smith school presentation rdl

Upload: mncoohio

Post on 01-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Smith School Presentation RDL

    1/103

    Status Report: Save our Smith GroupMarch 11, 2015

  • 8/9/2019 Smith School Presentation RDL

    2/103

  • 8/9/2019 Smith School Presentation RDL

    3/103

  • 8/9/2019 Smith School Presentation RDL

    4/103

    Save our Smith Group

    • All volunteer organization

    • Goal of economically renovating Smith SchoolBest interests of the students

    Best interests to taxpayers

    Best interests of the community

    • Increased public involvement

    • Work in a transparent and cooperative mannerThanks to Josh Predovich, AIA, at SHP

    Thanks to Jon Saxton, Superintendent

    • Initial petition of support had over 1100 signatures

    • Requested 90 days to study alternatives

    • If study results are positive, include Smith in the

    School System’s Master Plan for facilities

  • 8/9/2019 Smith School Presentation RDL

    5/103

    Save our Smith Group

    Technical Assistance Team

    • Franklin Conaway, Coordinator

    • Bob Loversidge, FAIA, Architect, Schooley Caldwell Associates

    • Dwight McCabe, Cost & Scheduling Analyst

    • Rex Hagerling, AIA, Architect, Moody-Nolan

    • David Holtzapple, P.E., Structural Engineer, Korda• Bill Lantz, P.E., Structural Engineer, SMBH

  • 8/9/2019 Smith School Presentation RDL

    6/103

  • 8/9/2019 Smith School Presentation RDL

    7/103

    Key Issues1. Process has been compromised by eliminating Smith in

    advance of thorough community polling and input

    2. OFCC process includes community consensus3. Master planning process is not complete. No confirmation of

    number of buildings, grades per building, student populations

    by grade

    4. Travel distance is perceived to negatively impact school

    operations (3-4 stories vs. 2 stories)

    5. Program flexibility needs to be addressed in existing buildingplan (1:1, 3:1. 25:1, 50:2)

    6. Compare and contrast new vs. like new

    7. Cost. Renovation costs less than new, but the OFCC funding

    formula shifts more cost to the LFI

    • Auditorium impact

    • Gym and locker area impact

    • Etc.

  • 8/9/2019 Smith School Presentation RDL

    8/103

    D E S I G N C O N C E P T S

  • 8/9/2019 Smith School Presentation RDL

    9/103

    2nd Floor

    1st

    Floor

    SHP SCHEME “A”

    New Building on Smith Site

  • 8/9/2019 Smith School Presentation RDL

    10/103

    SHP SCHEME “B”

    Smith with Small Addition

    2nd Floor Partial Basement

    1st

    Floor 3rd Floor

  • 8/9/2019 Smith School Presentation RDL

    11/103

    2nd Floor Partial Basement

    3rd Floor

    SHP SCHEME “C”

    Smith with Large Addition

    1st

    Floor

  • 8/9/2019 Smith School Presentation RDL

    12/103

    2nd Floor Partial Basement

    1st

    Floor 3rd Floor

    SAVE OUR SMITH CONCEPT

    Smith with Small Addition

    O P T I O N S :

    Partial Basement could house MUSIC and A

     – or –

    MUSIC and ART could go to the IA BUILDIN

     – or –CAFETERIA and KITCHEN could go to the IA BU

  • 8/9/2019 Smith School Presentation RDL

    13/103

    FLEXIBLE LEARNING SPACES

  • 8/9/2019 Smith School Presentation RDL

    14/103

    AUDITORIUM COMPLEX

  • 8/9/2019 Smith School Presentation RDL

    15/103

    D E C I S I O N – M A K I N G P R O C E S S

  • 8/9/2019 Smith School Presentation RDL

    16/103

    . :

      PARTICIPANTSo Control / Direction

      LEADERSHIP COMMITTEE

    o Guidance / Oversight  Board of Education

      TASKS / GOALSo Develop FRAMEWORK of the PLANNING PROCESS and WORK SESSIONS

      Define roles and responsibilities of the EDUCATIONAL PLANNING COMMITT  Defining school districts Educational Mission, Vision, Goals, and Objective

    developed by LEADERSHIP COMMITTEE in Phase 1  Development of planning concepts to implement mission, vision, goals, an

      Identify issues to be vetted  Define purpose and goals of the PLANNING PROCESS and WORK SESSION  Develop a schedule for decision making milestones  Clearly define outcomes and work product expectations  Create WORK SESSION group exercises to encourage thinking, participation,   Define roles and responsibilities of ALL other participants  Define objectives, outcomes and deliverables  Develop communication plan

    o  Identify and form an EDUCATIONAL PLANNING COMMITTEE (refer to section 005  EDUCATIONAL PLANNING COMMITTEE participants may include

      Learners 

      Parents 

      Representative Group of Community Members 

      Community Leaders   Community Seniors   Business Leaders 

      Local Government   Clubs / Organizations   Other Stakeholders   OSFC Planner (OSFC-P) 

      OSFC Project Manager (OSFC-PM)   Pre-Bond Design Professional (PBDP)   Design Professional (Agency CM) / Criteria Architect (Design Build) (optio  Educational Planner (EP) 

      Construction Professional (CP) 

      Instructors   Technology Coordinator(s) 

      Board of Education representative 

    o Notify participants - PLANNING COMMITTEE participantso Distribute timeline and planning process framework

      DELIVERABLESo Framework tasks and goals of the PLANNING PROCESS and WORK SESSIONSo Timeline of planning processo Custodian of information and compilation of ALL deliverables for presentation and p

    PROCESSDEVELOPMENT

    LeCo

    Board

  • 8/9/2019 Smith School Presentation RDL

    17/103

  • 8/9/2019 Smith School Presentation RDL

    18/103

    • Appear to be running two processes simultaneously• Too early in process to be doing schematic level planning

    • Know the look and character of the Smith School today

    • Have no representation of the look and character of a new building

    • SHP comments

    “Ahead of programming planning” “Like the concept”

    “ILA neat building. Disappointed they are not considering”

    “Nice community configuration”

    “Don’t need locker rooms for kids. Could use for shared football”

    Auditorium needs rear stage space

  • 8/9/2019 Smith School Presentation RDL

    19/103

    O F C C “ E C O N O M I C S ”

  • 8/9/2019 Smith School Presentation RDL

    20/103

    Process for Budgeting New School

    EstablishGrades to be

    Serviced and

    Project

    Student

    Population

    Calculate

    Building SQFT

    Based on

    OSFC

    Guidelines

    Apply OSFC

    Cost

    Calculator on

    a Gross $/sqft

    Basis

    OSFC Track

    As-built

    Facility Costs

    And EstablishSingular

    Cost/sqft

    Calculate

    Costs not

    Funded by

    OSFC

    T

    Mast

    Bu

  • 8/9/2019 Smith School Presentation RDL

    21/103

    Process for Budgeting Renovation

    EstablishGrades to be

    Serviced and

    Project

    Student

    Population

    Calculate

    Actual

    Building SQFT

    Apply OSFC

    Cost

    Calculator

    on a cost/unit

    basis

    OSFC Track

    As-built

    Element Unit

    Costs

    And Establish

    Singular

    Cost/sqft by

    Element

    Calculate

    Costs not

    Funded byOSFC

    (Which

    include items

    that do not

    align with

    OSFC

    Guidelines

    Tota

    Master

    Budg

    Perform

    Assessment

    of Existing

    Building and

    Establish

    Quantities

  • 8/9/2019 Smith School Presentation RDL

    22/103

    Process for Budgeting New School

    25,000

    45,000

    65,000

    85,000

    105,000

    125,000

    145,000

    165,000

    185,000

    0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00

     - 5.00

     10.00 15.00 20.00

     25.00 30.00 35.00 40.00 45.00 50.00

     55.00 60.00 65.00 70.00 75.00 80.00

     85.00 90.00 95.00

     100.00 105.00 110.00

     115.00 120.00 125.00 130.00 135.00 140.00

     145.00 150.00

    0 50,000 100,000 150,000 200,000 250,000 300,000

       C  o  s   t   /   A  c  r  e

    Acres

       C  o

      s   t   /   S .   F .

    Building Size (S.F.)

    SchoolsEstimated Cost Per Square Foot

    Total Cost/SF

    General TradesCost/SF

    F.P. Cost/SF

    HVAC Cost/SF

    Plumbing Cost/SF

    Electrical Cost/SF

    Sitework Cost per Acre

    Poly. (Total Cost/SF)

    Log. (General TradesCost/SF)

    Log. (F.P. Cost/SF)

    Log. (HVAC Cost/SF)

    Log. (PlumbingCost/SF)

    Log. (ElectricalCost/SF)

    Log. (Sitework Cost per  Acre)

    * Sticks and bricks only, no design or administrative costs

  • 8/9/2019 Smith School Presentation RDL

    23/103

    Process for Budgeting New School

    25,000

    45,000

    65,000

    85,000

    105,000

    125,000

    145,000

    165,000

    185,000

    0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00

     - 5.00

     10.00 15.00 20.00

     25.00 30.00 35.00 40.00 45.00 50.00

     55.00 60.00 65.00 70.00 75.00 80.00

     85.00 90.00 95.00

     100.00 105.00 110.00

     115.00 120.00 125.00 130.00 135.00 140.00

     145.00 150.00

    0 50,000 100,000 150,000 200,000 250,000 300,000

       C  o  s   t   /   A  c  r  e

    Acres

       C  o  s   t   /   S .   F .

    Building Size (S.F.)

    SchoolsEstimated Cost Per Square Foot

    Total Cost/SF

    General TradesCost/SF

    F.P. Cost/SF

    HVAC Cost/SF

    Plumbing Cost/SF

    Electrical Cost/SF

    Sitework Cost per Acre

    Poly. (Total Cost/SF)

    Log. (General TradesCost/SF)

    Log. (F.P. Cost/SF)

    Log. (HVAC Cost/SF)

    Log. (PlumbingCost/SF)

    Log. (ElectricalCost/SF)

    Log. (Sitework Cost per  Acre)

    $140

    $53 per sqft

    Variation

    $87

    * Sticks and bricks only, no design or administrative costs

    $104

    Median

    34%

    Over

    16%

    Over

  • 8/9/2019 Smith School Presentation RDL

    24/103

    Why such variation?

    UNIT COSTS

    Until you know how much of an item you have, you don’t

    know the magnitude of the impact to the budget.

    A large quantity of a low cost per unit item does not have as big

    an impact as a small quantity of a high cost per unit item

  • 8/9/2019 Smith School Presentation RDL

    25/103

    Description System Type Low Price SQFT High Low Total High

    Metal Siding Metal Siding, Vapor Battier,

    3-5/8" Metal Studs , Thermal Batt insulation8.75$ 9.00$ 10.00$ 437,500$ 450,000$ 500,000$

    Split Face Masonry 8" Split Face CMU, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation11.75$ 12.50$ 13.00$ 587,500$ 625,000$ 650,000$

    EIFS Exterior Insualtion Finish System,

    3-5/8" Metal Studs, Thermal Batt Insulation13.00$ 14.00$ 15.00$ 650,000$ 700,000$ 750,000$

    Stucco Exterior Plaster Stucco

    3-5/8" Metal Studs, Thermal Batt Insulation12.50$ 14.00$ 15.20$ 625,000$ 700,000$ 760,000$

    Brick Veneer  Face Brick - Running Bond, Sheathing

    3-5/8" Metal Studs, Thermal Batt Insulation20.00$ 22.00$ 25.00$ 1,000,000$ 1,100,000$ 1,250,000$

    Cast Stone 5" Cast Stone Panels, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation26.00$ 27.50$ 30.00$ 1,300,000$ 1,375,000$ 1,500,000$

    Brick w/CMUback-up Face Brick - Running Bond, Polystyrene Insulation

    6" CMU, 1-1/2" Furring Channels26.50$ 28.00$ 30.00$ 1,325,000$ 1,400,000$ 1,500,000$

    Alucobond  Alucobond Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation31.00$ 32.00$ 37.00$ 1,550,000$ 1,600,000$ 1,850,000$

    Architectural Precast 5" Precast Concrete Panel, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation30.00$ 33.50$ 38.00$ 1,500,000$ 1,675,000$ 1,900,000$

    Metal Panels 2" Insulated Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation

    33.50$ 35.00$ 37.00$ 1,675,000$ 1,750,000$ 1,850,000$

    Storefront 4" Aluminum/Glass Storefront w / metal spandrels

    3-5/8" Metal Studs, Thermal Batt Insulation37.00$ 40.00$ 48.00$ 1,850,000$ 2,000,000$ 2,400,000$

    Thin Stone on Aluminum Backing 1/8" Limestone on A luminumHoneycomb Frame

    3-5/8" Metal Studs, Thermal Batt Insulation39.00$ 41.00$ 50.00$ 1,950,000$ 2,050,000$ 2,500,000$

    Limestone 5" Limestone Panel, Polystyrene Insulation,

    6" CMU, 1-1/2" Furring Channels45.00$ 47.50$ 55.00$ 2,250,000$ 2,375,000$ 2,750,000$

    Granite Panels 4" Granite Panel, Polystyrene Insualtion,

    6" CMU, 1-1/2" Furring Channels55.00$ 57.00$ 65.00$ 2,750,000$ 2,850,000$ 3,250,000$

    Thin Stone on Aluminum Backing 1/8" Granite on AluminumHoneyc omb Frame

    8" CMU, Core Fill Insulation57.00$ 59.77$ 70.00$ 2,850,000$ 2,988,500$ 3,500,000$

    $-

     $10.00

     $20.00

     $30.00

     $40.00

     $50.00

     $60.00

     $70.00

     $80.00

       M  e   t  a

       l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M

      a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a  s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u

      c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l   P

      r  e  c  a  s   t

       M  e   t  a   l   P  a  n  e   l  s

       S   t

      o  r  e   f  r  o  n   t

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m    B  a  c   k   i  n  g

       L   i  m

      e  s   t  o  n  e

       G  r  a  n   i   t  e

       P  a  n  e   l  s

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m    B  a  c   k   i  n  g

       P  r   i  c  e  p  e  r   S   Q   F   T

      o   f   S   k   i  n

    Exterior Types

    Exterior Skin/Finishes

     $-

     $500,000

     $1,000,000

     $1,500,000

     $2,000,000

     $2,500,000

     $3,000,000

     $3,500,000

     $4,000,000

       M  e   t  a

       l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M

      a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a  s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u

      c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l   P

      r  e  c  a  s   t

       M  e   t  a   l   P  a  n  e   l  s

       P  r   i  c  e  p  e  r   5   0 ,   0

       0   0   S   Q   F   T

      o   f   S   k   i  n

    Exterior Typ

    Exterior Skin/Finishes

    UNIT COSTS

  • 8/9/2019 Smith School Presentation RDL

    26/103

    Description System Type Low Price SQFT High Low Total High

    Metal Siding Metal Siding, Vapor Battier,

    3-5/8" Metal Studs , Thermal Batt insulation8.75$ 9.00$ 10.00$ 437,500$ 450,000$ 500,000$

    Split Face Masonry 8" Split Face CMU, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation11.75$ 12.50$ 13.00$ 587,500$ 625,000$ 650,000$

    EIFS Exterior Insualtion Finish System,

    3-5/8" Metal Studs, Thermal Batt Insulation13.00$ 14.00$ 15.00$ 650,000$ 700,000$ 750,000$

    Stucco Exterior Plaster Stucco

    3-5/8" Metal Studs, Thermal Batt Insulation12.50$ 14.00$ 15.20$ 625,000$ 700,000$ 760,000$

    Brick Veneer  Face Brick - Running Bond, Sheathing

    3-5/8" Metal Studs, Thermal Batt Insulation20.00$ 22.00$ 25.00$ 1,000,000$ 1,100,000$ 1,250,000$

    Cast Stone 5" Cast Stone Panels, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation26.00$ 27.50$ 30.00$ 1,300,000$ 1,375,000$ 1,500,000$

    Brick w/CMUback-up Face Brick - Running Bond, Polystyrene Insulation

    6" CMU, 1-1/2" Furring Channels26.50$ 28.00$ 30.00$ 1,325,000$ 1,400,000$ 1,500,000$

    Alucobond  Alucobond Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation31.00$ 32.00$ 37.00$ 1,550,000$ 1,600,000$ 1,850,000$

    Architectural Precast 5" Precast Concrete Panel, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation30.00$ 33.50$ 38.00$ 1,500,000$ 1,675,000$ 1,900,000$

    Metal Panels 2" Insulated Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation

    33.50$ 35.00$ 37.00$ 1,675,000$ 1,750,000$ 1,850,000$

    Storefront 4" Aluminum/Glass Storefront w / metal spandrels

    3-5/8" Metal Studs, Thermal Batt Insulation37.00$ 40.00$ 48.00$ 1,850,000$ 2,000,000$ 2,400,000$

    Thin Stone on Aluminum Backing 1/8" Limestone on A luminumHoneycomb Frame

    3-5/8" Metal Studs, Thermal Batt Insulation39.00$ 41.00$ 50.00$ 1,950,000$ 2,050,000$ 2,500,000$

    Limestone 5" Limestone Panel, Polystyrene Insulation,

    6" CMU, 1-1/2" Furring Channels45.00$ 47.50$ 55.00$ 2,250,000$ 2,375,000$ 2,750,000$

    Granite Panels 4" Granite Panel, Polystyrene Insualtion,

    6" CMU, 1-1/2" Furring Channels55.00$ 57.00$ 65.00$ 2,750,000$ 2,850,000$ 3,250,000$

    Thin Stone on Aluminum Backing 1/8" Granite on AluminumHoneyc omb Frame

    8" CMU, Core Fill Insulation57.00$ 59.77$ 70.00$ 2,850,000$ 2,988,500$ 3,500,000$

    $-

     $10.00

     $20.00

     $30.00

     $40.00

     $50.00

     $60.00

     $70.00

     $80.00

       M  e   t  a

       l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M

      a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a  s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u

      c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l   P  r  e  c  a  s   t

       M  e   t  a

       l   P  a  n  e   l  s

       S   t  o  r  e   f  r  o  n   t

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m    B  a  c   k   i  n  g

       L   i  m

      e  s   t  o  n  e

       G  r  a  n   i   t  e

       P  a  n  e   l  s

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m    B  a  c   k   i  n  g

       P  r   i  c  e  p  e  r   S   Q   F   T

      o   f   S   k   i  n

    Exterior Types

    Exterior Skin/Finishes

     $-

     $500,000

     $1,000,000

     $1,500,000

     $2,000,000

     $2,500,000

     $3,000,000

     $3,500,000

     $4,000,000

       M  e   t  a

       l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M

      a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a  s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u

      c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l   P  r  e  c  a  s   t

       M  e   t  a

       l   P  a  n  e   l  s

       P  r   i  c  e  p  e  r   5   0 ,   0

       0   0   S   Q   F   T

      o   f   S   k   i  n

    Exterior Typ

    Exterior Skin/Finishes$8.75

    $61.25 per sqft

    Variation

    $70.00

    UNIT COSTS

  • 8/9/2019 Smith School Presentation RDL

    27/103

    Description System Type Low Price SQFT High Low Total High

    Metal Siding Metal Siding, Vapor Battier,

    3-5/8" Metal Studs , Thermal Batt insulation8.75$ 9.00$ 10.00$ 437,500$ 450,000$ 500,000$

    Split Face Masonry 8" Split Face CMU, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation11.75$ 12.50$ 13.00$ 587,500$ 625,000$ 650,000$

    EIFS Exterior Insualtion Finish System,

    3-5/8" Metal Studs, Thermal Batt Insulation13.00$ 14.00$ 15.00$ 650,000$ 700,000$ 750,000$

    Stucco Exterior Plaster Stucco

    3-5/8" Metal Studs, Thermal Batt Insulation12.50$ 14.00$ 15.20$ 625,000$ 700,000$ 760,000$

    Brick Veneer  Face Brick - Running Bond, Sheathing

    3-5/8" Metal Studs, Thermal Batt Insulation20.00$ 22.00$ 25.00$ 1,000,000$ 1,100,000$ 1,250,000$

    Cast Stone 5" Cast Stone Panels, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation26.00$ 27.50$ 30.00$ 1,300,000$ 1,375,000$ 1,500,000$

    Brick w/CMUback-up Face Brick - Running Bond, Polystyrene Insulation

    6" CMU, 1-1/2" Furring Channels26.50$ 28.00$ 30.00$ 1,325,000$ 1,400,000$ 1,500,000$

    Alucobond  Alucobond Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation31.00$ 32.00$ 37.00$ 1,550,000$ 1,600,000$ 1,850,000$

    Architectural Precast 5" Precast Concrete Panel, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation30.00$ 33.50$ 38.00$ 1,500,000$ 1,675,000$ 1,900,000$

    Metal Panels 2" Insulated Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation

    33.50$ 35.00$ 37.00$ 1,675,000$ 1,750,000$ 1,850,000$

    Storefront 4" Aluminum/Glass Storefront w / metal spandrels

    3-5/8" Metal Studs, Thermal Batt Insulation37.00$ 40.00$ 48.00$ 1,850,000$ 2,000,000$ 2,400,000$

    Thin Stone on Aluminum Backing 1/8" Limestone on A luminumHoneycomb Frame

    3-5/8" Metal Studs, Thermal Batt Insulation39.00$ 41.00$ 50.00$ 1,950,000$ 2,050,000$ 2,500,000$

    Limestone 5" Limestone Panel, Polystyrene Insulation,

    6" CMU, 1-1/2" Furring Channels45.00$ 47.50$ 55.00$ 2,250,000$ 2,375,000$ 2,750,000$

    Granite Panels 4" Granite Panel, Polystyrene Insualtion,

    6" CMU, 1-1/2" Furring Channels55.00$ 57.00$ 65.00$ 2,750,000$ 2,850,000$ 3,250,000$

    Thin Stone on Aluminum Backing 1/8" Granite on AluminumHoneyc omb Frame

    8" CMU, Core Fill Insulation57.00$ 59.77$ 70.00$ 2,850,000$ 2,988,500$ 3,500,000$

    $-

     $10.00

     $20.00

     $30.00

     $40.00

     $50.00

     $60.00

     $70.00

     $80.00

       M  e   t  a   l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M

      a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a  s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u

      c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l   P  r  e  c  a  s   t

       M  e   t  a

       l   P  a  n  e   l  s

       S   t  o  r  e   f  r  o  n   t

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m 

       B  a  c   k   i  n  g

       L   i  m

      e  s   t  o  n  e

       G  r  a  n   i   t  e

       P  a  n  e   l  s

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m 

       B  a  c   k   i  n  g

       P  r   i  c  e  p  e  r   S   Q   F   T

      o   f   S   k   i  n

    Exterior Types

    Exterior Skin/Finishes

     $-

     $500,000

     $1,000,000

     $1,500,000

     $2,000,000

     $2,500,000

     $3,000,000

     $3,500,000

     $4,000,000

       M  e   t  a   l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M

      a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a  s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u

      c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l   P  r  e  c  a  s   t

       M  e   t  a

       l   P  a  n  e   l  s

       P  r   i  c  e  p  e  r   5   0 ,   0

       0   0   S   Q   F   T

      o   f   S   k   i  n

    Exterior Typ

    Exterior Skin/Finishes$437,500

    $3,062,500

    Variation

    $3,500,000

    UNIT COSTS

  • 8/9/2019 Smith School Presentation RDL

    28/103

    Description System Type Low Price SQFT High Low Total High

    Metal Siding Metal Siding, Vapor Battier,

    3-5/8" Metal Studs , Thermal Batt insulation8.75$ 9.00$ 10.00$ 437,500$ 450,000$ 500,000$

    Split Face Masonry 8" Split Face CMU, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation11.75$ 12.50$ 13.00$ 587,500$ 625,000$ 650,000$

    EIFS Exterior Insualtion Finish System,

    3-5/8" Metal Studs, Thermal Batt Insulation13.00$ 14.00$ 15.00$ 650,000$ 700,000$ 750,000$

    Stucco Exterior Plaster Stucco

    3-5/8" Metal Studs, Thermal Batt Insulation12.50$ 14.00$ 15.20$ 625,000$ 700,000$ 760,000$

    Brick Veneer  Face Brick - Running Bond, Sheathing

    3-5/8" Metal Studs, Thermal Batt Insulation20.00$ 22.00$ 25.00$ 1,000,000$ 1,100,000$ 1,250,000$

    Cast Stone 5" Cast Stone Panels, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation26.00$ 27.50$ 30.00$ 1,300,000$ 1,375,000$ 1,500,000$

    Brick w/CMUback-up Face Brick - Running Bond, Polystyrene Insulation

    6" CMU, 1-1/2" Furring Channels26.50$ 28.00$ 30.00$ 1,325,000$ 1,400,000$ 1,500,000$

    Alucobond  Alucobond Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation31.00$ 32.00$ 37.00$ 1,550,000$ 1,600,000$ 1,850,000$

    Architectural Precast 5" Precast Concrete Panel, Vapor Barrier,

    3-5/8" Metal Studs, Thermal Batt Insulation30.00$ 33.50$ 38.00$ 1,500,000$ 1,675,000$ 1,900,000$

    Metal Panels 2" Insulated Panel, Vapor Barrier 

    3-5/8" Metal Studs, Thermal Batt Insulation

    33.50$ 35.00$ 37.00$ 1,675,000$ 1,750,000$ 1,850,000$

    Storefront 4" Aluminum/Glass Storefront w / metal spandrels

    3-5/8" Metal Studs, Thermal Batt Insulation37.00$ 40.00$ 48.00$ 1,850,000$ 2,000,000$ 2,400,000$

    Thin Stone on Aluminum Backing 1/8" Limestone on A luminumHoneycomb Frame

    3-5/8" Metal Studs, Thermal Batt Insulation39.00$ 41.00$ 50.00$ 1,950,000$ 2,050,000$ 2,500,000$

    Limestone 5" Limestone Panel, Polystyrene Insulation,

    6" CMU, 1-1/2" Furring Channels45.00$ 47.50$ 55.00$ 2,250,000$ 2,375,000$ 2,750,000$

    Granite Panels 4" Granite Panel, Polystyrene Insualtion,

    6" CMU, 1-1/2" Furring Channels55.00$ 57.00$ 65.00$ 2,750,000$ 2,850,000$ 3,250,000$

    Thin Stone on Aluminum Backing 1/8" Granite on AluminumHoneyc omb Frame

    8" CMU, Core Fill Insulation57.00$ 59.77$ 70.00$ 2,850,000$ 2,988,500$ 3,500,000$

    $-

     $10.00

     $20.00

     $30.00

     $40.00

     $50.00

     $60.00

     $70.00

     $80.00

       M  e   t  a   l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M  a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a

      s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u  c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l

       P  r  e  c  a  s   t

       M  e   t  a

       l   P  a  n  e   l  s

       S   t  o  r  e   f  r  o  n   t

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m    B  a  c   k   i  n  g

       L   i  m  e  s   t  o  n  e

       G  r  a  n   i   t  e   P  a  n  e   l  s

       T   h   i  n   S   t  o  n  e  o  n   A   l  u  m   i  n  u  m    B  a  c   k   i  n  g

       P  r   i  c  e  p  e  r   S   Q   F   T

      o   f   S   k   i  n

    Exterior Types

    Exterior Skin/Finishes

     $-

     $500,000

     $1,000,000

     $1,500,000

     $2,000,000

     $2,500,000

     $3,000,000

     $3,500,000

     $4,000,000

       M  e   t  a   l   S   i   d   i  n  g

       S  p   l   i   t   F  a  c  e   M  a  s  o  n  r  y

       E   I   F   S

       S   t  u  c  c  o

       B  r   i  c   k

       V  e  n  e  e  r

       C  a

      s   t   S   t  o  n  e

       B  r   i  c   k  w   /   C   M   U

       b  a  c   k  -  u  p

       A   l  u  c  o   b  o  n   d

       A  r  c   h   i   t  e  c   t  u  r  a   l

       P  r  e  c  a  s   t

       M  e   t  a

       l   P  a  n  e   l  s

       P  r   i  c  e  p  e  r   5   0 ,   0

       0   0   S   Q   F   T

      o   f   S   k   i  n

    Exterior Typ

    Exterior Skin/Finishes

    $20.00

    $250,000

    Variation

    UNIT COSTS

    $25.00

    $1,000,000

    $1,250,000

  • 8/9/2019 Smith School Presentation RDL

    29/103

    Why such variation?

    PROJECT SCOPE ITEMS NOT FUNDED BY OSFC

  • 8/9/2019 Smith School Presentation RDL

    30/103

    Program/BudgetSchematic Design

    Design DevelopmentConstruction Documents

    BiddingCon

    High Range

    Low Range

    Fixed Limit of Co

    Budget Control Process

    Budgeti

    ngEstimating

    BUDGET CONTROL PROCESS:

    THE DIFFERENCE BETWEEN

    BUDGETING AND ESTIMATING

    Objective is to Maintain Alignment of:

    Program

    Scope

    Quality

    Quantity

    Schedule

    Service

    Design

    Price

  • 8/9/2019 Smith School Presentation RDL

    31/103

    ASSESSMENT

  • 8/9/2019 Smith School Presentation RDL

    32/103

  • 8/9/2019 Smith School Presentation RDL

    33/103

  • 8/9/2019 Smith School Presentation RDL

    34/103

    $42 MillionScott High SchoolBuilt 1913

    Renovation completed 2011

    $1,000,000 Gates Foundatio

    284,000 sqft

    4 stories

    1,000 students (in 1913 2,37

    $20 MillionBuilt 1914Renovation 2012

    h ll f h h

  • 8/9/2019 Smith School Presentation RDL

    35/103

    Duket Architects

    Waite High SchoolThe current enrollment for the schoo

    students with a maximum capacity o

    290,191 sqft

    4 stories

    The extent of work included both ex

    renovations and interior reprogramm

    space.

  • 8/9/2019 Smith School Presentation RDL

    36/103

    Project: Seneca County Court House Budget Estimate LowDescription: Rennovation of 1884 3-Story Historic Court House

    Location: Seneca Co unty, Tiffin, Ohio

    Client: Seneca County Comissioners

    Tenant: Seneca County Common Please Court an Issued Date: 20-Jul-09

    Estimator: McCabe Version No. 1 Low Range

    E XE CU TIV E S UM MAR Y QU AN TIT Y U N IT C OS T/ UN IT T OT AL COS T $/ SQFT COST /U NIT T OT AL COST $/S QFT COST/UNIT TOTAL C

    FOUNDATIONS 13,279  SFFP 1.88 25,010 0.74 1.41  18,668  0.55 2.34   

    Building Areas SUBSTRUCTURE 13,279  SFFP 2.01 26,668 0.79 1.03  13,630  0.40 2.28   

    Units Usable SQFT Walls (int & ext) T ota l GSF SUPERSTRUCTURE 33,875  SQFT 5.38 182,381 5.38 3.63  123,086  3.63 6.00  2 

    Ground Floor (Historic Portion) 6,942  3 ,481 10,423  EXTERIOR CLOSURE 36,254  SFSKIN 21.76 788,969 23.29 19.44  704,753  20.80 24.08  8 

    First Floor (Historic Portion) 6,835  2,898 9,733  ROOF COVERING 13,279  SFFP 1.83 24,281 0.72 1.31  17,433  0.51 1.94   

    Second Floor (Historic Portion) 6,890  2,849 9,739  INTERIOR CONSTRUCTION 33,875  SQFT 34.42 1,165,852 34.42 30.55  1,034,948  30.55 39.97  1,3 

    New Connector  1,271  n/a 1,271  CONVEYING SYSTEM 11  STOPS 11,086.36 121,950 3.60 10,181.82  112,000  3.31 11,909.09  1 

    New Security Entrance 1,245  n/a 1,245  MECHANICAL 33,875  SQFT 32.46 1,099,430 32.46 27.00  914,520  27.00 35.59  1,2 

    New Space Below West Stair  340  n/a 340  ELECTRICAL 33,875  SQFT 24.67 835,650 24.67 22.60  765,559  22.60 27.96  9 Third Floor (Intermediate Floor) 1,124  n/a 1,124  SUBTOTAL BUILDING COST 4,270,192 126.06 3,704,597 109.36 4,80 

    Fourth Floor Attic -  EQUIPMENT 33,875  SQFT 0.04 1,320 0.04 0.03  1,180  0.03 0.04   

    -  SPECIAL CONSTRUCTION 33,875  SQFT -  -  -   

    -  SUBTOTAL EQU IPMENT & SPECIAL CONSTRUCTION 1,320 0.04 1,180 0.03  

    -  S IT EW OR K & DE MOLIT ION 1.20   ACRE 363,678.28 436,230 12.88 362,341  10.70 52 

    Totals 24,647  9,228  -  33,875  GENERAL CONDITIONS 12.0 MONT 28,873.81 346,486 10.23 25,895.12  310,741  9.17 34,469.34  4 

    -  INDIRECT AND RESERVES 33,875  SQFT 36.79 1,246,185 36.79 30.59  1,036,361  30.59 44.58  1,5 

    T o ta l Bui ld in g A re a 3 3, 87 5  CM/GC FEES 52.0  WEEKS 6,062.75 315,021 9.30 5,210.95  270,761  7.99 6,979.65  3 

    SUBTOTAL SITE, PERMITS AND FEES 1,907,691 56.32 1,617,863 47.76 2,28 

    TOTAL 6,615,434$ 195.29$ 5,685,981$ 167.85$ 7,61 

    ADDITIONAL COSTS

    Historic Exterior Skylight Replacement

    Landscaping Allowance 36,750 1.08 31,500 0.93 4

    Footpla te: 13,279 SQFT Window Treatments 12,921 0.38 10,768 0.32 1

    Number of Floors 4  Tower and Dome Reconstruction 829,836 24.50 786,996 23.23 89

    FF&E Allowance 500,000 14.76 500,000 14.76 50

    Perimeter (H istoric Portion): 438 LNFT

    Exterior Wall Height Above Grade (Historic): 66 LNFT  

    E xte ri or S kin H is to ric ( Ab ov e F lo or Line ) 2 8, 90 8  SQFT

    TOTAL W/ ADDIT IONAL COSTS 7,994,941$ 236.01$ 7,015,245$ 207.09$ 9,07$

    Exterior Skin Historic (Tower) 4,700  SQFT

    Perimeter (New Portion): 189 LNFT WOR K BY OTH ERS

    Exterior Wall Height Above Grade (New Portion): 14 LNFT The following items are not accounted for in this budget. These items are either to be provid ed by the Owner, or 

    E xte ri or S ki n N e w P ort io n ( Ab ov e F lo or Li ne ) 2 ,6 46 S QF T require additional definition of scope for inclusion in this budget.

    Total Exterior Skin 36,254 1. Excludes all winter construction: such as lost production, weather protection, -$

    enclosures or temporary heat.

    Skin to Floor Ratio 1.070 2. Excludes any consideration of unusual subterranean conditions such as rock, bad

    soils, or hazardous materials. -$

    Site Area (Work Area) 52,250 SQFT 3. Excludes any off-site utilities and sitework. -$

    1.20  ACRES 4. Excludes utility costs during construction, water, sewer, electric, natural ga s

    Coverage %: (Floor area/acre) 25.41% 5. Excludes any additional Owner contingency . -$

    Auto Parking Spaces 4 6. Excludes cost or removal of hazardous materials. -$

    8,469  SF/SPACE 7. Excludes sales tax. -$

    8. Excludes negotiation and costs involved with street shut-downs, traffic directing, etc. -$

    Duration 12.0 MONT HS 9. Excludes any financing or interest costs. -$

    52.0 WEEKS 10. Excludes any land or acquisition costs. -$

    364 DAYS 11. Excludes any special development assessments for public improvements. -$

    12. -$

    13. -$

    14. -$

    15. -$

    16. -$

    17.

    18. -$

    TOTAL PROJECT COST $ By Owner 

    PROJECT PARAMETERS

  • 8/9/2019 Smith School Presentation RDL

    37/103

    ($200,000) ($150,000) ($100,000) ($50,000) $0 $50,000 $100,000

      H.V.A.C. De molition & Patching

     Wall Finishes Vertical Circulation

      Caulking & Sealing & Stone Resoration  Special Electrical Systems

     Exterior Finishes  Fixtures & Lamps Finish Carpentry

      Temperature Control System  Interior partitions Structural Framing

     Floor Finishes  Circuits & Devices

      Plumbing  Cleaning & site maintenance

      Elevators  Interior Doors & Frames

     Fire Protection  Concrete Slabs on Grade

      Ceiling Finishes  Perimeter frame insul D.W.

     Vertical hoisting Ro ofing & flashing

     Performance/Payment Bonds Miscellaneous G.C.s

     Exterior Windows  Elevated Slabs & Decks

     Job Personnel  Pits & Trenches

      Safety & security Standard Foundations

     I nterior Fire Walls Exterior Doors

      Builder's Risk Insurance Foundation Treatments

      Sidewalks & Curbs Construction Aids

      Soffits  Interior Glazing

      Equipment & Vehicles  Identification devices

     Site Improvements Mi scellaneous Site Concrete

      Site Utilities  Specialties

      Paving Site Electrical

     Temporary Facilities  Fnd Excavation & Backfill

      Temporary Road  Dirtwork

      Landscaping  Appliances

     Travel Expenses  Testing

      Field Engineering Temporary Utilities

     Winter conditions  Preparation

      Foundation Walls  Basements

     Spray-on Fireproofing Architectural Louvers

     Roof Accessories Window Treatments

      Special Mechanical Systems  Main Feeders & Secondary  Switchgear & Transformers

     Parking Systems Temporary Construction

      Refrigeration  Permits, Fees, Cap. Charges, Assesmts.

      Liabili ty Insurance

    Variance to Base Budget by Element

       C  o  s   t   E   l  e  m  e  n   t  s

    Cost Variation Analysis by Element

    EXPOSUREOPPORTUNITY

    M Pl O i A N PK 3 N 4 6

  • 8/9/2019 Smith School Presentation RDL

    38/103

    Master Plan Option A - New PK-3, New 4-6

    Plan Description Co-funded Cost Local Funded Intiatives Total Project Cost State Share Local Share Total

    Build (1) New PK-3 for 884 students 21,809,412.00$ New PK-3 22,$

    Inflation Factor for Local Share 302,647.66$

    Building Enhancements 490,711.77$

    Build (1) New 4-6 for 670 students 19,337,547.00$ New 4-6 20,$

    Inflation Factor for Local Share 302,647.66$

    Additional square footage - Gymnasium 231,240.00$Building Enhancements 518,113.78$

    Site Enhancements 1,000,000.00$

    Maintenance Facility 300,000.00$

    Athletic Concessions / Restroom Facilities 600,000.00$

    No new work at MS/HS complex -$

    Abate and demolish allowance 3,689,732.00$

    44,836,691.00$ 3,745,360.88$ 48,582,051.88$ 24,660,180.05$ 23,921,871.83$

    *Will only fund value of replacement

    Master Plan Option B Ne PK 3 Reno ate JA Smith ith 5 447sf addition

  • 8/9/2019 Smith School Presentation RDL

    39/103

    Master Plan Option B - New PK-3, Renovate JA Smith with 5,447sf addition

    Plan Description Co-funded Cost Local Funded Intiatives Total Project Cost State Share (fixed) Local Share

    Build (1) New PK-3 for 884 students 21,809,412.00$ New PK-3 22,$

    Inflation Factor for Local Share 349,282.68$

    Building Enhancements 490,711.77$

    Re novate JA Smi th to 4- 6 for 670 stude nts 16,848,620.03$ Reno 4-6 23,$

    Add 5,447sf on to JA Smith (Academic) 1,332,548.14$

    (11.5% LFI unforeseen/misses in assessment/reno premium cost) 1,937,591.30$Inflation Factor for Local Share 349,282.68$

    Site Access Allowance 300,000.00$

    LEED Allowance 642,884.27$

    Renovation cost for oversived gym space (3,612sf) 613,714.92$

    LEED cost for oversized gym space 24,240.28$

    Renovation cost for auditorium 1,394,107.88$

    LEED cost for auditorium 60,580.58$

    Site Enhancements 1,000,000.00$

    Maintenance Facility 300,000.00$

    Athletic Concessions / Restroom Facilities 600,000.00$

    No new work at MS/HS complex -$

    Abate and demolish allowance 2,981,992.00$

    42,972,572.17$ 8,062,396.35$ 51,034,968.52$ 24,660,180.05$ 26,374,788.47$

    *Will only fund value of replacement

    Increase to Local Share 2,452,916.65$

    Possible reductions for "mothballing" auditorium (849,909.76)$

    42,972,572.17$ 7,212,486.59$ 50,185,058.76$ 24,660,180.05$ 25,524,878.71$

    Increase to Local Share 1,603,006.89$

    Master Plan Option B New PK 3 Renovate JA Smith with 5 447sf addition

  • 8/9/2019 Smith School Presentation RDL

    40/103

    Master Plan Option B - New PK-3, Renovate JA Smith with 5,447sf addition

    Plan Description Co-funded Cost Local Funded Intiatives Total Project Cost State Share (fixed) Local Share

    Build (1) New PK-3 for 884 students 21,809,412.00$ New PK-3 22,$

    Inflation Factor for Local Share 349,282.68$

    Building Enhancements 490,711.77$

    Re novate JA Smi th to 4- 6 for 670 stude nts 16,848,620.03$ Reno 4-6 21,$

    Add 5,447sf on to JA Smith (Academic) 1,332,548.14$

    (11.5% LFI unforeseen/misses in assessment/reno premium cost) 1,937,591.30$Inflation Factor for Local Share 349,282.68$

    Site Access Allowance 300,000.00$

    LEED Allowance 642,884.27$

    Renovation cost for oversived gym space (3,612sf) By Others

    LEED cost for oversized gym space By Others

    Renovation cost for auditorium By Others

    LEED cost for auditorium By Others

    Site Enhancements 1,000,000.00$

    Maintenance Facility 300,000.00$

    Athletic Concessions / Restroom Facilities 600,000.00$

    No new work at MS/HS complex -$

    Abate and demolish allowance 2,981,992.00$

    42,972,572.17$ 5,969,752.69$ 48,942,324.86$ 24,660,180.05$ 24,282,144.81$

    *Will only fund value of replacement

    Increase to Local Share 360,272.99$

    By Others

    Renovation cost for oversived gym space (3,612sf) 613,714.92$

    LEED cost for oversized gym space 24,240.28$

    Renovation cost for auditorium 1,394,107.88$LEED cost for auditorium 60,580.58$

    2,092,643.66$

  • 8/9/2019 Smith School Presentation RDL

    41/103

    “ G R E E N “ B U I L D I N G

  • 8/9/2019 Smith School Presentation RDL

    42/103

    United States Green Building Council

    Why energy efficiency is important

  • 8/9/2019 Smith School Presentation RDL

    43/103

    Image: architecture2030.org

    y gy y

    Sustainable Stewardship Principles

  • 8/9/2019 Smith School Presentation RDL

    44/103

    1.) Reuse existing buildings

    2.) Reinvest in communities

    3.) Retrofit older buildings

    4.) Respect historic integrity

    Sustainable Stewardship Principles

    Image: USGBC

    The impact of building demolition

  • 8/9/2019 Smith School Presentation RDL

    45/103

    Image: carolstream.org

    Image: carolstream.org

    • Construction debris accounts for 25%

    of the waste in municipal waste

    stream.

    • It takes 65 years for an energy

    efficient new building to save theamount of energy lost in demolishing

    an existing building.

  • 8/9/2019 Smith School Presentation RDL

    46/103

    “ N E W “ vs. “ L I K E N E W “

  • 8/9/2019 Smith School Presentation RDL

    47/103

  • 8/9/2019 Smith School Presentation RDL

    48/103

    Historic SchoolsBefore and After

    40% to 45%OF ALL OFCC SCHOOL PROJECTS

    ARE RENOVATIONS

    Cristo Rey Columbus High School (1898)

  • 8/9/2019 Smith School Presentation RDL

    49/103

    Cristo Rey Columbus High School (1898)

    Cristo Rey High SchoolColumbus, Ohio

    Original Construction: 189Renovation: 201485,000 SF

    500 Students4 StoriesConstruction Cost: $15.9M

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    50/103

    Cristo Rey Columbus High School

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    51/103

    Cristo Rey Columbus High School

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    52/103

    Cristo Rey Columbus High School

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    53/103

    y g

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    54/103

    First Floor Plan

    y g

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    55/103

    y g

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    56/103

    y g

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    57/103

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    58/103

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    59/103

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    60/103

    Cristo Rey Columbus High School

  • 8/9/2019 Smith School Presentation RDL

    61/103

    Clinton Elementary School (1922)

  • 8/9/2019 Smith School Presentation RDL

    62/103

    Clinton Elementary SchoolColumbus, Ohio

    Original Construction: 1922 400 Students

    Renovation: 2013 3 Stories53,900 SF Construction Cost: $9.7M

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    63/103

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    64/103

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    65/103

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    66/103

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    67/103

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    68/103

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    69/103

    Clinton Elementary School

  • 8/9/2019 Smith School Presentation RDL

    70/103

    East High School (1922)

  • 8/9/2019 Smith School Presentation RDL

    71/103

    East High SchoolColumbus, Ohio

    Original Construction: 192Renovation: 2008168,000 SF

    800 Students3 StoriesConstruction Cost: $22.8M

    East High School

  • 8/9/2019 Smith School Presentation RDL

    72/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    73/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    74/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    75/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    76/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    77/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    78/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    79/103

    East High School

  • 8/9/2019 Smith School Presentation RDL

    80/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    81/103

    Ft. Hayes Metropolitan Education Center (1860’s)

  • 8/9/2019 Smith School Presentation RDL

    82/103

    Columbus Barracks

    Fort Hayes High SchoolColumbus, Ohio

    (three buildings)

    Original Construction: 189Renovation: 201065,000 SF

    1000 Students2 - 3 StoriesConstruction Cost: $8.1M

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    83/103

    11th Company Headquarters at Columbus Barrac

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    84/103

    10th Company Headquarters

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    85/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    86/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    87/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    88/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    89/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    90/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    91/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    92/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    93/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    94/103

    Ft. Hayes Metropolitan Education Center

  • 8/9/2019 Smith School Presentation RDL

    95/103

    Benefits of Renovating Smith School

    1. Cost to community is the same or less

    2 100 year building vs 40 year building

  • 8/9/2019 Smith School Presentation RDL

    96/103

    2. 100 year building vs. 40 year building

    Brick, slate, sloping roofs

    3. School design High ceilings, huge windows, wood floors,

    Wide corridors, lockers vs. cubbies, special ELAs

    4. Community Landmark is preserved

    5. Restored Georgian Revival architectural gem

    6. Heritage Connections – linking generations

    7. Civic – community pride

    8. Auditorium/Gymnasium beyond OFCC

    9. Storm Shelter

    10. “Found Space” opportunities

  • 8/9/2019 Smith School Presentation RDL

    97/103

    Opportunities

    1. Auditorium / Cafeteria / Kitchen / Courtyard

    +/ 1 000 seats largest in community

  • 8/9/2019 Smith School Presentation RDL

    98/103

    +/- 1,000 seats – largest in community

    Excellent acoustics

    Benefits• Students

    • Community

    • Attracting major events to Chillicothe

    Including possible World Heritage Site

    2. Gymnasium

    History of after school hours community use

    3. Locker Rooms

    Home/Visiting teams at outdoor fields

    Conferences and camps

    Tournaments and club sports

    4. Availability of IA Building for additional uses

    The “A S K”

    1. Hold off immediate demolition of Smith School

  • 8/9/2019 Smith School Presentation RDL

    99/103

    2. Continue to engage the larger community to develop consensus

    around the School District’s master plan for facilities and funding plangoing forward

    3. Consider a marketing analysis for community use of the Auditorium

    complex, resulting in possible alternative funding possibilities

    Heritage tourism, and

    Special events, are increasing business segments

    4. Provide temporary safety and security measures at Smith

  • 8/9/2019 Smith School Presentation RDL

    100/103

    Why a little additional time is important

  • 8/9/2019 Smith School Presentation RDL

    101/103

    Why a little additional time is important

  • 8/9/2019 Smith School Presentation RDL

    102/103

    Status Report: Save our Smith GroupMarch 11, 2015

  • 8/9/2019 Smith School Presentation RDL

    103/103