smart city cluster collaboration, task 4. measurement and verification methodology for energy,...
Upload: dc4cities-project-environmentally-sustainable-data-centre-for-smart-cities
Post on 13-Aug-2015
48 views
TRANSCRIPT
1
Smart City Cluster Collaboration
Task 4 Data Centre Integration
Energy, Environmental, and Economic Efficiency Metrics: Measurement and Verification Methodology
2
Revision History
VERSION DATE PARTNERS DESCRIPTION/COMMENTS
4.1.1 2015 – 04 – 20 Jacinta Townley (GENiC /UTRCI)
Complied the work completed for Task 4.1
4.1.2 2015 – 04 – 22 Jaume Salom (RenewIT / IREC)
Comments
4.1.3 4.1.4 4.1.5
2015 – 04 – 28 2015 – 06 – 12 2015 – 06 – 12
Vasiliki Georgiadou (GEYSER / Green IT Amsterdam) Jacinta Townley (GENiC/UTRCI) Jacinta Townley (GENiC/UTRCI)
Review comments Updated sections based on comments, made some additional text change and added standardisation input. Updated ERE with footnote and extended intro section.
4.1.6 2015 – 06 - 25 Silvia Sanjoaquín Vives (DC4Cities/ GNF)
Last review
VERSION DATE PARTNERS DESCRIPTION/COMMENTS
4.2.1 2015 – 04 – 24 Daniela Isidori (RenewIT/Loccioni)
Complied the work completed for Task 4.2
4.2.2 2015 – 05 – 18 Gonzalo Díaz Vélez / Silvia Sanjoaquín Vives (DC4Cities / GNF)
Document review
4.2.3 2015 – 05 – 18 Daniela Isidori (RenewIT/Loccioni)
Document fixing after review
4.2.4 2015 – 06 – 01 Andrea Quintiliani (DC4Cities / ENEA)
Example for EES and few minor corrections in the EES chapter
4.2.5 2015 – 06 – 03 Daniela Isidori (RenewIT/Loccioni)
Examples for all metrics except for GUF
4.2.6 2015 – 06 – 04 Daniela Isidori (RenewIT/Loccioni
Document fixing after review (Figures, Tables, Sections and Equations cross references)
4.2.7 2015 – 06 -04 Vasiliki Georgiadou (GEYSER / Green IT Amsterdam)
Review
4.2.8 2015 – 06 -18 Jaume Salom (RenewIT/Irec) Review 4.2.9 2015 – 06 -19 Daniela Isidori
(RenewIT/Loccioni) Last Review
4.2.10 2015-06-25 Silvia Sanjoaquín Vives (DC4Cities/ GNF)
Last review
VERSION DATE PARTNERS DESCRIPTION/COMMENTS
4.1 2015 – 06 – 29 Alexis Aravanis (DOLFIN/Synelixis)
Task 4.1 and 4.2 consolidation
4.2 2015 -07 - 06 Silvia Sanjoaquín Vives (DC4Cities/GNF)
Last review
3
Metric M&V Synopsis
Metric Full Name Adaptability Power Curve
Metric Short Name APC
Metric Category DC Flexibility: Energy Shifting
Metric Description It provides an evaluation of the capability of a DC to adapt to a pre-defined DC energy consumption curve.
Metric Category Leader DOLFIN/Synelixis
Developing partners Artemis Voulkidis, Alexis Aravanis - DOLFIN/Synelixis Andrea Quintiliani, Marta Chinnici - DC4Cities/ENEA Vasiliki Georgiadou – GEYSER/Green IT Amsterdam Massimiliano Manca – RenewIT/Loccioni Tomas Fernandez Buckley – Acciona/GENiC
Reviewer partners Milagros Rey Porto, Silvia Sanjoaquín Vives, Gonzalo Díaz Vélez – DC4Cities/GNF; Andrea Quintiliani, - DC4Cities/ENEA
Metric Full Name Adaptability Power Curve at Renewable Energies
Metric Short Name
Metric Category Data Centre Flexibility: Energy Shifting
Metric Description It provides an evaluation of the capability of a data centre to adapt to the production curve of the renewable energy sources available to the data centre in hand.
Metric Category Leader DOLFIN/Synelixis
Developing partners
Artemis Voulkidis, Alexis Aravanis - DOLFIN/Synelixis Andrea Quintiliani, Marta Chinnici - DC4Cities/ENEA Vasiliki Georgiadou – GEYSER/Green IT Amsterdam Massimiliano Manca – RenewIT/Loccioni Tomas Fernandez Buckley – Acciona/GENiC
Reviewing partners Milagros Rey Porto/Silvia Sanjoaquín Vives, Gonzalo Díaz Vélez – DC4Cities/GNF, Andrea Quintiliani, - DC4Cities/ENEA
Metric Full Name Data Centre Adapt
Metric Short Name DCA
Metric Category DC Flexibility: Energy Shifting
Metric Description It provides an evaluation of the capability of a DC to change its energy consumption behaviour, compared to its respective behaviour before the application of a certain set of optimisation actions
4
Metric Category Leader DOLFIN/Synelixis
Developing partners
Artemis Voulkidis, Aravanis Alexis – DOLFIN/Synelixis Andrea Quintiliani, Marta Chinnici - DC4CITIES/ENEA Vasiliki Georgiadou – GEYSER/Green IT Amsterdam Massimiliano Manca – RenewIT/Loccioni Tomas Fernandez Buckley – Acciona/GENiC
Reviewing partners Milagros Rey Porto, Silvia Sanjoaquín Vives - GNF/DC4Cities, Andrea Quintiliani, - ENEA/DC4Cities
Metric Full Name Primary Energy Savings
Metric Short Name PE Savings
Metric Category PE Savings and CO2 avoided emissions
Metric Description The percentage of savings in terms of primary energy consumed by a data centre, once improvements have taken place with regard to its energetic, economic, or environmental management
Metric Category Leader Vasiliki Georgiadou (GEYSER / Green IT Amsterdam)
Developing partners Andrea Quintiliani, Marta Chinnici (DC4Cities / ENEA), Philip Inglesant (RenewIT / 451 Research), Davide Nardi Cesarini (RenewIT / Loccioni)
Reviewing partners Milagros Rey / Silvia Sanjoaquín Vives / Gonzalo Díaz Vélez (DC4Cities / GNF); Philip Inglesant (RenewIT/451 Research)
Metric Full Name CO2 Avoided Emissions
Metric Short Name CO2Savings
Metric Category PE Savings and CO2 avoided emissions
Metric Description The percentage of savings in terms of CO2 emissions generated by a data centre, once improvements have taken place with regard to its energetic, economic, or environmental management
Metric Category Leader Vasiliki Georgiadou (GEYSER / Green IT Amsterdam)
Developing partners Andrea Quintiliani, Marta Chinnici (DC4Cities / ENEA), Philip Inglesant (RenewIT / 451 Research), Davide Nardi Cesarini (RenewIT / Loccioni)
Reviewing partners Milagros Rey Porto, Silvia Sanjoaquín Vives, Gonzalo Díaz Vélez (DC4Cities / GNF)
Metric Full Name Energy Expenses
Metric Short Name EES
Metric Category Economic savings in energy expenses
Metric Description A measure of how much the energy related expenses have changed in comparison to a baseline scenario, after having performed actions to upgrade the energetic, economic or environmental behaviour of a data centre
Metric Category Leader Andrea Quintiliani, Marta Chinnici (DC4Cities / ENEA)
5
Developing partners Vasiliki Georgiadou (GEYSER / Green IT Amsterdam)
Reviewing partners Milagros Rey Porto, Silvia Sanjoaquín Vives, Gonzalo Díaz Vélez (DC4Cities / GNF), Anthony Schoofs (GEYSER / Wattics)
Metric Full Name Grid Utilization Factor
Metric Short Name GUF
Metric Category Renewables integration: Energy produced locally and Renewable usage
Metric Description Percentage of time that the local generation does not cover the building demand, and thus how often energy must be supplied by the grid
Metric Category Leader Davide Nardi Cesarini (RenewIT/Loccioni), Jaume Salom (RenewIT/IREC)
Developing partners Artemis Voulkidis (Dolfin/Synelixis)
Reviewing partners Gonzalo Díaz Vélez / Silvia Sanjoaquín Vives, Gonzalo Díaz Vélez (DC4Cities / GNF)
Metric Full Name Energy Reuse Effectiveness
Metric Short Name ERE
Metric Category Energy Recovered: Heat Recovered
Metric Description Measures the benefit of reusing any recovered energy from the data centre
Metric Category Leader Vasiliki Georgiadou (GEYSER / Green IT Amsterdam)
Developing partners Artemis Voulkidis, Alexis Aravanis (DOLFIN / Synelixis), Piotr Sobonski, Susan Rea, Christopher Burge (GENiC / CIT), Philip Inglesant (RenewIT / 451 Research)
Reviewing partners Fabrice Roudet ( GreenDataNet / Eaton), Milagros Rey Porto, Silvia Sanjoaquín Vives, Eduard Naranjo Cardoso (DC4Cities / GNF), Paul Hughes (GEYSER / ABB), Marco Cupelli (GEYSER / RWTH)
6
Contents 1 Introduction .............................................................................................................................................................. 8
2 Task 4.1 - Methodologies for existing Metrics .......................................................................................................... 9
2.1 Power Usage Effectiveness (PUE) ..................................................................................................................... 9
2.2 Renewable Energies Factor (REF) ................................................................................................................... 11
2.3 IT Equipment Energy Efficiency (ITEE) ............................................................................................................ 12
2.4 Cooling Effectiveness Rate (CER) .................................................................................................................... 12
2.5 Energy Reuse Effectiveness (ERE) ................................................................................................................... 14
2.5.1 M & V Plan Scope and Metric Overview ................................................................................................. 14
2.5.2 Measurements ........................................................................................................................................ 15
3 Task 4.2 – Methodologies for new Metrics............................................................................................................. 24
3.1 Adaptability Power Curve ............................................................................................................................... 24
3.1.1 M & V Plan Scope and Metric Overview ................................................................................................. 24
3.1.2 Measurements ........................................................................................................................................ 25
3.1.3 Example ................................................................................................................................................... 28
3.2 Adaptability Power Curve at Renewable Energies .......................................................................................... 29
3.2.1 M & V Plan Scope and Metric Overview ................................................................................................. 29
3.2.2 Measurements ........................................................................................................................................ 29
3.2.3 Example ................................................................................................................................................... 32
3.3 Data Centre Adapt .......................................................................................................................................... 33
3.3.1 M & V Plan Scope and Metric Overview ................................................................................................. 33
3.3.2 Measurements ........................................................................................................................................ 34
3.3.3 Example ................................................................................................................................................... 37
3.4 Primary Energy Savings ................................................................................................................................... 38
3.4.1 M & V Plan Scope and Metric Overview ................................................................................................. 38
3.4.2 Measurements ........................................................................................................................................ 39
3.4.3 Example ................................................................................................................................................... 44
3.5 CO2 Avoided Emissions.................................................................................................................................... 45
3.5.1 M & V Plan Scope and Metric Overview ................................................................................................. 45
3.5.2 Measurements ........................................................................................................................................ 47
3.5.3 Example ................................................................................................................................................... 48
3.6 Economic Saving in Energy Expenses (EES) ..................................................................................................... 49
3.6.1 M & V Plan Scope and Metric Overview ................................................................................................. 49
3.6.2 Measurements ........................................................................................................................................ 52
7
3.6.3 Example ................................................................................................................................................... 54
3.7 Grid Utilization Factor ..................................................................................................................................... 55
3.7.1 M & V Plan Scope and Metric Overview ................................................................................................. 55
3.7.2 Measurements ........................................................................................................................................ 56
3.8 Analysis & Verification .................................................................................................................................... 60
3.8.1 Error Filtering .......................................................................................................................................... 60
3.8.2 Statistical Analysis of Baseline models .................................................................................................... 61
3.8.3 Uncertainty analysis of the results achieved .......................................................................................... 61
3.9 Reporting ......................................................................................................................................................... 64
3.9.1 Reporting format ..................................................................................................................................... 64
3.9.2 Reporting frequency ............................................................................................................................... 64
4 References .............................................................................................................................................................. 65
8
1 Introduction
The standardization activities performed so far in the context of the Smart City Cluster collaboration have led to the
identification of appropriate methodologies and procedures for the calculation of new and existing metrics or Key
Performance Indicators (KPIs). Thus, allowing the standardization of procedures to the extent possible and the
determination of common baselines for the efficient comparison of Cluster projects and the aggregation and
comparison of common variables and metrics, conflating seamlessly input from all Cluster constituent projects.
The projects included in the cluster, as already detailed in section 1 of Task 3 are the following: All4Green,
CoolEmAll, GreenDataNet, RenewIT, GENiC, GEYSER, Dolfin and DC4Cities. Moreover, since April 2015 a new project
has joined the cluster, EURECA. Every one of the above projects focuses on different goals and objectives,
quantifying the performance of the involved systems by measuring different events. Hence, the comparison of the
obtained measurements requires the definition of common variables and metrics to compare results in the same
way.
In this course, Task 3 proposed new metrics based on the existing ones improving their performance. In particular,
Task 3.1 identified existing metrics that could be employed in the context of Cluster, whereas Task 3.2 built upon the
current metrics to define new for measuring concepts as e.g. the exploitation of RES and the flexibility of DCs to
adjust their energy consumption and Task 3.3 defined new metrics for measuring the performance of DCs.
However, in the direction of defining common methodologies for the measurement of common KPIs toward a
collective standard development, Task 4 focused on the definition of common measuring and verification
methodologies. Specifically, Task 4.1 presented measuring and verification methodologies for existing metrics which
are almost finalized by standardization bodies (e.g. ISO/IEC JTC 1/SC 39), using the quasi-finalized metrics as
common basis for comparison. In addition, Task 4.2 presented measuring and verification methodologies for new
metrics defined in Cluster activity Task 3.2.
The measuring and verification methodologies defined in Task 4 are compliant with the International Performance
Measurement and Verification Protocol (IPMVP). The IPMVP is a protocol developed by a consortium of
international organizations, defining standards for energy efficiency projects. Capitalizing on the success of IPMVP,
Task 4 determines measuring and verification methodologies fully in line with the successful and pervasive
methodologies of IPMVP, giving rise to a coherent Cluster protocol, allowing for the efficient comparison of Cluster
projects and the exploitation of registered measurements toward amalgamation of feedback and the emergence of a
holistic approach allowing the drawing of common Cluster conclusions.
However, a fully developed strategy on how to deal with the data gathered, stored, and analysed for the purpose of
computing, reporting, and potentially auditing the related metrics is out of scope of this cluster's goals and activities.
As such, each case would need to be handled on an ad-hoc basis, depending also on the data management systems
already in place. After the validation phase completes - see also Task 6 - the basic outline and guidelines of such a
plan will be designed and presented.
9
2 Task 4.1 - Methodologies for existing Metrics
As already mentioned above, the purpose of Task 4.1 was to take a subset of the metrics already selected by the
Smart Cities DC Cluster during Task 3 and propose measurement methodologies. Specifically, metrics defined outside
of the cluster were selected for Task 4.1. Hence, the work for this task involved considering methodologies already in
existence for these metrics, selecting those deemed most suitable for use by the cluster and, where appropriate,
extending known methodologies.
For the following Task 4.1 metrics, PUE, REF, ITEE, CER and ERE, the first three avail of existing work provided by
ISO/IEC JTC 1/SC 391, with the methodologies for the other two being discussed below.
2.1 Power Usage Effectiveness (PUE)
ISO/IEC JTC 1/SC 39 are close to finalizing the PUE metric (ISO/IEC JTC 1/SC 39 PUE, 2015). After careful
consideration, this has been selected as the Cluster methodology for measuring PUE. However, some considerations
and comments to the draft documents have been addressed by the Cluster using ISO/IEC templates through the
French Committee. It should be noted that this feedback was provided outside the normal request process and is as
follows:
Member Body Location Paragraph/Figure/
Table/Note Comment Type Justification
Proposed Change
FRO 52 Introduction ED Sentence not clear cancel ‘’it is’’ and to replace by ‘’, there are’’
IREC Line 220 Section 5.1 ED EDC is already defined in section 3.1.8. The use of “Total facility energy” also introduces confusion
Change to “Total data centre energy is defined in section 3.1.8”
IREC Line 225 Section 5.1 ED The IT equipment energy is already defined in section 3.1.2
Delete the final sentence in the paragraph about IT energy consumption
IREC Line 226 Section 5.1 ED Refer to Annex B in case that different energy carriers are energy sources to data centre. No reference to Annex B in the main part of the document
Add “In case that various types of source energy or on-site generation systems are serving the data centre, refer to Annex B for PUE calculation”
IREC Section 6.2.2 TE Section only refers to Meter and Measurement requirements in case of electricity. If other energy carriers are used (gas, chilled water, etc..) other kind of metering systems would be required.
IREC Line 556 Annex B. Section B.1 TE The sentence “Since PUE is not a metric to identify the efficiency of how electricity is
Change to “Since PUE is
not a metric to identify
the efficiency of how
1http://www.iso.org/iso/home/standards_development/list_of_iso_technical_committees/iso_technical_committee.htm?com
mid=654019
10
brought to the data centre, it is a metric to identify how efficient the electricity is used” is a clear contradiction with other ways of defining PUE in the document, as for example, section 3.1.4 or section 5.1 where clearly states that total data centre energy considers the total energy needed for the data centre facility
energy is brought to
the data centre, it is a
metric to identify how
efficient energy is used
within the data centre
boundaries”
IREC Annex B. Section B.1 TE A figure defining the data centre boundaries and energy flows through the boundaries and a formula for the calculation of PUE using different energy carriers will help to clarify calculation of PUE
A figure similar to
Figure 4.3 in document
“Metrics for Net Zero
Energy Data Centres”
from the RenewIT
project (attached) or a
similar one can help.
See additional document named “PUE equations” for suggested equations and references to energy conversion factors
IREC Example Data Centre C, starting line 589
Annex B. TE To be coherent, the energy source entering the data centre boundary is natural gas. So, assuming electrical energy efficiency in the generator of 32%, natural gas consumption will be 15,625 kWh.
See document “PUE equations”
IREC Example Data Centre D Annex B TE To be coherent, the energy source entering the data centre boundary is natural gas. So, assuming a electrical energy efficiency in the generator of 32%, natural gas consumption will be 7,812.5 kWh.
See document “PUE
equations”
Figure and formulas need to be changed
IREC Example Data Centre E Annex B TE Example A and Fig. B-5 can be eliminated to avoid confusion
Delete Example A and
Fig. B-5.
For calculation in
Example B, Method 2;
see document “PUE
equations”
IREC Example Data Centre with abosortion type refrigerator
Annex B TE Example A and Fig. B-7 can be eliminated to avoid confusion
Delete Example A and
Fig. B-7
For calculation in Example B, Method 2; see document “PUE equations”
IREC Annex B TE I would suggest adding an example with on-site PV generation to
A proposal of simple example is added in the document “PUE
11
show how to calculate PUE in that case.
equations”
2.2 Renewable Energies Factor (REF)
ISO/IEC JTC 1/SC 39 are close to finalizing the REF metric (ISO/IEC JTC 1/SC 39 REF, 2015). After careful consideration,
this has been selected as the Cluster methodology for measuring REF. Some considerations and comments to the
draft documents have been addressed by the Cluster using ISO/IEC templates through the French Committee. It
should be noted that this feedback was provided outside the normal request process and is as follows:
Member Body
Location Paragraph/Figure/
Table/Note Comment
Type Justification Proposed Change
GNF 5.1 Line 146 TE Renewable energy owned and controlled by a data centre is defined as any energy for which the DC owns the legal right to the environmental attributes of renewable generation, which includes for the reporting period in question:
- Renewable generation
onsite, whose legal
rights are retired in the
DC.
- Renewable energy
certificates.
- Renewable energy
portion of utility
electricity, which shall
be counted, provided
the data centre has
obtained documented
written evidence from
the source utility
provider(s) that the
energy supplied, for the
reporting period in
question, complies with
the ISO/IEC definition of
renewable energy
described in clause
3.1.2.
Justification for change: REF considers renewable energy consumed in the DC according to the renewable energy certificates that can be obtained from the DC energy supplier or from the market. Using this procedure, Er (Renewable energy used by the DC) is not a real value, since renewable energy is probably not being to be consumed in the DC. We understand that with this approach there is a partially responsibility transmission to a third party (REF): certificates do not guarantee that the DC is consuming less non-RES
Renewable energy is defined as any energy for which the DC for the reporting period in question as:
- Renewable generation onsite,
which is consumed in the DC.
- Renewable energy portion from
the grid, which shall be provided
by the energy supplier,
documenting written evidence
that the energy supplied, for the
reporting period in question,
complies with the ISO/IEC
definition of renewable energy
described in clause 3.1.2.
12
energy; this energy can be supplied to any other consumer.
GNF 6.1 Line 168 TE “REF shall be an annualized value.”
Justification for change:
We agree that REF shall be an annualized value, to consider seasonal changes from the supply and demand side point of view. However, it is important not to use aggregated values, but to evaluate within the KPI. Seasonal, monthly, daily and even hourly generation may differ a lot from other time scenarios.
“REF shall be an annualized value, and shall be calculated as a summation of the usage of renewable energies in the different time intervals, as it can be seen in the formula.”
Where:
- EDC grid-cons i = DC energy consumption from the grid during the period of time i (kWh).
- Eren i/ Etot i = Renewable energy portion from the grid (provided by the energy supplier) in the period i (kWh).
- EDC ren onsite i = DC energy consumption from own renewable energy production in the period of time i (kWh).
- EDC i = Total amount of energy that is consumed by the DC during the period i (kWh).
Time interval considered for each i period will depend on the degree of granularity, with which energy supplier can provide renewable energy portion from the grid (hourly, monthly, etc). Level of granularity will normally depend on the regulation established to energy suppliers for informing their customers.
2.3 IT Equipment Energy Efficiency (ITEE)
ISO/IEC JTC 1/SC 39 are close to finalizing the ITEE metric (ISO/IEC JTC 1/SC 39 ITEE, 2015). After careful
consideration, this has been selected as the Cluster methodology for measuring ITEE.
2.4 Cooling Effectiveness Rate (CER)
ISO/IEC JTC 1/SC 39 have just begun work on the CER metric and so this work is in early stages. The ISO/IEC 30134
(provisional) CER definition, discussed in the Cluster Task 3 documentation, has been selected as the Cluster
methodology for measuring REF. Some considerations and comments to the draft documents have been addressed
by the Cluster using ISO/IEC templates through the French Committee. It should be noted that this feedback was
provided outside the normal request process and is as follows:
Member Body
Location Paragraph/Figure/
Table/Note Comment
Type Justification Proposed Change
IREC 1 Scope GE As the CER is intended to
determine the performance of
the cooling system of a Data
13
Centre, one should define
which systems are included in
the definition of “the cooling
system” or “the cooling
infrastructure”. In section
6.1.1 (“requirements”), it is
stated that pumps, valves,
etc.. are included in all the
system. It is necessary to
clarify which kind of systems
are included as “cooling
infrastructure”, for example, if
water-chilled distribution
systems, air handling units, air-
cooled distribution systems,
buffer storage tanks, cooling
production machines (e.g,
vapor compressor chillers,
chillers, heat pumps,
absorption chillers, etc…)
Also, it is important to clarify
which are the limits of the
“cooling infrastructure” in the
production side. Some
examples can be given and
discussed. For example:
In the case of a gas
fired absorption
chiller, is the boiler
part of “the cooling
system”?
In the case of a
Data Centre
connected to a
District Cooling
network, is “the
cooling system”
starts at the
substation
connection system
with the network?
Are energy
renewable
production systems
integrated in the
Data Centre
technical systems
(e.g. PV solar or
solar thermal
systems)
considered part of
“the cooling
systems”?
IREC 3.1.1 Line 89 TE Use the same name “Cooling Efficiency Ratio” to define both the “instantaneous / actual” measurement and the ratio over a period of time (seasonal)
Seasonal Cooling Efficiency Ratio (SCER)
IREC 3.1.2 Line 92 TE Use the same name “Cooling Efficiency Ratio” to define both the “instantaneous / actual” measurement and the
Cooling Efficiency Ratio (CER)
14
ratio over a period of time (seasonal)
IREC 5.3 Line 144 TE Definition of SCER
IREC 5.3 Line 146 TE Units should differentiate thermal energy and electrical energy
But in kWhth/kWhel
IREC 5.3 Equation 2 TE Mathematical notation with integral notation and units
IREC 5.4 Line 150 TE Definition of CER
IREC 5,4 Line 151 TE Change COP by EER …into the direction of a EER for cooling infrastructure.
IREC A.3 Line 273-276 TE It is stated that infrastructure to distribute heat in a building is not considered as a part of the data centre (and then, not part of the cooling infrastructure either). But, within the following sentence, it is stated that energy to transfer heat out of the Data Centre shall be accounted. Better explanation or clarification is needed.
IREC A.4 Line 278 TE Change CPR by CER Using CER in Capacity Management
IREC TE In relationship with first general comment, an example of a non-electrical driven (or partially non-electrical driven) cooling system, (i.e. a gas fired absorption chiller) should be provided. For these cases, an equivalent electrical CER can be defined considering the performance of thermal driven cooling machines, performance of thermal generators and conversion factor between the energy carrier and electricity.
Add some example of non-electrical driven cooling system
2.5 Energy Reuse Effectiveness (ERE)
In contrast with other metrics of this category presented thus far, and to the best of our knowledge, there is
currently no ISO/IEC JTC 1/SC 39 dedicated to this metric. As such and for the purposes of this Cluster, in the
following we consolidate information related to this metric in our effort to improve its feasibility and applicability by
our project’s validation pilots.
2.5.1 M & V Plan Scope and Metric Overview This section describes in detail the Energy Reuse Effectiveness (ERE) metric, as initially suggested by The Green Grid
(The Green Grid, 2010). As stated in the white paper that introduced the metric, its goal is to capture and measure
the benefit of reusing any recovered energy from the data centre. In terms of applicable use cases, the focus lies on
heat reuse.
It should be noted that this metric focuses on energy being captured from within the data centre and reused outside
of its premises, since the benefits of reusing energy within the same data centre are captured by the Power Usage
Effectiveness (PUE). Computing and analysing both metrics can thus provide better insights into the data centre’s
energy recovering strategies in terms of both capabilities and opportunities.
15
Its formula, following the same line of thought as in the case of PUE (ISO/IEC JTC 1/SC 39 PUE, 2015), is defined as
follows:
(1)
As reused energy is essentially in the form of heat, energy source weighting factors should be applied. Section
2.5.2.1 provides details on such factors.
All values are units of energy, while the metric itself is just a number ranging from 0 to infinity. A value of 0 means
that 100% of the energy brought into the data centre is reused elsewhere, outside of the data centre boundaries.
One should therefore imagine a boundary line that defines the data centre’s co-called Control Volume (CV), the area
enclosing all data centre facilities and support infrastructure. For the purposes of this metric, energy crossing this
line should be accounted for. For an illustration of the CV concept, you can refer to section 2.5.2 of this document,
where a typical scenario is outlined in detail.
There is an alternate formula to compute the ERE metric based on PUE while introducing the Energy Reuse Factor
(ERF) as the portion of energy that is exported for reuse outside of the data centre. Its formula is defined as follows:
(2)
Equation (1) can be thus expressed as:
(3)
with ERF lying within [0,1]. A value of 0 means no energy is being exported from the data centre for reuse, while a
value of 1 means that the amount of energy brought into the data centre equals to the amount that is being reused
outside of the data centre. For more background information on this metric please refer to the (The Green Grid,
2010) whitepaper; a concise description of the ERF is also found within the report on harmonizing global metrics for
data centre energy efficiency (Global TaskForce, 2014).
For all intents and purposes of this document, definitions pertaining to commonly used terms are those specified
within ISO/IEC JTC 1/SC392 documents, unless otherwise explicitly stated. In addition, parameters of this metric
already defined and evaluated in the aforementioned documents, such as PUE and total energy consumption, are
measured and computed following the same methodology.
In the following we elaborate further on measurement specifications special to this metric and in particular related
to energy being reused, and provide concrete steps to analyse, validate, and report its values.
2.5.2 Measurements
2.5.2.1 Measurable variables determination
In order to compute a value of the ERE metric, provided that the corresponding PUE value is known, one just needs
to measure the energy that is being reused outside of the data centre. In this case the total energy consumption of
the date centre facility is assumed to be known, being one of the parameters necessary to compute the PUE.
2http://www.iso.org/iso/home/standards_development/list_of_iso_technical_committees/iso_technical_committee.htm?com
mid=654019
16
Figure 1 illustrates a typical scenario of reusing recovered heat from the data centre. In this example, the total
energy consumed by the data centre is measured at the Point of Delivery (POD) and assuming negligible
transmission losses this would be the sum of energy coming from the grid, A, plus energy that may be produced and
consumed onsite, B. Assuming the latter represents electricity generation on site, it is proposed to include the
quantity of electricity, measured at B, and not the source energy associated with the generation. This can be
considered as drawing the CV to exclude generation onsite, however the units may also function as standby
generation capacity, in which case they should be included, for the purposes of heating, parasitic load, and so on.
The joint Green Grid and ASHRAE publication on PUE (The Green Grid / ASHRAE, 2013) excludes generator efficiency
effects by introducing an additional internal IT Source factor for IT electricity; we propose a simpler method of
metering the energy generated and adding it to the energy taken from grid so as to get the total energy input.
In this example, the PUE3 would then be computed as:
(4)
Figure 1: Reuse of recovered heat from the data centre
Heat recovered by the data centre, H, may represent either hot air or water that is being fed into a heat pump and
further used by an external facility such as a nearby greenhouse, or the local/district heating grid. Based on ERF’s
definition by Equation (2), its value would then be:
(5)
with denoting the energy source weighting factor.
3 In this example, we assume the more advanced PUE category (3), where the IT load is measured at the IT equipment input.
17
All units are in kWh since the majority of data centres operate on electricity; as explained in detail within the report
(Global TaskForce, 2014), the energy from each energy type should first be converted into kWh, then multiplied by
the weighting factor for the type, and finally the source energy for all types can be added together. Table 1 lists the
global average weighting factors per (typical) energy type, which may be used when more exact regional values are
not available4.
4 As of writing, the factors reported within In order to compute a value of the ERE metric, provided that the
corresponding PUE value is known, one just needs to measure the energy that is being reused outside of the data
centre. In this case the total energy consumption of the date centre facility is assumed to be known, being one of the
parameters necessary to compute the PUE.
Figure 1 illustrates a typical scenario of reusing recovered heat from the data centre. In this example, the total
energy consumed by the data centre is measured at the Point of Delivery (POD) and assuming negligible
transmission losses this would be the sum of energy coming from the grid, A, plus energy that may be produced and
consumed onsite, B. Assuming the latter represents electricity generation on site, it is proposed to include the
quantity of electricity, measured at B, and not the source energy associated with the generation. This can be
considered as drawing the CV to exclude generation onsite, however the units may also function as standby
generation capacity, in which case they should be included, for the purposes of heating, parasitic load, and so on.
The joint Green Grid and ASHRAE publication on PUE excludes generator efficiency effects by introducing an
additional internal IT Source factor for IT electricity; we propose a simpler method of metering the energy generated
and adding it to the energy taken from grid so as to get the total energy input.
In this example, the PUE would then be computed as:
(4)
Figure 1: Reuse of recovered heat from the data centre
18
Table 1: Global average source energy weighting factors (Source: (Global TaskForce, 2014))
Energy type Weighting factor
Electricity 1.0
Gas (Natural gas) 0.35
Fuel oil 0.35
Other fuels 0.35
District chilled water 0.4
District hot water 0.4
District steam 0.4
As already implied by the discussion so far, this metric is data centre centric. In this sense, therefore, one does not
need to include in the computations pertaining to this metric the waste as a result of heat reused by the external
facility, J. That being said, one should ensure in advance that the business case for reusing recovered energy outside
the data centre’s premises is economically viable and environmentally sustainable: the resulted system’s total
energy consumption should be less when reusing energy.
In the remainder of this section we provide details on measurement points, metering equipment and assumptions,
along with guidelines on how to adequately identify a baseline scenario and possibly necessary adjustments. The
latter would be as part of the exercise to better capture, understand and analyse the energy recovered strategies
put in place along with opportunities for further improvements.
2.5.2.2 Baseline identification and calculation
To compute ERE no baseline identification is needed. However, an important step towards assessing the added value
of energy recovered from the data centre involves comparing the metric’s values between two different periods of
time. Such a comparison would then be made between the value over the period before implementing the measures
to recover energy, namely baseline, and the period following once improvements have been applied.
Baseline scenario must be representative of a typical operational period, normally being a year as thermal needs are
seasonal. Therefore, the base-year conditions refer to the knowledge base of the state of various data centre aspects
Heat recovered by the data centre, H, may represent either hot air or water that is being fed into a heat pump and
further used by an external facility such as a nearby greenhouse, or the local/district heating grid. Based on ERF’s
definition by Equation (2), its value would then be:
(5)
with denoting the energy source weighting factor.
All units are in kWh since the majority of data centres operate on electricity; as explained in detail within the report,
the energy from each energy type should first be converted into kWh, then multiplied by the weighting factor for the
type, and finally the source energy for all types can be added together. Table 1 lists the global average weighting
factors per (typical) energy type, which may be used when more exact regional values are not available.
Table 1 are in line with industry normal values, defined by The Green Grid, and due for inclusion in an updated version of the ERE definition document. It should be noted, however, that other European directives, particularly the Energy Performance of Buildings Directive (EPBD), utilise a different format, termed Primary Energy Factors. Whereas source energy factors use grid electricity as the base unity value (=1), primary energy factors use fossil fuel = 1, with electricity varying depending on grid electricity makeup.
19
during 12 months preceding the decision to deploy and use energy reuse infrastructure. In order to evaluate the
benefits of heat recovery, or changes to heat recovery, it is necessary to establish a baseline. This will require
gathering data over a range of operating conditions: IT loading, ambient weather conditions (seasonal variation) and
heat sink variations in load, temperature and flow, which is representative of the intended operating envelope.
Ideally this would involve at least 12 months with stable operating loads; in practice this may be difficult to attain
and a pragmatic approach should be adopted. For example, where heat recovery is considered beneficial during the
winter months only (heating season), then data from September – April may be considered adequate.
In the following, we divide this knowledge set into two categories, one pertaining information critical to enabling
accurate identification of the data centre’s baseline conditions and a second one, related to information that could
prove to be useful for enabling more fine-grained baseline identification, however affecting only slightly the resulting
baseline profile.
Collection and analysis of such data may allow us to compare variations in the ERE metric between these two
periods of time, eliminating to the degree possible the distortion effect on energy consumption introduced by such
variations – as already discussed in section 2.5.2.3.
The underlying assumption is that a data centre operator will normally be familiar with the main parameters that
affect data centre energy consumption. A detailed, orientative list is presented below, including the most common
parameters that relevantly affect data centre energy consumption, which would be mandatory to collect:
Electrical meter data, preferably for short time intervals (between 15 minutes and 1 hour, being every 30
minutes a good approach) for all factors necessary for PUE, ERE, and ERF calculation
Heat flow data across control volume: Medium, Humidity (for air), Flow, and Flow and Return Temperatures
Temperatures of IT Whitespace (CRAC/CRAH inlet and delivery) and Ambient and Heat sink
Confirmation that there has been no significant change in cooling plant configuration or operating
philosophy over the baseline period
A lighting levels investigation
A detailed report on the number and (static) energy characteristics of IT equipment (both for computing,
networking, and storage purposes) along with the respective energy consumption measurements, wherever
available
A detailed report on the number, and (static) energy characteristics of non-IT equipment (HVAC, lighting, and
so on) along with the respective energy consumption measurements, wherever available
A record of the temperature setting of cooling equipment
A report of the number, type and (static) energy characteristics of energy-reuse devices
A record of the number of working days and hours for each month of the year
A summary of detailed weather and climatic data for each month of the year
A report on the number, type, position and error of metering devices
A record of energy-efficiency techniques in place
In addition to these fundamental sets of data, the following pertain to information that could prove to be useful for
fine-tuning the data evaluation for the baseline identification if available, but are considered as too costly or too
hard to obtain;
More fine-grained reports regarding IT consumption behaviour of the various fundamental IT equipment
elements (CPU, RAM, HDD, Routers, Switches). In case a DCIM is used for monitoring and controlling the DC,
this information will most probably be available and should be used to identify the baseline.
20
More fine-grained reports of the components of the HVAC equipment (air conditioning, heating, lighting,
and so on) if the installation of a sufficient number of meters is not considered too costly, or a monitoring
framework is in place.
Bearing in mind the connection of this metric to PUE, for the aforementioned measurable entities, the sampling
period for measurements pertaining to dynamic parameters should be the same for both metrics. The base-year
energy use is metered at POD of Figure 1 spanning at least a 12-month period5. The base-year energy reuse is
metered at point H of Figure 1 spanning the same period as the one defined for the case of base energy use.
The base-year energy data should be analysed as follows. A mathematical model (e.g. linear regression) shall be
applied on representative period energy use and demand, IT load, metering period length, and degree days. The
latter shall be derived by third party information providers. Correlation of weather with energy demand, supply and
use is expected to be identified.
Benefits along with potential improvements derived from energy reuse will be determined under post-retrofit
conditions.
2.5.2.3 Baseline adjustments in case of anticipated changes
Baseline adjustments are needed to bring base-year energy use to the conditions of the post-retrofit period. The
method to measure and verify should be broadly in accordance with IPMVP Option C. Nevertheless, since formula (3)
is suggested to be used, then and bearing in mind that we measure PUE (IT energy consumption), the IPMVP Option
will be a mix of C and B.
2.5.2.3.1 Routine Adjustments
2.5.2.3.1.1 Electricity Consumption
At least, the electricity consumption is expected to be affected by the number of operating days and the weather. As
result, the following routine adjustments are normally needed:
The cooling equipment consumption may vary depending on the ambient temperature. Appropriate
adjustments should be made, based on manufacturer’s sheets.
The electricity consumption of air-conditioning and heating facilities should be adjusted to ambient
temperature based on manufacturers’ specifications.
2.5.2.3.1.2 Thermal Energy Waste
The waste heat may be used either to “heat” or “cool” external facilities. Adjustments on thermal energy waste may
be needed with respect to the number of operating days and hours, as well as the ambient temperature. Such
adjustments may be conducted following the specifications of the IT equipment manufacturers.
2.5.2.3.2 Electricity Demand
Adjustments on electricity demand may be needed, since the ambient temperature and daylight hours affect the
cooling, heating and lighting demand within the data centre.
In the cases that IT services offered to the customers have a relevant variation from year to year adjustments should
be applied.
2.5.2.3.2.1 Thermal Energy Demand
N/A
5 Ideally, integral multiples of 12-month periods (12, 24, 36 months, and so on) should be considered, in order to alleviate the
effects of seasonal DC workload variations.
21
2.5.2.3.3 Non-routine Adjustments
Procurement of new equipment during the post retrofit period raises the need for non-routine adjustments. The
new equipment may refer to IT (CPU, RAM, HDD, and networking devices), non-IT (cooling equipment), and facilities
(air-conditioning units, heating, and lighting). The adjustments should include calibrating the potential extra energy
consumption to the base-year one, referring to manufacturers’ factsheets on energy consumption.
2.5.2.4 Measurement boundaries determination & metering points
As already mentioned for this metric, being data centre centric, is not within scope to take into account whether an
equipment outside of the data centre’s premises is efficient or not. To that end, Coefficient of Performance (COP) of
external to the data centre heat pumps should not be considered. The energy reused should be measured exactly at
the point where it leaves the CV of the data centre. Nevertheless, the system’s total energy consumption should be
less when reusing energy.
On the other hand, cases where waste heat may be used, internally, to preheat generators for data centres
electricity production is also out of scope of ERE. In addition, electrical energy stored onsite for later use, including
possibly provision to external facilities, is considered out of scope of this metric, since stored energy is already
accounted for when measured at POD and in this context cannot be considered energy recovered.
2.5.2.4.1 Total energy consumption
Both the base-year and post-retrofit energy use for Equation (3) is taken directly from the metering equipment at
POD of Figure 1 without adjustment. Same guidelines as the ones related to PUE computation are to be followed.
2.5.2.4.2 Energy Reuse
Similarly both the base-year and post retro-fit energy reuse for Equation (3) is taken directly from the metering
equipment at point I of Figure 1 without adjustment.
2.5.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
Metering equipment should be able to track kWh from the desired circuit.
The output from the main metering options should be made available on a web portal for ease of use and for easy
dissemination of information.
The data capture can be from:
existing ‘micro’ meters already in situ where the data is sent via the communication unit to the web portal;
new CT clamps on wiring linked to communication unit which will feed the web portal; and
temporary data loggers with CTs around specific circuit wiring and data caught locally and then uploaded.
2.5.2.6 Metering equipment commissioning procedure
2.5.2.6.1 Electricity
The DC circuitry should be fully analysed.
A plan of what circuits to be measured should be assembled.
In order to ascertain the most basic KPI (EnPI), PUE, and continuing with the assumption of the more advanced PUE
category, a meter is required at POD and at (G), the latter denoting the point of measurement for the energy
consumed by the IT equipment6, as shown in Figure 1. Additional metering will add to the complexity of data
obtained and help with the other KPIs.
6 For details on PUE measurement, please refer to (ISO/IEC JTC 1/SC 39 PUE, 2015).
22
It may be necessary to change some circuitry so that all the cooling, say, is captured on the one meter. If this is not
possible, then a schematic of the system should be drawn up and additional meters placed so as to capture all of the
necessary data for that specific energy use. Careful consideration must be taken so that energy is not missed nor
counted twice as this will cause significant problems with calculations.
2.5.2.6.2 Thermal
It will be necessary to capture the quantity, namely the volume, and quality, the temperature, of air being exhausted
or water being transferred. As such, meters other than kWh will have to be employed.
Flow meters will be necessary to calculate the volume. These will produce an output that should be captured by the
main monitoring system and sent via the communication unit to the web-portal.
In addition to the volume, the temperature of the air (both inside the data centre and ambient external) or the
water, will have to be captured. In particular, for water systems flow and return temperatures will be required.
In addition, one should record ambient temperature, air exhaust from data centre, and temperature of heated space
or district heating circuit.
Again, this information should be captured by the main data-capture system and sent via the communication unit to
the web-portal.
2.5.2.7 Metering assumptions
Energy lost through the fabric of the building is ignored and not measured. Steps to minimise these should be taken,
but not measured.
Capture of the quantity of air and its temperature will allow the calculation of the energy that the air contains. It will
be necessary to elaborate how this should be done.
2.5.2.8 Metering sampling frequency
The data sampling frequency should facilitate calculations to give an accurate picture of the energy use in the data
centre. If the data centre energy use and processing speeds are very constant, then low sample rates may suffice.
However, if very rapid changes are observed, then a higher sampling rate may be required.
For example, in the data centres that Google operate, they collect these types of data every second. As such they
have 86,000 data points for every meter every day. This level may be too fine for some applications.
However, hourly data points may be too coarse. So a suitable medium position may be required.
A sample rate of, for example, between every 30 seconds and every 10 minutes will probably allow a good data set
from which to first start. Adjustments up or down from this may be necessary after the first tranche of data is
analysed. In general, sampling frequency should not be too short so as to avoid noise from actions of control
systems. Aggregating to periods of 1 hr or 1 day for modelling and metric calculation could be a good compromise.
Typical values of sample rate per parameter are listed in Table 2.
Table 2: Typical values of sample rate per parameter.
Level of Granularity Parameter Interval (min*)
Server room (non – IT)
Air temperature 5 – 10
Chilled water flow rate 0.5 – 1
Chilled water temperature 5 – 10
Relative humidity 5 – 10
Server room (IT) CPU utilisation % 0.5 – 1
23
Networking utilisation7 % 0.5 – 1
Storage utilisation8 % 0.5 – 1
Server room exit Air flow rate 0.5 – 1
Air temperature 5 – 10
Electricity
Main incomer 0.5 – 10
UPS 0.5 – 10
Server room incomer 0.5 – 10
General Degree days cooling 1 day
Outside dew point 1 hour
2.5.2.9 Metering duration (post-retrofit period)
The duration of the measurement should be at least over 12 months, or at least encompass both summer and winter
conditions. This will allow the analysis over a full cooling (and heating) season.
It will be preferable to allow 3 full years of data to show any annual trends. This will give a more robust result of the
system.
7 Current switching throughput / Max switching throughput
8 ((used storage capacity/maximum storage capacity) + (data transfer/max data transfer capacity))/2
24
3 Task 4.2 – Methodologies for new Metrics
The purpose of Task 4.2 was to define methodologies for new metrics selected by the Smart City Cluster
Collaboration during Task 3. Hence, the work for this task involved considering methodologies most suitable for use
by the cluster and extending known methodologies.
The methodologies hereby defined should be viewed as a first attempt in tackling the introduction of such a global,
environmental family of metrics for the data centre. As such, the document describes the proposed approach simply
as a step-by-step guideline the data centre operator may follow to measure the necessary parameters for computing
the selected metric(s). The project-members of the cluster will put this approach into practice during their pilot
trials. In doing so, insights will be obtained to refine the proposed methodology as necessary.
Metrics within Task 4.2 are classified into three categories:
Flexibility Mechanisms in Data Centres - Energy Shifting, including metrics such as Adaptability Power Curve
(APC), Adaptability Power Curve at Renewable Energies (APC_REN), and Data Centre Adapt (DCA)
Savings family of metrics including Primary Energy Savings (PE Savings), CO2 avoided emissions (CO2
Savings), and Energy Expenses (EES),
Renewables integration - Energy produced locally and Renewable usage with the Grid Utilization Factor
(GUF) metric.
3.1 Adaptability Power Curve
3.1.1 M & V Plan Scope and Metric Overview
The present section is aimed to provide the measurement and verification methodology for the APC metric, following the International Performance Measurement and Verification Protocol (IPMVP).
The APC metric belongs to the category of “Flexibility mechanisms in Data Centres: Energy shifting”, presented in “Cluster Activities Task 3” document (§2.2.1).
This metric assumes that an energy usage pattern is in place, to which the data centre must adapt to the greatest extent possible. The energy plan may be provided by an Energy Managing Entity within the Smart City or the Smart grid or by the DC itself, as a result of self-optimization policies. APC aims at measuring the degree of adaptation of the DC energy consumption to a planned energy curve.
APC is given by the following formula:
(1)
(2)
Where:
is the DC energy consumption in kWh;
is the planned energy in kWh;
is the individual time period
represents the sample size and
is the adjustment factor between and normalising the two energy consumption curves.
25
To specify better, the a priori defined cannot take into account possible changes in current conditions and the incurring variations in current . To eliminate the effect of these variations on the metric performance scales the planned energy at the level of the energy consumption , i.e. the two curves must subtend the same area in order to have the same total energy and be therefore comparable.
As derived from eq. (1), APC values are unit-less where 1.0 corresponds to full adaptation. The lower the adaptation between both curves is, the lower the value achieved for APC (very different curves can cause even APC negative values). In order to calculate the APC values, the planned and actual DC energy usage have to be provided; the former is calculated or provided, while the latter is measured.
3.1.2 Measurements
3.1.2.1 Measurable variables determination
According to the formula aforementioned, the only parameter to be measured is the total energy consumption of
the data centre for each time interval in kWh. More information on the selected timeframe and the baseline
scenario is found within sections 3.1.2.2 and 3.1.2.3. For details on measurement points please refer to section
3.1.2.4.
is not measured, as its values are predetermined by the DC management or some other entity. and are
energy consumptions produced at the same time (simultaneous), i.e. is the energy consumed by the DC after
trying to adapt its consumption to the demand order (
It must be noted that, unlike other metrics, no independent variables/static factors are needed to be measured, as
only the profiles of the curves are compared.
3.1.2.2 Baseline identification and calculation
Baseline is not applicable to this metric.
3.1.2.3 Baseline adjustments in case of anticipated changes
As no baseline is applicable to this metric, no adjustments are required.
3.1.2.4 Measurement boundaries determination & metering points
Figure 2: Data Centre Control Volume and Measurement Points illustrates a general scenario of a data centre. The
total energy consumption of such a data centre is measured at the Point of Delivery (POD) and is the summation of
energy coming from the utility (A) plus energy generated onsite (B); both measurements are in kWh. This means that
all types of energy are considered, both primary (e.g. fuel for an onsite generation engine) and secondary, and
converted in electricity.
26
Figure 2: Data Centre Control Volume and Measurement Points
However, it is worth highlighting that particular cases in which the energy plan provided to the Data Centres does
not include onsite production could happen. For example, in the case that there is a restriction or a demand order
only for the electricity consumed from the grid. In that case, energy consumption to consider will have to be
measured at the meter from the utility (A).
3.1.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
All the required variables can be metered using permanent energy meters, installed on the metering points
highlighted in the previous paragraph. Those energy meters should comply with the following requirements.
- Meters range must be consistent with the metered variables range and these meters should allow a
consistent unit selection.
- Meters must be equipped with a communication module (Modbus RTU RS485 protocol or equivalent), must
be connected to a gateway that via Ethernet allows concentrating data that are stored in log files or in a
database. A properly sized storage system must be designed and installed and data must be available for the
next phase of analysis and verification. In this way, each meter, becomes a node of the network.
Meters must be equipped with the required auxiliary devices such as amperometric transformers, voltmetric
commutators, surge protectors and surge arresters.
- The choice of measurement boundaries and metering points must be performed from the Data Centre
perspective. Moreover meters and auxiliary devices must be chosen according to the supply voltage. For this
reason, LV point of measures must be preferred to MV point of measures, also due to lower metering costs.
Measurement errors (defined by the HW’s accuracy classes), connections, communication protocols and networking
must be compliant with the existing standards (ANSI, IEC, IEEE, CEI EN) and national regulations.
3.1.2.6 Metering equipment commissioning procedure
The commissioning process assumes that owners, programmers, designers, contractors, operations and
maintenance entities are accountable for the quality of their work. Commissioning process includes several
27
procedures that are required in order to ensure the adequacy and the degree of precision required for the quality of
measurement and the product safety.
Once the measurement system is installed, a test procedure must be performed. During this procedure, once the
meter settings are set, the measure collected by the installed meter is compared with the measure collected through
a portable configured meter. The test procedure must not be confused with the calibration procedure performed by
the manufacturer. The test procedure includes the test of the communication channels (speed and reliability) and
the sampling time.
Together with the test procedure a maintenance procedure is required. The key tests required are:
- Every time the gateway does not communicate with the storage system or one or more nodes do not
communicate with the gateway it is necessary to check and solve the problems in due time.
- Periodically (once a year) it is important to inspect the measurement equipment and repeat the calibration
procedure.
- Every time hardware changes occur, the compliance between the meter range and the physical variable
range must to be checked and guaranteed.
If the commissioning procedure is workmanlike performed a maintenance procedure is not indispensable
3.1.2.7 Metering assumptions
As APC is based on comparing the total energy consumption of a DC to acomputed (optimal) energy consumption
curve, the main assumptions will be that Sections 3.1.2.1, 3.1.2.4 and 3.1.2.5 provide all the necessary information
(metering equipment, location) to measure the total energy consumption of the DC. All meters are assumed to be
calibrated, commissioned and tested, so the energy consumption measurement values are accurate and rigorously
collected and the samples are representative. If these assumptions are not met, an analysis to detect which
measurements are being missed or are not being considered should be made, and a procedure to include them with
new equipment or with estimations must be applied, including quantifying all the uncertainties added in case of
estimating any consumptions.
In case of changes in the metering equipment (including removal or plain change) during the sampling period, it is
assumed that the M&V plan describes all the specifications and calibration requirements and locations of the
metering equipment in order to continue the close as possible to the same metering scenario.
In case of changes in the metering equipment (including removal or plain change) during the sampling period, it is
assumed that the M&V plan describes all the specifications and calibration requirements and locations of the
metering equipment in order to continue the close as possible to the same metering scenario.
3.1.2.8 Metering sampling frequency
The sampling frequency will have dependency on hardware and software requirements (granularity of the meters,
data storage limitations, SCADA or Software limitations etc.); to capture the energy consumption pattern a
frequency in the order of minutes should be considered. Low measuring frequencies introduce the risk of not
capturing energy consumption peaks, reducing the effectiveness of the energy consumption behaviour capturing. To
this end, a measurement every 1 to 5 minutes would be recommendable with a maximum period not exceeding 15
minutes. In any case, the optimal energy consumption behaviour calculation should follow the DC energy
consumption measurements period and vice versa, in order to avoid unnecessary, overhead computational and
metering load.
In practice, a measurement period of 15 minutes (96 measures per day) is a good approach, providing a clear picture
of the daily energy pattern consumption of a DC, being adequate for the creation of different energy baselines.
3.1.2.9 Metering duration (post-retrofit period)
The pre- and post- implementation period should be measured with a similar period length and conducted using the
same procedure (equipment, sensor location, etc.).
28
As energy consumption depends on weather conditions, the measurements should include all the different seasons
and all different weather conditions: for this reason whole year duration is recommended. Similarly, variable DC
workload and usage patterns should be contemplated. For example, University or office building DCs will have
clearly less workload in summer or during holiday periods. Taking into consideration all the above, a post-retrofit
period of at least a year is the best option to capture DCs energy behaviour.
The minimum period must be one that sufficiently covers a wide range of weather and usage conditions. In this case
specific metering duration periods will be selected, depending on usage and location of the DC, in order to give a fair
representation of the DC behaviour.
3.1.3 Example Indicatively, Figure 3 presents an example calculation of the APC flexibility metric for a hypothetical DC. Specifically,
assuming that the measurement procedures described in the previous paragraphs were respected, Figure 3 depicts
the measured DC energy consumption , versus the planned energy consumption, for 6 consecutive time
intervals, i = 1,..,6.
In the example assumed, the adjustment factor equals
. Therefore, APC can be
calculated as follows:
(3)
Figure 3: DC energy consumption, and planned energy consumption, over time
29
3.2 Adaptability Power Curve at Renewable Energies
3.2.1 M & V Plan Scope and Metric Overview The present section is aimed to provide the measurement and verification methodology for the APCREN metric,
following the International Performance Measurement and Verification Protocol (IPMVP).
The APCREN metric belongs to the category of “Flexibility mechanisms in Data Centres: Energy shifting”, presented in
“Cluster Activities Task 3” document (§2.2.2).
This metric assumes that a renewable energy availability is provided, to which the data centre must adapt to the
greatest extent possible. The energy plan may be provided by an Energy Managing Entity within the Smart City or
the Smart grid or by the DC itself, as a result of self-optimization policies. APCREN aims at measuring the degree of
adaptation of the DC energy consumption to a planned renewable energy curve.
APCREN is given by the following formula:
(4)
(5)
where:
is the DC energy consumption in kWh;
is the available renewable energy (to be consumed) in kWh;
is the individual time period
represents the sample size and
is the adjustment factor between and .
Specifically, as accounts for all available renewable energy, its order of magnitude will generally be higher
than that of . The opposite is unlikely. In this course, allows the correlation of both variables providing
information - on the adaptability of the power curve - which otherwise would be suppressed by the difference in the
order of magnitude.
As derived from eq.(4), APCREN values are unit-less, where 1 corresponds to full adaptation. The lower the adaptation
between both curves is, the lower the value achieved for APCren (very different curves can result to negative APCren
values).
3.2.2 Measurements
3.2.2.1 Measurable variables determination
According to the formula aforementioned the parameters to be measured are:
total energy consumption of the DC for each time interval i expressed in kWh;
total energy coming from renewable sources, taking into account both the onsite generation and the energy
purchased on meter at time instant i expressed in kWh. In the case of primary energy containing a
percentage of energy coming from renewable sources, the calculation of the absolute value of purchased
renewable energy should derive as the multiplication of this percentage with the total energy purchased.
For details on measurement points please refer to section3.2.2.4.
30
3.2.2.2 Baseline identification and calculation
Baseline is not applicable to this metric.
3.2.2.3 Baseline adjustments in case of anticipated changes
Baseline is not applicable to this metric and therefore no baseline adjustment is required.
3.2.2.4 Measurement boundaries determination & metering points
Figure 4: DC Control Volume and Measurement Points illustrates a general scenario of a DC. The total energy
consumption of such a DC is measured at the Point of Delivery (POD) and it would be the summation of energy
coming from the utility (A) plus energy generated onsite (B); both measurements would be in kWh. This means that
all types of energy are considered, both primary and secondary, and converted in electricity.
The energy coming from renewable sources is the summation of energy produced locally BonsiteRes plus the
percentage, if any, purchased from the utility.
Figure 4: DC Control Volume and Measurement Points
3.2.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
All the required variables can be metered using permanent energy meters, installed on the metering points
highlighted in the previous paragraph. Those energy meters should comply with the following requirements.
- Meters range must be consistent with the metered variables range and these meters should allow a
consistent unit selection.
- Meters must be equipped with a communication module (Modbus RTU RS485 protocol or equivalent), must
be connected to a gateway that via Ethernet allows concentrating data that are stored in log files or in a
database. A properly sized storage system has to be designed and installed and data must be available for
the next phase of analysis and verification. In this way, each meter, becomes a node of the network.
31
Meters must be equipped with the required auxiliary devices such as amperometric transformers, voltmetric
commutators, surge protectors and surge arresters.
- The choice of measurement boundaries and metering points must be performed from the Data Centre
perspective. Moreover meters and auxiliary devices must be chosen according to the supply voltage. For this
reason, LV point of measures must be preferred to MV point of measures, also due to lower metering costs.
Finally, measurement errors (defined by the HW’s accuracy classes), connections, communication protocols and
networking must be compliant with the existing standards (ANSI, IEC, IEEE, CEI EN) and national regulations. The
requirements specified in these standards and regulations have to be considered as minimum values for the
meters under normal working conditions. For special application, higher constraints might be necessary and
should be agreed between the user and the manufacturer.
3.2.2.6 Metering equipment commissioning procedure
The commissioning process assumes that owners, programmers, designers, contractors, operations and
maintenance entities are accountable for the quality of their work. Commissioning process includes several
procedures that are required in order to ensure the adequacy and the degree of precision required for the quality of
measurement and the product safety.
Once the measurement system is installed, a test procedure must be performed. During this procedure, once the
meter settings are set, the measure collected by the installed meter is compared with the measure collected through
a portable configured meter. The test procedure must not be confused with the calibration procedure performed by
the manufacturer. The test procedure includes the test of the communication channels (speed and reliability) and
the sampling time.
Together with the test procedure a maintenance procedure is required. The key tests required are:
Every time the gateway does not communicate with the storage system or one or more nodes do not
communicate with the gateway it is necessary to check and solve the problems in due time.
Periodically (once a year) it is important to inspect the measurement equipment and repeat the calibration
procedure.
Every time hardware changes occur, the compliance between the meter range and the physical variable
range must to be checked and guaranteed.
If the commissioning procedure is workmanlike performed a maintenance procedure is not indispensable.
3.2.2.7 Metering assumptions
As APCREN is based on comparing the total energy consumption of a DC to the total energy provided by renewable
energy sources (RES availability from the grid and local generation), the main assumptions will be that Sections
3.2.2.1, 3.2.2.4 and 3.2.2.5 provide all the necessary information (metering equipment, location) to measure the
total energy consumption of the DC. All meters are assumed to be calibrated, commissioned and tested, so the
energy consumption measurement values are accurate and rigorously collected and the samples are representative.
For renewable energy availability curve the assumptions will be that the curve is produced taking into consideration
all the onsite renewable power systems that feed the DC, and that the energy provided by renewable systems has
been accurately measured. A procedure to measure the grid energy share that comes from renewables (RES
certificate) shall be established with a timeframe in the same order of the measurements provided by
measurements in the onsite installation.
If these assumptions are not met, an analysis to detect which measurements are being missed or are not being
considered should be made, and a procedure to include them with new equipment or with estimations must be
applied, including quantifying all the uncertainties added in case of estimating any consumptions.
32
In case of changes in the metering equipment (including removal or plain change) during the sampling period, it is
assumed that the M&V plan describes all the specifications and calibration requirements and locations of the
metering equipment in order to continue the close as possible to the same metering scenario.
3.2.2.8 Metering sampling frequency
The sampling frequency will have dependency on hardware and software requirements (granularity of the meters,
data storage limitations, SCADA or Software limitations etc.); to capture the energy consumption pattern a
frequency in the order of minutes should be considered. Low measuring frequencies introduce the risk of not
capturing energy consumption peaks, reducing the effectiveness of the energy consumption behaviour capturing. To
this end, a measurement every 1 to 5 minutes would be recommendable with a maximum period not exceeding 15
minutes.
In the case of renewable energy production, a higher measurement frequency is needed to cope with the
intermittent nature of the RES production. Indicatively, solar or wind energy production are extremely variable; a
recommending measurement period would be 1 minute. In any case, the measurements period regarding RES
should follow the DC energy consumption measurements period and vice versa, in order to avoid unnecessary,
overhead computational and metering load.
In practice, a measurement period of 15 minutes (96 measures per day) is a good approach, providing a clear picture
of the daily energy pattern consumption of a DC, being adequate for the creation of different energy baselines. For
renewable energy production measurements, 15 minute are too high and higher sampling rates in the order of 30
seconds to 1 minute would be necessary to capture the renewable energy contribution.
Summing up, a recommendable sample time would be 1 minute and the sample time shouldn’t be higher than 15
minutes.
3.2.2.9 Metering duration (post-retrofit period)
The pre- and post- implementation period should be measured with a similar period length and conducted using the
same procedure (equipment, sensor location, etc.).
As energy consumption depends on weather conditions, the measurements should include all the different seasons
and all different weather conditions: for this reason whole year duration is recommended. Similarly, variable DC
workload and usage patterns should be contemplated. For example, University or office building DCs will have
clearly less workload in summer or during holiday periods. Taking into consideration all the above, a post-retrofit
period of at least a year is the best option to capture DCs energy behaviour.
The minimum period must be one that sufficiently covers a wide range of weather and usage conditions. In this case
specific metering duration periods will be selected, depending on usage and location of the DC, in order to give a fair
representation of the DC behaviour.
3.2.3 Example Indicatively, Figure 5 presents an example calculation of the APC_REN flexibility metric for a hypothetical DC.
Specifically, assuming that the measurement procedures described in the following paragraphs have been respected,
Figure 5 depicts the measured DC energy consumption, , versus the available renewable energy, at 6
consecutive time intervals, i = 1,..,6.
In the example assumed, the adjustment factor equals
Therefore, can
be calculated as follows:
(6)
33
Figure 5: DC energy consumption, E_DC and the available renewable energy, E_Ren over time
3.3 Data Centre Adapt
3.3.1 M & V Plan Scope and Metric Overview
This section presents the measurement and verification plan pertaining to the newly proposed metric Data Centre Adapt (DCA). This metric provides information on how much the energy profile of a data centre has shifted from a baseline energy consumption after the implementation of flexibility mechanisms has taken place. By flexibility mechanisms we refer to strategies, policies or in general sets of actions, such as employing workload management techniques, in an effort to adapt the data centre’s energy consumption as much as possible to a planned energy curve. Ideally, the planned energy curve is one that represents running the data centre in a more energy efficient mode. This metric measures the change of the energy consumption curve.
It is important to distinguish DCA from a related energy shifting metric, namely APC. The latter compares a planned curve, suggested for example by an energy manager in order to modify the data centre’s energy consumption according to energy optimizations, constraints, or both, and its actual final consumption, modified in an effort to follow the suggested energy curve. The information then provided by this indicator is the data centre’s capability to adapt its consumption as in a demand response paradigm. Although the planned energy curve is determined previously, information given by both curves belongs to the same time period.
Conversely, DCA provides information about the flexibility that has been achieved after implementing actions to
adapt the data centre’s energy consumption during certain periods of time to energy profiles that are selected as
more advantageous, if compared with the energy profiles operating before. The reason for the changes will normally
be the adaptation of the consumption to a planned power curve (devised autonomously or provided by a smart grid
15 18
13 19 18 17
10
19
98
83
18 22
0
20
40
60
80
100
120
1 2 3 4 5 6
Ener
gy C
on
sum
pti
on
(M
Wh
)
Time Period i
EDC ERen
34
authority). However, this metric provides no information about the accuracy level of this adaptation; it rather
focuses on the degree of flexibility achieved due to the modifications in the operation approaches of the data centre.
These two curves, necessary to compute DCA, are not simultaneous in time. Therefore, information on the data
centre before and after implementing changes is required.
The equation below denotes the general mathematical formula to compute this metric:
(7)
is a scaling factor to render comparable the involved energy consumption curves. In particular, due to the inclusion of the flexibility mechanisms, variations in the global energy consumption may occur. Moreover, variations due to services provided, outside temperature, and so on, may appear as baseline and real consumption are not simultaneous in time; baseline measurements constitute the energy consumption pattern of a data centre before implementing actions or changes in SW or equipment that imply variations in this pattern (flexibility). Thus, it is necessary to normalise the resulted curves in order to compare the profile of energy consumption without introducing this distortion. The equation below provides the mathematical formula to compute this factor:
(8)
where:
denotes the data centre’s real energy consumption in kWh at a given point in time, i. This is the energy consumption after the implementation of flexibility mechanisms has taken place.
denotes the data centre’s baseline energy consumption in kWh at a given point in time, i. This is the energy consumption before the implementation of flexibility mechanisms. Baseline energy consumption profiles must be obtained by analysing and modelling the energy consumption of the data centre before the actions provided by flexibility mechanisms have been implemented (see section 3.3.2.2 for details).
represents the sample size.
The numerator within the formula for DCA represents the cumulative, absolute error between and , while the denominator represents the summation of over the whole sample, in other words the area below the baseline curve.
A DCA value equal to 1 means that the curve has not changed. A high flexibility of the consumption curve will imply a lower value for DCA (very different curves can cause even DCA negative values).
3.3.2 Measurements
3.3.2.1 Measurable variables determination
According to the formula aforementioned, the only parameter to be measured is the total energy consumption of
the data centre at a given point in time in kWh. More information on the selected timeframe and the baseline
scenario is found within sections 3.3.2.2 and 3.3.2.3. For details on measurement points please refer to section
3.3.2.4.
3.3.2.2 Baseline identification and calculation
The baseline is evaluated experimentally measuring power values at points A and B of the diagram as well as the
Point of Delivery (POD) of the DC. Given that the DC can be considered as a “black box”, no other measurements are
needed in this case. To perform the baseline evaluation an appropriate value for Δt must be selected.
We are dealing here with a metric in which the variation as a function of time is of particular importance. Typical daily profiles must therefore be measured. To do so, frequent measures of Energy consumed must be taken to
35
determine the baseline scenario. Obviously, the same frequency will be adopted to obtain the measures in the “real” scenario, i. e. after actions/changes in SW or equipment that imply variations have taken place. For practical purposes Δt = 15 min seems adequate (choice currently being used in DC4Cities). Daily profiles must be collected under different operational conditions of the DC. Effectively, profiles can exhibit significant variations depending on seasonal effects (winter/summer), workload changes (i.e. working day/weekend, specific deadlines, etc.). In order to assess correctly the Baseline it will be therefore necessary to create a set of typical profiles. Requisites and characteristics of the set must be determined for the specific DC under study.
3.3.2.3 Baseline adjustments in case of anticipated changes
For this metric Baseline adjustment is not needed, due to the usage of the scaling factor .
3.3.2.4 Measurement boundaries determination & metering points
Figure 6 illustrates a typical scenario of a data centre. The total energy consumption of such a data centre is
measured at the Point of Delivery (POD) and it is the summation of energy coming from the grid (A) plus energy
generated onsite (B); both measurements are in kWh. This means that all sources of energy are considered and
converted in electricity. For details on conversion factors please refer to the cluster report pertaining to the metric
“Primary Energy Savings”.
Figure 6: Data Centre Control Volume and Measurement Points
3.3.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
All the required variables can be metered using permanent energy meters, installed on the metering points
highlighted in the previous paragraph. Those energy meters should comply with the following requirements.
- Meters range must be consistent with the metered variables range and these meters should allow a
consistent unit selection.
- Meters must be equipped with a communication module (Modbus RTU RS485 protocol or equivalent), must
be connected to a gateway that via Ethernet allows concentrating data that are stored in log files or in a
36
database. A properly sized storage system must be designed and installed and data must be available for the
next phase of analysis and verification. In this way, each meter, becomes a node of the network.
Meters must be equipped with the required auxiliary devices such as amperometric transformers, voltmetric
commutators, surge protectors and surge arresters.
- The choice of measurement boundaries and metering points must be performed from the Data Centre
perspective. Moreover meters and auxiliary devices must be chosen according to the supply voltage. For this
reason, LV point of measures must be preferred to MV point of measures, also due to lower metering costs.
Finally, measurement errors (defined by the HW’s accuracy classes), connections, communication protocols and
networking must be compliant with the existing standards (ANSI, IEC, IEEE, CEI EN) and national regulation. The
requirements specified in these standards and regulations have to be considered as minimum values for the
meters under normal working conditions. For special application, higher constraints might be necessary and
should be agreed between the user and the manufacturer.
3.3.2.6 Metering equipment commissioning procedure
The commissioning process assumes that owners, programmers, designers, contractors, operations and
maintenance entities are accountable for the quality of their work. Commissioning process includes several
procedures that are required in order to ensure the adequacy and the degree of precision required for the quality of
measurement and the product safety.
Once the measurement system is installed, a test procedure must be performed. During this procedure, once the
meter settings are set, the measure collected by the installed meter is compared with the measure collected through
a portable configured meter. The test procedure must not be confused with the calibration procedure performed by
the manufacturer. The test procedure includes the test of the communication channels (speed and reliability) and
the sampling time.
Together with the test procedure a maintenance procedure is required. The key tests required are:
- Every time the gateway does not communicate with the storage system or one or more nodes do not
communicate with the gateway it is necessary to check and solve the problems in due time.
- Periodically (once a year) it is important to inspect the measurement equipment and repeat the calibration
procedure.
- Every time hardware changes occur, the compliance between the meter range and the physical variable
range must to be checked and guaranteed.
If the commissioning procedure is workmanlike performed a maintenance procedure is not indispensable.
3.3.2.7 Metering assumptions
As DCA is based on comparing the total energy consumption of a DC to its energy consumption during a previous
time period, the main assumptions will be that Sections 3.3.2.1, 3.3.2.4 and 3.3.2.5 provide all the necessary
information (metering equipment, location) to measure the total energy consumption of the DC. All meters are
assumed to be calibrated, commissioned and tested, so the energy consumption measurement values are accurate
and rigorously collected and the samples are representative. If these assumptions are not met, an analysis to detect
which measurements are being missed or are not being considered should be made, and a procedure to include
them with new equipment or with estimations must be applied, including quantifying all the uncertainties added in
case of estimating any consumptions.
For Section 3.3.2.2, the assumption will be that all the different baselines and profiles necessary for measurement
and verification process are defined. As these baselines will be used to calculate the energy savings after the energy
saving process it is important that the consumption behaviour of the DC is completely addressed.
In case of changes in the metering equipment (including removal or plain change) during the sampling period, it is
assumed that the M&V plan describes all the specifications and calibration requirements and locations of the
metering equipment in order to continue the close as possible to the same metering scenario.
37
3.3.2.8 Metering sampling frequency
The sampling frequency will have dependency on hardware and software requirements (granularity of the meters,
data storage limitations, SCADA or Software limitations etc.), to capture the energy consumption pattern a
frequency in the order of minutes should be considered. Low measuring frequencies introduce the risk of not
capturing energy consumption peaks, reducing the effectiveness of the energy consumption behaviour capturing. To
this end, a measurement every 1 to 5 minutes would be recommendable with a maximum period not exceeding 15
minutes.
In practice, a measurement period of 15 minutes (96 measures per day) is a good approach, providing a clear picture
of the daily energy pattern consumption of a DC, being adequate for the creation of different energy baselines.
3.3.2.9 Metering duration (post-retrofit period)
The pre- and post- implementation period should be measured with a similar period length and conducted using the
same procedure (equipment, sensor location, etc.).
As energy consumption depends on weather conditions, the measurements should include all the different seasons
and all different weather conditions: for this reason, a whole year duration is recommended. Similarly, variable DC
workload and usage patterns should be contemplated. For example, University or office building DCs will have
clearly less workload in summer or during holiday periods. Taking into consideration all the above, a post-retrofit
period of at least a year is the best option to capture DCs energy behaviour.
The minimum period must be one that sufficiently covers a wide range of weather and usage conditions. In this case
specific metering duration periods will be selected, depending on usage and location of the DC, in order to give a
fair representation of the DC behaviour.
3.3.3 Example Indicatively, Figure 7: Energy consumption, both real and baseline presents an example calculation of the DCA
flexibility metric for a hypothetical DC. Specifically, assuming that the measurement procedures described in the
previous paragraphs were respected, Figure 7: Energy consumption, both real and baseline depicts the data centre’s
real energy consumption in kWh and the data centre’s baseline energy consumption in kWh
for 7 consecutive time intervals, i = 1,..,7.
In the example assumed, the adjustment factor equals
. Therefore, DCA can
be calculated as follows:
(9)
38
Figure 7: Energy consumption, both real and baseline
3.4 Primary Energy Savings
3.4.1 M & V Plan Scope and Metric Overview This section discusses in detail the metric denoting the savings in terms of primary energy consumed by a data
centre, once improvements have taken place with regard to its energetic, economic, or environmental management.
This metric was initially introduced within the report released by the cluster as a result of the work on identifying
new metrics to accommodate for newly introduced dimensions such as usage of renewable energy sources, energy
re-use, and data centre flexibility mechanisms9. The suggested formula was given as:
(10)
The current section, taking as a starting point the above formula, will further elaborate and detail the proposed
metric along with guidelines pertaining to its computation and related measurements.
For all intents and purposes of this section definitions pertaining to commonly used terms are those specified within
ISO/IEC JTC 1/SC39 documents, unless otherwise explicitly stated, and in particular (ISO/IEC JTC 1/SC 39, 2014).
To better understand what this formula represents, one may collapse the parameters involved as follows while
introducing the percentage aspect:
9 https://ec.europa.eu/digital-agenda/en/news/cluster-fp7-projects-proposes-new-environmental-efficiency-metrics-data-
centres
20 22
29
33 35
32
26 25
30
35
30
35
30
25
0
5
10
15
20
25
30
35
40
0 1 2 3 4 5 6 7 8
ener
gy c
on
sum
pti
on
(M
Wh
)
time i
EDC Real EDC Baseline
39
(11)
where,
denotes the total energy consumed by the data centre, in terms of primary energy, measured during
period as a summation of discrete intervals10 in time, while
denotes the total energy that would have been consumed by the data centre, also in terms of
primary energy, during the “same” period provided that conditions would have remained the same as in the
baseline scenario.
Total energy in this case takes into consideration not only the energy consumed by the data centre in form of
electricity, , but also energy consumed in any other form, , such as for example chilled water for
cooling purposes:
(12)
All parameters are in primary energy terms with the unit of measurement being the kWh.
The selected period may depend on the type of the data centre in question, the characteristics of its business
model, the type of the intervention and so forth. On a business as usual scenario, one should opt for a period equal
to a year – so as to take into account a statistical average of the typical behaviour of a data centre, including end-
user’s consumption patterns, along with variations pertaining to environmental conditions, such as outside
temperature, sun and wind intensity. However, for practical reasons and for the purposes of the projects within the
cluster this period may be adapted to fit the general planning.
For details on the selection of the timeframe along with information on the baseline scenario please refer to
sections 3.4.2.2 and 3.4.2.3.
It should be noted that this metric along with the related ones on CO2 emissions and economic expenses are meant
to be global metrics11; as such the data centre is therefore viewed as a black box. Both of these metrics are actually
variants of the one pertaining to the primary energy, adjusted with appropriate factors.
More information on the related metrics and their measurement and validation plan is found within their respective
reports.
In the following we provide details on the methodology related to measurement, analysis, and reporting of this
metric.
3.4.2 Measurements
3.4.2.1 Measurable variables determination
Based on the formula aforementioned and in line with the concept of treating the data centre as a black box the
parameters to be measured are:
10
Discrete interval will depend on the goal pursued to compute the metric, and may vary from a time interval equal to 15 minutes or 1 hour to a time interval of 1 week, month or year. 11
In case the data centre operator is interested in evaluating improvements pertaining to a subsystem instead (such as primary
energy savings of the cooling system), the methodology defined within this section may be applied; naturally the measurement
boundaries would have to be adjusted accordingly.
40
Total energy taken by the grid, measured at the meter for each interval, and consumed during a pre-selected
period of time ; and
Total energy produced and consumed on site for immediate and own consumption (back-up generators,
solar panels, natural gas for absorption chillers, and so on) for each interval.
For details on baseline scenario specifications please refer to sections 3.4.2.2 and 3.4.2.3, while for information
related to measurements points to section 0.
3.4.2.2 Baseline identification and calculation
The baseline is evaluated experimentally measuring energy values at points as indicated within section 0 Given that
the data centre can be considered as a “black box”, no other energy measurements are needed in this case.
To perform the baseline evaluation an appropriate value for must be selected. In principle, we are dealing with an
aggregated value, and therefore corresponds to a relatively long period, typically 1 year. Metering sampling
frequency has to be the same in both current and baseline scenarios (see section 3.4.2.8).
In practice it may not be always possible to carry out the determination of a baseline scenario throughout a year.
This can be true, for example, in cases where measurements are bound to a shorter period such as during pilots or
an energy audit to evaluate the feasibility of a business case. Under such conditions, the baseline scenario may be
simulated by assessing the value of the energy consumption for a set of “typical days” and then projecting these on a
one-year period. Requisites and characteristics of the set must be determined for the specific data centre under
study.
Daily values building up the typical behaviour must be collected under different operational conditions of the data
centre, including also variations in energy supply patterns. This is because significant variations due to seasonal
effects (winter/summer), workload changes (for example working day/weekend, specific deadlines, and so on), and
different hourly prices depending on the day/month may occur.
3.4.2.3 Baseline adjustments in case of anticipated changes
A need for baseline adjustment arises when some “external factor” introduces a change in the baseline value.
External factors of practical importance are:
• substantial changes in the equipment, IT, power, cooling or otherwise, of the data centre;
• refurbishment/renovation of the premises where the data centre is located;
• changes in environmental parameters (temperature, relative humidity, and so on);
• business changes, for example partnerships, mergers, acquisitions, opening of new markets and activities;
• significant changes in workloads, workload distribution, or both.
It is worth distinguishing between routine and non-routine adjustments.
Routine adjustments are those that would be done regularly, for example, due to changes in weather conditions or
IT workloads. Most of such external factors introduce non-linear effects in the formulas. For instance, increases in
the total workload of a data centre do not imply corresponding proportional increases in the energy consumption.
As an example, the simple routine adjustment of the baseline through a multiplying factor, therefore a relation
obtained as a linear regression, as in Equation (13), is hardly ever possible:
(13)
In general, it is therefore not possible to estimate “theoretically” values for the parameters above; at least not
without performing a new experimental assessment of the baseline. In certain specific cases it might appear possible
to perform such an estimate, but a general operational rule cannot be given and the calculation of the adjustment
will have to be performed on a case-by-case basis.
41
A non-routine adjustment would occur due to an isolated event, for example, an increase of the total DC surface
(new equipment). In this case, a new mathematical model has to be performed. Following the previous example, a
new linear regression would have been to be calculated and this new formula would be used to adjust baseline:
(14)
3.4.2.4 Measurement boundaries determination & metering points
Figure 8 illustrates a typical scenario of a data centre. The total energy consumption taken by the grid is measured at
point A, for example with a meter close to the POD. For other forms of energy such as gas, fuel, or chilled water the
measurement is taken at the point of delivery of each source, for example as input to the non-RES element of Figure
8, while for renewable generation onsite the energy produced and consumed is measured with a meter at the
output of the RES element.
All forms of available to the data centre energy must be considered in terms of primary energy; naturally in order to
consolidate the various sources, their value must be adjusted accordingly based on the Primary Energy Factors (PEFs)
as discussed in section 3.4.2.7.
Figure 8: Data Centre Control Volume and Measuring Points
3.4.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
All the required variables can be metered using permanent energy meters. They should be provided of a
communication protocol module such as for example ModbusRTU RS485 or equivalent. The measure error has to be
1% or lower (active energy).
3.4.2.6 Metering equipment commissioning procedure
Meter range has to be consistent with the variable range. Meters setup during commissioning should include
consistent unit selection. Meters calibration preferably should take place once a year.
42
3.4.2.7 Metering assumptions
By primary energy we refer to all energy forms as found in nature, which are used to generate the supply of energy
carriers, electricity being the most common of the latter. For both the nominator and denominator in the formulas
given by Equation (14), all forms of energy sources available to the data centre, such as electricity, gas and so on, are
taken into consideration. As already mentioned all sources are converted to primary energy terms; the unit of
measurement being the kWh12.
The purpose of the source energy conversion is to enable comparison of different forms of energy by data centres.
Since the majority of data centres operate with 100% electricity, the Harmonizing Metrics Task Force (Global
TaskForce, 2014) recommends energy factors weighted with respect to electricity. However, this does not allow for
any weighting between grid and locally generated electricity to produce comparable source energy measures. In
addition, converting all energy sources in primary energy terms has a real physical meaning, as electricity is energy
already transformed by either bulk or distributed generation and thus may introduce significant distortion related to
equipment performance efficiency, transportation losses, and so on.
For the conversion, appropriate and established conversion factors must be used, the so-called PEFs. However, there
is no unified approach in European regulations on how to calculate these factors (Molebroek, Stricker, & Boermans,
2011).
Generally speaking, for electricity this factor should represent "the average efficiency of all the power plants and the
probability of each of them in operation at a certain time minus the amount of electricity from renewable sources
and their probability plus the distribution losses" per country or region. Electricity has usually the highest primary
energy factor due to low efficiency of power plants which on average is around 35%. The calculation of such a factor
is very complicated, not to mention that in most cases exact details of the algorithm are not even publicly available.
As such it is always estimated and actually it seems political decisions have a large influence on the final value; in
other words it should be provided by the national or local governments.
Table 3 lists the PEFs of seven European countries for delivery of electricity to a building according to their national
building regulations. The PEF for the majority of countries is approximately 2.6.
Table 3: PEFs of seven European countries for delivery of electricity to a building (Source: (Molebroek, Stricker, & Boermans, 2011))
France Germany NL Poland Spain Sweden UK
PEF 2.58 2.60 2.56 3.00 2.60 2.00 2.92
However, these values are typically updated every few years; therefore one should always check with the local or
national authority for the most recent value. For example, in Germany the PEF for electricity was changed from 2.6
to 2.4 in 2014 (DIN V 18599-1) and is expected to change to 1.8 in 2016 with a factor of 1.2 as the target for the year
2020 (EnEV 2014 “Energy Saving Regulation in Germany”).
Moreover, this aggregated value has relevant seasonal variations, or even relevant variation within the same day.
Therefore, should one wishes to use this metric to also evaluate demand response scenarios, where flexibility
mechanisms are introduced in the data centre, electricity PEF may not be considered as a constant value; in this case
one may compute this factor for each while taking into account variations in the (local) electricity mix.
12
Energy is commonly measured in Btus (U.S. units) or kWh (metric units); for reference, the definition of a Btu, or British thermal unit, is the energy it takes to heat one pound of water by one degree Fahrenheit. Note that kWh, although it is typically used for electricity, is a unit of energy (not just electricity)—and can thus be applied to any fuel source.
43
On the other hand, an annual average should suffice when the KPI is used for other purposes. This would include, for
example, evaluating general energy efficiency scenarios such as retrofitting of cooling systems, replacing electric
heat pumps with absorption chillers, and so on.
includes an example of total weighting factors and that the weighting factors for general grid-delivered electricity
exceed 1. Primary energy weighting factors are given for largely or wholly renewable energy sources including wood
and on-site solar PV. As aforementioned, some of these factors can be variable, depending on the origin of the
source (e.g. coal from different compositions), the performance for each technology or the approach followed by
each country. includes an example of total weighting factors and that the weighting factors for general grid-delivered
electricity exceed 1. Primary energy weighting factors are given for largely or wholly renewable energy sources
including wood and on-site solar PV. As aforementioned, some of these factors can be variable, depending on the
origin of the source (e.g. coal from different compositions), the performance for each technology or the approach
followed by each country.
Table 4: Total primary energy weighting factors - delivered and exported energy. (Source: CEN: EN 15459 Energy Performance of buildings - Economic evaluation procedure for energy systems in buildings, 2007 (quoted in RenewIT D3.1 Metrics for Net Zero Data Centres)).
Form of energy supplied Non-renewable primary energy weighting factor
Gas 1.05
Oil 1.05
Coal 1.05
Grid electricity
2.3
Grid electricity by hydraulic power plant
0.5
Liquid biomass and biogas 0.5
Wood 0.05
District heating (based in gas fired boiler plant)
1.3
District cooling 1.3
Solar PV on site 0
Thermal solar on site 0
Cogeneration unit electricity (non-renewable fuel)
1.6
PV electricity 1.6
Cogeneration unit electricity (non-renewable fuel)
2
PV electricity 2
Cogeneration unit electricity 2.5
PV electricity 2.5
Grid electricity factor, in case variations are to be considered, can be calculated taking into account the following
factors: electricity mix (by technologies/sources), performances, PE energy coefficient, and electric losses. Data is
generally provided in all the countries by the official institutions such as ministries or the grid operator.
That being said, a European-wide source of relevant data to support the computation of such factors – including
ones pertaining to carbon and other greenhouse gas emissions – is the so called European Reference Life Cycle
(ERLC) Database maintained and updated by the EC’s JRC, http://eplca.jrc.ec.europa.eu/ELCD3/.
Primary energy for fuels or renewable sources can be then computed by multiplying actual consumption with the
corresponding factor. For example consumption of 400 litres of diesel, by for example a diesel back-up generator, in
primary energy terms would be:
44
(15)
Assuming that 1 litre of diesel contains 11.1 kWh (average based on Gross Calorific Value) and the factor pertaining
to diesel is equivalent to oil (see includes an example of total weighting factors and that the weighting factors for
general grid-delivered electricity exceed 1. Primary energy weighting factors are given for largely or wholly
renewable energy sources including wood and on-site solar PV. As aforementioned, some of these factors can be
variable, depending on the origin of the source (e.g. coal from different compositions), the performance for each
technology or the approach followed by each country.).
3.4.2.8 Metering sampling frequency
Data collected from the field are to be sampled with an hourly frequency.
3.4.2.9 Metering duration (post-retrofit period)
Concerning metering duration please refer to section 3.4.2.2.
3.4.3 Example Let’s assume a typical scenario, also illustrated within Figure 8. The data centre is connected to the grid to
accommodate for its basic needs in energy, while is also equipped with a diesel generator, as a back-up energy
source, and solar panels.
The first step then would be to identify the baseline scenario in advance to any intervention to the data centre. For
related details, please refer to section 3.4.2.2.
Let’s now assume that load management operations are enacted to ensure that the data centre energy consumption
follows as much as possible the production of the onsite (renewable) energy. In order to assess the savings on
primary energy a simple step-by-step procedure is followed:
a. Define period ;
b. Adjust the baseline taking into account the various modifications that might have taken place;
c. Calculate according to the formula.
Table 5 provides an overview of measured and computed parameters pertaining to the baseline scenario,
Table 6 whereas lists the equivalent values for the improved scenario. For the former we have already assumed that
appropriate adjustments have taken place. In addition, we have also assumed that the average energy mix of the
grid, and as such the related PEF, is practically the same for both scenarios and no relevant variations occur during
the different periods, and in particular equal to 2.5. Energy produced onsite by for example solar panels is also
assumed to be consumed within the premises of the data centre – no export to the grid takes place – and as such
the related PEF is equal to 1.
Table 5: Adjusted baseline scenario parameter
Period 1 Period 2 Period 3 Period 4 Total
Days 100 120 60 85 365
EDC grid (kWh) 25,000 30,000 20,000 25,000 100,000
PEDC grid 62,500 75,000 50,000 62,500 250,000
EDC diesel (litres) 0 0 400 0 400
PEDC gas (kWh) 0 0 4,662 0 4,662
PEDC RES (kWh)13 5,000 5,000 0 0 10,000
13
Assuming onsite generated energy is not exported to the grid and as such PEF would be equal to 1.
45
PEDC (kWh) 67,500 80,000 54,662 62,500 264,662 d.
Table 6: Improved scenario parameters
Period 1 Period 2 Period 3 Period 4 Total
Days 100 120 60 85 365
EDC grid (kWh) 20,000 25,000 15,000 20,000 80,000
PEDC grid 50,000 62,500 37,500 50,000 200,000
EDC diesel (litres) 0 0 400 0 400
PEDC gas (kWh) 0 0 4662 0 4662
PEDC RES (kWh) 10,000 10,000 5,000 5,000 30,000
PEDC (kWh) 60,000 72,500 47,162 55,000 234,662
In this example, primary energy savings would be equal to 11.34%, even though the total energy consumption in
electricity remains the same.
3.5 CO2 Avoided Emissions
3.5.1 M & V Plan Scope and Metric Overview This section discusses in detail the metric denoting the savings in terms of CO2 emissions generated by a data centre
(CO2Savings), once improvements have taken place with regard to its energetic, economic, or environmental
management.
Naturally, this metric belongs to the same family of metrics as the ones related to the primary energy savings (see
PESavings) and savings on economic expenses (EES). These metrics were initially introduced within the report
released by the cluster as a result of their work on identifying new metrics to accommodate for newly introduced
dimensions such as usage of renewable energy sources, energy re-use, and data centre flexibility mechanism14. The
suggested formula pertaining to the CO2 variant was given as:
(16)
This section, taking as a starting point the above formula, will further elaborate and detail the proposed metric along
with guidelines pertaining to its computation and related measurements.
For all intents and purposes of this section definitions pertaining to commonly used terms are those specified within
ISO/IEC JTC 1/SC39 documents, unless otherwise explicitly stated, and in particular (ISO/IEC JTC 1/SC 39, 2014).
Similarly to PESavings, to better understand what this formula represents, one may collapse the parameters involved
while introducing the percentage aspect as follows:
(17)
14
https://ec.europa.eu/digital-agenda/en/news/cluster-fp7-projects-proposes-new-environmental-efficiency-metrics-data-centres
46
where,
denotes the total CO2 emissions released due to the energy consumed by the data centre during
period , as a summation of discrete intervals15 in time, while
denotes the total CO2 emissions that would have been released due to the energy consumed
by the data centre during the “same” period provided that conditions would have remained the same as in the
baseline scenario, namely no improvements would have taken place.
As in the PESavings, the selected period may depend on the type of the data centre in question, the
characteristics of its business model, the type of the intervention and so forth. Please refer to the section describing
the metric on PESavings for detailed information on this issue.
Obviously for the purposes of this metric we consider only the CO2 emissions released due to the consumption of
energy by the data centre; a full life-cycle analysis of the data centre and its equipment (IT and otherwise), although
important to the environmental sustainability efforts of the sector, is out of scope.
To further elaborate on the computation of this metric, one can decompose its parameters, similarly as in PESavings,
to emissions due to electricity, , and those due to energy consumed in any other form, , such as
for example diesel generator for back-up purposes:
(18)
In particular, emissions related to electricity taken from the grid should be computed as the product of the energy
consumed and the Carbon Emission Factor (CEF) of the site based on regional or national published data for the
selected period.
(19)
As in PESavings, the measurement unit of energy is kWh, while CEF is measured in kgCO2eq/kWh (metric system).
However, in case one wish to use this metric to also evaluate demand response scenarios, where flexibility
mechanisms that involve modifying the energy consumption profile are introduced in the data centre, CEF may not
be considered as a constant value; in this case one may compute this factor for each while taking into account
variations in the (local) electricity mix.
In this case, one should reference the source used for acquiring the appropriate values; Table 7: Recommended
source data for CEF per region. lists recommended sources for obtaining such data, as also presented within (Global
TaskForce, 2014).
Table 7: Recommended source data for CEF per region.
Region Data Source
E.U. http://re.jrc.ec.europa.eu/energyefficiency/covenantofmayors/seap_guidelines_en-2.pdf
http://archive.defra.gov.uk/environment/business/reporting/pdf/100805-guidelines-ghg-conversion-factors.pdf
Japan http://ghg-santeikohyo.env.go.jp/files/calc/itiran.pdf
15
As for PE_savings, discrete interval will depend on the goal pursued to compute the metric, and may vary from a time interval equal to 15 minutes or 1 hour to a time interval of 1 week, month or year.
47
USA http://www.epa.gov/cleanenergy/documents/egridzips/eGRID2007V1_1_year05_SummaryTables.pdf
http://www.energystar.gov/ia/business/evaluate_performance/Emissions_Supporting_Doc.pdf?ac4e-840b
Other sources of energy should also be accounted for; ideally, CO2 emissions data would be gathered from real-time
CO2 meters that collect data from the local power source (natural gas, diesel, fuel oil, coal, turbines/generators/fuel
cells, or other). However, if real-time CO2 emission data is not available, then calculations should be made using the
generator manufacturer(s) data for emission and fuel source, calculated for the specific, actual load profile over time
(The Green Grid, 2010).
In the following we provide information on baseline identification and adjustment, analysis, verification, and
reporting methodology, before presenting a simple example illustrating the proposed methodology.
3.5.2 Measurements
3.5.2.1 Measurable variables determination
Based on the formula aforementioned and in line with the concept of treating the data centre as a black box the
parameters to be measured are:
Total energy taken by the grid, measured at the meter for each time interval, and consumed during a pre-
selected period of time ; and
Total energy produced and consumed on site for each time interval for immediate and own consumption
(back-up generators, solar panels, and so on), or whenever possible CO2 emissions measurements from real-
time CO2 meters that collect data per local source.
For details on baseline scenario specifications please refer to sections 3.5.2.2 and 3.5.2.3, while for information
related to measurements points to section 3.5.2.4.
3.5.2.2 Baseline identification and calculation
See paragraph 3.4 on PESavings metric.
3.5.2.3 Baseline adjustments in case of anticipated changes
See paragraph 3.4 on PESavings metric.
3.5.2.4 Measurement boundaries determination & metering points
See paragraph 3.4 on PESavings metric in case only energy related measurements are available.
In case one can obtain real time information from CO2 meters dedicated to collect data from a particular source,
then such meters would be located at the output of the source.
3.5.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
See paragraph 3.4 on PESavings metric.
In case direct CO2 emissions measurements are possible, meters are necessary to be deployed according to their
manufacturer’s standards and methodology.
3.5.2.6 Metering equipment commissioning procedure
See paragraph 3.4 on PESavings.
Similarly, special attention should be paid in case CO2 meters are deployed.
3.5.2.7 Metering assumptions
See paragraph 3.4 on PESavings.
48
Similarly, special attention should be paid in case CO2 meters are deployed.
3.5.2.8 Metering sampling frequency
See paragraph 3.4 on PESavings.
Similarly, special attention should be paid in case CO2 meters are deployed.
3.5.2.9 Metering duration (post-retrofit period)
See paragraph 3.4 on PESavings.
Similarly, special attention should be paid in case CO2 meters are deployed.
3.5.3 Example Let’s assume the same scenario as the one described within the document pertaining to the PESavings: A data
centre, located for example in the Netherlands, is connected to the grid to accommodate for its basic needs in
energy, while is also equipped with a diesel generator, as a back-up energy source, and solar panels.
The first step then would be to identify the baseline scenario in advance to any intervention to the data centre. For
related details, please refer to the PESavings metric.
Let’s now assume that load management operations are put in place to ensure that the data centre energy
consumption follows as much as possible the production of the onsite (renewable) energy. In order to assess the
savings on CO2 emissions the same as in PESavings step-by-step procedure is followed.
Table 8 provides an overview of measured and computed parameters pertaining to the baseline scenario, while
Table 9 lists the equivalent values for the improved scenario. For the former we have already assumed that
appropriate adjustments have taken place.
Table 8: Adjusted baseline scenario calculations.
Period 1 Period 2 Period 3 Period 4 Total
Days 100 120 60 85 365
E DC grid (KWh) 25,000.00 30,000.00 20,000.00 25,000.00 100,000.00
CO2 DC grid (kgCO2eq) 17,900 21,480 14,320 17,900 71,600
E DC onsite: gen (litres) 0.00 0.00 400.00 0.00 400.00
E DC onsite: gen (kWh) 0.00 0.00 4440.00 0.00 4440.00
CO2 onsite: gen (kgCO2eq) 0.00 0.00 1354.20 0.00 1354.20
E DC onsite: RES (kWh) 5,000.00 5,000.00 0.00 0.00 10,000.00
CO2 onsite: RES (kgCO2eq) 100.00 100.00 0.00 0.00 200.00
Tot. CO2 emissions (kgCO2eq) 18,000.00 21,580.00 15,674.20 17,900.00 73,154.20
Table 9: Improved scenario calculations.
Period 1 Period 2 Period 3 Period 4 Total
Days 100 120 60 85 365
E DC grid (KWh) 20,000.00 25,000.00 15,000.00 20,000.00 80,000.00
CO2 DC grid (kgCO2eq) 14,320 17,900 10,740 14,320 57,280
E DC onsite: gen (litres) 0.00 0.00 400.00 0.00 400.00
E DC onsite: gen (kWh) 0.00 0.00 4,440.00 0.00 4,440.00
CO2 onsite: gen (kgCO2eq) 0.00 0.00 1,354.20 0.00 1,354.20
E DC onsite: RES (kWh) 10,000.00 10,000.00 5,000.00 5,000.00 30,000.00
49
CO2 onsite: RES (kgCO2eq) 200.00 200.00 100.00 100.00 600.00
Tot. CO2 emissions (kgCO2eq) 14,520.00 18,100.00 12,194.20 14,420.00 59,234.20
Table 10 lists all emissions factors used in the calculations above. So as to keep the example simple, we have
assumed that the emission factor of the grid has remained the same between the baseline year and the one of the
improved scenario.
Table 10: Emissions factors used in example calculations (Source: http://www.eumayors.eu/IMG/pdf/technical_annex_en.pdf)
CEF Value (t CO2 eq / MWh)
grid (NL) 0.716
diesel 0.305
solar panel 0.020
Assuming that 1 litre of diesel contains 11.1 kWh (average based on Gross Calorific Value), consumption of 400 litres
of diesel would be:
(20)
The CO2 emissions savings would then be equal to 19.03 %, even though the total energy consumption in electricity
is essentially the same. The primary energy savings for this example are equal to 11.34 %.
3.6 Economic Saving in Energy Expenses (EES)
3.6.1 M & V Plan Scope and Metric Overview This section is a detailed presentation of the Energy Expenses metric, EES, which provides an expression for overall
economic savings in energy expenses within a data centre, once improvements have taken place with regard to its
energetic, economic, or environmental management.
This metric belongs to the same family of metrics as the ones related to the primary energy savings (see PESavings)
and the CO2 emissions savings (CO2Savings). These metrics were initially introduced within the report released by
the cluster as a result of their work on identifying new metrics to accommodate for newly introduced dimensions
such as usage of renewable energy sources, energy re-use, and data centre flexibility mechanism16. The suggested
formula pertaining to the economic expenses variant was given as:
In general, assuming no changes in contracted power are introduced, no fix costs are included in the analysis (for
example pertaining to grid operators’ fees) or savings due to potentially less related taxes.
The current document, taking as a starting point the above formula, will further elaborate and detail the proposed
metric along with guidelines pertaining to its computation and related measurements.
16
https://ec.europa.eu/digital-agenda/en/news/cluster-fp7-projects-proposes-new-environmental-efficiency-metrics-data-centres
50
For all intents and purposes of this document definitions pertaining to commonly used terms are those specified
within ISO/IEC JTC 1/SC39 documents, unless otherwise explicitly stated, and in particular (ISO/IEC JTC 1/SC 39,
2014).
Similarly to PESavings, to better understand what this formula represents, one may collapse the parameters
involved, while introducing the percentage aspect, as follows:
(21)
where:
denotes the total energy consumption of the data centre, pertaining to the grid (electricity, natural gas, and
so on), in kWh during a given time interval as a summation of discrete intervals17 in time;
denotes the average energy cost in €/kWh during the same time interval; it should be noted that the average
cost is calculated by weighting the energy consumptions at different energy prices periods; most commonly such
average cost takes no consideration for costs paid to the energy supplier for power contracted; however, in case of
any modification, fix costs will have to be considered to calculate the energy average cost;
denotes the total energy consumed by the data centre that was produced on site during the same time
interval; and
denotes the average energy cost pertaining to energy produced and consumed on site during the same
time interval. The same approach than for should be followed in case of hourly prices variations.
An effort was made to devise a general metric that takes into account also costs incurred in the set-up of an onsite
energy producing facility. Nevertheless, this metric can be very useful for optimization purposes as well, for example
analysing, once a local source is installed, the potential benefits of using this source during a period (and thus linked
to flexibility mechanisms in data centres). In the case that the simple computation of energy costs is desired, certain
factors may be considered equal to 0, such as terms pertaining to amortization, maintenance, installation and
operational costs, for analysing various scenarios.
The expression current denotes the total cost of the energy consumed by the data centre in its “final” configuration,
measured during time period , while baseline adjusted denotes the total cost of the energy that would have been
consumed by the data centre during the same period, provided that conditions would have remained the same as in
the baseline scenario. Conditions between the two periods will most likely be different, not only in relation to
environmental parameters, but also for IT and facility equipment and workload, especially considering that
continuous optimization efforts may have been put in place. One should, therefore, adjust the baseline by for
example measuring and analysing the correlation of kWh with external parameters, so that these external
parameters can be used to estimate what the consumption would have been during the reporting period.
It is important to remark that revenues coming from exported energy produced onsite will have to be considered to
calculate EES, in case the data centre sells a share of its production (for example photovoltaic surpluses injected to
the electricity grid or recovery heat from a CHP sold to another building).
As already mentioned above, the quantities and , are the results of weighted summations over
period Δt, because energy prices may vary within this period.
17
Discrete interval will depend on the goal pursued to compute the metric, and may vary from a time interval equal to 15 minutes or 1 hour to a time interval of 1 week, month or year.
51
More specifically:
=
(22)
in which the total period is divided in n sub-periods, each with its own energy cost. Similar expressions can be
defined for the other variables.
is provided by the contract between the data centre and the energy supplier. Normally this is a fixed-price
rate, which is agreed upon at the start of the contract. Situations with a variable-price situation must be taken into
account. In this case will be calculated as an average weighted value, thus:
(23)
While represents the electricity as taken from the grid, is computed based on all available sources
of energy within the data centre premises. In a typical scenario where the data centre, for example, has only a
couple of back up diesel generators, the situation is straightforward. One only needs to take into account the
amount of litres or m3 consumed within period multiplied by the (average) cost (€/litre) during the same period,
similarly to the situation above.
However, in case of further energy sources available on site, such as for example PV panels, the total cost pertaining
to energy produced and consumed onsite would be given by the formula below:
(24)
where,
denotes the average cost per unit of energy produced onsite by energy source j.
Depending on the purposes for which the data centre needs to calculate this KPI, energy costs can be
calculated only considering energy costs or also considering other terms, as for example, maintenance costs onsite.
For example, if a data centre wants to evaluate how energy costs will be affected by a demand side management
project, Cost will have to be calculated considering only energy costs.
For other more complex evaluations (as TCO), the inclusion of other terms that take into account investments and
operational costs can be needed. The TCO general expression can be quite complicated. A simplified expression that
can be valid for the purposes of this document is:
(25)
where,
= cost of amortization of equipment/infrastructures in the period Δt
= cost of amortization of installation in the period Δt
= cost of operation (including energy costs) & maintenance in the period Δt
Thus:
(26)
52
3.6.2 Measurements
3.6.2.1 Measurable variables determination
Based on the formula aforementioned the parameters to be measured are:
Total energy (electricity or other form) consumption taken by the grid and measured at the meter for each
time interval; and
Total primary energy source consumption on site (back-up generators, solar panels, and so on) for each time
interval
For details on baseline scenario specifications please refer to sections 3.6.2.2 and 0, while for information related to
measurements points to section 0.
3.6.2.2 Baseline identification and calculation
The baseline is evaluated experimentally measuring energy values at points A, B, POD of the diagram. Given that the
DC can be considered as a “black box”, no other measurements are needed in this case.
To perform the baseline evaluation an appropriate value for Δt must be selected. In principle, we are dealing with an
aggregate value, and therefore Δt corresponds to a relatively long period, typically 1 year.
For practical purposes, in case measurements are bound to a shorter period (e.g. demonstrative project or energy audit to evaluate the feasibility of a project), if it is not possible to carry out the determination of a baseline and current value throughout one year, this can be simulated by assessing the value of the energy consumption in a set of “typical days” and then projecting these on a 1-year period. Although IPMVP does not allow for simulated data, we nevertheless opt for such approach since, at this stage, the idea is to provide a general formula considering expenses savings at data centre level. However, if sub-meters are installed, methodology will be the same as option B (no option A as we are measuring energy). Requisites and characteristics of the set must be determined for the specific data centre under study. Daily values must be collected under different operational conditions of the data centre. This aggregate value can
exhibit significant variations depending on seasonal effects (winter/summer), workload changes (that is working
day/weekend, specific deadlines, and so on) and different hourly prices depending on the day/month.
3.6.2.3 Baseline adjustments in case of anticipated changes
A need for baseline adjustments arises when some “external factor” introduces a change in the baseline value.
External factors of practical importance are:
• substantial changes in the equipment of the Data centre;
• refurbishment/renovation of the premises where the Data centre is located;
• changes in environmental parameters (temperature, relative humidity, etc.);
• business changes, i. e. partnerships, mergers, acquisitions, opening of new markets/activities;
• significant changes in workloads and/or workload distribution.
Routine adjustments are those that would be done regularly, for example, due to changes in weather conditions or
IT workloads. Most of such external factors introduce non-linear effects in the formulas. For instance, increases in
the total workload of a Datacentre do not imply corresponding proportional increases in the energy consumption. As
an example, the simple adjustment of the baseline through a multiplying factor, therefore a relation obtained as a
linear regression, as in the expression:
Energy consumption = α x independent variable+ b (27)
is hardly ever possible. In general, it is therefore not possible to estimate values for the above parameters “theoretically” (i. e. without performing a new experimental assessment of the baseline). In certain specific cases it
53
might appear possible to perform such an estimate, but a general operational rule cannot be given and the
calculation of the adjustment will have to be performed on a case-by-case basis.
A non-routine adjustment would occur due to an isolated event, for example, an increase of the total DC surface
(new equipment). In this case, a new mathematical model has to be performed. As explained for PEsavings, a new
mathematical model needs to be performed.
3.6.2.4 Measurement boundaries determination & metering points
Figure 9 Figure 9 illustrates a typical scenario of a data centre. The total energy consumption taken by the grid is
measured at point A, for example with a meter close to the POD. For other forms of energy such as gas, fuel, or
chilled water the measurement is taken at the point of delivery of each source, for example as input to the non-RES
element of Figure 9, while for renewable generation onsite the energy produced and consumed is measured with a
meter at the output of the RES element.
Therefore all forms of energy are considered, as primary (source) energy, and converted in primary energy following
the conversion factors defined in the document pertaining to primary energy savings.
Figure 9: Data Centre Control Volume and Measuring Points
3.6.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
All the required variables can be metered using permanent energy meters. They should be provided of a
communication protocol module such as for example ModbusRTU RS485 or equivalent. The measure error has to be
1% or lower (active energy).
3.6.2.6 Metering equipment commissioning procedure
Meter range has to be consistent with the variable range. Meters setup during commissioning should include
consistent unit selection. Meters calibration should take place preferably once a year.
54
3.6.2.7 Metering assumptions
Assumptions related to the costs of the electricity and thermal energy in the different countries should be taken into
considerations.
3.6.2.8 Metering sampling frequency
Data collected from the field have to be sampled with an hourly frequency.
3.6.2.9 Metering duration (post-retrofit period)
Concerning metering duration please refer to section 3.6.2.2.
3.6.3 Example Let us assume a typical scenario, also illustrated within Figure 9. The data centre is connected to the grid to
accommodate for its basic needs in energy, while is also equipped with a diesel generator as a back-up energy
source.
The first step then would be to identify the baseline scenario in advance to any intervention to the data centre. For
related details, please refer to section 3.6.2.2. After some action has been performed on the data centre, the need
for an assessment of EES arises; a simple step-by-step guide follows:
a. Define period Δt.
b. Calculate the TCO for the onsite energy production plant for the period Δt.
c. Calculate , the cost of a KWh produced onsite
d. Adjust the baseline taking into account the various modifications that might have taken place.
e. Calculate , the average cost of energy provided by an external energy supplier
f. Calculate EES according to the formula.
Table 11 provides an overview of measured and computed parameters pertaining to the baseline scenario, whereas
Table 12 lists the equivalent values for the improved scenario. Let’s assume variable cost of energy per 4 periods
over a total duration of 1 year. For ease of comparison we further assume that energy prices between baseline year
and “current” year remain the same. In addition, we assume that the data centre consumes a total of 100,000 kWh
of energy per year.
Table 11: Adjusted baseline scenario parameter
Period 1 Period 2 Period 3 Period 4 Total
Days 100 120 60 85 365
EDCgrid (kWh) 25,000 30,000 20,000 25,000 100,000
COSTgrid (€/kWh) 0.2 0.19 0.22 0.21
Tot. Exp. Grid (€) 5,000 5,700 4,400 5,250 20,350
EDCgas (litres) 0 0 400 0 400
Costgas ((€/litres) - - 0.5918 -
Tot. Exp. Onsite (€) - - 234.58 - 234.58
Tot. En. Exp. (€) 5,000 5,700 4,634.58 5,250 20,584.58
Table 12: Improved scenario parameters
Period 1 Period 2 Period 3 Period 4 Total
18
Dec 2013; http://www.indexmundi.com/commodities/?commodity=diesel&months=120¤cy=eur
55
Days 100 120 60 85 365
EDCgrid (kWh) 15,000 20,000 15,000 20,000 70,000
COSTgrid (€/kWh) 0.20 0.19 0.22 0.21
Tot. Exp. Grid (€) 3,000 3,800 3,300 4,200 14,207.60
EDCgas (litre) 0 0 400 0 400
EDCRES (kWh) 10,000 10,000 5,000 5,000 30,000
Costgas - - 0.4419 -
CostRES 0.18 0.18 0.18 0.18
Tot. Exp. Onsite (€) 1,800 1,800 1,074.35 900 5,574.35
Tot. En. Exp. (€) 4,800 5,600 4,374.35 5,100 19,874.35
In this example, EES would be equal to 3.45% denoting the percentage of energy related cost savings (even though
the data centre’s total energy consumption remained the same).
3.7 Grid Utilization Factor
3.7.1 M & V Plan Scope and Metric Overview The scope of the M & V plan described hereafter is to provide the specifications required to assess correctly the Grid
Utilization Factor (GUF) belonging to the category: “Renewables integration: Energy produced locally and Renewable
usage. GUF represents the percentage of time that the local generation does not cover the electricity demand (in
this case, a DC, but in general this will be applicable to any kind of consumer), and thus how often energy must be
supplied by the grid..
This metric is linked to the net exported electricity and is defined according to the following formula:
(28)
(29)
where:
is a step function representing the capability of the Renewable Energy Sources (RES) of covering the
demand at time ,
and are the start and end time respectively for GUF monitoring,
represents the net exported electricity at time and is given by:
(30)
where:
is the aggregate exported electricity or the electricity generated at RES,
is the aggregate delivered electricity or the electricity demand.
For the metric calculation purposes equation (31) has to be transformed as follows: 19
Dec 2014; http://www.indexmundi.com/commodities/?commodity=diesel&months=120¤cy=eur
56
(31)
(32)
Where:
is a step function given by eq. (32),
is the measurement index,
is the number of measurements,
is the average value of the net exported electricity at the sampling period between measurements
and .
3.7.2 Measurements
3.7.2.1 Measurable variables determination
Following the metric description presented in section 3.7.1, the periods during which the renewable energy
generation is sufficient to cover the electricity demand or not need to be determined. As a result, the following
values have to be assessed:
: the electricity generated at RES and exported to the grid. It can be measured at the point of
connection between the electrical power plant and the grid.
: the electricity acquired from the grid. It can be usually assessed through the electrical counter
installed by the utility for billing reasons.
the portion of time during which the net exported electricity, as given from equation (30) is negative.
The system setup for GUF assessment is depicted in Figure 10. Based on this figure, can be measured at point
B, while can be measured at point C. As a result:
(33)
57
Figure 10: System setup for GUF assessment
3.7.2.2 Baseline identification and calculation
The baseyear conditions are the Data Centre (DC) conditions during 12 months preceding the decision to deploy and
use (additional) renewable energy sources. These conditions can be identified from the electricity bill of the utility
serving the DC. Moreover, the following should be taken into account as baseline conditions affecting the DC
electricity consumption:
a report on the number, type and yearly energy profiles of any on-site RES;
a lighting level survey;
a report of the number, type and energy characteristics of IT equipment (CPU, RAM, HDD, networking
devices), along with an estimate of the operating hours and load of each;
a report of the number, type and energy characteristics of non-IT equipment (CRAH, CRAC, etc.), along with
an estimate of the operating hours and load of each;
a report of the number, type and energy characteristics of facility equipment (air-conditioning, heating,
lighting, etc.), along with an estimate of the operating hours and load of each;
a record of the temperature setting of cooling equipment;
a record of the used capacity of CPUs, RAMs, HDDs;
a record of the IT load for each month of the year;
a record of the provided services, along with the contracted SLAs and a count on the number of customers
a report of the number, type and energy characteristics of energy-reuse devices;
a record of the number of working days and hours for each month of the year;
a summary of weather and climatic data for each month of the year;
a report on the number, type, position and error of metering devices;
a record of any energy-efficient techniques in place;
the goal of workload and energy optimization (if any) per day for each month of the year.
The sampling period for measurements should be at least 15 minutes.
The baseyear energy use is metered at point C of Figure 10 spanning a 12-month period.
The baseyear renewable energy use is metered at point B of Figure 10 spanning a 12-month period.
58
The baseyear energy data shall be analysed as follows. Linear regression shall be applied on monthly total and
renewable electricity use, as well as total electricity demand, metering period length and degree days. The latter
shall be derived by third party information providers. Correlation of weather with electricity demand, (total or
renewable) supply and (total or renewable) use is expected to be identified.
Savings derived from renewable energy usage will be determined under post-retrofit conditions.
3.7.2.2.1 Baseyear Electricity Use
The baseyear electricity use for Eq. (32) is taken directly from the metering equipment at point C Figure 10 without
adjustment.
3.7.2.2.2 Baseyear Renewable Energy Use
The baseyear renewable energy use for Eq. (30) is taken directly from the metering equipment at point B of Figure
10 without adjustment.
3.7.2.2.3 Post-Retrofit Electricity Use
The post-retrofit electricity use for Eq. (30) is taken from the metering equipment at point C of Figure 10 without
adjustment.
3.7.2.2.4 Post-Retrofit Renewable Energy Use
The post-retrofit renewable energy use for Eq. (30) is taken from the metering equipment at point B of Figure 10
without adjustment.
3.7.2.3 Baseline adjustments in case of anticipated changes
Baseline adjustments may be needed to bring baseyear energy use to the conditions of the post-retrofit period.
Adjustments are not needed to calculate the KPI, but to compare the KPI between two different time intervals (e.g.
two consecutive years after installing a PV power plant in the DC).
3.7.2.3.1 Routine Adjustments
3.7.2.3.1.1 Electricity Demand
The electricity demand is expected to be affected by changes in the external temperature (Degree Days) and the
number of operating days. As result, the following routine adjustments are needed:
The electricity demand of the cooling equipment may vary depending on the ambient temperature.
Appropriate adjustments should be made, based on manufacturer’s specifications.
The electricity demand of air-conditioning and heating facilities should be adjusted to ambient temperature
based on manufacturers’ specifications.
Electricity demand due to lighting requirements within the DC may vary depending on the daylight hours.
Electricity demand may vary due different IT workload between years and appropriate adjustments should
be made
3.7.2.3.1.2 Renewable Energy Generation
The electricity generation of installed on-site RES may be affected by weather conditions, such as solar radiation and
wind speed. Specifically, solar radiation directly influences the production of photovoltaic (PV) and solar thermal
systems, while the wind speed directly influences the production of wind turbines. Adjustments on the renewable
energy generation must be made according to the manufacturers’ datasheet for the current configuration and
weather conditions.
59
3.7.2.3.2 Non-routine Adjustments
Procurement of new equipment during the post retrofit period raises the need for non-routine adjustments. The
new equipment may refer to IT (CPU, RAM, HDD, networking devices), non-IT (cooling equipment), facilities (air-
conditioning units, heating, lighting), as well as on-site RES. IT and non-IT installed power affects the amount of
electricity demand and consumption. Moreover, software changes, such as cloud adoption or virtualization may
affect the electricity demand of the IT equipment. The adjustments should refer to both the electricity consumption
and demand, referring to manufacturers’ factsheets on electricity consumption.
In the following an example is given for local RES, which affect the amount of exported electricity. The impact on the
annual balance depends on the typology of renewable energy source that has been installed. The adjustment factor
depends on the ratio between annual production and installed power. In other words:
(34)
Where:
: baseline exported energy adjusted according to normalization variables for the RES ,
: installed peak power for the RES during the test period,
: installed peak power for the RES during the baseline period,
: specific energy factor (kwh/kWp) for the RES
3.7.2.4 Measurement boundaries determination & metering points
The area of interest for GUF measurements is depicted in Figure 10 within a grey-line polygon.
Maximum boundaries: energy balance between electricity exported to the grid and electricity delivered to the grid is
measured at the POD. All onsite renewable power plants are connected below the POD. In this case a single
metering point is needed.
Minimum boundaries: each single onsite renewable energy sources power plant is metered and each single power
supply switchboard is metered too.
3.7.2.5 Metering equipment desired characteristics/capabilities (HW / SW)
All the required variables can be metered using permanent energy meters, installed on the metering points
highlighted in the previous paragraph. Those energy meters should comply with the following requirements.
- Meters range has to be consistent with the metered variables range and these meters should allow a
consistent unit selection.
- Meters have to be provided of a communication module (ModbusRTU RS485 protocol or equivalent),have to
be connected to a gateway that via Ethernet allows concentrating data that are stored in log files or in a
database. A properly sized storage system has to be designed and installed and data must be available for
the next phase of analysis and verification. In this way, each meter, becomes a node of the network.
- Meters have to be equipped with the required auxiliary devices such as amperometric transformers,
voltmetric commutators, surge protectors and surge arresters
- Meters and auxiliary devices have to be chosen according to the supply voltage. LV point of measures have
to be preferred on MV point of measures due to lower metering costs.
Finally, measurement errors (defined by the HW’s accuracy classes), connections, communication protocols and
networking have to be compliant with the existing standards (ANSI, IEC, IEEE, CEI EN). The requirements specified in
these standards have to be considered as minimum values for the meters under normal working conditions. For
60
special application, higher constraints might be necessary and should be agreed between the user and the
manufacturer.
3.7.2.6 Metering equipment commissioning procedure
The commissioning process assumes that owners, programmers, designers, contractors, operations and
maintenance entities are accountable for the quality of their work. Commissioning process includes several
procedures that are required in order to ensure the adequacy and the degree of precision required for the quality of
measurement and the product safety.
Once the measurement system is installed it a test procedure has to be applied. During this procedure, once the
meter settings are set, the measure collected by the installed meter is compared to the measure collected trough a
portable configured meter. The test procedure must not be confused with the calibration procedure performed by
the manufacturer. The test procedure includes the test of the communication channels (speed and reliability) and
the sampling time.
Together with the test procedure a maintenance procedure is required. The key tests required are:
Every time the gateway don’t communicate with the storage system or one or more nodes don’t communicate with
the gateway it is necessary to check and solve the problems in due time.
Periodically (once a year) it is important to inspect the measurement equipment and repeat the calibration
procedure.
Every time hardware changes occur, the compliance between the meter range and the physical variable range must
be checked and guaranteed.
3.7.2.7 Metering assumptions
No comment
3.7.2.8 Metering sampling frequency
The required meter sampling frequency is 64 samples/cycle. The metered energy minimum sampling frequency is of
one second. Higher sampling rates are not required since the variability of the metered physical values is not so
rapid. GUF value must be stored at least every 15 minutes.
3.7.2.9 Metering duration (post-retrofit period)
Concerning metering duration at least a whole year data set should be collected: this is because renewables have a
yearly production profile.
3.8 Analysis & Verification
Important Notice: The whole section is going to be the same for all identified metrics, namely it should be
consistent across all developed methodologies. General ways of dealing with analysis and verification will be
provided, their application depending on DC configurations.
3.8.1 Error Filtering Erroneous measurements introduce inaccuracies to the measured quantities, which subsequently propagate to the
calculation of the metrics. As a result, the performance indicators are distorted, providing a falsified picture of the
system performance. Therefore, error filtering techniques must be employed, in order to mitigate the effect of
erroneous measurements on the calculation of the KPIs.
61
In the direction of pinpointing measurements that are likely to be erroneous the mean value and the standard
deviation of the last 5 measurements are retained and compared to the value of the current measurement. Having a
sample of actual readings
the Mean value of the measurements is defined by
,
(35)
and the Sample Standard Deviation is defined by
(36)
Thus, if the current measurement falls within the range , it can be considered to be within
the expected range. However, if the measurement falls out of this range, the measurement is flagged as potentially
erroneous and the DC operator is prompted to repeat the measurement. If the repetition provides a very similar
value (for example, within 2% of the value flagged as potentially erroneous), then the flag is eliminated and the value
is accepted as correct. The new measurement is then registered and used for the calculation of the metric. Else, if
the values are very different, it is flagged as erroneous.
Apart from employing the above process for pinpointing potentially erroneous measurements, the DC operator also
has to isolate erroneous measurements. In particular, measurements that, given the specifics of each DC, are clearly
out of range and remain out of range despite the repetition of the measurement should be filtered out by the DC
operator. The erroneous measurements are then substituted by the average of the preceding ( ) and the
following ( measurement.
3.8.2 Statistical Analysis of Baseline models The statistical analysis and evaluation of the baseline models is only applicable to metrics where baseline
adjustments are required. Such statistical analyses are essential to evaluate the accuracy of the baseline models.
Specifically, in order to evaluate the extent to which the variations of the actual baseline data are explained by the
baseline model the Coefficient of Determination ( ) should be calculated. is defined by
, (37)
where:
is the model predicted value at the individual time period
is the actual observed value at the individual time period
is the mean value of the actual observed values, as defined by eq. (35)
The range of the possible values of the coefficient of determination is 0 to 1. A value of zero indicates a poor
baseline model where the variations of the actual values are not explained by the model and a value of 1 indicates
an excellent baseline model predicting the variations of the actual observed values to the fullest. In general, the
closest the value of the coefficient of determination is to 1 the better the baseline model is. A generally accepted
value of is 0.75, whereas low values of indicate that the baseline model needs to be improved.
3.8.3 Uncertainty analysis of the results achieved In order to evaluate the achieved results (primarily through the calculation of the saving KPIs) we need to validate
their accuracy and precision. In this course, the standard error of the reported results needs to be defined along with
the expected range of the results with a given confidence level.
62
In general, if a quantity is involved in the calculation of the achieved results, we can obtain the standard deviation of
the measured quantity by eq. (36). However, if not just a sample, but the entire population of measurements of the
measured quantity is available, then the population standard deviation is defined by
, (38)
and the Standard Error is defined by
SE =
,
(39)
However, if a baseline adjusted quantity is involved in the calculation of the achieved result the standard error of the
baseline adjusted quantity is defined by
, (40)
where, is the (baseline) model predicted value at the individual time period , is the actual observed value at
the individual time period and is the number of independent variables in the baseline model.
Moreover, if the achieved result is obtained as the sum or difference of independent quantities of
given standard error (SE) the standard error of the result can be estimated by
, (41)
Having defined the standard error, one can define the absolute precision at a given confidence level and the
estimated range of the result with the predefined confidence level.
To elaborate, the Absolute Precision is defined as: t · SE, where t depends on the number of actual readings n and is
obtained from sample standard error tables (Table 13). Such t-Tables can be found in statistic tables and books20.
Table 13: t-Table
Degrees of
Freedom (DF)
Confidence Level Degrees of
Freedom (DF)
Confidence Level
95% 90% 80% 50% 95% 90% 80% 50%
1 12.71 6.31 3.08 1.00 16 2.12 1.75 1.34 0.69
2 4.30 2.92 1.89 0.82 17 2.11 1.74 1.33 0.69
3 3.18 2.35 1.64 0.76 18 2.10 1.73 1.33 0.69
4 2.78 2.13 1.53 0.74 19 2.09 1.73 1.33 0.69
5 2.57 2.02 1.48 0.73 21 2.08 1.72 1.32 0.69
20
http://www.evo-world.org/index.php?option=com_rsform&formId=125&lang=en
63
6 2.45 1.94 1.44 0.72 23 2.07 1.71 1.32 0.69
7 2.36 1.89 1.41 0.71 25 2.06 1.71 1.32 0.68
8 2.31 1.86 1.40 0.71 27 2.05 1.70 1.31 0.68
9 2.26 1.83 1.38 0.70 31 2.04 1.70 1.31 0.68
10 2.23 1.81 1.37 0.70 35 2.03 1.69 1.31 0.68
11 2.20 1.80 1.36 0.70 41 2.02 1.68 1.30 0.68
12 2.18 1.78 1.36 0.70 49 2.01 1.68 1.30 0.68
13 2.16 1.77 1.35 0.69 60 2.00 1.67 1.30 0.68
14 2.14 1.76 1.35 0.69 120 1.98 1.66 1.29 0.68
15 2.13 1.75 1.34 0.69 ∞ 1.96 1.64 1.28 0.67
DF = n-1
Where n = sample size.
Subsequently, the true value of any statistical estimate is expected with a given confidence level, to fall with the
range defined by
Range = estimate ± absolute precision (42)
Where “estimate” is any statistically derived value of a parameter of interest and in the context of the above analysis
the value of the achieved result (primarily savings result).
Thus, the average value of a set of 6 measurements
Measurement Actual Reading
1 15
2 18
3 13
4 19
5 18
6 17
is defined by the Mean value of the measurements
(43)
the Variance
64
(44)
the Standard Error
SE =
(45)
And for a confidence level of 95% the absolute precision
t · SE = 2.57 · 0.919=2.36 (46)
So there is a 95% confidence that the true mean value lies in the range
Range = 16.7 ± 2.36. (47)
3.9 Reporting
3.9.1 Reporting format An indicative reporting template is presented hereafter.
Metering Equipment:
Metering Point:
Metering Sampling Frequency:
Metering Assumptions:
Date / Time Measurable Variable 1
Value:
5 Last Measurements Measurable Variable 2
Value:
5 Last Measurements
Mean Deviation Mean Deviation
3.9.2 Reporting frequency The frequency of such a report is determined by the metering duration defined in Paragraph X.2.9 of each metric.
65
4 References
ASHRAE. (2009). Real-Time Energy Consumption Measurements in data centers . American Society of Heating,
Refrigerating and Air-Conditioning Engineers, Inc. . Atlanta, GA, USA: ASHRAE.
EIA. (2010). Energy Calculators. White Paper, EIA.
Global TaskForce. (2014). Harmonizing Global Metrics for Data Center Energy Efficiency.
ISO/IEC JTC 1/SC 39 ITEE. (2015). ISO/IEC CD 30134-4: Information Technology -- Data Centres -- Key performance
indicators -- Part 4: IT Equipment Energy Efficiency for Servers (ITEE).
ISO/IEC JTC 1/SC 39 PUE. (2015). ISO/IEC DIS 30134-2: Information Technology -- Data Centres -- Key performance
indicators -- Part 2: Power usage effectiveness (PUE).
ISO/IEC JTC 1/SC 39 REF. (2015). ISO/IEC DIS 30134-3: Information Technology -- Data Centres -- Key Performance
Indicators -- Part 3: Renewable Energy Factor (REF).
The Green Grid / ASHRAE. (2013). PUE : A Comprehensive Examination of the Metric.
The Green Grid. (2010). ERE: A Metric for Measuring the Benefit of Reuse Energy from a Data Center. The Green Grid.
The Green Grid.
The Green Grid. (n.d.). Usage and Public Reporting Guidelines for The Green Grid's Infrastructure Metrics PUE/DCiE.
Global TaskForce. (2014). Harmonizing Global Metrics for Data Center Energy Efficiency.
ISO/IEC JTC 1/SC 39. (2014). ISO/IEC DIS 30134-2: Information Technology -- Data Centres -- Key performance
indicators -- Part 2: Power usage effectiveness (PUE).
Molebroek, E., Stricker, E., & Boermans, T. (2011). Primary Energy Factors for electricity in buildings. Ecofys
Netherlands B.V.
The Green Grid. (2010). Carbon Usage Effectiveness (CUE): A Green Grid Data Center Sustainability Metric.
Noris, F., Musall, E., Salom, J., Berggren, B., Jensen, S. Ø., Lindberg, K., & Sartori, I. (2014). Implications of weighting
factors on technology preference in net zero energy buildings. Energy and Buildings, 82, 250-262.