$ssolhg 3urmhfw &rqwurov · schedule status at the end of week 2: • activity a started on...

72

Upload: others

Post on 25-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

PAPERBACK BOOK - STANDING

www.PhotoshopActionScripts.com

Project ControlsTraining Manual

Applied

Your Ultimate Guide to Successin Project Control and Management

Page 2: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on
Page 3: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

                                                                                                                                                                                                                                                                             

 

Table  of  Contents    

 

Module  5-­‐  Execution  of  Project  Controls    

Record  Schedule  Status  .............................................................................................................................................  6  

Record  Cost  Status  ...................................................................................................................................................  14  

Measure  Earned  Value  Key  Components  ..................................................................................................  16  

Exercise  #  1-­‐  Calculating  the  key  components  of  Earned  Value  .................................................................  34  

Performance  Measurement  Methods  .......................................................................................................  41  

Fixed  Formula  ..................................................................................................................................  45  

Percent  Complete  ............................................................................................................................  48  

Weighted  Milestone  ........................................................................................................................  50  

Apportioned  Effort  ..........................................................................................................................  53  

Level  of  Effort  (LOE)  .........................................................................................................................  57  

Review  of  Module  5  .................................................................................................................................................  60  

 

Page 4: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 1 2014 © Project Control Academy, All rights reserved

   By  the  end  of  this  module,  you  will  learn:      The  elements  of  schedule  and  cost  status  recording.      The  steps  involved  in  schedule  upda;ng  process.    Three  key  components  (  PV,  AC,  EV)  of  cost  status  recording  in  applying  the  Earned  Value  Management  technique.    The  difference  between  the  Tradi;onal  Management  and  Earned  Value  Management.    Various  techniques  available  to  calculate  Earned  Value.  

 

Page 5: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 2 2014 © Project Control Academy, All rights reserved

   In  previous  modules,  three  major  elements  of  planning;  Scope  Planning,  Time  Planning,  and  Cost  planning  were  discussed.      Through  the  integrated  scope,  ;me,  and  cost  planning,  the  project  “baseline”  is  established.      ANer  establishing  the  project’s  Baseline  and  freezing  the  Baseline,  we  are  ready  to  execute  the  work.      The  execu;on  stage  is  covered  in  this  module.  

Page 6: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 3 2014 © Project Control Academy, All rights reserved

Execu&on  of  Project  Controls  Record                                        Schedule  Status  

Record  /  Measure  Cost  Status  

Do

  The  role  of  Project  Controls  in  the  execu;on  stage  of  the  project  is  to  accurately  and  regularly  record  and  measure  the  project  progress  against  the  frozen  baseline.    

 

  The  role  of  planner/scheduler  during  the  execu;on  stage  is  to  record  the  schedule  progress.  

  The  role  of  a  cost  controller  during  execu;on  stage  is  to  capture  actual  costs,  physical  progress,  and  changes  to  the  BL.  

  The  above  figures  will  be  used  for  monitoring  and  controlling  performance  against  the  frozen  project’s  baseline.  

Page 7: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 4 2014 © Project Control Academy, All rights reserved

Measure  EV                                              Key  Components                                          

(PV,  AC,  EV)  

Select  EV  Measurement  

Method  

Record Cost Status

  In  execu;ng  a  project,  to  determine  the  status  of  projects,  three  key  components  are  examined:    

  Cost  and  Schedule  Baseline  (What  is  Planned)    Actual  expenditures  (What  is  done)    Recorded  accomplishment  or  “Earned  Value”  (What  is  earned)  

  To  measure  progress  (“physical”  accomplishments),  we  will  review  various  Earned  Value  methods.  

Page 8: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 5 2014 © Project Control Academy, All rights reserved

WBS Schedule Budget

Scope                  Planning  

Time  Planning  

Cost  Planning  

Planning

PMB PV

EV Methods

AC

Physical% Complete

EV

Financial Accounting

Sys.

Cost Control System

Execution

Schedule Updates Schedule

Software

Page 9: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 6 2014 © Project Control Academy, All rights reserved

Record  Schedule  Status   Record  Cost  Status  

Page 10: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 7 2014 © Project Control Academy, All rights reserved

 

  Change  is  inevitable  and  every  project  will  experience  it.      Change  can  occur  simply  by:  

  Work  progressing  more  quickly  or  slowly  than  planned,    Changes  in  other  elements  of  the  project  occur  (e.g.  scope  changes),  

  The  project  team  decides  to  modify  its  approach  to  the  project  work.  

  The  purpose  of  schedule  status  recording/  upda;ng  is  to  ;mely  track  the  changes  to  the  schedule  baseline.  

Page 11: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 8 2014 © Project Control Academy, All rights reserved

 

  The  steps  involved  in  schedule  upda;ng  process  during  the  repor;ng  cycle  are:    Collect  and  record  the  actual  status  of  the  work.  The  informa;on  collected  should  include:    The  actual  start  dates  for  all  ac;vi;es  that  have  been  commenced.    The  actual  finish  dates  for  all  ac;vi;es  that  have  been  completed.    Where  an  ac;vity  is  in  progress,  the  amount  of  work  accomplished  and  the  ;me  needed  to  complete  the  remaining  work  should  be  determined.  

- PMI Practice Standard for Scheduling

Page 12: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 9 2014 © Project Control Academy, All rights reserved

 

  The  steps  involved  in  schedule  upda;ng  process  during  the  repor;ng  cycle  are:    Enter  status  informa;on  into  the  schedule  model  and  re-­‐analyze  the  remaining    work  to  determine  the  project  status.    The  new  project  status  is  determined  aNer  changing  the  data  date  and  re-­‐calcula;ng  the  cri;cal  path.    The  data  is  collected  as  of  a  nominated  date/;me.  This  date/;me  is  called  the  data  date  and  is  analogous  to  “;me  now”  in  EVM.  

- PMI Practice Standard for Scheduling

Page 13: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 10 2014 © Project Control Academy, All rights reserved

Ac&vity   Dura&on   Preceding  Ac&vity  

Start   O  

A   3   Start  

B   4   Start  

C   2   Start  

D   2   B  

E   5   A,  C  

F   1   B  

G   6   D,  F  

H   11   E  

I   8   D,  F  

Finish   0   G,  H,  I  

1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19  

A

B

C

D

E

F

G

H

I

Page 14: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 11 2014 © Project Control Academy, All rights reserved

Ac&vity   Dura&on   Preceding  Ac&vity  

Start   O  

A   3   Start  

B   4   Start  

C   2   Start  

D   2   B  

E   5   A,  C  

F   1   B  

G   6   D,  F  

H   11   E  

I   8   D,  F  

Finish   0   G,  H,  I  

1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19  

A

B

C

D

E

F

G

H

I

Schedule Status at the end of Week 2:

•  Activity A started on time and is completed. •  Activity B has not started yet. It is forecasted to start on week 4. •  Activity C is completed as per the plan.

Page 15: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 12 2014 © Project Control Academy, All rights reserved

Ac&vity   Dura&on   Preceding  Ac&vity  

Start   O  

A   3   Start  

B   4   Start  

C   2   Start  

D   2   B  

E   5   A,  C  

F   1   B  

G   6   D,  F  

H   11   E  

I   8   D,  F  

Finish   0   G,  H,  I  

1   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19  

A

B

C

D

E

F

G

H

I

Page 16: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 13 2014 © Project Control Academy, All rights reserved

 

  The  newly  updated  schedule  should  be  compared  with  the  baseline  and  schedule  variances  should  be  managed.    The  status/  update  process  occurs  on  a  regular  basis  determined  during  project  planning  process,  which  is  documented  on  the  Basis  of  Schedule  document.  

Page 17: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 14 2014 © Project Control Academy, All rights reserved

Record  Schedule  Status   Record  Cost  Status  

Record/  Measure  EV                                              Key  Components                                          

(PV,  AC,  EV)  

Select  EV  Measurement  

Method  

Page 18: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 15 2014 © Project Control Academy, All rights reserved

 

  You  must  record  cost  informa;on  periodically  to  use  Earned  Value  Management  (EVM).    More  and  more  organiza;ons  around  the  world  are  using  EVM  to  help  control  project  costs.    EVM  is  a  project  performance  measurement  technique  that  integrates  scope,  ;me,  and  cost  data.    “Earned  Value  Management”  is  an  industry  standard  way  to:    

  measure  a  project’s  progress,    forecast  its  comple;on  date  and  final  cost,  and    provide  schedule  and  budget  variances  along  the  way  

Page 19: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 16 2014 © Project Control Academy, All rights reserved

Record  Cost  Status  

Record/  Measure  EV                                              Key  Components                                          

(PV,  AC,  EV)  

Select  EV  Measurement  Method  

Page 20: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 17 2014 © Project Control Academy, All rights reserved

Painting 4 Bedrooms

$1000 Budget

5 Weeks

Page 21: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 18 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Page 22: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 19 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Plan

Actual

Can you make your friend happy?!

Page 23: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 20 2014 © Project Control Academy, All rights reserved

• What is your physical progress?!

•  Only Painted 1 BDR out of 4 BDRs (25% Progress)

Earned = 25% x $1000 = $250

Page 24: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 21 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Plan

Actual

Earned

Page 25: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 22 2014 © Project Control Academy, All rights reserved

•  PV = Budgeted Cost of Work Planned

Page 26: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 23 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Plan

Actual

Earned

PV = $600

What is the PV on Week 3?

Page 27: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 24 2014 © Project Control Academy, All rights reserved

•  PV = Budgeted Cost of Work Planned •  AC = Actual Cost of Work Performed

Page 28: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 25 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Plan

Actual

Earned

PV = $600 AC = $500

What is the AC on Week 3?

Page 29: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 26 2014 © Project Control Academy, All rights reserved

•  PV = Budgeted Cost of Work Planned •  AC = Actual Cost of Work Performed •  EV = Budgeted Cost of Work Performed

Page 30: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 27 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Plan

Actual

Earned

PV = $600 AC = $500

EV = $250

What is the EV on Week 3?

Page 31: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 28 2014 © Project Control Academy, All rights reserved

Budget = $1000 PV = $600 AC = $500 EV = $250

$1000  

$600

PV AC

$500

EV $250

Page 32: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 29 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Plan

Actual

Page 33: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 30 2014 © Project Control Academy, All rights reserved

$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5$0

$200

$400

$600

$800

$1,000

$1,200

Week 1 Week 2 Week 3 Week 4 Week 5

Plan

Actual

Earned

PV = $600 AC = $500

EV = $250

Page 34: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 31 2014 © Project Control Academy, All rights reserved

 

  Tradi&onal  Management  provides  you  with…    How  much  money  and  ;me  a  par;cular  job  is  likely  to  require  prior  to  star;ng  and  once  started,  how  much  money  was  spent  at  any  given  ;me.  

  Earned  Value  Management  provides  you  with…    How  much  money  and  ;me  a  par;cular  job  is  likely  to  require  prior  to  star;ng  and  once  started,  how  much  money  was  spent  at  any  given  ;me.  

PLUS    Once  started,  what  work  has  been  accomplished  to  date  for  the  funds  expended  (what  you  got  for  what  you  spent)  

  Once  started,  what  the  total  job  will  cost  at  comple;on,  and  how  long  it  will  take  to  complete.  

 

Source: DOE Introduction to Earned Value Management by Booz Allen Hamilton

Page 35: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 32 2014 © Project Control Academy, All rights reserved

Planned  Value  (PV)      

  PV = Budgeted Cost of Work Planned   PV is a numeric reflection of the budgeted work that is scheduled to be performed, and it is the established baseline (PMB) against which the actual progress of the project is measured.   PV is the result of Cost & Schedule Baseline.   Cumulative PV is the sum of the approved budget for activities scheduled to be performed to date.   Period PV is the approved budget for activities scheduled to be performed during a given period.

Page 36: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 33 2014 © Project Control Academy, All rights reserved

Planned  Value  (PV)      

Keep some important points in mind regarding PV:   Project Total PV must always equal to the Project Budget at Completion (BAC) BAC= Sum of all budgets allocated to a project scope. BAC= PMB= Project Total PV   If Project Total PV # BAC, your EV calculations and analysis will be inaccurate.

Page 37: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 34 2014 © Project Control Academy, All rights reserved

Calcula;ng  Key  Components  of  EVM    (  PV,  EV,  AC)  

Page 38: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 35 2014 © Project Control Academy, All rights reserved

Planned  Value  (PV)      

You are working on a computer programming project, and part of the scope is for software design. The time frame for software design is 6 months and the budget for this scope is $12,000, resulting in a budget of $2000 per month.

Calculate the Cumulative and Period PV at the end

of 3rd month. What is the Project Total PV for the complete software design scope of the project?

Page 39: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 36 2014 © Project Control Academy, All rights reserved

Actual  Cost  (AC)      

  AC = Actual Cost of Work Performed   AC = Actual Expenditure, the cost incurred for executing the work.   Cumulative AC is the sum of the actual cost for activities performed to date.   Period AC is the actual costs of activities performed during a given period.

Page 40: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 37 2014 © Project Control Academy, All rights reserved

Actual  Cost  (AC)   Computer Programming Project- WBS 1.1.1 Software Design Calculate the Cumulative and Period ACs on Month 3rd.

Month  1   Month  2   Month  3   Month  4   Month  5   Month  6  

$2000   $2000    

$2000    

$2000    

$2000    

$2000    

$1200   $800   $1500  

Time Now

Page 41: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 38 2014 © Project Control Academy, All rights reserved

Earned  Value  (EV)      

EV = Budgeted Cost of Work Performed EV = Quantification of the “worth” of the work done to date. EV = Physical accomplishment of the project to date EV= Physical % Complete x Current Budget   Cumulative EV is the sum of the budget for the activities accomplished to date.   Period EV is the sum of the budget for the activities accomplished in a given period.

Page 42: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 39 2014 © Project Control Academy, All rights reserved

Earned  Value  (EV)   Computer Programming Project- WBS 1.1.1 Software Design Calculate the Cumulative and Period EV on Month 3 by assuming that the

physical % complete to date ( 3rd month) is 40% and the cum. actual progress in the previous month was 30%.

Month  1   Month  2   Month  3   Month  4   Month  5   Month  6  

$2000   $2000    

$2000    

$2000    

$2000    

$2000    

$1200   $800   $1500  

Time Now

PV

AC

Page 43: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 40 2014 © Project Control Academy, All rights reserved

Earned  Value  Key  Components  (PV,  AC,EV)    

 

At this point, you should have a good understanding of the three key Earned Value components:   Planned Value (PV) is the result of PMB ( cost & schedule baseline, discussed in previous modules)   Actual Cost (AC) is determined by the actual cost incurred on the project.   Earned Value (EV) tells you, in physical terms, what the project is accomplished.   Question: How do you determine the physical accomplishment in a project?

Page 44: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 41 2014 © Project Control Academy, All rights reserved

Record  Cost  Status  

Record/  Measure  EV                                              Key  Components                                          

(PV,  AC,  EV)  

Select  EV  Measurement  Method  

Page 45: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 42 2014 © Project Control Academy, All rights reserved

  Earned Value (EV) = Objective measuring the physical accomplishment of an activity.

( EV = Physical % x Budget )

Measure  EV                                              Key  Components                                          

(PV,  AC,  EV)  

Select  EV  Measurement  

Method  

Physical %?

100%

Page 46: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 43 2014 © Project Control Academy, All rights reserved

  Earned Value techniques should be selected based on the key attributes of the work:

- The Duration of the Effort - The tangibility of its products/ services

Measure  EV                                              Key  Components                                          

(PV,  AC,  EV)  

Select  EV  Measurement  

Method  

Page 47: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 44 2014 © Project Control Academy, All rights reserved

 Product  /  Service  

of  Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  Periods  

>2  Measurement  Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor;oned  Effort  Level  of  Effort  

Earned Value Measurement Techniques

Source: PMI Practice Standard for Earned Value Management

Page 48: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 45 2014 © Project Control Academy, All rights reserved

 Product  /  

Service  of  Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  

Periods  

>2  Measurement  

Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor;oned  Effort  Level  of  Effort  

Fixed Formula X% 100-X%

  X% of the work is credited as complete for the measurement period in which the work begins, regardless of how much work has actually been accomplished.

  The remaining (100-X%) is credited when the work is completed.

  Requires very detailed and short span work packages.

  Example: 25%/75% method for purchased material.

Page 49: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 46 2014 © Project Control Academy, All rights reserved

 Product  /  

Service  of  Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  

Periods  

>2  Measurement  

Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor;oned  Effort  Level  of  Effort  

Fixed Formula X% 100-X%

Important rule in using this method: •  Defined tasks not exceed one or

two maximum reporting periods, measured either weekly or monthly.

Page 50: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 47 2014 © Project Control Academy, All rights reserved

Fixed Formula- Exercise Calculate Earned Value for following tasks: ( EV= Budget x Physical%)

  Task 1 Budget: 12

  Task 2 Budget: 100

  Task 3 Budget: 55

  Task 4 Budget: 82

50% 50%

25% 75%

0% 100%

Cut-Off date

25% 75%

Page 51: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 48 2014 © Project Control Academy, All rights reserved

 Product  /  

Service  of  Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  

Periods  

>2  Measurement  

Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor;oned  Effort  Level  of  Effort  

Percent Complete X% 100%

  Estimate of the % of work completed during the reporting period.   Such estimates are made by individuals in charge of the a

given work package.   The Simplest and easiest method, but can be the most

subjective of the EV measurement techniques if there are no objective indicator to back it up.

  This method requires a sort of informal “check and balance” on the accuracy of the periodic estimates.

Page 52: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 49 2014 © Project Control Academy, All rights reserved

Percent Complete- Exercise X% 100%

  What is the physical % completion of this “Applied Project Controls Course” at this moment?!

Page 53: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 50 2014 © Project Control Academy, All rights reserved

 Product  /  

Service  of  Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  

Periods  

>2  Measurement  

Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor;oned  Effort  Level  of  Effort  

Weighted Milestone

  Divides the work to be completed

into segments, each ending with an observable milestone; it then assigns a value to the

achievement of each milestone.   More suitable for longer duration tasks having tangible

outcomes.   Once the work is underway, values should not be changed.   A preferred method used in performance measurement, but

also a most difficult method to initially plan.

Page 54: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 51 2014 © Project Control Academy, All rights reserved

Weighted Milestone- Example

P&IDs Gated Milestones   1- CAD Set-up 5%   2- Engineering related to P&IDs 25%   3- Initial Drafting 20%   4- Issue for In-House Review 10%   5- Issue for Customer Review 10%   6- Issue for Design Review/ HAZOP 15%   7- Issue for Design 15%

1

5% 25% 20% 10% 10% 15% 15%

2 3 4 5 6 7

100%

Page 55: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 52 2014 © Project Control Academy, All rights reserved

Weighted Milestone- Exercise

P&IDs Gated Milestones

  1- CAD Set-up 5%   2- Engineering related to P&IDs 25%   3- Initial Drafting 20%   4- Issue for In-House Review 10%   5- Issue for Customer Review 10%   6- Issue for Design Review/ HAZOP 15%   7- Issue for Design 15%

P&ID Issued for Customer Review. P&ID issued for HAZOP @ 50%. Calculate the Physical % Complete.

1

5% 25% 20% 10% 10% 15% 15%

2 3 4 5 6 7

Page 56: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 53 2014 © Project Control Academy, All rights reserved

 Product  /  

Service  of  Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  

Periods  

>2  Measurement  

Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor&oned  Effort  Level  of  Effort  

Apportioned Effort   If a task has a direct, supportive

relationship to another task that has its own EV, the value for the support task may be determined based on ( or apportioned to) the EV of the reference base activity.   When work is performed in the base task, it is assumed that

work will be performed in the apportioned task.   Examples of apportioned tasks include QA and inspection

activities.

Page 57: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 54 2014 © Project Control Academy, All rights reserved

Apportioned Effort   An apportioned effort PV is directly proportional to the

associated base effort’s budget and time phasing.   An apportioned effort EV is directly proportional to actual

amount of base work that is completed during the reporting period.

  An advantage of this technique is that it simplifies the earned value management of recurring support activities by defining standardized percentages for these tasks.

Page 58: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 55 2014 © Project Control Academy, All rights reserved

Apportioned Effort- Example QA  Control  Account  appor;oned  @  10%  of  produc;on  control  account  

Mar   Apr   May   Total  

Produc;on  Control  Account  PV   100   500   200   800  

QA  Control  Account  PV   10   50   20   80  

Produc;on  Control  Account  EV   250   400   150   800  

QA  Control  Account  EV   25   40   15   80  

Page 59: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 56 2014 © Project Control Academy, All rights reserved

Apportioned Effort- Example

Actual

Page 60: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 57 2014 © Project Control Academy, All rights reserved

 Product  /  

Service  of  Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  

Periods  

>2  Measurement  

Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor;oned  Effort  Level  of  Effort  

Level of Effort (LOE)   The project activities that do not

produce tangible outcomes and cannot be measured objectively, but are necessary to support a project uses the LOE method.   LOEs are more “time” sensitive than “performance” sensitive.   Examples of the LOE tasks are the tasks related to Project

Management Team, project controls, procurement, contract admin, security guards, cooks, helpdesks,…

  Whenever these functions are charged to the project, they normally start at the beginning of project and continue for the full term of the project.

Page 61: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 58 2014 © Project Control Academy, All rights reserved

Level of Effort (LOE)   LOE tasks have no schedule variance ( EV= PV) and can bias

the project data towards an on-schedule condition.   Although LOE tasks resemble indirect work on projects, the

performance measurement on LOE tasks has an impact on the overall project performance.

  LOE efforts generally have no measurable or deliverable outputs. So, LOE method should be used only when the task does not lend itself to a technique that actually measures physical work progress.

Page 62: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 59 2014 © Project Control Academy, All rights reserved

Level of Effort (LOE)-Example Planned Value for Project Coordination & Support: What is the Cum. EV in March?

Month   Jan   Feb   Mar   Apr   May   Jun   Jul   Aug  

PV   1000   1200   1000   900   1100   1500   1000   500  

Time Now

Page 63: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 60 2014 © Project Control Academy, All rights reserved

Execution of Project Controls

Page 64: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 61 2014 © Project Control Academy, All rights reserved

  The role of Project Controls in the execution stage of the project is to accurately and regularly record and measure the project progress against the frozen baseline.   Record Schedule Status   Record Cost Status (EV, AC)

  The purpose of schedule status recording/ updating is to timely track the changes to the schedule baseline.

Page 65: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 62 2014 © Project Control Academy, All rights reserved

  There are three key components to Cost Recording: Planned Value, Earned Value, and Actual Cost.   PV is the work scheduled or “what you plan to do”.   EV is the quantification of the “worth” of the work done to date or “what you physically achieved”.   AC is the cost incurred for executing work on a project or “what you have spent”.

Page 66: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 63 2014 © Project Control Academy, All rights reserved

Acronym   Variable   Defini&on   Meaning  

PV   Budgeted  Cost  of  Work  Scheduled  

Time  phased  es;mated  value  of  planned  work.  

Planning  Baseline-­‐  PMB  

EV   Budgeted  Cost  of  Work  Performed  

Time  phased  es;mated  value  of  completed  work  

Work  Accomplishment  Earned  Value  

AC   Actual  Cost  of  Work  Performed  

Time  phased  costs  incurred  for  completed  work  

Expenditures  Actuals  are  Actuals  

Page 67: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 64 2014 © Project Control Academy, All rights reserved

  Techniques for measuring work performed ( Physical % Progress) are the basis for performance measurement during project execution and control.   Earned Value techniques should be selected based on the key attributes of the work; duration & tangibility of end deliverables.

 Product  /  Service  of  

Work  

Dura&on  of  Work  Effort  

1-­‐2  Measurement  Periods  

>2  Measurement  Periods  

Tangible   Fixed  Formula   Weighted  Milestone  Percent  Complete  

Intangible   Appor;oned  Effort  Level  of  Effort  

Page 68: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 65 2014 © Project Control Academy, All rights reserved

EV Method Meaning Advantage Disadvantage

Fixed Formula

X% of the work is credited as complete for the measurement period in which the work begins, regardless of how much work has actually been accomplished. The remaining (100-X%) is credited when the work is completed.

For short term work packages Requires minimal effort to status

Defined tasks not exceed one or two maximum reporting periods. Not effective for longer term work packages

% Complete Estimate of the % of work completed during the reporting period.

The Simplest and easiest method. Based on the CAM's assessment of the work packages progress

The most subjective of the EV measurement techniques if there are no objective indicator to back it up. Requires a sort of informal “check and balance” on the accuracy of the periodic estimates

Weighted Milestone

Divides the work to be completed into segments, each ending with an observable milestone; it then assigns a value to the achievement of each milestone.

A preferred method used in performance measurement. Suitable for longer duration tasks having tangible outcomes.

One of the most difficult methods to initially plan.

Apportioned Effort

If a task has a direct, supportive relationship to another task that has its own EV, the value for the support task may be determined based on ( or apportioned to) the EV of the reference base activity.

Simplifies the earned value management of recurring support activities

Used only for tasks that have a direct, supportive relationship to another task.

Level of Effort (LOE)

The project activities that do not produce tangible outcomes and cannot be measured objectively, but are necessary to support a project uses the LOE method

Does not require statusing, and is appropriate for sustaining tasks such as Program Management.

LOE tasks have no schedule variance ( EV= PV) and can bias the project data towards an on-schedule condition. LOE method should be kept to a minimal number of work packages. LOE method should be used only when the task does not lend itself to a technique that actually measures physical work progress.

Page 69: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 66 2014 © Project Control Academy, All rights reserved

Record  /  Measure                              Cost  Status  

Record        Schedule  Status  

Project Controls Scope                  

Planning  Time  

Planning  Cost  

Planning  

Plan

Do

Checking  &  Measuring  Variances  

Measuring  Performance  Indices  

Check

Future  Analysis   Trend  Analysis  

Baseline  Analysis  

Change  Control  

Act

Page 70: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 67 2014 © Project Control Academy, All rights reserved

Project Controls

Execution of Project Control (Recording/ Measuring Cost and Schedule Status)

Planning & Development of Scope, Time, and Cost (Fundamental steps to Form Project Baseline)

Checking the Performance (Measuring & Monitoring Cost and Schedule Performance against Baseline) Cost & Schedule

Analysis & Taking Action (Analyzing Performance Results and Forecasting Project behaviour)

Page 71: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Page: 68 2014 © Project Control Academy, All rights reserved

Are  you  Ready  to  Move  on  to  Module  6,    

Checking  the  Performance?        

Page 72: $SSOLHG 3URMHFW &RQWUROV · Schedule Status at the end of Week 2: • Activity A started on time and is completed. • Activity B has not started yet. It is forecasted to start on

Copyrig ht © 20 12 Project Control A cadem y.A ll Rig hts Res erved. Do not du plicate or dis tribu te w ithou t perm is s ion.

Applied Project Controls TrainingMaintain Control, Boost Performance, and

Achieve Successin Your Projects

Your Unique Guide to …

The A pplied Project Controls training s eries equ ips you w ith fu ndam ental and practical tools to enhance you r com petency and perform ance in controlling and m anag ing you r projects . This cou rs e provides you a s tep-by-s tep proces s from planning to execu tion and control of project’s s chedu le and cos t in a s im ple yet effective m anner. Clos ely alig ned w ith the Project M anag em ent Ins titu te’s s tandards and g u idelines ,A pplied Project Controls training offers bas ic and advanced m ethods for k eeping you r projects in control. It provides you a clear u nders tanding of the Project Controls ’ concepts , tools , and techniqu es that can be applied to any project w ithin any indu s try.

TheThe A pplied Project Controls video training is com pos ed of 7 m odu les that are delivered as 12 online videos or DVDs :

- M odu le 1- Introdu ction to Project Controls - M odu le 2- Scope Planning - M odu le 3- Tim e Planning (Parts 1-3) - M odu le 4- Cos t Planning - M odu le 5- Execu tion of Project Controls (Parts 1-2) - M odu le 6- Check ing the Perform ance - M odu le 7- Cos t and Schedu le A nalys is (Parts 1-3)

J u s t w atch the videos , learn from the exam ples , do the exercis es , and follow the s ys tem . You can becom e the next expert in you r field. You can do this . The project m anag em ent w orld needs you .

Shohreh G horbani, PM P, is a s eas oned Project Control Profes s ional w ith years of hands -on experience on a w ide rang e of project m anag em ent technical areas in variou s indu s tries . She has a dem ons trated track record of s u cces s in execu ting earned valu e m anag em ent, cos t control, planning /s chedu ling , ris k m anag em ent, and qu ality m anag em ent. She has m anag ed larg e nu m ber of s u cces s fu l oil and g as and m anu factu ring projects of varying s ize and com plexity in Canada and overs eas .

Prior to es tablis hing Project Control A cadem y, s he developed s eries of training videos for Project Control departm ent of an international com pany. Her training videos w ere w ell received and s hared g lobally w ithin the com pany. Finding her pas s ion in Project Controls , s he continu ed to s hare her k now ledg e throu g h teaching at edu cational ins titu tes and corporations . She fou nded Project Control A cadem y to fu rther s hare her k now ledg e and s erve m ore people.

Shohreh is a profes s ional m em ber of Project M anag em ent Ins titu te (PM I) and A m erican A s s ociation of Cos t Eng ineers (A A CE). She holds M as ter of Science in Indu s trial Eng ineering . M eet her at w wM eet her at w w w .ProjectControlA cadem y.com

Meet Shohreh Ghorbani, Founder of Project Control Academy