spacecraft and payload · cruise 2 overview constraints: 1. timeline not to scale. 2. precesses...

7
PI’s OPAG Overview: New Horizons ! 0289 Days into Flight ! 0112 Days to Jupiter ! 3170 Days to Pluto 19 Jan 2006 ROUTE OF FLIGHT Pluto-Charon July 2015 KBOs 2016-2020 Jupiter System March 2007 The First Reconnaissance The First Reconnaissance Of The Solar System Of The Solar System’ s s “Third Zone Third Zone” Launch Jan 2006 SPACECRAFT AND SCIENCE TEAM SPACECRAFT AND PAYLOAD LORRI PEPSSI SWAP RALPH ALICE Student Dust Counter Remote Sensing: " RALPH VIS/IR Imaging & Imaging spectroscopy " ALICE UV imaging spectroscopy " LORRI High-Resolution Imager " REX Radio Science & Radiometry In Situ: " SWAP Plasma Spectrometer " PEPSSI Energetic Particle Spectrometer " SDC Student Dust Impact REX

Upload: others

Post on 30-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SPACECRAFT AND PAYLOAD · CRUISE 2 OVERVIEW Constraints: 1. Timeline not to scale. 2. Precesses outside of A/C to maintain 10bps MGA to 70m . 3. OpNavs per direction of NAV 4. Precess

PI’s OPAG Overview: New Horizons

! 0289 Days into Flight

! 0112 Days to Jupiter

! 3170 Days to Pluto

19 Jan 2006

ROUTE OF FLIGHT

Pluto-CharonJuly 2015

KBOs2016-2020

Jupiter SystemMarch 2007

The First ReconnaissanceThe First Reconnaissance

Of The Solar SystemOf The Solar System’’s s ““Third ZoneThird Zone””

LaunchJan 2006

SPACECRAFT AND SCIENCETEAM

SPACECRAFTAND PAYLOAD

LORRI

PEPSSI

SWAP

RALPH

ALICE

Student DustCounter

Remote Sensing:

" RALPH VIS/IR Imaging &

Imaging spectroscopy

" ALICE UV imaging spectroscopy

" LORRI High-Resolution Imager

" REX Radio Science & Radiometry

In Situ:

" SWAP Plasma Spectrometer

" PEPSSI Energetic Particle

Spectrometer

" SDC Student Dust Impact

Counter

REX

Page 2: SPACECRAFT AND PAYLOAD · CRUISE 2 OVERVIEW Constraints: 1. Timeline not to scale. 2. Precesses outside of A/C to maintain 10bps MGA to 70m . 3. OpNavs per direction of NAV 4. Precess

PS-Hibernation

PS-Normal

PS-TCM

AS-Normal

AS-TCM

AS-EA

AS-SA

3A-Normal

3A-

Encounter

3A-TCM

Notes:

1. Timeline not to scale.

2. Activities allowed in Nav. block

that do not change attitude of

Observatory.

3. +Y to Sun <100º, OK. Need to

evaluate thermal environment if +Y

to Sun >100º at <2AU.

4. AU is Obs. distance from Earth

L

L+60

(~0.4 AU)

Separation ~L+40 min

Transmitter on ~L+43 min

1st contact ~ L+47 min aft LGA

TCM 1a L+8

TCM 1b L+10

Precess HGA to Earth

Initial Instrument

Activation & c/o (L+4wks)

G&C c/o (L+1wks)

Continuous 16h/d Cont. 5x16h/wk 5x8hrs/wk

L to L+7

PS-Normal

G&C on (IMU) – discern spin direction

Burp & Prime Propulsion lines

OL spin down 72 to 15 rpm

AS-Normal

CL spin down to 5rpm

Subsystem checkout

Autonomous Seq &

Redundant Unit c/o

(3wks)

G&C Saturation

test (4hrs)

TCM 2

L+20(~0.15AU)

Navigation 3A calibration

(1wk)

G&C c/o (L+3wks)

EARLY OPERATIONS CRUISE 1 OPS

Notes:

1. Timeline not to scale.

2. AU is Obs. distance from Earth

L+60

(9wks) Instrument Calibration,

Commissioning, MVIC OpNav(L+165),

Interference test

5x8 2x8 5x8 2x8 3x8 2,7,9,5,3,3,3x8h/wk 2x8h/wk 3x8h/wk 2x8h/wk 7x8 3x8

Solar

Conjunction

DOY 323-331

L+365

(5wks) Instrument

Calibration &

Commissioning 3A

90 120 150 180 210 240 270 300 330

Instr. Comm.

(4wks)

PS-Hibernation

PS-Normal

PS-TCM

AS-Normal

AS-TCM

AS-EA

AS-SA

3A-Normal

3A-

Encounter

3A-TCM

L+75 CDH 3.5 load

L+305 (DOY286)

Autonomy Rel. 14

L+211 (DOY 230)

CDH 4.1 load

L+253 (DOY 272)

GC 4.0 load

L+ 64 Autonomy Rel. 12d

L+ 106

Autonomy Rel. 12e

3A-Enc

mode c/o

Autonomy Rel. 13

(DOY 188)

Today

Instrument

Calibration &

Commissioning

Spin Mode

Instrument

Calibration &

Commissioning

Spin Mode

SPACECRAFTCHECKOUT STATUS

Still

working

Power

Switching

Commands

Power

Switching

Commands

Th

rus

ter

Va

lve

Dri

ve

, C

at.

Be

d H

ea

ters

1PPS

Cross

Strap #1

1PPS

Cross

Strap #2

BP

A

BP

A

BP

A

BP

A

External

Shunts

Internal

Shunts

Cat. Bed Temp

Sensors

On All

REAs

RS

-422

INS

TR

UM

EN

TS

G&

C P

roc

es

so

r

C&

DH

Pro

ce

ss

or

SS

R

Do

wn

lin

k T

x

G&

C P

roc

es

so

r

C&

DH

Pro

ce

ss

or

Do

wn

lin

k T

x

SRU

PDU

RTG

Obs. Power Bus (30V +/- 1V)

Star

Tracker

Star

Tracker

POWER

GUIDANCE

& CONTROL

Component

Power

I2C

Mil Std 1553 Bus

LNA

LO

RR

I

PE

PS

SI

AL

ICE

RA

LP

H

RS

- 422

LNA

Aft

LGA

Fwd

LGA

Switch

Network

RF COMMUNICATIONS

USO

Dip

lex

er

Co

mm

an

d

De

co

de

r

TWTA

Ins

tru

me

nt

Inte

rfa

ce

Ins

tru

me

nt

Inte

rfa

ce

C&DH (PCI Backplane)

SW

AP

Star

Tracker

Star

Tracker

SS

R

C&DH (PCI Backplane)

Internal

Heaters

THERMAL

CONTROL

INTEGRATED ELECTRONICS MODULE #1

INTEGRATED ELECTRONICS MODULE #2

Shunt Regulator

Majo

rity

Vo

ter

& T

LM

LV

DS

RS

- 422

LV

DS

RS

- 422

RS

- 422

LV

DS

HGA

RIO

(7)

RIO

(7)

RIO

(7)

RIO

(7)

SD

C MGA

Up

lin

k R

xC

CD

Up

lin

k R

xC

CD

P

A1

A2

A3

Latch

Valves

0.8 N ACS

Thrusters

4.4 N !V

Thrusters

Filter

Fill/Drain

Fill/Vent

GN2

N2H4

P

Orifice

PROPULSION

Pressure

Transducer

C4 D4

B1

B2

B3

T

C1

C2

C3

D1

D2

D3

F1 F2

Hybrid

USO

EPC

EPC

Po

we

r

Sw

itc

hin

g

Cu

rre

nt

Lim

it

(8 S

lic

es

)

Ca

pa

cit

or

Ba

nk

(33

mF

)

Dri

vers

(15

)

Au

xilia

ry

LV

S

TL

M

Auxiliary

Interfaces

RE

X,

Re

g.

Ra

ng

eR

EX

, R

eg

. R

an

ge

I2C

1PPS

Cross

Strap #2

TWTA

1PPS

Cross

Strap #1

DC/DC Converter, Uplink/DownlinkDC/DC Converter, IEM Digital

DC/DC Converter, Uplink/DownlinkDC/DC Converter, IEM Digital

Fine Sun

Sensors

Co

ntr

ol

(3)

PDB

(2)

IMU

IMU

Sun Pulse

Sensors

15

53

CM

D/T

LM

STRUCTURE

HARNESS

FLIGHT SOFTWARE

C&DH 3.5

G&C 3.3.1

Boot 3.8

Autonomy 13

COMMAND & DATA HANDLING

Legend

Checked Out OK

Not Checked Out

Checked Out With Issue

Checkout Not Planned

Modes and States

AS-N

PS-N

PS-H

3A-N

3A-E

AS-EA

AS-SAAS-T

PS-T

3A-T

EARLY OPS MILESTONES

Completed

Eliminated

New

Begin JupiterEncounter Planning

NHOPS Upgrade

InstrumentCommissioning

Upload G&CFSWV4.0

Upload C&DH FSWV3.5 & 4.1

Autonomy Loads

G&C Check-out

TCMs

Launch

Dec

NovOct

Sep

AugJulJun

MayApr

Mar

FebJanTasks

1 2 34

Reviews

12d12c 13

RR PDR

12e

Delayed until January 2008

PR

14

Page 3: SPACECRAFT AND PAYLOAD · CRUISE 2 OVERVIEW Constraints: 1. Timeline not to scale. 2. Precesses outside of A/C to maintain 10bps MGA to 70m . 3. OpNavs per direction of NAV 4. Precess

SUBSYSTEM STATUSTRACKER

Jun JUL Aug Sep Oct Nov

Mission Ops G G G Y Y Y

Systems Eng G G G G G G

Autonomy G G G G G G

RF G G G G G G

Thermal G G G G G G

Propulsion G G G G G G

C&DH Y G G G G G

G&C Y Y G G G G

Navigation G G G G G G

Mission Des G G G G G G

Ground Sys G G G G G G

Alice G G G G G G

Ralph G G Y Y G G

REX G G G G G G

LORRI G G G Y G G

SWAP G G G G G G

PEPSSI G G G G G G

SDC G G G G G G

PA G G G G G G

SPACECRAFT ISSUES

! Post launch change in spin

axis of 0.256 deg, likely due to

fuel shape change: Some

impact on downlink rates,

spinning science.

! Two onboard thrusters have

high valve counts: Taking

action to mitigate their usage.

REMAINING CHECKOUTS

" Instruments:

" C&DH Side B interfaces

" REX Side B

" Alice Solar Occultation Channel

" Payload EMI/EMC Tests

" RF: Regenerative Ranging.

" Propulsion: F1/F2 Thrusters, Two TCM Modes.

" Internal Shunts: Planned to be checked out late in

the mission when RTG power <200W.

PAYLOAD STATUS 1! All instruments functional; commissioning >87% complete.

! Two minor anomalies exist, but both are non-critical.

! 6 of 7 mechanisms now open; Alice-SOCC opening spring ‘07.

! Science in Cruise 1: Asteroid Images, SDC/SWAP/PEPSSICruise Science, Initial Uranus & Neptune Phase CurveImaging.

Co

un

ts/b

in (

log

)

1

10

ReferenceSpectrum

LEISA

Rel

ati

ve

Sig

nal

Wavelength (microns)

Page 4: SPACECRAFT AND PAYLOAD · CRUISE 2 OVERVIEW Constraints: 1. Timeline not to scale. 2. Precesses outside of A/C to maintain 10bps MGA to 70m . 3. OpNavs per direction of NAV 4. Precess

PAYLOAD STATUS 2

Spacecraft NoisesExcellentV-SDC

ExcellentSWAP

Misalignment Error:No Effect At Pluto

ExcellentPEPSSI

NoneExcellentLORRI

NoneExcellentREX

NoneExcellentAlice

LEISA-Only Light Leak:Small, No Effect At Pluto

Very GoodRalph

IssuesStatusInstrument

19 Oct 2006:TCM-4 CANCELLED

MISSION STATUS:“PINCH ME, I’M DREAMING”

! Spacecraft and Payload Are Performing Well.

! Fuel and Power Situation Also Look Good.

! Payload Commissioning ~4/5 Complete, Results: Good.

! Trajectory: Good, TCM’s Not Expected on Jupiter Approach.

! High Ops Team Workload Continues.

! Increase in Phase E Budget Has Lowered Risk: Very Good.

Page 5: SPACECRAFT AND PAYLOAD · CRUISE 2 OVERVIEW Constraints: 1. Timeline not to scale. 2. Precesses outside of A/C to maintain 10bps MGA to 70m . 3. OpNavs per direction of NAV 4. Precess

JUPITER FLYBYOBJECTIVES

! Achieve the Pluto JGA

! Protect the spacecraft and instruments

! Serve as a flyby/encounter pathfinder

! Do good Jupiter science

JUPITER FLYBY

Jupiter science will include studies of Jovianmeteorology, satellite geology and composition,Auroral phenomena, and magnetospheric physics.

32 RJRange

28 Feb 2007C/A Date

BASELINE JUPITER OPS

Constraints:

1. Timeline not to scale.

2. Science Ops allowed

outside of DSN contacts.

3. Activities allowed inside

Nav. time that do not change

attitude of Observatory.

PS-Hibernation

PS-Normal

PS-TCM

AS-Normal

AS-TCM

AS-EA

AS-SA

3A-Normal

3A-

Encounter

3A-TCM

J+120

End

Jupiter

Phase

Cruise 2

Preparations

Final Data

Retrieval

TCM 5

J-20

5x8h/wk 8h/d Continuous 8h/d 5x 8h/wk 8h/d 3x8h/wk

J-60

J C/ATCM 6

J-5 TCM 7

J+15

Final Jupiter

Rehearsal (2d)

Instr. Obs.-

Particle

J-30

Io, Ganymede, Europa, Callisto,

Elara (Obs, Map, Terminator,

Composition, Occultations, Eclipse,

UV Spectra)

Calibration REX (1)

Jupiter Ring Search for satellites

Flat Field Obs

Little Red Spot Obs

Ring ansa

Particle Instr.

TCM 8

J+84

OpNav 1 per week (MVIC & LORRI) (min 3?)

J-3

J+3

Nav. Track

(7d)

Nav. Track

(7d)

Nav. Track

(7d)

Nav. Track (1wk)

Data RetrievalMOps

Tests (3d)

3A-E mode test

LORRI global maps(3)

Calibration obs.(3)

Global view of satellites(1)

Alice aurorae & Io torus

Particle instr.

Nav. Delta Dor 2x/wk

(4wks starting J-6wks)

Alice SOC Door Open 4.5AU

SSR

p/b

J-14

Observatory Phase Approach Phase Near Phase

Calibration Obs (4)

Calibration obs.(3)

Global view of satellites(1)

Alice aurorae & Io torus

Particle instr.

Annual C/O #0

Pt 1

Annual C/O #0

Pt 2

PRELIM JDAP PLANS

"2-Year JDAP effort to be funded by

NASA ROSES-07.

"All NH-Jupiter Level-2 data in PDS by

Nov 2007.

"Space Sci. Revs. Article preprints to be

posted early-2007 at:

www.boulder.swri.edu/pkb

"Approx >$1M/year.

"Proposals Due: 1 Feb 2008 (Earlier?).

"Selection: Mid-2008.

Page 6: SPACECRAFT AND PAYLOAD · CRUISE 2 OVERVIEW Constraints: 1. Timeline not to scale. 2. Precesses outside of A/C to maintain 10bps MGA to 70m . 3. OpNavs per direction of NAV 4. Precess

CRUISE 2 OVERVIEW

Constraints:

1. Timeline not to scale.

2. Precesses outside of A/C to

maintain 10bps MGA to 70m .

3. OpNavs per direction of NAV

4. Precess at end of each A/C

5. TCMs per direction of MD/NAV

PS-Hibernation

PS-Normal

PS-TCM

AS-Normal

AS-TCM

AS-EA

AS-SA

3A-Normal

3A-

Encounter

3A-TCM

2014

(6/14-8/14)

Annual c/o#8

TCM 15

Pluto Rehearsal #2

Wkly Beacon, monthly Tel. contact in PS-H. 2-3x8h/wk for Annual c/os 7x 8h/d for Precess TCMs in 3A-TCM or AS-TCM

P-200

2008

(9/08-11/08)

Annual c/o #2

TCM 9 (P-7y)

J+120

Precess

11/20/07

Precess

12/27/07

Precess

12/18/08

2007

(9/07-11/07)

Annual c/o #1

2010

(9/10-11/10)

Annual c/o #4

TCM 11 (P-5y)

2009

(9/09-11/09)

Annual c/o #3

TCM 10

2011

(9/11-11/11)

Annual c/o #5

TCM 12

2012

(6/12-8/12)

Annual c/o #6

TCM 13 (P-3y)

Pluto Rehearsal #1

2013

(6/13-8/13)

Annual c/o #7

TCM 14

Precess

06/11/10

Precess

11/25/11

Precess

12/11/12

Precess

12/10/10

Precess

10/13/13

OpNavs last annual c/o: 1 every 12hrs for 7 days

Precess

05/29/08

Precess

06/09/09

Precess

12/13/09

Precess

06/15/11

Precess

12/20/13

P-1yr

Phase in

PS-H

AND THEN IN 2015:WHAT WE CAME FOR

! Mar-May: Obs Phase

! Closest Approach: 14 July

! Downlink: Aug-Dec

PI’s TOP CONCERNS

! Ops Team Staffing is Thin, Ops Pace is High, Threats

to Jupiter Science Have Resulted.

! Longevity & Personnel Retention Issues Continue.

! Funds Adequate, But Leave Little Room for Mistakes.

RECAP! New Horizons Is Doing Well.

! Hard Work and Vigilance Remain Required.

! Jupiter A’Hoy!

Page 7: SPACECRAFT AND PAYLOAD · CRUISE 2 OVERVIEW Constraints: 1. Timeline not to scale. 2. Precesses outside of A/C to maintain 10bps MGA to 70m . 3. OpNavs per direction of NAV 4. Precess

ONWARD! Risk Matrix

Lik

elih

ood (

Pf)

117 Thruster Use (C4,L4)116 MOps Process (C4,L2)109 NHOPS failure (C3,L2)108 Knowledge retention

during hibernation(C3,L3)

109 110 Hibernation (C3,L1)103 Unplanned Ground

System upgrade(C2,L2) ($)

83 Software designdocumentation (C2,L2)

107 RF degradation (C2,L1)105 Unplanned C&DH build

(C2,L1) ($)106 Unplanned Autonomy

build (C2,L1) ($)104 Unplanned G&C build

(C2,L1) ($)Consequence (Cf)

1

2

3

4

5

54321

107-RF105-CDH106-Auto

104-GC

103-GS83-SDD

110-Hib

109-

NHOPS

108-Know

116 – MOps

117 –Thruster