simulation group 2
TRANSCRIPT
-
7/27/2019 Simulation Group 2
1/5
Simulation Report By Group 2
1. What was your initial strategy (Scope Vs. Time Vs. Costs)
During the initial part of the project, we wanted to complete the project
by 18th week, as the project was time critical. Therefore for us, our
strategy revolved around completing the project in time and we
ensured that the scope of the project was achieved. Later on, as we
went way ahead of the schedule we changed our strategy to bring
down costs
2. Which risks you identified and what was risk management plan
The project was time critical therefore the main risk was any delay in
the project. The complete the work mostly high and medium-high
skills resources were used to complete the tasks. Since the resources
where high skilled, only standup meeting were done to conducted to
effectively use the time. Also most of the tasks were outsourced to
better manage the time and keep few resources ready when any more
tasks to be completed or the pace of the work needed to quicken.
3. What actions did you take at each crisis and why? What was the
outcome?
The major crises that we encountered during project are as follows
Over budgeting
Project was behind the schedule
Resources were not satisfied with the work load(frustrated,
bored)
Over budgeting
We tried to compensate the cost by varying the team size
between 8 to 12 members
-
7/27/2019 Simulation Group 2
2/5
As per the management the project scope and time frame were
changed so we had to put in all the resources to accomplish the
task on time, instead of bringing down the cost we finally ended
up completing the project in 15
th
week with a higher cost
Project behind the schedule
We outsourced all the resources to accomplish the task on time
We allowed overtime and utilized the maximum possible number
of resources
To monitor the project status we did stand up meetings with all
the resources
Unsatisfied resources
To provide a sufficient work load we minimized the team size
To deal with the work load issues of team we brought in one on
one coaching
4. How you computed earned value and used it for decision-making
We computed the earned value of the project based on the cost that
we had actually accrued for the given week and based on the
percentage completion of the project. At the end we computed the
earned value for the entire project.
Earned Value = Cost of the project * percentage completion (Based on
stages)
Therefore, the earned value of our entire project was $ 128,000 as
compared to the planned value of $ 80,000
5. What was your final score? What was the learning?
We got a score of 823.
(We are attaching the screen shot of the various functionalities. But we
are unable to take the screen shot of the score page, as the final rating
column was no longer visible for us)
-
7/27/2019 Simulation Group 2
3/5
Going through the simulation game we gain a lot of insights about
project management and the various issues that a manager has to face
in real life situation. We also gained insights related to decision that a
manager has to take and how to approach the situation and review it
while the project is going on.
Learnings:
We learn that while doing a project the balance should be maintained
between cost of the project and project schedule. In our case we gave
a lot of emphasis on schedule and neglect the cost, leading to a high
cumulative cost
Focus should be given in each stage of the project starting from the
beginning. If we neglect any part of the project or stage it will reflect in
the final stage
The team should be aware of its objective. So that the final decision
could be taken easily. For example: while we were running behind the
schedule, we tried to focus on completion of job. But our cost
increased and again we struggled to maintain the cost. So has to
decide whether to assign more weightage to job completion or to keep
the cost within budget
The output was directly related to the performance of the resources.
Initially the team was bored as most of the work was outsourced and
skills were not effectively utilized. Later when the dead line
approached and the project schedule was reduced to 13 week, the
team was highly stressed. The balance between the overtime, team
meetings and coaching was not achieved.
We tried to balance our resources by providing them one on one
coaching as and when the team felt stressed or confused. Throughout
the lifespan of the project we ensured that the weekly reviews were
taking place. We implemented stand-up meeting only when the
situation demanded
-
7/27/2019 Simulation Group 2
4/5
Screenshots
-
7/27/2019 Simulation Group 2
5/5