changes in other elements of the project occur (e.g. scope changes),
The project team decides to modify its approach to the project work.
The purpose of schedule status recording/ upda;ng is to ;mely track the changes to the schedule baseline.
Page: 8 2014 © Project Control Academy, All rights reserved
The steps involved in schedule upda;ng process during the repor;ng cycle are: Collect and record the actual status of the work. The informa;on collected should include: The actual start dates for all ac;vi;es that have been commenced. The actual finish dates for all ac;vi;es that have been completed. Where an ac;vity is in progress, the amount of work accomplished and the ;me needed to complete the remaining work should be determined.
- PMI Practice Standard for Scheduling
Page: 9 2014 © Project Control Academy, All rights reserved
The steps involved in schedule upda;ng process during the repor;ng cycle are: Enter status informa;on into the schedule model and re-‐analyze the remaining work to determine the project status. The new project status is determined aNer changing the data date and re-‐calcula;ng the cri;cal path. The data is collected as of a nominated date/;me. This date/;me is called the data date and is analogous to “;me now” in EVM.
- PMI Practice Standard for Scheduling
Page: 10 2014 © Project Control Academy, All rights reserved
Ac&vity Dura&on Preceding Ac&vity
Start O
A 3 Start
B 4 Start
C 2 Start
D 2 B
E 5 A, C
F 1 B
G 6 D, F
H 11 E
I 8 D, F
Finish 0 G, H, I
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
A
B
C
D
E
F
G
H
I
Page: 11 2014 © Project Control Academy, All rights reserved
Ac&vity Dura&on Preceding Ac&vity
Start O
A 3 Start
B 4 Start
C 2 Start
D 2 B
E 5 A, C
F 1 B
G 6 D, F
H 11 E
I 8 D, F
Finish 0 G, H, I
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
A
B
C
D
E
F
G
H
I
Schedule Status at the end of Week 2:
• Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on week 4. • Activity C is completed as per the plan.
Page: 12 2014 © Project Control Academy, All rights reserved
Ac&vity Dura&on Preceding Ac&vity
Start O
A 3 Start
B 4 Start
C 2 Start
D 2 B
E 5 A, C
F 1 B
G 6 D, F
H 11 E
I 8 D, F
Finish 0 G, H, I
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
A
B
C
D
E
F
G
H
I
Page: 13 2014 © Project Control Academy, All rights reserved
The newly updated schedule should be compared with the baseline and schedule variances should be managed. The status/ update process occurs on a regular basis determined during project planning process, which is documented on the Basis of Schedule document.
Page: 14 2014 © Project Control Academy, All rights reserved
Record Schedule Status Record Cost Status
Record/ Measure EV Key Components
(PV, AC, EV)
Select EV Measurement
Method
Page: 15 2014 © Project Control Academy, All rights reserved
You must record cost informa;on periodically to use Earned Value Management (EVM). More and more organiza;ons around the world are using EVM to help control project costs. EVM is a project performance measurement technique that integrates scope, ;me, and cost data. “Earned Value Management” is an industry standard way to:
measure a project’s progress, forecast its comple;on date and final cost, and provide schedule and budget variances along the way
Page: 16 2014 © Project Control Academy, All rights reserved
Record Cost Status
Record/ Measure EV Key Components
(PV, AC, EV)
Select EV Measurement Method
Page: 17 2014 © Project Control Academy, All rights reserved
Painting 4 Bedrooms
$1000 Budget
5 Weeks
Page: 18 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Page: 19 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Plan
Actual
Can you make your friend happy?!
Page: 20 2014 © Project Control Academy, All rights reserved
• What is your physical progress?!
• Only Painted 1 BDR out of 4 BDRs (25% Progress)
Earned = 25% x $1000 = $250
Page: 21 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Plan
Actual
Earned
Page: 22 2014 © Project Control Academy, All rights reserved
• PV = Budgeted Cost of Work Planned
Page: 23 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Plan
Actual
Earned
PV = $600
What is the PV on Week 3?
Page: 24 2014 © Project Control Academy, All rights reserved
• PV = Budgeted Cost of Work Planned • AC = Actual Cost of Work Performed
Page: 25 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Plan
Actual
Earned
PV = $600 AC = $500
What is the AC on Week 3?
Page: 26 2014 © Project Control Academy, All rights reserved
• PV = Budgeted Cost of Work Planned • AC = Actual Cost of Work Performed • EV = Budgeted Cost of Work Performed
Page: 27 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Plan
Actual
Earned
PV = $600 AC = $500
EV = $250
What is the EV on Week 3?
Page: 28 2014 © Project Control Academy, All rights reserved
Budget = $1000 PV = $600 AC = $500 EV = $250
$1000
$600
PV AC
$500
EV $250
Page: 29 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Plan
Actual
Page: 30 2014 © Project Control Academy, All rights reserved
$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5$0
$200
$400
$600
$800
$1,000
$1,200
Week 1 Week 2 Week 3 Week 4 Week 5
Plan
Actual
Earned
PV = $600 AC = $500
EV = $250
Page: 31 2014 © Project Control Academy, All rights reserved
Tradi&onal Management provides you with… How much money and ;me a par;cular job is likely to require prior to star;ng and once started, how much money was spent at any given ;me.
Earned Value Management provides you with… How much money and ;me a par;cular job is likely to require prior to star;ng and once started, how much money was spent at any given ;me.
PLUS Once started, what work has been accomplished to date for the funds expended (what you got for what you spent)
Once started, what the total job will cost at comple;on, and how long it will take to complete.
Source: DOE Introduction to Earned Value Management by Booz Allen Hamilton
Page: 32 2014 © Project Control Academy, All rights reserved
Planned Value (PV)
PV = Budgeted Cost of Work Planned PV is a numeric reflection of the budgeted work that is scheduled to be performed, and it is the established baseline (PMB) against which the actual progress of the project is measured. PV is the result of Cost & Schedule Baseline. Cumulative PV is the sum of the approved budget for activities scheduled to be performed to date. Period PV is the approved budget for activities scheduled to be performed during a given period.
Page: 33 2014 © Project Control Academy, All rights reserved
Planned Value (PV)
Keep some important points in mind regarding PV: Project Total PV must always equal to the Project Budget at Completion (BAC) BAC= Sum of all budgets allocated to a project scope. BAC= PMB= Project Total PV If Project Total PV # BAC, your EV calculations and analysis will be inaccurate.
Page: 34 2014 © Project Control Academy, All rights reserved
Calcula;ng Key Components of EVM ( PV, EV, AC)
Page: 35 2014 © Project Control Academy, All rights reserved
Planned Value (PV)
You are working on a computer programming project, and part of the scope is for software design. The time frame for software design is 6 months and the budget for this scope is $12,000, resulting in a budget of $2000 per month.
Calculate the Cumulative and Period PV at the end
of 3rd month. What is the Project Total PV for the complete software design scope of the project?
Page: 36 2014 © Project Control Academy, All rights reserved
Actual Cost (AC)
AC = Actual Cost of Work Performed AC = Actual Expenditure, the cost incurred for executing the work. Cumulative AC is the sum of the actual cost for activities performed to date. Period AC is the actual costs of activities performed during a given period.
Page: 37 2014 © Project Control Academy, All rights reserved
Actual Cost (AC) Computer Programming Project- WBS 1.1.1 Software Design Calculate the Cumulative and Period ACs on Month 3rd.
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
$2000 $2000
$2000
$2000
$2000
$2000
$1200 $800 $1500
Time Now
Page: 38 2014 © Project Control Academy, All rights reserved
Earned Value (EV)
EV = Budgeted Cost of Work Performed EV = Quantification of the “worth” of the work done to date. EV = Physical accomplishment of the project to date EV= Physical % Complete x Current Budget Cumulative EV is the sum of the budget for the activities accomplished to date. Period EV is the sum of the budget for the activities accomplished in a given period.
Page: 39 2014 © Project Control Academy, All rights reserved
Earned Value (EV) Computer Programming Project- WBS 1.1.1 Software Design Calculate the Cumulative and Period EV on Month 3 by assuming that the
physical % complete to date ( 3rd month) is 40% and the cum. actual progress in the previous month was 30%.
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
$2000 $2000
$2000
$2000
$2000
$2000
$1200 $800 $1500
Time Now
PV
AC
Page: 40 2014 © Project Control Academy, All rights reserved
Earned Value Key Components (PV, AC,EV)
At this point, you should have a good understanding of the three key Earned Value components: Planned Value (PV) is the result of PMB ( cost & schedule baseline, discussed in previous modules) Actual Cost (AC) is determined by the actual cost incurred on the project. Earned Value (EV) tells you, in physical terms, what the project is accomplished. Question: How do you determine the physical accomplishment in a project?
Page: 41 2014 © Project Control Academy, All rights reserved
Record Cost Status
Record/ Measure EV Key Components
(PV, AC, EV)
Select EV Measurement Method
Page: 42 2014 © Project Control Academy, All rights reserved
Earned Value (EV) = Objective measuring the physical accomplishment of an activity.
( EV = Physical % x Budget )
Measure EV Key Components
(PV, AC, EV)
Select EV Measurement
Method
Physical %?
100%
Page: 43 2014 © Project Control Academy, All rights reserved
Earned Value techniques should be selected based on the key attributes of the work:
- The Duration of the Effort - The tangibility of its products/ services
Measure EV Key Components
(PV, AC, EV)
Select EV Measurement
Method
Page: 44 2014 © Project Control Academy, All rights reserved
Product / Service
of Work
Dura&on of Work Effort
1-‐2 Measurement Periods
>2 Measurement Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor;oned Effort Level of Effort
Earned Value Measurement Techniques
Source: PMI Practice Standard for Earned Value Management
Page: 45 2014 © Project Control Academy, All rights reserved
Product /
Service of Work
Dura&on of Work Effort
1-‐2 Measurement
Periods
>2 Measurement
Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor;oned Effort Level of Effort
Fixed Formula X% 100-X%
X% of the work is credited as complete for the measurement period in which the work begins, regardless of how much work has actually been accomplished.
The remaining (100-X%) is credited when the work is completed.
Requires very detailed and short span work packages.
Example: 25%/75% method for purchased material.
Page: 46 2014 © Project Control Academy, All rights reserved
Product /
Service of Work
Dura&on of Work Effort
1-‐2 Measurement
Periods
>2 Measurement
Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor;oned Effort Level of Effort
Fixed Formula X% 100-X%
Important rule in using this method: • Defined tasks not exceed one or
two maximum reporting periods, measured either weekly or monthly.
Page: 47 2014 © Project Control Academy, All rights reserved
Fixed Formula- Exercise Calculate Earned Value for following tasks: ( EV= Budget x Physical%)
Task 1 Budget: 12
Task 2 Budget: 100
Task 3 Budget: 55
Task 4 Budget: 82
50% 50%
25% 75%
0% 100%
Cut-Off date
25% 75%
Page: 48 2014 © Project Control Academy, All rights reserved
Product /
Service of Work
Dura&on of Work Effort
1-‐2 Measurement
Periods
>2 Measurement
Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor;oned Effort Level of Effort
Percent Complete X% 100%
Estimate of the % of work completed during the reporting period. Such estimates are made by individuals in charge of the a
given work package. The Simplest and easiest method, but can be the most
subjective of the EV measurement techniques if there are no objective indicator to back it up.
This method requires a sort of informal “check and balance” on the accuracy of the periodic estimates.
Page: 49 2014 © Project Control Academy, All rights reserved
Percent Complete- Exercise X% 100%
What is the physical % completion of this “Applied Project Controls Course” at this moment?!
Page: 50 2014 © Project Control Academy, All rights reserved
Product /
Service of Work
Dura&on of Work Effort
1-‐2 Measurement
Periods
>2 Measurement
Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor;oned Effort Level of Effort
Weighted Milestone
Divides the work to be completed
into segments, each ending with an observable milestone; it then assigns a value to the
achievement of each milestone. More suitable for longer duration tasks having tangible
outcomes. Once the work is underway, values should not be changed. A preferred method used in performance measurement, but
also a most difficult method to initially plan.
Page: 51 2014 © Project Control Academy, All rights reserved
Weighted Milestone- Example
P&IDs Gated Milestones 1- CAD Set-up 5% 2- Engineering related to P&IDs 25% 3- Initial Drafting 20% 4- Issue for In-House Review 10% 5- Issue for Customer Review 10% 6- Issue for Design Review/ HAZOP 15% 7- Issue for Design 15%
1
5% 25% 20% 10% 10% 15% 15%
2 3 4 5 6 7
100%
Page: 52 2014 © Project Control Academy, All rights reserved
Weighted Milestone- Exercise
P&IDs Gated Milestones
1- CAD Set-up 5% 2- Engineering related to P&IDs 25% 3- Initial Drafting 20% 4- Issue for In-House Review 10% 5- Issue for Customer Review 10% 6- Issue for Design Review/ HAZOP 15% 7- Issue for Design 15%
P&ID Issued for Customer Review. P&ID issued for HAZOP @ 50%. Calculate the Physical % Complete.
1
5% 25% 20% 10% 10% 15% 15%
2 3 4 5 6 7
Page: 53 2014 © Project Control Academy, All rights reserved
Product /
Service of Work
Dura&on of Work Effort
1-‐2 Measurement
Periods
>2 Measurement
Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor&oned Effort Level of Effort
Apportioned Effort If a task has a direct, supportive
relationship to another task that has its own EV, the value for the support task may be determined based on ( or apportioned to) the EV of the reference base activity. When work is performed in the base task, it is assumed that
work will be performed in the apportioned task. Examples of apportioned tasks include QA and inspection
activities.
Page: 54 2014 © Project Control Academy, All rights reserved
Apportioned Effort An apportioned effort PV is directly proportional to the
associated base effort’s budget and time phasing. An apportioned effort EV is directly proportional to actual
amount of base work that is completed during the reporting period.
An advantage of this technique is that it simplifies the earned value management of recurring support activities by defining standardized percentages for these tasks.
Page: 55 2014 © Project Control Academy, All rights reserved
Apportioned Effort- Example QA Control Account appor;oned @ 10% of produc;on control account
Mar Apr May Total
Produc;on Control Account PV 100 500 200 800
QA Control Account PV 10 50 20 80
Produc;on Control Account EV 250 400 150 800
QA Control Account EV 25 40 15 80
Page: 56 2014 © Project Control Academy, All rights reserved
Apportioned Effort- Example
Actual
Page: 57 2014 © Project Control Academy, All rights reserved
Product /
Service of Work
Dura&on of Work Effort
1-‐2 Measurement
Periods
>2 Measurement
Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor;oned Effort Level of Effort
Level of Effort (LOE) The project activities that do not
produce tangible outcomes and cannot be measured objectively, but are necessary to support a project uses the LOE method. LOEs are more “time” sensitive than “performance” sensitive. Examples of the LOE tasks are the tasks related to Project
Management Team, project controls, procurement, contract admin, security guards, cooks, helpdesks,…
Whenever these functions are charged to the project, they normally start at the beginning of project and continue for the full term of the project.
Page: 58 2014 © Project Control Academy, All rights reserved
Level of Effort (LOE) LOE tasks have no schedule variance ( EV= PV) and can bias
the project data towards an on-schedule condition. Although LOE tasks resemble indirect work on projects, the
performance measurement on LOE tasks has an impact on the overall project performance.
LOE efforts generally have no measurable or deliverable outputs. So, LOE method should be used only when the task does not lend itself to a technique that actually measures physical work progress.
Page: 59 2014 © Project Control Academy, All rights reserved
Level of Effort (LOE)-Example Planned Value for Project Coordination & Support: What is the Cum. EV in March?
Month Jan Feb Mar Apr May Jun Jul Aug
PV 1000 1200 1000 900 1100 1500 1000 500
Time Now
Page: 60 2014 © Project Control Academy, All rights reserved
Execution of Project Controls
Page: 61 2014 © Project Control Academy, All rights reserved
The role of Project Controls in the execution stage of the project is to accurately and regularly record and measure the project progress against the frozen baseline. Record Schedule Status Record Cost Status (EV, AC)
The purpose of schedule status recording/ updating is to timely track the changes to the schedule baseline.
Page: 62 2014 © Project Control Academy, All rights reserved
There are three key components to Cost Recording: Planned Value, Earned Value, and Actual Cost. PV is the work scheduled or “what you plan to do”. EV is the quantification of the “worth” of the work done to date or “what you physically achieved”. AC is the cost incurred for executing work on a project or “what you have spent”.
Page: 63 2014 © Project Control Academy, All rights reserved
Acronym Variable Defini&on Meaning
PV Budgeted Cost of Work Scheduled
Time phased es;mated value of planned work.
Planning Baseline-‐ PMB
EV Budgeted Cost of Work Performed
Time phased es;mated value of completed work
Work Accomplishment Earned Value
AC Actual Cost of Work Performed
Time phased costs incurred for completed work
Expenditures Actuals are Actuals
Page: 64 2014 © Project Control Academy, All rights reserved
Techniques for measuring work performed ( Physical % Progress) are the basis for performance measurement during project execution and control. Earned Value techniques should be selected based on the key attributes of the work; duration & tangibility of end deliverables.
Product / Service of
Work
Dura&on of Work Effort
1-‐2 Measurement Periods
>2 Measurement Periods
Tangible Fixed Formula Weighted Milestone Percent Complete
Intangible Appor;oned Effort Level of Effort
Page: 65 2014 © Project Control Academy, All rights reserved
EV Method Meaning Advantage Disadvantage
Fixed Formula
X% of the work is credited as complete for the measurement period in which the work begins, regardless of how much work has actually been accomplished. The remaining (100-X%) is credited when the work is completed.
For short term work packages Requires minimal effort to status
Defined tasks not exceed one or two maximum reporting periods. Not effective for longer term work packages
% Complete Estimate of the % of work completed during the reporting period.
The Simplest and easiest method. Based on the CAM's assessment of the work packages progress
The most subjective of the EV measurement techniques if there are no objective indicator to back it up. Requires a sort of informal “check and balance” on the accuracy of the periodic estimates
Weighted Milestone
Divides the work to be completed into segments, each ending with an observable milestone; it then assigns a value to the achievement of each milestone.
A preferred method used in performance measurement. Suitable for longer duration tasks having tangible outcomes.
One of the most difficult methods to initially plan.
Apportioned Effort
If a task has a direct, supportive relationship to another task that has its own EV, the value for the support task may be determined based on ( or apportioned to) the EV of the reference base activity.
Simplifies the earned value management of recurring support activities
Used only for tasks that have a direct, supportive relationship to another task.
Level of Effort (LOE)
The project activities that do not produce tangible outcomes and cannot be measured objectively, but are necessary to support a project uses the LOE method
Does not require statusing, and is appropriate for sustaining tasks such as Program Management.
LOE tasks have no schedule variance ( EV= PV) and can bias the project data towards an on-schedule condition. LOE method should be kept to a minimal number of work packages. LOE method should be used only when the task does not lend itself to a technique that actually measures physical work progress.
Page: 66 2014 © Project Control Academy, All rights reserved
Record / Measure Cost Status
Record Schedule Status
Project Controls Scope
Planning Time
Planning Cost
Planning
Plan
Do
Checking & Measuring Variances
Measuring Performance Indices
Check
Future Analysis Trend Analysis
Baseline Analysis
Change Control
Act
Page: 67 2014 © Project Control Academy, All rights reserved
Project Controls
Execution of Project Control (Recording/ Measuring Cost and Schedule Status)
Planning & Development of Scope, Time, and Cost (Fundamental steps to Form Project Baseline)
Checking the Performance (Measuring & Monitoring Cost and Schedule Performance against Baseline) Cost & Schedule
Analysis & Taking Action (Analyzing Performance Results and Forecasting Project behaviour)
Page: 68 2014 © Project Control Academy, All rights reserved
Are you Ready to Move on to Module 6,
Checking the Performance?
Copyrig ht © 20 12 Project Control A cadem y.A ll Rig hts Res erved. Do not du plicate or dis tribu te w ithou t perm is s ion.
Applied Project Controls TrainingMaintain Control, Boost Performance, and
Achieve Successin Your Projects
Your Unique Guide to …
The A pplied Project Controls training s eries equ ips you w ith fu ndam ental and practical tools to enhance you r com petency and perform ance in controlling and m anag ing you r projects . This cou rs e provides you a s tep-by-s tep proces s from planning to execu tion and control of project’s s chedu le and cos t in a s im ple yet effective m anner. Clos ely alig ned w ith the Project M anag em ent Ins titu te’s s tandards and g u idelines ,A pplied Project Controls training offers bas ic and advanced m ethods for k eeping you r projects in control. It provides you a clear u nders tanding of the Project Controls ’ concepts , tools , and techniqu es that can be applied to any project w ithin any indu s try.
TheThe A pplied Project Controls video training is com pos ed of 7 m odu les that are delivered as 12 online videos or DVDs :
- M odu le 1- Introdu ction to Project Controls - M odu le 2- Scope Planning - M odu le 3- Tim e Planning (Parts 1-3) - M odu le 4- Cos t Planning - M odu le 5- Execu tion of Project Controls (Parts 1-2) - M odu le 6- Check ing the Perform ance - M odu le 7- Cos t and Schedu le A nalys is (Parts 1-3)
J u s t w atch the videos , learn from the exam ples , do the exercis es , and follow the s ys tem . You can becom e the next expert in you r field. You can do this . The project m anag em ent w orld needs you .
Shohreh G horbani, PM P, is a s eas oned Project Control Profes s ional w ith years of hands -on experience on a w ide rang e of project m anag em ent technical areas in variou s indu s tries . She has a dem ons trated track record of s u cces s in execu ting earned valu e m anag em ent, cos t control, planning /s chedu ling , ris k m anag em ent, and qu ality m anag em ent. She has m anag ed larg e nu m ber of s u cces s fu l oil and g as and m anu factu ring projects of varying s ize and com plexity in Canada and overs eas .
Prior to es tablis hing Project Control A cadem y, s he developed s eries of training videos for Project Control departm ent of an international com pany. Her training videos w ere w ell received and s hared g lobally w ithin the com pany. Finding her pas s ion in Project Controls , s he continu ed to s hare her k now ledg e throu g h teaching at edu cational ins titu tes and corporations . She fou nded Project Control A cadem y to fu rther s hare her k now ledg e and s erve m ore people.
Shohreh is a profes s ional m em ber of Project M anag em ent Ins titu te (PM I) and A m erican A s s ociation of Cos t Eng ineers (A A CE). She holds M as ter of Science in Indu s trial Eng ineering . M eet her at w wM eet her at w w w .ProjectControlA cadem y.com
Meet Shohreh Ghorbani, Founder of Project Control Academy