simulation group 2

Upload: tejas030

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Simulation Group 2

    1/5

    Simulation Report By Group 2

    1. What was your initial strategy (Scope Vs. Time Vs. Costs)

    During the initial part of the project, we wanted to complete the project

    by 18th week, as the project was time critical. Therefore for us, our

    strategy revolved around completing the project in time and we

    ensured that the scope of the project was achieved. Later on, as we

    went way ahead of the schedule we changed our strategy to bring

    down costs

    2. Which risks you identified and what was risk management plan

    The project was time critical therefore the main risk was any delay in

    the project. The complete the work mostly high and medium-high

    skills resources were used to complete the tasks. Since the resources

    where high skilled, only standup meeting were done to conducted to

    effectively use the time. Also most of the tasks were outsourced to

    better manage the time and keep few resources ready when any more

    tasks to be completed or the pace of the work needed to quicken.

    3. What actions did you take at each crisis and why? What was the

    outcome?

    The major crises that we encountered during project are as follows

    Over budgeting

    Project was behind the schedule

    Resources were not satisfied with the work load(frustrated,

    bored)

    Over budgeting

    We tried to compensate the cost by varying the team size

    between 8 to 12 members

  • 7/27/2019 Simulation Group 2

    2/5

    As per the management the project scope and time frame were

    changed so we had to put in all the resources to accomplish the

    task on time, instead of bringing down the cost we finally ended

    up completing the project in 15

    th

    week with a higher cost

    Project behind the schedule

    We outsourced all the resources to accomplish the task on time

    We allowed overtime and utilized the maximum possible number

    of resources

    To monitor the project status we did stand up meetings with all

    the resources

    Unsatisfied resources

    To provide a sufficient work load we minimized the team size

    To deal with the work load issues of team we brought in one on

    one coaching

    4. How you computed earned value and used it for decision-making

    We computed the earned value of the project based on the cost that

    we had actually accrued for the given week and based on the

    percentage completion of the project. At the end we computed the

    earned value for the entire project.

    Earned Value = Cost of the project * percentage completion (Based on

    stages)

    Therefore, the earned value of our entire project was $ 128,000 as

    compared to the planned value of $ 80,000

    5. What was your final score? What was the learning?

    We got a score of 823.

    (We are attaching the screen shot of the various functionalities. But we

    are unable to take the screen shot of the score page, as the final rating

    column was no longer visible for us)

  • 7/27/2019 Simulation Group 2

    3/5

    Going through the simulation game we gain a lot of insights about

    project management and the various issues that a manager has to face

    in real life situation. We also gained insights related to decision that a

    manager has to take and how to approach the situation and review it

    while the project is going on.

    Learnings:

    We learn that while doing a project the balance should be maintained

    between cost of the project and project schedule. In our case we gave

    a lot of emphasis on schedule and neglect the cost, leading to a high

    cumulative cost

    Focus should be given in each stage of the project starting from the

    beginning. If we neglect any part of the project or stage it will reflect in

    the final stage

    The team should be aware of its objective. So that the final decision

    could be taken easily. For example: while we were running behind the

    schedule, we tried to focus on completion of job. But our cost

    increased and again we struggled to maintain the cost. So has to

    decide whether to assign more weightage to job completion or to keep

    the cost within budget

    The output was directly related to the performance of the resources.

    Initially the team was bored as most of the work was outsourced and

    skills were not effectively utilized. Later when the dead line

    approached and the project schedule was reduced to 13 week, the

    team was highly stressed. The balance between the overtime, team

    meetings and coaching was not achieved.

    We tried to balance our resources by providing them one on one

    coaching as and when the team felt stressed or confused. Throughout

    the lifespan of the project we ensured that the weekly reviews were

    taking place. We implemented stand-up meeting only when the

    situation demanded

  • 7/27/2019 Simulation Group 2

    4/5

    Screenshots

  • 7/27/2019 Simulation Group 2

    5/5