social- environmental impact study report

166
1 Social- Environmental Impact Study Report 300 MW Wind Power Project Dangri, Jaisalmer District Rajasthan Inox Renewable Limited (IRL) May 2012

Upload: vanxuyen

Post on 01-Jan-2017

225 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Social- Environmental Impact Study Report

1

Social- Environmental Impact Study Report

300 MW Wind Power Project

Dangri, Jaisalmer District Rajasthan

Inox Renewable Limited (IRL)

May 2012

Page 2: Social- Environmental Impact Study Report

2

TABLE OF CONTENTS

CHAPTER NO

CONTENT PAGE NO.

I EXECUTIVE SUMMARY 10

II INTRODUCTION 13

III ENVIRONMENTAL AND SOCIAL REGULATORY FRAMEWORK 17

IV PROJECT DESCRIPTION 24

V BASELINE ENVIRONMENTAL CONDITION 34

VI ENVIRONMENTAL IMPACT ASSESSMENT 53

VII ENVIRONMENTAL MANAGEMENT PLAN 68

VIII PUBLIC CONSULTATION, FINDINGS AND RECOMMENDATIONS 90

Page 3: Social- Environmental Impact Study Report

3

LIST OF FIGURES

FIGURE NO CONTENT PAGE NO.

II.1 LOCATION MAP SHOWING THE PROJECT SITE

15

IV.1 AERIAL VIEW SHOWING THE APPROXIMATE BOUNDARY OF

THE PROJECT SITE 25

IV.2 INDICATIVE CONSTRUCTION AND COMMISSIONING

SCHEDULE FOR 300 MW CAPACITY WHICH IS EXPECTED TO

BE COMMISSIONED BY MARCH 2013

27

IV.3 PROJECT SITE CONNECTIVITY BY ROAD 30

IV.4 VIEW OF IWL WT 2000 DF WIND TURBINE GENERATOR 32

IV.5 CONNECTIVITY DIAGRAM FOR POWER EVACUATION OF 300 MW WIND FARM, DANGRI

33

V.1 SATELLITE VIEW OF THE PROJECT SITE 36

V.2 YEARLY (20 YEARS) WIND ROSE DIAGRAM FOR JAISALMER IMD STATION

37

V.3 WIND ROSE DIAGRAM OF PROJECT SITE FOR MARCH 2012 38

V.4 HOURLY TEMPERATURE VARIATION AT PROJECT SITE 38

V.5 HOURLY HUMIDITY VARIATION AT PROJECT SITE 39

V.6 LANDUSE PATTERN OF STUDY AREA 42

V.7 LITERACY LEVEL OF THE SURROUNDING AREA 44

V.8 OCCUPATIONAL STRUCTURE 45

V.9 LIVESTOCK POPULATION IN THE SURROUNDING AREA 45

Page 4: Social- Environmental Impact Study Report

4

FIGURE NO CONTENT PAGE NO.

V.10 VEGETATION OF THE STUDY AREA 48

VI.1 LOCATION MAP OF PROPOSED WIND FARM IN THE VICINITY

OF THE PROPOSED PROJECT 66

VIII.1 STAKEHOLDERS DURING PUBLIC CONSULTATION 91

Page 5: Social- Environmental Impact Study Report

5

LIST OF TABLE

TABLE NO CONTENT PAGE NO.

VI.1 VEHICULAR REQUIREMENT ON MONTHLY BASIS 29

V.1

SUMMARY OF THE ANNUAL MICROMETEOROLOGY OF THE REGION

35

V.2 SUMMARY OF METEOROLOGICAL DATA AT THE PROJECT SITE

39

V.3 SUMMARY OF AMBIENT AIR QUALITY DATA 40

V.4 EQUIVALENT NOISE LEVELS (LEQ) OF THE STUDY AREA 40

V.5 GROUND WATER QUALITY OF THE STUDY AREA 41

V.6 LANDUSE PATTERN OF THE STUDY AREA 41

V.7 SUMMARY OF THE SOIL QUALITY DATA OF THE STUDY AREA 42

V.8 SUMMARY OF THE POPULATION FOR STUDY AREA 43

V.9 INVENTORY OF FLORA IN THE STUDY AREA 46

V.10 INVENTORY OF FAUNA IN THE STUDY AREA 49

VI.1 CATEGORIZATION OF LIKELIHOOD AND CONSEQUENCE OF

IMPACTS 53

VI.2 NOISE SOURCE STRENGTH OF CONSTRUCTION MACHINERIES

55

VI.3 ADDITION OF SOUND LEVELS, L1 AND L2 (L1 > L2) 56

VII.1 ENVIRONMENTAL MANAGEMENT PLAN: CONSTRUCTION PHASE

68

Page 6: Social- Environmental Impact Study Report

6

TABLE NO CONTENT PAGE NO.

VII.2 ENVIRONMENTAL MANAGEMENT PLAN: OPERATION PHASE 81

VII.3 ENVIRONMENTAL MONITORING PROGRAMME – CONSTRUCTION PHASE

87

VII.4 ENVIRONMENTAL MONITORING PROGRAMME - OPERATION PHASE

88

Page 7: Social- Environmental Impact Study Report

7

LIST OF APPENDICES

APPENDIX NO

CONTENT PAGE NO.

1 COORDINATE LOCATION OF WTGs

94

2 MICROSITING DRAWING

99

3 AMBIENT AIR MONITORING LOCATIONS MAP

101

4 NATIONAL AMBIENT AIR QUALITY STANDARDS

102

5 NOISE MONITORING LOCATIONS MAP

104

6 NOISE MONITORING DATA

105

7 AMBIENT AIR QUALITY STANDARDS IN RESPECT OF NOISE

109

8 NOISE LEVEL AS PER IFC GUIDELINES

110

9 GROUND WATER MONITORING LOCATIONS MAP

111

10 GROUND WATER QUALITY

112

11 SOIL MONITORING LOCATIONS MAP

114

12 SOIL CHARACTERISTICS

115

13 DEMOGRAPHIC STRUCTURE OF THE STUDY AREA

116

14 LITERACY LEVEL IN THE STUDY AREA

117

15 OCCUPATIONAL STRUCTURE

118

16 BIRD AND BAT STUDY FOR DANGRI WIND FARM PROJECT AT JAISALMER, RAJASTHAN

120

Page 8: Social- Environmental Impact Study Report

8

ABBREVIATION

AAQMS Ambient Air Quality Monitoring Stations

APHA American Public Health Association

BIS Bureau of Indian Standards

CDM Clean Development Mechanism

CERs Carbon Emission Reduction Certifications

CPCB Central Pollution control board

CWET Centre for Wind Energy Technology

EHS Environment, Health and Safety

EIA Environmental Impact Assessment

EMP Environmental Management Assessment

FIs Financial Intermediaries

GFL Gujarat Fluro chemicals limited

GHS Green House Gasses

HGV Heavy Goods Vehicles

HVS High Volume Sampling

IFC International Finance Corporation‟s

IRL Inox Renewable Limited

IWL Inox Wind limited

LAA Land Acquisition Act

MoEF Ministry of Environment and Forest

NAAQS National Ambient Air Quality Standards

PS Performance Standard

PUC Pollution under Control

RTI Right to Information

RVPNL Rajasthan Rajya vidyut Prasaran Nigam Limited

SIA Social Impact Assessment

SPCB State Pollution control board

TCE Tata Consulting Engineers Limited

TFD Traditional Forest Dwellers

WGB World Bank Group

WTGs Wind Turbine Generators

Page 9: Social- Environmental Impact Study Report

9

REVISION STATUS SHEET

REVISION NO.

MONTH AND YEAR OF ISSUE DETAILS OF REVISION

1 March 2012 Draft report for review and comments

2 April 2012 Final report after incorporating comments

3 May 2012 Final Report

4 June 2012 Final report

Page 10: Social- Environmental Impact Study Report

10

CHAPTER I

EXECUTIVE SUMMARY

There has been an enormous increase in global demand for energy in recent years as a result

of industrial development, population growth and enhanced lifestyles. Supply of energy is,

therefore, far less than its actual demand. On the other hand, rise in the global average

temperature has become a major concern, which needs immediate attention.

One of the solutions for improving these situations with minimal impact lies in utilizing the

available potential of renewable source of energy. In this regard wind energy has emerged as

one of the promising renewable energy technologies in India.

It is found that State of Rajasthan witnesses high intensity winds and based on the assessment

made by the Centre for Wind Energy Technology (C-WET), the estimated wind power potential

in the state is estimated to be 5050 MW (source: As per revised estimate by CWET as on

December 2011). Considering the enormous potential in Rajasthan, Inox Renewable Limited

(IRL) proposes to set up 300 MW wind energy project near Dangri village in Jaisalmer District of

Rajasthan.

The proposed wind farm consists of 150 numbers of wind turbine generators (WTGs) with rated

capacity of 2 MW each. The proposed wind turbine sites are located approximately between

26°26' 47.8"N & 26°37'33.3"N latitude and 71°17' 06.04"E & 71°34' 50.2"E longitude. The

project will be developed in the vicinity of Bhalabasti, Rajgarh, Baisanra, Ola, Dangri, Malusar,

Chhodiya, Ramsar, Laxmansar, Mahreri, Samel Nagar, Pabnasar, Khodiyasar villages.

The power generated will be evacuated to Akal GSS (which is operated and maintained by

RVPNL) from pooling Substation of the proposed wind farm.

This project does not fall in any of the eight categories of the projects for which prior

environment clearance from Ministry of Environment and Forest (MoEF) is required as per

Notification SO. 1533 dated 14th Sept‟06 and its subsequent revisions.

The present SEIA study is carried out considering International Finance Corporation‟s (IFC)

Performance Standards (PS‟s) and IFC guidelines. IFC applies PS‟s to manage social and

environmental risks and impacts and to enhance development opportunities in its private sector

financing in its member countries eligible for financing. An investment funded by IFC has to

meet the following PS‟s throughout the construction and operation phases of the project.

The Performance Standards consist of the following:

Performance Standard 1 (PS1): Assessment and Management of Environmental and Social

Risks and Impacts

Performance Standard 2 (PS 2): Labor and Working Conditions

Performance Standard 3 (PS 3): Resource Efficiency and Pollution Prevention

Performance Standard 4 (PS 4): Community Health, Safety, and Security

Performance Standard 5 (PS 5): Land Acquisition and Involuntary Resettlement

Performance Standard 6 (PS 6): Biodiversity Conservation and Sustainable Management of

Living Natural Resources

Page 11: Social- Environmental Impact Study Report

11

Performance Standard 7 (PS 7): Indigenous Peoples

Performance Standard 8 (PS 8): Cultural Heritage

The proposed Wind project is developed on Government revenue land. No acquisition of land

from Private land owners is involved. However, in order to assess impacts on the community

due to project related land acquisition and restrictions on land use, PS5 is included for the

project.

There are no indigenous groups or individuals present in the proposed project Site. There are

no significant cultural heritage assets in the proposed project area. Hence PS7 and PS8 are

excluded for this specific Project.

During the due course of construction and operation phase, Performance standards PS 1, PS2,

PS 3 and PS 4 are applicable for this specific project.

Therefore the Performance standards applicable for the proposed wind farm project are PS1,

PS2, PS3, PS4, PS5 and PS6.

There are no airports, air-force stations and other installations within zone of 10 km from the

nearest WTG.

The Land required for the proposed WTGs, access roads and Electrical substation will be

developed on the Government Revenue Land. The proposed project does not involve any

physical displacement (relocation or loss of shelter) or economic displacement (loss of assets or

access to assets that leads to loss of income sources or other means of livelihood).

The project area represents the characteristics that of degraded vegetation and dry and

semiarid landscape. The project area does not have any threatened, endangered or

conservation concerned faunal species. The area does not make part of any significant

breeding, roosting or feeding habitats of important and endangered species.

Moreover, the project area does not fall in vicinity of any important wildlife hotspot in the region.

The project site does not fall in the eco-sensitive/fragile zone identified by the State/Central

Government agencies. The area does not fall in any of the critical wildlife habitats identified by

any agencies till date. Hence impact on ecology is not anticipated.

Public consultation was undertaken to give opportunity to the affected people to express their

views. The outcome of the consultation was positive. The expectation level with regard to

community and individual benefits from the proposed project included consistent power supply

as there is frequent shutdown of power, employment opportunities, improvement of roads and

economic development.

Few of the settlements were observed in the neighboring area of the identified WTGs. It is

recommended to IRL to consider alternate feasible sites which are located close to such

settlement, in order to ensure that there will be no hardships due to community health and

safety issues during the due course of implementation and long run of the project.

As Corporate Social Activities it is recommended to IRL to support the activities such as

development and improvement of the educational and medical facilities in the area.

Minor impacts are expected on environmental quality of the surrounding area. The proposed

project will lead to employment generation, which will have a positive impact on the socio

Page 12: Social- Environmental Impact Study Report

12

economic environment. To the extent feasible, preference will be given to local population for

employment opportunities especially for unskilled activities. Proposed EMP will help in

mitigating the residual, social and environmental impacts.

Considering IFC principles, impacts have been assessed for relevant social and environmental

parameters. The negative impacts were found to be minimal in most of the cases.

Implementation of the mitigation measures and management plan would mitigate the negative

impacts. Based on this the project can be considered as Category B project.

Based on the above, it may be concluded that proposed project is eco-friendly and

environmentally sustainable in the long run. Proposed wind farm will not only help in reducing

the CO2 responsible for global warming but other gases and particulate emissions also, which

otherwise would be generated using conventional fossil fuel based power plants. Besides the

implementation of project will conserve, equivalent amount of fossil fuels and water as a natural

resource.

Page 13: Social- Environmental Impact Study Report

13

CHAPTER II

INTRODUCTION

2.1 INTRODUCTION

India witnesses high intensity winds in various regions due to the topographical diversity

in India. Rajasthan is one of the States which is blessed with high wind energy potential.

Efforts have been made to utilize this natural source of energy available free of cost for

wind power generation.

Centre for Wind Energy Technology (C-WET) has recently declared estimated wind

power potential at height of 80 m (above ground level) in India as 1,02,788 MW. The

gross wind potential in the state of Rajasthan is estimated as 5050 MW (source: As per

revised estimate by CWET dated December 2011). As on 30 July, 2011 Wind installed

capacity in the State of Rajasthan is 1643 MW.

2.2 PROJECT PROPONENT

Inox Renewable Limited (IRL) is part of Gujarat Fluro chemicals limited (GFL) is the

promoter of the proposed wind power project.

Currently GFL has installed capacity of ~70 MW in wind energy sector. By the end of May

2012 it is expected increase to 180 MW where the wind farms will be spread across in the

states of Rajasthan, Gujarat, Maharashtra and Tamil Nadu.

Present Proposal: IRL proposes to set up a 300 MW wind farm near Dangri Village,

Jaisalmer District, Rajasthan State. The wind farm consists of 150 WTGs each rated

capacity of 2000 kW. The proposed project will be operational by March 2013. This

includes 150 numbers of WTGs, access roads, transmission lines and substation.

2.3 THE PROJECT SITE

The proposed project site is located near Dangri village approximately 50 km (aerial

Distance) South East of Jaisalmer City of Rajasthan State. The proposed project site is

connected by road through National Highway NH -15. The nearest railway station is

Jaisalmer Railway station and nearest operational airport to Jaisalmer is Jodhpur Airport.

Figure II.1 indicates the location of the proposed project site with reference to India. The

proposed site is located between 26°26' 47.8"N & 26°37'33.3"N latitude and 71°17'

06.04"E & 71°34' 50.2"E longitude.

The WTGs are proposed to be located in the villages of Bhalabasti, Rajgarh, Baisanra,

Ola, Dangri, Malusar, Chhodiya, Ramsar, Laxmansar, Mahreri, Samel Nagar, Pabnasar,

Khodiyasar.

2.4 ENVIRONMENTAL JUSTIFICATION OF THE PROJECT

Wind energy projects are generally considered as green projects with insignificant impact

on the environment, which are reversible in nature and can be minimized by proper

Environmental management plan. As per MoEF EIA notification S.O.1533 dated 14th

September 2006 and its subsequent amendments, setting up of wind power project does

Page 14: Social- Environmental Impact Study Report

14

not require prior environmental clearance from MoEF or State Department of

Environment.

Wind energy is clean, zero emission and eco-friendly source of energy. This will reduce

the emission of CO2, the major greenhouse gas and other emissions like SO2, NOx,

PM10, PM2.5. The proposed project will not generate any solid or liquid effluents and

thereby the chances of land pollution or pollution of surface or ground water resources

are insignificant.

There are no forest land acquisition involved and thereby no disturbance to wildlife

habitat, flora and fauna. As there are no National parks, Sanctuaries, Wetlands or any

other ecologically sensitive areas in the vicinity of the project site or for that matter,

endangered or threatened bird nesting /breeding places in the vicinity of the site and

hence the project is not expected to have any negative impact in so far as any of the

foregoing aspects are considered.

The wind turbines pertaining to the project are predominantly being developed on

revenue land. There is no physical or economic displacement anticipated in the proposed

project. Hence, there is no rehabilitation & resettlement or loss of livelihood issues

involved.

The nearest airport is Jaisalmer Airport which is currently not operational. This is situated

more than 50 km from the proposed Wind Farm site. This will not pose any impact on air

safety, if it becomes operational in future. Also, Jaisalmer Air force station is situated

more than 50 Km towards North West of the proposed wind farm site. No Air base

installations, radar stations or airports are located within 10 km of the project site and

hence impact on air safety is not envisaged.

The International Financial Corporation (IFC) is institution that have developed the

“Performance Standards” in order to ensure that the project being financed by them are

developed in a manner that is socially responsible and reflect sound environmental

management practices. In India, wind power projects are categorized as green projects

and categorized as having low impact.

The development, construction and operation of the Wind Power project at Dangri,

Rajasthan will have site-specific, but limited, impacts on the bio-physical and social

environment of the Project area which the Environmental and Social Impact Assessment

(ESIA) studies undertaken has confirmed.

Page 15: Social- Environmental Impact Study Report

15

Figure II.1

Location Map Showing the Project site

Proposed Dangri Wind Farm Site

Page 16: Social- Environmental Impact Study Report

16

2.5 OBJECTIVE OF THE STUDY

a) Identify the social and environmental impacts due to the construction and operational phase of the wind project.

b) Review the regulatory framework that is relevant for the project including identifying the key environment and social legislations that get triggered by the project and their requirements.

c) Identify the significant social and environmental parameters & assess the baseline status of air, water, noise, soil, land, ecology, cultural heritage and socioeconomic aspects.

d) Environment and Social Impact Assessment in compliance with IFC performance standards

e) Social and environmental categorization of the project in accordance with IFC guidelines.

f) Developing Environmental Management Plan in accordance with applicable World Bank Group (WBG) Environment, Health and Safety (EHS) guidelines as applicable for the proposed Wind energy project

g) Preparation of Social and Environmental Impact Assessment Report

Page 17: Social- Environmental Impact Study Report

17

CHAPTER III

ENVIRONMENTAL AND SOCIAL REGULATORY FRAMEWORK

3.1. ENVIRONMENTAL REGULATORY FRAMEWORK

This section outlines the regulatory system for prevention and control of

environmental pollution and the pollution control standards applicable in India. In

1980, Government of India constituted Department of Environment for

coordinating programmes related to environment. Subsequently in 1985, full-

fledged Ministry of Environment and Forest (MoEF) was constituted which is the

apex administrative body in the country for regulating and ensuring

environmental protection. The key responsibilities of the MoEF are as under:

a) Environmental, Policy planning

b) Ensure effective implementation of legislation

c) Pollution Monitoring and Control

d) Survey and Conservation of Natural Resources

e) Eco Development and Biosphere Reserve Programme

f) Management of Forests and Conservation and Wildlife

g) Environment Clearance for Industrial and Development Projects

h) Environmental Education, Awareness and Information

i) Co-ordination with concerned agencies at National and International

Levels

India‟s environmental regulatory framework is based on a system of shared

central government/state pollution control administration. Central Pollution control

board (CPCB) plays an advisory role to the Government and State Pollution

Control Boards (SPCB) in matters relating to the implementation and

enforcement of the Air, Water and Environmental Acts. In this sense, the CPCB

through various SPCBs is responsible for the enforcement and implementation of

pollution control legislation and discharge standards. In addition, the EIA review

committee formed by the EIA division consists of a representative from the

CPCB.

The SPCB is responsible for issuing consent to operate to all proposed industries

within the state. This is as per the requirements of the Water Act and Air Rules.

This consent identifies the pollutant discharge standards applicable to the

proposed industry.

The MoEF/State Level Environment Impact Assessment Authority is responsible

for issuing environmental clearances for the certain categories of projects as

mentioned in MoEF notification SO1533 dated 14th Sept 06 and its subsequent

amendments till date. Wind energy projects are not listed in any category of the

MoEF notification SO 1533. So for this wind energy project, environmental

clearance is not required.

Page 18: Social- Environmental Impact Study Report

18

3.1.1 THE ENVIRONMENT (PROTECTION) ACT, 1986

The Environment (Protection) Act is an umbrella act designed to provide a

framework for the coordination of central and state authorities established under

Water and Air Act. The Environment (Protection) Act, 1986 is established by the

GOI to fulfill its commitment to protect and improve the human environment. It is

applicable to the entire country. From time to time the central government issues

notifications under the EPA Act 1986 for the protection of ecologically-sensitive

areas or issues guidelines for matters under the EPA.

It empowers the Central Government to take necessary measures for the

purpose of protecting and improving environmental quality and preventing,

controlling and abating environmental pollution. An important power of the

Central Government includes laying down standards for environmental quality

and emission/ discharge of environmental pollution from various sources. This

power defines procedures and establishes safeguards for handling of hazardous

substances, and establishes rules to regulate environmental pollution.

3.1.2 FOREST (CONSERVATION) RULES, 2003

These rules came into existence on 10th January 2003. Rules framed to carry

out the provisions of the Forest (Conservation) Act, 1980. As per these rules,

every user agency, who wants to use any forest land for non-forest purposes

shall make his proposal in the appropriate Form appended to these rules, i.e.

Form „A‟ for proposals seeking first time approval under the Act and Form „B‟ for

proposals seeking renewal of leases where approval of the Central Government

under the Act. FC Rules, 2003 prescribe specific time limits for processing the

cases related with forest clearance.

However proposed land for the wind energy project is not falling under any

reserved forest.

3.1.3 EIA NOTIFICATION S.O 1533, DATED 14.09.2006

MoEF has stipulated new Environment Impact Assessment Notification of 14th

September 2006 (EIA 2006) replacing the EIA Notification of 27th January 1994

and its various amendments. EIA notification 2006 has further undergone

revisions in the year 2009 and 2011 with certain amendments.

All new projects or activities listed in the Schedule I of EIA notification 2006,

Expansion and modernization of existing projects and any change in product -

mix in an existing manufacturing shall require prior environmental clearance from

the concerned regulatory authority.

As per this notification the wind farm projects are not included in any of the

categorization listed in Schedule I.

Hence, set up of wind power project does not require environmental clearance

from MoEF or State Department of Environment and Forest.

3.1.4 THE WATER (PREVENTION & CONTROL OF POLLUTION) ACT, 1974 (WATER ACT)

This Act represented India‟s first attempts to comprehensively deal with

environmental issues. The purpose of this act is to prevent and control water

pollution and to maintain or restore the quality of water.

Page 19: Social- Environmental Impact Study Report

19

In order to achieve its goals this act empowers the CPCB and SPCB and defines

their functions.

This Act requires industries, local bodies and agencies engaged in any trade to

obtain consent from the SPCB for discharge of effluent into water bodies. The

SPCBs have the authority to enforce this Act, if any projects discharge effluent in

water bodies, land or sea.

3.1.5 THE AIR (PREVENTION AND CONTROL OF POLLUTION) ACT, 1981

The purpose of this act is to prevent, and control air pollution including noise

pollution and preserve air quality.

In order to achieve its goals this act empowers the CPCB and SPCB and defines

their functions. An important function of the CPCB is to establish Environmental

standards.

This Act requires industries, local bodies and agencies engaged in any trade to

obtain consent from the State Pollution Control Board (SPCB) for discharge of

emissions into air. The SPCBs have the authority to enforce this Act.

Separate Noise regulations for DG set of various capacities were introduced in

2002 vide notification of MoEF of 17 May 2002 under the Environmental

(Protection) Second Amendment Rules 2002.

This required that all DG sets should be provided with exhaust muffler with

insertion loss of minimum 25 dB(A). All DG sets manufactured on or after 1 July

2003 have to comply with these regulations.

Wind energy projects involve construction activities like excavation, drilling,

concreting and access roads, which cause temporary fugitive dust emissions.

However, it may be noted that the operation of wind projects do not cause any

air, water and/or soil pollution.

3.1.6 WILD LIFE ACT 1972

The Government of India enacted Wild Life (Protection) Act 1972 with the

objective of effectively protecting the wild life of this country and to control

poaching, smuggling and illegal trade in wildlife and its derivatives. The Act was

amended in January 2003 and punishment and penalty for offences under the

Act have been made more stringent. The Ministry has proposed further

amendments in the law by introducing more rigid measures to strengthen the Act.

The objective is to provide protection to the listed endangered flora and fauna

and ecologically important protected areas.

3.2. SOCIAL REGULATORY FRAMEWORK

While all the environmental clearances are governed by one or the other

Act/policy/rule of the central or state government, a majority of social „regulations‟

remain untied to any law and are governed more by social obligations coming

under the realm of constitutional provisions of fundamental rights.

However, it may also be noted that the laws pertaining to environmental

clearances also have many aspects, which primarily affect the human being and

their social environment, and hence the consideration for social factors gets

included there. Taking the social regulations further, the constitution marks some

Page 20: Social- Environmental Impact Study Report

20

mandatory and some prohibitory regulations pertaining to the weaker and

vulnerable section of the society (women, children, Scheduled Caste/Scheduled

Tribes/Other Backward Class, tribal population etc.) that basically safeguards

their rights to a dignified living, by ensuring the minimums. For this the

constitution entrusts various responsibilities on the state government and also

delegates powers to the local bodies under the decentralized administration. The

decentralization empowers local bodies primarily in rural areas to put across their

concerns, raise their voice against injustice, plan and instrument their own

development.

The government also takes various steps to develop the backward and

vulnerable section of the society through various development schemes. To

ensure that the benefits of these schemes reach the right target and to make the

process transparent government has instituted Right to Information Act (RTI),

under which information on any aspect of institutional functioning (records,

contracts, plans, budgets, circulars, logbooks etc) can be sought by the general

citizen of the country.

3.2.1 LAND REQUIREMENT/ DIVERSION

Land acquisition in India is covered by a national law, Land Acquisition Act (LAA)

1894 and its subsequent amendments. The LAA allows for land acquisition in the

national interest to be carried out by the respective states, in accordance with its

provisions. The Act lays down procedures for acquisition of land, including

notification, payment for damages, hearing of objections, declaration of the

intended acquisition, enquiry into measurement, values and claims and award by

the competent authority and finally taking possession of the land. The key

features include:

Preliminary notification for land proposed for acquisition;

Clearing of objection within 30 days of the notification and the provision for

hearing of all objections;

Declaration of intended acquisition award;

Reference to court if award is not accepted and hearing in court;

Apportionment of compensation and dispute settlement regarding the

same;

Payment of compensation for land value, trees and structures including

30% solatium and 12% p.a. interest for delayed payment;

The wind farm would also require permission and consent from local panchayat,

relevant planning authority and private parties for expansion and strengthening of

existing village roads.

The land required for the proposed project fall under Government Revenue land.

3.2.2 RESETTLEMENT AND REHABILITATION

The proposed wind farm does not envisage any displacement of people or any

particular community. However, for any future reference it must be noted that:

No central law or Act governs resettlement & rehabilitation in India.

The National Policy (2003) is in the process of being amended again in

order to address the key issues that came out of the implementation of the

Page 21: Social- Environmental Impact Study Report

21

2003 policy. It is more progressive in its approach. The key features of the

2006 policy are:

It includes displacement due to land acquisition;

The minimum number of people being displaced to trigger the

policy are 400 in plains, and 200 or more in the hills, tribal areas

and DDP blocks;

It is mandatory for the Requiring Body to prepare a Social Impact

Assessment (SIA);

SIAs shall go through a clearance process similar to the

Environmental Clearance process, and shall be linked to the EIA.

Public hearings shall include social impact issues and, where the

EC process does not require a Public Hearing, a separate hearing

for the SIA shall be held;

Draft resettlement and rehabilitation plans need to be discussed in

the gram sabha in rural areas and through public hearings in

urban and rural areas without gram sabhas; and

Provision of shares to the affected family as a part of the

rehabilitation grant, if the Requiring Body is a corporate

organization/company

The Indian Constitution dictates that resettlement and

rehabilitation is the responsibility of individual union states.

3.2.3 SCHEDULED TRIBE RELATED POLICIES AND LEGISLATIONS

3.2.3.1 CONSTITUTIONAL PROVISIONS PROTECTING TRIBES AND EXTENDING SPECIAL STATUS

The Constitution of India identifies certain groups/communities as tribal groups

and lays out special provisions for such group with the objective of promoting and

safeguarding the social, educational and economic interests of the Schedules

Tribes. The President is empowered to specify, after consultations with the

Governor of a state “tribes or tribal communities” to be listed under the

Schedules tribe list. In conjunction with this certain areas have been declared as

“Scheduled Areas” in the constitution. Regulations are framed under the Fifth

schedule of the Constitution to prevent the exploitation of tribals by non-tribals

and alienation of agricultural land of tribals being passed on to non-tribals.

3.2.3.2 THE SCHEDULED TRIBES AND OTHER TRADITIONAL FOREST DWELLERS (RECOGNITION OF FOREST RIGHTS) ACT, 2006 AND FOREST RULES 2007

This recently promulgated act is to recognize and vest forest rights and

occupation in forest land in forest dwelling Scheduled Tribes and other traditional

forest dwellers (TFD) who have been residing in such forests for generations but

whose rights could not be recorded. It also provides a framework for recording

forest rights and the nature of evidence required for such recognition and vesting

in respect to forest land. The rights included are:

rights to hold and live in forest land under individual or common occupation

for habitation or self cultivation for livelihood by STs /other TFD;

community rights such as those of non timber forest produce, grazing, fuel

wood etc

Page 22: Social- Environmental Impact Study Report

22

rights of ownership, access to collect, use and dispose of minor forest

produce which has been traditionally collected within or outside village

boundaries;

other community rights of uses or entitlements such as fish and other

products of water bodies, grazing and traditional access to natural

resources of nomadic /pastoralist communities;

rights in or over disputed lands;

rights for conversion of Pattas or leases or grants issues by any local

authority or any State Government on forest land to titles;

rights of settlement and conversion of all forest villages, old habitation,

unsurveyed villages and other villages into revenue villages;

rights to protect, regenerate or conserve or manage any community forest

resource;

rights of access to biodiversity and community rights to intellectual property

and traditional knowledge;

any other traditional rights customarily enjoyed by STs /TFDs other than

hunting of wild animals and rights to in situ rehabilitation including

alternative land in cases where ST and TFDs have been illegally evicted or

displaced from forest.

The Gram sabhas and the panchayats have been accorded with powers to

decide upon matters of traditional and customary rights under the forest rules

and institutional mechanisms have been put in place at the district, state and

central level to decide upon community/ individual rights and ownerships.

There is no physical or economic displacement of any schedule tribe community

involved due to proposed project.

3.2.4 LABOUR LAWS

The construction and full-fledged operation of the proposed wind farm will involve

short term/long term contractual hiring of unskilled, semiskilled and skilled

labourers and some technical staff. This will trigger the legislations governing the

labour laws, wages and compensation, working condition and worker welfare etc.

Some of the key legislations and regulations that govern labour issues in India

are;

The Payment of Wages Act, 1936

The Minimum Wages Act, 1948

The Factories Act, 1948

Workmen's Compensation Act

The Contract Labour (Regulation & Abolition) Act, 1970

The Equal Remuneration Act, 1976

3.3 IFC PERFORMANCE STANDARDS 2012

IFC strives for positive development outcomes in the activities it supports in

developing countries. These activities includes

I. investment financed directly by IFC

Page 23: Social- Environmental Impact Study Report

23

II. investments implemented through financial intermediaries (FIs) or managed by IFC‟s Asset Management Company or any other IFC subsidiary, as well as investments funded in part or in whole by donors; and

III. advisory services.

IFC believes that an important component of achieving positive development

outcomes is the environmental and social sustainability of these activities, which

IFC pursues and expects to achieve through the application of this Policy on

Environmental and Social Sustainability (the Sustainability Policy or the Policy),

and a comprehensive set of environmental and social Performance Standards.

The Performance Standards consist of the following:

i. Performance Standard 1: Assessment and Management of

Environmental and Social Risks and Impacts

ii. Performance Standard 2: Labor and Working Conditions

iii. Performance Standard 3: Resource Efficiency and Pollution Prevention

iv. Performance Standard 4: Community Health, Safety, and

v. Performance Standard 5: Land Acquisition and Involuntary

Resettlement

vi. Performance Standard 6: Biodiversity Conservation and Sustainable

Management of Living Natural Resources

vii. Performance Standard 7: Indigenous Peoples

viii. Performance Standard 8: Cultural Heritage

By doing so, negative impacts of the project, if any, on affected ecosystems and

local communities are avoided wherever possible, and if these impacts are

unavoidable, they may be reduced, mitigated and/or compensated as

appropriate.

Page 24: Social- Environmental Impact Study Report

24

CHAPTER IV

PROJECT DESCRIPTION

4.1 INTRODUCTION

IRL proposes to set up a 300 MW wind farm near Dangri Village, Jaisalmer District, Rajasthan State. The wind farm consists of 150 WTGs each rated capacity of 2000 kW. The proposed project is scheduled to commission by March 2013, which includes 150 numbers of WTGs, access roads, transmission lines and substation.

4.2 DESCRIPTION OF THE PROJECT DEVELOPMENT

The proposed wind energy development comprise of construction and operation

of 150 wind turbines, mounted at an operating (hub) height of 80m together with

associated infrastructure, including foundations, access roads, connection

cables, substations (including control room), transmission line and temporary

storage yard. Arial view of approximate site boundary is shown in the Figure

IV.1.

4.2.1 Land requirement

The proposed wind farm project will be developed in the Bhalabasti, Rajgarh,

Baisanra, Ola, Dangri, Malusar, Chhodiya, Ramsar, Laxmansar, Mahreri, Samel

Nagar, Pabnasar, Khodiyasar. The project will be developed over revenue land.

Wind Turbines locations are spread in parcels of land over an area of 20 km2. In

the present report the study area considered is the area within the extreme Wind

Turbine locations of the proposed project and the peripheral area of 1 km

distance which covers an area of about 20 km2 as shown in Figure IV.1.

However the project area involves only the parcel of land where the WTGs are

sited, land required for substation and access roads.

IRL has identified 210 locations, out of which 150 locations will be finalized

during the detailed engineering. The identified geographic co-ordinate location of

210 Wind Turbines is listed in Appendix -1. The micrositing diagram is given in

the Appendix -2.

At present IRL is in possession of 32 locations (64 MW) where project

development activity (as mentioned in the next paragraph is going on and other

118 locations to complete 300 MW are identified and are currently under

acquisition. The identified parcels of wind turbine sites are not used for grazing,

farming or planting, nor there exist settlements. Informal settlers are found in the

neighboring area of few of the identified wind turbine locations. These settlers are

from local villages that have moved to these areas for practicing farming and

livestock rearing. In addition to above, the identified settlements are not coming

under land to be acquired for this project. So resettlement and rehabilitation is

not expected in this project.

Page 25: Social- Environmental Impact Study Report

25

Figure IV.1

Aerial View showing the approximate boundary of the project site

Page 26: Social- Environmental Impact Study Report

26

4.2.2 DETAILED PROJECT ACTIVITIES

Following development activities will be carried out for 300 MW wind power

project:

Setting up of 150 wind turbine generator units

Concrete foundations (approximately 15m x 15m x 2m) to support the

turbine towers.

Aboveground electrical distribution cabling between turbines

One substation on the site to receive generated power (approximate size

160m x 100m) which will be initially developed for 100 MW capacity and

will be upgraded for 300 MW capacity

Power lines from WTGs to 220 KV pooling substation (Approximate

length per turbine is 1 km)

An access road to the site from the main road/s within the area

Internal access road to each wind turbine to link the turbines on site

(approximately 3-6 m in width); and

A Storage yard for storage and maintenance.

4.2.3.1 CONSTRUCTION PHASE

Wind energy development project of 300 MW will take 10 months depending on

weather and ground conditions encountered. Construction and commissioning

schedule for completion of 300 MW capacities is shown in Figure IV.2. and is

expected to be commissioned by March 2013.

Page 27: Social- Environmental Impact Study Report

27

Figure IV.2

Construction and Commissioning Schedule for 300 MW Capacity which is

expected to be commissioned by March 2013

The activities during construction phase include:

i. Undertake site investigations to determine foundations conditions;

ii. Carry out road improvements along the agreed off-site access route to

the site as required;

iii. Make improvements to access route entrance;

iv. Prepare and establish temporary construction compound;

v. Construct access road, crane hard standings, field gates and temporary

fencing;

vi. Excavate and construct the turbine foundations;

vii. Construct the substation and grid connection;

viii. Erect the turbines;

ix. Commissioning the turbines; and

x. Carry out land reinstatement, remove temporary accommodation,

reinstate temporary construction compound and crane hard standings

and clear the site.

For an ideal size of approximate 100 MW wind farm development around 100-

125 skilled & 450-500 unskilled manpower is required.During the construction

works there will be a varied man power (skilled and unskilled) of between 50-60

people on site at any one time. In the category of unskilled man power 40 to 50%

will be outsourced from local contractors or nearby villages where possible.

Page 28: Social- Environmental Impact Study Report

28

Since the proposed 300 MW wind development will be developed in the phases

over a period of 10 months, the manpower for 300 MW will not vary as specified

above.

Vehicle movements will vary; involve the use of specialized heavy transport

trailer trucks, heavy lifting cranes. However, the following is an indication of the

material that will be used and the types/numbers of vehicles likely to be required:

Each turbine would be delivered on approximately ten vehicles

comprising the blades (3 vehicles), the hub (1 vehicle), the nacelle (1

vehicle), the tower (4 vehicles for 4 steel tower sections) and electrical &

other accessories (1 Vehicle).

Each turbine foundation would comprise approximately 360 m3 of

concrete, necessitating between 60 deliveries from batch plant to

individual WTGs (based on 6 m3 batches of concrete). Up to 250-300 m3

of concrete will be required for the substation foundation, necessitating a

further 40 to 50 concrete deliveries.

The reinforcing for each foundation would comprise approximately 90-100

tonnes of steel bar which would be delivered on 4-5 vehicles (based on

20 tonne loads).

All stone for access roads is likely to be produced on-site from foundation

excavation and borrow pits avoiding significant numbers of vehicles

movement on public highway.

The erection of each turbine and tower will require maximum two mobile

cranes even if the activity will be carried out as a continuous operation.

Construction plants such as excavators, bulldozers etc., would be

transported to and from site on low loaders.

The likely number of vehicles required per month during the construction phase

based on the following assumption is given in the Table IV.1.

Assumptions:

Assuming 16 Turbines will be erected per month.

At a time 6 turbines will be under construction hence 6

construction equipments will be there at site at time

Construction machinery and erection equipments will be used

from site to site

Generally, 1 crane is required which consists of package of 50MT,

100MT and 450MT cranes.

Page 29: Social- Environmental Impact Study Report

29

Table IV.1

Vehicular Requirement on Monthly Basis

Activity Type of

Vehicle

Number per

Month

Route or

Path

A. Supply of Material

Supply of WTG Component

at Storage Yard of Project

Site

Truck/

Trailers

10 X 16 = 160 From National

Highway and

Local road to

Storage Yard

1 and 1

Material required for Civil

Works

Truck/

Trailers

64 X 16 = 1024 From National

Highway and

Local road to

Batching

Plant 1 and 2

B. WTGs Foundation and Other Civil Activities

Foundation of WTGs and

Related Civil Works

Excavator 6 From

Batching

Plant to

Individual

WTGS

Bull Dozer 6

Concrete

Mixer

6

C. Erection of WTGs

Transfer of Material from

Storage yard to WTGs

locations

Trailers 6 From storage

yard to WTGs

Locations

Erection of WTGs 50T, 100T,

200T & 450T

Crane

6 From storage

yard to WTGs

locations

About 1184 number of vehicles per month would be required for material

transfer and these vehicles will be using the route through national

highway and local roads upto storage yard. Figure IV.3 represents routes

likely to be used at the project site for transportation of the material upto

the storage yard/ batch reactor.

While from storage yard and batching plant to WTGs locations, total

number vehicles per month would be around 84 numbers. Additional

traffic is required for the delivery of tools, temporary site huts etc. and

vehicles that would be on site at any one time being used by site

personnel. In total additional site traffic would require no more than 100

vehicles per month from storage yard to WTGs locations.

Page 30: Social- Environmental Impact Study Report

30

Figure IV.3

Project Site Connectivity by Road

4.2.3.2 OPERATION PHASE

As the proposed wind farm project will be developed over government revenue

land on lease, IRL would have rights for access etc, in order to carry out

operation and maintenance works. Permanent fencing of the complete

development, individual turbines, access roads etc would not be required.

A wind energy development operates without the need for round the clock on-

site supervision. However, during the normal working week a team of 8 to 10 site

technicians, travelling by van, will nearly always be on-site to carry out

preventive and corrective maintenance works.

Most preventive and corrective maintenance work would not normally involve the

use of any large machinery or specialist vehicles. However, in some

circumstances, cranes and other specialist may need to visit the site when, for

example, large turbine components need to be repaired or replaced.

4.2.3.3 DECOMMISSIONING PHASE

Generally, The lifecycle of the wind power project is expected from 20-25 years

and may be longer. At the end of the lifecycle, further advances in technology

may justify the replacement of critical components to modernize or

decommissioned.

Page 31: Social- Environmental Impact Study Report

31

De-commissioning of the wind farm would require de-installation and removal of

all physical components and machinery from the site. The access roads would

remain, if the landowners so desired. The gathering-up lines, sub-station and

control building would be removed. Concrete turbine pads and building

foundations will be removed to a reasonalbe depth and re-claimed, unless the

landowner wished to use them as they are. The equipment used for the de-

construction would be essentially the same as for the construction e.g. heavy

lifting and transport equipment, earth moving equipment etc.

4.2.4 EQUIPMENT/ PROJECT COST

The estimated project cost is approximately for the proposed wind farm project is

approximately USD 342 million.

4.2.5 PROJECT TECHNOLOGY

4.2.5.1 Wind Turbine Generator (WTG)

The technical specifications of the WT 2000 DF are as follows:

Rated power: 2000kW

Cut- in wind speed: 3 m/s

Rated wind speed: 11.5 m/s

Cut-out wind speed: 20 m/s

Survival Wind speed: 52.5 m/s

Hub Height: 80 m

Rotor Speed: 15.9 RPM

Blade material: Epoxy Glass fibre

4.2.5.2 Technology

Rotor Blades: IWL WT 2000 DF consists of a three bladed upwind rotor of 93 m

diameter. Its rotational speed is controlled by blade pitch control. Pitch control

helps in lowering the peak loads during high windy conditions.

Asynchronous Generator: The wind turbines are equipped with a double fed

induction generator.

Drive System: The patented integral drive train incorporates the rotor shaft and

gearbox as a single unit. The gear box has forced lubrication system.

Active pitch: WT 2000 DF active pitch is driven by three separate pitch drives for

each of the rotor blades. Active pitch system is used to change the blade angle

so that the angle of attack changes and the aerodynamic efficiency is altered

depending on the speed of wind. In the event of a fault, the pitch motor is

powered by and ultra capacitor system and can therefore still control the pitch

and bring the WTG to safety.

Safety system:

Some of the Safety system designed for the WTGs includes

Page 32: Social- Environmental Impact Study Report

32

Aerodynamic braking using pitch system to protect the WTG from

adverse wind forces

A mechanical disc brake is mounted on the high speed shaft of the gear

box and hydraulically operated using intelligent braking system which

controls the braking sequence.

The rotor lock drive at the input shaft enables the drive train to be

mechanically locked during maintenance.

Control and Communication: The WTG status can be monitored and checked on

the display in the nacelle cabinet. Advanced remote and optical communication is

used for transmitting the data to central monitoring points.

The view of IWL WT 2000 DF make wind turbine generator is shown in the Figure IV.4

Figure IV.4

View of IWL WT 2000 DF Wind Turbine Generator

4.2.6 POWER EVACUATION

The planned capacity of the proposed project is 300 MW from 150 number of

IWL WTG with rated capacity of 2000 kW each.

Power Generated from Dangri will be evacuated from Akal GSS operated &

maintained by RVPNL. Akal GSS is around 47 KM far from pooling Substation

built at site. Company has already received NOC from RVPNL for power

evacuation. Pooling station will be initially developed for 100 MW capacity and

will be upgraded for 300 MW capacity as the project progress. Detailed power

evacuation is shown in Figure IV.5.

Page 33: Social- Environmental Impact Study Report

33

Figure IV.5

4.3 CDM ARRANGMENT

The Kyoto Protocol to mitigate climate change has resulted in creating an

International carbon market which has grown strongly over the years. India, as

an Annexure 2 signatory of the Kyoto Protocol, is entitled to benefit from the

Clean Development Mechanism (CDM). This project may be eligible to achieve

accreditation and receive Carbon Emission Reduction Certifications (CERs). The

project is expected to satisfy the additionality requirement, which may qualify as

an eligible project for CDM purposes. However, this additionality is required to be

proven through an appropriate study and validated by designated validators.

Once additionally of the project is proven the same may receive approval from

CDM authority for registration with UNFCC and issuing CERs.

Page 34: Social- Environmental Impact Study Report

34

CHAPTER V

BASELINE ENVIRONMENTAL CONDITION

5.1. INTRODUCTION

In order to predict anticipated impacts due to proposed wind energy project

during construction and operational phase, it is necessary to obtain baseline

information of the environment as it exists, which would serve as a datum. The

interaction of baseline environment and the anticipated impacts are the basis for

developing the environmental management plan relating to the activities of the

proposed project.

5.2. BASELINE DATA

The baseline environmental and social quality status was assessed during March

2012 through field studies within the study area. The wind turbine generators are

spread in parcels of land over a large area. For baseline collection, the area

within the extreme Wind Turbine location of the proposed project and peripheral

area of 1 km distance is considered as study area. A study area is approximately

20 km2 which covers Dangri, Rajgarh, Mehreri, Chhodiya, Laxmansar, Ramsar,

Bhasana and Bahla Basti villages.

A general reconnaissance survey of the study area was done before the

selection of sites for environmental monitoring. Monitoring sites were considered

based on the aspects such as accessibility to the sampling sites, topography and

terrain of the study area, major habitation, population, historically important

places and location of sensitive areas. Some of the recently generated data from

secondary sources were also collected and used as baseline information.

The baseline status of environmental quality represents the background

environmental conditions of various environmental components such as

meteorology, air, noise, soil, water, biological and socioeconomic status of the

study area during study period. The baseline status serves as a basis for

identification and prediction of the impact. Satellite view of the project site is

shown in Figure V.1.

5.3. REGIONAL CLIMATOLOGY

Jaisalmer is situated amid Thar Desert and experience less rainfall though

western disturbance during the monsoon. Jaisalmer have extreme temperature

range. It has very low temperature at night and typical of arid desert climate. The

air contains little moisture & therefore holds little heat. As soon as the sun sets

the area cools quickly, cloudless skies increase the release of heat at night.

The month of May is the hottest with a mean daily maximum temperature of

41.5oC and a mean daily minimum temperature of 25.2 oC. January is the coldest

month of the year with a mean daily maximum temperature of 23.6 oC and a

mean daily minimum temperature of 7.1 oC.

Page 35: Social- Environmental Impact Study Report

35

The nearest meteorological station is in Jaisalmer, which is approximately 50 km

away from the nearest WTG location. Yearly wind-rose diagram based on long

term climatologically table by IMD is shown in Figure V.2

The summary of the micro-meteorology of the region is given below in Table V.1.

Table V.1.

Summary of the Annual Micrometeorology of the Region

S. No.

Parameter Annual

1 Temperature Max. 33.9 ˚C

2 Temperature Min. 18.6 ˚C

3 Relative Humidity 60%

4 Annual Rainfall 200.1 mm

5 Annually wind speed 12.6 kmph

Source: IMD Climatalogical Table (1950 -1980), GOI

5.4. SITE CLIMATOLOGY

Meteorological station was established at the proposed project site near Dangri

village, Jaisalmer district, Rajasthan in March 2012 to record various

meteorological parameters. Meteorological data was recorded on a hourly basis

to understand wind pattern, temperature variation and relative humidity.

Percentage frequencies of wind in 8 directions have been computed from the

recorded data and windrose was plotted for a study period from19th March to 26th

March 2012. The windrose diagram is given in Figure V.3

5.4.1 WIND PATTERN DURING STUDY PERIOD

The predominant wind directions during the study period was from the South to

North accounting to about 18% of the total time with calm wind less than 2.0

m/sec. The Figure V.3 represents the wind pattern of the study area based on

the data collected from 19th March to 26th March 2012. Maximum and minimum

wind speeds, recorded during the study period were 7.78 m/sec and 1.61 m/sec

respectively.

The nearest metrological station is in Jaisalmer which is nearly 50 km away from

the site. Yearly wind rose diagram based on long term climatologically table by

IMD is shown in Figure V.2 and a site specific wind rose is illustrated in Figure

V.3.

Page 36: Social- Environmental Impact Study Report

36

Figure V.1

Satellite view of the Project Site

Page 37: Social- Environmental Impact Study Report

37

Figure V.2

Yearly (20 years) Wind Rose Diagram for Jaisalmer IMD Station

Page 38: Social- Environmental Impact Study Report

38

Figure V.3

Wind Rose Diagram of Project Site for March 2012

5.4.2 HOURLY AVERAGE TEMPERATURE VARIATION DURING STUDY PERIOD

The recorded data during the study indicates that temperature at site varies between maximum of 40.2°C and a minimum of 24.5°C. Hourly temperature variation at project site is shown in Figure V.4.

Figure V.4

Hourly Temperature Variation at Project Site

Page 39: Social- Environmental Impact Study Report

39

5.4.3 HOURLY AVERAGE RELATIVE HUMIDITY DURING STUDY PERIOD

Recorded data during the study indicates that the relative humidity at site varies between a maximum of 54.5% and a minimum of 10.2%. Hourly RH variations during study period at the project site are shown in Figure V.5.

Figure V.5

Hourly Humidity Variation at Project Site

There was no rainfall recorded during the study period. Summary of meteorological data collected from project site is shown in Table V.2.

Table V.2

Summary of Meteorological Data at the Project Site

Sr. No.

Parameter Max. Value Average Min. Value

1 Wind speed, m/sec 7.78 1.61 0

2 Temperature, C 40.2 31.91 24.5

3 Relative Humidity, %

54.5 28.2 10.2

5.5. AMBIENT AIR ENVIRONMENT

Reconnaissance survey of the study area was carried out for selection of

sampling locations for Ambient Air Quality Monitoring Stations (AAQMS).

Sampling sites for ambient air, noise, soil and water quality monitoring stations

was finalized based on reconnaissance survey of the study area.

The existing Ambient Air Quality (AAQ) status has been monitored at four

locations for PM10, PM2.5, SO2, NOX and CO. Location map of monitoring stations

is shown in Appendix 3. Pre-calibrated high volume respirable dust samplers

have been used for monitoring of the existing AAQ status.

The selection of monitoring location, analysis and methodology used for the

monitoring was based on the procedures recommended by the National Ambient

Air Quality Standards (NAAQS) issued by CPCB / MoEF.

Page 40: Social- Environmental Impact Study Report

40

Ambient air quality was monitored at four representative locations. Results of the Ambient air quality for the period of 19th March 2012 to 25th March 2012 are given in Appendix-1. Summary of the ambient air quality data is shown in Table V.3.

Table V.3.

Summary of Ambient Air Quality Data

Location Date of

sampling

Ground Level Concentration (µg/m3)

PM10 PM2.5 SO2 NOx CO

Dangri Minimum 97 50 4.5 23.4 BDL

Maximum 115 63 5.8 28.1 BDL

Bhainsra Minimum 122 67 5.6 26.8 BDL

Maximum 134 71 6.1 30.2 BDL

Lakhmona Minimum 80 42 4.0 20.5 BDL

Maximum 96 54 4.2 23.6 BDL

Lakhmanser Minimum 64 37 4.0 21.4 BDL

Maximum 94 53 4.0 23.6 BDL

The analysis results shows that all the parameters are well within the NAAQ

standards for residential and rural areas. Out of the four villages, the highest

values for PM10 and PM2.5 are reported in Fategar village. The National Ambient

Air Quality Standard (NAAQS) prescribed by Central Pollution Control Borad

(CPCB) is given in Appendix 4.

5.6. NOISE ENVIRONMENT

In order to assess the noise levels, monitoring was carried out at four different

locations. Location map of monitoring stations is shown in Appendix 5. Sound

levels were recorded for 24 hours for the duration of fifteen minutes at hourly

intervals using precision noise level meter (LUTRON, Model SL 4001). Noise

levels recorded during the study period is given in Appendix-6.

Data recorded at each station were computed for equivalent noise levels for day-

equivalent and night-equivalent as shown in Table V.4.

Table V.4.

Equivalent Noise Levels (Leq) of the Study Area

S.No

Code of Noise

Monitoring Station

dB(A)

Location Day-

Equivalent Night-

Equivalent Day- Night Equivalent

1 N 1 Dangri 46.2 37.8 46.2

2 N 2 Bhainsra 46.8 39.0 46.8

3 N 3 Lakhmona 45.5 38.3 45.5

4 N 4 Lakhmanser 47.6 40.6 47.6

The monitored noise levels at all locations are found to be within the prescribed

limit of National Ambient Air Quality Standards (NAAQS) in respect of noise. The

Page 41: Social- Environmental Impact Study Report

41

NAAQS and IFC guidelines in respect of noise is given in Appendix 7 and

Appendix 8 respectively.

5.7. WATER ENVIRONMENT

Four ground water samples were collected for assessment of the physico-

chemical and bacteriological characteristics. Location map of monitoring stations

is shown in Appendix 9. Methodologies adopted for sampling and analysis were

according to the Bureau of Indian Standards (BIS) /American Public Health

Association (APHA) methods. Monitored ground water parameters are given in

the Appendix 10 and summmarised in th Table V.5.

Table V.5.

Ground Water Quality of the Study Area

pH 6.78- 7.86

Alkalinity (mg/l) 247.52-714

Chlorides (mg/l) 270-1359.58

Total dissolved solids (mg/l) 940-3020

Fluoride (mg/l) <0.1

Hardness (mg/l) 198-986.04

Total Coliform (MPN/100ml) 30-500

Iron (mg/l) 0.1-0.83

Other Heavy metal (mg/l) <0.5

Ground water quality is compared with the Drinking Water Standard of IS: 10500 and it is found that most of the water quality parameter are exceeding the permissible limits. Also the total coliform is found to be high at one location i.e. Laxmansar Village. This may be due to discharge of domestic sewage from the nearby area. There was no surface water observed in the study area.

5.8. LAND USE PATTERN OF STUDY AREA

Land use utilization pattern in study area i.e. surrounding villages as mentioned

earlier is shown in Table V.6.

Table V.6

Landuse Pattern of the study area

Sr.No. Land Class Area (ha)

1 Total Irrigated Area 16

2 Unirrigated Area 6821.07

3 Forest 67

4 Culturable waste (including gauchar and groves) 9158.72

5 Area not available for cultivation 2148

Total Land 18210.31 Source: Census data 2001

The statistical figures indicate 50 % of the area is culturable waste land (land

which has potential to cultivate, however these lands are not taken up for

cultivation. These lands are usually either fallow or covered with shrubs), 12% of

Page 42: Social- Environmental Impact Study Report

42

land is not available for cultivation and nearly 38% of land is unirrigated area.

Forest land and Irrigated area is found to be very less in this region. The

percentage wise break up of landuse pattern is given in Figure V.6.

Figure V.6

Landuse Pattern of study area

Source: Census data 2001

5.9. SOIL QUALITY

To assess the existing soil quality of the surrounding area, four representative

soil samples were collected from various locations within the surrounding areas

of the project site. Location map of monitoring stations is shown in Appendix 11.

Standard procedures were followed for sampling and analysis. Samples collected

were also analysed for physico-chemical characteristics. Results of the soil

quality are given in Appendix-12. Summary of the soil quality data is given in

Table V.7.

Table V.7.

Summary of the Soil Quality data of the study area

Parameter Minimum Maximum

Sand, % 69.5 94.4

Silt, % 1.4 28.5

Clay, % 2 4.2

Nitrogen, mg/gm 76.83 109.76

Phosphorus, mg/gm <4 7.12

Page 43: Social- Environmental Impact Study Report

43

Parameter Minimum Maximum

Potassium, mg/gm 70 300

pH (1:2.5 suspension at 270C) 8.47 9.69

5.10. HISTORICAL AND ARCHAEOLOGICAL PLACES

As per Archeological survey of India, and reconnaisance survey conducted,

there are no historical places, protected, conserved monuments within 10 km

radius of the project site.

5.11. SOCIO ECONOMIC ENVIRONMENT

A brief survey of the study area was conducted site reconnaissance survey to

address socio-economic conditions. Primary Census Abstract data of 2001 have

been used to develop the baseline socio-economic condition of the study area.

As mentioned earlier, there is no settlement in the project site identified for wind

energy development. During site visit, few informal settlers living in the

neighbouring of the identified WTG site location was observed. It was

understood during the consultation with these informal settlers that the parcel of

land identified for setting up of WTGs are not acquired or used by these informal

settlers. It was also understood that they are staying there from last 10-15 years

for farming and livestock rearing. However, they have also mentioned that

normally they have home in nearby villages and are staying for temporary basis

only. It was also found out that they are counted in demography pattern of

villages where they are permanently staying.

A social profile has been developed for the villages of Dangri, Rajgarh, Mehreri,

chhodiya, Laxmansar, and Bahla Basti which are located in the vicinity of the

proposed wind farm area and hence considered as the project influence area.

Total population of the surrounding area of the project site as per Census 2001 is

4982 with a sex ratio of 806 no. of females per 1000 males. Details of the

population in each Villages of study area is given in Appendix-13. Summary of

the population are given below in Table.V.8.

Table V.8

Summary of the Population for Study Area

Number of Households 810

Total population 4982

Male Population 2759

Female Population 2223

0-6 Age Group Persons 1204

Scheduled Caste Persons 417

Scheduled Tribe Persons 560

Source : Census 2001

Page 44: Social- Environmental Impact Study Report

44

5.11.1 LITERACY LEVEL AND EDUCATIONAL FACILITIES

As per census data 2001, the overall literacy rate in the study area is found to be

37%. The male literacy rate is found to be higher than the female literacy rate in

the study area. Graphical representation of literacy pattern is shown in Figure

V.7 below. Details of population and literacy level in the study area are given in

Appendix-14.

Figure V.7

Literacy Level of the Surrounding Area

Source: Census 2001 data

As per census data 2001, all the villages have primary school facility. Most of the

villages of study area have middle school facility within 10 km distance except for

Chhodiya Village.

5.11.2 AMENITIES

All villages in the vicinity of the study area were observed to have drinking water

facilities, in the form of wells, tanks, tubewells and hand pumps.

All villages are well connected by local roads. Approach road in most of the

villages are either by mud roads or by foot paths. Few of the villages also have

paved roads facility.

Medical facilities are poor in these villages. To avail the medical facilities villagers

have to go beyond 10 km distance. One Primary health sub centre is available in

Dangri village.

5.11.3 OCCUPATIONAL STRUCTURE

Only 45.76 % of the total population come under the working category which

include both main workers and marginal workers. Among the Main workers, 57 %

of the population are cultivators, 1 % of the population are agricultural laborers, 8

% of population are involved in the household industry and 34 % of population

are involved in other activities. Details of occupational structure of the villages

within the surrounding of the project area are given in Appendix-15.

Page 45: Social- Environmental Impact Study Report

45

Figure V.8

Occupational Structure

Majority of the population is involved in the agricultural activities which is major

source of income.

5.11.4 LIVESTOCK

The livestock population comprises mainly of cattle, sheep, goats, etc. Figure

V.9 shows a typical views of the livestock found in the study area. However, none

of the parcel of land identified for WTGs was used for grazing nor vegetation

was observed during site visit.

Figure V.9

Livestock Population in the Surrounding Area

5.12. BIOLOGICAL ENVIRONMENT

A reconnaissance survey of the study area was carried out during the study

period to establish the existing baseline ecological/ biological condition of the

study area. Secondary information about flora and fauna were also collected.

Page 46: Social- Environmental Impact Study Report

46

5.12.1 FLORA OF THE STUDY AREA

Data were collected on flora of the study area (20 km2). A total of 30 quadrates of

10 x 10 m2 were laid randomly in the study area. All the plant species present in

the quadrates were identified and recorded. The collected data was then

systematically analyzed to produce information on following parameters of flora:

1) species inventory in the project area and

2) species present in different life forms (i.e. grass, herb, shrub, tree).

The checklist of the vegetation in the project area are mentioned in Table V.9

Table V.9

Inventory of Flora in the Study area

No Species Life Form

1 Citrullus colocynthis Climber

2 Citrullus lanatus Climber

3 Coccinia grandis Climber

4 Cocculus pendulus Climber

5 Cucumis sp. Climber

6 Momordica dioica Climber

7 Mukia maderaspatana Climber

8 Pergularia daemia Climber

1 Aristida funiculata Grass

2 Blepharis sindica Grass

3 Cenchrus biflorus Grass

4 Cenchrus ciliaris Grass

5 Cenchrus prieurii Grass

6 Cenchrus setigerus Grass

7 Dactyloctenium aegyptium Grass

8 Dactyloctenium Scindicum Grass

9 Eleusine compressa Grass

10 Eragrostis ciliaris Grass

11 Lasiurus sindicus Grass

12 Maytenus emarginatus Grass

13 Melanocenchris jaquemontii Grass

14 Oropetium thomaeum Grass

15 Tragus roxburghii Grass

16 Aristida adescensionis Grass

17 Sorghum halepense Grass

18 Saccharum spontaneum Grass

1 Aerva javanica Herb

2 Aerva tomentosa Herb

Page 47: Social- Environmental Impact Study Report

47

No Species Life Form

3 Argemone mexicana Herb

4 Boerhavia diffusa Herb

5 Convolvulus microphyllous Herb

6 Crotolaria burhia Herb

7 Echinops echinatus Herb

8 Euphorbia granulata Herb

9 Euphorbia prostrata Herb

10 Farsetia hamiltonii Herb

11 Heliotropium rariflorum Herb

12 Indigofera cordifolia Herb

13 Indigofera linifolia Herb

14 Indigofera linnaei Herb

15 Lycium barbarum Herb

16 Tephrosia purpurea Herb

17 Tephrosia falciformis Herb

18 Tribulus rajasthanensis Herb

19 Tribulus terrestris Herb

1 Anogeissus pendula Shrub

2 Asparagus racemosus Shrub

3 Balanites aegyptiaca Shrub

4 Calligonum polygonoides Shrub

5 Calotropis procera Shrub

6 Capparis decidua Shrub

7 Carissa carandus Shrub

8 Clerodendrum multiflorum Shrub

9 Commiphora wightii Shrub

10 Euphorbia caudicifolia Shrub

11 Leptadenia pyrotechnica Shrub

12 Mimosa hamata Shrub

13 Simmondsia chinensis Shrub

1 Acacia Jacquemontii Tree

2 Acacia leucophloea Tree

3 Acacia senegal Tree

4 Acacia tortilis Tree

5 Albizia lebbeck Tree

6 Azadirachta indica Tree

7 Balanites roxburghii Tree

8 Prosopis cineraria Tree

9 Salvadora oleoides Tree

Page 48: Social- Environmental Impact Study Report

48

No Species Life Form

10 Salvadora persica Tree

11 Tecomella undulata Tree

Figure V.10

Vegetation of the Study Area

5.12.2 FAUNA OF THE STUDY AREA

Data were collected on fauna within project area boundaries. Inventory of fauna

in the study area is given in the Table V.9.

Reptiles: A walkthrough study was carried out to identify various reptiles and

their presence i.e. lizards, snakes etc. in the study areas. This was mainly

prepared through interview survey of the local people.

Birds: Birds, occupying higher trophic levels in the ecosystems, respond quickly

to the changes in the habitats and therefore serve as one of the best indicators

for evaluating the status of the eco-system. Baseline information was collected

on the occurrence and distribution of avian species and information on flight

directions and passage rates of birds through the project area. Data collected

during the field visit and information gathered from the secondary literature was

used for generating baseline status of birds for project area. Baseline status of

birds in the project area is detailed in the Appendix 16.

Mammals: Like birds, mammals are also occupying higher trophic levels in many

ecosystems and respond quickly to the changes in their habitats therefore, serve

as best indicators of the ecosystem health. Since the presence of mammalian

species is low affecting probability of their sightings, in the study area, it was

difficult to estimate their population using line transect method. More importantly,

it was difficult to accommodate the sightings of nocturnal and diurnal animals in

the study. Therefore, indices of presences and absence using indirect evidences

Page 49: Social- Environmental Impact Study Report

49

and signs such as footprints, dens, droppings, diggings, scrap marks, etc. is

considered in the project area.

The sites where likelihood or presence of animals such as shady trees,

waterholes, dense and undisturbed bushes etc. were surveyed intensively during

the survey in the study area. For faunal inventory, both direct sightings and

indirect evidences (like dung, scats, pellets, foot prints, nests, dens etc.) were

accounted for.

Table V.10

Inventory of fauna in the Study area

S. No.

Name of Species Evidence Type

Conservation Status as per

IWPA-1972 (Schedule I to

VI)

Conservation

Status as per IUCN

Scientific Name Common Name

Mammals

1 Herpestes edwardsi Common mongoose Seen Schedule-II Least Concern

2 Lepus nigricollis Indian Hare Seen Schedule-IV Least Concern

3 Canis aureus Indian Jackal Foot Prints Schedule-II Least Concern

4 Felis chaus Jungle cat Foot Prints Schedule-II Least Concern

5 Boselaphus tragocamelus Nilgai Seen Schedule-III

Least Concern

6 Sus scrofa Wild Pig Seen Schedule-III Least Concern

7 Rhinopoma microphyllum

Greater Mouse-tailed Bat Literature Schedule-III

Least Concern

8 Rhinopoma hardwickii Lesser Mouse-tailed Bat Literature Schedule-III Least Concern

9 Hemiechinus auritus Long eared Hedgehog Seen Schedule-III Least Concern

10 Gazella bennettii Chinkara Seen Schedule-I Least Concern

Reptiles

1 Echis carinatus Saw scaled Viper Interview Schedule-III Least Concern

2 Naja naja Indian Cobra Interview Schedule-II Least Concern

3 Bungarus caeruleus Common Krait Interview Schedule-III Least Concern

4 Eryx johni John Sand Boa Interview Schedule-III Least Concern

5 Eryx conicus Common Sand Boa Interview Schedule-III Least Concern

6 Ptyas mucosus Rat Snake Interview Schedule-II Least Concern

7 Natrix piscator Cheakered Keelback Interview Schedule-II Least Concern

8 Calotes versicolor Garden Lizard Seen Schedule-IV Least Concern

9 Agama minor Short tailed Agama Seen Schedule-IV Least Concern

Page 50: Social- Environmental Impact Study Report

50

S. No.

Name of Species Evidence Type

Conservation Status as per

IWPA-1972 (Schedule I to

VI)

Conservation

Status as per IUCN

Scientific Name Common Name

10 Mubuya carinata Common Skink Seen Schedule-IV Least Concern

11 Varanus bengalensis Monitor Lizard Interview Schedule-IV Least Concern

12 Vulpes vulpes Red Fox Interview Schedule-IV Least Concern

13 Uromastyx hardwickii. Spiny-tailed Lizard Interview Schedule-IV Least Concern

Birds

1 Accipiter badius Shikra Seen Schedule-IV Least Concern

2 Acridotheres tristis Common myna Seen Schedule-IV Least Concern

3 Actitis hypoleucos Common Sandpiper Seen Schedule-IV

Least Concern

4 Aegithina tiphia Common Iora Seen Schedule-IV Least Concern

5 Ammomanes phoenicurus Rufus tailed lark Seen Schedule-IV Least Concern

6 Anthus campestris Tawny Pipit Seen Schedule-IV Least Concern

7 Anthus similis Long-billed Pipit Seen Schedule-IV Least Concern

8 Apus affinis House Swift Seen Schedule-IV Least Concern

9 Aquila nipalensis Steppe Eagle Seen Schedule-IV Least Concern

10 Aquila rapax Tawny Eagle Seen Schedule-IV Least Concern

11 Athene brama Spotted Owlet Seen Schedule-IV Least Concern

12 Bulbulcus ibis Cattle egret Seen Schedule-IV Least Concern

13 Burhinus oedicnemus Eurasian Thick-knee Seen Schedule-IV

Least Concern

14 Butastur teesa White-eyed Buzzard Seen Schedule-IV

Least Concern

15 Buteo rufinus Long-Legged Buzzard Seen Schedule-IV

Least Concern

16 Calandrella brachydactyla Greater Short-toed lark Seen Schedule-IV

Least Concern

17 Caprimulgus europaeus Eurasian Nightjar Seen Schedule-IV Least Concern

18 Centropus sinensis Greater Coucal Seen Schedule-IV Least Concern

19 Circus macrourus Pallid Harrier Seen Schedule-IV Least Concern

20 Circus pygargus Montagu's Harrier Seen Schedule-IV Least Concern

21 Columba livia Blue rock pigeon Seen Schedule-IV Least Concern

22 Copsychus saularis Oriental magpie Seen Schedule-IV Least

Page 51: Social- Environmental Impact Study Report

51

S. No.

Name of Species Evidence Type

Conservation Status as per

IWPA-1972 (Schedule I to

VI)

Conservation

Status as per IUCN

Scientific Name Common Name

robin Concern

23 Coracias benghalensis Indian Roller Seen Schedule-IV Least Concern

24 Coracias garrulus European Roller Seen Schedule-IV Least Concern

25 Corax corax subcorax Common Raven Seen Schedule-IV Least Concern

26 Corvus splendens House crow Seen Schedule-V Least Concern

27 Dicrurus macrocercus Black drongo Seen Schedule-IV Least Concern

28 Eremopterix griseus) Ashy Crowned Sparrow Lark Seen Schedule-IV

Least Concern

29 Erythropygia galactotes Rufous-tailed Scrub-Robin, Seen Schedule-IV

Least Concern

30 Falco tinnunculus Common Kestrel Seen Schedule-IV Least Concern

31 Francolinus pondicerianus Grey francolin Seen Schedule-IV Least Concern

32 Galerida cristata Crested Lark Seen Schedule-IV Least Concern

33 Gyps bengalensis White-rumped Vulture Seen Schedule-IV

Least Concern

34 Gyps fulvus Eurasian Griffon Vulture Seen Schedule-IV

Least Concern

35 Halcyon smyrnensis White-Breasted kingfisher Seen Schedule-IV

Least Concern

36 Hieraaetus fasciatus Bonelli's Eagle Seen Schedule-IV Least Concern

37 Lanius meridionalis Southern Grey-Shrike Seen Schedule-IV

Least Concern

38 Lanius vittatus Bay-Backed Shrike Seen Schedule-IV Least Concern

39 Lonchura malabarica Indian silverbill Seen Schedule-IV Least Concern

40 Merops orientalis Green bee eater Seen Schedule-IV Least Concern

41 Merops superciliosus Blue-cheeked Bee-eater Seen Schedule-IV

Least Concern

42 Mirafra cantillans Singing Bushlark Seen Schedule-IV Least Concern

43 Motacilla flava Yellow Wagtail Seen Schedule-IV Least Concern

44 Muscicapa striata Spotted Flycatcher Seen Schedule-IV Least Concern

45 Neophron percnopterus Egyptian Vulture Seen Schedule-IV Least Concern

46 Oenanthe deserti Desert Wheatear Seen Schedule-IV Least Concern

47 Oenanthe isabellina Isabelline Wheatear Seen Schedule-IV Least Concern

48 Oenanthe picata Variable Wheatear Seen Schedule-IV Least

Page 52: Social- Environmental Impact Study Report

52

S. No.

Name of Species Evidence Type

Conservation Status as per

IWPA-1972 (Schedule I to

VI)

Conservation

Status as per IUCN

Scientific Name Common Name

opistholeuca Concern

49 Passer domesticus House sparrow Seen Schedule-IV Least Concern

50 Pavo cristatus Indian Peafowl Seen Schedule-I Least Concern

51 Petronia xanthocollis

Chestnut-shouldered Petronia Seen Schedule-IV

Least Concern

52 Prinia hodgsonii Grey-breasted Prinia Seen Schedule-IV

Least Concern

53 Pterocles exustus Chestnut-Bellied Sandgrouse Seen Schedule-IV

Least Concern

54 Pycnonotus cafer Red vented bulbul Seen Schedule-IV Least Concern

55 Pycnonotus leucotis White-eared Bulbul Seen Schedule-IV Least Concern

56 Saxicoloides fulicata Indian robin Seen Schedule-IV Least Concern

57 Streptopelia decaocto Eurasian collared dove Seen Schedule-IV

Least Concern

58 Streptopelia senegalensis Laughing dove Seen Schedule-IV Least Concern

59 Streptopelia tranquebarica Red-collared Dove Seen Schedule-IV Least Concern

60 Sturnia pagodarum Brahminy Myna Seen Schedule-IV Least Concern

61 Sturnus roseus Rosy Starling Seen Schedule-IV Least Concern

62 Sylvia curruca Lesser Whitethroat Seen Schedule-IV Least Concern

63 Tephrodornis pondicerianus Common Woodshrike Seen Schedule-IV

Least Concern

64 Turdoides caudatus Common Babbler Seen Schedule-IV Least Concern

65 Upupa epops Common Hoopoe Seen Schedule-IV Least Concern

66 Vanellus indicus Red wattled lapwing Seen Schedule-IV

Least Concern

Page 53: Social- Environmental Impact Study Report

53

CHAPTER VI

ENVIRONMENTAL IMPACT ASSESSMENT

6.1. INTRODUCTION

The wind power infrastructure principally includes wind turbines, power

transmission lines & substation and the access road needed for construction and

maintenance of turbine and transmission lines. The proposed project comes

under desert area where very minimal rainfall observed. So there is no significant

change in the impact seasonally. The wind power project does not require

continuous supply of water. Minor air and water emissions are envisaged and will

be limited to construction and maintenance of the wind turbines and transmission

lines.

Likelihood and Consequence of the impacts are categorized as per the Table

VI.1.

Table VI.1

Categorization of Likelihood and Consequence of Impacts

Level Definition

Likelihood of Impact

Certain The impact will occur in most circumstances

Likely It is most likely that impact will occur

Possible There is a distinct possibility that impact will occur

Unlikely The impact is very unlikely to occur but may occur at some time in normal conditions

Rare The possibility of the impact materializing is very low either because of design or historic experience or in exceptional circumstances

Consequence of Impact

No Impact or Insignificant

No Impacts or insignificant during the life of the project.

Minor Potential impact may result in slight decline in resource in the study area for short term duration and will return to baseline levels

Moderate Potential impact may result in slight decline in resource in the study area during the life of the project.

Major Potential impact could result in a decline in resource to lower than baseline but stable levels in the study area after project closure and into the predictable future.

Extreme Potential impact could threaten sustainability of the resources and should be considered a management concern.

In the following sections the likely impacts due to proposed wind power

infrastructure are assessed and suggestive mitigations measures are reported.

Page 54: Social- Environmental Impact Study Report

54

6.2. IMPACT ON AIR QUALITY

6.2.1. CONSTRUCTION PHASE

The construction activities for wind energy projects typically includes land

clearing for site preparation and access routes; excavation, filling; transportation

of supply materials; construction of foundations involving excavations and

concrete works; operating cranes for unloading and installation of equipment;

and commissioning of new equipment. The nearest receptors are informal

settlers which are found in the neighbouring area of identified WTGs locations.

Other than this, all the villages are located 1 Km away from the identified WTGs

locations. The major source of air pollution during the construction phase can be

due to:

Air borne emissions from the construction heavy machineries and

vehicular movements at site.

Air borne emissions during land clearing for site preparation and access

routes, cutting and filling of soil and other construction activities

Exhaust emissions from the vehicular movement and other stationery

generator sets.

The impact on air quality during construction phase is certain and minor in nature

and can be minimized or mitigated by proper preventive measures.

These impacts can be minimized by proper maintenance of machinery and

vehicles and by limiting the speed of vehicles.

The dust emission can be reduced by

Minimizing the disturbance of vegetation cover present

Stabilization of as much unpaved operations area as is feasible

Sprinkling of water is one of the measures to suppress the dust emission.

However considering the fact that the project is located in the desert area

and availability of the surface water is lean in this area, sprinkling of water

is not recommended.

Since, most of the cables used for power transmission are overhead, only

construction of base tower is involved in the transmission line related activities,

which may have minimal dust emissions.

The vehicular emissions will be depending on the condition of the pavement and

type of vehicles used in the construction activities. Moreover this impact due to

the movement of vehicles and usage of machineries during the construction

phase is of temporary nature. Suggested EMP during the construction phase will

reduce the negative impact on air quality, if any.

In the vicinity of a few of the WTG sites informal settlements were observed

during site survey. Minimum 300 m distance should be provided from the nearest

receptors in order to minimize the impact due to proposed project activities.

During the construction phase, the activities include land clearing, excavation,

concrete work, material supply etc due to which fugitive dust will be generated.

These activities will occur at each WTG site for period of 4 to 5 days. Considering

this short duration of activities and assuming that the WTGs will be sited beyond

Page 55: Social- Environmental Impact Study Report

55

300m distance from the nearest receptors, the impact due to fugitive emissions

will be minimal or insignificant at these receptors.

6.2.2. OPERATIONAL PHASE

Operational phase of the project will have limited activities, which mostly relates

to maintenance of wind turbines. These activities will include exhaust emission

from the vehicles used occasionally for maintenance and repair activities at Wind

Turbine locations. Frequency of these activities will be very less.

Therefore, impact on ambient air quality of the surrounding area will be minimum

from the proposed project.

The major positive impact from this project is the replacement of conventional

power resources like fossil fuels by clean and zero emission renewable energy.

Hence, emission of Green House Gasses (GHG) like CO2 generated from other

sources of energy is avoided.

6.3. NOISE IMPACT

Noise Receptors in the project area include residential houses and some informal settlers present near the WTG locations. Most of the WTGs are located at a distance of at least 1 Km from the village houses. Some of the informal settlers are located in the neighboring area of identified WTGs. Typical Noise Sensitive Time period for the residential area is Evening/Night.

6.3.1. CONSTRUCTION PHASE

The major sources of the noise pollution due to construction activity is from road

works, earth moving, concrete batching, levelling, grading, excavating and

compacting, movement of trucks for transportation of wind turbine assemblies,

construction materials, concrete mixers, asphalt mixing and laying equipment.

Noise may be generated from DG sets used during construction and erection of

Wind Turbine towers. All these may add to noise levels and impact the

surrounding ambient noise quality.

The construction activities will be limited to day timings (7:00am to 7:00pm) at

most of the WTG location. However, the region experience extreme temperature

during summer, hence project activities during day time is avoided. During this

season, the project activities will be carried out during night time and will

conclude by 10.00 am in the morning.

The Noise produced by the various construction machineries working at the site is tabulated in Table VI.2.

Table VI.2

Noise Source Strength of Construction Machineries

S. N. Machine Operation dBA

1. Motor Scraper Cut 84

2. Face Shovel Cut 80

3. Dump Truck Haul 83

Page 56: Social- Environmental Impact Study Report

56

4. Compactor Fill 81

5. Dozer Fill 83

6. Excavation by Shovel Cut 87

7. Excavation by Caterpillar Cut 109

Excavation by caterpillar will be used only at regions where there are rock

formations. For the proposed wind project, excavation will be done by shovel at

most of the locations. Considering the utilization of excavation by shovel for

excavation activity, predicted noise level at receptor located at 1 km is as follows:

NOISE CALCULATIONS Source = 87 dBA at 1.0 m

Noise at a distance of 1000 m from WTG

Lp2 = Lp1 - 20 log (r2/r1) Lp2 = 87 - 20 log (1000/1)

Lp2 = 27 dB

Therefore, the predicted noise at the villages located at 1km distance will be 27

dB (noise). The highest baseline noise measured at the village is 47.8 dB during

day time and 40.6 dB during night time. So difference between the predicted and

measured noise is more than 9 dB during day time as well as night time. As per

the Table VI.3, there will be no increment in baseline noise due to construction

activities at the nearest villages which are located at a distance of 1 km.

Table VI.3

Addition of Sound Levels, L1 and L2 (L1 > L2)

L1 – L2, dB Add to L1

0 or 1 3 dB

2 or 3 2 dB

4 – 8 1 dB

9 or more 0 dB

Source: Franken A. Peter, Community Noise Pollution, Industrial Pollution, Van

Noistrand Reinhold Company, New Your, 1974 ed.

However, there would be increase in the noise level due to ongoing activities of

WTGs on the surrounding area where the informal settlers are located.

Construction activities should be avoided during the night time at such locations.

If the noise generated at these locations are measured significant, then noise

barriers should be used. Noise producing activities should be carried away from

the habitations as far as possible. Since the construction activities at a WTG

location will be limited for short duration (4-7 days), the impact on the

surrounding would be minimal.

Page 57: Social- Environmental Impact Study Report

57

6.3.2. OPERATIONAL PHASE

The noise generated during operational phase of the project will be due to turbine

blades moving across the air, vehicle movement and some periodical

maintenance and repair activities carried out at the site. However, vehicle

movements, periodical maintenance and repairs will be limited short duration.

The noise generated due to operating WTGs are generally due to mechanical noise and aerodynamic noise. Assuming that at a distance of 1m, a WTG produces approximately 90dB noise, noise generation at 1km distance will be as follows.

NOISE CALCULATIONS

Source = 90 dBA at 1.0 m

Noise at a distance of 1000 m from WTG

Lp2 = Lp1 - 20 log (r2/r1) Lp2 = 90 - 20 log (1000/1)

Lp2 = 30 dB Therefore, the predicted noise at the 1 km distance where the Villages are located will be 30 dB (noise). The maximum base line noise level measured at villages is 47.8 dB during day time and 40.6 dB during night time. As per the Table VI.3 the difference between base line noise level and predicted WTG noise level at 1 km distance is more than 9. Hence, there will be no increase in existing baseline noise level at the villages during day and night time.

The baseline noise level at informal settlers‟ locations is not available. However,

the baseline noise levels measured at the villages would be more when

compared to the noise level at these informal settlers location as these sites are

scattered and generally minimal noise generation activities would take place. In

order to predict the noise generation at the informal settlers‟ location, baseline

noise level measured at villages has been considered in the present study.

Noise generation at 300 m distance:

NOISE CALCULATIONS

Source = 90 dBA at 1.0 m

Noise at a distance of 300 m from WTG

Lp2 = Lp1 - 20 log (r2/r1) Lp2 = 90 - 20 log (300/1)

Lp2 = 40.45 dB

As mentioned earlier the maximum noise level measured at villages during day

time is 47.8 dB and 40.6 dB during night time. As per the Table VI.3, the

difference between base line noise level and predicted WTG noise level at 300 m

distance is in the range of 4-8 dB during day time and 0-1 dB during night time.

Therefore, there would be an increment of about 1 dB over and above the

existing baseline level during day time and 3 dB over and above the existing

baseline level during night time at the informal settlements located at 300m

distance.

Page 58: Social- Environmental Impact Study Report

58

The predicted noise levels are not exceeding the limits as mentioned in the IFC‟s

General EHS guidelines (as given in Appendix 8), nor increasing the background

level of 3 dB at nearest receptor location.

Further, Blade design and controlled rotation in high wind conditions will further reduce aerodynamic noise emanating from the movement of air around the turbine blades and tower. The Double-Fed Induction Generator Technology used in IRL wind turbine is such that generation of the noise from the nacelle is minimal. Typical background sound levels for these areas would be generated by residential, agricultural, and small commercial activities, ambient sound from wind, and vehicle noise from regional roads. This background noise generally increases under such wind conditions and can mask the WTG noise.

Hence, the noise impact is expected to be minor on surrounding ambient noise

quality or ecology.

6.4. IMPACT ON WATER QUALITY

6.4.1. CONSTRUCTION PHASE

During site visit no surface water bodies were observed nearby to wind turbine

site locations. Hence impact from soil erosion or sedimentation of surface water

is insignificant.

Since, the foundation levels are well above the existing ground water levels more

than 40 m, the water used in construction does not mix with ground water table.

Further this activity does not involve blockage or diversion of ground water flow.

During the construction works there will be a varied man power (skilled and

unskilled) of between 50-60 people on site at any one time. In the category of

unskilled man power 40 to 50% will be outsourced from local contractors or

nearby villages where possible.

Most of the construction staff members will be from the surrounding villages.

Hence the generation of domestic wastewater will be minimal. Temporary

arrangement such as septic tanks will be provided for collection of the

wastewater in the wind farm yard area. There will be no direct discharge of

wastewater to any receiving water body.

No wastewater generation is envisaged during the operation phase. Once the

construction phase in completed the excess of excavated soil will be applied on

embankment and upper surface of leveled and unpaved area in the adjacent

area and slopes will be stabilized. This helps in prevention of soil erosion and

thus preventing contamination of water bodies.

6.5. LAND ENVIRONMENT

Land disturbance from construction activities such as excavation, leveling, filling,

topsoil stockpiling, Installation of tower foundation, etc. are expected during the

construction stage of the project which are insignificant, temporary in nature and

limited to construction phase only. Around 450-500 m3 of earth material will be

excavated per WTGs and the same top soil will be used for the filling in around

the WTGs, preparing of access roads etc.

Page 59: Social- Environmental Impact Study Report

59

Top soil removed during construction phase will be stored separately will be

applied on embankment and upper surface of leveled and unpaved area. The top

soil may be utilized for landscape development in adjacent areas. This will help in

retaining the spores of grass and shrub species that will germinate at the same

place during the monsoon period. This practice will help in reducing the soil

erosion while conserving the original plant species along with preservation of

precious top soil.

6.6. SOLID AND HAZARDOUS WASTE

The minimal quantity of solid waste generated during construction phase may

include small concrete materials, bins, unused metals, package materials,

scraps, plastic, paper and food materials etc. These kinds of wastes are limited

in quantity and generation of the same is temporary in nature. These wastes will

be collected, segregated and disposed of as per the existing municipal solid

waste rules. Therefore, soil contamination is not expected due to solid waste

generated from construction activities.

Solid waste generation during operation phase will be from replacement of

mechanical and electrical parts of the WTGs, used oil, electrical cables etc.

However, the frequency of maintenance is very less and as & when the

requirement arises. All the discarded electrical and mechanical parts have a

recycling value so same can be given to local scrap dealer.

There may be negligible amount of hazardous materials like lubricants, hydraulic

fluids from maintenance of machinery or operating vehicles, empty paint or oil

cans, waste batteries, transformers etc. generated during construction.

Highly refined, mineral insulating oils are used to cool transformers and provide

electrical insulation between live components. They are typically found at

electrical substation and maintenance shops.

In order to minimize the contamination of soil due to accidental spill or leaks of

fuels, the Substation area shall be designed sufficiently with impervious layer at

the storage areas and transformer areas. Proper sloping and drainage shall be

provided with proper collection or containment structure.

The used oils, other hazardous material will be properly collected and disposed

of as per the Hazardous waste Management and Handling Rules, 2008.

6.7. SOCIO-ECONOMIC IMPACT

An overview of the socio-economic baseline status in the study area is given in

chapter 5.

The Land required for the proposed WTGs, Right of Way and Electrical

substation will be developed on the Government Revenue Land. The proposed

project does not involve any physical displacement (relocation or loss of shelter)

or economic displacement (loss of assets or access to assets that leads to loss

of income sources or other means of livelihood).

During site reconnaissance survey, some of the settlements were observed in

the neighboring area of the WTGs locations. During interaction with these

residents it was understood that they have moved into this land and have set the

settlement over there for managing their livestocks and for farming purpose.

Page 60: Social- Environmental Impact Study Report

60

However, these informal settlers do not use the land identified by IRL for their

livelihood or for other uses. Identified locations neither restrict their access

routes. Same thing was reflected during the interaction with these residents

during site survey.

In order to provide safe setbacks, it is recommended that IRL should identify

alternative site for WTGs which are located close to WTG location and shall

ensure that distance shall be minimum 300m from the settlements or the

sensitive receptors.

6.7.1 TRAFFIC MOVEMENT AND SAFETY

Vehicular movements in the construction stage would include heavy vehicles like

trucks carrying large equipment. The movement of the heavy machineries such

as blades, towers etc. will occur only during the night times. Hence, the traffic

during the day time would be mainly due to concrete trucks, trucks carrying steel

bars and other vehicles whose movements would be spread throughout the

construction period. The vehicular movement in a month would be around 1184

in numbers.

These may lead to impact on transportation route and increased traffic load thus

may cause threat to the lives of animals and people using the access roads.

The traffic movement along the village roads should be effectively managed in

order to ensure safety and security of humans and livestock. Traffic movement

can be managed by

Limiting the speed limits of the vehicles about 40 km/hr;

Traffic signage shall be used.

Trucks carrying heavy machineries shall be mobilized during night time;

and

Driver should be authorized and should have valid driving license,

Implement contract clauses to ensure trucks adhere to recommended

transportation routes. Impose financial penalties for non-compliance to

ensure safe operation of trucks on local roads

Inform the public of the ongoing construction operations

6.7.2 WORKING LABOURS

As mentioned earlier in this report, for an ideal size of approximate 100 MW wind

farm development around 100-125 skilled & 450-500 unskilled manpower is

required. During the construction works there will be a varied man power (skilled

and unskilled) of between 50-60 people on site at any one time. In the category

of unskilled man power 40 to 50% will be outsourced from local contractors or

nearby villages where possible. Since the proposed 300 MW wind development

will be developed in the phases over a period of 10 months, the manpower for

300 MW will not vary as specified above.

The migrant workers will be accommodated in the local villages and in Jaisalmer

city.

Page 61: Social- Environmental Impact Study Report

61

IRL should plan for collective attachment i.e marginal workers identity as group

or community, provide all facilities to all groups, interact them with community as

member , identify and review cultural interest, tradition of the marginal workers

and interact with community people so that all they identify as a whole group.

Compensate cultural impacts in an appropriate manner and propose time bound

plan such as migrant labor development plan or a broader community

development plan.

During operational phase, approximately 15-20 people are required for an ideal

100 MW project and will stay at Jaisalmer city.

6.7.3 POSITIVE IMPACTS

This project will create employment and other opportunities (e.g. service sector such as catering, cleaning, transport, security etc) for skill development. The proposed wind farm would require manpower during the time of construction phase. Members of the local community are likely to be in the position to qualify for the majority of the low skilled and some of the semi skilled employment opportunities. The other employment opportunities would be linked to service sector such as catering, cleaning, transport and security.

The project will have a positive impact by developing access roads. This will benefit to local villages for easy transportation. The internal village roads although motorable are not likely to withstand constant heavy vehicle movement and will need repair/ construction. The construction of new roads and strengthening of existing roads will lead to improved access and connectivity to the villages and agricultural fields.

The major positive impact of the proposed project is development of clean, renewable energy infrastructure for power generation. However, generated power will be given to state government and further distribution will be done by them.

6.8. ECOLOGICAL IMPACT

The results of the baseline vegetation study suggest that the project area falls in

the semi arid region and the vegetation of the area represents the same. The

vegetation species and life forms suggests that the project area represents the

characteristics that of degraded vegetation and dry and semiarid landscape.

The project area does not have any threatened, endangered or conservation

concerned faunal species. Majority of the species found in and around project

site are common throughout the state. The area does not make part of any

significant breeding, roosting or feeding habitats of important and endangered

species.

Moreover, the project area does not fall in vicinity of any important wildlife

hotspot in the region. The project site does not fall in the eco-sensitive/fragile

zone identified by the State/Central Government agencies. The area does not fall

in any of the critical wildlife habitats identified by any agencies till date.

In view of the results of the flora and fauna study it is inferred that the project

shall have least impacts on ecology of the region.

Page 62: Social- Environmental Impact Study Report

62

6.9. IMPACT ON BIRD MIGRATION AND MORTALITY

In order to predict the impact on the birds due to the proposed wind farm, a study

was carried out by Dr. Bharat Jethva, a Wild life biologist. The study report is

enclosed in the Appendix 12. Based on his study, the conclusions drawn are as

follows

The baseline status of the birds and bats clearly suggests that no

endemic or threatened species is present in and around the proposed

project area.

The sensitive receptors such as habitats of Bird‟s & Bat‟s i.e. Desert

National Park/Grassland, Wetland and roosting sites of bats do not fall in

and around the project area and they are located more than 10 km away.

Great Indian Bustard and other endangered species are less likely to be

affected because of their very small surviving population in Jaisalmer

district and it is currently restricted in Desert National Park.

Observations on movement of bats from Jaisalmer roosts suggests that

majority of the bats were moving towards the agriculture fields aligned

along the Indira Gandhi Canal 40 km north of Jaisalmer town.

Interview survey of local villagers and herders suggested the absence of

Bustards from the project area due to disturbance, developmental

activities and general increase in the human population and their

movements in the region.

Literature survey suggested that Rajasthan/India falls on Central Asian

Flyway which is broadly defined flyway for several migratory birds and

there is no specific bird route that passes only through the Jaisalmer or

Rajasthan as such.

Literature survey also suggested that wind turbines do not significantly

harm the migratory waterbirds, especially when the wetlands are located

far away from the proposed project site.

Though, there are not many cases of bird hits by windmills have been

observed in India till date, it is important that project site should be monitored

properly and specifically for bird mortality. Proposed management plan would

mitigate any likely impacts on the birds.

Suggestive Mitigation measures to minimize the impact on the birds are given in

the Appendix 16 and briefly summarized below:

Annual Monitoring of Bird hits and Mortality

Precautions to avoid disturbance to wildlife

Regular removal of carcasses of animals from the project areas that

would attract raptors or vultures

Training of Project Personals against poaching or harassment

Page 63: Social- Environmental Impact Study Report

63

6.10. ARCHEOLOGICAL AND CULTURAL HERITAGE

It should be noted that the proposed project will not pose any problem with

respect to cultural and historical assets. As per archaeological survey of India

and state archaeology department there are no specific archaeological sites,

structures, remains or artifacts notified or demarcated within 10 Km radius of the

proposed site.

6.11. STORM AND SEISMIC HAZARD

The continuous variable pitch regulation system of the blades helps to operate at

a continuous variable speed in synchronism with the varying wind speeds.

Turbine blades are designed to work at a cut out wind speed of 20 m/s and

having storm control. These mills will stop automatically for the wind speeds

reaching more than 20 m/s.

The proposed project site is located in Zone II (Low Damage Risk Zone) as per the seismic zones of India Map IS:1893-2002, BIS GOI. However seismic hazard has been taken into account in the design of the turbine foundations to prevent tower failure in the event of shocks. Therefore, storm and seismic hazards are not of any significance for the proposed project.

6.12. IMPACT ON AIR TRAFFIC AND SAFETY

Jaisalmer airport and Air force station are situated more than 50 Km towards

North West of the proposed wind farm site. Therefore, impact on air traffic and

safety are not expected due to set of proposed wind power.

As per air navigational marking regulations, the blades of the WTGs are marked

with red bands with specific width for more visibility.

6.13. VISUAL IMPACTS

Primarily visual impacts depend on the location and public perception. During

consultation, it was understood that the local villagers were very much aware

about the wind farm project and did not have any concerns about visual impacts.

Visual impacts associated with wind power projects typically relate to the turbine

itself such as color, type, height, etc. and impacts relating to their interaction with

character of the surrounding landscape. All the proposed WTGs of this project

are of uniform diameter & color and have non-reflective paints. Use of overhead

cables for power transmission, could potentially create minimal visual impact.

However transmission line and WTGs are located away from the populated areas

as identified project will be developed on government revenue land. Hence visual

impact due to transmission line and WTGs will be insignificant. The features

blend with the natural landscape & prevent interference with the overall scenic

beauty of the surrounding area.

6.14. LIGHT AND ILLUMINATION ISSUES

Shadow Flicker

Shadow flicker occurs generally during the operation phase of the project, when

the sun passes behind the wind turbine and casts a shadow. As the rotor blades

rotate, shadows pass over the same point causing an effect termed shadow

flicker. Shadow flicker may become a problem when residences are located near,

or have a specific orientation to, the wind farm.

Page 64: Social- Environmental Impact Study Report

64

Majority of the WTGs are located 1 Km away from nearby villages. Hence impact

due to of shadow flicker is expected to be minimal from the proposed project.

Considering fact that there are no issues raised by the public so far regarding the

shadow flicker from the existing WTGs in the district, impact due to shadow

flicker on the nearest receptors such as informal settlers is not anticipated

Blade Glint:

Similar to shadow flicker, blade or tower glint occurs when the sun strikes a rotor

blade or the tower at a particular orientation. This can impact the community, as

the reflection of sunlight off the rotor blade may be angled toward nearby

residences. Blade glint is a temporary phenomenon for new turbines only, and

typically disappears when blades get soiled after a few months of operation. Also

the wind turbine towers are painted with non-reflective coatings; hence the

reflection from tower is not anticipated.

6.15. ELECTROMAGNETIC INTERFERENCE AND IMPACT ON OPERATION OF AVIATION RADAR

Wind farms located near an airport may impact the operation of aviation radar by causing signal distortion, which may cause loss of signal and/or erroneous signals on the radar screen. These effects are caused by tower and rotor component reflection due to radar chopping. Design site plan of project facilities to comply with the requirement of aviation authorities to avoid electromagnetic interference.

The nearest airport which is currently not operational is located 50 Km away from

the nearest wind turbine location. Further IRL has obtained no objection

certificate from the aviation authority.

Also the design of the turbine components such as nacelle, tower and blades are

designed in such a fashion that there will be no electromagnetic interferences.

Turbine blades are made of fiberglass material of reinforced epoxy resins with

non reflecting coating which will minimize the electromagnetic interferences.

6.16. CUMULATIVE IMPACTS

Currently 110MW is under construction and is expected to be operational by May

2012. IRL is also planning to develop additional 300 MW (over and above the

300 MW being developed in FY 13) in the area between Dangri and Devikot. The

location map of the proposed site is shown in Figure VI.1.

The WTGs coordinate locations for the additional 300 MW are not identified yet,

however these WTGs will be spread in the villages of Khelena, Bonanda,

Savalpura, Lakhamana, Hastinapur, Betina, Betanjpura, Sangram Singh ki

Dhani, Pratappura, Lunakalan, Luna Khurd. There will be no overlapping of

construction activities of the three projects.

6.16.1 CUMULATIVE EFFECTS DUE TO TRAFFIC AND TRANSPORTATION

Cumulative construction effects are usually of most concern with the main traffic

impacts likely to be associated with the movements of commercial Heavy Goods

Vehicles (HGVs) transporting construction materials and wind turbine

components, to the site. Increase in traffic volumes are expected as a result of

the construction of the Project. The construction schedules of the proposed and

Page 65: Social- Environmental Impact Study Report

65

planned wind farm projects do not significantly overlap. Hence the cumulative

impact due to traffic is not anticipated.

Traffic movement once the wind farm becomes operational is usually minimal

and comprises occasional visits for maintenance activities and an occasional

need for an HGV / crane for more substantial maintenance or equipment

replacement. The effects of operational traffic would generally be considered

negligible.

6.16.2 CUMULATIVE IMPACT ON VEGETATION/FLORA:

Since Wind Farm projects occupy small land areas for wind turbine installation,

their impacts on vegetation is generally minimal. It was noticed during site visit,

that vegetation in the study area represents that of Thar Desert. Majority of the

species reported in the study area are common throughout the Thar Desert.

During the site visit no plant species with restricted distribution was observed in

the study area. It is therefore, inferred that if there is expansion or addition in the

wind farm areas in the periphery of the Dangri Project site, the cumulative impact

on the vegetation is less likely to threaten any plant species of the region.

6.16.3 CUMULATIVE IMPACT ON FAUNA:

As per the literature survey and the present study, only birds, bats and natural

habitats are likely to be affected by the wind farm development. Due to lack of

comprehensive data and information (of surrounding areas) the exact nature and

magnitude of the cumulative impacts of wind farm development is difficult to

predict. However, the cumulative impact of the wind farm development around

Dangri project site may be low on fauna due to following reasons.

During the study, it was found all the fauna that are common throughout

the Thar Desert and have wider distribution. There was not a single

species of fauna with restricted distribution present in and around the

project site and in the study area i.e. 20Km2.

No threatened bird or bat species was found in the study area.

The sensitive habitats of important fauna (particularly birds and bats) are

not located within 10km periphery of the project site.

Due to lack of wetlands (as observed through Google earth) in the 10 km

periphery of the project site, it is inferred that this area do not fall on the

route of migratory waterbirds. Therefore, it is less likely that the expansion

or addition of more wind turbines in the periphery of the study area may

cause any cumulative impact on the migratory birds.

There may be some local and common bird species (which are abundant

and having wider distribution) may lose their roosting, feeding and nesting

grounds. This may not threaten their populations.

Page 66: Social- Environmental Impact Study Report

66

Figure VI.1

Location Map of Proposed Wind Farm in the vicinity of the Proposed

Project

6.16.4 CUMULATIVE NOISE EFFECT

The expected cumulative operational impact that might be considered due to

wind farm project is Noise impact.

Since the WTG locations of the planned 300 MW (during FY 13-14) wind farm

site is not determined at the moment, it is not possible to make cumulative noise

impact at this stage. However, considering 15 km distance between the two wind

farm sites, overlapping of the noise levels reaching nearby settlement is not

anticipated.

6.16.5 EMPLOYMENT OPPURTUNITIES

As mentioned earlier, the proposed wind farm will create employment

opportunities. The planned 300 MW wind project will increase the job

opportunities and will extend for next 2 years. This will also increase the local

business in the area. Hence there will be a positive impact due to both the

project.

6.17. OVERALL IMPACTS

Temporary impacts expected during the construction phase will be mitigated

through proper implementation of mitigation measures suggested in Chapter VII

– Environmental Management Plan. The proposed project will also generate

positive impact, which includes developing of the access roads, employment

opportunities etc. However, overall impacts of both operational and construction

Page 67: Social- Environmental Impact Study Report

67

phase on the surrounding environment are expected to be positive based on

likelihood and severity of consequence as interpreted below:

Attributes Likelihood Consequence

During Construction phase

Impact on Air Quality Certain Minor

Impact on Noise Possible Minor

Impact on Water Unlikely Insignificant

Impact on Land environment Likely Minor

Impact due Solid waste Hazardous waste generation

Possible Minor

Impact on Socio economic Possible Minor

Impact on ecology Unlikely Minor

Impact on Archeological and heritage sites

Rare Insignificant

Storm and Seismic hazard

Rare Insignificant

Visual impact Likely Minor

Operational phase

Impact on Air Quality Rare Minor

Impact on Noise Possible Minor

Impact due Solid waste Hazardous waste generation

Possible Minor

Impact on Socio economic Unlikely Minor

Impact on ecology Possible Moderate

Impact on Archeological and heritage sites

Rare Insignificant

Visual impact Likely Insignificant

Impact on Aircraft traffic and Safety.

Rare Insignificant

Page 68: Social- Environmental Impact Study Report

68

CHAPTER VII

ENVIRONMENTAL MANAGEMENT PLAN

7.1. ENVIRONMENTAL MANAGEMENT PLAN (EMP)

This section of the chapter proposes an environment management plans during

the construction and operational phase of the proposed wind energy project.

The objectives of the environmental management plan is to achieve the following

objectives:

To ensure that good engineering practices are followed during

construction and operational phases to minimize environmental

impacts.

To avoid, or where avoidance is not possible, minimize, mitigate,

or compensate for adverse impacts on workers, affected

communities and the surrounding.

To ensure that rehabilitation, resettlement of the affected

communities if any due to project shall be done properly.

To ensure good occupational health and safety practices during

construction and operation phase at the project.

To ensure that the pollutant concentration in the workplace does

not exceed the NAAQS

To monitor impacts on the environment and the effectiveness of

mitigation measures during operation

EMP, which covers IFC guideline, April 2007 on relevant features of Environment, Health and Safety required for wind energy project is recommended to be followed during the construction and operation phase of the project. EMP for construction phase and operation phase of the project is given in Table VII.1 and Table VII.2.

The promoter‟s organizational setup shall include the following department for effective monitoring and implementation of the action plan.

Human resource department

Procurement Department

Corporate Social Responsibility department

Environmental department

Project management department

Page 69: Social- Environmental Impact Study Report

69

Table VII.1

Environmental Management Plan: Construction phase

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

1 Air Quality Dust emission

during construction

activities and

movement of the

vehicles on

unpaved roads

Minimizing the

disturbance of vegetation

cover present

Stabilization of as much

unpaved operations area

as is feasible

Limiting the speed limits of

the vehicles on the

unpaved surface to 40

km/hr

Monitoring of the dust

emissions during high

wind periods

During

construction

Developer/

Contractor PS3

Inspection of implementation of action plans by Environmental and safety dept during regular audits.

Carry out the environmental monitoring by accredited Agency once in Quarter Year.

Implementation of action plans and compliance or non compliance shall be reported in the Quarterly report which will be submitted to the lenders.

Page 70: Social- Environmental Impact Study Report

70

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

Gaseous

emissions from the

construction

machineries and

Vehicles

Vehicle used for

transportation should have

the Pollution under Control

(PUC) Certificate

Regular maintenance of

the vehicles and heavy

machinery to ensure the

minimal exhaust emission

During

construction

Developer/

Contractor

PS3 Regular

maintenance of

the vehicles and

test certificates

will be

registered.

Test records will

be inspected

during Quarterly

audits.

Implementation of action plans and compliance or non compliance shall be reported in the Quarterly report which will be submitted to the lenders.

Page 71: Social- Environmental Impact Study Report

71

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

2 Noise

Quality

Noise emission

from the

Construction

related equipments

and due

movement of

Vehicles

Engine powered

construction machineries

and vehicles shall be

provided with exhaust

silencers.

Proper maintenance and

service of the machineries

and vehicles to adhere the

NAAQ noise standards

and IFC noise standards.

Limiting the speed limits of

the vehicles to 40 km/hr

Workers should be

provided with earplugs/

earmuffs to avoid the

noise impacts near high

noisy areas.

Noise levels shall be

monitored at the sensitive

receptors.

Inform residents when

activities will be

particularly noisy

During

construction

phase

Developer/

contractor PS 3

Inspection of implementation of action plans by Environmental and safety dept.

Carry out the environmental monitoring by accredited Agency once in Quarterly Year near the sensitive receptors.

Implementation of action plans and compliance or non compliance shall be reported in the Quarterly report which will be submitted to the lenders.

3 Land

environment

Impact on

receiving water

Store construction

materials containing fine

During

construction

Developer/

contractor PS3

Inspection of implementation

Page 72: Social- Environmental Impact Study Report

72

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

and water

environment

body due to soil

erosion

particles in an enclosure

such that sediment laden

water does not drain into

nearby water drains If any

Stabilize slopes on road or

elsewhere any

embankments to control

sedimentation, erosion

and water pollution.

Also consider the use of

geo-textiles to prevent soil

erosion during

construction.

Top soil shall be re-use in

the adjacent areas

phase of action plans by Environmental and safety dept.

Implementation of action plans and compliance or non compliance shall be reported in the Quarterly report which will be submitted to the lenders.

4 Waste

managemen

t

Wastewater Minimal wastewater will be

generated which will be

collected in the septic tank

No wastewater generated

will be discharged into the

water bodies.

During

construction

phase

During

constructio

n phase

PS3

Inspection of implementation of action plans by Environmental and safety dept during random checks.

Implementation of action plans and compliance or non

Solid waste Minimal solid waste will be

generated which includes

concrete materials, bins,

unused metals, package

materials, scraps, plastic,

Page 73: Social- Environmental Impact Study Report

73

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

paper and food materials

etc. which will be disposed

of as per municipal solid

waste rules

compliance shall be reported in the Quarterly report which will be submitted to the lenders

Excavation

material

Excavation generated

material will be used for

embankment of road and

minor leveling of site

during the conclusion of

construction activities and

filling low lying area of the

site

Top soil will be stored

separately and will be

applied on the

embankment and upper

surface of the leveled and

unpaved area.

Hazardous waste Minimum waste will be

generated such as empty

oil/paint containers and

the lubricating/ hydraulic

fluids used for the

maintenance. These

wastes will be stored in

the containers and

Inspection of implementation of action plans by Environmental and safety dept during random checks.

Implementation

Page 74: Social- Environmental Impact Study Report

74

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

disposed of as per

Hazardous waste

Management and

Handling Rules, 2008.

Substation area shall be

designed sufficiently with

impervious layer at the

storage areas and

transformer areas. Proper

sloping and drainage shall

be provided with proper

collection or containment

structure.

of action plans and compliance or non compliance shall be reported in the Quarterly report which will be submitted to the lenders

5 Socio-

economic

Safety of

community due

traffic movements

and construction

workers

Limiting the speed limits of

the vehicles to 40 km/ hr

within the villages and site

Trucks carrying Heavy

machineries shall be

mobilized during night

time.

Driver should have valid

driving license

Implement clause of

contract to adhere the

conditions in the Code of

conduct developed by IRL

During

construction

phase

Developer PS1

Non compliance of the action plans will be registered by the safety officer.

Appropriate actions will be taken up for noncompliance.

Non compliance and the actions taken shall be reported and shall be included in the quarterly

Page 75: Social- Environmental Impact Study Report

75

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

in order to mitigate the

impact on the community

due to presence of

construction workers in

the area.

report

Grievances Assess the grievances/ suggestions and if they are found to be genuine, will be resolved at the site office level itself within 30 days from the date of receipt. The detailed grievance Mechanism is dealt in section 7.3

During

construction

phase

Developer PS1

the detailed grievance Mechanism is dealt in section 7.3

Prepare Quarterly report and presenting it to lenders

6 Ecology Minimizing the footprint of

the construction related

activities. Once the

Construction is completed

it should be ensured that

the disturbed areas are re-

vegetated with native plant

species

Training the Project

personnel‟s to avoid any

accidents, poaching or

harassments to any

During

Constructio

n phase

Developer/

contractor PS6

Compliance and non compliance of the mitigation measures the shall be inspected by the safety and environment department once in a week

and which will be quarterly limited and

Page 76: Social- Environmental Impact Study Report

76

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

animal or bird species by

the project staff such as

laborers, drivers or any

other employees

submitted to the lenders

7 Occupationa

l Health and

safety

Workers shall be trained

for operational health and

safety requirements as

per IFC‟s EHS

guidelines.

Only trained and certified

workers to install,

maintain or repair

electrical equipment.

Deactivating and properly

grounding live power

distribution lines before

work is performed on, or

in close proximity to the

lines

Take proper care during

loading and unloading to

avoid any mechanical

injury

Provide and effective use

of necessary safety

appliance like, Safety net,

During

construction

phase

Developer/

contractor PS2

Inspection and implementation of Action plan by the Environmental and safety department.

Near-miss and other accidents shall be registered. Appropriate measures taken shall also be recorded

This will be recorded in the quarterly reports and shall be submitted to lenders

Page 77: Social- Environmental Impact Study Report

77

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

Safety belt, safety

harness etc.

All the precautions shall

be taken which includes

physical hazards due to

working at heights,

working with rotating

machinery and falling

objects.

Implementation of a fall

protection program

includes training in

climbing techniques and

use of fall protection

measures, inspection,

maintenance and

replacement etc.

Install fixtures on tower

components to facilitate

the use of fall protection

systems.

Provide workers with

adequate work

positioning device system

Ensure that hoisting

equipment is properly

Page 78: Social- Environmental Impact Study Report

78

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

rated and maintained and

that hoist operators are

properly trained.

Safety belts should be of

not less than 15.8 mm

two in one nylon or

material of equivalent

strength.

Check road embankment

for erosion and rutting,

any sign of instability to

be taken care before

every monsoon. Identify

the personnel for

monitoring and mitigating

the effect of project on

environmental and socio-

cultural resources

Lifting Tool & Tackle

should be tested as per

relevant act and mark the

safe operating limit,

testing and due test date.

Visual inspection is to be

done, before starting to

use lifting tool & tackle

Page 79: Social- Environmental Impact Study Report

79

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

Provide Personnel

protective equipments

Provide the temporary

shade in the nearby area,

so concern worker can

take rest in the different

interval and it can be

prevent from Sunstroke.

Sufficient and hygienic

drinking water should be

available at site.

Develop the nearby

available medical services

contact number and

address, in case of

emergency use.

8 Community

health and

safety

Prevent unauthorized

personnel from assessing

the site.

Wind turbine site shall be

designed with appropriate

safety setback.

Adhering to speed limits

for the traffic movement

within the project site.

Clear signs, flag-marks

During

construction

phase

Developer/

contractor PS4

Compliance reports shall be prepared and be included in the quarterly report

Page 80: Social- Environmental Impact Study Report

80

Sr.

No. Issues Impact

Actions/ Mitigation

measures

Time

schedule

Responsib

ility

IFC

Performance

standard

Supervision and

reporting

shall be used where ever

necessary in the vicinity of

the construction activity.

Develop an operational

and emergency response

program for fire and major

accidents including

emergency equipment

9 Visual

impacts

All the debris and waste

will be collected, stored

and transported in an

orderly manner to prevent

any adverse visual impact

on the surrounding.

Project equipment storage

area will be maintained

properly to prevent

adverse visual impact

During

construction

phase

Developer/

contractor PS3

Regular inspection

at site.

Compliance and

non compliance

shall be recorded.

This will be

include as a part

of Quarterly

report.

10 Storm and

Seismic

hazard

Developer/ contractor will

take necessary precaution

during the foundation

design

During

Design

Phase

Developer/

Contractor PS3

Check by the Project management Dept during the design engineering.

Page 81: Social- Environmental Impact Study Report

81

TABLE VII.2

Environmental Management Plan: Operation phase

Sr. No.

Issues Impact Actions/ Mitigation measures

Time schedule

Implementation

IFC Performance standard

Supervision and reporting

1 Noise Quality

Noise resulting from the wind turbines

Proper maintenance of instruments. Monitor the noise levels at sensitive receptors as per monitoring plan.

When the turbine is out of operation for maintenance the sound level in the nacelle is below 80 dB. In operation mode ear protection is required.

During Operation Phase

Promoter/ Developer

PS3 Inspection of implementation of action plans by Environmental and safety dept.

Carry out the environmental monitoring by accredited Agency once in Quarterly Year near the sensitive receptors.

Implementation of action plans and compliance or non compliance shall be reported in the Quarterly

Page 82: Social- Environmental Impact Study Report

82

Sr. No.

Issues Impact Actions/ Mitigation measures

Time schedule

Implementation

IFC Performance standard

Supervision and reporting

report which will be submitted to the lenders.

2 Waste management

Hazardous waste (Waste oil)

Waste oils resulting from the maintenance works will be collected, stored and will be disposed of as per Hazardous waste Management and Handling Rules, 2008.

Ensure proper and contained disposal of enamel and paint drums and other waste at sites

During Operation Phase

Promoter/ Developer

PS3 Inspection of implementation of action plans by Environmental and safety dept during random checks.

Implementation of action plans and compliance or non compliance shall be reported in the Quarterly report which will be submitted to the lenders

3 Socio-economic

Grievances Assess the grievances/ suggestions and if they

During operation

Promoter/ developer

PS1 the detailed grievance

Page 83: Social- Environmental Impact Study Report

83

Sr. No.

Issues Impact Actions/ Mitigation measures

Time schedule

Implementation

IFC Performance standard

Supervision and reporting

are found to be genuine, will be resolved at the site office level itself within 30 days from the date of receipt.

phase Mechanism is dealt in section 7.3

preparation of annual report and presenting it to Lenders annually

4 Ecology Bird Hits and Mortality

annual monitoring of windmills shall be carried out at least for two years for two migratory bird season(November to March) in order to understand if there are any significant mortality of birds or disturbance to them due installation of windmills in the project area.

Regular removal of the animal carcasses in avoid vultures and raptors

Training project personnel against harassment or poaching.

Plantation of native trees in other areas selected in consultation with

During operation phase

Promoter/ Developer

PS6 Monitoring avian fauna for 2 years by expert ornithologist.

Presenting the half yearly reports to the lenders

Page 84: Social- Environmental Impact Study Report

84

Sr. No.

Issues Impact Actions/ Mitigation measures

Time schedule

Implementation

IFC Performance standard

Supervision and reporting

biologists or with local forest officials post construction.

5 Occupational health and safety

Workers will be trained for the health and safety requirements as per IFC EHS guidelines.

All the precautions will be taken while working at heights

Only trained and certified

workers to install,

maintain or repair

electrical equipment.

Deactivating and properly

grounding live power

distribution lines before

work is performed on, or

in close proximity to the

lines

Provide Personnel protective equipments

Implementation of a fall protection program includes training in climbing techniques and use of fall protection measures, inspection,

During Operation phase

Promoter/ Developer

PS2 Inspection and implementation of Action plan by the Environmental and safety department.

Near-miss and other accidents shall be registered. Appropriate measures taken shall also be recorded.

This will be recorded in the quarterly reports and shall be submitted to lenders

Page 85: Social- Environmental Impact Study Report

85

Sr. No.

Issues Impact Actions/ Mitigation measures

Time schedule

Implementation

IFC Performance standard

Supervision and reporting

maintenance and replacement etc.

Lifting Tool & Tackle should be tested as per relevant act and mark the safe operating limit, testing and due test date.

Provide workers with adequate work positioning device system.

6

Community health and safety

Design site plan of project facilities to comply with the requirement of aviation authorities to avoid electromagnetic interference.

Prevent unauthorized personnel from accessing the towers by locking the doors of the tower

Grounding conducting objects which are installed near power lines, to prevent shock.

Wind turbine site shall be designed with appropriate safety setback.

Enforce traffic control including speed limits.

During Operation phase

Promoter/ Developer

PS4 Compliance reports shall be prepared and be included in the quarterly report

Page 86: Social- Environmental Impact Study Report

86

Sr. No.

Issues Impact Actions/ Mitigation measures

Time schedule

Implementation

IFC Performance standard

Supervision and reporting

Provide rational speed control to ensure the safe operation of wind turbine rotors.

Develop an operational and emergency response program for fire and major accidents including emergency equipment.

Warning labels and public hazard information boards will be available at site to ensure public safety.

7 Visual impacts

Turbine will be painted a uniform color generally that will blend with sky i.e. light grey , white

Use anti-collision lighting and marking systems on towers and blades to provide aviation safety.

Use identical turbine model for all turbines

Repair turbines immediately

Clean turbines Remove excess materials

and litter

During Operation phase

Promoter/ Developer

PS3 Inspection of implementation of action plans by Environmental and safety dept.

Compliance reports shall be prepared and be included in the quarterly report

Page 87: Social- Environmental Impact Study Report

87

Disclosure of the action plan:

1) Prepare a quarterly report of issues involved during Project activities and the implementation of respective mitigation measures/ action plan.

2) The Reports will be made accessible at the Office sites for the Project affected communities

7.2. ENVIRONMENTAL MONITORING PROGRAMME

Environmental monitoring and supervision programme is a vital process of any management plan of the development project. This helps in alarming the potential problems that may result from the proposed project. This will help in taking prompt action for implementation of effective corrective measures. The main objectives of the monitoring program are:

To assess the changes in environmental conditions.

To monitor the effective implementation of mitigation measures.

Changes in environmental quality for further preventive action.

An environmental monitoring programme with parameters and frequency location are given in Table: VII.3 & 4. In order to ensure the effective implementation of

the monitoring programme, regular inspection shall be taken up by the Environmental and Safety team. Compliance/ non compliance of the monitoring programme shall be recorded and quarterly report shall be submitted to the lenders.

Table VII.3

Environmental Monitoring Programme – Construction Phase

Item Location of Sampling

Parameters Frequency Standard methods

Air quality at nearest

village from wind turbine.

At Storage Yard

Nearest Village

Nearest Informal Settler

SO2 (24 hrly)

Twice in year during

construction period.

Improved West and Gaeke method.

Ultraviolet Fluorescence

NOx (24 hrly)

Jacob & Hochheiser modified method.

Gas Phase Chemiluminescence

SPM(24 hrly) High Volume

Sampling (HVS)

PM 10µ and 2.5µ (24 hrly)

Respirable Particulate

Matter Sampler

Noise measuremen

All the Informal settler

Equivalent noise level (Leq) for day

Once in a three month

Hourly

Page 88: Social- Environmental Impact Study Report

88

t at nearest village or.

Nearest Villages or nearest settlement from wind turbine

time and night time (Ld and Ln).

during construction

period.

Water quality at the

nearest WTG location (if

any)

Borewell locations Nearest Village

Ground water samples

Twice in year during

construction period.

IS: 10500

Soil

at substation and storage yard

Texture, physico chemical analysis

and relevant heavy metals

Twice in year during

construction period.

As per applicable standard

Table VII.4

Environmental Monitoring Programme - Operation Phase

Item

Parameters Frequency Standard methods

Noise Equivalent noise level (Leq) for day time and night time (Ld and Ln).

Once in year at nearest village from wind turbine.

Hourly

Surface Water quality

Measurement of surface, ground water

and soil quality for lubricating oil if any

contamination occurs as a result of considerable

oil spill to a nearby surface or unpaved ground due to the maintenance and operation of wind turbine activities.

Once in year at the nearest Surface water/ ground water

from the wind turbine

IS: 10500

Ground Water quality

IS:2296

Soil As per

applicable standard

Bird mortality

annual monitoring of windmills be carried out at least for two years for two migratory bird seasons (November-

March) in order to understand if there are any significant mortality of birds or disturbance to them due installation

of windmills in the project area.

-

7.3 GRIEVANCE MECHANISM

A joint social and environmental redress mechanism should be implemented under the project. Grievances and suggestions from local and affected people may come-up related to inappropriate implementation of the project and components of EMP. The expected range of grievances to be handled through this mechanism will encompass but not limited to the following:

a) Nuisance from noise, dust, and temporary blocking of access;

b) Emissions from increase vehicular traffic and stationary sources;

Page 89: Social- Environmental Impact Study Report

89

c) Conflict between local residents and migrant workers;

d) Underpayment or delayed payment of local workers,

e) Ownership of vegetation for clearing; and

f) Damage compensation.

These issues will be addressed through acknowledgement, evaluation and corrective action and response approach. Grievances from public or stakeholders concerning the project and EMP implementation will be received by the concerned „Project In-charge‟ at site. A site register will be maintained where all complaints are registered with the signature of the complainant and the „Site In-charge‟. The „Site In-charge‟ shall send one copy of the complaints to the following departments in the project promoter‟s organizational set up.

Human Resource Department,

Procurement Department,

Corporate Social Responsibility Department (Liaison Officer)

Environmental and Safety Department and

Project Management Department

If present, the Project Supervisor will then assess the grievances/suggestions and if they are found to be genuine, will be resolved at the site office level itself within 30 days from the date of receipt. In case, the issue is unable to be resolved, the matter will be forwarded to the Social and Environmental department to the clients head quarter. The final responsibility of Grievance Redressal shall lie with the Project Management Department or the „Project In-charge‟. For management of complex grievance issues the client shall include local administration and local community representatives to resolve the issues when required. Grievance mechanism shall applicable during due course of construction phase and implementation phase of the project.

Page 90: Social- Environmental Impact Study Report

90

CHAPTER VIII

PUBLIC CONSULTATION, FINDINGS AND RECOMMENDATIONS

8.1 PUBLIC CONSULTATION

Public Consultation is an important component of this study. As the proposed

project site involves only government revenue land, residents of the nearby

villages, local gram panchayats and representative of the local community were

considered as stakeholders and were consulted during the study. All the

stakeholders were informed well in advance about public consultation.

Stakeholder‟s consultation meeting was organized on 25th Feb, 2012 at

Fatehgarh Primary School, at Fatehgarh. All the stakeholders were informed

well in advance about venue, date and meeting date. The stakeholders included

the residents of the nearby villages, representatives of Inox team,

representatives of Tata Consulting Engineers Limited (TCE), IFC personnel and

farmers from different villages etc.

The meeting was opened with the introduction of the project by TCE. An

interactive session was held in Hindi Language (local language) with the villagers

to help them have better understanding of the project and its related impacts.

The stakeholders were informed regarding project benefits. Importance of the

project in terms of utilization of renewable energy resources and mitigation of

climate change was highlighted in during the interactive session. The photograph

of the interactive session held between during public consultation is shown in the

Figure VIII.1.

The meeting had a positive ambience and the participants supported the Project.

The discussion was intended to understand public opinion of the proposed

project.

Outcome of the public consutlation are as follows:

(a) The local public was aware about the wind energy project

IRL has conducted knowledge sharing camps for proposed project with

the intention to create awareness about the wind energy project among

the people. Local public was versed with the knowledge about wind

turbines and same was also reflected during the public consultation.

(b) Gist of Views of the public about the proposed project

Villagers were happy, as huge investment was planned in the

area. They were excited about new employment opportunities and

infrastructure developments in the area. The project will generate

employment to villagers.

The separate access roads are also welcomed by the villagers as

it will improve their accessibility to the fields.

Villagers expect more cashflow, income generation & thereby

economy development of the area.

Few villagers raised the concern that noise generation due WTG

might scare their cattle away. This concern of villagers was

addressed by giving example of already operating wind turbine in

Page 91: Social- Environmental Impact Study Report

91

the surrounding area where the cattle routinely graze underneath

the operating turbine. Also it was addressed that generation of

noise will be minimal due to the technology and design used for

the proposed project WTGs.

The expectation level with regard to community and individual

benefits from the proposed project included consistent power

supply as there is frequent power shut down in the area.

The public mentioned that they have not come across any case of bird collision or bird injury due to existing wind turbines in the surrounding area.

Figure VIII.1

Stakeholders during Public Consultation

Page 92: Social- Environmental Impact Study Report

92

List of stakeholder Attendees during public consultation

Page 93: Social- Environmental Impact Study Report

93

8.2 FINDINGS AND RECOMMENDATIONS

The proposed project is not generating any solid or liquid effluents and thereby pollution of land, surface water or ground water resources is not anticipated.

Wind energy project are considered as green projects which have either insignificant or minimal negative impact on the surrounding environment. The negative impact are reversible in nature and can be mitigated by proper Environmental Management Plan (EMP).

It is recommended to follow the EMP for construction and operational phases of the project in order to mitigate the adverse impacts.

During site recoinaissance survey it was observed that few human settlements are in the close vicinity of the proposed wind farm site. During interaction with residents of settlement it was understood that they have migrated to revenue land and managing their livelihood through farming and livestocks.

There is no phyical diplacement or economic displacment, however it is recommended to IRL to consider alternate feasible site for WTG locations which are located less than 300 m to such settlement, in order to ensure that there will be no hardships due to community health and safety issues during the due course of implementation and long run of the project.

It is recommended to IRL to support the activities such as development and improvement of the educational and medical facilities in the area as a part of CSR activity since the area is deprived of these facilities.

The major source of income in the area is from tourism and farming. The proposed project will additionally generate of temporary and long term employment oppurtunities.

Project will have positive socioeconomic benefits in the surrounding villages.

This project attracts CDM benefits for which relevant study is required to be undertaken after execution.

The proposed wind project falls under category “B” implying limited minimal social or environmental impacts - specific to site, largely reversible and which can readily be managed through envisaged mitigation measures.

It can be concluded that proposed project is environment-friendly and environmentally sustainable in the long run.

Page 94: Social- Environmental Impact Study Report

94

APPENDIX 1

COORDINATE LOCATION OF WTGs

Turbine ID Turbine Easting* (m) Northing* (m)

185 WTG Points

1 DANT202 734532 2943386

2 DANT201 734414 2943750

3 DANT205 734487 2944402

4 DANT203 735041 2943914

5 DANT204 734868 2944222

6 DANT206 734298 2944708

7 DANT208 735020 2944944

8 DANT207 734832 2945256

9 DANT200 733931 2943882

10 DANT199 733702 2944171

11 DANT209 735293 2944675

12 DANT210 735569 2944441

13 DANT197 734014 2945165

14 DANT196 733836 2945463

15 DANT195 733600 2945742

16 DANT194 733113 2945912

17 DANT198 734743 2945685

18 DANT193 732926 2946217

19 DANT192 732820 2946579

20 DANT191 732713 2946931

21 DANT179 732215 2946010

22 DANT178 731745 2946209

23 DANT190 732730 2947328

24 DANT189 732569 2947667

25 DANT181 732032 2947151

26 DANT180 732062 2946765

27 DANT177 731396 2946561

28 DANT176 731214 2946895

29 DANT188 732642 2948092

30 DANT187 732449 2948429

31 DANT185 732132 2948694

32 DANT184 732022 2949129

33 DANT183 731443 2948567

34 DANT186 732927 2948934

35 DANT182 731746 2948266

36 DANT173 730390 2946270

37 DANT174 730446 2945730

38 DANT175 730633 2945285

39 DAN-T3 731406 2941519

40 DAN-T4 731248 2940638

41 DANT94 742222 2937458

42 DANT6 732114 2940460

43 DANT7 731489 2940185

44 DANT8 731639 2939913

45 DANT9 731904 2939646

46 DANT14 732691 2940132

Page 95: Social- Environmental Impact Study Report

95

Turbine ID Turbine Easting* (m) Northing* (m)

47 DANT13 732825 2940594

48 DANT15 733065 2939787

49 DANT16 733575 2939086

50 DANT12 732283 2938819

51 DANT11 732421 2939128

52 DANT10 732186 2939406

53 DAN-T2 730467 2942136

54 DAN-T1 729776 2942327

55 DANT17 734485 2940494

56 DANT18 734853 2940419

57 DANT20 735147 2939204

58 DANT21 735379 2938925

59 DANT25 736281 2937831

60 DANT34 737550 2935058

61 DANT35 737522 2934557

62 DANT36 738029 2934213

63 DANT37 738558 2933868

64 DANT38 738713 2933579

65 DANT39 739050 2933268

66 DANT40 738907 2932871

67 DANT41 739070 2932558

68 DANT42 739309 2932240

69 DANT56 741824 2936884

70 DANT57 742244 2936780

71 DANT55 740710 2936728

72 DANT62 741718 2935184

73 DANT63 741780 2934859

74 DANT64 741872 2934486

75 DANT61 741612 2935650

76 DANT86 742995 2935269

77 DANT85 743499 2935226

78 DANT58 742461 2936510

79 DANT92 742918 2936955

80 DANT91 743259 2936829

81 DANT90 743484 2936557

82 DANT65 741876 2934093

83 DANT66 741954 2933757

84 DANT67 741955 2933316

85 DANT68 742147 2932874

86 DANT69 742890 2932833

87 DANT70 742555 2932452

88 DANT71 742400 2932049

89 DANT72 742537 2931765

90 DANT73 743781 2931583

91 DANT108 739011 2941868

92 DANT155 748745 2944987

93 DANT154 748804 2944652

94 DANT153 748233 2944034

95 DANT152 748397 2943443

96 DANT150 748396 2942994

Page 96: Social- Environmental Impact Study Report

96

Turbine ID Turbine Easting* (m) Northing* (m)

97 DANT151 748923 2943144

98 DANT148 749563 2942662

99 DANT149 748755 2942595

100 DANT134 747171 2942233

101 DANT133 747195 2941364

102 DANT132 746904 2941044

103 DANT131 746614 2940529

104 DANT130 746662 2939849

105 DANT127 745947 2939154

106 DANT126 746180 2938944

107 DANT125 745978 2938562

108 DANT124 745846 2938236

109 DANT137 747409 2939582

110 DANT138 747672 2939395

111 DANT128 746934 2939106

112 DANT156 747127 2937530

113 DANT157 747214 2937205

114 DANT158 747434 2936726

115 DANT159 747456 2936400

116 DANT165 748419 2936240

117 DANT164 748447 2936619

118 DANT162 748556 2936970

119 DANT161 748612 2937475

120 DANT163 749311 2936955

121 DANT160 748272 2937717

122 DANT139 749081 2938465

123 DANT140 750033 2938315

124 DANT141 749927 2939541

125 DANT143 750190 2940349

126 DANT142 750626 2940332

127 DANT147 750804 2941971

128 DANT144 749544 2941031

129 DANT145 749503 2941410

130 DANT146 749986 2941792

131 DANT135 748141 2940986

132 DANT136 748196 2940624

133 DANT129 746763 2939384

134 DANT166 748498 2935865

135 DANT167 748666 2935528

136 DANT168 748865 2935155

137 DANT169 748320 2935058

138 DANT170 748337 2934611

139 DANT171 749215 2933096

140 DANT172 749482 2932534

141 DANT80 746315 2933767

142 DANT79 746396 2933156

143 DANT119 744648 2936776

144 DANT120 744581 2936424

145 DANT121 744938 2936289

146 DANT122 744706 2935900

Page 97: Social- Environmental Impact Study Report

97

Turbine ID Turbine Easting* (m) Northing* (m)

147 DANT123 745023 2935476

148 DANT83 745095 2934778

149 DANT82 745053 2934442

150 DANT81 744938 2934158

151 DANT117 743793 2936975

152 DANT118 744060 2936700

153 DANT89 743967 2936271

154 DANT88 744177 2935821

155 DANT84 744420 2934966

156 DANT78 745259 2932962

157 DANT77 745314 2932646

158 DANT76 745561 2931779

159 DANT74 744911 2931599

160 DANT75 744785 2931958

161 DAN-T5 731605 2940550

162 DANT22 736017 2939233

163 DANT24 736228 2938228

164 DANT23 736249 2939046

165 DANT19 736430 2940542

166 DANT26 736451 2937596

167 DANT27 736690 2937340

168 DANT31 737004 2935770

169 DANT32 737081 2935457

170 DANT28 737211 2937061

171 DANT29 737745 2936889

172 DANT33 737835 2935438

173 DANT30 738015 2936114

174 DANT51 738677 2938014

175 DANT52 739323 2938121

176 DANT53 739361 2937794

177 DANT54 740154 2937665

178 DANT98 740843 2938320

179 DANT97 741436 2938085

180 DANT96 741476 2937782

181 DANT95 741739 2937602

182 DANT59 742418 2935938

183 DANT93 742629 2937178

184 DANT60 742789 2935936

185 DANT87 743625 2935807

25 WTG points

1 DANT44 737302 2941352

2 DANT43 737386 2941671

3 DANT45 737431 2940997

4 DANT47 737856 2940331

5 DANT46 737889 2940890

6 DANT50 737983 2938879

7 DANT48 738508 2940360

8 DANT109 738600 2942290

9 DANT49 738837 2940174

10 DANT107 739277 2941586

Page 98: Social- Environmental Impact Study Report

98

Turbine ID Turbine Easting* (m) Northing* (m)

11 DANT104 739279 2940614

12 DANT103 739464 2940391

13 DANT102 739612 2940095

14 DANT99 739702 2939114

15 DANT106 739713 2941518

16 DANT105 739753 2941126

17 DANT101 739791 2939858

18 DANT100 740154 2939706

19 DANT111 740186 2942637

20 DANT112 740274 2942349

21 DANT110 740277 2943041

22 DANT113 740570 2941000

23 DANT114 740671 2940724

24 DANT115 740761 2940352

25 DANT116 741072 2940150

* Co-ordinate system is UTM Zone 42 R, WGS84 datum.

Page 99: Social- Environmental Impact Study Report

99

APPENDIX 2

MICROSITING DRAWING FOR 185 LOCATIONS

Page 100: Social- Environmental Impact Study Report

100

APPENDIX 2

MICROSITING DRAWING FOR 25 LOCATIONS

Page 101: Social- Environmental Impact Study Report

101

APPENDIX 3

AMBIENT AIR MONITORING LOCATIONS MAP

Page 102: Social- Environmental Impact Study Report

102

APPENDIX 4

NATIONAL AMBIENT AIR QUALITY STANDARDS

S.No. Pollutant Time

Weighted Average

Concentration in Ambient Air

Industrial, Residential, Rural and Other area

Ecologically Sensitive

Area (notified by Central

Government

Methods of Measurement

(1) (2) (3) (4) (5) (6)

1 Sulphur Dioxide (SO2), µg/m3

Annual* 50 20 -Improved West and Gaeke

24 hours** 80 80 -Ultraviolet

Fluorescence

2 Nitrogen Dioxide (NO2), µg/m3

Annual* 40 30 -Modified Jacob & Hochheiser

(Na-Arsenic)

24 hours** 80 80 - Chemiluminescence

3

Particulate Matter (size less than 10 µm) or PM10 µg/m3

Annual* 24 hours**

60

100

60

100

- Gravimetric

- TOEM

- Beta attenuation

4

Particulate Matter (size less than 2.5 µm) or PM2.5 µg/m3

Annual* 40 40 - Gravimetric

- TOEM

24 hours** 60 60 - Beta attenuation

5 Ozone (O3) µg/m3

8 hours **

100 100 - UV photometric

- Chemiluminescence

1 hour** 180 180 - Chemical method

6 Lead (Pb) µg/m3

Annual* 0.5 0.5

- AAS/ICP method after sampling on EPM 2000 or equivalent filter paper

24 hours** 1 1 - ED-XRF using Teflon filter

7 Carbon Monoxide (CO) mg/m3

8 hours ** 2 2 - Non Dispersive Infrared (NDIR)Spectroscopy 1 hour** 4 4

8 Ammonia (NH3) µg/m3

Annual* 100 100 - Chemiluminescence

24 hours** 400 400 - Indophenol blue method

9 Benzene (C6H6) µg/m3

Annual* 5 5 - Gas chromatography

based continuous analyser

Page 103: Social- Environmental Impact Study Report

103

Note- Whenever and wherever monitoring results on two consecutive days of monitoring exceed the limits specified above for the respective category, it shall be considered adequate reason to institute regular or continuous monitoring and further investigation

-The Principal rules were published in the Gazette of India, Extraordinary vide number S.O. 844(E), dated the 19th November , 1986; and subsequently amended vide numbers S.O.433(E), dated the 18th April, 1987; G.S.R. 176(E), dated 2nd April 1996; and were recently amended vide numbers G.S.R 97 (E), dated the 18 th February, 2009; G.S.R. 149(E), dated the 4th March, 2009;G.S.R. 512(E0, dated the 9th July, 2009; G.S.R. 543(E), dated the 22nd July 2009;G.S.R.595 (E), dated the 21st August 2009; and G.S.R 794(E), dated the 4th November ,2009.

- Adsorption and Desorption followed by GC analysis

10

Benzo (α) Pyrene (BaP) -Particulate Phase only ng/m3

Annual* 1 1 - Solvent extraction

followed by HPLC/GC analysis

11 Arsenic (As), ng/m3

Annual* 6 6

- AAS/ICP method after sampling on EPM 2000 or equivalent filter paper

12 Nickel (Ni),ng/m3

Annual* 20 20

- AAS/ICP method after sampling on EPM 2000 or equivalent filter paper

* Annual Arithmetic mean of minimum 104 measurements in a year at a particular site taken twice a week 24 hourly at uniform intervals.

** 24 hourly or 8 hourly or 01 hourly monitored values, as applicable, shall be complied with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring.

Page 104: Social- Environmental Impact Study Report

104

APPENDIX 5

NOISE MONITORING LOCATIONS MAP

Page 105: Social- Environmental Impact Study Report

105

APPENDIX 6

NOISE MONITORING DATA

Location N1: Dangri Village Monitoring Period: 19.03.12 & 20.03.12 Environmental Setting: Residential Area

TIME

(IN HRS.)

NOISE LEVEL

IN dB (A)

AVERAGE DAY NOISE

LEVEL dB (A) (6.00

A.M TO 10.00 P.M)

AVERAGE NIGHT NOISE

LEVEL dB (A) (10.00 P.M TO 06.00

A.M)

DAY TIME (6.00 A.M TO 10.00 P.M)

Standard Limits in dB (A)

NIGHT TIME (10.00 P.M TO

06.00 A.M) Standard Limits

in dB (A)

06.00 AM 36.6

46.2 37.8

(A)Industrial

area-75 (B)Commercial

area-65

(C)Residential area-55

(D)Silence zone-50

(A)Industrial

area-70 (B)Commercial

area-55

(C)Residential area-45

(D)Silence zone-40

07.00 AM 39.9

08.00 AM 43.1

09.00 AM 45.0

10.00 AM 48.6

11.00 AM 49.9

12.00 PM 53.1

01.00 PM 54.5

02.00 PM 51.5

03.00 PM 50.0

04.00 PM 47.6

05.00 PM 45.7

06.00 PM 44.9

07.00 PM 43.5

08.00 PM 45.1

09.00 PM 41.4

10.00 PM 40.3

11.00 PM 40.3

12.00 AM 39.9

01.00 AM 37.9

02.00 AM 36.7

03.00 AM 35.0

04.00 AM 34.0

05.00 AM 35.3

Page 106: Social- Environmental Impact Study Report

106

Location N2: Bhainsra Village Monitoring Period: 23.03.12 & 24.03.12 Environmental Setting: Residential Zone

TIME

(IN HRS.)

NOISE LEVEL

IN dB (A)

AVERAGE DAY NOISE

LEVEL dB (A) (6.00

A.M TO 10.00 P.M)

AVERAGE NIGHT NOISE

LEVEL dB (A) (10.00 P.M TO 06.00

A.M)

DAY TIME (6.00 A.M TO

10.00 P.M) Standard Limits

in dB (A)

NIGHT TIME (10.00 P.M TO

06.00 A.M) Standard Limits

in dB (A)

06.00 AM 38.6

46.8 39.0

(A)Industrial area-75

(B)Commercial area-65

(C)Residential area-55

(D)Silence zone-50

(A)Industrial area-70

(B)Commercial area-55

(C)Residential area-45

(D)Silence zone-40

07.00 AM 41.9

08.00 AM 43.6

09.00 AM 45.2

10.00 AM 46.7

11.00 AM 52.0

12.00 PM 55.7

01.00 PM 58.8

02.00 PM 49.8

03.00 PM 50.8

04.00 PM 48.7

05.00 PM 46.5

06.00 PM 43.8

07.00 PM 43.7

08.00 PM 43.4

09.00 PM 40.1

10.00 PM 41.8

11.00 PM 41.1

12.00 AM 39.8

01.00 AM 37.5

02.00 AM 37.0

03.00 AM 36.5

04.00 AM 39.1

05.00 AM 39.8

Page 107: Social- Environmental Impact Study Report

107

Location N3: Lakhmona Village Monitoring Period: 22.03.12 & 23.03.12 Environmental Setting: Residential Zone

TIME

(IN HRS.)

NOISE LEVEL IN dB

(A)

AVERAGE DAY NOISE

LEVEL dB (A) (6.00

A.M TO 10.00 P.M)

AVERAGE NIGHT NOISE

LEVEL dB (A) (10.00 P.M TO 06.00

A.M)

DAY TIME (6.00 A.M TO

10.00 P.M) Standard Limits

in dB (A)

NIGHT TIME (10.00 P.M TO

06.00 A.M) Standard Limits

in dB (A)

06.00 AM 34.1

45.5 38.3

(A)Industrial area-75

(B)Commercial area-65

(C)Residential area-55

(D)Silence zone-50

(A)Industrial area-70

(B)Commercial area-55

(C)Residential area-45

(D)Silence zone-40

07.00 AM 36.6

08.00 AM 41.2

09.00 AM 43.0

10.00 AM 44.7

11.00 AM 47.1

12.00 PM 51.7

01.00 PM 55.2

02.00 PM 54.4

03.00 PM 51.9

04.00 PM 47.6

05.00 PM 47.7

06.00 PM 43.8

07.00 PM 43.5

08.00 PM 43.8

09.00 PM 43.0

10.00 PM 41.9

11.00 PM 40.0

12.00 AM 39.1

01.00 AM 36.6

02.00 AM 39.7

03.00 AM 35.9

04.00 AM 37.5

05.00 AM 36.0

Page 108: Social- Environmental Impact Study Report

108

Location N4: Lakhmanser Village Monitoring Period: 26.03.12 & 27.03.12 Environmental Setting: Residential Zone

TIME

(IN HRS.)

NOISE LEVEL IN dB

(A)

AVERAGE DAY NOISE

LEVEL dB (A) (6.00

A.M TO 10.00 P.M)

AVERAGE NIGHT NOISE

LEVEL dB (A) (10.00 P.M TO 06.00

A.M)

DAY TIME (6.00 A.M TO

10.00 P.M) Standard Limits

in dB (A)

NIGHT TIME (10.00 P.M TO

06.00 A.M) Standard Limits

in dB (A)

06.00 AM 37.6

47.6 40.6

(A)Industrial area-75

(B)Commercial area-65

(C)Residential area-55

(D)Silence zone-50

(A)Industrial area-70

(B)Commercial area-55

(C)Residential area-45

(D)Silence zone-40

07.00 AM 42.0

08.00 AM 44.3

09.00 AM 45.6

10.00 AM 47.9

11.00 AM 51.1

12.00 PM 53.3

01.00 PM 55.5

02.00 PM 52.9

03.00 PM 51.1

04.00 PM 49.9

05.00 PM 47.8

06.00 PM 46.9

07.00 PM 46.2

08.00 PM 45.8

09.00 PM 43.8

10.00 PM 43.2

11.00 PM 42.8

12.00 AM 42.5

01.00 AM 41.1

02.00 AM 39.8

03.00 AM 39.7

04.00 AM 37.4

05.00 AM 38.8

Page 109: Social- Environmental Impact Study Report

109

APPENDIX 7

AMBIENT AIR QUALITY STANDARDS IN RESPECT OF NOISE

Area Code Category of Area/ Zone

Limit in dBA (Leq)*

Day Time Night Time

(A) Industrial area 75 70

(B) Commercial area 65 55

(C) Residential area 55 45

(D) Silence Zone 50 40

Note:

1. Day time shall mean from 6.00 a.m. to 10.00 p.m.

2. Night time shall mean from 10.00 p.m. to 6.00 a.m.

3. Silence zone is defined as an area comprising not less than 100 metres around hospitals, educational institutes and courts. The silence zones are zones which are declared as such by the competent

authority.

4. Mixed categories of areas may be declared as one of the four above

mentioned categories by the competent authority.

* dB(A) Leq denotes the time weighted average of the level of sound in decibels

on scale A which is relatable to human hearing.

A "decibel" is a unit in which noise is measured.

"A", in dB(A) Leq, denotes the frequency weighting in the measurement of noise

and corresponds to frequency response characteristics of the human ear.

Leq: It is an energy mean of the noise level over a specified period.

Page 110: Social- Environmental Impact Study Report

110

APPENDIX 8

NOISE LEVEL AS PER IFC GUIDELINES

Receptor Daytime

One Hour LAeq (dBA)

Day time (07:00 - 22:00)

Night time (22:00 - 07:00)

Residential; institutional; Educational

55 45

Industrial, commercial

70 70

Page 111: Social- Environmental Impact Study Report

111

APPENDIX 9

GROUND WATER MONITORING LOCATIONS MAP

Page 112: Social- Environmental Impact Study Report

112

APPENDIX 10

GROUND WATER QUALITY

Sr. No

Parameter Unit

Dangri Village,

Tube well (GW)

Mehreri, Tube well (GW)

Bhainsra, Tube well

(GW)

Laxmansar Village,

Tube well (GW)

1 pH (at 270C) 6.78 7.6 7.21 7.86

2 Temperature 0C 26 27 26 26

3 Turbidity NTU 5.4 18 7.2 8.2

4

Electrical

Conductivity(at

25⁰C) µS/cm 2400 5950 2330 1758

5 Colour Hazen <1.0 <1.0 <1.0 <1.0

6 Total Dissolved

solids mg/l 1108 3020 1134 940

7 Total Suspended

Solids mg/l 8.3 20 9.6 11.6

8 Total Alkalinity mg/l 471.24 714 247.52 428.4

9 Total Hardness mg/l 396 241.56 986.04 198

10 Chloride as Cl mg/l 357.01 1359.58 270 299.91

11 Sulphate as SO4 mg/l 89.88 297.6 149.31 67.19

12 Nitrate as NO3 mg/l 51.88 62.7 246.03 7.01

13 Fluoride as F mg/l <0.1 <0.1 <0.1 <0.1

14 Sodium as Na mg/l 320 1200 200 400

15 Potassium as K mg/l 3 6 5 5

16 Salinity mg/l 645 2456 487.76 541

17 T KN mg/l <0.3 <0.3 <0.3 <0.3

18 Total phosphorus mg/l <0.05 <0.05 <0.05 <0.05

19 Dissolved Oxygen mg/l 6.7 6.2 5.6 6.9

20 BOD mg/l <2.0 3.21 <2.0 <2.0

21 COD mg/l <4.0 15.62 <4.0 <4.0

22 Phenolic Compound mg/l <0.001 <0.001 <0.001 <0.001

23 Arsenic mg/l <0.01 <0.01 <0.01 <0.01

24 Mercury as Hg mg/l <0.001 <0.001 <0.001 <0.001

25 Lead mg/l 0.03 0.04 <0.005 <0.005

26 Cadmium as Cd mg/l <0.002 <0.002 <0.002 <0.002

27 Hexavalent Chromium mg/l 0.09 0.08 <0.05 <0.05

28 Total Chromium mg/l 0.2 0.25 0.24 0.24

29 Copper as Cu mg/l <0.02 <0.02 <0.02 <0.02

30 Zinc as Zn mg/l <0.02 0.08 0.75 0.23

31 Selenium as Se mg/l <0.005 <0.005 <0.005 <0.005

Page 113: Social- Environmental Impact Study Report

113

Sr. No

Parameter Unit

Dangri Village,

Tube well (GW)

Mehreri, Tube well (GW)

Bhainsra, Tube well

(GW)

Laxmansar Village,

Tube well (GW)

32 Iron as Fe mg/l <0.05 0.23 0.08 0.1

33 Oil & Grease mg/l <1.4 <1.4 <1.4 <1.4

34 Ca mg/l 66.53 20.59 142.56 25.34

35 TPH mg/l <0.02 <0.02 <0.02 <0.02

36 MBAS mg/l <0.02 <0.02 <0.02 <0.02

37 PCB mg/l <0.001 <0.001 <0.001 <0.001

38 SiO2 mg/l <0.01 3.2 <0.01 <0.01

39 Mn mg/l <0.02 0.04 <0.02 <0.02

40 PO4 mg/l <0.15 <0.15 <0.15 <0.15

41 Ba mg/l <0.1 <0.1 <0.1 <0.1

42 Mg mg/l 55.12 45.62 151.11 32.31

43 Total Coliform MPN/100ml <2 <2 30 500

44 Faecal Coliform /100ml Absent Absent Present Present

45 Phytoplankton Units/l --- --- --- ---

46 Zooplankton Units/l --- --- --- ---

Page 114: Social- Environmental Impact Study Report

114

APPENDIX 11

SOIL MONITORING LOCATIONS MAP

Page 115: Social- Environmental Impact Study Report

115

APPENDIX 12

SOIL CHARACTERISTICS

Sr. No Parameter Unit Dangri Village

Mehreri Project

Site Bhainsra

Laxmansar Village

1 Texture Sand Sandy

loam Sand Sand

2

pH (1:2.5) at

27⁰C

8.47 8.91 9.02 9.69

3 Permeability Cm/hr 5.62 4.42 5.42 5.82

4

Electrical Conductivity at

25⁰C

µs/cm 77.21 118.34 126.1 190.99

5 Nitrite mg/kg < 1 4.24 < 1 < 1

6 Nitrate mg/kg 2.58 5.2 4.88 4.6

7 Phosphates mg/kg <12 <12 <12 21.83

8 TPH mg/kg <1.0 <1.0 <1.0 <1.0

9 N mg/kg 87.81 109.76 76.83 82.32

10 As mg/kg < 0.2 < 0.2 < 0.2 < 0.2

11 Hg mg/kg < 0.1 < 0.1 < 0.1 < 0.1

12 Pb mg/kg 1.96 2.08 1.04 0.84

13 Cd mg/kg <0.04 <0.04 <0.04 <0.04

14 Cr mg/kg < 2.0 < 2.0 < 2.0 < 2.0

15 Cu mg/kg <0.4 <0.4 <0.4 <0.4

16 Zn mg/kg 0.44 <0.4 0.74 <0.4

17 P mg/kg <4 < 4 <4 7.12

18 Fe mg/kg 3.36 2.99 <1.4 1.94

19 Mn mg/kg 4.86 3.62 4.54 3.62

20 Ni mg/kg 0.84 0.48 <0.2 <0.2

21 Ba mg/kg < 1.0 < 1.0 < 1.0 < 1.0

22 K mg/kg 70 200 300 130

23 Porosity % 44.35 43.59 47.1 42.85

24 Total

Hydrocarbons mg/kg <0.1 <0.1 <0.1 <0.1

25

Cation exchange capacity

meq/100g 5.76 12.56 5.8 6.2

26 Sand %(W/W) 92.2 69.5 93.8 94.4

27 Silt %(W/W) 3.8 28.5 3.2 1.4

28 Clay %(W/W) 4 2 3 4.2

Page 116: Social- Environmental Impact Study Report

116

APPENDIX 13

DEMOGRAPHIC STRUCTURE OF THE STUDY AREA

NAME of the village

No of Households

Population Population 0-6 Years SC Population ST Population

Total Male Female Total Male Female Total Male Female Total Male Female

Rajgarh 161 952 563 389 207 139 68 48 27 21 57 34 23

Bahla Basti 55 347 194 153 93 50 43 5 2 3 0 0 0

Chhodiya 55 335 189 146 78 44 34 180 96 84 5 4 1

Laxmansar 75 487 289 198 121 74 47 55 33 22 0 0 0

Dangri 394 2400 1284 1116 592 313 279 70 39 31 498 255 243

Mehreri 70 461 240 221 113 55 58 59 27 32 0 0 0

Page 117: Social- Environmental Impact Study Report

117

APPENDIX 14

LITERACY LEVEL IN THE STUDY AREA

NAME of the village

Literate Illiterate

Total Male Female Total Male Female

Rajgarh 390 271 119 562 292 270

Bahla Basti 148 93 55 199 101 98

Chhodiya 147 107 40 188 82 106

Laxmansar 161 123 38 326 166 160

Dangri 827 613 214 1573 671 902

Mehreri 172 129 43 289 111 178

Page 118: Social- Environmental Impact Study Report

118

APPENDIX 15

OCCUPATIONAL STRUCTURE

Village name

Total Workers

(Main+Marginal)

Persons

Total Workers (Main+Marginal)

Males

Total Workers (Main+Marginal)

Females

Main

Workers

- Persons

Main Workers - Males

Main Workers

- Females

Main Workers

Cultivators - Persons

Main Workers

Cultivators - Males

Main Workers

Cultivators -

Females

Rajgarh 535 311 224 424 253 171 305 181 124

Bahla Basti 97 88 9 92 86 6 53 49 4

Chhodiya 119 85 34 93 85 8 70 63 7

Laxmansar 254 146 108 202 138 64 123 62 61

Dangri 1066 667 399 358 291 67 101 90 11

Mehreri 209 120 89 121 98 23 78 66 12

Page 119: Social- Environmental Impact Study Report

119

APPENDIX 15 (continued)

OCCUPATIONAL STRUCTURE

Village name

Main Workers

Agricultural Labourers -

Persons

Main Workers

Agricultural Labourers -

Males

Main Workers

Agricultural Labourers -

Females

Main Workers

Household Industry - Persons

Main Workers

Household Industry -

Males

Main Workers

Household Industry - Females

Main Workers Other -

Persons

Main Workers Other - Males

Main Workers Other -

Females

Rajgarh 7 6 1 3 3 0 109 63 46

Bahla Basti 4 3 1 0 0 0 35 34 1

Chhodiya 0 0 0 0 0 0 23 22 1

Laxmansar 3 0 3 1 1 0 75 75 0

Dangri 0 0 0 99 98 1 158 103 55

Mehreri 0 0 0 0 0 0 43 32 11

Page 120: Social- Environmental Impact Study Report

APPENDIX 16 Bird and Bat Study for Dangri Wind farm project at Jaisalmer, Rajasthan

Page 121: Social- Environmental Impact Study Report

BIRD AND BAT STUDY FOR DANGRI

WINDFARM PROJECT AT JAISALMER,

RAJASTHAN

Submitted to

INOX Renewable Limited

Submitted by

Tata Consulting Engineers

Expert

Dr. Bharat Jethva

Page 122: Social- Environmental Impact Study Report

i

Preface

It is largely believed that any industrial development is essentially a destructive activity, where

ecology suffers at the altar of economy, fortunately for wind energy projects, it is not true. It is

therefore the harvesting of wind energy has widespread encouragement as it does not harm

or cause any environmental degradation and adverse impact on forests and wildlife.

However, if wind farms are developed in and around forest and wildlife areas, there are still

wide concern about their placements and conservation of habitats and species.

It is in this context M/s Inox Private Limited approached us to get a thorough and

independent study done on their proposed wind farm project in Jaisalmer district. The study

could also be a prerequisite for getting approval and financial assistance from various

agencies.

In order to provide facts, and support informed decision on the development versus nature

conservation issues, we took up this study. As an independent agency, we carried out

intensive fieldwork for firsthand data collection, surveyed relevant literature, interviewed local

people, gathered maps and project details from the company and carefully analyzed the

situation at the project site and built our own opinion. The study was restricted to project area

and its 10 km periphery from the project area.

We are happy to provide our technical input at the planning stage for this ecologically

compatible industry in this ecologically important region. We anticipate that the user agencies

would perceive this study in right sense.

Page 123: Social- Environmental Impact Study Report

ii

Executive Summary

1. M/s Inox Private Limited has planned to install 185 wind turbines in 3 villages of

Jaisalmer District. These villages are Dangri, Bhesda, Mehriri. The site selected is

one of the most feasible and scarcely available locations in the State for wind farm

development and therefore, company does not have any other alternative to this

site. The company proposes to develop wind farm by procuring government land

from Rajasthan Government. Owing to widespread concern over the windfarm

development and bird, bats mortalities and impacts on natural habitats the company

approached our agency to carry out a comprehensive study on the issue.

2. Subsequently, a detailed ecological study of Birds, Bats and natural habitats in

relation to project activities is carried out by a team led by expert wildlife biologist.

The study is carried out in line with several other international studies carried out

elsewhere. Field visits were made to carryout direct and indirect observations;

interview survey and survey of secondary literature for conducting the study. Study

also gave special emphasis on impacts of project on Birds, Bats and endemic and

threatened birds of the region.

3. The study carefully reviewed the distances of the proposed windmill locations from

sensitive receptors such as Desert National Park/Grasslands, wetlands, Bat roosting

sites.

4. The study envisaged lower impacts of proposed project on birds, bats and natural

habitats and subsequently suggested a brief management plan for the project. This

chiefly include, annual monitoring of birds and bats mortalities, precautions to avoid

birds attracted to carcasses, training project personals and post construction

planning and management.

5. It is opined that the project could be ecologically compatible and shall have

negligible impacts on birds and bats of the region. However, this could be true only if

the suggested broad mitigation plan is implemented and executed by the company

and supervised by the governmental agencies.

Page 124: Social- Environmental Impact Study Report

iii

Contents 1. Introduction 1

1.1. Wind energy projects and concerns of Bird & Bats mortalities 1

1.2. Wind Energy Sector Promotion by the Indian Government 2

1.3. Legal framework & India’s international obligations for biodiversity conservation

3

1.4. Objectives & scope of the work 6

2. Methodology 7

2.1. Basic frame work of data collection 7

2.2. Basic understanding of the project & surrounding areas 8

2.2.1. Field visits 8

22.2. Orientation and location 8

2.2.3. Surrounding area and geography 8

2.3. Baseline status of birds and bats species 8

2.4. Important bird & bats habitats, hotspots and their distances 10

2.5. Literature Review 10

2.6. Analysis to evaluate the potential impacts. 10

3. Ecological Scenario Assessments 11

3.1. Basic understanding of the project & surrounding areas 11

3.2. Baseline status of birds and bats species 12

3.2.1. Bird Species diversity 12

3.2.2. Bird species abundance 13

3.2.3. Bat species abundance 15

3.2.4. Bat Species in the project area 17

3.3. Migratory bird Flyway/routes 18

3.4. Natural habitats/Protected Areas 19

3.4.1. Grasslands 19

3.4.2. The Desert National Park 20

3.4.3 Wetlands 21

3.5. Threatened Birds species 22

3.5.1. Great Indian Bustard 22

4. Impact Analysis 26

4.1. Analysis to Predict the Potential Impacts on Birds 26

4.1.1. Disturbance leading to displacement of bird groups 28

4.1.2. Barrier to movements 28

4.1.3. Collision with turbine blades 28

Page 125: Social- Environmental Impact Study Report

iv

4.1.4. Direct habitat loss 28

4.2. Analysis to predict the potential impacts on Bats 28

4.3. Analysis to evaluate overall impacts 29

5. Proposed Mitigation Plan 30

5.1. Annual Monitoring of Bird Hits and Mortality 30

5.2. Precautions to avoid disturbance to wildlife 30

5.3. Regular removal of carcasses from the project areas 31

5.4. Training Project Personals 31

5.5. Post Construction Planning and management 31

6. Conclusions 32

7. References 33

Annexure 35

Page 126: Social- Environmental Impact Study Report

v

List of Tables Maps & Figures

MAPS

3.1 Desert National Park and the proposed project site in Jaisalmer district. 20

2.1 Landuse types in and around proposed project site showing absence of wetlands. 21

TABLES

3.1 Status of birds in and around the project area. 13

3.2 Encounter rate of birds recorded from the project area. 14

4.1 Bird group wise comparison with known impacts 27

4.2 General inferences drawn from the various aspects of the study 29

PLATES

3.1 Proposed project site near Dangri-Ramsar villages in Rajasthan (February 2012). 11

3.2 Megachiroptera, Indian Flying fox on the roost at Gadisar Pond in Jaisalmer. 16

3.3 Central Asian Flyway for migratory birds (Wetlands International). 18

3.4 Migratory Crane Flyway (Source International Crane Foundation Website) 18

3.5 Representative photo of vegetation and habitat types present in the project site. 19

3.6 Great Indian Bustards in Grasslands. 23

3.7 Interview of local people to know the status of endangered birds in the project area. 24

Page 127: Social- Environmental Impact Study Report

1

1. Introduction

1.1. Wind energy projects and concerns of Bird & Bats mortalities

Wind farms are a relatively new method of obtaining ‗clean‘ energy by avoiding air pollution

and other forms of environmental degradation associated with fossil fuel technologies (Nelson

and Curry 1995) and have received strong public support as an alternative energy source

(Leddy et al. 1999). Moreover, wind farms have shown a spectacular growth because they

have reduced the costs of energy production. This phenomenon has resulted in a

proliferation of wind farms around the world (Germany, Holland, Spain, United States, etc.)

(Osborn et al. 2000).

However, there are wide concerns over wind farm developments, that they are cause of bird

and bats mortalities. Bird and bats are known to hit windmill blades and die. There are three

special concerns that arise with respect to the development of wind farms. Several studies

across the world have raised the concerns on the wind farm development.

They represent a source of noise, they have an aesthetic impact on landscapes and they

might represent a supplemental negative impact on bird populations (Nelson and Curry

1995). Wind turbine farms in landscapes have given rise to much controversy relating to bird

conservation issues in many European countries (Larsen and Madsen 2000). Wind turbines

seem to add an obstacle for bird movements and research has shown that birds fly into the

rotor blades (Morrison and Sinclair 1998).

Although some studies have recorded bird collisions with rotor blades (Orloff and Flannery

1992; Barrios 1995; Musters et al. 1996; Hunt 1999), other studies gave evidence that birds

could detect the presence of wind turbines and generally avoid them (Nelson and Curry 1995;

Osborn et al. 1998). The scarce information on the possible interactions between birds and

wind turbines has shown that: (1) waterfowl and raptors seem to be the groups with the

highest risk of collision, not directly related to their abundance (Orloff and Flannery 1993;

Osborn et al. 1998), (2) familiarity with turbines, leading to a decrease in awareness, may be

an important factor contributing to increased mortality (Orloff and Flannery 1993), (3) dark

nights increase mortality of waders (Dirksen et al. 1998), (4) passerine species appear to be

at greatest risk of colliding during spring and autumn migrations (Higgins et al. 1996; Osborn

Page 128: Social- Environmental Impact Study Report

2

et al. 1998), and (5) there is evidence that waterfowl, wading bird and raptor densities near

turbines are lower (Leddy et al. 1999). Moreover, birds avoid flying in areas with wind turbines

and their flight patterns are deferred when wind turbines are rotating or not rotating (Osborn et

al. 1998). However, up to now population-level effects have not yet been demonstrated to

reject the further development of wind power. The main purposes of our research were to

determine (1) the possible impacts of wind turbines on both the local, breeding and migratory

bird populations in one of the most important migration points between Europe and Africa, the

Strait of Gibraltar in the south of Spain, and (2) the degree of flight behavioural change in

birds resulting from the presence of a wind farm.

Research shows that wind farms can impact wildlife in 2 principal ways: 1) they can eat up or

fragment habitat and/or 2) they can directly kill birds and bats. Habitat fragmentation occurs

when wind farms and their associated roads, power lines, and other structures displace

wildlife. The impacts of habitat fragmentation go far beyond the immediate ―footprint‖ of the

wind farm, because some wildlife particularly grassland species will avoid areas with high

towers.

Bird and bat deaths occur in two ways. Birds die when they collide with turbines, power lines,

and other structures. Although bat collisions can occur (sometimes bats turn off their

echolocation and can run into things), recent scientific studies indicate that barotrauma may

be a significant cause of bat deaths at wind farms. Baratrauma occurs as bats chase the

turbine blade (their echolocation detects a moving object). As the bat gets close to the blade,

it is pulled into a low pressure area immediately behind the blade. This low pressure area

causes the bat‘s lungs to expand into its body cavity, exploding the blood capillaries in the

bat‘s lungs. This phenomenon was recently established as a significant killer of bats at an

Alberta wind farm.

1.2. Wind Energy Sector Promotion by the Indian Government

In view of the need of substantial energy to match country‘s growth, and security, Indian

government is promoting development of renewable energy projects in the country. The

government of India has announced many benefits for such projects. Wind energy projects in

India are given special incentives and benefits by the Government of India.

Page 129: Social- Environmental Impact Study Report

3

Ministry of Environment & Forests, Government of India, has issued

guidelines dtd 10.11.2003 and amendments thereafter for diversion of forest

land for non-forest purpose under the forest (conservation) act, 1980 for

promoting wind energy.

Wind Power Project does not fall in the purview of getting ―Environment

Clearance‖ under Environment Protection Act 1980.

Guidelines for declaration of Eco-Sensitive zones around National Parks and

Wildlife Sanctuaries issued by Ministry of Environment and Forests,

Government of India, dtd 9th

February 2011 also suggest promotion of green

technology and use of renewable energy in these zones.

Dandi eco-sensitive zone notification by Ministry of Environment and Forests,

Government of India, dated 13th

October 2010 (F.No. 24011/11/2009-

SICOM) also promotes setting up of non-conventional energy sources such

as wind and solar.

1.3. Legal framework & India’s international obligations for biodiversity

conservation

Though, wind farm projects are considered clean energy projects and they are

encouraged by the Governments, there are still wide concerns over their impacts on

birds, bats, natural habitats and wildlife especially when they are close to protected

areas. The impacts of wind farm projects are being studied and several studies have

shown that it can prove detrimental if the projects are placed without considering the

biodiversity conservation of the area. India being signatory to various international

conventions and treaties, it is bound to preserve its biodiversity, conserve natural

habitats, and protect migratory birds by various laws and acts. Some of the

conventions, treaties, laws, rules and acts are listed below. Any undue impacts of

project on biodiversity, wildlife, killing or torturing of animals could be subjected to these

laws.

1.3.1. Wildlife (Protection Act 1972)

The Government of India enacted Wild Life (Protection) Act 1972 with the objective of

effectively protecting the wild life of this country and to control poaching, smuggling and

illegal trade in wildlife and its derivatives. The Act was amended in January 2003 and

punishment and penalty for offences under the Act have been made more stringent.

Page 130: Social- Environmental Impact Study Report

4

The Ministry has proposed further amendments in the law by introducing more rigid

measures to strengthen the Act. The objective is to provide protection to the listed

endangered flora and fauna and ecologically important protected areas.

1.3.2. The Biological Diversity Act 2002

This act was born out of India‘s attempt to realize the objectives enshrined in the

United Nations Convention on Biological Diversity (CBD) 1992 which recognizes the

sovereign rights of states to use their own Biological Resources. The Act aims at the

conservation of biological resources and associated knowledge as well as facilitating

access to them in a sustainable manner and through a just process for purposes of

implementing the objects of the Act it establishes the National Biodiversity Authority in

Chennai.

1.3.3. The Prevention of Cruelty to Animals Act 1960

The Prevention of Cruelty to Animals Act was enacted in 1960 to prevent the infliction

of unnecessary pain or suffering on animals and to amend the laws relating to the

prevention of cruelty to animals. After the enactment of this Act, the Animal Board of

India was formed for the promotion of animal welfare.

India is also signatory to following conventions which bind and guide the country to take

initiatives for conservation of its biodiversity, wetlands and migratory species including

migratory birds.

1.3.4. Convention on Biological Diversity 1992

The Convention on Biological Diversity (CBD), known informally as the Biodiversity

Convention, is an international legally binding treaty. The Convention has three main

goals: 1) conservation of biological diversity (or biodiversity); 2) sustainable use of its

components; and 3) fair and equitable sharing of benefits arising from genetic

resources In other words, its objective is to develop national strategies for the

conservation and sustainable use of biological diversity. It is often seen as the key

document regarding sustainable development. The Convention was opened for

signature at the Earth Summit in Rio de Janeiro on 5 June 1992 and entered into force

on 29 December 1993. 2010 was the International Year of Biodiversity. The Secretariat

of the Convention on Biological Diversity is the focal point for the International Year of

Biodiversity. At the 2010 10th Conference of Parties (COP) to the Convention on

Page 131: Social- Environmental Impact Study Report

5

Biological Diversity in October in Nagoya, Japan, the Nagoya Protocol was

adopted. On 22 December 2010, the UN declared the period from 2011 to 2020 as the

UN-Decade on Biodiversity. They, hence, followed a recommendation of the CBD

signatories during COP10 at Nagoya in October 2010.

1.3.5. Ramsar Convention 1971

The Convention on Wetlands (Ramsar, Iran, 1971) -- called the "Ramsar Convention" -

- is an intergovernmental treaty that embodies the commitments of its member

countries to maintain the ecological character of their Wetlands of International

Importance and to plan for the "wise use", or sustainable use, of all of the wetlands in

their territories. Unlike the other global environmental conventions, Ramsar is not

affiliated with the United Nations system of Multilateral Environmental Agreements, but

it works very closely with the other MEAs and is a full partner among the "biodiversity-

related cluster" of treaties and agreements.

1.3.6. Convention on Migratory Species 1979

The Convention on the Conservation of Migratory Species of Wild Animals (also known

as CMS or the Bonn Convention) aims to conserve terrestrial, marine and avian

migratory species throughout their range. It is an intergovernmental treaty, concluded

under the aegis of the United Nations Environment Programme, concerned with the

conservation of wildlife and habitats on a global scale. The Convention was signed in

1979 in Bonn (hence the name) and entered into force in 1983.

Migratory species threatened with extinction are listed on Appendix I of the Convention.

CMS Parties strive towards strictly protecting these animals, conserving or restoring the

places where they live, mitigating obstacles to migration and controlling other factors

that might endanger them. Besides establishing obligations for each State joining the

Convention, CMS promotes concerted action among the Range States of many of

these species. The Agreements may range from legally binding treaties (called

Agreements) to less formal instruments, such as Memoranda of Understanding, and

can be adapted to the requirements of particular regions.

Page 132: Social- Environmental Impact Study Report

6

1.4. Objectives & scope of the work

In view of the above mention facts, country‘s laws/acts and obligations as well as

company‘s requirement to meet with international environmental safety standards, we

carried out the present study. The study was carried out with following objectives to

assess the impacts of proposed wind farm on bird, bats and natural habiatas.

i. Evaluate the proposed project site and its surrounding areas for presence bird

species, their status(migratory, threatened) and their critical habitats.

ii. Evaluate the project site and its surrounding areas for bats species, their

movement and rendezvous.

iii. Evaluate the impacts of proposed wind farm project on important natural habitas.

iv. Provide possible suggestions and mitigations for windfarm development.

Page 133: Social- Environmental Impact Study Report

7

2. Methodology 2.1. Basic frame work of data collection

As with other sources of renewable energy, wind energy is generally considered to result in

few environmental impacts. Despite this, assessment of impacts of wind farm development

on birds and bats and other biodiversity requires sufficient and systematic data on various

aspects in and around the proposed site. The prediction of impacts of wind farm industries on

birds and bats depends on understanding of the proposed activities and its extent, scale and

ecological conditions in the surrounding area. Collection of comprehensive baseline

information on birds, bats and natural habitats is a prerequisite for assessment of impacts of

wind farm development activities. It would also help in advance planning and mitigate the

impacts and ultimately managing the natural habitats and resources. The approach to

achieve the stated objectives within defined scope of work, include field surveys, interviews,

and reviews of literature. Following was the basic fame work of the data collection.

a) Basic understanding of the project & surrounding areas

i. Field visit

ii. Orientation and location

iii. Surrounding area and geography

b) Baseline status of birds and bats species

i. Species checklist prepared during field visit

ii. Encounter rate of birds calculated through transect surveys

iii. Interview survey of local people and naturalists

iv. Spatio temporal distribution of birds and bats

v. Rare, endangered and migratory species

vi. Important habitats for birds & bats

c) Important natural habitats, biodiversity hotspots and their distances

i. Protected area

ii. Wetlands

iii. Grasslands

d) Literature review

Page 134: Social- Environmental Impact Study Report

8

2.2. Basic understanding of the project & surrounding areas

It is important to understand the project area and its geography in order to collect data and

predict impacts of the project. Following activities were carried out to get basic understanding

of the project area.

2.2.1. Field visits

A field visit was conducted between 21st and 26

th February 2012 to understand and assess

the impacts of proposed wind farm development on birds. We evaluated the distribution of

birds in and around the project site.

2.2.2. Orientation and location

In order to know the orientation and location of the project site with reference to the distances

and boundaries of important bird and habitats, we studied project site maps. We also used

Global Positioning System (GPS) to find out distances from each of these. This was useful in

assessing whether the proposed project site is within the boundaries of any important bird

habitats and the Desert National park or beyond it.

2.2.3. Surrounding area and geography

In order to know the surrounding habitats, geography and land use pattern, we made a field

visit to the proposed project site, studied maps of the area and used freely available satellite

imageries on internet (Google Earth). This was useful in assessing the overall suitability of

land for wildlife and to see if it makes any part of corridors/migration route for any important

bird species or not.

2.3. Baseline status of birds and bats species

We randomly surveyed project site area and its periphery of 10 Km radius for direct and

indirect observation on birds, bats and natural habitats. A checklist of birds sighted in the

project area and their abundance was recorded. Species were identified and finalized using

standard reference bird books and existing checklists for the area. We calculated the

encountered rate of birds (i.e. bird sighted per kilometre of walk) in the project areas. Total 2

transects of 10 kilometre each were walked in the project site. This was done in morning

hours i.e. between 6:30 Am to 9:00 Am. The transects were laid between 1) Dangri to Mehriri

and 2) Dangri to Bhesda. During the transects direct sightings of bird‘s species were recorded

systematically for further analysis. For studying status of bats, we chose evening timing i.e.

Page 135: Social- Environmental Impact Study Report

9

between 6:45 PM till 7:45PM beyond this timing it was difficult to cite any flying object in the

sky.

Apart from these, In order to obtain information on birds and bats around project site, specific

search was carried out. The search efforts were made at various important areas in the study

area which includes looking for habitat specific birds in grasslands, wetlands and dense

bushes, shady trees etc.

In order to get information on bats, we made specific searches at various locations where

likelihood of bats was higher. These places include fort, large trees and abandoned houses

etc. This survey has helped us in identifying various locations of bats and their behaviour and

characteristics.

In order to acquire additional information on the distribution of birds species of the area, we

interviewed several local people who included farmers, herders and villagers, tourist guides

etc. They were asked several questions about the presence of various bird species in the

surroundings and their sightings, breeding habitats such as nests, their observation seasons

and timings etc. The respondents were also shown bird photographs from the standard bird

books in order to improve the check list of birds of the project area. They were also asked

specific questions, whether the windmill may have any negative impacts on wildlife,

agriculture and the people etc. In human dominated landscape, human response to wildlife

presence can serve as an index to understand the intensity of wildlife use of the area. Field

observations were therefore complemented by efforts to generate information from informal

consultations with local people on use of area, corridor by any wildlife species.

The information received on the status of the birds and bats species were plotted in matrix of

season, time and places with reference to the project site. This spatio-temporal distribution of

birds and bats provided us clear understanding of the species present in the project area and

their seasonality. For example, migratory birds are found in the winter season and most of

them are found in the wetlands. Now measuring the distances from wetlands would let us

know if the migratory birds would be affected from the project or not. In order to understand

the importance of the species of the project area, the birds and bats species observed in the

study were classified in the threat categories defined by the Birdlife International. The species

list was classified into endangered, vulnerable, near threatened, least concerned categories.

Page 136: Social- Environmental Impact Study Report

10

They were further classified in to migratory, resident and passage migrant‘s categories of bird

species.

2.4. Important birds & bats habitats, hotspots and their distances

The distances from important bird and habitats such as protected area i.e. Desert National

Park, Important large wetlands, and grassland area were measured using GPS. These

important areas such as Important Bird Areas (IBAs), classified by Birdlife International.

Boundary of the Desert National Park was prepared using GPS and also plotted on Google

Earth TM for better understanding or the surrounding areas and presentation. These areas

were personally visited in order to check the status of habitats i.e. grassland and wetlands etc.

2.5. Literature Review

Considering the time limitation to undertake statistically rigorous data gathering system, study

also relied on existing knowledge about the ecology and biodiversity of the region.

Importantly, there are quite a few studies undertaken in the past dealing with the impacts of

wind turbines on birds and bats and other concerns of biodiversity conservation in many

countries. Literature on wind farm and associated environmental issues, were downloaded

and collated using internet. Various relevant papers and reports were surveyed during the

study for collection of baseline information on migratory bird‘s flyways/routes, migratory birds

such as cranes and their flyways/routes etc. Maps of the flyways & routes of the important

migratory birds routes were also studied. Books on birds, bats and wildlife were also studied

in order to understand the biology of several species.

2.6. Analysis to evaluate the potential impacts.

The information collected on status of birds & bats, their spatio temporal distributions,

hotspots, and potential impacts of wind farm project development were logically analyzed and

conclusions were extracted for making suggestions for project development.

Page 137: Social- Environmental Impact Study Report

11

3. Ecological Scenario Assessments

3.1. Basic understanding of the project & surrounding areas

The project site falls at around 50 km distance in South-East ditection from Jaisalmer town in

Rajasthan. The project site is located in the Dangri, Meheriri, Ramsar, Bhesda etc. villages

(Plate-3.1). The proposed site is located in the Thar Desert (zone 3A) bio-geographic zone of

India (Rodgers et al. 2002). The Thar or Indian Desert is one of the smallest deserts in the

world, but most thickly populated.

Plate-3.1: Proposed project site near Dangri-Ramsar villages in Rajasthan (February 2012).

The Thar Desert is located at the crossing where the Palaearctic, Oriental and Saharan

elements of biodiversity are found (Baqri and Kankane 2002). The Thar is also known for its

great civilization in Ghaggar and the Indus river basin. It occupies about 9% of India‘s

geographical area and covers 208,751 sq. km in Rajasthan alone (Rahmani 1997a). The

desert extends to the Ferozepur, Sangrur and Bhatinda districts of Punjab in the north and to

the Mahendragarh and Hissar districts of Haryana in the northeast. The major part of the Thar

is occupied either by dry open grassland or by grassland interspersed with trees and thorny

bushes (Gupta 1975). The main grass type of the Thar is Dichanthium-Lasiurus-Cenchrus

Page 138: Social- Environmental Impact Study Report

12

(Dabadghao and Shankarnarayan 1973). Bhandari in 1990 wrote: ―in general the vegetation

in the arid region is sparse. Plants with only xerophytes adaptations are able to establish

themselves. The bulk of the vegetation consists of stunted, thorny or prickly shrubs and

perennial herbs capable of drought resistance.‖ Nearly 58% of the Thar is covered with sand

dunes and interdunal valleys. Many shifting dunes which have stabilized are covered with

Capparis decidua, Calotropis procera, Calligonum polygonoides, Acacia senegal, Prosopis

cineraria, Aerva javanica, Aristida adescensionis and other psammophytic species (Shetty

1994).

3.2. Baseline status of birds and bats species

Data collected during the field visit and Information gathered from the secondary literature

was used for generating baseline status of birds and bats for the project area. In order to

create baseline, the baseline data were created for the study area i.e. project area and 10 Km

radius of the project site. All the bird records for this entire study area were collated from

primary data collected from the field visits and secondary literature. We used this information

for better understanding of the bird diversity at the project site. These are given in the

following sections.

3.2.1. Bird Species diversity:

As per our field visit records and secondary literature there are around 66 species of the birds

in and around the project site. However, apart from these records there are some historical

records of presence of Great Indian Bustard, Lesser Florican and Houbara Bustards area

there which may not hold true today, as the developmental scenario and human population in

this region has increased many folds since then. During our field visit in February, 2012 we

observed total 37 species in the reperesentative project area that we visited (Table-3.1 &

Annexure-I).

Of these recorded species only one species i.e. Indian Peafowl is listed as Schedule-I

species by the Indian Wildlife Protection Act 1972, whereas House crow is listed as

Schedule-V and rest all the species are listed as Schedule-IV. As per IUCN & Birdlife

International threat categories, all 66 species recorded in the study area and 37 species

recorded in the project area belonged to Least Concerned category (Table-3.1 & Annexure-I).

Total 21 species reported in the study area (10 km radius) were migratory. However, only 7

migratory species were reported from the project sites. Of 66 species reported in the study

Page 139: Social- Environmental Impact Study Report

13

area during the visit, 45 were found to be resident breeder in this region, however, only 8

common species are reported to breed in the project site (Table-3.1 & Annexure-I).

Table- 3.1: Status of birds in and around the project area.

Status as per Categories Study area (10

Km Radius) Project Site

Indian Wildlife Protection Act 1972

Schedule- IV 64 36

Schedule-I 1 0

Schedule-V 1 1

IUCN Threat Categories

Least Concerned 66 37

Vulnerable 0 0

Near Threatened 0 0

Critically Endangered 0 0

Endangered 0 0

Migratory Resident Migratory 21 7

Resident 45 30

Breeding Records Breeding 45 8

3.2.2. Bird species abundance

Abundance of the bird species in the project area was calculated as birds encountered per

kilometre of walk in the project area (Table 3.2). It appears form the results that small

passerine species such as House Sparrow, Rosy Starling, Cattle Egret, Crested Lark, Red

vented bulbul, Indian Silverbill, Ashy crowned sparrow lark, Indian Silverbill, etc. had higher

encounter rate compared to that of large birds such as House crow etc. Majority of the birds

are found in the open scrub land and semi arid to arid landscapes. Moreover, majority of the

species that has higher encounter rate in the project area are listed as Schedule-IV in the

Indian Wildlife Protection Act 1972 and Least Concerned species by the IUCN-Birdlife

International threat categories. Overall low encounter rate suggests lower density of

occurrency of birds in the project area. This results safely states that the project site does not

fall in the prime habitat (most important breeding and feeding areas) of any endemic or

threatened birds species and therefore, do not pose major threat to their populations in the

region.

Page 140: Social- Environmental Impact Study Report

14

Table-3.2: Encounter rates of birds recorded in the project area.

No Common Name Scientific Name encounter

rate per Km

1 Ashy Crowned Sparrow Lark Eremopterix griseus) 0.15

2 Bay-Backed Shrike Lanius vittatus 0.05

3 Black drongo Dicrurus macrocercus 0.05

4 Blue rock pigeon Columba livia 0.1

5 Blue-cheeked Bee-eater Merops superciliosus 0.05

7 Brahminy Myna Sturnia pagodarum 0.05

8 Cattle egret Bulbulcus ibis 0.2

9 Chestnut-Bellied Sandgrouse Pterocles exustus 0.05

10 Chestnut-shouldered Petronia Petronia xanthocollis 0.05

11 Common Babbler Turdoides caudatus 0.1

13 Common Iora Aegithina tiphia 0.05

14 Common Kestrel Falco tinnunculus 0.1

15 Common myna Acridotheres tristis 0.05

18 Common Woodshrike Tephrodornis pondicerianus 0.05

19 Crested Lark Galerida cristata 0.2

21 Egyptian Vulture Neophron percnopterus 0.1

23 Eurasian collared dove Streptopelia decaocto 0.1

26 European Roller Coracias garrulus 0.05

29 Green bee eater Merops orientalis 0.05

31 Grey-breasted Prinia Prinia hodgsonii 0.05

32 House crow Corvus splendens 0.1

33 House sparrow Passer domesticus 0.3

34 House Swift Apus affinis 0.05

36 Indian robin Saxicoloides fulicata 0.05

37 Indian Roller Coracias benghalensis 0.05

38 Indian silverbill Lonchura malabarica 0.2

40 Laughing dove Streptopelia senegalensis 0.05

42 Long-billed Pipit Anthus similis 0.1

45 Oriental magpie robin Copsychus saularis 0.1

47 Red vented bulbul Pycnonotus cafer 0.1

48 Red wattled lapwing Vanellus indicus 0.1

49 Red-collared Dove Streptopelia tranquebarica 0.05

50 Rosy Starling Sturnus roseus 0.3

54 Singing Bushlark Mirafra cantillans 0.05

55 Southern Grey-Shrike Lanius meridionalis 0.05

60 Tawny Pipit Anthus campestris 0.05

61 Variable Wheatear Oenanthe picata opistholeuca 0.15

Page 141: Social- Environmental Impact Study Report

15

3.2.3. Bat species abundance

There are 114 species of bats (17 mega bats and 97 micro bats) reported from India. Of

these, 11 species are found in Thar Desert region. Based on the secondary literature (Purohit

& Senacha 2004) and our field visits, we confirmed that there are only 4 species of bats (3

microchiropteran and 1megachiroptera) found in Jaisalmer region of Thar Desert. The

species of bats found in region are listed as following.

Microchiropteran

i. Greater Mouse-tailed Bat (Rhinopoma microphyllum)

ii. Lesser Mouse-tailed Bat (Rhinopoma hardwickii)

iii. Naked-rumped Tomb Bat (Taphozous nudiventris)

Megachiroptera

i. Indian Flying Fox (Pteropus giganteus giganteus)

It is important to mention here that none of the bats species found in this region are

threatened as per IUCN threat categories. Moreover, none of the species were found to be

endemic of Thar Desert or the Jaisalmer region. All 4 species of bats are listed as Least

Concerned category of species as per IUCN categories meaning that there is no immediate

threat to their populations and they have wider distribution in the region.

Based on secondary literature and our field visit we found that there are 9 roosting sites of the

bats in and around Jaisalmer town. Of these 9 sites, megachiroptera species are found at

only two sites i.e. Gajroop Sagar village/Lodurva and Gadisagar Pond (Plate-3.2), rest all the

roosts are within and close periphery of Jaisalmer town. Lodurva village roosting site is only

7.0 Km from the proposed project site.

Roosts of Bats in Jaisalmer (Purohit & Senacha 2004 and Primary field visit data)

1. Annapurana Bhandar, Sonar Fort (26° 54‘ 45‖ N, 70° 54‘ 58‖ E).

2. Raj Mahal Palace, Sonar Fort (26° 54‘ 51‖ N, 70° 54‘ 48‖ E).

3. Rani Mahal Palace, Sonar fort (26° 54‘ 42‖ N & 70° 54‘ 50‖ E

4. Patawa Haveli (26° 54‘ 58‖ N, 70° 54‘ 54‖ E).

5. Amar Sagar Garden, Amar Sagar Village (26° 55‘ 55‖ N, 70° 52‘ 17‖ E).

6. Shri Adinath Jain Temple, Amar Sagar Village (26° 55‘ 45‖ N, 70° 52‘ 18‖ E).

Page 142: Social- Environmental Impact Study Report

16

7. Gajroop Sagar Tunnel, Gajroop Sagar Village (26° 56‘ 50‖ N, 70° 55‘ 44‖ E).

8. Gajroop Sagar Well, Gajroop Sagar Village (26° 56‘ 41‖ N, 70° 55‘ 54‖ E).

9. Gadisagar Pond (26°54'31.14"N, 70°55'14.33"E)

Plate-3.2: Megachiroptera, Indian Flying fox on the roost at Gadisar Pond in Jaisalmer.

As per the literature survey (Purohit & Senacha 2004) it is found that the diversity and density

of bats is much lower in this region compared to Jodhpur and other parts of Rajasthan. This

could be due to the inherent characteristics of the region. Extreme climatic conditions and

semi arid, arid condition prevails in the region and that does not support higher diversity of the

bats in this part of the desert. Moreover, all the roosts of bats were located inside and close

periphery of the Jaisalmer town. No roost was found in and round or any close proximity to

the proposed Wind farm project site. The population estimation of the microchiropteran

species was difficult becuase of the limitation of counting opportunities and inaccessible sites.

However, the population of megachirecptora was found to be between 125-150 individuals

only. This includes counts at two roosts i.e. Gajroop Sagar village and Gadisagar Pond

(Plate-3.2).

Page 143: Social- Environmental Impact Study Report

17

3.2.4. Bat Species in the project area

Presence of the microchiropteran bat species in the project area was difficult to study

because of their smaller size and nocturnal behaviour. However, during our field visits it was

possible to observe megachiroptera species such as Indian Flying Fox due to its larger size

and their timing of leaving roost was in dusk. We tried to record the presence of Indian Flying

Fox in three points in the project site between 6:45 to 7:45 PM.

The results of our observations efforts suggest absence of any fruit bats/megachiroptera

species. During the period of our observations, there was not a single bat (Indian Flying Fox)

was seen in the observation areas. Upon interviewing local people, our own understanding of

the region and literature survey it was believed that the bats were not moving through the

proposed project site. This could be because of the unavailability of food resources for the

species in monotonous arid habitat. No presence of large trees & fruit bearing trees could

also be one of the reasons for absence of fruit bats movement through the region.

3.3. Migratory waterbird Flyway/routes:

Each year over 100 million waterbirds migrate through the Asian, Southeast Asian and

Australasian region. During migration, these waterbirds rely on a chain of highly productive

wetlands to rest and feed, building up sufficient energy to fuel the next phase of their journey.

This chain of wetland is normally called as migratory bird flyway. Therefore, A Flyway is the

total area used by a group of species during its entire life cycle. The term can be used to

describe such area for a single species, but also to indicate such area for all populations

migrating through it. India falls on the Central Asian Flyway (Plate-3.3).

In the context of the present study, the migratory waterbird flyway is a broad consideration.

This is because the migratory birds do not take only one trajectory, they fly over a broad

region choosing wetlands on their way for resting and feeding. In the present study we found

that there are no major wetlands which are located in 10 km periphery of the project site. This

could be further confirmed by viewing the project site and its periphery in the Google Earth.

Since the proposed project is located far away from the wetlands, it is less likely to fall on the

migratory water bird‘s active flyway or routes. Therefore the proposed project is less likely to

affect the migratory waterbirds and their populations.

Page 144: Social- Environmental Impact Study Report

18

Plate-3.3: Central Asian Flyway for migratory birds (Wetlands International).

Plate-3.4: Migratory Crane Flyway (Source International Crane Foundation Website)

Page 145: Social- Environmental Impact Study Report

19

It is also observed from the literature survey, that some of the migratory crane i.e. Demoiselle

Crane (Anthropoides virgo) avoids extremely harsh winter climatic conditions of Thar Desert

particularly areas around Jaisalmer (Plate-3.4).

3.4. Natural habitats/Protected Areas

Some of the major concerns about wind energy projects is their proximity to the natural

habitats/biodiversity hotspots. It is therefore important to evaluate whether the wind farm

project site occupies any natural habitats or ecosystems if yes what are the impacts. In

context to Thar Desert Biome, only grasslands ecosystem is considered as one of the most

important natural habitats as they harbour considerable biological diversity. However, in

context to present project site we evaluated the presence of 1) Grasslands, 2) Wetlands and

3) Protected areas.

3.4.1. Grasslands

Duirng our field visits we observed that there are no major grassland patches located within

the proposed project site boundary. Majority of the project site land is covered with scanty

vegetation particularly Caparis deciduas, Acacia nilotica, Prosopis cineraria and Calotropis

procera as dominant vegetation (Plate-3.5). This is probably because of the moving

sandunes, low rainfall, extreme climatic conditions coupled with inherent geological and

hydrological features of the land.

Plate-3.5: Representative vegetation and habitat types present in the project site.

Page 146: Social- Environmental Impact Study Report

20

3.4.2. The Desert National Park

The Desert National Park is one of the Important Bird Areas (IBAs) identified by Birdlife

International. The National Park has 3162 km2 of area. It is given protected form by the

Government of India as National Park in 1992. This national park is created in order to protect

unique biodiversity and habitat representing Thar Desert. The area is home to many rare,

endangered birds and animal species. The Desert National Park is located at 60 Km distance

from the project boundary (Map-3.1). Primarily the Desert National Park is known for

supporting large populations of birds of Bustard family i.e. Great Indian Bustard, Houbara

Bustard and Lesser Florican. Of these, Great Indian Bustard and Lesser Floricans are known

to breed in good numbers and Houbara Bustards are known to winter in this landscape. This

Important Bird Area (IBA) is known to harbour 3 critically endangered species, 2 vulnerable

species, and 9 near threatened species (IBA Book).

Map-3.1: Desert National Park and the proposed project site in Jaisalmer district.

Due to 60 kilometre distance of the project site from the boundary of the Desert National

Park, the project is less likely to affect its natural habitats and fauna of the DNP. Historically

the project site could have supported all the representative birds and animals of the Thar

Desert, but in the current time it is less likely to support them due to various types of

Page 147: Social- Environmental Impact Study Report

21

disturbances and developments taking place in Thar Desert. It is believed that the flagship

species of the Park i.e. Great Indian Bustard population is declining rapidly (Dutta et al 2010).

3.4.3. Wetlands

Wetlands are the most important hotspot for birds and that too migratory birds. Majority of the

migratory birds are waterbirds and they spend entire winter in a wetland. Therefore, large

wetlands which sustain water till winter are considered migratory bird hotspots and wind farm

development in the vicinity of such wetlands should be done carefully to prevent mortalities of

birds.

Map-3.2: Landuse types in and around proposed project site showing absence of wetlands.

During our survey we found that there are no major wetlands in and around the project site

(Map-3.2). There are one or two very small seasonal ponds located in and around the project

site. These ponds are near Dangri and Bhesda villages. These small ponds does not hold

water for longer duration and therefore, do not harbour significant populations of the

waterbirds. The abasence of major wetlands in and around the proposed project site

suggests that, there is no possibility of project site falling on the migratory bird‘s movement

path or annual migration.

Page 148: Social- Environmental Impact Study Report

22

3.5. Threatened Birds species

3.5.1. Great Indian Bustard

The Indian Bustard is large handsome bird inhabiting short grass plains of Indian

subcontinent (Rahmani 2006). The Indian Bustard is the second heaviest bird that could fly in

the world. It is the flagship species of our grassland ecosystem especially in arid to semiarid

biogeographic zones of India. The Indian Bustard could well be considered as indicator of the

health of grasslands, therefore conserving it in its natural habitat would lead to conservation of

the entire ecosystem and species there in.

The Indian Bustard is probably one of the most endangered members of the Bustard

Family(Plate-3.6). The species is protected as Schedule-I in under Indian Wildlife Protection

Act (1972). Indian Bustard is categorized by IUCN Red Data Book as critically endangered

C1. C2b Vulnerable D1 hence qualifies as an endangered because of its very small and

declining population. Formally it was widely distributed from Punjab and West Bengal in the

North to Tamilnadu in South and Sindh (Pakistan), in the west to Orissa in the East (Rahmani

2006). At present the Indian Bustard is distributed in 6 states of India which include Gujarat,

Rajsthan, Maharashtra, Madhya Pradesh, Karnataka and Andhra Pradesh. It is locally extinct

from almost 90% of its former range and ironically it has disappeared from three sanctuaries

made especially for its protection (Rahmani 2006).

In other sanctuaries it is declining rapidly. Earlier it was mainly poaching and habitat

destruction that resulted in such a pitiable situation of this grand bird of the Indian grassy

plains, but now mismanagement of the habitat, sentimental protection of certain problem

animals, insecure and confusing tenurial systems, apathy and ignoring of scientific advice

now exacerbates the threats faced by this species in India (Rahmani 2006). Conservationists

today strongly believe that the Indian Bustard is now on the brink of extinction in Indian

subcontinent as their population could be as low as only 300 birds in the world. The Indian

Bustard once common in Rajasthan has also experienced a sharp decline in terms of its

population and a heavy shrinkage in its distribution range in compared to the past. In

Rajasthan, the Desert National Park in the districts of Jaiselmer and Barmer along with the

agro-pastoral landscapes of Bikaner holds the largest global population of the GIB currently

numbering between 100 and 125 birds, along with another 25–50 birds in Ajmer, Pali, and

Tonk districts (Rahmani 2006).

Page 149: Social- Environmental Impact Study Report

23

Plate-3.6: Great Indian Bustards in Grasslands.

According to Birdlife International Species Factsheet- 2012, major threats to the species are

widespread hunting for sport and food precipitated its decline, accelerated by vehicular

access to remote areas. Some poaching continues, including one documented case where

mine-workers that lost their livelihoods when mines near Gwalior were closed for the creation

of the Ghatigaon Bustard Sanctuary hunted bustards to undermine the criteria on which the

area was first designated as a sanctuary. Egg-collecting is a threat in the states of Karnataka

and Andhra Pradesh. The current key threats are habitat loss, modification and fragmentation

as a result of widespread agricultural development and land-use change, particularly

conversion of large areas to intensive crop cultivation, irrigation schemes (to convert areas to

rice paddy), increased pesticide usage and livestock-grazing, and high levels of disturbance.

Increases in the construction of irrigation canals and use of pesticides are highlighted as on-

going threats in Maharashtra state. Some habitat is also threatened by mining operations and

conversion to plantations. Inappropriate protected area management and increasing

instances of nest-trampling are further problems. In some areas, the species suffers an

increasing level of disturbance by dogs from nearby villages. Threats posed by infrastructure

development, such as collisions with vehicles, power-lines and wind turbines, further

exacerbate the situation. However according to a recent study by Khan et al, 2008, the major

threat to Great Indian Bustard is its rampant hunting in Pakistan side of Thar Desert. In about

Page 150: Social- Environmental Impact Study Report

24

four years, nearly 49 out of 63 birds sighted were killed. The bird is under intense pressure of

human persecution and trade (Khan et al, 2008).

During our field visit, we did not observe this bird in the project area or its surroundings.

Moreover, the records of recent past suggest that there are no Great Indian Bustards sighted

in the project area. Even interview survey (Plate-3.7) of local villagers, elderly villagers,

herders etc. suggested that the Great Indian Bustard does not occur in the areas of proposed

project villages.

The local people informed us that the Great Indian Bustard is now seen in areas such as

Bandh Khujala, Ramgadh, Raghwa, Sewa, Raimala, Sadhna,Nagga kiRani, Nagga, Tejpala,

Nehdai, Sudasari etc. However, they informed that they have not seen Great Indian Bustard

in project villages where they often graze their livestock in this land.

Plate: 3.7: Interview of local people to know the status of endangered birds in the project area.

According to local people, the increasing human population in the region, developmental

activities, tourism and hunting are responsible for Great Indian Bustard and other bustard‘s

species not being sighted in these areas. Local people‘s views are often provides most

reliable information on the wildlife and are often used as an indices to study the rare and

endangered species.

Major threats envisaged to Great Indina Bustard population in Rajasthan are-

Poaching- (in Pakistan & Rajasthan).

Habitat Loss- due to conversion of grasslands in to agriculture, irrigation schemes

Page 151: Social- Environmental Impact Study Report

25

Direct disturbances- vehicular access, increasing human population, agriculture

In appropriate Protected area management practices

Roads, electric poles, windmills etc. have have increased the severity of habitat

degradation

In view of our field surveys, interview surveys and literature review it is understood that

proposed project is less likely to affect Great Indian Bustard. The following reasons are

mentioned as explanations for the same.

The guidelines for the ―Great Indian Bustard Recovery Programme‖ by the Ministry of

Environment and Forests, Government of India (2011) also recognized that It is

extremely important to protect the breeding sites from all human-induced disturbances

and reduce poaching to nil. Securing these two life history phases is likely to revive the

declining trend of Great Indian Bustard populations. Low intensity poaching still

persists within India outside protected areas. Given the life history traits of Great Indian

Bustard, this level of removal threatens its extinction in immediate future.

The distribution map shown in Dutta et al 2010 and Guidelines for Great Indian

Bustard Recovery Plan does not seem to be based on updated facts as per our

understanding. Munjpara et al 2011 has clearly defined distribution of the species in

Gujarat.

During our survey we noticed that the proposed project site and its surrounding areas

does not offer any breeding sites to Great Indian Bustards. As there are no grasslands

present. Moreover, local herders and graziers are also not aware of the presence of

the species in and around the proposed project site.

Therefore two major threats (poaching and breeding habitat loss) to the species that

are likely to bring extinction of the species are not likely to be aggravated by the

proposed project development.

Page 152: Social- Environmental Impact Study Report

26

4. Impact Analysis

4.1. Analysis to Predict the Potential Impacts on Birds.

An important study and comprehensive literature reviewed by Langston & Pullan 2004, has

listed out several impacts of wind farm on the bird groups. Keeping these known impacts as

reference for the present study, we developed a matrix (Table-4.1) where observations of the

present study were juxtaposed against the known impacts (Langston & Pullan 2004) on bird

groups.

Langston & Pullan 2004, based on extensive literature survey, has listed 4 major threats on

several bird groups. These threats are 1) Disturbance leading to displacement of bird groups,

2) Barrier to movements 3) Collision with turbine blades, and 4) Direct habitat loss. In order to

predict the impacts of proposed project with respect to the above listed threats, all the bird

species recorded in the study area were classified by their species groups. The spatio-

temporal distribution of these species groups were seen against the known threats to predict

the impacts of proposed project (Table-4.1).

Using known impacts (Langston & Pullan 2004) of windfarm on various bird groups, we

predicted impacts as Low, Moderate and High. We analyzed the information on birds/groups

collected during the field visits in a matrix form and tried to predict the impacts of windfarm

project. The information on abundance, spatio-temporal distribution, status, habits, habitats

of various bird groups were used for predicting level of impacts and their reasons.

Total 66 species belonged to 11 bird groups/orders. During our assessment we found that

birds belong to order Passeriformes, were at moderate risk, where as birds belonging to all 10

other orders were at lower level of risk. This is because majority of the bird groups were

occurring at very low abundances, there were very few species respresenting some of the

bird groups, and some groups were either absent in the project area or their species number

were low in the project area. Moreover, majority of waterbirds and grassland birds would be at

very low risk as there are no major wetlands and grasslands present inside or in the close

periphery of the project area.

Some of the known impacts (Langston & Pullan 2004) predicted in reference to the proposed

project are described as follow.

Page 153: Social- Environmental Impact Study Report

27

Table-4.1: Bird group wise comparison with known impacts

No Bird Species group

Impacts (As per

Langston & Pullan

2004, Bidrdlife

International study)

species reported in and around

project site the present study Predicted

level of

Impact on

the

species

groups

due to

project

Reasons for predicted impacts for the project

Dis

turb

an

ce

Dis

pla

cem

en

t

Barr

ier

to

mo

vem

en

t

Co

llis

ion

Dir

ect h

ab

itat lo

ss

To

tal S

pecie

s

Sp

ecie

s r

ep

ort

ed

in p

roje

ct site

Hab

it

Hab

itats

1 Accipitridae (Raptors)

13 2 Diurnal Grassland Scrubland

Low Only 2 species recorded in project site, No breeding sites recorded, low encounter rate/ abundance, half of them are migratory species which would be absent in summer/high wind speed duration.

2 Alcidae (Kingfishers)

√ √ 1 0 Diurnal Wetlands Low Only 1 species reported, that too outside project area, Mostly diurnal & wetland species, no major wetlands in and around project aera.

3 Caprimulgidae (nightjars)

√ √ 1 0 Noctornal Grassland Scrubland

Low Low abundance, not reported from project site

4 Charadriiformes (Waders)

√ √

3 1 Diurnal Wetlands, scrubland

Low All reported species are solitary species, Only 1 species reported from the project site, Mostly diurnal & wetland species, no major wetlands in and around project aera.

5 Ciconiiformes (Herons & Storks)

1 1 Diurnal Wetlands, Agriculture

Low Mostly diurnal wetland species, No major wetlands in and around the project site.

6 Columbidae ( Doves & Pigeons)

4 4 Diurnal Agriculture Low Mostly diurnal & solitary secies, most common species with wider distribution across the region, not threatened species

7 Coraciidae ( Rollers &

Hoopoo) √

3 2 Diurnal

Scrubland Agriculture

Low Only 3 species reported, one of them is migratory, mostly diurnal & solitary secies with low abundance,no breeding sites reported in project area.

8 Cuculidae (cuckoo)

1 0 Diurnal Agriculture, Scrubland

Low Mostly diurnal & solitary secies with low abundance

9 Passeriformes

36 26 Diurnal All habitats Moderate No threatened species in this group, lower flight height during movements therefore can avoid the turbines, mostly small in size and diurnal

10 Tetraonidae (Grouse)

√ √ 1 1 Diurnal Scubland, grassland

Low only one species, diurnal therefore can avoid the turbines.

11 Gali formes √

√ √ 2 0 Diurnal Grassland Scubland

Low Not reported from the project aera, mostly diurnal, not threatened species

Page 154: Social- Environmental Impact Study Report

28

4.1.1. Disturbance leading to displacement of bird groups

Since not many speices are found to breed in the project area, the disturbance leading to

displacement of birds would be very low. Our data suggests (Table-4.1) that only 4 species

are likely to be affected by the project. All these 4 species are most common species which

are abundant throughout the region. All of the species reported common and listed as

Schedule-IV in the Indian Wildlife Protection Act 1972, and as Least Concerned by IUCN.

4.1.2. Barrier to movements

This impact is more prone to the waterbirds and waterdependent species, it includes Ducks &

Geese, Waders and Cranes. These bird groups are generally known to fly in large flocks or

move near wetlands. However, in case of the present project, there are no wetlands in and

around project site and therefore, the project may not pose significant threat to these bird

groups. Only 3 species are reported in this group, and all the 3 species are solitary and

diurnal in their habits therefore the project is less likely to be barrier to their movements.

4.1.3. Collision with turbine blades

Majority of the bird groups are prone to collision with the turbines (except Waders,Cormorants

and Grebes). Total 36 species are shown to be affected by the collision in our analysis

(Table 4.1). However, many of the species are solitary, diurnal, having low flights during local

movements, and their major habitats are being away from the project site, they are likely to be

less affected. Moreover, no rare, endangered, endemic or threatened species are listed in

this group.

4.1.4. Direct habitat loss

Majority of the ground nesting birds such as Sandgrouse are likely to experience gross loss of

their habitat worth the project area. However only one species i.e. Chestnut-bellied

Sandgrouse is found to be in and around the project area. This species is considered as

Least Concerned by IUCN and in Schedule-IV in the Wildlie Protection Act in India.

Therefore, only one species which occur at very low abundance is likely to be affected by the

project development.

4.2. Analysis to predict the potential impacts on Bats.

As per our observations it is evident that there are only four species of bats present in the

vicinity of the project. Majoiryt of the bat species hotspot/roosting sites are away from project

Page 155: Social- Environmental Impact Study Report

29

site i.e. minimum 50 km at Lodurva village (Amar Sagar Garden & Adinath Jain Temple). The

flight direction of megachiroptera (fruit bats) suggested that the bats move towards the

agriculture area in north towards the Indira Gandhi Canal. Therfore, the project site does not

fall near to their roosting sites or movement path and suggests that the impacts of proposed

wind farm project could be very low on bats.

4.3. Analysis to evaluate overall impacts.

Based on the collected information and data on various aspects, we made an effort to draw

general inferences from each of the aspects that are listed in the following Table-4.2. This

information is used for making conclusions as following.

Table-4.2: General inferences drawn from the baseline status on various aspects of the study.

No Parameter studied Impacts

Reasons Birds Bats

1 Status of the birds and Bats

Low Very low No endemic or threatened species, no major habitatst found in and around project area

2 Interview survey Very low Very low No presence of endangered species such as Great Indian Bustard etc. due to disturbances, poaching, development pressure

3 Desert National Park/Natural habitats

Very low

Located at 60 Km distance hence no impacts on this habitat

4 Great Indian Bustard/ endangered specise

Very low

Distribution in Desert National Park at 60 km away & lower population

5 Important Bird Areas/ bird receptors

Very low Very low DNP 60 km away from project site, no major wetlands and grasslands in and around project site

6 Roosting colonies of bats & their mortalities

Very low Very low Located at 50 km away from project site.

7 Migratory waterbird routes Very low

Routes are broad and are not restricted over project site, no wetlands in and around project site

8 Literature review Very low Very low No significant impacts are envisaged

Page 156: Social- Environmental Impact Study Report

30

5. Proposed Mitigation Measures It is largely believed that any industrial development is essentially a destructive activity, where

ecology suffers at the altar of economy, fortunately for wind energy projects, it is not true. It is

therefore the harvesting of wind energy has widespread encouragement as it does not harm

or cause any environmental degradation and adverse impacts on environment. However, if

wind farms are developed in and around forest and wildlife areas, there are still wide concern

about their placements and conservation of habitats and species.

Careful and environmentally responsible industrial operations accompanied by ecological

restoration, judicious use of resources, with search for eco-friendly substitutes and

alternatives provide the answer to our worries and concerns for the environment. Several

care and precautions to be taken for environmentally responsible industrial activities are

proposed in the form of environmental management plan for the wind farm development

project.

5.1. Annual Monitoring of Bird hits and Mortality:

During the present study, our sampling and observation did not suggest any higher chances

of mortality or damage to the birds by the proposed project. However, these observations was

for a short duration, therefore, It is suggested that annual monitoring of windmills be carried

out in order to understand if there are any significant mortality of birds or disturbance to them

due installation of windmills in the project area. Though, there are not many cases of bird hits

with windmills have been observed in India till date, it is important that proposed sites should

be monitored properly and specifically for bird mortalities.

5.2. Precautions to avoid disturbance to wildlife

Though, endemic or threatened bird and bat species have not been reported in and around

the proposed project area, prior to commencing any construction activities such as excavation

etc., a thorough survey for presence of ground nesting birds should be carried out. On a

precautionary principle, the company staff should check for the presence of Indian Bustard,

Lesser Floricans or Houbara Bustards. If any of the Bustard species are found in the project

area, the company staff should immediately stop the construction or transportation (till the bird

leaves the area safely or completes the nesting activities) in order to minimize disturbance to

the birds.

Page 157: Social- Environmental Impact Study Report

31

5.3. Regular removal of carcasses from the project areas

Dead animal (cow, buffalo, camel etc.) carcasses attracts large number of vultures and

raptors. Duirng and after construction of the wind farm, the project staff should monitor the

project area for any presence of such large animal carcasses. If there is any communal

dumping ground of such carcasses present in and around the project site, they should be

removed away from the project site. The villagers should be convienced and the dumping

ground of cattle carcasses could be taken at least 5-10 km away from the project site

boundary.

5.4. Training of Project Personals

In order to avoid any accidents, poaching or harassments to any bird species by the project

staff involved in construction or operation, such as labourers, drivers or any other employees,

a training program should be carried out. During training they should be made aware of the

presence of various bird species in the project area and surrounding area. They should be

trained in identification of Great Indian Bustard etc. so that if there is any sightings of this

species or any of the Bustard species located in the project area, appropriate measures are

taken immediately.

5.5. Post Construction Planning and management

After the completion of the construction work, company should restore the area in terms of

any damage caused to the public roads, or drainage etc. in and around the project site. There

are several activities suggested which the company should take up as Corporate Social

Responsibility.

a. Restoration of damaged (if any) roads, trails, drainages, etc.

b. Plantation of native trees in other areas selected in consultation with biologists or

with local forest officials.

c. The species suggested for plantation are: Acacia nilotica- Desi babul, Salvadora

oleoides- Mithi Pilu, Salvadora persica- Khari Piiu

d. The company should generously support the management activities of the Desert

National Park by contributing mutually agreeable funds to the Rajasthan Forest

Department. The funds for various activities such as boundary demarcation,

grassland improvement, purchase of equipments (such as GPS, Binoculars,

Spotting Scopes etc.), vehicles (such as motorbikes for forest guards) which are

needed for better management and protection of the Desert National Park.

Page 158: Social- Environmental Impact Study Report

32

6. Conclusions

The baseline status of the birds and bats clearly suggests that no endemic or

threatened species is present in and around the proposed project area.

The sensitive receptors such as habitats of Bird‘s & Bat‘s i.e. Desert National

Park/Grassland, Wetland and roosting sites of bats do not fall in and around the

project area and they are located at a substantial distances.

Great Indian Bustard and other endangered species are less likely to be affected

because of their very small surviving population in Jaisalmer district and it is currently

restricted in Desert National Park.

Our observation on movement of bats from Jaisalmer roosts suggests that majority of

the bats were moving towards the agriculture fields aligned along the Indira Gandhi

Canal 40 km north of Jaisalmer town.

Interview survey of local villagers and herders suggested the absence of Bustards

from the project area due to disturbance, developmental activities and general

increase in the human population and their movements in the region.

Literature survey suggested that Rajasthan/India falls on Central Asian Flyway which

is broadly defined flyway for several migratory birds and there is no specific bird route

that passes only through the Jaisalmer or Rajasthan as such.

Literature survey also suggested that wind turbines do not significantly harm the

migratory waterbirds, especially when the wetlands are located far away from the

proposed project site.

Page 159: Social- Environmental Impact Study Report

33

7. References Baqri, Q. H. and P. L. Kankane (2002) Deserts: Thar. Pp. 93-109. In Alfred, J. R. B., Das, A.

K. and Sanyal, A. K. (2002) Ecosystems of India, ENVIS-Zool. Surv. India, Kolkata: 1-410.

Barrios L. 1995. Energ´ıa eo´lica y aves en el Campo de Gibraltar. La Garcilla 93: 39–41.

BirdLife International (2012) Species factsheet: Ardeotis nigriceps. Downloaded from http://www.birdlife.org on 14/03/2012.

Dirksen S., Winden J.V.D. and Spaans A.L. 1998. Nocturnal collision risks of birds with wind

turbines in tidal and semi-offshore areas. In: Ratto C.F. and Solari G. (eds), Wind Energy and Landscape. Balkema, Rotterdam, The Netherlands, pp. 99–107.

Dutta Sutirtha., Asad R. Rahmani., Yadvendradev V. Jhala. 2010. Running out of time? The

great Indian bustard Ardeotis nigriceps—status, viability, and conservation strategies. Eur J Wildl Res DOI 10.1007/s10344-010-0472-z

Higgins K.F., Osborn R.G., Dieter C.D. and Usgaard R.E. 1996. Monitoring of Seasonal Bird

Activity and Mortality at the Buffalo Ridge Wind Resource Area, Minnesota, 1994–1995. South Dakota Cooperative Fish and Wildlife Research Unit, National Biological Service, Brookings, South Dakota.

Hunt G. 1999. A Population Study of Golden Eagles in the Altamont Pass Wind Resource

Area. National Renewable Energy Laboratory (NREL), Santa Cruz, California. Khan Aleem Ahmed, Imran Khaliq, Muhammad Jamshed Iqbal Choudhry, Amjad Farooq

and Nazim Hussain. 2008. Status, threats and conservation of the Great Indian Bustard Ardeotis nigriceps (Vigors) in Pakistan. Current Science, vol. 95, no. 8, 25 October 2008.

Langston R.H. W, Pullan J. D., 2004., Effect of Windfarm on Birds. Convention on the

conservation of European Wildlife and Habitats(Bern Convention).Nature and Environment No. 139.

Larsen J.K.; Madsen J. 2000. Effects of wind turbines and other physical elements on field

utilization by pink-footed geese (Anser brachyrhynchus): A landscape perspective., Landscape Ecology, Volume 15, Number 8, December 2000 , pp. 755-764(10).

Leddy K.L., Higgins K.F. and Naugle D.E. 1999. Effects of wind turbine on upland nesting

birds in conservation reserve program grasslands. Wilson Bulletin 111: 100–104. Morrison M.L. and Sinclair K. 1998. Avian Risk and Fatality Protocol. National Renewable

Energy Laboratory (NREL), Golden, Colorado. Munjpara Sandeep B., B. Jethva & C.N. Pandey. 2011. Distribution of the Indian Bustard

Ardeotis nigriceps (Gruiformes: Otididae) in Gujarat State, India Journal of Threatened Taxa Short Communication 3(9): 2090–2094

Page 160: Social- Environmental Impact Study Report

34

Musters C.J.M., Noordervliet M.A.W. and Terkeus W.J. 1996. Bird casualties caused by a wind energy project in an estuary. Bird Study 43: 124–126.

Nelson, H. K. and R. C. Curry. 1995. Assessing avian interactions with windplant

development and operation. Trans. N. Am. Wildl. Conf 60:266–287. Orloff S. and Flannery A. 1992. Wind Turbine Effects on Avian Activity, Habitat Use, and

Mortality in Altamont Pass and Solano County Wind Resource Areas. California Energy Commission (CEC), Sacramento, California.

Orloff S.G. and Flannery A.W. 1993. Wind turbine effects on avian activity, habitat use, and mortality in the Altamont Pass and Solano County Wind Resource Areas. In: Huckabee J.W. (ed.), Avian Interactions with Utility Structures. Avian Power Line Interactions Committee (APLIC). Electric Power Research Institute, Palo Alto, California, pp. 1–14.

Osborn R.G., Dieter C.D., Higgins K.F. and Usgaard R.E. 1998. Bird flight characteristics near

wind turbines in Minnesota. The American Midland Naturalist 139: 28–38. Osborn R.G., Higgins K.F., Usgaard R.E., Dieter C.D. and Neiger R.D. 2000. Bird mortality

associated with wind turbines at the Buffalo Ridge Wind Resource Area, Minnesota. The American Midland Naturalist 143: 41–52.

Purohit Ashok, Senacha Kalu Ram. 2004. Distribution of bats in and around Jaisalmer of the

Great Indian Desert, India Vespertilio 8: 99–104, 2004.ISSN 1213-6123. Rahmani, A. R. (1997a) Wildlife of the Thar. WWF India, New Delhi. 100 pp. Rahmani AR (2006) Need to start project bustards. Bombay Natural History Society, Mumbai. Rodgers, W. A., Panwar, H. S. and Mathur, V. B. (2000) Wildlife Protected Area Network in

India: A Review (Executive Summary). Wildlife Institute of India, Dehra Dun. Pp. 44.

Shetty, B. V. (1994) Flora of the Indian arid zone. pp 55-63. in Sustainable Development of the Indian Arid Zone (eds. R. P. Singh & S. Singh), Scientific Publishers, Jodhpur.

Wildlife (Protection) Act (1972) 1993. Ministry of Environment and Forests, Government of

India. http://envfor.nic.in/legis/wildlife/wildlife1.html [accessed 6 Nov 2008].

Page 161: Social- Environmental Impact Study Report

35

Annexure-I: Checklist of birds found in the study area (10 km radius of project area and project areas).

No Common Name Scientific Name

Conservation

Status as per

IWPA-1972

(Schedule I to

VI)

Conservation

Status as per

IUCN

Recorded

in 10 Km

radius *

Observed

in Project

site

during

field visit

Migratory

Record

ed

Breedig

in

Project

site

1 Ashy Crowned Sparrow Lark Eremopterix griseus) Schedule-IV Least Concern 1 1 1

2 Bay-Backed Shrike Lanius vittatus Schedule-IV Least Concern 1 1

3 Black drongo Dicrurus macrocercus Schedule-IV Least Concern 1 1

4 Blue rock pigeon Columba livia Schedule-IV Least Concern 1 1

5 Blue-cheeked Bee-eater Merops superciliosus Schedule-IV Least Concern 1 1

6 Bonelli's Eagle Hieraaetus fasciatus Schedule-IV Least Concern 1

7 Brahminy Myna Sturnia pagodarum Schedule-IV Least Concern 1 1

8 Cattle egret Bulbulcus ibis Schedule-IV Least Concern 1 1

9 Chestnut-Bellied Sandgrouse Pterocles exustus Schedule-IV Least Concern 1 1

10 Chestnut-shouldered Petronia Petronia xanthocollis Schedule-IV Least Concern 1 1

11 Common Babbler Turdoides caudatus Schedule-IV Least Concern 1 1

12 Common Hoopoe Upupa epops Schedule-IV Least Concern 1

13 Common Iora Aegithina tiphia Schedule-IV Least Concern 1 1

14 Common Kestrel Falco tinnunculus Schedule-IV Least Concern 1 1 1

15 Common myna Acridotheres tristis Schedule-IV Least Concern 1 1 1

16 Common Raven Corax corax subcorax Schedule-IV Least Concern 1 1

17 Common Sandpiper Actitis hypoleucos Schedule-IV Least Concern 1 1

18 Common Woodshrike Tephrodornis pondicerianus Schedule-IV Least Concern 1 1

19 Crested Lark Galerida cristata Schedule-IV Least Concern 1 1

20 Desert Wheatear Oenanthe deserti Schedule-IV Least Concern 1 1

21 Egyptian Vulture Neophron percnopterus Schedule-IV Least Concern 1 1 1

22 Eurasian Griffon Vulture Gyps fulvus Schedule-IV Least Concern 1 1

23 Eurasian collared dove Streptopelia decaocto Schedule-IV Least Concern 1 1

Page 162: Social- Environmental Impact Study Report

36

24 Eurasian Nightjar Caprimulgus europaeus Schedule-IV Least Concern 1

25 Eurasian Thick-knee Burhinus oedicnemus Schedule-IV Least Concern 1

26 European Roller Coracias garrulus Schedule-IV Least Concern 1 1 1

27 Greater Coucal Centropus sinensis Schedule-IV Least Concern 1

28 Greater Short-toed lark Calandrella brachydactyla Schedule-IV Least Concern 1 1

29 Green bee eater Merops orientalis Schedule-IV Least Concern 1 1

30 Grey francolin Francolinus pondicerianus Schedule-IV Least Concern 1

31 Grey-breasted Prinia Prinia hodgsonii Schedule-IV Least Concern 1 1

32 House crow Corvus splendens Schedule-V Least Concern 1 1

33 House sparrow Passer domesticus Schedule-IV Least Concern 1 1

34 House Swift Apus affinis Schedule-IV Least Concern 1 1

35 Indian Peafowl Pavo cristatus Schedule-I Least Concern 1

36 Indian robin Saxicoloides fulicata Schedule-IV Least Concern 1 1 1

37 Indian Roller Coracias benghalensis Schedule-IV Least Concern 1 1

38 Indian silverbill Lonchura malabarica Schedule-IV Least Concern 1 1 1

39 Isabelline Wheatear Oenanthe isabellina Schedule-IV Least Concern 1 1

40 Laughing dove Streptopelia senegalensis Schedule-IV Least Concern 1 1 1

41 Lesser Whitethroat Sylvia curruca Schedule-IV Least Concern 1 1

42 Long-billed Pipit Anthus similis Schedule-IV Least Concern 1 1 1

43 Long-legged Buzzard Buteo rufinus Schedule-IV Least Concern 1

44 Montagu's Harrier Circus pygargus Schedule-IV Least Concern 1 1

45 Oriental magpie robin Copsychus saularis Schedule-IV Least Concern 1 1

46 Pallid Harrier Circus macrourus Schedule-IV Least Concern 1 1

47 Red vented bulbul Pycnonotus cafer Schedule-IV Least Concern 1 1 1

48 Red wattled lapwing Vanellus indicus Schedule-IV Least Concern 1 1 1

49 Red-collared Dove Streptopelia tranquebarica Schedule-IV Least Concern 1 1

50 Rosy Starling Sturnus roseus Schedule-IV Least Concern 1 1 1

51 Rufous-tailed Scrub-Robin, Erythropygia galactotes Schedule-IV Least Concern 1

52 Rufus tailed lark Ammomanes phoenicurus Schedule-IV Least Concern 1

53 Shikra Accipiter badius Schedule-IV Least Concern 1

Page 163: Social- Environmental Impact Study Report

37

54 Singing Bushlark Mirafra cantillans Schedule-IV Least Concern 1 1 1

55 Southern Grey-Shrike Lanius meridionalis Schedule-IV Least Concern 1 1

56 Spotted Flycatcher Muscicapa striata Schedule-IV Least Concern 1 1

57 Spotted Owlet Athene brama Schedule-IV Least Concern 1

58 Steppe Eagle Aquila nipalensis Schedule-IV Least Concern 1 1

59 Tawny Eagle Aquila rapax Schedule-IV Least Concern 1

60 Tawny Pipit Anthus campestris Schedule-IV Least Concern 1 1 1

61 Variable Wheatear Oenanthe picata opistholeuca Schedule-IV Least Concern 1 1 1

62 White-Breasted kingfisher Halcyon smyrnensis Schedule-IV Least Concern 1

63 White-eared Bulbul Pycnonotus leucotis Schedule-IV Least Concern 1

64 White-eyed Buzzard Butastur teesa Schedule-IV Least Concern 1

65 White-rumped Vulture Gyps bengalensis Schedule-IV Least Concern 1

66 Yellow Wagtail Motacilla flava Schedule-IV Least Concern 1 1

Total 66 37 19 8

Page 164: Social- Environmental Impact Study Report

38

Annexure- 2: Curriculam Vitae of the Expert

Dr. Bharat Jethva (Wildlife Biologist) ACADEMIC QUALIFICATION:

1. Ph.D. in Ecological & Wildlife Sciences-FEB-23 from Wildlife Institute of India-FRI

Deemed University-. Thesis title: Feeding Ecology and Habitat Needs of Wolves in the

Bhal Area of Gujarat).

2. M.Phil., Zoology, 1995 Department of Zoology, School of Sciences, Gujarat University

Ahmedabad. (Topic of M. Phil. Thesis: Short term Treatment of Fluoride and its

Reversal on Kidney, Liver and Muscle of Male Mice).

3. M.Sc., Zoology 1994 (with special subject as Reproductive physiology and

Endocrinology). Department of Zoology, School of Sciences, Gujarat University

Ahmedabad. India

4. B.Sc., Zoology, 1992 from Bahauddin College-Junagadh, Saurashtra University

Gujarat, India.

WORK EXPERIENCE: 1. More than 16 years of experience in the field of Wildlife Research and Conservation

with special emphasis on Endangered species, Birds, Wetlands, Coastal and Marine

Ecosystems, Grasslands and Desert Ecosystems and Environmental Impact

Assessments.

2. Asian Waterbird Census Coordinator with Wetlands International South Asia, New

Delhi, Setp-28-June 211.

3. Scientist at GEER Foundation, Gandhinagar, September 23-August 28.

4. Senior Research Fellow in the Conservation of the India Wolf Research Project at

Wildlife Institute of India from January-2 to August 23.

5. Junior Research Fellow, in the Conservation of the India Wolf Research Project at

Wildlife Institute of India. From December-1997 to December-1999.

6. Technical Assistant on Conservation of the Indian Wolf Research Project at Wildlife

Institute of India. From November 1995 to December 1997.

MEMBERSHIPS:

1. Member of IUCN-Flamingo Specialist Group.

2. Member International Society for Mangrove Ecosystems (ISME)

3. Member Executive Committee, Mangrove Society of India (MSI)

4. Member Sirenian International, USA

5. Indian Bird Conservation Network (IBCN)

6. Bird Conservation Society of Gujarat

Page 165: Social- Environmental Impact Study Report

39

PEER REVIEWED PUBLICATIONS:

1. Jethva B. D. and Jhala Y. V. 24. Computing biomass consumption from prey

occurrences in Indian wolf scats. ZooBiology, Volume 23, Issue 6, Pages 513 - 52.

2. Jethva B. D. and Jhala Y. V. 23. Foraging Ecology, Economics and Conservation of

Indian Wolves in the Bhal Region of Gujarat, Western India. Biological

Conservation: 116: 351-357.

3. Jethva B. D. and Jhala Y. V. 23. Sample Size Considerations for Food Habits Studies

of Wolves from Scats: Mammalia 67: 589-591

4. Sankar K, Jethva B. 22. Notes on Food habits of Stripped Hyena (Hyena hyena) in

Sariska Tiger Reserve: short note in Journal of Bombay Natural History Society.

5. Ramesh Sabapara; Suresh Chugh; Bharat Jethva; Budhan Pukazhenth; David E.

Widt; Terri L. Roth (1994) A note on reproduction research. Asiatic Lion Population

Habitat Viability Analysis (PHVA) report, Vadodara, 1993

PROJECT REPORTS:

1. Status, distribution and habitat Survey of Great Indian Bustard Ardeotis nigriceps in

Gujarat, 28. Project sponsored by Ministry of Environment and Forests, Government of

India.

2. Status of Gyps Vultures in Gujarat, 27- A comprehensive state-wide survey of vulture

nests and population. Project sponsored by Ministry of Environment and Forests,

Government of India. Published by GEER Foundation.

3. Biodiversity of Purna Wildlife Sanctuary a comprehensive ecological and socio-

economic study. Mammals and socio-economic studies 27.

4. Biodiversity of Jessore Wildlife Sanctuary a comprehensive ecological and socio-

economic study. Contribution in studies on mammals 28.

5. Movement Pattern of Wild Ass Across the Proposed Kachachh Branch Canal

(Sardar Sarovar Narmada Nigam Limited) on the Northern Fringe of Wild Ass

Sanctuary in Gujarat, 26.

6. Status of Gyps Vultures in Gujarat, 25- A comprehensive state-wide survey of vulture

nests and population. Published by GEER Foundation

7. Proceedings of the workshop on “Cranes and Community in Gujarat-a holistic

conservation strategy for future‖ held on 23rd November-24 at GEER Foundation,

Gandhinagar, Gujarat, India.

8. Ecological Impacts of Lignite Mining in Kutch with Special Emphasis on the Indian

Grey Wolf and its Habitats, 1997. WII-EIA Technical Report No-19, Wildlife Institute of

India.

Page 166: Social- Environmental Impact Study Report

40

TRAININGS OBTAINED: 1. One week Regional Training Programme on Wetland Management and Conservation

held between 2-6th May 28 at GEER Foundation, Gandhinagar, Gujarat.

2. UNESCO Regional training program on Satellite Image Processing for Natural

Resources Management (21-31 January 22), conducted by Center for Geo-Sciences

and Engineering, Anna University, Chennai.

3. Animal Welfare Training Course 1995. Conducted by Animal Welfare Board of India,

Ministry of Environment and Forests held at Sakkarbaug Zoo, Junagadh Gujarat.

SELECTED PRESENTATIONS/ABSTRACTS : (International conferences)

1. Conservation Potential of Green Sea Turtle (Chelonia mydas) in Gujarat. National

workshop on Marine biodiversity and community held at GEER Foundation with the

support of MoEF, Government of India at Ahmedabad.

2. Jethva B. 25, Vulture Conservation initiatives in Gujarat, Abstract and Oral

Presentation in the conference of Society for Conservation Biology Asia Chapter

held in Kathmandu, Nepal, November-25.

3. Jethva B. 25, Crane Conservation and community in Gujarat, Abstract and Oral

Presentation in the conference of Society for Conservation Biology Asia Chapter

held in Kathmandu, Nepal November-25.

4. Jethva B and Jhala Y.V 23, Foraging ecology, economics, and conservation of Indian

wolves. Abstract for an oral presentation in International Wolf congress to be held

at Banff, Alberta Canada on September-25–28, 23.

5. Jhala Y.V., Jethva B, and Chauhan K, 21. The Role of Predation by Wolves (Canis

lupus pallipes) and Jackals (Canis aureus) on Blackbuck (Antelope cervicapra) in

Velavadar National Park, India. Presentation in International Canid Conference held

in Oxford University U.K.

6. Jethva B and Jhala Y.V 2, ―Food habits, Consumption and predation by wolves in the

Bhal, India, Abstract in an international symposium ―Beyond 2: Realities of Global Wolf

Restoration held at Duluth, Minnesota, USA, Feb-2.

7. Jethva B. and Jhala Y.V. 2. ―Ecological Impact Assessment of Lignite Mining in Kutch

India‖. Oral presentation given in an international symposium: Carnivore-2, held in

November-2 at Denver, Colorado. USA.