social impact assessment study final report english final.pdf · monitoring and evaluation 10.1...
TRANSCRIPT
1
SOCIAL IMPACT ASSESSMENT STUDY
FINAL REPORT
KOCHI WATER METRO PROJECT
KAKKANAD BOAT JETTY
District : Ernakulam
Taluk : Kanayannoor
Municipality : Thrikkakkara
Village : Kakkanad
Submission
The District Collector, Ernakulam
SIA Unit
Youth Social Service Organisation
Social Service Centre
College P.O
Kothamangalam-686666
Phone: 0485 2971222, 9446510628
Website: ysso.net, Email: [email protected]
2
DECLARATION
As per Kerala Gazatte notification No.G.O (P) No. 74/2019/RD dated
4/11/2019. From District Administration, Ernakulam, Youth Social Service
Organization is assigned as the SIA Unit to study the Social impact Assessment
of Land Acquisition for Kakkanad Boat Jetty to be constructed under Kochi
Water Metro Project. The land details are given to the SIA team by Special
Tahasildar Office (L.A) NO2, KMRL, Ernakulam. The SIA team has collected
data from the project affected families and the stake holders at Kakkanad Boat
Jetty to be constructed under Kochi Water Metro Project, the proposed project
area. The supportive documents have to be verified by the concerned authorities.
Chairman,
SIA Unit
Youth Social Service Organisation
Ernakulam,
23-12-2019.
3
FORM NO.6
[See Rule 15(5)]
KOCHI WATER METRO PROJECT
KAKKANAD BOAT JETTY
Chapter Contents
1. Summary of the study 1.1 Project And Popular Goals
1.2 The Site
1.3 Sixe of The Acquired Land
1.4 Alternative Routes
1.5 Social Impacts And Mitigation Steps
2. Detailed Project
Description
2.1 Background of the project and rationale for the
project
2.2 Project Size, Location, Products, targets and costs
2.3 Authorised Basis Of Project
2.4 Examination of alternatives
2.5 Work Force Requirements
2.6 The Project’s Construction Progress
2.7 Public Relevance of The Project
2.8 Environment Impact Assessment Details
2.9 Previous Studies
2.10 Applicable rules and statutes
3. Team composition, Study
Approach And Methodology
3.1 Back Ground
3.2 Information about the study group
3.3 The Process of Impact Assessment and Project
4
Implementation Preparations
3.4 Desk Research
3.5 Secondary Data
3.6 The Affected Area Visit And Project Awareness
Campaigns
3.7 Evaluation of Circumstances
3.8 Schedule of Consultations With Key Stake
Holders
4. Valuation of land 4.1 Background
Land inventories(Site Map)
4.2 Entire area of impact under the influence of the
project
4.3 Land requirement for the project
4.4 Use of public land
4.5 Land already purchased
4.6 Geography, Current Purpose, And Landforms
4.7 Nature of Ownership
4.8 Previous Transactions In The Area
4.9 Period of Ownership of Land
5. Assessment And
Calculations
5.1 Preface
5.2 Direct Impact of the Project
5.3 Indirect impact of the project
5.4 Family of scheduled tribes and other traditional
forest dwellers who have lost any of their forest
rights
5.5 Families which depend on common property
resources which will be affected due to
5
acquisition of land for their livelihood
5.6 Families which have been assigned land by the
state government or the central government
under any of its schemes and such land is under
acquisition
5.7 Families which have been residing on any land in
the urban areas for presending three years or
more prior to the acquisition of the land
5.8 Families which have depend on the land being
acquired as a primary source of livelihood for
three years prior to the acquisition
5.9 Inventory of productive assets
6. Socio- Economic Design 6.1 Preface
6.2 Family details
6.3 Religious Group
6.4 The Affected Livelihood
7. Planning Of Counter –
Impact Implementation
7.1 Approach to impact mitigation
7.2 Methods for negation, Mitigation and
compensation of the impact
7.3 Measures to Fulfill The Project Suggestions
7.4 Employment opportunities
7.5 Impact Mitigation and management plan
8. Social impact action plan
directorate
Directorate and responsible officials
9. Social Impact Management
Budget and Financing of
Mitigation plan
9.1 Costs of all resettlement and rehabilitation
required
9.2 Annual budget and plan of action
9.3 Finding sources with break up
6
10. Social Impact
Management Plan
Monitoring and Evaluation
10.1 Supervision And Evaluation – Major Indexes
10.2 Reporting mechanisms and monitoring roles
10.3 Plan of Independent evaluation
11. Analysis of Costs And
Benefits Recommendation on
Acquisition
11.1 Final conclusion and assessing the aims
11.2 Character of social impacts
Summary
Acknowledgment
7
LIST OF TABLES
Table No 3.1 Details of Properties Affected
Table No 4.1 Details of Properties Affected
Table No.4.2 Acquiring Project Affected Land
Table No. 4.3 Type of Possession
Table No. 4.4 Period of Ownership
Table No. 6.1 Family Income
Table No.6.2 Age Wise Detail
Table No. 6.3 Marital Status
Table No.6.4 Education Details
Table No.6.5 Occupation Details
Table No.6.6 Ration Card Grading
8
LIST OF ANNEXURES
Annexure 1 (a) Gazatte notification
Annexure 1 (b) Draft notice copy
Annexure 2 Socio economic survey questionnaire
Annexure 3 Public hearing notification news (Mangalam, Metro)
Annexure 4 Notice to the affected families
Annexure 5 List of participants-officials and affected families
9
CHAPTER 1
SUMMARY OF THE STUDY
1.1 PREFACE : THE PROJECT AND GOALS
Kochi is a major port city situated on the western coast in the Indian Peninsula
as well as one of the densely inhabited cities in the State of Kerala. Kochi has achieved
extra ordinary economic growth in the last decade. She has earned enormous
investments by means of Vallarpadam International Terminal, Special Economic Zone,
Smart City, Infopark and such industrial centres. And these strategic economic
investments as a whole, have rendered great contributions to the local financial
structure and field of employment.
Kakkanad is situated close to Thrikkakkara, and ancient capital of the legendary
King, Mahabali. The place is a basic part of Kochi’s industrial basic as well as its
broadcasting bastion. In local terms of democratic administration, Kakkanad belongs to
Thrikkakkara Municipality. Being the administrative hub of Ernakulam District, there
are several central government offices at Kakkanad; Such as Civil Station (District
Collectorate, R.D.O) District Panchayat Office, Airman Selection Board, Shiksha
Bhavan (Central H.R.D Ministry Office) Central Sreemsadan (local Labour
Commissioner’s Office) etc. And these make Kakkanad very popular. Thus Kochi Water
Metro Project is a golden feather on the developmental cap of Kakkanad.
207.79 Ares of land belonging to various villages at 3 taluks of Kanayannoor,
Paravoor and Kochi, Ernakulam district are to be acquired for the construction of 15
Boat Jetties for the Project. This reports deals with the social impact study on Kakkanad
Boat Jetty construction.
The land area required to the acquired for the building of Kakkanad Boat Jetty is
0.1525 hectare area at Kakkanad Village, Kanayannoor Taluk, Ernakulam District. The
said Boat Jetty is within the Municipal area of Thrikkakkara.
The Kochi Water Metro Project is an integral system mutually connecting the
islands of Kochi. The Project under the aegis of KMRL has obtained the approval of the
Central and state Governments.
10
The Water transport system envisaged for Kochi focuses not only on the ferry
services as the mode for public transportation, but also envisions a holistic development
of the areas being connected by integrating the waterway system as a part of the entire
public transport system of the city. Apart from the ferry service development, the project
also looks into developing the existing and new roads providing increased access to the
jetties and also within the islands, ensuring safety and security to all its users by way of
active and well-lit streets, promoting use of small occupancy feeder modes to access the
jetties, promoting property development around the jetties and place making. Besides
the above, the project also aims at developing non motor vehicle modes, travel facilities
for the differently abled, availability and parking facility for bicycles at the jetties,
entertainment facilities, promoting tourism as a part of the project, and above all
develop on overall Consumer – Centered and community – Participatory transport
system, over and above a mere ferry service from one jetty to another.
The goal of the project is to develop the best system at the least cost. Along with
the development of travel modes, the project also includes plants to assess and expand
the existing routes. Indeed a development Project might face adverse phases and the
Rights Act – 2013 has been a device in place to protect the interests of those who suffer
impact due to the project. This study is expected to help solving the problems and
anxieties of the affected people, paying compensation and defining firm terms for the
rehabilitation activities as per legal stipulations.
KOCHI WATER METRO
Kochi Water Metro Project is an integrated water transport project proposed by
Kochi Metro Rail Limited. The project has been a jewel on the crown of Kochi, the Queen
of the Arabia Sea.
In the ancient times, water transportation had been the primary mode of
movement in the Vempanadu Lake for people and Cargo. However, this has declined
during the recent decades. The project helps reducing the pollution and traffic jams in
the city and pave easy access for the island residents to the mainland and business
centres. Water transportation is rather island than rail or road ways. The project makes
it possible to launch eco-friendly efficient and safe boats fitted with state of the art
engines.
11
The Project proposes variants of modernised air-conditioned catamaran
passenger boats with wi-fi facility.Boat will have the latest safety and communication
equipment. 50-100 passenger – capacity boats have a speed of 8 nautical. Small – size
battery – powered boats will ply along the narrow routes. The frequency of service in
different routes is every 10-20 minutes. As a part of the infrastructure, it will have
intelligent Navigation System and Operation Control Centre (O.C.C.) which will be
connected to the City’s intelligent transportation system. It is, as well, expected that the
Automatic Fase Collection System to be implemented by Kochi Metro will be extended to
water transportation System. It has been learned during the study that the approval of
the Environment Committee of the central government has been obtained for the project
that connect 10 islands in Kochi through 15 routes at a distance within 78 Kms.
1.2 PROJECT AREA
The land to be acquired for Kakkanad Boat Jetty under Kochi Water Metro
Project belongs to18th ward of Thrikkakkara Municipality in Kakkanad Village in
Kanayannur Taluk of Ernakulam District.
12
1.3 SIZE AND CHARACTERISTICS
The affected land area to be undertaken for the construction of Kakkanad Boat
Jetty is 0.1525 hectare belonging to Kakkanad Village, Kanayannoor Taluk, Ernakulam
District. It is open expanse of land with no cultivation.
1.4 ALTERNATIVE SITE CONSIDERED
As the proposed land is adjacent to the project area, no other land need to be
sought.
1.5 IMPACT MITIGATION STEPS
Sl.
No.
Expected loss Approach Possible reduction measures
1. Loss of access to rest of the
land
Control Re-settlement of accesses
2. Sound, atmosphere pollution,
dust etc.
Control Include in the blueprint of
impact reduction measures
3. Delay in land acquisition and
compensation distribution
Effective
monitoring and
control
Distribution of compensation
before land acquisition
4. Include the affected through
land acquisition measures
Control Ensure participation of the
affected in proceedings
5. Grievance redressal Control Functioning of efficient
grievance redressal
committees at district and
panchayat level
13
CHAPTER -2
DETAILS OF THE PROJECT
2.1 BACKGROUND AND RATIONALE OF PROJECT
This chapter contains details regarding land acquisition for Kakkanad Boat
Jetty, Part of the Kochi Water Metro Project. It also includes the projects popular goals,
cost etc.
2.2 PROJECT’S SIZE, LOCATION, GOAL COST ETC.
The project is proposed to be implemented at 0.1525 hectare of lands belonging to
various Survey Nos of Kakkanad Village, at KanayannoorTaluk, Ernakulam District.
The project aims at developing a multi faceted transport system focussed on the need for
improved water transportation. As per the instruction of the Urban Development
Department the project is being implemented under the aegis of KMRL.
Kochi City has been reported to have the maximum number of vehicles in Kerala.
Lack of adequate public transport system and ever-increasing vehicular multiplicity
cause acute problems related to transportation. The proposed water transport project
has been designed in such a way as to substantially reduce traffic blocks in the city. It is,
as well an integral part of a seamless concept for the city to be implemented outside the
city. The goal of the project is to offer a far better water transport system at a low price.
Water Metro is the first public transportation project of the state. It yields saving
on time by providing improved travelling facilities while promoting social and economic
growth. The project is also helpful in increasing employment opportunities, annual
income as well as industrial development.
The scope of this integrated water transport development project being
implemented following Kochi Metro, is much larger. While improving public
transportation, it can also curtail dependence on roadways.
The Kochi Water Metro Project is 78 Km long, including 15 routes and 38
stations. The estimated cost of the project is Rs. 747 Crore.
Kochi Water Metro Project is envisaged with the view to bringing urban
transportation under public transport system. With the realisation of the project, the
14
number of travellers by water is expected to increase. The project is developing a water
network connecting Kochi City and its neighbouring residential areas which are
surrounded by rivers and lakes.
2.3 AUTHORISED BASIS OF PROJECT
State Govt. entrusted the Revenue Dept. with the acquisition of land as per the
rules and regulation of the new Act of 2013 and handing over to the KMRL.
As per Notification No.2652 of Volume 8 of Special Gazette dated november 05,
2019 of Kerala Govt. Youth Social Service Organisation was authorized to
conduct a social impact study as per the laws and statutes of 2013, Act and
submit a social impact study Report and counter impact implementation Plan.
For the Kakkanad Boat Jetty, Social impact study was conducted in 0.1525
hectare of land.
Dispensation of compensation prior to land acquisitional as per 2013, Act is the
demand of the impacted stakeholders.
The Kochi Metro Rail Ltd Dept. shall be the Finance Authority and the Special
Tahsildar (L.A) No. 2 shall be the Land Acquisition Officer.
2.4 ALTERNATIVE SITE CONSIDERED
As the proposed land is adjacent to the project area, no other land need to be
sought.
2.5 WORK FORCE REQUIREMENTS
In order to complete the proposed project successfully in time, it is important to
ensure the availability of multi-skilled labour force during the implementation phase.
Modern equipment and expert engineers are essential. Once the work takes off, it ought
to be completed without delay. The project is expected to provide work opportunities for
the local as well as outside people.
2.6 THE PROJECT’S CONSTRUCTION PROGRESS
Construction activities of the Kakkanad Boat Jetty to be undertaken as part of
the project, has not started yet.
15
2.7 PUBLIC RELEVANCE OF THE PROJECT
The Kochi Water Metro Project set to acquire land subjected to social impact
study, aims at developing the necessary infrastructure for the economic growth of
Kerala.
2.8 DETAILS OF ENVIRONMENTAL IMPACT STUDY
As the Kochi Water Metro Project opens up a new realm in transportation
development field for public utility, it is expected to receive a warmer acceptability
rather than environmental impairment.
2.9 PREVIOUS STUDIES
No previous studies have been conducted on Kakkanad Boat Jetty and the
present study organized by the Youth Social Service Organisation can well be deemed as
the first of its kind in this regard.
2.10 APPLICABLE LEGISLATIONS AND POLICIES
Acts & rules listed below affect Land Acquisition, Transparency, Rehabilitation
and Re-settlement related to Kochi Water Metro Project.
Sl. No. Acts and Rules Affected area
1. The Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Re-Settlement act
and rules
Impact reduction
2. Land Acquisition Act 1893
Land Acquisition Act (Rules in Kerala 1990)
Land Acquisition Act 1961
Rules regarding land acquisition
Rehabilitation & Re-settlement act of the government
Right to Information act 2005
Land acquisition
Rehabilitation and
Re-settlement
16
RIGHT TO INFORMATION ACT – 2005
The Right to Information Act came into effect in 2005 in order to empower
citizens, ensure transparency and accountability in administration and prevent
corruption, and to strengthen democratic process and make it people – centric. An
informed public is essential for the effective functioning of a democratic regime. It is the
most effective law to provide information to the citizens with regard to the activities of
Governments.
17
CHAPTER -3
UNIT, APPROACH AND RATIONALE OF THE STUDY
3.1 BACKGROUND
The SIA Division of The Youth Social Service Organization, Social Service
Centre, College P.O. Kothamangalam has been entrusted with undertaking the Social
Impact Assessment Study for Kakkanad Boat Jetty, as per the Kerala Gazette
Notification G.O (P) No. 74/2019/RD dated 4.11.2019. The study unit’s responsibility is
to assess the Social impact owing to the project.
3.2 DETAILS OF THE STUDY UNIT
The data collection for the social impact assessment study and their integration
was done under Team Director of Youth Social Service Organisation by a group of 6
experienced members. Services of experts from development and legal sector have been
availed for the study and report preparation. And, revenue official helped to identify the
affected areas.
Sl. No. Name Designation, eligibility and experience
1. Jose Paruthuvayalil MSW, Director, 22 years experience in SIA unit
2. Kuriakose George Project Coordinator, LLB, 15 years experience in
development sector
3. Baiju PT Research Associate, MSW, 10 years experience in
development sector
4. SavithaSajeesh Research Associate, BA, 2 years experience in
development sector
5. Jinu Joseph Research Associate, B.Com, ICW, 2 years experience
in development sector
6. Mini Jibish Research Associate, BA, 2 years experience in
development sector
18
3.3 THE PROCESS OF IMPACT ASSESSMENT AND PROJECT
IMPLEMENTATION PREPARATIONS
Acquisition of land and properties affects social and economic sustainability,
social impact study and properly planned rehabilitation programs should be done.
Rehabilitation plans should establish livelihood programs of the affected people same as
before the land acquisition. The study unit has conducted the preparations for the social
impact assessment with these obligations as priority.
Figure 3.1 shows the approach and rationale of the study in a flowchart. And
stages of the study are listed below.
FIGURE 3.1: SOCIAL IMPACT ASSESSMENT STUDY DESIGN AND METHOD
STAGE 1: ACTIVITIES BEFORE STUDY
Social Analysis and pilot meeting Pilot survey and beginning of external works
Detailed project analysis
Preparation of the project
blueprint
RFCT in LARR Act 2013
State laws on land acquisition
Pilot study
Preparation and checking of survey tools
Identifying the groups for data collection
Finalizing the pilot report
STAGE 2: DATA COLLECTION METHODS AND IMPLEMENTATION
The affected families/people/society Facilities required for the project
Training for the field staff
Data collection from the affected
family members
Discussions with officials of concerned
departments
Analysis of legal rules and regulations
Analysis of rehabilitation programs with
local officials
Data analysis
Draft of collected data, their analysis and
impact assessment
19
STAGE 3: ACTIVITIES AFTER SURVEY AND BLUEPRINT OF THE
ANALYSIS
Tabulation of the collected data and
blueprint of analysis
Concerns on the Social Impact Assessment
Study
Integration, categorization of data
Finalization of the report
Analysis of the collected data
Preparation and submission of the
draft report of the social impact
assessment study
Organize public hearing
Meeting and discussions on study
findings with affected people
Analysis and opinions of concerned
officials
Integration of the opinions and
submission of final report
3.4 DESK RESEARCH
Study Team examined the relevant documents, Reports, Project Plans etc. in
details.
3.5 SECONDARY DATA
Secondary data was prepared from the studies conducted earlier and concerned
departments. The study unit could realize the social economic and cultural
circumstances of the affected people through the social impact assessment study.
3.6 THE AFFECTED AREA VISIT AND PROJECT AWARENESS
CAMPAIGNS
Before beginning the detailed study on the social impact, site visit for the socio-
economic survey and preliminary study were done. In addition, interviews were held
with the affected persons and their response was recorded. The study team had made
the necessary additions and corrections in the interview schedules as appropriate.
20
Based on locating the project site and identifying the impacted persons and
families, primary data was collected directly from the concerned parties in November,
2019 and social impact study draft report was prepared, editing the data thus compiled.
3.7 DATA COMPILING AND CHECKING
The whole data thus collected for analysis and assessment was compiled and the
necessary checking was made. Moreover, available data was being collected from time to
time and they were updated. The team had taken the necessary precautions to delete
errors in the data.
3.8 SCHEDULE OF CONSULTATIONS WITH KEY STAKE HOLDERS
Discussion with village officer
Affected Area
Affected Area
21
Table 3.1 contains the socio-economic impact on the parties who are to be
compensated for giving up land for the Project.
TABLE 3.1: DETAILS OF PROPERTIES AFFECTED
Sl.
No.
Address of the Person Survey
Number
Issues/ requirements
put forward
1 Bonifas Satheesh,
Kooruveliparambil,
Aiwarya Lane,
Thammanam P.O., Pin
682032
Kakkanad
Village
540/4-2pt
Have informed that they are ready to
contribute their property and need
adequate compensation
Issues arose during Public hearing:
Informed that they need required support
to construct new building in the
remaining land
2 Asha Abraham,
Kunnathu, Cess P.O.,
Chittethukara,
Kakkanad, Pin 682037,
Arun Jacob, Abraham, Ann
Maria Abraham
Kakkanad
Village
541/1 pt
Earlier this land has been acquired twice
(Seaport-Airport road, bridges). They are
willing to give land, if adequate
compensation and job for their son as per
his qualification are provided.
Issues arose during Public hearing:
The property is in triangular shape. And
hence, as the land’s value is being lost, it
is a huge loss. If the land is being
acquired in this manner, they are not
willing to provide land. They requested to
acquire the land without affecting rest of
the land.
3 Babu&Sussanna,
Parekkara,
Kothamangalam,
Ernakulam, Pin-686691
Kakkanad
Village
541/2 pt
This property has been acquired earlier
for Container Terminal. They have
demanded to provide way to the rest of
the land after acquiring for water metro
project. And have informed that they are
ready to provide land if adequate
compensation paid.
Issues arose during Public hearing:
Demanded required support for
construction of a building in the
remaining land and pathway to that land.
4. State Corporation Kakkanad Remainder govt. land
22
Panchayat Road Village
540/5
3.9 SUMMARY OF PUBLIC HEARING
A public hearing of the landowners affected by acquisition of plots belonging to
Kakkanad Village at Kanayannoor Taluk, Ernakulam District, was held before the
authorities at 11.00 am on 12 December. 2019 at the Municipality Hall, Thrikkakkara.
The whole procedure had been video graphed to keep on record.
PARTICIPATED OFFICIALS
1. Sri. Abraham - Deputy Collector (L.A.)
2. Sri. Joe Paul M - JGM, KMRL.
3. Sri. Abbas JE - Special Tahsildar (LA) No. 2
4. Sri. KP Mohan Das - CRO, KMRP
5. Sri. Gangadharan - Advisor KMRL
6. Sri. K S Sudhakaran - Consultant (LA) KMRL
7. Sri. Nishanth. - Manager, KMRL
8. Sri. Felix Medwin - Consultant (LA) KMRL
9. K.T. Eldho - Vice Chairman,
10. Sri. P.S. Shibu - Municipal Secretary, Thrikkakkara
11. Sri. K.P. Sivan - Counciller, Thrikkakkara Municipality
12. Sri. T.M. Ali - Counciller, Thrikkakkara Municipality
REPLY OF AUTHORITIES
GANGADHARAN (Advisor KMRL)
As per earlier law, there was no social impact assessment (SIA). But in 2013, as
per RFCT LARR Act, this assessment is a prerequisite. If a land is to be acquired for
Government programs, first step is to decide whether this acquisition is required or not.
As per the act in 2013, the issues and concerns of the affected are heard in SIA, and final
report is submitted including all these. And this final report is to be submitted to Expert
committee under District Collector. This report is then transferred to Government and
final decision is of theirs. Water Metro Project of Kochi Metro is a government project.
Vyttila Boat Jetty and Kakkanad Boat Jetty are two jetties which can change the face of
Kochi. Kakkanad boat Jetty requires 72 cents of land, of which 35 cents of land will be
given by 1WA. But their demand was to broaden roads and provide space for parking
facilities. Otherwise, this 35 cent land was enough for Kakkanad Boat Jetty. But as the
23
land is required for parking and broadening the road, shape of land required is in this
manner. It is planned by reducing maximum adverse effects.
He also informed that plan may change again, and final decision maker is not
KMRL. The triangular land required is for parking, and path will be open to all. He also
assured that as the water metro comes, value of land will increase (as a reply to concern
of the affected). He also said that RFCT LARR Act 2013, is an act giving importance to
land owners.
SPECIAL TAHSILDAR (LA) NO.2.
The RFCT LARR Act 2013 is very supportive to land owners and it protects the
owners in a way that they should have no loses during or after acquisition. 100%
solatium will be given for the concern on land’s price. If there is a building in the land,
this Act also provides for packages to the tenants and employees of the shops in this
building.
Tax extension has been given for acquiring land for water metro. Thos who file
income tax can avail most of this act. This should be used properly by people affected. In
case if anyone is not satisfied by this act, they can approach court on this regard.
DEPUTY COLLECTOR (LA)
The price will be decided after considering documents of land before 3 years, and
taking the maximum price into consideration, that is after publishing 11(1) notification.
VICE CHAIRMAN
Kochi Water Metro will be most appropriate solution for traffic issues in Kochi.
All should provide possible support and cooperation. And he opined that those who are
willing to provide land should leave adversaries.
SECRETARY
Water metro project will also be supportive to tourism. And will support
transportation from Infopark till Veegaland. He felicitated that this project may go
forward in all positive ways.
COUNSELLOR
This project integrates all waterways and thus provides good transportation
facility and tourism. And he believes that Water Metro will give a new face to our place.
24
PHOTOS OF PUBLIC HEARING
25
CHAPTER -4
LAND ASSESSMENT
4.1 PREFACE
For acquiring land for Kochi Water Metro Project, details of people losing land,
the affected people, their socio economic information were collected through interview
schedule prepared for it in 2019 November. Details regarding the affected properties,
their type, ownership, impacts on private properties, income and livelihood of people,
and depth of impact due to project were collected. The effects of land acquisition for
Kochi water metro project is depicted below with the help of survey with an image.
LAND INVENTORIES (MAP OF SITE)
26
4.2 TOTAL IMPACT DUE TO THE PROJECT
Table 4.1 shows the Socio – economic impact on those receiving compensation for
surrendering lands for the project.
Sl.
No.
Address of the Person Survey
No.
Problems/Demands Raised
1 BonifasSatheesh,
Kooruveliparambil,
Aiwarya Lane,
Thammanam P.O., Pin
682032
Kakkanad
Village
540/4-2pt
Have informed that they are ready to
contribute their property and need adequate
compensation
Issues arose during Public hearing:
Informed that they need required support to
construct new building in the remaining
land
2 Asha Abraham,
Kunnathu, Cess P.O.,
Chittethukara,
Kakkanad, Pin 682037,
Arun Jacob, Abraham,
Ann Maria Abraham
Kakkanad
Village
541/1 pt
Earlier this land has been acquired twice
(Seaport-Airport road, bridges). They are
willing to give land, if adequate
compensation and job for their son as per his
qualification are provided.
Issues arose during Public hearing:
The property is in triangular shape. And
hence, as the land’s value is being lost, it is a
huge loss. If the land is being acquired in
this manner, they are not willing to provide
land. They requested to acquire the land
without affecting rest of the land.
3 Babu&Sussanna,
Parekkara,
Kothamangalam,
Ernakulam, Pin-686691
Kakkanad
Village
541/2 pt
This property has been acquired earlier for
Container Terminal. They have demanded
to provide way to the rest of the land after
acquiring for water metro project. And have
informed that they are ready to provide land
if adequate compensation paid.
Issues arose during Public hearing:
Demanded required support for construction
of a building in the remaining land and
pathway to that land.
4. State Corporation
Panchayat Road
Kakkanad
Village
540/5
Remainder govt. land
27
4.3 LAND REQUIREMENT FOR PROJECT
0.1525 hectare land area belonging to Kakkanad village, Kanayannoor Taluk, has
to be acquired for the Kakkanad Boat Jetty, a part of Water Metro Project. It is empty
land including government land.
TABLE 4.2 ACQUISITION IN IMPACTED AREA
Sl.No. Name of the land owner Survey No. Size
1 Bonifas Satheesh, Kooruveliparambil,
Aiwarya Lane, Thammanam P.O., Pin
682032
540/4-2pt 0.0042
2 Asha Abraham, Kunnathu, Cess P.O.,
Chittethukara, Kakkanad, Pin 682037,
Arun Jacob, Abraham, Ann Maria
Abraham
541/1 pt 0.1320
3 Babu & Sussanna, Parekkara,
Kothamangalam, Ernakulam,
Pin-68669
541/2 pt 0.0152
4 State Corporation Panchayat Road 540/5 0.0011
Total 0.1525 h
4.4 NEED OF PUBLIC LAND
Public land is to be taken over for the construction of Kakkanad Boat Jetty.
4.5 LAND PURCHASED FOR THE PROJECT
No land has been purchased till date. Acquisition activities will begin only after
social impact assessment study.
4.6 NATURE OF LAND, CURRENT UTILITY STRUCTURE OF LAND
28
The land to be acquired is city area. No commercial or industrial activity on the
land and it is not agricultural land at all
4.7 TYPE OF OWNERSHIP
Table No. 4.3 Type of Ownership
Type Number Percentage
Ancestral 2 66.67
Purchased 1 33.33
Total 3 100
4.8 PREVIOUS TRANSACTIONS IN PROJECT AREA
One transaction had taken place for land belonging to Survey No. 540/4 pt on
4.6.2019. Official documents are to be checked for verification and details.
4.9 DURATION OF OWNERSHIP OF LAND
Table no.4.4 duration of
ownership of land
Year Number Percentage
Above 50 years 1 33.33
Between 20-30 1 33.33
2019 1 33.33
Total 3 100
(The information furnished above is based on statements provided by the
concerned parties during the visits; supporting documents are to be referred to for
verification.
29
CHAPTER -5
NUMBER OF IMPACTED FAMILIES AND
LOSS OF ASSETS
5.1 PREFACE
This chapter contains the dimension of the direct and indirect impacts of the
project on families.
5.2 DIRECT IMPACT OF THE PROJECT
As the 0.1525 hectare land to be undertaken for the project is open grounds, no
significant direct impact is likely to be caused.
5.3 INDIRECT IMPACT OF THE PROJECT
Those persons who live or work in the area, but are not affected directly by the
acquisition, are considered to be the indirectly affected persons.In terms of such a
definition, there are no indirectly impacted person in the Project Area.
5.4 FAMILIES OF SCHEDULED TRIBES OR TRADITIONAL FOREST –
DWELLERS WHO FORFEIT FOREST RIGHTS.
In the construction activities of Kakkanadu Boat Jetty, no families of Scheduled
Tribes of traditional forest dwellers who lose their forest rights, are impacted
5.5 ARE THE ACQUIRED LANDS BEING DEPENDED FOR 3 YEARS FOR
FAMILIES FOR LIVELIHOOD ?
In connection with land acquisition for the project, the impacted persons lose land
only. Hence the Boat Jetty construction does not affect livelihood at all.
5.6 IS THE ACQUIRED LAND’S ORIGINAL OWNERSHIP AWARDED BY
VIRTUE OF ANY WELFARE SCHEME OF THE CENTRAL OR STATE GOVT.?
30
The land to be acquired for the Boat Jetty was not obtained as part of any welfare
scheme of the State of Central Government.
5.7 HAS THE FAMILY BEEN LIVING IN URBAN AREA FOR THE LAST 3
OR MORE YEARS ?
The impacted families have been living in the city area.
5.8 ARE THE FAMILIES DEPENDANT ON PUBLIC LAND FOLLOWING
LOSS OF LIVELIHOOD DUE TO THE ACQUISITION ?
No families dependant on public property following loss of livelihood due to the
acquisition, are involved in connection with the construction of Kakkanad Boat Jetty
5.9 DETAILS OF YIELDING LAND
The proposed project area contains no yielding crops
31
CHAPTER - 6
SOCIO – ECONOMIC PLAN
6.1 BACKGROUND
This chapter includes socio economic cultural details of affected families and the
situation of these factors. Demographic details, situation, livelihood affected families
and additional information of the affected people are also enlisted.
6.2 FAMILY DETAILS
Table6.1 FAMILY INCOME
Income No. Percentage
40000-50000 2 66.67
Above 1 Lakh 1 33.33
Total 3 100
TABLE 6.2 AGE WISE DETAIL
Age No. Percentage
15-25 2 18.18
25-35 4 36.36
45-55 2 18.18
55-65 3 27.27
Total 11 100
32
TABLE 6.3 MARITAL STATUS
Income No. Percentage
Married 6 54.54
Unmarried 4 36.36
Widows 1 9.09
Total 11 100
TABLE 6.4 EDUCATION DETAILS
Education No. Percentage
Secondary 1 9.09
Degree 4 36.36
Masters degree 6 54.54
Total 11 100
TABLE 6.5 OCCUPATION DETAILS
Employment No. Percentage
Business 1 9.09
Private job 2 18.18
Others 8 72.73
Total 11 100
33
TABLE 6.6 RATION CARD GRADING
Type No. Percentage
Above poverty line 2 66.67
No 1 33.33
Total 3 100
6.3 RELIGIOUS GROUP
The affected people belongs to Christian community
6.4 THE AFFECTED LIVELIHOOD
The affected area contains open grounds which has no homestead or
commercial complexes.
34
CHAPTER – 7
SOCIAL IMPACT MITIGATION
7.1 IMPACT MITIGATION APPROACH
The affected individuals are demanding compensation amount and job for family
members in order to reduce the impact of land acquisition. Hence, in order to reduce the
impact, compensation of land acquisition needs to be decided through discussions with
the affected families and distribute them before land acquisition.
The affected families should be made aware of the benefits of Kochi Water Metro
Project, and take necessary steps to provide them the advantages of the project.
7.2 METHODS FOR NEGATION, MITIGATION AND COMPENSATION OF
THE IMPACT
The compensation should be decided and distributed as per ‘The Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and
Re-Settlement act, 2013 (RFCTLARR Act 2013) in a timely manner.
7.3 MEASURES TO FULFILL THE PROJECT SUGGESTIONS
A special budget needs to be identified for distribution of compensation.
7.4 EMPLOYMENT OPPORTUNITIES
One of the major demands of the local people is employment in the vacancies
arising for the project. Educational qualification can be laid down as criteria.
7.5 IMPACT MITIGATION STEPS
Sl. No. Expected loss Approach Possible reduction measures
1. Loss of access to rest of the land Control Re-settlement of accesses
2. Sound, atmosphere pollution, dust
etc
Control Include in the blueprint of
impact reduction measures
3. Delay in land acquisition and Effective
monitoring
Distribution of compensation
35
compensation distribution and control before land acquisition
4. Include the affected through land
acquisition measures
Control Ensure participation of the
affected in proceedings
5. Grievance redressal Control Functioning of efficient
grievance redressal
committees at district and
panchayat level
36
CHAPTER - 8
SOCIAL IMPACT ACTION PLAN DIRECTORATE
8.1 DIRECTORATE AND RESPONSIBLE OFFICIALS
Administrator appointed by government as per RFCTLARR Act 2013 will be
responsible for developing re-settlement scheme for affected families. Under the
supervision and guidance of government and Commissioner of rehabilitation and re-
settlement, Administrator of Rehabilitation and Re-settlement will be responsible for
the formulation, implementation and monitoring of scheme for Rehabilitation and Re-
settlement.
Provision of adequate compensation to the affected, as per RFCTLARR Act 2013,
will not reduce impact.
As per the laws of state government, the district level committee on adequate
compensation, Rehabilitation and Re-settlement should include following persons.
District Collector
Administrator of Rehabilitation and Re-settlement
Land acquisition officer
Finance officials
Representatives of Arthana officials for taking financial decisions
Representatives of Local Self Government
37
CHAPTER -9
SOCIAL IMPACT ALIENATION BUDGET
9.1 COST OF REHABILITATION AND RE-SETTLEMENT
The expenditure for Rehabilitation and Re-settlement is not calculated.
9.2 ANNUAL BUDGET AND PLANNING DOCUMENT
Not applicable
9.3 FINANCIAL SOURCE BY CATEGORY
Financial source of the affected area is not categorized.
38
CHAPTER -10
SOCIAL IMPACT ELEMINATION PLAN –
SUPERVISION AND EVALUATION
10.1 SUPERVISION AND EVALUATION – MAJOR INDEXES
Participation of land owners in district level purchasing committee
Land was purchased directly from how many land owners
Indicators used to calculate compensation
Re-settlement of blocked entrances
Formation of grievance redressal committee
Time required for Rehabilitation and Re-settlement
10.2 REPORTING PATTERN, SUPERVISION AND DUTIES
Not applicable
10.3 INDEPENDENT EVALUATION – PLAN
Not applicable
39
CHAPTER -11
MERITS AND DEMERITS, ANALYSIS AND
PROPOSAL REGARDING ACQUISITION
11.1 CONCLUSION AND APPRAISAL OF POPULAR GOALS
The Kochi Water Metro Project mainly targets not only ferry services for public
transportation, but also environment – friendly development of all the locations that can
be connected by water transportation by being a link in the chain of the city’s integrated
public transportation. Much more than a common place ferry service, it intends to
device a customer centered and community – partaking transportation facility. It is a
link of a great concept, that is, a flawless integration for the city. The project is an easy
and fast means to reach the city and a remedial measure for the illnesses that affect the
body of transportation. With the advent of the proposed project, the accursed traffic
blocks in the city are expected to be straightened well-nigh.
11.2 THE NATURE AND SEVERITY OF THE IMPACT
That the project is not impacting on socially backward community, is helpful to
mitigate the impact.
By Way of establishing an improved water transport system by harnessing water
resources, saving in time and travel facilities are advantages. The project gives priorities
to employment opportunities as well as developmental activities.
The Project promotes the social and economic developments, of the region while
helping mitigation of social impacts. It was much as a public development project,
people have to forsake land. Though land is undertaken for a public purpose, it affects
people adversely. In such a situation when people face impacts, the Rights Act of 2013
which stipulates Fair Compensation, Transparency, Rehabilitation and Re-settlement,
comes to their rescue Providing protection. Article -4 of this Act mandates that public
interest and Social impacts should be assessed as and when land is taken over for any
developmental activity in India.
40
CONCLUSION
The Kochi Water Metro Project that can solve the problems of the city’s traffic
jams and travel difficulties, is a boon to Kochi. 207.79 Ares land is acquired for the
construction of 15 Boat jetties, out of which 0.1525 hectare is for Kakkanad Boat Jetty.
This study has been instrumental in providing fair compensation to the affected people
as per RFCTLARR Act of 2013.
Developing a multi – purpose transport system in consideration of the
inevitability of an advanced water transport, is the goal of the project. It is implemented
under the aegis of KMRL as per the directive of the Dept of Urban Development. The
Project’s over all driving force is to develop a sustainable integrated water transport
system of international standard, integrating with the other systems of metro pattern at
a common ticket rate and general time schedule for the city of Kochi in tune with the
expectations of the people
In view of the innumerable advantages that the project offer to the general public
land acquisition is indispensible. However, the fairest deal is, indeed to transact the
process of the take-over by providing lawfull and just compensation to the affected
citizens.
41
ACKNOWLEDGEMENT
This SIA Study project would not have completed without the help of different
people and organisations. First of all we are grateful to the revenue department for
entrusting this project to Youth Social Service Organisation. We also remember and
acknowledge our gratitude to Ernakulam District Collector and all the staff members for
their timely guidance to complete this project successfully.
We also acknowledge our gratitude to Special Thahasildar LA,No2, and all the
staff members for helping us to collect all the details of land acquisition. We remember
KMRL and all the staff members for their service to complete this project.
We Thank Thrikkakara Municipality Chairperson, all the staff members, staff
members of Kakkanad Village and all the people of project area for their help and co-
operation.
We also gratefully remember the Executive Director of Youth Social Service
Organisation for being the back bone of this project and guiding us in every step. If we
could not have received any support from all these persons, we would not have
completed this project successfully.
42
43
Annexure 1 (a) Gazatte notification
44
45
46
Annexure 1 (b) Draft notice copy
47
48
49
50
Annexure 2 Socio economic survey questionnaire
Socio Economic Survey for Social Impact Assessment Study
Land Acquisition for Kochi Water Metro Project
Kakkanad Boat Jetty, Ernakulam District
SIA Ref No.
Interviewer’s Name
Survey Date
Supervisor Name
Data Entry Staff Name
Date Entered Date
Data verified by, and Date
Respondent’s Name
Name of the affected person (if different
from above)
Address including PINCODE (Location in
the Affected Area)
Contact (Landline No.)
Contact (Mobile No)
Identity Card Details (any one id proof)
Aadhaar No.
Ration Card No.
Passport No.
Voters Id
Q.1 Identification Place/Location
Ward No.
Name of Panchayath
51
Q. 2 Respondent Owner Representative of Owner
Q. 3 Name & Address
of the Respondent
Owner Representative
of Owner
ASSET DETAILS
Q. 4 Type of Property
Open Land Nilam Nilam Nikathu
Purayidam
Q. 5 Type of use
Open Land Wet Land
(Agricultural Land)
Others (specify)
Q. 6 Name of title holder of the property
(Specify the names of all the members
specified as per the title deed)
a) Communication Address (with
PINCODE)
b) Contact No
c) Relationship with family head
d) Acquisition by Hereditary
Purchase
Encroached/squatter
Others (specify)
e) Date of acquiring of the property (approx
period)
f) Details of transactions made on the
property within the last three years
52
Q. 7 Property Details
a) Survey No (Mandatory
b) Total Area (in hectares)
c) Area Affected (in hectares)
In case of more than one property please use additional pages
IMPACT
Q.8 Extent of acquisition Fully Partially
Q. 9 Whether property viable after
implementation of project
Yes No
Q. VULNERABILITY
Q. 10 Do you have Ration Card? Yes No If Yes, Mention
Number
Q. 11 Type of Ration Care BPL APL AAY
GENERAL INFORMATION
Q. 12 Size of
Family/household (specify
no of family members)
Male Female
Family
Pattern
Joint Nuclear Individual
Q. 13
Religious
Hindu Muslim Christian Jain Others
Q. 14
Social
Group
SC ST OBC General Others
53
FAMILY MEMBERS – DETAILS
SL.
No.
Name Relationship
with the
Head of the
family
Age Sex Marital
Status
Education Job Monthly
Income
Major
diseases
Completed Continuing
Q. 15 Livelihood (Major Source of Income) of Family
affected
Yes No
Q. 16 Family Income & Source
a) Family monthly income (in Rs.)
b) Family monthly expenditure (in Rs.)
c) Major Source of Income
c) No of adult earning members
d) No of depenents
Project Related Information
Q. 17. Are you aware of the proposed Kakkanad Boat
Jetty Project
Yes No
54
Q. 18 If yes, source of information
Newspaper Internet/Social media TV/Media
Community members All of the above Other (Specify)
Q19. What is the positive or other impacts envisaged from this project development
Positive impacts perceived Other perceived impacts
Increase in employment opportunities
due to better access facilities
Loss of productive land for agriculture
Increase in movement in terms of
facility and frequency
Pressure on existing infrastructure
Increase in economic and business
activities
Conflict with outsiders
Increase land prices Increase in the density around the
project area
Improvement in the real estate sector Increased spread of communicable
diseases and other vulnerabilities
Better reach/access to larger towns
(health/education)
Increase in rentals for tenants for both
residential and commercial properties
Higher income from rental due to this
infrastructure development
Others (specify) ........................
Others (specify) ......................
Q. 20 REHABILITATION OPTIONS
a) Owner
Equivalent/better productive land
What is preferred rehabilitation measure Case compensation at replacement value
Training for income restoration
Other (Specify) ..................
Additional information
55
Annexure 3 Public hearing notification news (Mangalam)
56
Annexure 4 Notice to the affected families
57
Annexure 5 List of participants-officials and affected families
58