single-pole operation leads to hazardous
TRANSCRIPT
-
7/26/2019 Single-Pole Operation Leads to Hazardous
1/12
1
AbstractBC Hydro recently developed a radial 287 kV
Northwest Transmission system which includes a long (340 km)
line. After the terminal station it connects to two shorter lines.
Short time after when the system went into the service, the long
line experienced multiple line-to-ground faults due to icing and it
led to single-phase trip protection and auto-reclose operations.
During open-pole condition phase duration, the floating phase on
the short lines experienced unsafe over-voltages causing
transformer and reactor protection trips. This paper will use
disturbance records to explain the sequence of events and present
the detailed waveform analysis. It was found that the sensitive
phase-to-phase fault protection operated on the shunt reactor.
The transformer protections operated on excessive magnetizing
current due to the differential restraint element fifth harmonic
currents dropping below the setting threshold (35% on three
phases). It appeared that the harmonic restraint dropped on
higher voltage due to excessive saturation causing flux to transfer
from transformer core to tank. The disturbance has been
simulated with EMTP and this helped to identify the causes of
the over-voltage. The paper will also discuss the simulation
results and some recommend solutions to avoid re-occurrence of
the over-voltages problem.
Index Terms Single-Pole Operation, Temporary Over-
Voltage, Transformer over-excitation
I. INTRODUCTION
he BC Hydro transmission system, in a remote corner ofthe province, had a sizeable addition brought into service
near the end of 2014. To spur economic activity in the region a
series of new transmission lines were constructed to
accommodate both non-utility generation and large industrialloads. The main 287 kV transmission line to the area is very
long and had significantly more faults than anticipated in
months following the first energization. The protectionsystems had been very dependable during all the faults in the
initial months and in the time since then as well. The security
of the relaying system has also been quite good. It was tested
though under a severe unintended operating condition for a
fault that occurred on January 7 th 2015. This paper outlines
how multiple faults that day left the system in the unintendedoperating configuration. This condition resulted in
approximately 1.7 pu voltage at multiple substations. Next the
paper will discuss how protection relaying in the regionresponded while the system was operating in a critical state.
Three protection relays operated while there was no fault
Submitted September 2015
Mukesh Nagpal e-mail BC Hydro, Burnaby, BC V3N 4X8, Canada
within their protection zones. The paper includes detailedsteady-state and high frequency analysis to re-create the
conditions witnessed in the field. Finally, the paper will briefly
describe potential remedies to prevent further abnormal
conditions in the system.
II. BCHYDRO SYSTEM
BC Hydro, the third largest utility in Canada, possesses
major hydro-electric generation assets. These resources,
primarily located in the northern (Peace River) region of theprovince and in the south eastern (Columbia River) region, are
remote from the south-west corner of the province where most
of the demand for electricity is concentrated.
A. Northwest Transmission System
Figure 1 shows geographic one-line diagram of the
Northwest Transmission System (NTL). It consists of a new
287-kilovolt (kV), 340 km long transmission line, 2L102,connecting the existing BC Hydro Skeena (SKA) Substation
near Terrace with a new substation Bob Quinn (BQN) near
Bob Quinn Lake.
The system was expanded to provide a secure
interconnection point for clean generation projects via 39 km
long 287 kV transmission circuit 2L379. The three connected
non-utility generating clusters are Forrest Kerr (FKR), andVolcano Creek (VOL), all on the Iskut River near Forrest Kerr
Creek, north of Stewart in northwestern BC. The total outputfrom these clusters would be 305 MW from run of river
generation units. These generators supply clean electricity to
support development in the area.
The system is also serving the industrial and residential loadvia a three terminal 287 kV 110 km long transmission line
2L374. The transmission system one - line diagram including
existing BC Hydro northern region transmission network, the
NTL, new Bob Quinn substation and IPP generation andtransmission system is shown in Figure 2. The area can now
reduce greenhouse gas emission by enabling communities now
relying on diesel generation to connect to the BC Hydrotransmission grid as well.
B. Detail of a 287 kV Line in Northwest System
Figure 3 shows a simplified one-line diagram showing
circuit 2L102, which was involved in the incident. As shown
in Figure 1, this line is the only transmission path betweenSkeena (SKA) Substation and Bob Quinn (BQN) switching
stations. The line is 340 km long and is fully transposed. There
is an optical ground wire (OPGW) cable run between the topsof high voltage electricity towers. The optical fiber within the
Mukesh Nagpal, Terry Martinich, Ska-Hiish, Tyler Scott, Gurinder Hundal and Apollo Zhang
BC Hydro, BC, Canada
Single-Pole Operation Leads to Hazardous Over-
Voltage on Adjacent Lines
T
-
7/26/2019 Single-Pole Operation Leads to Hazardous
2/12
2
cable is used for high speed protection and SCADA functions.
Tower construction, conductor data along with the line
parameters determined from the construction data are listed in
Appendix I. There is 35% series compensation at the BQN endof line and 72% positive sequence shunt compensation using
two reactors at SKA and one at BQN. The shunt reactors at
SKA (2RX1 & 2RX2) are fixed and the one at BQN
(2RX231) is switchable.
2L102 is protected by modern microprocessor-based relayswith a high speed, sub-cycle, current differential scheme. The
line breakers are rated as having a three cycle interrupt time.Therefore overall fault clearing time is less than four cycles
for all bolted faults. This speed is within the performance
target specified in NTL system planning studies.
Figure 1: BC Hydro Northwest Transmission SystemGeographical Map.
Figure 2: Northern Region BC Hydro Transmission System
One-Line Diagram.
To maintain the system stability, single-shot high speed
automatic reclose is attempted after line trips. The reclose
scheme is designed to initiate single-pole trips for single-
phase-to-ground faults and three-pole trips for all multi-phasefaults. The SKA bus is the lead or master end for auto-reclose
and the associated breakers 2CB7 and 2CB8 are equipped with
point-on-wave (POW) closing to minimize the line pickuptransients. 2CB7 is the first breaker to close followed by
2CB8. The BQN bus is the follow end with 2CB3 closing first
and 2CB4 closing second.
-
7/26/2019 Single-Pole Operation Leads to Hazardous
3/12
3
Figure 3: Simplified 2L102 One-Line Diagram NTL
System.
III. EVENT DESCRIPTION
This section is divided into two subsections. The firstsection describes a series of incidents which includes five
individual faults at different times and the nature of these
faults. The events with time stamps are listed in sequence inTable 1. The second subsection focuses specifically on the
fifth event. During this event the entire system north of BQN
experienced significant over-voltage on one phase. Thesubsection presents detailed analyses of the waveforms
recorded by the high speed digital fault recorders during this
incident.
A. Overview of the Incident
Table 1 lists the sequence of events for this series of events.On 7th January, 2015 at 05:38:39 PST, the first Phase C-to-
ground fault occurred on 2L102 about 2 km from BQNstation. The line protection responded correctly to trip single-
pole (Phase C) in three cycles and executed an auto-reclose
after the one second open pole interval. The fault was caused
by an OPGW wire sagging under the heavy snow
accumulation on the wire. Since the sagging wire reducedclearance between the phase conductor and ground wire, it
took longer for the fault to self-extinguish than expected.
Hence, the line was auto-reclosed onto a persistent fault. The
failure of auto-reclose resulted in a three-pole trip at both line
terminals (SKA and BQN). Referring to system one-line
diagram in Figure 2, 2L102 protection operation keys direct
transfer trip (DTT) to the downstream line protection relays,
2L374 and 2L379, to isolate the remote generation andtransmission customer load upon disconnection from BC
Hydro integrated system. On receipt of DTT, 2L374 tripped at
BQN terminal and RDC entrance circuit breakers. Similarly,
2L379 tripped BQN terminal as well as FKR and VOL
entrance circuit breakers. Note that RDC load remaineddisconnected and 2L379 remained open-end at FKR and VOL
throughout the rest of events that morning.
A second Phase C-to-ground fault occurred at 05:44:42.732
PST; shortly after BC Hydro control center restored 2L102.
The control center had not yet restored 2L374 and 2L379.
Similar to the first event, the line tripped single-pole and then
ended up tipping three-pole trip due to the auto-reclose failure.The third and fourth events are failed attempts to energize
2L102 from SKA station by BC Hydro control center. They
both failed due to a persistent fault on the line.
Before the fifth event, BC Hydro control center was in the
process of restoring the Northwest Transmission system. It
was restored to a point such that 2L102 was fully restored atboth ends, 2L374 energized from BQN to TAT and open
ended at RDC, and 2L379 energized at BQN but open endedat FKR and VOL. In this system configuration, 2L102 from
SKA is the only source in the Northwest system. A Phase C-
to-ground fault on 2L102 reoccurred at 06:21:21.972 PST at
the same location as the previous events - 2.8 km from BQN.Breakers associated with Phase C of 2L102 were tripped by
the protection. Because non-utility generation was not
reconnected after the previous fault, opening of Phase Cbreakers on 2L102 led to loss of source on that phase for all
three circuits in the Northwest Transmission system. In
absence of regulated source on Phase C, the voltage on that
phase in the BQN-2L374-2L379 sub-system experienced atemporary over-voltage exceeding 1.7 pu. The high voltagecaused one shunt reactor and two transformer protections to
operate. This event is the main subject of analysis being
reported on this paper. The remaining paper will discussprotection response during this event, analytical simulations
replicating the event and methods to avoid its reoccurrence.
B. Over-Voltage Waveforms
Figure 4 shows three phase-to-ground voltages captured by
the digital fault recorders (DFR) at the BQN bus. Phase C-to-ground voltage exceeded 1.6 pu within two cycles after
opening of Phase C beakers on 2L102. It is interesting to note
that, during the temporary over-voltage (TOV), Phase B-to-ground and the C phase-to-ground voltages are nearly 180
degrees out-of-phase. Figure 5 shows phase-to-phase voltages
which indicate that the BQN T3 delta-connected windingbetween Phases B and C was subjected to the over-voltage and
saturation of that winding. This over-voltage resulted in BQN
T3 tripping in about 10 cycles after the single-phase opening.
Since BQN T3 and 2RX22 share the tripping zone, 2RX22
was disconnected from the system at the same time. This leadto the voltage increasing yet again, this time to more than 1.7
pu. About 8.5 cycles after tripping of BQN T3 and reactor
-
7/26/2019 Single-Pole Operation Leads to Hazardous
4/12
2
su
Ta
1
2
3
4
5
X22, TAT
siding.
ble 1:Sequen
Time stamp
05:38:39.942
05:38:41.17
05:38:41.21
05:41:12.47
05:44:42.732
05:44:43.941
05:47:42.54
05:48:47.02
06:11:33.00
06:15:18.00
06:15:28.00
06:21:21.97
06:21:22.02
06:21:22.182
06:21:22.32
06:21:22.42
T1 tripped
e of Event on
2L102 initSKA and
2L102 autSKA and
2L102 ope
trips to 2L
2L374 trip
2L379 trip
2L102 re-e
2L102 sin
and BQN
2L102 aut
SKA and
SKA 2L10to the persi
SKA 2L10to the persi
2L102 suc
BQN
2L379 re-e
2L374 re-e
2L102 C-
BQN
2L102 sin
and BQN
BQN 287over-volta
BQN T3 P
of serviceBQN 287
higher ove
TAT T1 P
service
BQN 287
below 1 pu
BQN 2RX
287 kV bu
nd the ove
07 January, 2
Event
al single-poleQN
-reclose fail,QN
terminal logi
74 and 2L379
at BQN and R
at BQN, FKR
nergized at bo
le-pole trip (
-reclose fail,
QN
2 energizatiostent fault
2 energizatiostent fault
cessful restora
nergized at B
nergized at B
fault initiati
le-pole trip (
kV bus Ce (1.6 pu.)
N tripped HV
kV bus C
-voltage (1.7
tripped 2CB
kV bus C ph
.
25 PN trippe
de-energized
-voltage star
15
trip (C phase
three-pole tri
c initiate tran
DC
and VOL
h ends
phase) at S
three-pole tri
attempt fail
attempt fail
tion at SKA
N
N and TAT
on, 2.8 km fr
phase) at S
hase experie
CBs, 2RX22
hase experie
u.)
2, TAT T1 ou
ase voltage d
bus CBs, B
ted
at
at
fer
A
at
ue
ue
nd
m
A
ce
out
ce
of
op
N
Figure
BQN 2
Figure
BQN 2
4: The Phase
7kV Bus.
5: The Phas
7 kV Bus.
-Ground Volt
e-Phase Volta
ages Capture
ges Captured
4
by DFR at
by DFR at
-
7/26/2019 Single-Pole Operation Leads to Hazardous
5/12
5
IV. PROTECTION AND CONTROL DESCRIPTION
In two months following Northwest Transmission system
energization, 2L102 had several phase-to-ground faults and
the protection performed correctly during all faults. Previous
sections detailed how the system ended up in an undesirableoperational state on the morning of 7 thJanuary 2015.
The following protection section will detail the protection
operations in the NTL system that morning besides the 2L102
operations. It will also discuss the protection operations thatdid not occur. Section V will discuss the measures taken to
quickly take action in the protection system to reduce the
chance of a high temporary over-voltage in the future.
A. Duration of Over-Voltage Condition
The 2L102 line protection had single-phase tripping (SPT)
enabled on January 7th, which opens only the faulted phase
for any single-phase-to-ground fault. If the fault persists whenthe open phase is closed (unsuccessful reclose), then the line
protection would open all phases with three-phase tripping
(3PT) logic, and send direct transfer trips to open entrance
breakers of RDC, FKR and VOL. The single-phase openinterval of the line is approximately 60 cycles (1 second). Thefirst phase-to-ground fault occurred at 5:38 AM and it was
persistent so, a direct transfer trip was sent to RDC, FKR, and
VOL taking them offline for the remainder of this time period.During the 6:21 AM event 2L102 line protection detected the
single-phase-to-ground fault. During the approximately 1
second single-phase open (SPO) period, a number of additionprotection operations occurred, some unexpectedly.
B. BQN Transformer T3 Protection Operation
BQN T3 is a 10 MVA transformer with an HV delta
winding and an LV wye winding. The transformer serves a
fourth harmonic filter bank and the station service transformerat BQN substation.
As shown in Figure 3, the voltage between Phase B and C
became very high (more 1.6 pu) during open pole period. It
saturated the delta winding of BQN T3 connected between the
two phases. Figure 6 shows the disturbance records from thetransformer differential relay. Three analog traces on top are
three-phase line currents processed by the 60-Hz digital filter
embedded in the relay. Two analog traces in the middle of thefigure are fifth harmonic frequency content relative to the
fundamental frequency in differential current measured by the
relay for the B and C phases. In bottom part of the figure,digital traces are illustrating responses various relay elements
to the differential currents measured when the B-to-C windingwas overexcited by over-voltage. To illustrate distorted nature,
Figure 7 shows the unfiltered analog traces of the line currents
into the transformer. T3 primary (287 kV side) currentsdemonstrate that, with harmonic distortion considered, these
currents were about 3 times the 20 Arms rated primary
current. Though not shown, negligible currents were comingout of the transformer low-voltage windings confirming that
the high-side currents were transformer magnetizing currents.
In Figure 6 and Figure 7, Phase B and C line currents werepractically 180 out-of-phase which confirmed the saturation
of the B-to-C winding transformer core. There was negligible
line current in Phase A.
The magnetizing currents on high-side appeared as Phase B
and C differential or operate currents. However, the relay
operation was initially blocked for approximately three cyclesby the 2nd and 5th harmonic elements as shown by digital
traces in Figure 6. The relay was set to restrain the trip
operation when the 2ndharmonic component of the differential
current exceeded 15% of the fundamental frequency current inone or more phase. Likewise, 5thharmonic restraint was set to
35%. Once the 2nd and 5th harmonic current content droppedbeyond their individual setting threshold, the relay tripped.
The BQN T3 tripping zone trips 287 kV circuit breakers
2CB2 and 2CB3. This protection operation also tripped reactor
BQN 2RX22 as collateral since they share a tripping zone. It
is likely that BQN 2RX22 would have eventually tripped aswell if given more time.
Figure 6: From the BQN T3 Protection Event Report,
Showing the Filtered Primary Currents.
Figure 7: From the BQN T3 Protection Event Report,
Showing the Unfiltered Transformer Magnetizing
Currents.
C. TAT Transformer T1 Protection Operation
TAT T1 is a 16.6 MVA transformer with an HV wye
winding and an LV wye winding. The transformer has aburied delta tertiary winding. The transformer serves the small
amount of distribution load in the area at 25 kV.
TAT T1 was also exposed to high voltages well above the
knee point voltage of the saturation characteristic. T1
conducted a relatively high current for 8 cycles before itsprotection tripped the transformer. From the event report, the
-
7/26/2019 Single-Pole Operation Leads to Hazardous
6/12
6
filtered primary currents are shown in Figure 8 and the
unfiltered currents appear in Figure 9. The maximum
instantaneous currents (Phase B and C) were about 170 A
peak, due to severe harmonic distortion. As a comparison, therated primary current is 33 Arms (47 A peak).
Like BQN T3, a high percentage of 5th harmonic current
blocked the transformer from operating instantaneously when
it began to saturate from the high voltage. This event report
also shows the 5th harmonic current dropping below 35% andtripping shortly afterwards. Compared to BQN T3, this
transformer took nearly 8 cycles longer to saturate to the pointwhere 5th harmonic current dropped below the inrush
threshold.
The unfiltered event report shows that the harmonic current
started to reduce while the fundamental current increased four
cycles after the relays event report was triggered. This alignswith the tripping of BQN T3 and RX22 and the subsequent
voltage rise that was recorded in the area. The even higher
voltage drove the TAT transformer core deeper into saturationcausing the magnetizing flux to leak out of the core and setting
up eddy currents in the non-laminated parts of transformer. As
a result, the fifth harmonic current dropped relative to thefundamental frequency component and contributed to
transformer tripping. Similar to other transmission anddistribution transformers in BC Hydro, the transformers in the
new NTL system were neither equipped with over-voltage nor
Volt-per-Hertz protection. Trips by the differential protection
saved the transformers from possible damage.
Figure 8: From the TAT T1 Protection Event Report,
Showing the Filtered Primary Currents
Figure 9: From the TAT T1 Protection Event Report,
Showing the Filtered Primary Currents
D. BQN Reactor 2RX25 Protection Operation
BQN 2RX25 is a 20 MVA oil filled reactor. The primarypurpose of the reactor is to compensate line charging
capacitance for 2L374.
The reactor protection consists of primary high impedance
differential protection as well as primary and standby phaseand ground over-current protection. The differential protectionis able to detect phase-to-ground faults and trip
instantaneously. It is unable to detect turn to turn faults
though. We deploy two sets of over-current protection toensure we have redundant protection to detect turn to turn
faults with the reactor.
The reactor was subject to a 1.7 pu voltage, which translates
to a higher than 1.7 pu current due to saturation. Currentsobserved during the over-voltage were 3 pu and were
sufficient to activate the inverse-time over-current protection.
Unlike the transformers discussed earlier there was no
differential current in the reactor. All current entering the
reactor left the corresponding low voltage terminal of thereactor. This reactor has a phase over-current element set to
pick-up at 1.2 times nominal phase current with an inverse
time tripping element. It was initially assumed that this wasthe element that tripped 2RX25. Upon investigating the event
reports from the protection relays it was determined that the
phase over-current element did not actually trip the reactor.
BC Hydro has devolved a specialized element to detect phase-to-phase faults deep within multi-phase reactors. A phase-to-
phase fault will result in an increase in phase-to-phase current
along with a corresponding decrease in phase-to-phase
voltage. Our element is looking for a 25 percent increase incurrent along with and 20 percent decrease in phase-to-phase
voltage. Figure 10 is an event report for the reactor over-
current protection. Element 50BCS is the Phase B to C over-current and Element 27CA is the Phase A to C under-voltage
element. Element SV5T is an 8 cycle pick-up timer required
for the phase-to-phase fault detector to operate.
-
7/26/2019 Single-Pole Operation Leads to Hazardous
7/12
7
Figure 10: From the BQN 2RX25 Protection Event Report.
The unfiltered event report in Figure 11 shows significantly
less harmonic current than either of the two transformers
experienced. More than 1.7 pu of phase-to-ground temporaryover-voltage was present at the transformer terminal at the
time of protection operation. The slope of the flux-current
characteristic of 2RX25 in the fully saturated region is
significantly higher than that of the transformer (air-coreinductance). Hence, the smaller harmonic content in thereactor currents.
Figure 11: From the BQN 2RX25 Unfiltered Event Report.
E. Observations on Protection Operations
The operation of the protection systems helped to reduce theseverity of the over-voltage in the area. This is especially true
following the clearing of TAT T1. Figure 12 shows an
immediate decrease in voltage following TAT T1 breakers
opening.
It is also interesting to review the breaker clearing times for
these operations. The three protection operations were nearlyuniform in their breaker clearing times as shown in Figure 12.
All the breakers in this system are rated at a 2.4 cycle nominal
clearing speed. In actual operation under these conditions theclearing time recorded by the protection relays was 6 cycles
more than double the rated time. All breakers are rated at 362
kV, but were exposed to voltages above the voltage rating. Allcurrents were well below the breaker rated interrupting current
of 40 kA. Higher than nominal breaker interrupting times are
expected at the lower fault currents. It must be taken into
account for breaker failure timer settings. An event report
from the BQN 2L374 protection relay nearly capture the entire
event with filtered currents and voltages. The clearing points
of various protections are easily identified with changes in
currents and voltages at the BQN terminal.
Figure 12: BQN Composite Protection Operations.
V. SYSTEM ANALYSIS
A. Simplified Steady-State Analysis
Simplified steady-state analysis for the unbalanced open
phase conditions is given in this section to estimate the natural
resonance frequency provided by the open phase condition.
When the natural resonance frequency is near the powerfrequency (60Hz), it is highly possible [1-5] that this will lead
to the over-voltage phenomenon during the incident reported
in this paper.
Figure 13 shows the three-phase circuit diagramrepresenting BQN-2L374-2L379 sub-network. For simplicity,
there are a few assumption made to the network. They are asfollows:
Assume the healthy phase voltages (A and B) are equal
and 120 degree apart
Assume both lines are fully and properly transposed
Ignore non-linear effects, i.e. surge arrestor conduction,
transformer or reactor magnetic saturation, or coronaeffects
Lump phase-to-ground capacitance and interphase
capacitance on both lines as one set of capacitance
Ignore the TAT primary to secondary coupling since the
load is very small
-
7/26/2019 Single-Pole Operation Leads to Hazardous
8/12
8
Figure 13: Simplified BQN-2L374-2L379 sub-system with C
phase open.
The symbols used on Figure 13 are self-explanatory. The
shunt reactor 2RX25 at BQN can be represented by the shunt
inductance (Lg). The transformer TAT T1 leakage impedance
between Primary winding and Tertiary Winding can berepresented by the inductance LT. For each transmission line,
the phase-to-ground capacitance (Cg) and the inter-phase
capacitance (Cm) can be obtained from the line parameters Positive Sequence Capacitance (C1) and Zero Sequence
Capacitance (C0):
3
01 CCCm
, 0CCg
The two transmission lines 2L374 and 2L379 are in parallel.
Therefore, their inter-phase mutual capacitance (Cm) and
ground capacitance (Cg) can be lumped together and berepresented by a total Cmand Cg.
Figure 14 (a) shows the equivalent network representationfor one open phase condition in Figure 13. It can be further
simplified by finding its Thevenin Equivalent circuit which is
shown in Figure 14 (b). The equivalent circuit is a simple LCcircuit, and the natural resonance frequency of this circuit can
be derived as follows:
Hz
LL
CCLLf
Tg
mgTg
6.62)2(
2
1
The simplified circuit natural frequency is 62.6Hz which is
very close to the power frequency of 60Hz. With the
consideration of the transformer saturation, the leakage
impedance will become larger and hence change the resonancefrequency still closer to 60Hz. It is highly possible that the
resonance phenomenon could result in the open-pole voltage
rising above the source voltage level (1p.u.). Therefore, it
gives a general indication of how the system voltage couldpossibly behave in the open pole condition.
Tg
Tg
LL
LL
Figure 14: Simplified Thevenin Equivalent Circuit.
This simplified analysis is only for the purpose of
understanding. It does not include non-linear components
which will be considered in the following sections for moreaccurate modelling and simulation.
B. EMTP Linear Analysis with and without TAT T1
To establish the dominant causes of the high over-voltages
during the 2L102 SPO period, all the nonlinear effects
(arrestor conduction, magnetic saturation, and corona losses)
are neglected; only the linear effects are simulation. Through aprocess of elimination, each transformer and reactor is
removed one by one and the 2L102 SPO period is simulated.The C phase voltages are then observed. It was determined
that TAT T1 was the dominant cause of the high C Phase
over-voltages. See Figure 15 for simulation with TAT T1 as
well as without TAT T1.
Other than the opening of 2L102 Phase C at BQN 3 cyclesafter fault inception, no other switching occurs during the
simulations. For simplicity, in the simulations the small station
service load supplied from BQN T3 was neglected and theTAT distribution load was assumed to be only 300 kW. Since
the instantaneous Phase C-to-ground voltage is of primary
interest, only that phase is plotted.a) Linear Case with TAT T1
This case assumes the same initial conditions as on 7thJanuary Phase C fault near BQN and the same SPO switching
times. All shunt reactors and the BQN and TAT transformers
are in service. As can be clearly seen in Figure 15 (a), as soon
as 2L102 Phase C is disconnected at BQN, the magnitude ofthe fundamental frequency voltage in Phase C of the BQN-
FKR-RDC system escalates dramatically, to more than 5 pu
after six cycles. This indicates the presence of a nearfundamental frequency resonance for this open-phase
condition. The Phase C voltage waveform is actually the first
part of a ring-down waveform. The waveform results from the
modulation of two frequencies, one being the power frequencyor forcing frequency and the other being the natural (orresonant) frequency of the circuit. Capacitive and magnetic
coupling to two phases energized from the grid provides the
sustained source at power frequency. The transient resonantresponse of Phase C will be shown to be close to 60 Hz.
Increasing the EMTP simulation time shows a beating effect
in the waveform where the modulation would have eventuallyreached a minimum voltage (less than 1 pu) and then repeated
but with reduced magnitudes.
-
7/26/2019 Single-Pole Operation Leads to Hazardous
9/12
b)
gr
se
Fipr
fre
wi
inTha
th
Fi
C.
lin
re
k
dias
necy
W
int
ar
20
boT
T1
Linear Case
For this EMTunded-star a
vice. The Ph
ure 15 (b) sceding case,
quency of th
h TAT T1 a
tantaneous ois case clearlyominant role i
t occurred for
ure 15: EMT
EMTP Non-
Figure 16 coear effects t
order (DFR)
instantaneo
played in solidotted lines.
r BQN at T =les later and
thin 1.5 cycl
o a high TOV
und 1.67 pu
0 ms BQN T
th T3 as wellV on Phase
trips off.
without TAT
simulation,d delta terti
se C phase-to
ow a dramatof the over-v
modulated
d BQN T3 o
er-voltage ondemonstratesn producing t
the January 7,
P Linear Anal
inear Analysi
pares the E the recorde
t the BQN e
s C Phase
d lines whilePhase C-to-
0 and the Pha SKA Phase
s, Phase C-to
, with an initia
ollowed by a
protection o
as 2RX22. Th to about 1.7
1
AT T1 (HVry) is assum
-ground volta
ic reduction,oltages durin
aveform is si
t of service
ly marginallythat TAT T1e high tempor
06:21:21 SP
sis with and
with TAT T1
TP simulati data from
d of the 2L3
voltage (phas
he simulatedround fault o
se C of the linC opens one
-ground volta
l 2 cycles of a
TOV of abo
ens 2CB2 an
ere is an imm1 pu, which p
rounded-stared to be out
e waveforms
compared toSPO. The b
ilar to the c
ut the maxim
exceeds 1.0ust have pla
ary over-volta
event.
ithout TAT T
n with the nthe digital f
9. The DFR
e-to-ground)
alues are shocurred on 2L
at BQN openhalf cycle la
e at BQN g
n over-voltag
t 1.6 pu. At
2CB3 and tr
diate increasersists until T
Vof
of
theeat
ase
um
pu.edes
1.
on-ult
87
are
wn02
s 3er.
oes
of
=
ips
inT
The
correspdots su
287 k
voltagewavefo
the Rel
of the
RMSEphase
conside
offsets.
field re0.9673
Theref
kV syinvesti
Figure
The
metal
absorptfor this
simulat
instantacurrent
energy
the tim
voltage
capabili
EMTP simul
onding to theperimposed o
voltages. A
waveforms arms. The goo
tive Mean Sq
rror divided
for phase A iis 7.39%. Th
ration the err
In addition, t
cording and sifor A phase
re, the EMT
tem has beeations.
16: EMTP No
228kV rated
xide arrester
ion capabilityarrester is the
ion of the 2S
neous voltagduring the S
accumulation
e that TAT T
, the arrester h
ty. Once a m
ation of the
equence of ev the three pl
s can be see
re in good agness of fit of t
uared Error (
by the RMS
s 2.10%, fore RMSE is us
r magnitude
e Pearson cor
mulation valu, B phase, a
model of th
n verified an
n-linear Anal
urge arresters
s rated IEC
of around 10efore about 2.
A25 Phase C
e across thePO. As can b
occurs after
1 trips off, e
as absorbed 1.
tal oxide arre
phase-to-gro
ents is shownots of the me
n, the simula
eement withhe model is d
MSE), which
f the field re
hase B is 1.2ed because it
hile consideri
elation coeffi
es are 0.9899,d C Phase,
linear and n
d is suitable
sis with TAT
2SA25 on B
Class 4 wit
kJ/kVr. The3 MJ. Figure
energy accu
arrester, ande seen, the hi
3 and 2RX22
ding the tem
94 MJ, or 84
ster is subject
9
nd voltages
as a series ofsured BQN
ted Phase C
the recordedtermined by
is the square
ording. The
4%, and foran take into
ng the phase
ients for the
0.9944, andrespectively.
onlinear 287
for further
T1.
QN 2B5 are
an energy
rated energy17 shows the
ulation, the
the arresterhest rate of
trip off. By
orary over-
ercent of its
ed to energy
-
7/26/2019 Single-Pole Operation Leads to Hazardous
10/12
ab
loco
Fi
En
ter
A.
Imph
soltri
A
Di
sorption abov
ses may responents and
ure 17: EMT
ergy Absorpti
V
This sectionm over-voltag
Immediate A
mediately aftase trip and
utions couldand auto-recl
vantages:
This solutio
temporary
investment isadvantages:
Any single-l
of the Nortloss of rev
Chris Mine,
of service to
its rating, th
lt in thermathe arrester fai
P Simulation
n.
. MITIGATIO
escribes thee mitigation al
tion
r 7th January
reclose mod
be developed.ose three-pole
prevented a
over-voltage
hardware an
ine to ground
hwest Transnue for the
loss of station
distribution c
internal heati
runaway ofls.
of BQN Surg
ALTERNATIV
short-term, internatives.
2015 incidee was disabl
The 2L102 rfor all detecte
repeat of the
event wit
communicati
ault causes a
ission systemnon-utility ge
service at BQ
stomers.
ng due to ene
the zinc ox
Arrestor 2S
ES
terim, and lo
t, 2L102 sined until furt
lays were setd faults.
January 7th h
out additio
ons.
omplete brea
, disruptionnerator and
N, as well as l
gy
ide
25
g-
le-her
to
igh
nal
up
nded
oss
B. Lo
Analyti
generat
of a se2L102.
to prov
It wa
dynamiloadingtesting
MW in
chosenNUG a
connec
single-
EMP18. A
possibl
enable/
This m
relay b
Advant
Disadv
g Term Soluti
cal studies
ion and/or loa
ere over-voltFaults betwee
e these results.
s decided that
cally controllat BQN subsit was decide
low into BQ
as this guarare operating a
ion from the
ole tripping o
T studies anaurther long t
use rem
isable single-
ay achieve m
sed solution.
ages:
This solutio
additional
operational i
ntages:
This soluti
resonant circ
n
identified tha
in the BQN
ge during sinn October 201
single-pole tr
ed by moniation. To simd to focus so
substation.
tees at least tt their full ou
L379 to 2L10
n and off.
yzing this solrm solution i
dial action
pole tripping
re dependabil
n does not r
ajor equip
n the least tim
n does not
uit.
t if there i
ystem then th
gle-pole open4 and January
ipping of 2L1
toring real tlify protectioely on monit
threshold of
wo generatingtput. A simpl
2 protection r
ution are shos being explo
scheme co
ased on area
ity than a pu
equire the in
ent, is expe
and at the le
detune the
10
s sufficient
ere is no risk
intervals on2015 helped
02 would be
ime systemsetting and
oring 2L379
23 MW was
units at thehard wired
lays toggles
n in Figureed that will
trollers to
ower flows.
e protection
vestment in
cted to be
st cost.
fundamental
-
7/26/2019 Single-Pole Operation Leads to Hazardous
11/12
Fi
2L
C.
de
dein
A
Di
ure 18: EM
379 and Singl
Equipment R
For this optio
ta-grounded
signed, single-SPO and all ot
vantages:
This option
During SP
system wou
temporary o
A STATC
problem inperiod of th
sadvantages:
There couldBQN 25 k
two of the p
SPO conditi
pumps, sewby the oscill
The over-vo
installs a n
connect the
will have a
create a sim
P Simulation
e-Phase Trip.
eplacement
, the existing
tar transform
line to grounher faults wou
etunes the re
, the voltag
ld be similar
er-voltage.
M that wou
the distributiSPO
be a power qsystems ther
ase-to-groun
on. Rotating
ge treatmentting electrom
ltage problem
ew 287/69 k
future McLy
delta-connec
lar problem a
of 23 MW
AT T1 woul
er, the same
faults on 2Lld result in 3P
onance and sh
waveforms
to Case 6,
ld reduce th
n voltages at
ality concern.e will be seve
voltages duri
achinery (e.g
umps, etc.) cagnetic torque.
may re-emerg
autotransfo
ont project.
ted tertiary
s found for T
f Generation
be replaced b
as BQN T3.
102 would reO.
ifts it to 53 Hz
on the 287
aving negligi
power qua
TAT during
On the TATre modulation
g the 1.1 sec
. water treatm
ould be impac
e when the N
mer at FKR
This transfor
inding and
T T1. Howe
on
y a
As
ult
.
kV
ble
ity
the
ndin
nd
ent
ted
G
to
er
ill
er,
if
traCo
an
aut
A.
Eff
Over
priority
in a r
plannervariety
configu
reactor
B. Eff
Trippin
The
This p
couplin
the prisystem.
networ
studiesespecia
subsyst
C. Pr
Damag
Withthe 1.7
cycles.
voltage
was ex
area woperati
arrestor
effectethe hig
D. Qu
Proble
Mod
in a mOnce t
identifi
modific
when stime fo
conduc
the 2L379 te
sformer wilnsequently, a
problem
otransformer,
cts of Single-
-voltage miti
when consid
mote or radi
s to considerof intent
rations when
and transfor
cts of Magnet
g Schemes
effects of L-
per highlight
g of a transfo
ary cause oThis effect is
analysis and
when desiglly in a radi
ems.
tection Syst
e
out the threepu over-volt
The protectio
to 20 cycles.
eriencing an
s experiencinns helped to
s from prolo
equipmentlighted incide
ick Protection
s
ern multi-func
nner beyonde source of t
ed BC Hydr
ations to rest
stem configur further studi
ed without im
minal breake
not be c operating o
created by
if Alternative
II. CONCLU
ole Tripping
ation should
ring using a s
al system. It
the system reional and
specifying eq
ers
ic Coupling of
circuit reson
d that a prev
rmers buried
f the over-vnot easily de
highlights th
ning single-pal system th
em Operatio
perations in tge condition
n relays reduc
Although non
nternal fault,
g a severe ovave the transf
ged over-volt
as shown lasnt.
Solutions to P
tion relays ha
he original inhe January 7t
was able to
re single-pol
ation will safes such as eq
mediate time
s at FKR ar
nnected toder can prob
the additio
is implemen
SIONS
n Radial Syst
be a prima
ingle-pole trip
is important
onance frequunintentional
ipment such
Equipment in
ance are well
iously unkno
delta tertiary
ltage experieonstrated by
e need for det
ole trippingt supplies o
n Prevented
e BQN protewould have l
ed the length
e of the trippe
all of the equi
er-voltage. Tormers, reacto
age. To date,
ing negative
revent System
e the versatili
tention of relover-voltage
quickly mak
tripping to t
ly allow. Thisipment repla
onstraints.
11
e open, this
the system.bly prevent
n of this
ed.
ms
ry planning
ping scheme
for system
ncy under aoperating
s line shunt
Single-Pole
understood.
n magnetic
inding was
ced by theonventional
ailed EMPT
schemes ne or more
Equipment
ction systemasted for 60
of the over-
d equipment
pment in the
e protections, and surge
none of the
effects from
Operation
y to be used
y engineers.was clearly
e protection
e area only
has allowedement to be
-
7/26/2019 Single-Pole Operation Leads to Hazardous
12/12
12
VIII. APPENDIX I
A. 2L102 Construction
Figure I-1 shows a typical steel-Y type monopole tower for
this flat-configuration circuit. The average height of the
conductor above ground at the tower is 15.0 m. Each phasecomprises a bundle of two 2B-1590 KCMIL ASCR Lapwing
conductors in a 45.7 cm arrangement.
Figure I-1: 2L102 Tower Configuration
IX. REFERENCES
1. F. Iliceto, E. Cinieri and A. Di Vita, Overvoltages Due to
Open-Phase Occurrence in Reactor Compensated EHV
Lines, IEEE Transactions on Power Apparatus and
Systems, Vol. PAS-103, No. 3, March 1984, pp. 474-482.2. Marta Val Escudero and Miles Refern, Effects of
Transmission Line Construction on Resonance in Shunt
Compensated EHV Lines, Presented at the InternationalConference on Power Systems Transients (IPST05),
Montreal, Canada, June 19-23, 2005, Paper No. IPST05-
09.
3.
M. Nagpal, Terry Martinich, Amitpal Bimbhra and Dave
Sydor, Damaging Open-Phase Overvoltage Disturbanceon a Shunt-Compensated 500 kV Line Initiated by
Unintended Trip, IEEE Transactions on Power Delivery,
Vol. 30, No. 1, February 2015.4. M. Nagpal, Terry Martinich, Amitpal Bimbhra, Dave
Sydor and Jerry Wen, Damaging Open Pole Over-
Voltage Disturbance Initiated by Personnel Incident,Western Protective Relaying Conference in October 2013,
Spokane, WA, USA.
5. Terry Martinich, M. Nagpal and S. Manuel, Analysis of
Damaging Open-Phase Event on a Healthy Shunt
Compensated 500 kV Line Initiated by Unintended Trip,
Presented at the International Conference on Power
Systems Transients (IPST2015), Cavtat, Croatia June 15-18, 2015, Paper No. 15IPST200