simulation- based design study modeling a wind turbine chris gloss, andrew lincoln, matthew mustard,...

17
Based Design Study Modeling a Wind Turbine Chris Gloss, Andrew Lincoln, Matthew Mustard, John Semmens, & Shereef Shehab

Upload: lorena-madison-baldwin

Post on 17-Dec-2015

219 views

Category:

Documents


1 download

TRANSCRIPT

Simulation-Based Design

Study Modeling a

Wind TurbineChris Gloss, Andrew Lincoln, Matthew Mustard, John Semmens, & Shereef

Shehab

2

Introduction

Wind Turbine Modeling 3

Scope

• Goalso Develop a fully functional model

of a 1.5 MW wind turbine based on industry standards

o Utilize available wind data for Atlanta’s Airport

o Determine the feasibility of installing a wind turbine in Atlanta

• Design Variableso Rotor Radiuso Tower Height

To develop a model of a wind turbine that will provide its expected utility using the Dymola and Model Center software.

Wind Turbine Modeling 4

Influence Diagram

Wind Turbine Modeling 5

Blades

• NACA 4412 Airfoil• Triangular planform.• Assumed to be made

of fiberglass and hollow.

• Moment of inertia of the blade about the base was calculated.

Wind Turbine Modeling 6

Dymola Model: Overview

Wind Turbine Modeling 7

Implementation of a PID Controller

Wind Turbine Modeling 8

Role of Uncertainty• The central composite experiment showed which

uncertain variables have the greatest effect.

Wind Turbine Modeling 9

Monte Carlo Analysis

0-0.

08

0.08

-0.1

6

0.16

-0.2

4

0.24

-0.3

2

0.32

-0.4

0

0.40

-0.4

8

0.48

-0.5

6

0.56

-0.6

4

0.64

-0.7

2

0.72

-0.8

0

0.80

-0.8

8

0.88

-0.9

6

0.96

-1.0

4

1.04

-1.1

2

1.12

-1.2

0

1.20

-1.2

8

1.28

-1.3

6

>1.36

0

500

1000

1500

2000

2500

3000

Monte Carlo Results Histogram

Frequency

Cost of Electricity ($/kWh)

Fre

quency

Wind Turbine Modeling 10

Dymola Model: Cost

Wind Turbine Modeling 11

Total Turbine System Cost* $1,770,000.00AEP (kW-h) 3,950,000 Minimum Most Likely MaximumYear Rand# 1.00 Years of Operation 10 20 30Years of Operation 24 Utility Rate $0.01 $0.07 $0.17Cost of Capital Rand# 0.55 Cost of Capital 0.01 0.15 0.2Cost of Capital 0.13 Demand (kW-h) 1,316,667 2,633,333 3,950,000

Year Utility Rand# Utility Rate Demand Rand# Demand Revenue Discounted Cash Flow0 ($1,770,000.00)1 0.55 $0.09 0.87 3,058,387 $269,164.88 $237,293.332 0.66 $0.10 0.39 2,481,096 $246,009.48 $191,199.223 0.99 $0.16 0.70 2,869,197 $473,286.18 $324,283.784 0.29 $0.07 0.78 2,963,799 $194,610.79 $117,553.475 0.33 $0.07 0.51 2,640,777 $182,951.26 $97,425.156 0.64 $0.10 0.34 2,403,537 $234,506.45 $110,092.477 0.55 $0.09 0.99 3,171,980 $279,190.64 $115,550.238 0.98 $0.16 0.52 2,654,834 $422,195.86 $154,046.229 0.85 $0.13 0.92 3,104,736 $390,259.24 $125,532.86

10 0.40 $0.07 0.18 2,111,968 $157,331.60 $44,615.6611 0.05 $0.03 0.37 2,453,465 $80,821.08 $20,205.2012 0.52 $0.09 0.79 2,973,503 $255,100.96 $56,223.4813 0.10 $0.05 0.84 3,027,528 $159,312.26 $30,954.3714 0.55 $0.09 0.32 2,368,422 $208,321.29 $35,684.0015 0.93 $0.14 0.61 2,773,283 $391,709.26 $59,152.2016 0.95 $0.15 0.28 2,295,123 $334,891.83 $44,583.9717 0.55 $0.09 0.91 3,091,594 $272,301.31 $31,958.8418 0.68 $0.10 0.09 1,888,677 $193,291.30 $19,999.5719 0.08 $0.05 0.61 2,774,641 $140,909.47 $12,853.3320 0.34 $0.07 0.45 2,566,567 $178,922.10 $14,388.2121 0.18 $0.06 0.66 2,829,171 $163,737.63 $11,608.0222 0.07 $0.04 0.66 2,830,131 $106,234.38 $6,639.6023 0.12 $0.05 0.87 3,056,485 $163,450.74 $9,005.9824 0.21 $0.06 0.04 1,678,043 $101,118.69 $4,911.82252627282930

Triangular Distributions

NPV Model

Wind Turbine Modeling 12

@Risk – Monte Carlo within Excel

66.5% 33.5%

0.000 +∞

-1.5

0-1

.00

-0.5

00

.00

0.5

01

.00

1.5

02

.00

2.5

03

.00

3.5

0

Values in Millions ($)

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Val

ue

s x

10

^-6

NPV - Demand / Utility Rate

NPV - Demand / Utility Rate

Minimum -$1,173,934.14Maximum $3,107,918.10Mean -$101,096.28Std Dev $585,569.89Values 5000

@RISK Textbook VersionFor Academic Use Only

60.3% 39.7%

0.000 +∞

-1.5

0-1

.00

-0.5

00

.00

0.5

01

.00

1.5

02

.00

2.5

03

.00

3.5

04

.00

Values in Millions ($)

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Val

ues

x 1

0^

-6

NPV - Demand / Utility Rate

NPV - Demand / Utility Rate

Minimum -$1,034,270.62Maximum $3,856,616.88Mean $11,442.90Std Dev $597,216.87Values 5000

@RISK Textbook VersionFor Academic Use Only

AEP = 3,950,000 kW-hrLeft: Cost = $1,880,000

Right: Cost = $1,770,000

Wind Turbine Modeling 13

Determination of r

• NPV Maximum = $3,856,616.88• NPV Minimum = ($1,173,934.14)

At what dollar amount are we indifferent between the NPV maximum and minimum?• Chosen value = $200,000 • Using a Matlab script the risk aversion

coefficient is 4.2438x10-7

NPVeu )102438.4(7

7

11024.4

1

Wind Turbine Modeling 14

Full Factorial Exploration

Wind Turbine Modeling 15

Deterministic Optimization

Wind Turbine Modeling 16

Optimization with Uncertainty

Results

Optimum Rotor Radius

43.65 m

Optimum Hub Height

85 m

Maximum Expected Utility

-$14,205.40

Statistic Expected Utility ($)

Minimum -1,917,290

Maximum 950,206

Mean -14,205.40

Median 53,432.20

Lower 25% -134,740

Upper 25% 265,559

Standard Deviation

521,651

Wind Turbine Modeling 17

Thank You

Does any one have any questions?