Solar Probe Plus A NASA Mission to Touch the Sun

16-19 March 2015

Instrument Suite Name

Presenter's Name

Page 2: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

2Solar Probe Plus Mission CDR

Instrument/Suite NameScience Overview

1 page Introduce instrument and science contribution to the mission

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 3: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

3Solar Probe Plus Mission CDR

Instrument/Suite Name Team

1 page Organization chart of the instrument/suite team members

Include team member roles Include any key partners, subcontractors or major suppliers If appropriate, list suite chart and then chart for each team in each

team section

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 4: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

4Solar Probe Plus Mission CDR

Instrument/Suite Name Instrument Overview

1 page General description of the instrument to the level of the major

subsystems. Block diagram of the total instrument Serves as an introduction to the detailed presentations to follow

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 5: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

5Solar Probe Plus Mission CDR

Instrument/Suite NameTechnical Changes since PDR

1 page Give each change (recommend table below).

Give reason for change and provide impact, as appropriate, on resources of mass, power, size, telemetry, cost and schedule.

Include any science requirement changes or add statement at bottom that there were no science requirement changes.

Change since PDR Reason for Change Impact on Resources

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 6: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

6Solar Probe Plus Mission CDR

Instrument/Suite Name Summary of Engineering Design

5 pages Design description

Electrical and thermal instrument and components performance requirements Software architecture and design Mechanical design and analyses

Descriptions of any engineering or technology developments Summarize resource requirements

Table of mass and power for the components, including maturity of the estimates (EM measurement, Pro/E estimate, etc)

Commanding and housekeeping telemetry requirements Power services required Margins Other

Summarize drawing status (with definition of that status) Instrument Performance

Describe any known shortcomings in instrument performance relative to known science requirements

Identify any Long-Lead Time procurements

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 7: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

7Solar Probe Plus Mission CDR

Instrument/Suite Name CDR Summary

1 page Summarize I-CDR results

Review board membership, dates Action item summary Liens (if any)

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 8: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

8Solar Probe Plus Mission CDR

Instrument/Suite Name Engineering Model

2-3 pages List items completed since I-CDR

Link any new progress to action items where possible Include any peer reviews help between I-CDR and Mission CDR

If Lien at CDR was established and work not completed, address detailed schedule to complete lien

Fidelity of EM design (differences to FM) EM Test plan EM Test results Remaining work to FM build (example: remaining testing, drawing

updates)

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 9: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

9Solar Probe Plus Mission CDR

Instrument/Suite Name Verification and Validation Plans

3-4 pages Describe the process for verifying all instrument interfaces

(hardware & software), resources, form factor, performance and operations, environmental worthiness, and science performance requirements

List documentation (V&V plans, TE-001, requirements verification matrix)

Show a portion of your V&V matrix

Explain how tools are used (DOORS, etc) Walkthrough an example flow from requirement to verification

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 10: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

10Solar Probe Plus Mission CDR

Instrument/Suite Name Assembly, I&T Description

3-4 pages Assembly, I&T description, including

Flow chart(s) showing plans for the assembly, integration, functional and environmental testing (EMI, sniff, vibration, thermal balance, thermal vacuum, etc.), and calibration

Major milestones in the I&T flow with dates Description of any cleanliness requirements imposed on the

mission by the instrument as well as any special facilities needed Instrument alignment requirements and plans for verification of

alignment Purge requirements and plans for maintaining purge Expected number of operating hours on the instrument at launch Identify any special facilities Discuss any risks including mitigation plans Test-as-you-fly exceptions (i.e., what does not get tested)

Address Refurbishment plan if applicable16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 11: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

11Solar Probe Plus Mission CDR

Instrument/Suite Name Calibration

2 pages Detailed discussion of plans for instrument calibration

facilities planned for calibration range of parameters over which the instrument will be calibrated any shortcomings to the calibration that bring into question the

ability of the instrument to meet its mission science requirements

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 12: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

12Solar Probe Plus Mission CDR

Instrument/Suite Name Systems Assurance

1-2 pages Describe Performance Assurance Matrix Status

Identify any exceptions and status of exceptions

Identify any submitted waiver requests and status of approval (could be in back-up)

Identify any expected waivers that will be submitted (could be in back-up) System Safety

Discuss status of inputs to the Missile System Prelaunch Safety Package (MSPSP)

Identify any safety hazards along with methods for controlling them

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 13: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

13Solar Probe Plus Mission CDR

Instrument/Suite Name Science Operations Center

1 page Top-level Science Operations Center description including:

SOC/SDC driving requirements SOC/SDC design description SOC/SDC operating approach

Changes since PDR Review date for the SOC CDR

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 14: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

14Solar Probe Plus Mission CDR

Instrument/Suite Name Flight Operations Description

2 pages Status of Command and Telemetry definitions Describe the flight operations including

key elements of the instrument ground system that allows the operation of the instrument

command definitions and critical housekeeping telemetry definitions commanding path and telemetry data concept of operations for command and data handling of your

instrument during the commissioning phase of the mission as well as normal operations shall be presented.

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 15: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

15Solar Probe Plus Mission CDR

Instrument/Suite Name Risk Status

1 page Describe risk status, including

5x5 risk matrix Top 10 summary stop light chart showing instrument risks,

consequences and likelihood

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Page 16: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

16Solar Probe Plus Mission CDR

Instrument/Suite Name Development Status

1 page Describe development status, including

Project schedule showing critical path, schedule reserves and margins

List of threats to the schedule and schedule risk mitigation plans Trends in the schedule performance of the team such as the gain or

loss of float along the critical path

16 - 19 March 2015

General note to teams: The # of slides per topics may vary per team and these can be adjusted as necessary

Include a take-away statement that describes the Instrument Suite’s readiness to move onto flight build. Example:

“Instrument Name is ready to move to flight build”

Page 17: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

17Solar Probe Plus Mission CDR

Instrument/Suite Name

16 - 19 March 2015

Backup

Page 18: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

18Solar Probe Plus Mission CDR

Instrument/Suite NamePhase C Peer Reviews

Review # A/I # Open # Close # Concurred

I-PDR

Peer Review A

Peer Review B

I-CDR

16 - 19 March 2015

Page 19: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

19Solar Probe Plus Mission CDR

Instrument/Suite Name Summary of Documentation Status

1 page Give a list of your documents and their release status

Include requirements docs Specs Limited life item list Other matrix required documents CDRL status

16 - 19 March 2015

Page 20: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

20Solar Probe Plus Mission CDR

Instrument/Suite Name Parts and Materials Status

Summarize MIL and PIL approval status and procurement status

16 - 19 March 2015

Page 21: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

21Solar Probe Plus Mission CDR

Instrument/Suite Name Red and Green Tag Items

List red and green tag items

16 - 19 March 2015

Page 22: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name

22Solar Probe Plus Mission CDR

Instrument/Suite Name GSE

1 page - top-level summary only GSE design description, including

EGSE and MGSE requirements and implementation associated with the GSE

EGSE software including requirements, design and verification of EGSE software

Instrument purge equipment Instrument shipping container Slings or other special fixtures needed to mount and align the

instrument

16 - 19 March 2015

Page 23: Solar Probe Plus A NASA Mission to Touch the Sun 16-19 March 2015 Instrument Suite Name Presenter's Name