smoking machine for emissions and lung cast deposition evaluation

39
SMOKING MACHINE FOR EMISSIONS AND LUNG CAST DEPOSITION EVALUATION Christopher Boise Eric Cawley Gideon Oladunjoye Jose Paredes Matthew Cross Megan Guarnieri-Cleary 12-10-13 Team 14054 1

Upload: keefe

Post on 24-Feb-2016

31 views

Category:

Documents


0 download

DESCRIPTION

Smoking Machine for emissions and lung cast deposition evaluation. Christopher Boise Eric Cawley Gideon Oladunjoye Jose Paredes Matthew Cross Megan Guarnieri-Cleary. Concept Generation Concept Screening Critical Design Challenges Risk Management Flow Diagram Block Diagram - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Smoking Machine  for emissions and lung cast deposition evaluation

SMOKING MACHINE FOR EMISSIONS AND LUNG CAST

DEPOSITION EVALUATION

Christopher BoiseEric Cawley

Gideon OladunjoyeJose Paredes

Matthew CrossMegan Guarnieri-Cleary

12-10-13 Team 14054 1

Page 2: Smoking Machine  for emissions and lung cast deposition evaluation

AGENDA Week 3 Opportunities Schedule Problem Statement Customer Requirements Engineering Requirements Relationship Matrix Functional Decomposition

Concept Generation Concept Screening Critical Design Challenges Risk Management Flow Diagram Block Diagram Future Action Work Breakdown

12-10-13 Team 14054 2

Page 3: Smoking Machine  for emissions and lung cast deposition evaluation

WEEK 3 OPPORTUNITIES

Improve project schedule with added in deliverables

Goal- receive an approved system level design by week 6 review

12-10-13 Team 14054 3

Page 4: Smoking Machine  for emissions and lung cast deposition evaluation

SCHEDULEPART 1

12-10-13 Team 14054 4

Page 5: Smoking Machine  for emissions and lung cast deposition evaluation

SCHEDULEPART 2

12-10-13 Team 14054 5

Page 6: Smoking Machine  for emissions and lung cast deposition evaluation

SCHEDULEPART 3

12-10-13 Team 14054 6

Page 7: Smoking Machine  for emissions and lung cast deposition evaluation

SCHEDULEFUTURE

12-10-13 Team 14054 7

Page 8: Smoking Machine  for emissions and lung cast deposition evaluation

PROBLEM STATEMENT

In order to simultaneously collect emissions and transport undisturbed casts for analysis, current hollow cast models will be combined with the existing side stream smoking machine. Device will operate using acquired data from the wPSMD. Unit needs to be self-contained, portable, fit on a workbench, and user friendly. The unit must also be production ready for identical machines in other labs. During operation smoke needs to be ventilated responsibly and the unit must be interfaced with LabVIEW.

12-10-13 Team 14054 8

Page 9: Smoking Machine  for emissions and lung cast deposition evaluation

PROBLEM STATEMENT(BULLET FORM)

Smoke single Cigarette Smoke travels through

main-stream lung casting while the side-steam machine captures the remaining smoke

Smoke that travels through the lung casting will be recirculated through the side-stream machine (2nd hand smoke)

Unit will fit on a portable cart Samples will be taken to the

NTID lab for analysis 12-10-13 Team 14054 9

Page 10: Smoking Machine  for emissions and lung cast deposition evaluation

CUSTOMER REQUIREMENTS

Revision #: 1

Date CreatedCustomer Rqmt. # Importance Description Comments/Status

Aug. 28, 2013CR1 9

Puff cigarettes at different progammable flow rates Data will be obtained from wPSMD

CR2 9Collect mainstream emissions

and transport them to NTID chemical lab

Collected simultanesously with CR3

CR3 9Collect sidestream emissions and transport them to NTID chemical

labCollected simultanesously with CR2

CR4 9 Incorperate hollow lung cast into mainstream emissions test

Dr. Robinson is in charge of the cast after the test.

CR5 9 Must be self-contained and portable

Must fit on a workbench

CR6 3 Must be user friendly

CR7 1 Must be able to be assembled in other labs

Not for mass production.

CR8 3 Smoke must be ventilated to an outside enviornment

Improve upon current system

Sept. 24, 2013CR9 9 Direct exaust from main stream

through side stream machineCR10 3 Humidify main stream smoke Be aware of ISO standardCR11 1 Design to ISO/Coresta standards If production is hindered, ignore standards

12-10-13 Team 14054 10

Page 11: Smoking Machine  for emissions and lung cast deposition evaluation

ENGINEERING REQUIREMENTS

Project: Smoking machine for emissions and lung cast deposition evaluation P14054Revision #: 2

Date Created rqmt. # Importance Source Function Engr. Requirement (metric) Unit of Measure

Marginal Value Ideal Value

Aug. 28, 2013 S1 9 CR1 Generate puffing profile from the data obtained from wPSMD % 5% <5%S2 9 CR1 Reproduction of generated puff profile % 5% <5%S3 3 CR5 Fit on a workbench and be portable m2 1.5 <1S4 9 CR6 Create a user-friendly manual for machine operation(Mainstream, Sidestream and Casting)- - -S5 9 CR6 Make a user-friendly LabView interface - - -S6 9 CR2,CR3 Collect mainstream and sidestream emissions simultaneously - - -S7 9 Deliverables Generate Labeled and documented flow diagrams of Pressures Pascals - -S8 9 Deliverables Generate Labeled and documented flow diagrams of Flow Rates ml/s - -S9 9 Deliverables Generate labeled and documented wiring diagram V - -S10 9 Deliverables Label system according to respective diagrams - - -S11 1 Deliverables Generate parts list with BOM per vendor specifications - - -S12 3 Deliverables Incorporate adaptor to smoke electronic cigarettes - - -S13 3 Deliverables Improve ventilation system from prior projects. - - -

Sept. 24, 2013 S14 3 CR6, CR11 Consistant polypro tubing size/connector size mm 9.5 (3/8 in)S15 3 CR9 Vent main stream exaust to side stream system - - -

Sept. 30, 2013 S16 3 CR11 Cigarette holder needs to be level deg +5 deg 0 degS17 1 CR11 Ash tray below cigarette mm 20-60 40S18 3 CR11 Pressure drop of complete flow path for 17.5 mL/sec Pascals 300 0S19 3 CR11 Dead volume mL 100 0S20 3 CR11 Filter system pressure drop across all filters Pascals 250 0S21 9 CR11 Puff termination device - - -S22 3 CR11 Temerature and Relative humidity measurement - - -S23 3 CR11 Flameless first-try ignition - - -S24 3 CR11 Fishtail chimney testing height above ash tray mm - 6S25 3 CR11 Side stream smoke flow rate L/min +/- 0.1 3

12-10-13 Team 14054 11

Page 12: Smoking Machine  for emissions and lung cast deposition evaluation

RELATIONSHIP DIAGRAM

Need Priority Gene

rate

puffi

ng p

rofil

e fr

om th

e da

ta

obta

ined

from

wPS

MD

Repr

oduc

tion

of g

ener

ated

puff

pro

file

Fit o

n a

wor

kben

ch a

nd b

e po

rtab

le

Crea

te a

use

r-fr

iend

ly m

anua

l for

m

achi

ne o

pera

tion(

Mai

nstr

eam

, Si

dest

ream

and

Cas

ting)

Mak

e a

user

-frie

ndly

Lab

View

in

terf

ace

Colle

ct m

ains

trea

m a

nd si

dest

ream

em

issio

ns si

mul

tane

ously

Gene

rate

Lab

eled

and

doc

umen

ted

flow

dia

gram

s of P

ress

ures

Gene

rate

Lab

eled

and

doc

umen

ted

flow

dia

gram

s of F

low

Rat

es

Gene

rate

labe

led

and

docu

men

ted

wiri

ng d

iagr

am

Labe

l sys

tem

acc

ordi

ng to

resp

ectiv

e di

agra

ms

Puff cigarettes at different progammable 9 x xCollect mainstream emissions and transport them to NTID chemical lab 9 x xCollect sidestream emissions and transport them to NTID chemical lab 9 x xIncorperate hollow lung cast into mainstream emissions test 9 x xMust be self-contained and portable 9 xMust be user friendly 3 x x x x x xMust be able to be assembled in other labs 1 x x x x xSmoke must be ventilated to an outside 3Direct exaust from main stream through side stream machine 9Humidify main stream smoke 3 xDesign to ISO/Coresta standards 1

Rev. 2 Measure % % m2 - - - Pascals ml/s V -12-10-13 Team 14054 12

Page 13: Smoking Machine  for emissions and lung cast deposition evaluation

RELATIONSHIP DIAGRAM

12-10-13 Team 14054 13

Page 14: Smoking Machine  for emissions and lung cast deposition evaluation

FUNCTIONAL DECOMPOSITION

12-10-13 Team 14054 14

Page 15: Smoking Machine  for emissions and lung cast deposition evaluation

FUNCTIONAL DECOMPOSITION (1)

12-10-13 Team 14054 15

Page 16: Smoking Machine  for emissions and lung cast deposition evaluation

FUNCTIONAL DECOMPOSITION (2)

12-10-13 Team 14054 16

Page 17: Smoking Machine  for emissions and lung cast deposition evaluation

FUNCTIONAL DECOMPOSITION (3)

12-10-13 Team 14054 17

Page 18: Smoking Machine  for emissions and lung cast deposition evaluation

FUNCTIONAL DECOMPOSITION (3)

12-10-13 Team 14054 18

Page 19: Smoking Machine  for emissions and lung cast deposition evaluation

CONCEPT GENERATIONCategories Solutions

Inhale Smoke Syringe pump

Centrifugal Pump

Human Squeeze pump

Human Lung

Fire Starter

Compressed Air

hold Lung Velcro

Finger Clamp

Rod & sleeve

Glue

Tie Wraps

Bottom hanging support

Hold Cig I.S.O standard piece

Finger Clamps

Sleeves

McDonalds Straw

V supports

Lips Casting

Light Cig Laser

Lighter

Electric coil

Flamethrower

Magnifying glass

Flint

Humidifier Spit

Sprinkler system

Steam from boiled water

bubbles

Exhale Reverse pump cycle through

3 Way Valve

Negative Vacuum

Vent Fan

compressed Air

Vacuums

Hand Power

Ventilation System

12-10-13 Team 14054 19

Page 20: Smoking Machine  for emissions and lung cast deposition evaluation

CONCEPT GENERATIONCONTINUED

12-10-13 Team 14054 20

Page 21: Smoking Machine  for emissions and lung cast deposition evaluation

CONCEPT SCREENING

12-10-13 Team 14054 21

Page 22: Smoking Machine  for emissions and lung cast deposition evaluation

CRITICAL DESIGN CHALLENGES

(C.D.C) Pump- Eric Valve- Chris Tubing- Chris Lighting- Gideon Humidifier- Megan

12-10-13 Team 14054 22

Page 23: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C - PUMP Best solution- OEM 570 Syringe Pump

Pros- LabVIEW programmable Appropriate mimic of a lung Simple to use/set up Runs by itself after set up

Cons- Expensive ~$650 Only for Main Stream testing. Need separate

pump for Side stream machine

12-10-13 Team 14054 23

Page 24: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C – PUMP, SIDE STREAM

Best solution- Electric vacuum pump Pros-

Already have High vacuum Oil free

Cons- Expensive (if had to buy) Continuous run, need to limit flow

12-10-13 Team 14054 24

Page 25: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C – PUMP, SMOKING PROFILE

12-10-13 Team 14054 25

Page 26: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C - VALVE Best solution- 2-way check valve

Pros- Inexpensive ~ $5.00 Corrosion resistance ~ polypropylene Easy to clean Low cracking pressure ~ 1 psi Rubber hose connections ~ range of sizes

Cons- No built in flow sensor

12-10-13 Team 14054 26

Page 27: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C - TUBING Best solution- standard size/material tubing

Pros- Professional looking Easy disassembly for maintenance, testing, and cleaning “1 size fits all” Constant flow rate

Cons- Need for reducers or enlargers Replacement of all old tubing

Tube to Pipe AdapterApprox. $2.25 each

Polypropylene Tubing Approx. $.37/footFDA approved

12-10-13 Team 14054 27

Page 28: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C - LIGHTING Best solution- electric cigar lighter

Pros- Remotely activated/autonomously controlled Flexibility No human interaction Safety using fuses or biased impedance Non chemical use

Cons- Lighting Difficulties

12-10-13 Team 14054 28

Page 29: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C - LIGHTING

12-10-13 Team 14054 29

Page 30: Smoking Machine  for emissions and lung cast deposition evaluation

C.D.C - HUMIDIFIER Best solution- Ecoflo

Pros- Easy to control Built in feedback system

Cons- Large Unit Implementation

Previous Unit Pros-

Easy to implement, small footprint Cons-

No feedback, hard to control12-10-13 Team 14054 30

Page 31: Smoking Machine  for emissions and lung cast deposition evaluation

RISK MANAGEMENTID Risk Item Effect Cause Likelih

ood

Severity

Importance

Action to Minimize Risk Owner

  Describe the risk brieflyWhat is the effect on any

or all of the project deliverables if the cause

actually happens?

What are the possible cause(s) of this risk?     L*S

What action(s) will you take (and by when) to prevent, reduce the impact of,

or transfer the risk of this occurring?

Who is responsible for

following through on mitigation?

1 System catching on fire Destruction of unitMisuse of Lighting

method, Pump overheating, electrical

short, cigarette ash1 3 3 Have a fire extinguisher in room, proper

use of lighting method Megan

2 Over bearing of cart Destruction of system, loss of mobility,

Weight exceeds cart tolerance, caster

wheels failure, cart handle failure

1 3 3 Follow cart specified FOS Chris

3 Cart instability Fragile equipment might break, flow performance

Improper distribution of equipment 1 3 3 Measure and proper distribution of

equipment Chris

4 Smoke containment failure Fire alarm goes off, health concerns

Improper sealing, poor ventilation, improper

use of system2 1 2

Use of hand-held smoke detector, proper ventilation, proper sealant,

possible time delay for opening doorEric

5 Fragile equipment failureFaulty data, no data, expensive to replace, injury during removal

Transportation, recklessness, proximity to heat source, pump

vibration2 3 6 Use of Proper Protective Equipment,

insulate fragile equipment Matt

6 Faulty wiringFaulty data, no data, noisy data, equipment failure,

electrical shorts

Improper coating, improper wire gauge,

burn out near heat source, improper

grounding

2 1 2 Double check against schematic Gideon

7 Collision of moving partsDamaged equipment,

pinch hazards, technician injury

Improper programming, faulty sensors, power surge

2 1 2 Manually test system Jose

8 Pump failureNo flow, experimental failure, expensive to

replace

Loss of power, improper filtering, over use, incorrect gauging,

improper set up1 1 1 Proper filtration, proper cleaning,

proper cooling Eric

9 Contamination Faulty data, equipment destruction, lab hazards

Leaks in tubing, faulty seals, backflow,

improper sterilization2 3 6

Insuring proper seal, checking from pressure drop, use of hand-held smoke

detectorMatt

10 Power FailureNo data, uncontrolled cigarette burn, no user

interface

Power grid failure, breaker trip, computer unplugged from wall

3 1 3 Secure power cord Megan12-10-13 Team 14054 31

Page 32: Smoking Machine  for emissions and lung cast deposition evaluation

BASIC FLOW DEPICTION

12-10-13 Team 14054 32

Page 33: Smoking Machine  for emissions and lung cast deposition evaluation

FLOW DIAGRAM

12-10-13 Team 14054 33

Page 34: Smoking Machine  for emissions and lung cast deposition evaluation

BLOCK DIAGRAM

12-10-13 Team 14054 34

Page 35: Smoking Machine  for emissions and lung cast deposition evaluation

INVENTORY RESULTS

Category Part Description Part Number Quantity Supplier Price Per Unit Total Price Lead Time Possible Solutions

Data AcquisitionNI Static and Waveform Analog

Output - 13 bit, 32 Channels (PCI Card)

778701-01 1 National Instruments $1,099.00 $1,099.00 10-15 days Borrow from Systems Lab

Data Acquisition NI Static and Waveform Analog Output - 13 bit, 32 Channels (Cable)

186381-02 2 National Instruments $89.00 $178.00 10-15 days Borrow from Systems Lab

Data AcquisitionNI Static and Waveform Analog

Output - 13 bit, 32 Channels (Connector Block)

776844-01 2 National Instruments $299.00 $598.00 10-15 days Borrow from Systems Lab

Data AcquisitionNI 16-Bit, 250kS/s, 32 Analog Inputs,

48 digital I/O (PCI Card) 779067-01 1 National Instruments $599.00 $599.00 10-15 days Borrow from Systems Lab

Data AcquisitionNI 16-Bit, 250kS/s, 32 Analog Inputs,

48 digital I/O (Cable) 192061-02 2 National Instruments $119.00 $238.00 10-15 days Borrow from Systems Lab

Data AcquisitionNI 16-Bit, 250kS/s, 32 Analog Inputs,

48 digital I/O (Connector Block)

779475-01 2 National Instruments $299.00 $598.00 10-15 days Borrow from Systems Lab

Lung Cast Pressure Sensors 4043A1 4 Kistler $1,530.00 $6,120.00 FOUND in-line pressure transmitter in lab

Lung Cast Remote Signal Conditional 4618A0 4 Kistler $510.00 $2,040.00 ASK KEMPSKI, IS IT NEEDED?

Pump Oil-Free High Vacuum Pump 5.0 CFM Free Air

4299K4 1 McMaster-Carr $642.50 $642.50 Researching alternatives, looking at syringe pumps

Sensors Silicon on Sapphire Pressure Transmitter

PX4200-015GI 1 Omega $295.00 $295.00 IS IT NEEDED?

full list $12,407.50List-NI equipment $9,097.50

Possibly what we need $2,977.5012-10-13 Team 14054 35

Page 36: Smoking Machine  for emissions and lung cast deposition evaluation

FUTURE ACTIONS Component Finalization Create B.O.M. Test Plan

Pressure Flow Mechanical movement

3D Models Assembly Diagrams

12-10-13 Team 14054 36

Page 37: Smoking Machine  for emissions and lung cast deposition evaluation

Work Breakdown Matt and Megan

Flow Path Flow correction

Chris 3D models of

components Finding existing models Creation of new models

Eric LabView research

Gideon Wiring diagram Schematic/block

diagrams Jose

Space constraints Initial system layout

12-10-13 Team 14054 37

Page 38: Smoking Machine  for emissions and lung cast deposition evaluation

SUMMARY Week 3 Opportunities Schedule Problem Statement Customer Requirements Engineering Requirements Relationship Matrix Functional Decomposition

Concept Generation Concept Screening Critical Design Challenges Risk Management Flow Diagram Block Diagram Future Action Work Breakdown

12-10-13 Team 14054 38

Page 39: Smoking Machine  for emissions and lung cast deposition evaluation

QUESTIONS?

http://www.youtube.com/watch?v=VoBGau9623I