s.no. reference to the original document context queries/amendments (details) comments · 2010. 11....

76
S.No. Reference to the original document Context Queries/Amendments (Details) Comments 1 Vol2; Section 5.6, a Page No 43 & Annexure XVI Format for Commercial bid Form I Financial Bid, page 73 Performance Warranty Page No 43 mention Warranty period of 24 months. Form I of financial bid and page no 13, Payment schedule table mentions warranty period of One year (12 months). Please specify the exact period of warranty support to consider for software part. We understand from the RFP that the total engagement period with IA is 5 yrs. If the warranty support for the software part of 2 yrs then the AMC should be for the remaining 3 yrs. In the same form I of commercial bid, the table 3 asks AMC charges from 1st yr to 5th yr. If the warranty is of 2 yrs then why the charges of 1st yr to 5th yr has been asked. Please clearly define the warranty and AMC requirement of Software part in the price schedule. Warranty period is one year from the date of Go Live. AMC will be applicable post the Warranty period till end of 5th year from the date of Go Live. 2 Vol 2, Annexure XVI Format for commercial bid, page 73 Hardware Cost There is no place holder to put hardware price required for development phase. Where should it be included? The cost for the hardware can be put in the BoM. 3 Vol 2, Annexure XVII Format of Bill of Material for software components (page No 75) Software Licenses AMC cost There is no place holder to put AMC price of the software licenses for the period of 5 yrs. The table provided for Annual Maintenance Charges should contain the AMC price of Software licensing. 4 Vol2, Annexure XVII Format of Bill of Material for Services (page No 75) Software Licenses Purchase Software licenses will be procured on whose name? Whether IDRA wants IA to buy licenses on IDRA’s name on the first day of the purchase OR does it want licenses to be transferred on IRDA’s name after 5 yrs. The licenses should be procured in the name of IRDA. 1 of 76

Upload: others

Post on 01-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    1 Vol2; Section 5.6, a

    Page No 43 &

    Annexure XVI Format for

    Commercial bid Form I Financial Bid,

    page 73

    Performance Warranty Page No 43 mention Warranty period of 24 months.

    Form I of financial bid and page no 13, Payment schedule

    table mentions warranty period of One year (12 months).

    Please specify the exact period of warranty support to

    consider for software part.

    We understand from the RFP that the total engagement

    period with IA is 5 yrs. If the warranty support for the

    software part of 2 yrs then the AMC should be for the

    remaining 3 yrs.

    In the same form I of commercial bid, the table 3 asks

    AMC charges from 1st yr to 5th yr. If the warranty is of 2

    yrs then why the charges of 1st yr to 5th yr has been

    asked.

    Please clearly define the warranty and AMC requirement

    of Software part in the price schedule.

    Warranty period is one year from the

    date of Go Live. AMC will be

    applicable post the Warranty period

    till end of 5th year from the date of

    Go Live.

    2 Vol 2, Annexure XVI Format for

    commercial bid, page 73

    Hardware Cost There is no place holder to put hardware price required

    for development phase. Where should it be included?

    The cost for the hardware can be put

    in the BoM.

    3 Vol 2, Annexure XVII Format of Bill of

    Material for software components

    (page No 75)

    Software Licenses AMC cost There is no place holder to put AMC price of the software

    licenses for the period of 5 yrs.

    The table provided for Annual

    Maintenance Charges should contain

    the AMC price of Software licensing.

    4 Vol2, Annexure XVII Format of Bill of

    Material for Services (page No 75)

    Software Licenses Purchase Software licenses will be procured on whose name?

    Whether IDRA wants IA to buy licenses on IDRA’s name

    on the first day of the purchase OR does it want licenses

    to be transferred on IRDA’s name after 5 yrs.

    The licenses should be procured in

    the name of IRDA.

    1 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    5 Vol2, Annexure XVII Format of Bill of

    Material for Services (page No 75)

    Bill of Material for services: Please give an example for the software services in this

    table. Or elaborate the object of this table

    This table should be used for

    providing cost elements required for

    the managed services.

    6 Vol 2, Annexure XVI Format for

    Commercial bid Form II Financial Bid,

    page 74

    Man Month Rate Please verify our understanding. This table will be only

    utilized for additional scope scenario. At the time of bid

    submission, IA need not to fill this table and can be

    submitted as blank.

    This table would be used for

    providing the manpower cost for the

    entire implementation of the project

    including post go live support

    7 Vol2, Clause 4.6, page no. 40. Price comparison Please specify the tables which will be considered for

    arriving on the total cost of ownership (TCO) in the price

    schedule. There are also man month’s rates asked in the

    bid. So please clarify the price component table wise for

    finalization of TCO.

    Costs for SW development should be

    mentioned in the first table of the

    annexure XVI. Hosting charges should

    be mentioned in the second table

    and the third table should contain

    the costs for AMC. Costs from all

    these three tables combined

    together will provide the TCO for the

    project.

    8 Annexure III It is envisaged that a bandwidth

    requirement of approximately 8.325

    MBPS.

    Please indicate whether IRDA will maintain the

    connectivity of the users with the datacenter or does the

    IA need to provision for the same and charge IRDA

    accordingly.

    Is it expected that AI should provision for internet

    bandwidth? And for how many years AI should provision

    for bandwidth.

    IA will maintain the connectivity of

    the users with the datacenter and

    will charge IRDA accordingly.

    9 Annexure III Bandwidth Can you please detail the processing and storage

    capacity of DR with respect to DC?

    The DR should be running at 80%

    processing capacity of the DC but

    there should be 100% data

    replication in the DR.

    10 Annexure III Bandwidth Is it possible to provide bandwidth requirement year on

    year for entire contract period for primary and secondary

    link?

    Bandwidth has been specified in RFP.

    2 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    11 Annexure III Users Please indicate the rise in the number of users of this

    solution over the next 8 years for which this solution has

    to be supported

    The approximate per year growth in

    the no. of users will be 8-12%.

    12 IRDA_RFP_Vol1_V15.5/Section 305/

    Page 15

    Dashboard Please provide a list of all types of KPI's/ performance

    metrics required on Dashboard & calculation logic for

    each.

    The detailed report and dashboard

    formats would be provided to the

    selected IA.

    13 IRDA_RFP_Vol1_V15.5/Section 8.2/

    Page 45

    Balanced Scorecard Please elaborate on business logic for Balanced

    Scorecard generation.

    The reports or dashboards may have

    similar representations as of a

    scorecard. But no scorecard

    requirements have been envisaged

    as of now.

    14 IRDA_RFP_Vol1_V15.5/Section 1.2/

    Page 4

    Report Security Please provide details of security requirements for

    reports (when uploaded by external parties/ when

    displayed on public domain)

    The IA will have to assess this during

    the design phase.

    15 BAP_Requirements

    Specifications_v25/ Section IV (i)/

    Page 209

    Analysis by IRDA Please list some scenarios (& corresponding logic) that

    are required to be covered for performing “What-if

    Analysis”

    The detailed logic for the same would

    be provided to the selected IA.

    16 IRDA_RFP_Vol1_V15.5/Section 3.6/

    Page 18

    Data reconciliation How is reconciliation of data in Finance & other

    departments done? Please elaborate on what data are

    reconciled & provide the reconciliation process & logic.

    Also, provide a list of non-compliance deviations w.r.t

    IRDA regulations & also mention at what point validation

    for each is fired in the business process.

    The detailed report formats on

    exceptions, non compliance and

    reconciliations would be provided to

    the selected IA along with the

    business logic for the same.

    17 IRDA_RFP_Vol1_V15.5/Section 3.6/

    Page 18

    IRDA Inter-departmental communication Is Inter-departmental communication a part of the

    proposed system? If yes, please elaborate

    No

    18 IRDA_RFP_Vol1_V15.5/Section 2.2/

    Page 9

    Insurer advertisements What are Insurer advertisements? How are they to be

    handled?

    The detailed input formats and

    reports on advertisements would be

    provided to the selected IA.

    3 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    19 IRDA_RFP_Vol1_V15.5/Section 3.4/

    Page 14

    Access Control Please provide all details on access control i.e. role-based

    definitions for sub-modules/reports etc. Also provide

    access control matrix.

    Please refer to the sections on

    authorization and access

    management in the requirements

    specifications document for further

    details. The access control matrix will

    be defined by IA, in consultation with

    IRDA, during the design phase of the

    implementation.

    20 IRDA_RFP_Vol1_V15.5/Section 3.2/

    Page 13

    Document Template Will IRDA be using standard templates for all parties

    during data upload? In any case, please provide format

    for standard/ non-standard templates used by various

    stakeholders.

    The detailed input formats for data

    submission and uploading would be

    provided to the selected IA. As an

    example please refer to the sample

    forms and reports provided along

    with the RFP document.

    21 BAP_Requirements

    Specifications_v25/ Section III

    Appendix/Page 92

    Intermediaries-Brokers-Reports

    Management-Status on Registration-

    Granted but cancelled

    Applications where in-principal approval

    issued but license not granted.

    Please elaborate on what is meant by Granted but

    cancelled

    How do we track this? Do we have any particular status

    for such cases

    By this it is meant that the license to

    a broker has been granted initially

    but cancelled at a later point in time

    due to some violations with respect

    to the regulations. The detailed

    report format and logic for tracking

    this information to the selected IA.

    22 IRDA_RFP_Vol1_V15.5.pdf/1.2 (g)/

    Page 5.

    Benchmarking the existing financial

    reporting framework with the

    international best practices

    Benchmark details to be provided or not ? The detailed report/study on

    international best practices study will

    be provided to IA if required.

    23 IRDA_RFP_Vol1_V15.5.pdf/4 ii/ Page

    21

    On the basis of the application design

    signed off by IRDA or its representative,

    the individual applications shall be

    modeled and designed using relevant

    modeling and design languages like UML.

    Does first reference to application design refer to

    solution architecting and does the rest of the statement

    signify that the solution architecting should be signed of

    before individual application designing? Or is it the SRS

    which is actually referenced?

    The sign off on SDD or the software

    design document has been referred

    here.

    4 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    24 IRDA_RFP_Vol1_V15.5.pdf/4 ii/ Page

    22

    IA shall provide all necessary support,

    including setting up the required test

    environment, making seating

    arrangements and providing suitable

    computer systems & peripherals, to the

    agency for conducting acceptance testing

    IRDA shall provide the number of testers who will be

    involved in the UAT, and hence IA can make the

    necessary seating arrangements?

    Yes

    25 IRDA_RFP_Vol1_V15.5.pdf/4 iii/

    Page 22 & Section 6 of Page 25

    Migration of legacy data Is migration of legacy data is a part of requirement study

    and will be part of SRS document or it will be separate? If

    yes, does it falls within the project execution timeline of

    12 months? Project Timeline does not explicitly states

    anything on the same.

    Data migration will be a part of

    requirements study and the 12

    months timeline for the

    implementation of the project will be

    inclusive of the same.

    26 IRDA_RFP_Vol1_V15.5.pdf/4 v/ Page

    31

    Procurement of testing tool Since the tool will be decided later, how will it be priced

    in the bid?

    Pricing information of testing tools

    are not necessary.

    27 IRDA_RFP_Vol1_V15.5.pdf/4 v/ Page

    53

    Payment gateway Will it be an IRDA provided payment gateway or part of

    the infrastructure provided by the IA?

    IRDA as of now hasn't got any

    payment gateway in place. The

    payment gateway including the

    interface requirements needs to be

    developed by the IA. Please refer to

    page 53 of the volume I of the RFP

    document for further details.

    28 IRDA_RFP_Vol1_V15.5.pdf/4 v/ Page

    59

    Active passive mode between DC and

    DRC

    Is IRDA mandating processing from the DRC even in

    normal time?

    Only when the DC is down, the

    processing from DRC would start.

    29 IRDA_RFP_Vol1_V15.5.pdf/Section

    10.2- BCP/Page60

    Two similar sites (one DC and one DR site)

    have been proposed which should always

    be up and running for normal operation.

    In case of higher recovery normal

    expectations a near site is also proposed

    which will get replicated at almost at a

    near real time.

    We would like to understand the requirement for a "near

    site", considering that high availability can be achieved

    using a DC-DR setup.

    Near site has been cited as an option

    in the RFP document. Suggestions are

    open from the bidder in this regard

    5 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    30 IRDA_RFP_Vol1_V15.5.pdf/Section

    10.2- BCP/Page59

    Minimal data loss should be envisaged

    during failure and that too only to the

    extent of data being in the transmission

    lines. Also, all such incidents should be

    suitably notified to the clients/users.

    What is the acceptable amount of data loss applicable for

    BAP solution?

    Zero data loss is applicable for BAP

    solution.

    31 BAP_Requirement

    Specifications_v25.pdf/Section

    6/Page 49

    Content Publishing and Authoring:

    upload/download documents by both the

    internal and external users of the system

    How many external users are expected to use the

    system?

    The content management system is

    going to be used by both internal

    users and external entities i.e.

    insurers and intermediaries.

    Approximately 1000 external users

    will use this module.

    32 BAP_Requirement

    Specifications_v25.pdf/Section

    1.3/Page 31

    1.3: File and Use Workflow for new

    product launches

    The status of the product is updated in

    the database and UIN is assigned to the

    product

    Our assumption is that application /system to generate

    UIN is already in place. It is expected that the proposed

    system workflow will integrate with the UIN generation

    application. Please confirm

    As of UIN related data is maintained

    in spreadsheets which needs to be

    loaded in the Business Analytics

    Solution

    33 BAP_Requirement

    Specifications_v25.pdf/Section

    1.3/Page 33+B41

    1.4: Licensing of Brokers/ Surveyors, TPAs

    and ATIs

    System should generate a License

    certificate with the unique license

    number, put digital certificate on the

    certificate and email it to the applicant

    Our assumption is that as of today also, IRDA issues

    license certificates to brokers and other entities. Will the

    same application/ system be used to generate this

    certificate in the future?

    The functionalities for licensing of

    intermediaries needs to be built

    inside the BAP solution.

    34 BAP_Requirement

    Specifications_v25.pdf

    Use of digital certificates as part of

    workflows

    Does IRDA use digital certificate as of today? Do you

    need the vendor to also provide digital certificates and

    system to verify the same?

    No. As of now there is no facility to

    generate digital certificate by IRDA.

    The issuance of digital certificate is

    in the scope of work for the bidder.

    35 BAP Requirement Spec Is there a need for real time reporting? What would be

    the frequency of data update in each of these reports

    No

    6 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    36 BAP Requirement Spec/Page 160 Any approximate complexity distribution to the list of

    forms provided?

    Sample formats, shared with the RFP,

    is representative of the complexity

    distribution. The complete set of

    forms will be shared with the

    selected IA.

    37 BAP Requirement

    specification/Section 2.1/Page 40

    2.1.14. The system should support

    reporting over both thin client and rich

    client i.e. over web interface and client

    desktop interface

    Please explain the expectation in detail. Who will use the

    desktop interface of BAP system

    IRDA users.

    38 BAP Requirement

    specification/Section 2.6/Page 62

    The system should have flexibility to

    regenerate the programs and features

    without starting the development process

    from very beginning. The system should

    have an user interface to support the

    same so that the entire development

    activity can be replicated to a new set up

    without much of problems

    Please explain in detail By this it is meant that the

    application should have in built back

    up and replication mechanism

    through which the status of the

    system can be restored at any point

    in time without replicating the

    development efforts from the scratch

    7 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    39 IRDA_RFP_Vol1_V15.5.pdf IRDA Portal: The portal will provide a

    platform for the extended enterprise to

    be managed. It will therefore expose both

    enterprise applications and a number of

    functional applications to the extended

    enterprise. The portal should therefore

    operate through an appropriate parser

    that is able to render a broad number of

    services while connected to the portal.

    Each response request in the portal

    should be well integrated with the

    parsing application. The parser

    application and infrastructure is expected

    to form a key component of solution

    design.

    Please clarify what is meant by "parser"? Parser is a generic term used here as

    an intermediate layer to handle

    response and requests within the

    modules/services within and outside

    the portal application.

    8 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    40 IRDA_RFP_Vol1_V15.5.pdf Digitization We understand that as part of process reengineering,

    Documents will be electronically uploaded on the IRDA

    site. As part of digitization, scanning and data capture is

    required to be performed for data migration.

    1) Would IRDA be purchasing the scanners and

    infrastructure required for Digitization?

    2) If no, would you require the IA to provide the

    infrastructure for digitization process?

    3) Do you also want the IA vendor to provide services like

    scanning, data entry, quality check etc?

    4) What is the volume of documents in pages required to

    be digitized? What is the expected time-frame?

    5) What is the percentage distribution of historical data

    across Hard copy documents, RDBMS, excel sheets,

    unstructured content?

    The entire data migration activity

    starting from the infrastructure

    requirement to the

    digitization/scanning is in the scope

    for the selected IA. The IA can

    leverage their existing infrastructure

    for the digitization activity. The

    bidder needs to propose the timeline

    for these activities.

    41 IRDA_RFP_Vol1_V15.5.pdf Present IT System Infrastructure Will the proposed portal replace any of the existing

    portals /website of IRDA?

    No. But the portal for online filing for

    brokers may get decommissioned in

    future since online filing

    functionalities for brokers would be

    covered in the BAP solution,

    42 IRDA_RFP_Vol1_V15.5.pdf, Section

    4, Page 23

    XII. IA shall set up an appropriately

    staffed and centralized helpdesk for

    providing helpdesk support to various

    users of the BAP application. The

    helpdesk team should comprise of at

    least four members for support on a

    continuous basis in the onsite support

    phase

    Understand that the onsite support will constitute the L1

    team. This team will log the tickets and pass on the

    incident to the technical team for resolution. Pls confirm

    Yes

    9 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    43 IRDA_RFP_Vol1_V15.5.pdf, Section

    7.1.1, Page 26

    Solution Sizing

    Consumers - what is the profile of consumers? Are they

    internal or external users of the system?

    Consumers are the policyholders.

    They are external users.

    44 IRDA_RFP_Vol1_V15.5.pdf, Section

    7.1.12 Page 32, Section 11.2 Page 64

    Section 7.1.12

    A detailed Training Plan shall be

    submitted by the Implementer for which

    the logistics and supportive arrangements

    will be borne by IRDA.

    Section 11.2

    IX. IA shall provide comfortable training

    space with sufficient arrangements (e.g.

    air conditioning, printed course material,

    workstations, refreshments etc.) for

    trainees at the training location

    It is mentioned that logistics and supporting arrangement

    for end user training will be provided by IRDA in Section

    7.1.12, where as Section 11.2 Point IX mentions that

    these have to be provided by IA.

    Request clarification

    A detailed Training Plan shall be

    submitted by the IA for which the

    logistics and supportive

    arrangements will be borne by IRDA.

    45 IRDA_RFP_Vol1_V15.5.pdf/Section

    7.1.1 -Solution Sizing/Page26

    1 Insurers 200 Users

    2 Internal Users 80 Users

    3 Brokers and TPAs 350 Users

    4 Surveyors 220 Users

    5 Peer Regulators, Govt. bodies and

    others 50 Users

    6 Consumers 100 Users

    Is the user data mentioned are for 1st Year ? .Please

    provide year wise projections for next 5 years

    The approximate per year growth in

    the no. of users will be 8-12%.

    46 IRDA_RFP_Vol1_V15.5.pdf/Section1

    0.1 RPO/Page 57

    There should not be any data loss under

    any circumstances

    Pls specify RPO requirements if any The detailed RTO and RPO

    requirements will be provided to the

    selected IA.

    10 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    47 IRDA_RFP_Vol1_V15.5.pdf/Section

    7.1.1 and 8.1.2 /Page no 26 and 44

    1.Ref. Page 26-IRDA Internal Users =80

    2.Ref Page 44-Intranet

    Are there any WAN/Intranet requirement? Is IRDA

    looking for connectivity between existing IRDA offices

    and proposed hosted solution?

    Please specify the number of IRDA offices need to be

    connect to the proposed hosted DC and DRC over WAN?

    Please provide the all office addresses which has to

    connect to the proposed hosted DC and DRC location?

    The Hyderabad office for IRDA shall

    be connected by dedicated VPN or

    MPLS to the proposed hosted DC

    48 IRDA_RFP_Vol3_ v23.5.pdf/ SLA

    Table-sr no-4/Page No 71

    System support for Concurrent users.

    Expected SLA-Support 500 Concurrent

    Users for Internet Portal

    Number of Concurrent Users mentioned in Volume-

    1/page no 104 is 150. In the SLA table Vol-3, concurrent

    users = 500 . Can you pls confirm which data can be used

    for sizing estimation.

    No. of concurrent users should be

    150.

    49 IRDA_RFP_Vol1_V15.5.pdf , Section

    11.3.5

    Helpdesk Please let us know the coverage window required for the

    help desk

    24X7 for 5 years post go live of the

    BAP solution.

    50 RFP VOL I3, Pg 70, SLAs, Availability, Scalability Should the solution support scalability (both vertical &

    horizontal) with no downtime and without repartitioning

    or changes to the database objects or 3rd party

    transaction routing mechanisms

    Suggestions are open from the

    bidders in this regard

    51 RFP VOL I. pg 59, Sec 10.2 During normal operations, both the DC

    and DRC should be running in the

    ―Active-Passive mode with an automatic

    load balancer between them, sharing 80

    per cent of the full envisaged load.

    Kindly clarify whether the servers in DC and DR will be in

    the active-passive mode or whether they will be

    synchronized by the changes happening in the DC

    Servers in DC and DR will be active-

    passive mode with zero data loss.

    52 RFP VOL I, 97, Annexure I: Strategic

    Control Requirements

    Audit of DBA Actions Apart from auditing DBA actions, is it also required to

    prevent the DBAs to access confidential application data

    Yes

    53 RFP VOL I, 97, Annexure I: Strategic

    Control Requirements

    Protection of Confidentiality and Integrity

    of data

    Kindly clarify the following:

    “the data which must not be modified shall be hashed

    and digitally signed by the application at the time of

    original data population itself”

    Data which is non modifiable in

    nature at a future reference time

    should have to be signed digitally.

    54 RFP VOL I, 103, Anx III Solution sizing Does the data sizing estimate “include” data generated

    during “data migration/digitization”.

    Yes

    11 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    55 RFP VOL I,9, Sec 2.2 Kindly clarify about the capabilities of the

    existing Content management system

    Does IRDA has a full fledged content management

    system or is it a custom build one?

    A content management system

    needs to be built from scratch for the

    BAP solution.

    56 BAP_Requirements

    Specifications_v25, Pg 67, Section 6

    User Interface Requirement Clarification on do third parties also require access to

    static reports or online reports? will it be Read-only or

    interactive ?

    The reports accessed by external

    entities would be of read only and

    static nature

    57 Clarification on master data

    management requirement? Is it a full

    fledged MDM solution required or is

    it management of some master

    tables that contain reference data ?

    The system should have the ability to

    create/update the Master data as per the

    need of the implementation.

    Clarification on master data management requirement?

    Is it a full-fledged MDM solution required or is it

    management of some master tables that contain

    reference data ?

    Master Data Management is limited

    to only BAP solution not across all the

    applications within the organization

    58 BAP_Requirements

    Specifications_v25, pg 39, Section 6

    Is the reporting solution required to run

    on Active-Active clustering?

    Reporting Active - Passive Clustering is also

    applicable for the reporting solution

    59 BAP_Requirements

    Specifications_v25, pg 62, Section 2

    Metadata management tool Could you clarify on Metadata management tool – What

    context are we planning to use this for? Is metadata

    management only at DW layer?

    Metadata management is only

    applicable to the DW and reporting

    layer.

    60 BAP_Requirements

    Specifications_v25, section 1.1/Page

    56

    1.1.4 The system should support

    ASP.NET, JDBC and other open standards

    options.

    ASP.NET is not open standards based, it is Microsoft

    proprietary.

    The system should support ASP.NET,

    JDBC and open standards options.

    12 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    61 BAP_Requirements

    Specifications_v25, Section 11:

    Master Data Management

    Master Data Management Please let us know the rough estimate of number of

    records need to be maintained under each of the

    following category:

    IRDA Organization structure

    Channels(Agents, Brokers, Corporate agents, etc)

    Rider master

    Segment master

    Geography master

    Rural / Urban Master

    Account Master

    Asset Master

    Complaints Master

    Currency Master

    Surveyor Master

    ATI Master

    Master list of category of Investment

    Fund Type

    An overall data sizing estimation has

    been provided in the RFP. Further

    detailing needs to be assessed during

    implementation.

    62 BAP_Requirements

    Specifications_v25

    Section 2.7: Metadata Management

    Metadata Management 1. List the metadata from different sources that you want

    to store in metadata

    repository(For example, Two Oracle 9.2 sources, four

    Cognos reporting source, etc)

    2. Estimate the total anticipated number of Metadata

    users that will be operating

    3. Concurrent Metadata Management users

    An overall data sizing estimation has

    been provided in the RFP. Further

    detailing needs to be assessed during

    implementation.

    13 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    63 BAP_Requirements

    Specifications_v25

    Section 2.9: Data Migration and

    Integration

    Data Migration and Integration Please provide a short high level description of your

    current environment, such as applications, database

    systems, servers, end user clients, ETL tools, etc..

    Number of Data Sources:

    Type of each source (mainframe, relational, flat files):

    Initial/current total data(from all the above sources) that

    needs to be migrated to Business Analytics database

    Time kept for initial data migration

    Daily data volume from all the above sources

    Daily batch time to load the daily volume from the above

    mentioned data sources

    How frequently will each source need to be processed

    (daily, weekly, monthly)

    What are the estimates of growth in data volume for

    each source over the sizing time period?

    Estimate what could be the maximum number of Jobs

    that need to execute concurrently.

    Estimated complexity of these jobs: (Very

    Complex/Complex/Medium/Simple).

    How many jobs will need to run at peak times?

    Users for Client software

    Number of environments that you would like to have (for

    example, 1 production, 2 development, 2 QA,etc)

    Average number of concurrent web service request

    made through SOAP. And total number of web service

    requests to be made daily

    Relevant information for the existing

    applications have been provided in

    the RFP. Further detailing needs to

    be assessed during implementation.

    14 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    64 BAP_Requirements

    Specifications_v25

    Section 2.9: Data Migration and

    Integration

    2.9.6.6 Incremental loading

    2.9.6.7 Refresh with ability to Change

    1. What are all the data sources(databases) from where

    incremental data needs to be taken. Also, lists the

    hardware configuration of each of these source systems

    where database server is running. For example, DB2 9.1

    running on IBM P6 570 server with 8 cores and 16 GB

    RAM

    2. Do you intend to capture incremental or change data

    on a real-time or near real-time

    3. Is Archive logging enabled on all the source system

    where incremental/change data needs to be captured

    Data needs to be fetched from the

    system both on an incremental and

    near real/real time basis.

    65 IRDA_RFP_Vol1_V15.5 / 7.1.2 Data Migration What is the volume of data to be migrated/digitized?

    Please provide the inputs split by the source application/

    subject area.

    The size of historical data has been

    mentioned in annexure III of the

    volume I of the RFP document.

    Approximately 40% of the data

    available in hardcopies.

    66 IRDA_RFP_Vol1_V15.5.pdf /

    Annexure III

    Detailed Data Sizing The data volumes & growth rates mentioned in this

    section, are these past metrics or estimated future

    metrics?

    - If future, what is the volume of historical information to

    be considered.

    - If past, what is the future data growth rate.

    Also the data volumes shown here need to be considered

    for the central data repository. Is this correct?

    Data sizing estimation has been

    provided taking into account the

    history data for the past 8 years till

    the present time period and has been

    projected for the next 8 years. For

    growth rates of data please refer to

    annexure III of the volume I of the

    RFP document.

    15 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    67 Generic questions What is the maximum number of documents published

    into the content repository per day ?

    What is the maximum number of documents retrieved

    from the content repository per day ?

    What is the average size of a document stored in the

    content repository?

    How many pages approximately constitute a document?

    How many pages to be scanned per day?

    How many document related workflow processes are

    launched per day?

    What should be the total data backup duration?

    We request IRDA to provide us the compliance in the

    form of an excel sheet

    At present there is no content

    management solution is present in

    IRDA, standard assumptions needs to

    be considered

    68 BAP_Requirements Specifications -

    Page 112 -

    File Management/ Correspondence

    management

    As mentioned in the RFP there is a high priority

    requirement for Correspondence Management, File

    movement tracking & management.

    We understand that the proposed solution should

    preferably be based on Manual of office Procedure MOP

    from DARPG- Department of Administrative Reforms And

    Public Grievances), which is the file movement and

    record management standard of Government of India

    and features like Whitehall based file movement ,

    Supports for Green Note sheet, Secure notes and

    annotations, Support for Hindi are important. Kindly

    confirm our understanding.

    Yes

    69 Volume I IRDA RFP - Page 39 -

    Section 8

    Solution Architecture As it is mentioned in RFP that the scalability and

    performance of solution is one of the key objectives, so

    are you looking for an architecture in which

    images/documents are stored in a file server while only

    the metadata is stored in databases so as to increase the

    scalability of the application

    Yes

    16 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    70 Volume I – IRDA RFP - Page 48 -

    Section 8.3

    Business Process Management As this RFP aims to replace existing manual

    systems of paper based working in the IRDA departments

    by automating the multiple workflows involved in the

    day to day business activities of the departments of the

    IRDA, our understanding is that you need a Business

    Process Management (BPM) platform which has the

    capabilities of graphically modeling the processes, in built

    Form designer, process simulator, rule engine,

    configurable Business Activity Monitoring tool and

    integrated Document Management System for storing

    documents. Please confirm our understanding is correct.

    Yes

    71 Volume I – IRDA RFP - Page 49-

    Section 8.3

    Content Management We understand that less paper initiative is key

    requirement of project and so there will be requirement

    of capture solution for scanning backlog as well as

    ongoing paper documents with support for following :

    page separator, barcode separator and fix page

    Please confirm our understanding is correct.

    Bidder needs to propose the same.

    72 Volume I – IRDA RFP - Page 194 -

    Section 8.3

    Content Management System/Document

    management system

    Since the Enterprise Content Management System will

    be storing critical documents of IRDA which needs to be

    archived for long term, so is the department looking at

    archiving documents in PDF/A format which is an open

    ISO standard for long term archival and is now becoming

    de-facto standard in most government projects

    As per the prevalent industry

    standards.

    17 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    73 Volume I – IRDA RFP - Page 75 -

    Section 12.1

    Data Digitization As digitization is one of the key requirement of the

    project so our understanding is that the proposed

    solution for digitization/ scanning should take care of

    automatic correction of parameters like improper

    resolution, format/ compression not proper, skew,

    wrong orientation, error in automatic cropping, punch

    hole marks etc so that the quality of digitized data is

    ensured.

    Yes

    74 Volume I – IRDA RFP - Page 75 -

    Section 12.1

    Data Digitization As there is requirement of ICR solution in the RFP so are

    you looking at data capturing solution for extracting

    business-critical information from Forms for further use

    in Applications, Workflow, and other Information

    Management Systems

    Yes

    75 Volume II – IRDA RFP - Page 79 - Ann

    XIX

    Checklist of the documents

    Checklist of the documents to be

    submitted along with commercial

    proposal.

    Performance Guarantee with the

    covering letter as per the format specified

    (Only applicable after award of contract)

    Stage for submission for this commercial proposal.

    Need clarification as EMD indemnify till contract signing

    and PBG to come post to that. Hence what should be

    submission date?

    Technical and commercial proposal

    would be submitted together along

    with the EMD.

    76 Volume III – IRDA RFP - Page 6 Draft MSA Please confirm on the understanding that MSA to be

    reviewed for during contract signing. Comments

    regarding MSA to be provided, only after technical

    presentation i.e. at the time of contract signing.

    Yes

    77 Back Up How many Windows / Linux /Unix Servers Participating in

    the Environment

    The exact technical specifications

    would be shared with the selected IA.

    78 Back Up Any Virtualization in the environment ? Like Xen , Hyper-

    v or ESX

    The exact technical specifications

    would be shared with the selected IA.

    79 Back Up How many tape drives / Library in the environment ? The exact technical specifications

    would be shared with the selected IA.

    18 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    80 Back Up Is the Environment on SAN ? The exact technical specifications

    would be shared with the selected IA.

    81 Back Up What are the databases associated in this environment

    and in which platform?

    The exact technical specifications

    would be shared with the selected IA.

    82 Availability What are the databases and Servers needs to be

    replicated and needs High Availability?

    The exact technical specifications

    would be shared with the selected IA.

    83 Availability Does the customer requires SAN based replication or

    Host based replication?

    The exact technical specifications

    would be shared with the selected IA.

    84 IRDA_RFP_Vol1_V15.5/Section

    2.3/Pg: 10

    Existing Application and its status IA understands that in the table provided in the ‘Existing

    Application section’, the grievance management system

    and agency portal system will continue as it is. Can you

    let us know how other systems are getting transformed

    in the new system?

    As far as the BAP solution is

    concerned it is going to be loosely

    integrated with agency licensing

    portal, integrated grievance

    management systems, Health

    Database and broker return

    submission application only. The

    status of other systems has no

    relevance with BAP.

    85 IRDA_RFP_Vol1_V15.5/Section

    3.5/Pg: 16

    Report Administrators Are ‘Report Administrators’ referred here business

    users/technical team/developers?

    Report administrators are persons

    from the technical team of both IRDA

    and IA

    86 IRDA_RFP_Vol1_V15.5/Section

    12/Pg: 73

    Pre Migration Activities: Clean up source

    data in current system

    Our understanding is that IRDA currently has a database,

    which holds data from all the stakeholders. IA

    understands that they have to clean up this data before

    loading it into the new system. Please confirm.

    At present data is captured in the

    form of spreadsheets, word

    document, PDFs, e-mails and

    hardcopies in unstructured formats.

    By cleaning up it is meant that these

    data needs to be first converted into

    a structured format and then

    migrated into an RDBMS.

    19 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    87 What are the various source systems holding the data

    each of the below groups? What is the total number of

    files from each source system?

    i. Insurance Companies

    ii. Standalone health Insurance Companies

    iii. Brokers

    iv. ATI

    v. TPA

    Also, please provide details of "other" databases that

    need to be integrated into ODS and DW.

    As per the present scope, the BAP

    solution is not going to be integrated

    with applications / systems of

    external stakeholders. This is a future

    requirement. However, the BAP

    system should have the flexibility to

    have seamless integration with these

    external systems in future if required.

    Hence understanding of the external

    applications / systems belonging to

    external stakeholders in not required

    at present.

    88 How will data be available for IA to extract? Will IA be

    pulling data connecting to each source system or will it

    be provided to IRDA using push mechanism? Please

    clarify.

    The external entities

    (insurers/intermediaries etc.) will

    either key in data in online forms or

    will upload the data through a batch

    process. Data will be provided to the

    IA for loading. The IA will not be

    responsible for pulling data from the

    source systems of these external

    entities.

    IRDA_RFP_Vol1_V15.5/Section

    3.1/Pg: 12

    Proposed Business Analytics Solution:

    In the proposed system, both statistical

    and regulatory data coming from the

    external entities will be stored in a

    centralized data store which will be

    transformed, cleaned and structured to

    make them available in form of reports

    and analysis to both IRDA internal

    stakeholders and external entities.

    20 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    89 IA assumes that they will implement BAP reporting

    solution while considering the reporting requirements

    for the departments given below:

    a) Actuarial

    b) F&A

    c) Investments

    d) Re-insurance

    e) Life

    f) Non life

    g) Health

    h) Intermediaries

    Please confirm the same.

    Apart from these departments, there

    is an inspection department which

    uses data from the other

    departments for reporting purpose.

    Each department can be further split

    into different analysis areas or

    subject areas on which final reporting

    and analysis will be performed.

    However, since in present scenario,

    new regulations are coming few

    more departments can get

    introduced in future.

    90 IA understands that unstructured format is hard

    copy/unformatted files.

    How many source systems and total number of hard

    copy/files in each system will be received in unstructured

    format?

    Other than hard copy, In which format the unstructured

    data will be (.xls, .doc, .csv etc) received. If any other

    format, please specify.

    Apart from the hardcopies, data is

    maintained in form of spreadsheets,

    word documents , PDFs and picture

    formats (JPD,JPEG,BMP)

    91 What is the total number of unstructured data files (pdf,

    doc, xls etc) which needs to be migrated to the new

    system?

    Mentioned in the RFP

    IRDA_RFP_Vol1_V15.5/Section

    3.1/Pg: 12

    Proposed Business Analytics Solution:

    In the proposed system, both statistical

    and regulatory data coming from the

    external entities will be stored in a

    centralized data store which will be

    transformed, cleaned and structured to

    make them available in form of reports

    and analysis to both IRDA internal

    stakeholders and external entities.

    IRDA_RFP_Vol1_V15.5/Section

    12/Pg: 73

    Pre-Migration Activities:

    Format unstructured data in other

    systems

    21 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    92 IRDA_RFP_Vol1_V15.5/Section

    12/Pg: 73

    Key Activities during Data Migration: Run

    data extracts from current system(s)

    Are the hard copies provided by the Insurers all in the

    same format? If no, Please specify the formats.

    The hardcopies provided by the

    entities (insurers/intermediaries) are

    in different formats. As of now for

    most of the departments, data is

    collected in dissimilar formats. As a

    part of form reengineering activity in

    new forms have been designed for all

    the departments which will be used

    for data collection from the entities.

    Some sample forms have been

    shared along with the RFP document.

    Post selection of the IA, the final set

    of reengineered forms will be

    provided to the IA.

    93 Can IRDA get hard copies of all historical data in an

    electronic format from the Insurance companies and the

    other stakeholders like brokers, TPA etc?

    No

    94 IRDA_RFP_Vol1_V15.5/Section

    12/Pg: 73

    Pre Migration Activities: Create metrics to

    capture data volume, peak hours and off-

    peak hours.

    What kind of metrics is expected out of IA? Please clarify

    and provide all the metrics required.

    Metrics here refer to average data

    volume migrated/converted per day,

    data volume migrated/converted at

    peak hours and data volume

    migrated/converted at off peak

    hours.

    95 IRDA_RFP_Vol1_V15.5/Section

    12/Pg: 73

    Data Migration and Digitization

    Requirements

    IA assumes that Data Migration means extracting the

    history data from various unstructured sources into ODS

    and DW for reporting requirements. Please confirm.

    Data migration is not only meant for

    DW or reporting perspective but also

    from a document management and

    archival perspective.

    22 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    96 IA understanding is that IA has to identify the data

    quality issues based on the sample data and business

    rules which will be provided by IRDA. Please confirm.

    Yes

    97 The Data Stewards from each system will fix the data

    quality issues identified by IA and re-send the data for

    migration.

    Yes

    98 IRDA_RFP_Vol1_V15.5/Section 4/Pg:

    21

    Please clarify the role of IA in performing acceptance

    testing.

    IA shall provide all necessary support,

    including setting up the required test

    environment, making seating

    arrangements and providing suitable

    computer systems & peripherals, to

    the agency for conducting

    acceptance testing.

    99 Please provide the number of: Following are the possible no. of

    members for dimensions mentioned

    below. However, these are subject to

    change with respect to future

    regulations

    100 1. Product categories? 2

    101 2. Divisions? 4

    102 3. Groups? 2

    103 4. Channels? 10

    104 5. Premium types? 2

    105 IA assumes that all data from various external entities is

    at summary level and not at individual policy/claims

    transactional level. Please confirm.

    The bidder's assumption is in order

    IRDA_RFP_Vol1_V15.5/Annexure

    III/Pg: 103

    Annexure III: Detailed Data Sizing Estimate for IRDA BAP

    IRDA_RFP_Vol1_V15.5/Section

    12/Pg: 73

    Data Cleansing: A ‗semantic‘ data quality

    issue in which data does not comply with

    ‗As Is‘ business rules

    IRDA_RFP_Vol1_V15.5 Delivery channel Architecture

    23 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    106 If ‘Yes’ to the previous question, then please clarify the

    number of files that are summary files, which will be

    available for BAP reporting from each external interfaces

    and what is the expected granularity of data in each

    source files?

    If ‘No’, then please clarify the number of daily

    transactional files and the granularity of data in source

    files.

    Please refer to annexure III of the

    requirements specification document

    for details. Once, the IA has been

    selected the exact report formats

    will be provided to the IA which will

    help the IA in understanding the

    exact granularity of the data.

    107 IRDA_RFP_Vol1_V15.5 Data Archival Please provide the frequency and the period of archival. Data is to be archived for 8 years of

    history data and all the data including

    history needs to be archived for

    future reference. The frequency of

    the data archival should be yearly.

    108 IRDA_RFP_Vol1_V15.5 Go Live and Final Acceptance IA understands that Maintenance and Support starts

    from Go-Live and not from Final Acceptance Date. Please

    clarify.

    Maintenance and Support starts from

    successful Go-Live of the solution

    109 IRDA_RFP_Vol1_V15.5/Section

    11.3.1.2/Pg: 65

    Application Management: 24/7 Support IA assumes that the requirement for 24/7 availability is

    only applicable for online applications and not for

    reporting applications. As data load for reporting will

    happen during the night time and hence reporting

    applications may not be available.

    This is applicable for both reporting

    and the online portal.

    110 IRDA_RFP_Vol1_V15.5 BI Reports What is the latency period in BI reports? IA assumes that

    it is one day. Please clarify.

    Minimum one day period of latency

    on an usual basis. However in some

    cases, extraction frequency can be

    real time also.

    111 IRDA_RFP_Vol1_V15.5 BI Testing Can you specify the non-functional requirements for

    performance testing (like peak load, concurrent users,

    the minimum response time at that load etc)?

    The IA need to propose this in testing

    methodology proposed for BAP.

    IRDA_RFP_Vol1_V15.5 Delivery channel Architecture

    24 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    112 IRDA_RFP_Vol1_V15.5 BI Testing Is there need for data masking required in SIT,

    Performance testing and UAT. What % of tables or fields

    are required data masking?

    Data security aspect has been

    specified in RFP

    113 IRDA_RFP_Vol1_V15.5 BI Testing Is Downstream Extracts/Report Testing in scope, if so

    what are the downstream systems and complexity of

    data extracts?

    Testing has been specified in RFP

    114 IRDA_RFP_Vol1_V15.5 BI Testing What is the current defect logging system and defect

    triage (include the defect status)

    There is no defect logging system

    present with IRDA. IRDA would like to

    best leverage this based on the

    capabilities of the IA in this area.

    115 IRDA_RFP_Vol1_V15.5 BI Testing Can you please share the QA certification process for

    reports and Analytics data (on what parameters

    certification is done)?

    The detailed quality certification

    process will be shared only after final

    selection of the IA.

    116 IRDA_RFP_Vol1_V15.5/Annexure

    III/Pg: 104

    Daily Server Load Estimate: Based on the

    above observations, it is envisaged that a

    bandwidth requirement of approximately

    8.325 MBPS.

    IA assumes that Bandwidth requirement expected is

    8.325 Mbps. Please confirm.

    Yes

    117 IRDA_RFP_Vol1_V15.5./Section

    4/Pg: 22/Point IV

    It should be noted that IRDA will not

    make any investment for hardware and

    network equipments and related

    platform/ system software. IA should be

    able to offer managed services for the

    above. This infrastructure has to be

    dedicated for the proposed solution of

    IRDA.

    Hosting partner would like to offer its shared backup &

    SAN storage services. These are pay per use in model and

    offers cost benefits to the customers. Please confirm if

    Shared Backup and SAN can be deployed at the DC & DR.

    The infrastructure has to be

    dedicated for the proposed solution

    of IRDA as mentioned in the RFP.

    118 IRDA_RFP_Vol1_V15.5 DC & DR Location IRDA is requested to provide if they have any preference

    in location of DC & DR.

    There are no location preferences in

    the DC and DR selection leaving the

    condition that the DC and DR

    shouldn't be in the same seismic

    zone.

    119 IRDA_RFP_Vol1_V15.5 Anti Virus Licensing Does IRDA have an enterprise wide anti-virus license? Yes. IRDA is having an enterprise

    wide anti-virus license.

    25 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    120 IRDA_RFP_Vol1_V15.5/Section

    3.1/Pg: 12

    Proposed Business Analytics Solution As per the new architecture, will all end users access the

    platform over Internet or any Private VPN solution needs

    to be deployed.

    If Private VPN solution has to be deployed, can IRDA

    specify the requirement, locations, addresses,

    bandwidths required?

    All the functionalities mentioned in

    the functional specifications

    mentioned in the functional

    requirements specifications

    document should be accessible by

    VPN for IRDA internal users

    irrespective of any locations.

    121 IA assumes that the strategy should be holistic in

    addressing both Technical Metadata and functional /

    business Meta data. Please confirm.

    Yes

    122 Please indicate if the business metadata is currently

    maintained in any format?

    At present no business metadata is

    maintained in structure formats in

    IRDA.

    123 What is the frequency at which BI metadata undergoes

    significant changes with respect to metadata?

    As per Industry benchmark.

    Selected IA should assess the same.

    124 What is the frequency at which ETL metadata undergoes

    significant changes with respect to metadata?

    As per Industry benchmark.

    Selected IA should assess the same.

    125 What is the frequency at which Source System metadata

    undergoes significant changes with respect to metadata?

    Not very frequently as all the data

    captured are used for regulatory

    purpose. Highest frequency may be

    daily but in rare cases.

    126 What are the metadata elements you would like to

    capture and manage in the metadata management tool?

    (for e.g.: Business Metadata, Technical Metadata about

    the Data warehouse / Data Marts, Technical Metadata

    from BI / ETL / Source DB’s repository, etc)

    Business Metadata

    Technical Metadata from DW/Data

    marts

    Technical Metadata of the source

    systems.

    127 What are the categories of users for Metadata

    management tool? Is it going to be only Report

    Administrators (or) Business Analysts, Data Architects,

    Developers, etc

    Report administrators for reporting

    metadata, data administrators for

    technical metadata

    IRDA_RFP_Vol1_V15.5/ Section

    8.1/Pg: 39

    Metadata Management

    26 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    128 Please indicate the type of reports that will have to be

    generated from the metadata tool. (For e.g.: Ad hoc

    query and analysis, dashboards, scheduled reporting, etc)

    Please refer to section 2.0 of the

    functional requirements

    specifications for the details

    129 IRDA_RFP_Vol3__v23.5/Section

    1.3/Pg: 5

    The aforementioned SLA parameters shall

    be measured on a daily/weekly/monthly/

    quarterly basis as per the individual SLA

    parameter requirements, through

    appropriate SLA Measurement tools to be

    designed by the IA for the purpose and

    audited by a 3rd party audit agency for

    accuracy, reliability and completeness.

    Can you please let us know whether the cost of

    conducting the 3rd party audit like CAG, Security Audit

    etc will be borne by IRDA?

    3rd party on testing, performance

    and security will be borne by IRDA.

    130 IRDA_RFP_Vol3__v23.5/Section

    2.2.2/Pg: 13

    Period Of Contract: IRDA may choose to

    extend the term for a further period of

    one year, with all the terms and

    conditions being the same as for the

    original term

    If the contract gets extended by 1 year then IA assumes

    that the value of that contract will be paid separately,

    Can you please clarify?

    Value for the extended year shall be

    paid separately with all the terms

    and conditions being the same as for

    the original term

    131 IRDA_RFP_Vol3__v23.5/Section

    2.2.6/Pg: 14

    The Parties will cooperate reasonably to

    obtain, maintain and observe all relevant

    and customary regulatory and

    governmental licenses, clearances and

    applicable approvals (hereinafter the

    “Approvals”) necessary for the

    Implementation Agency to provide the

    Services. The costs of such Approvals shall

    be borne by the Implementation Agency

    Can you please give more information on this

    requirement?

    This not mandatory. Only relevant if

    applicable.

    132 Is High Availability required on the Firewalls? Please

    confirm.

    Yes.

    133 Do you require IDPS? If yes please specify is that a

    separate dedicated IPS box or IPS built within the

    Firewall?

    Firewall requirement has been

    specified in RFP.

    IRDA_RFP_Vol1_V15.5/ Section

    8.1/Pg: 39

    Metadata Management

    IRDA_RFP_Vol3__v23.5/IRDA_RFP_V

    ol1_V15.5

    Firewall Security

    27 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    134 Please confirm the type of Gateway Multi-Threat

    protection required along with Firewall/VPN (i.e.

    Gateway Antivirus, Web URL Filtering, and Anti-Spam)

    Firewall requirement has been

    specified in RFP.

    135 Please specify the number of physical interfaces required

    on the firewall & use / requirement for each interface

    (including internet / WAN links & physical DMZs for LAN

    connectivity)

    The detailed specifications will be

    provided to the IA after final

    selection.

    136 Please provide the number of Internal LAN Users with

    concurrent traffic statistics, if any. Please mention along

    with future growth perspective.

    User related information has been

    provided in the RFP.

    137 Please provide the throughput required on the LAN

    segments of the firewall e.g. 10/100/1000 Mbps

    The IA needs to assess this as per

    SLA specified.

    138 Please provide the total number of Internet users for this

    application with concurrent numbers if any.

    User related information has been

    provided in the RFP.

    139 Please provide the concurrent VPN connections expected

    over the Public Internet (Site-to-Site IPSec VPN with

    other office location, Client-to-Site IPSec/SSL VPN for

    employee access to Corporate Network from Internet).

    The IA needs to assess this as per

    SLA specified.

    140 Please provide more information on the following:

    Future expansion (Number of Users, Number of ISP/WAN

    links, Bandwidth increase of ISP/WAN links, increase in

    VPN tunnels, introducing any real time Application like

    Voice/Video in the network etc

    The IA needs to assess this during

    the implementation.

    141 IRDA_RFP_Vol3__v23.5/IRDA_RFP_V

    ol1_V15.5

    Backup Do the servers require file level backup too apart from

    the regular OS backup that we support by default?

    Yes.

    IRDA_RFP_Vol3__v23.5/IRDA_RFP_V

    ol1_V15.5

    Firewall Security

    28 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    142 IRDA_RFP_Vol3__v23.5/IRDA_RFP_V

    ol1_V15.5

    DC – DR Replication IA understands that DC has to be provided with a fail

    over strategy. Please confirm if DR needs a fail over

    strategy as well.

    Since zero data loss is expected, it is

    expected from the bidder to provide

    all kinds of suggestions and technical

    options to prevent any data loss.

    143 BAP_Requirements

    Specifications_v25/ Pg: 18/

    Technical specifications What is the security data stored used currently? Does

    IRDA plan to reuse the same store for the BAS

    application?

    The BAP solution will preferably have

    to be integrated with the default

    authentication provider in IRDA. The

    user log in credentials will be reused

    in such a case. The access for the

    different modules, functionalities,

    data will have to be defined

    separately.

    144 BAP_Requirements

    Specifications_v25/ Section

    1.1.4,1.1.5/ Pg: 27

    Capability of reconciling the data across

    departments. So any data which is

    captured in one department as well as in

    others, the figures should match with

    each other, Capability of automatically

    reconciling the data from one form with

    different forms.

    Should these checks happen at the time user is entering

    the data (online) and show him appropriate messages or

    Should it happen as an offline process which generates

    reports (either on screen or mail) for internal IRDA users?

    These reconciliation checks should

    happen at both the data submission

    and the reporting end.

    145 BAP_Requirements

    Specifications_v25/ Section 1.1.9/Pg:

    27

    It should be possible to define rules for

    populating the content dynamically on

    the web portal based on the usage,

    contact type, online behavior, alerts (e.g.

    pending document from insurer), etc

    Could you please provide more clarity on these

    requirements with additional examples (like a specific

    online behavior and how it impacts the contents on the

    screen)?IA assumes that these rules would be

    maintained by the technical team not directly by the

    business users.

    For example, the system should auto

    calculate the calculated the fields in

    an online form or if any data to be

    submitted by the entities is pending

    for submission, in such as case, the

    system should throw alerts

    reminding the pending submission.

    29 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    146 BAP_Requirements

    Specifications_v25/ Section 1.2.2/Pg:

    30

    On successful completion of online

    submission / fling the system should send

    certificates to the filing entity as an

    acknowledgement of the completion of

    the process

    IA assumes that this will be done through email or online

    receipt and not a printed certificate generated through a

    batch process and sent through conventional mail. Please

    confirm.

    Yes

    147 Do any of IRDA's current applications maintain the

    ratings of RI’s? Else, how does IRDA expect get this

    information?

    At present, this data is maintained is

    offline in spreadsheets. These data

    can be maintained in the system by

    loading external files (such as CSVs,

    TXTs) at a monthly internal.

    148 Does IRDA propose to restrict the number of user ids per

    insurer / intermediary organization?

    Yes.

    149 BAP_Requirements

    Specifications_v25/ Section 1.3.2/Pg:

    32

    Automatic verification and validation of

    data submitted by insurers for

    consistency checking. If relevant product

    documents are not uploaded, other

    errors and omissions by insurer (with

    product application) then the system

    should generate an alert to IRDA about

    the discrepancy.

    IA assumes that the documents uploaded by the insurer

    would be in standard templates issued by IRDA and

    hence automated validations on these are possible.

    Please confirm.

    Yes

    150 BAP_Requirements

    Specifications_v25/ Section

    1.4.4.1.2/Pg: 35

    Should be configurable to enable

    automated payments to the respective

    departments based on a pre-defined

    schedule

    Please explain what is meant by “pre-defined schedule”

    and what parameters are expected to be configurable?

    Pre Defined Schedule here refer to

    the time period when a payment has

    to flow from the external entities to

    IRDA. For example, renewal of

    surveyor licenses.

    151 BAP_Requirements

    Specifications_v25/ Section

    1.4.4.1.3/Pg: 35

    Should have the ability to process and

    display status updates in the entire

    payment and collection process

    Who are the intended audience for this report and what

    information will it contain?

    IRDA administration will be the users

    of this report. The objective of this

    report is to track and monitor the

    defaults in payment by the external

    entities.

    BAP_Requirements

    Specifications_v25/ Section 1.2.8/Pg:

    30

    Ability to cross-verify whether Insurers

    are placing risk with an RI with at least

    BBB rating.

    30 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    152 BAP_Requirements

    Specifications_v25/ Section

    1.4.4.1.3/Pg: 35

    Should have the ability to process and

    display status updates in the entire

    payment and collection process

    By ‘Collection process” please confirm if the reference is

    to tracking the credit of payments done online only and

    not tracking of any manual payments received through

    check or other offline means.

    Deals with online payments only.

    153 BAP_Requirements

    Specifications_v25/ Section 1.5/Pg:

    36

    Inspections Planning and Management –

    Detailed Workflow

    IA assumes that this application would be used by the

    Inspection department only – insurers and non-IRDA

    personnel will not have access / roles in this system.

    Please confirm.

    Yes

    154 BAP_Requirements

    Specifications_v25/ Section

    Business Process Reengineering –

    Key objectives/Pg: 70

    To automate the data transfer from

    Insurers, Intermediaries and TPAs

    Can IA assume that based on this objective, that ALL data

    being fed into the BAP system will be automated? That

    is, we will have digitization of paper records at the time

    of implementation only as a onetime activity? Please

    confirm.

    The automation of data transfer from

    the external entities system is a

    future state of requirement.

    However, the digitization activity is a

    one time activity.

    155 The major components of the BPR

    exercise are:

    156 1. Reengineering the forms (includes

    modifying the existing forms and creating

    new forms)

    157 2. Reengineering the reports (includes

    modifying the existing reports and

    creating new reports)

    158 3. Reengineering the processes of data

    capture, storage and reporting

    159 Among the three components, the first

    two has been done during the detailed

    TO BE exercise.

    160 BAP_Requirements

    Specifications_v25/ Section 3.9/Pg:

    44

    The system should monitor claim

    Settlement in terms of Turnaround Time

    (TAT) (Monthly) for each insurer so that

    IRDA can take action on the claims

    unsettled for long time.

    IA understands that insurance companies provide

    summary level data to IRDA. Would Insurance company

    share policy holder level details as well?

    Policyholders wise data needn't be

    captured in Business Analytics

    Solution. Hence not relevant.

    BAP_Requirements

    Specifications_v25/ Section

    Business Process Reengineering –

    Major components/ Pg: 70

    Can IA assume that this is by far the final set of forms and

    reports that need to be developed as part of this project

    or does IA expect significant number of additional forms

    and reports at the time of requirements detailing?

    So far these are the final sets of

    reports and forms. However, since

    forms are subject to regulation also

    are the reports, a few new forms may

    be added or some changes may be

    performed on these forms at a later

    point in time during the

    implementation.

    31 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    161 BAP_Requirements

    Specifications_v25/ Section 5.10/Pg:

    48

    Provision for digital signatures so that the

    data security is maintained properly and

    the insurers can only view the data but

    will not be able to edit it.

    Has IRDA digital signature already? Or IA has to procure

    the same for IRDA?

    IA has to procure digital signature for

    IRDA.IRDA as of now is not having

    digital signature technology.

    162 BAP_Requirements

    Specifications_v25/ Section 6.1/Pg:

    49

    All relevant documents need to be

    uploaded and digitally signed by insurer

    before upload.

    'IA assumes that it is the responsibility of insurers to

    ensure that all relevant digital documents are digitally

    signed before uploading'. Please confirm

    Yes

    163 BAP_Requirements

    Specifications_v25/ Section 7.2/Pg:

    49

    The system should also have a search

    facility that should enable searching of

    contents over the internet through a

    standard search engine like Google

    search.

    Is it mandatory that IA use ‘Google search engine’ or can

    IA use other industry standard engine like ‘Bing’ or

    ‘Yahoo search’?

    There is no mandatory requirements

    of searching facility through any

    particular search engine. "Google"

    has been mentioned as an example.

    The objective is to have searching

    facility through the most robust

    search engine possible.

    164 BAP_Requirements_Specifications_v

    25/Section 1.1.2.4/Pg: 56

    Tokens (RSA SecurID, SafeWord, etc.) Does IRDA expect RSA Secure token support for VPN

    connections for employees or for even form based

    authentication by end users as well?

    Bidders needs to recommend as per

    the security requirements specified

    165 BAP_Requirements_Specifications_v

    25/Section 2.6.1/Pg: 62

    The system should have flexibility to

    regenerate the programs and features

    without starting the development process

    from very beginning. The system should

    have an user interface to support the

    same so that the entire development

    activity can be replicated to a new set up

    without much of problems

    Can you please provide more information on this

    requirement?

    By this it is meant that the

    application should have in built back

    up and replication mechanism

    through which the status of the

    system can be restored at any point

    in time without replicating the

    development efforts from the scratch

    32 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    166 BAP_Requirements

    Specifications_v25/Section 2.1.9/Pg:

    40

    Producing different reports in different

    formats as per the requirements

    displaying the characteristics of two or

    more products in a comparative tabular

    form so that if there is any duplication or

    almost duplication of products, IRDA can

    take suitable action against such

    products.

    What could be the maximum number of Products to be

    compared at a time?

    Number will change over time. The

    max limit need to be finalized during

    preparation of SRS.

    167 What are the various formats of the financial statements

    (Excel, PDF etc)?

    PDFs and MS word

    168 How many financial statements to be considered for

    generating financial reports?

    Detailed list of forms and reports

    have been provided in the FRS

    document alongwith a fair sample of

    the complete set of forms and

    reports have been shared with the

    bidders.

    169 Is there any calculation logic to be applied over the

    uploaded data or data to be put together for

    consolidated view?

    Same as above.

    170 BAP_Requirements

    Specifications_v25/Section

    2.1.11/Pg: 40

    The system should show summarized

    reports consolidating / integrating data

    from different departments.

    Is there any data granularity difference in data across

    departments?

    The data collected by the different

    departments can be of different

    granularity. For this purpose, the

    detailed set of reports will be

    provided to the selected IA only after

    finalization of IA.

    171 Is there any Ad-hoc reporting facility required over web? Yes.

    172 How many concurrent users expected over web? Please refer to annexure III of the

    volume I of the RFP document for

    detailed specifications of the user

    173 Is generated Ad-hoc report to be saved in server for

    feature access?

    Yes.

    BAP_Requirements

    Specifications_v25/Section

    2.1.10/Pg: 40

    Generating financial reports out of the

    different kinds of financial statements

    uploaded by the external stakeholders

    BAP_Requirements

    Specifications_v25/Section

    2.1.11/Pg: 40

    The system should support reporting

    over both thin client and rich client i.e.

    over web interface and client desktop

    interface

    33 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    174 Are reports scheduled to run at periodic intervals? Yes.

    175 What is the least granularity of data to be expected in

    the reports hierarchy?

    For this purpose, the detailed set of

    reports will be provided to the

    selected IA only after finalization of

    IA.

    176 How many level of Drill through reports required from

    main reports (for e.g.: 2, 3 etc)?

    For this purpose, the detailed set of

    reports will be provided to the

    selected IA only after finalization of

    IA.

    177 Is there any dynamic hierarchy required in drill-down? Same as above.

    178 IA assumes that the security considerations for IRDA

    reports will be Role based. Please confirm.

    As of now, role based access is

    proposed, however this may be

    subject to change.

    179 BAP_Requirements

    Specifications_v25/ Pg: 40

    Section 2.3, General Analytics Section 2.3 refers to the system having the capability to

    perform mentioned analysis. Does IA have to perform

    the statistical analysis or build statistical models for IRDA

    as a part of this requirement? Please confirm.

    The solution must have capabilities

    so that the business users can define

    their own statistical models based on

    the requirements. IA won't need to

    perform statistical analysis. In some

    cases for canned reports, the IA may

    be required to build statistical models

    proposed by the business users.

    180 BAP_Requirements

    Specifications_v25/ Section 2.6/Pg:

    42

    Advanced Analytics: The system should

    have early warning management

    flexibility, i.e. system should be able to

    perform analyses on some leading

    indicators (KPIs) and should show

    indications of a particular KPI to be going

    down and the reasons for it.

    Will IA be required to build the statistical model to

    analyze leading KPIs and trigger early warnings for KPIs to

    be going down? Please confirm. If yes, is an indicative

    number of KPIs to be tracked and analyzed, available?

    The solution must have capabilities

    so that the business users can define

    their own statistical models based on

    the requirements. IA won't need to

    perform statistical analysis. In some

    cases for canned reports, the IA may

    be required to build statistical models

    proposed by the business users.

    BAP_Requirements

    Specifications_v25/Section

    2.1.11/Pg: 40

    The system should support reporting

    over both thin client and rich client i.e.

    over web interface and client desktop

    interface

    34 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    181 BAP_Requirements

    Specifications_v25/ Pg: 53

    Other Requirements: The system should

    have a suitable ALM module which will

    have cash flow management

    functionalities and other financial

    analytics capabilities.

    Please elaborate on the requirements for ALM module. There are predefined formats for the

    ALM module. For this purpose, the

    detailed set of reports will be

    provided to the selected IA only after

    finalization of IA.

    182 BAP_Requirements

    Specifications_v25/ Pg: 78/Point 18

    183 BAP_Requirements

    Specifications_v25/ Pg: 141/Point

    17

    184 BAP_Requirements

    Specifications_v25/ Pg: 150/Point 1

    185 1.please provide example of Breach as defined; Self Explanatory

    186 2.Pleasee confirm if Project definition can be modified as- The definition of the terms shall

    remain as it is mentioned in the

    volume III of the RFP document.

    187 “Project” means BAP Project involving the Design,

    Development, Implementation, Operations, and

    Maintenance of BAP system as per the requirements,

    terms and conditions laid down in the Statement of Work

    (SOW) and provision of related services in conformance

    to the SLA;

    The definition of the terms shall

    remain as it is mentioned in the

    volume III of the RFP document.

    188 3. Please confirm if Deliverables definition can be

    modified as–

    The definition of the terms shall

    remain as it is mentioned in the

    volume III of the RFP document.

    189 “Deliverables mean deliverables under this Agreement as

    specifically set forth under the statement of work (SOW)

    that Bidder is agreed to furnish and is obligated to

    provide to IRDA”

    The definition of the terms shall

    remain as it is mentioned in the

    volume III of the RFP document.

    Appendix I Is there a requirement for a Solution to execute

    Insurance specific Risk calculations such as - Solvency

    Ratio, IBNR Reserve Estimation (Chain Ladder,

    Bornhuetter-Ferguson etc,.) using various

    methodologies?

    Yes. There are predefined formats for

    these reports. The formats and

    calculation logic will be provided to

    IA after finalization of IA.

    IRDA_RFP_Vol3_ v23.5/Section

    2.1.1/Pg: 7

    Definitions

    35 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    190 IRDA_RFP_Vol3_ v23.5/Section

    2.2.4/Pg: 13

    Scope and Provision of the Services Please clarify who are the stakeholders referred in

    clause2.2.4 (a) here and such reference can be deleted.

    Refer to the volume I of the RFP

    document for details on the

    stakeholders

    191 IRDA_RFP_Vol3_ v23.5/Section

    2.2.6/Pg: 14

    Approvals and required consents Any cost increase due to change in applicable laws and

    related approvals need to be borne by IRDA.

    The costs of such Approvals shall be

    borne by the Implementation Agency

    as per clause 2.2.6 in the page 14 on

    the volume III of the RFP document.

    192 Safety and security of assets purchased by Bidder for

    IRDA shall rests with IRDA when such assets are on IRDA

    premises.

    The terms specified in the clause

    2.2.6 in the volume III of the RFP

    would remain the same.

    193 Will IRDA bear the cost of insurance policies required to

    be taken out?

    The terms specified in the clause

    2.2.6 on insurance in the volume III of

    the RFP would remain the same.

    194 Are insurance provisions subject to negotiations? The terms specified in the clause

    2.2.6 on insurance in the volume III of

    the RFP would remain the same.

    195

    196

    197

    198 IRDA_RFP_Vol3_ v23.5/Section

    2.3.4/Pg: 18

    Security and Safety Will IRDA provide safety and security policies to Bidder in

    advance and in writing for its confirmation and review?

    RFP provides relevant details.

    IRDA_RFP_Vol3_ v23.5/Section

    2.2.6/Pg: 15

    Use and Acquisition of Assets

    IRDA_RFP_Vol3_ v23.5/Section

    2.3.3/Pg: 18

    Changes Please confirm if it is acceptable that – Bidder can

    propose provisions to be added to allow each party to

    propose changes to the applicable work order/statement

    of work shall be added. Also, that neither party should

    have any obligation respecting any change until an

    appropriate change order or amendment to the

    applicable work schedule/ statement of work is executed

    by both parties.

    Provisions to be added to allow the

    IA to propose changes to the

    applicable work order/statement of

    work is NOT ACCEPTABLE

    36 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    199 IRDA_RFP_Vol3_ v23.5/Section

    2.4/Pg: 19

    Financial Issues Bidder believes that Financial terms are subject to

    negotiations between the parties. Please confirm.

    Article IV on Financial Issues in the

    volume III of the RFP document shall

    remain as it is.

    200 IRDA_RFP_Vol3_ v23.5/Section

    2.4.3/Pg: 21

    Tax Please confirm if it is acceptable that – IRDA shall be

    responsible for payment of any sales, service, value-

    added, use, excise, consumption, or other taxes assessed

    with respect to Bidder’s provision of the Services. Tax

    provisions are subject to negotiations.

    Section 2.3 on the Tax in the Article

    IV on Financial Issues in the volume

    III of the RFP document shall remain

    as it is.

    201 Please confirm –

    202 whether the length of the cure period in Section 2.5.1

    can be increased?

    If there is Breach which translates

    into default in providing Services by

    the Implementation agency as per

    this Agreement or the SLA,

    continuously for more than one

    week, then the Project Director,

    IRDA, will serve a FIFTEEN days notice

    for curing such Breach.

    203 Bidder proposes that both parties should be able, with an

    appropriate notice period, to terminate only for a

    material breach of respective parties’ obligations under

    the Agreement. In addition, Bidder feels that, regardless

    of the reason for termination, Bidder should be paid for

    all services rendered through the effective date of

    termination at mutually agreed rates and, in the case of

    termination of the Agreement by IRDA without cause or

    by Bidder for cause for all costs reasonably incurred in

    anticipation of the performance of services to the extent

    that they cannot reasonably be eliminated.

    No. It should retain as mentioned in

    the section 2.5 of the volume III of

    the RFP document.

    204 Please provide clarifications if clause 2.5.5 can be

    removed? Or any modifications be suggested to the

    wordings?

    No. It should retain as mentioned.

    IRDA_RFP_Vol3_ v23.5/Section

    2.5/Pg: 22

    Breach, Rectification and Termination

    37 of 76

  • S.No. Reference to the original document Context Queries/Amendments (Details) Comments

    205 Will following modifications be accepted by IRDA:

    206 Certain of the warranties (including Section 2.6.1 (a) and

    (b)) should be subject to a mutually agreeable time

    period. Also, reference to 3.2.4 of Article II seems

    incorrect. In addition, Bidder would request the inclusion

    of certain industry standard requirements for warranty

    claims (e.g., notice before expiration of warranty period,

    confirmation of defects, absence of alterations or

    modifications by parties other than Bidder). Bidder

    would like to suggest modifications that Bidder believes

    would make certain of the provisions more consistent

    with industry standards. Additionally, guarantee under