solstice ˜ sand lake...extending south from the sand lake station the proposed transmission line...

2
The components of the proposed Solstice - Sand Lake Transmission Line Project include: • Expanding the existing Solstice Station to accommodate 345-kV transmission equipment • Building approximately 40 miles of double-circuit 345-kV transmission line • Approximately 20 miles to be built by AEP Texas, extending north from the Solstice Station • Approximately 20 miles to be built by Oncor, extending south from the Sand Lake Station The proposed transmission line will begin at the AEP Texas Solstice Station, just west of Fort Stockton, and end at the Sand Lake Station, located north of Pecos. The Permian Basin is the most active shale oil producing region in the United States and the Solstice - Sand Lake project is necessary to support the related work in the area. ERCOT, the regional transmission organization responsible for overseeing the adequate supply of electricity for 80 percent of Texas, designated this project as critical to the continued electric reliability in the region. This transmission line project will directly support the area’s economic development and ensure reliable electric service to commercial and residential customers. AEP Texas and Oncor will submit a joint application for a Certificate of Convenience and Necessity (CCN) in Fall 2018. The Public Utility Commission of Texas (PUCT) will then determine a final line route. Because of the critical designation by ERCOT, the PUCT is expected to provide a decision by early Summer 2019. WHAT/WHERE WHY WHEN SOLSTICE SAND LAKE TRANSMISSION LINE PROJECT AEP Texas and Oncor plan to address the need for a more reliable power grid for future growth and economic development in west Texas. Following recent electrical studies, the Electric Reliability Council of Texas (ERCOT) designated the project as critical. The new 345-kilovolt (kV) transmission line will provide west Texans and commercial energy developers with more reliable electric service. PROJECT SCHEDULE SITING STUDY & ROUTE LINK DEVELOPMENT Spring 2018 PROJECT ANNOUNCEMENT & OPEN HOUSE Summer 2018 ROUTE LINK & PUBLIC INPUT REVIEW BEGINS Early Fall 2018 ROW COMMUNICATIONS & EASEMENT OPTION DISCUSSIONS BEGIN Fall 2018 SUBMIT JOINT CNN APPLICATION FOR THE PUCT* Fall 2018 RESPONSE ANTICIPATED FROM PUCT*; FINAL ROUTE DETERMINATION & ANNOUNCEMENT Early Summer 2019 EASEMENT ACQUISITION BEGINS Summer 2019 PRE-CONSTRUCTION ACTIVITIES BEGINS (I.E. GATES & CULVERT INSTALLATION, SURVEY) Fall 2019 ROW CLEARING & CONSTRUCTION BEGINS Late 2019 FACILITIES PLACE IN-SERVICE Late 2020 *Timeline subject to change. *Timeline subject to change. *PUCT: Public Utility Commission of Texas *PUCT: Public Utility Commission of Texas *ROW: Right-of-Way *ROW: Right-of-Way 2018 2020 2019 2021 AEP Texas provides electric service to customers across a nearly 100,000 square-mile service territory. The commitment to provide customers with reliable electric service drives AEP Texas to join efforts with LCRA Transmission Services Corporation and Oncor to invest more than $150 million to bolster the electric transmission grid in west Texas. Find out more about the West Texas Energy Connection at www.AEPTexas.com/WTEC. WEST TEXAS ENERGY CONNECTION

Upload: others

Post on 03-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SOLSTICE ˜ SAND LAKE...extending south from the Sand Lake Station The proposed transmission line will begin at the AEP Texas Solstice Station, just west of Fort Stockton, and end

The components of the proposed Solstice -

Sand Lake Transmission Line Project include:

• Expanding the existing Solstice Station to

accommodate 345-kV transmission equipment

• Building approximately 40 miles of

double-circuit 345-kV transmission line

• Approximately 20 miles to be built by AEP

Texas, extending north from the Solstice

Station

• Approximately 20 miles to be built by Oncor,

extending south from the Sand Lake Station

The proposed transmission line will begin at

the AEP Texas Solstice Station, just west of

Fort Stockton, and end at the Sand Lake

Station, located north of Pecos.

The Permian Basin is the most active shale oil

producing region in the United States and the

Solstice - Sand Lake project is necessary to

support the related work in the area.

ERCOT, the regional transmission organization

responsible for overseeing the adequate supply

of electricity for 80 percent of Texas, designated

this project as critical to the continued electric

reliability in the region.

This transmission line project will directly

support the area’s economic development and

ensure reliable electric service to commercial

and residential customers.

AEP Texas and Oncor will submit a joint

application for a Certificate of Convenience and

Necessity (CCN) in Fall 2018. The Public Utility

Commission of Texas (PUCT) will then

determine a final line

route. Because of the

critical designation by

ERCOT, the PUCT

is expected to

provide a decision by

early Summer 2019.

WHAT/WHERE WHY WHEN

SOLSTICE SAND LAKETRANSMISSION LINE PROJECT

AEP Texas and Oncor plan to address the need for a more reliable

power grid for future growth and economic development in west

Texas. Following recent electrical studies, the Electric Reliability

Council of Texas (ERCOT) designated the project as critical. The new

345-kilovolt (kV) transmission line will provide west Texans and

commercial energy developers with more reliable electric service.

PROJECT SCHEDULE

SITING STUDY & ROUTE LINK DEVELOPMENTSpring 2018PROJECT ANNOUNCEMENT & OPEN HOUSESummer 2018ROUTE LINK & PUBLIC INPUT REVIEW BEGINSEarly Fall 2018ROW COMMUNICATIONS & EASEMENT OPTION DISCUSSIONS BEGINFall 2018SUBMIT JOINT CNN APPLICATION FOR THE PUCT*Fall 2018RESPONSE ANTICIPATED FROM PUCT*; FINAL ROUTE DETERMINATION & ANNOUNCEMENTEarly Summer 2019EASEMENT ACQUISITION BEGINSSummer 2019PRE-CONSTRUCTION ACTIVITIES BEGINS (I.E. GATES & CULVERT INSTALLATION, SURVEY)Fall 2019ROW CLEARING & CONSTRUCTION BEGINSLate 2019FACILITIES PLACE IN-SERVICELate 2020

*Timeline subject to change.*Timeline subject to change.*PUCT: Public Utility Commission of Texas*PUCT: Public Utility Commission of Texas*ROW: Right-of-Way*ROW: Right-of-Way

2018 20202019 2021

AEP Texas provides electric service to customers across a nearly

100,000 square-mile service territory. The commitment to provide

customers with reliable electric service drives AEP Texas to join efforts

with LCRA Transmission Services Corporation and Oncor to invest

more than $150 million to bolster the electric transmission grid in west

Texas. Find out more about the West Texas Energy Connection at

www.AEPTexas.com/WTEC.

WEST TEXAS ENERGY CONNECTION

Page 2: SOLSTICE ˜ SAND LAKE...extending south from the Sand Lake Station The proposed transmission line will begin at the AEP Texas Solstice Station, just west of Fort Stockton, and end

WHAT ARE ROUTE LINKS?

The route links are preliminary line segments

developed following a field review and initial

review of environmental and social

constraints. The input gathered from the

presentation of these route links at the open

house provides a comprehensive review for

the PUCT in the CCN application. Not all route

links will be constructed. Rather, one route

will be determined by the PUCT.

285

10

20

WARD COUNTYWARD COUNTY

PECOS

COUNTY

PECOS

COUNTY

PECOSPECOS

SOLSTICESTATION

SAND LAKESTATION

REEVE

S COUNTY

REEVE

S COUNTY

AEP TEXAS VALUES YOUR INPUT ABOUT THIS PROJECT. PLEASE SEND COMMENTS AND QUESTIONS TO:

11/5/201811/5/2018

SOLSTICE SAND LAKE TRANSMISSION LINE PROJECT

ROUTE LINKS N

*Exact structure, height and right-of-wayrequirements may vary

Structure Type: LatticeStructure Height: Approximately 160 - 180 feetDistance between Structures: Approximately 1,150 feetRight-of-Way Width: Approximately 150 feet

TYPICAL STRUCTURES

AEP TEXAS VALUES YOUR INPUT ABOUT THIS PROJECT. PLEASE SEND COMMENTS AND QUESTIONS TO:

STATION TO BE EXPANDED EXISTING STATION

JULIET CAPEHEARTAEP Project Outreach [email protected]/Solstice-SandLake