simem concrete special projects 12 2009 - india & italy special... · the joint venture between...
TRANSCRIPT
1989-1990 – MOBILE MIXING PLANTS FOR THE GROUP CIMENT FRANCAIS (France)
Twenty-two mobile mixing plants named EUROMIX manufactured in co-operation with BETP
company (Guerande - France), each one equipped
with twin shaft mixer model MSO 2500, supplied
to the Group Ciment Francais for concrete production required within different projects in
France, such as: the triumph arc “La Defence” in
Paris, the enlargement of landing strips in Paris
and Lyon airports, the high-speed railways of TGV, the enlargement of Marseille port docks.
1990 – EUROTUNNEL PROJECT
Eight concreting trains manufactured in co-operation with the company Demler-Maitrap
(Paris) designed for mix ing and distribution of
concrete inside the tunnels under the Brit ish
Channel: each train has been equipped with two different twin shaft mixers, one unit model MSO
3700 and one unit model 9000 Super (capacity 7
cb.mt. per cycle of compacted concrete - the
biggest twin shaft mixer in the world). When the Eurotunnel project was completed, all the mixers
have been sold and installed for ready-mix
concrete production within the plants of different
companies in Belgium, Holland, Germany and France.
1993 – NEW HONK KONG AIRPORT (China)
Three continuous concrete plants
manufactured in co-operation with the
company Planters & Co. for the client ACG in Hong Kong, installed for the
construction of the landing stripes of the
new airport of Hong Kong. The
Flowbeton 500 plants each have a MDC 500 continuous mixer for the production
of up to 300 m³/hr of zero slump
concrete.
1994 – SYDNEY 2000 OLYMPICS PROJECT (Australia)
Three concrete mixing towers,
manufactured in co-operation with local
steel fabricators, under commitment of the company CSR Co. - Ready Mix
division in Paramatta, designed for the
construction of the new 2000 Olympics
quarters in Australia; each plant has been designed equipped with two units
MSO 4500 twin shaft mixers, suitable to
achieve a 200 cb.mt. hourly production
capacity.
1994 – PETRONAS TOWERS (Kuala Lumpur, Malaysia))
Complete Wetbeton 120 Special plant
has been installed on the construction site of the highest twin towers in the
world where Pioneer was awarded as the
concrete major supplier. The
configuration of the plant was designed with MSO 4500 twin shaft mixer
completed with dry/wet by-pass system
for switching the production process
according to the requirements of the different areas of the construction.
1995 – GRAN STADE PARIS (France)
Two concrete mixing plants, designed
and manufactured in cooperation with the company Imer France, under
commitment of the Group Bouygues-
Dumez, for the construction site of the
new super-stadium in Paris, where the World Football Championship was
organised. Each plant was equipped with
one MSO 3000 twin shaft mixer, for an
hourly production up to 100 m³ concrete with variable slump.
1997 – TOKER DAM (Eritrea)
The joint venture between ASI RCC – USA
(spec ialised in the production of RCC) and
Keangnam Ent. Ltd. – Korea (construction division of the Daewoo Group) built a dam in
the Toker river, necessary for the distribution
of water and electricity in the capital Asmara.
Simem supplied two complete plants: one Wetbeton 65 with a capacity of 65 m³/hr that
was used for approx. 9 months and one
Wetbeton 160 with a capacity of 160/240
m³/hr that was in function for about 5 months. The Wetbeton plants were chosen
espec ially because of their modular
composit ion, which made it possible to install
the plants on the steep mountains that run along the river.
1997 – GHAZI BAROTHA DAM (Pakistan)
Two wet batching plants manufactured in co-
operation with the company Planters & Co.
for the client Dong Fang, installed for the
construction of the Ghazi Barotha dam in Pakistan. They required a concrete production
of 240 m³/hr and the concrete could have a
maximum temperature of 26 °C. The two Wetbeton 120 plants were combined with two complete plants for the production of flaked
ice.
2000 – MONTBLANC TUNNEL RECONSTRUCTION (Italy)
One unit Wetbeton 120 plant
installed for the client Calcestruzzi
(Italcementi Group) in Courmayeur
for the supply of “spritz beton” and structural concrete for the
reconstruction of the MontBlanc
tunnel after the fire acc ident
occurred in 1998. The plant has been intensively producing 24
hours a day for 15 months for
matching the schedule of the
tunnel reconstruction.
2001 – SUSA DAM (Italy)
Two units Wetbeton 120 plants
installed for the client Calcestruzzi
– Italcementi Group within the
construction site of the Susa Dam in Northern-West Italy. The plants
have been producing both low
slump concrete for the dam
construction as well as self-compacting concrete for the
finishing cover of the dam walls.
Aggregates adopted for the project
were spec ified up to 150 mm size.
2001 – CINDERE DAM (Turkey)
Complete double WB160 plant
supplied to the company Ozalt in in
Turkey for the construction of the
RCC dam named Cindere Dam, for the production of 220 m³ x hour
with aggregates rated up to 80
mm, flaked ice and chilled water.
The plant has been spec ified with two units MSO 6000, standard
version, complete with washing
system, filtering system and mixer
mind.
2002 – SE SAN DAM (Vietnam)
Complete WB 120 plant supplied to
the company Song Da 12 in
Vietnam, for the construction of the RCC dam named Se San Dam,
for the production of 100 m³ per
hour with aggregates rated up to
160 mm.
2002 – KURICHU DAM (Buthan)
Complete WB 120 plant supplied to the company Hindustan Construction Company, one of the biggest
contractors in India, for the construction of the RCC dam named Kurichu Dam, for the production of 100 m³ x hour with aggregates rated up to 120 mm, flaked ice and chilled water.
Actually the WB 120 plant is used for the Tala Hydro-electric Project in Bhutan which is being implemented as a part of bilateral trade agreement between Government of India and Royal
Government of Bhutan is another important project being executed by HCC. The project is one amongst
the largest hydro power projects in the world. HCC's scope of work here inc ludes the construction of a
dam, desilt ing chamber and head race tunnel.
2003 – CHALILLO DAM (Belize)
Client
China Hydropower Engineering Consulting Group
Co. (CHECC) is a government administrat ive
agency responsible for engineering and
construction of water resources and hydropower projects.
Requirement
The client had been awarded Chalillo Dam project
located high in the Pine Ridge Mountains in Belize.
Our solution
FLOWBETON 500
• Production capacity 500 Ton./h.
• Aggregate storage with 4 compartments, total
capacity 70 m³;
• Aggregate weighing and extracting system with
four dosing belt conveyors and one extracting belt
conveyor;
• One cement weighing system by volume with rotary feeding valve;
• One volumetric water dosing system;
• One volumetric admixture dosing system;
• One SIMEM MDC500 continuous flow mixer.
2003 – KOUDIAT ACERDOUNE DAM (Algeria)
Client
RAZEL, a French contractor and part of the
Bilfinger Berger Group, with more than 100
years of experience in c ivil works projects, dams, roadwork, etc.
Requirement
Construction of the RCC dam Koudiat
Acerdoune in Algeria.
Our solution
FLOWBETON 500 DOUBLE:
• Production capacity 2 X 700 Ton./h
• Aggregate storage system with 4 double
compartments, total capac ity 240 m³;
• Two independent aggregate weighing
systems with two extracting belts (one per
mixer) and double dosing gates;
• Four independent powder weighing systems (two per mixer);
• Two independent volumetric water dosing systems;
• Two SIMEM MDC 500 Continuous Flow
Mixers.
2004 – JAGHING DAM (Iran)
Client
Jyane Construction Company, established in 1959,
has been active for 45 years in c ivil engineering contracts in Iran.
Requirement
To construct the first ever RCC dam in Iran.
Our solution
WET BETON 160 DAM:
• Production capacity 160 m³/h;
• Aggregate storage system with five
compartments, total capac ity of 160 m³;
• Five double pneumatically operated dosing gates
for aggregate with one extracting belt conveyor;
• One aggregate weighing system;
• One cement dosing;
• One fly ash dosing system;
• One water dosing system;
• One ice dosing system;
• One SIMEM MSO 6000DAM Twin Shaft Mixer.
2008/2009 – CHANGUINOLA DAM (Panama)
Client
Pihl is Denmark’s most active contracting company
internationally and is among the 80 largest contracting companies in the world. During the last
twenty years Pihl has completed projects in more
than 40 countries.
Requirement
The Project consists of the construction of two
hydropower plants on the Changuinola River in the
Bocas del Toro Province in Panama.
Our solution
WET BETON 160 DAM TWIN
• Production capacity 2X160 m³/h;
• Aggregate storage system with 3 + 2 double
compartments, total capac ity 560 m³;
• Four independent aggregate weighing systems
with four extracting belts (two per mixer) and
double dosing gates;
• Two independent cement dosing systems;
• Two independent water dosing systems;
• Two independent ice dosing systems;
• Two independent admixture dosing systems;
• Two SIMEM MSO 6000 DAM Twin Shaft Mixers.
2008/2009 – M.O.S.E. PROJECT (Italy)
Clients
Three specialized Italian companies specialized in ready-mixed concrete.
Requirement
MOSE (Modulo Sperimentale Elettromeccanico) project consists on the achievement of 79 steel sluice gates placed on the seabed at the three outlets of Venice Lagoon. These sluice
gates, hollow inside, are filled with water and remain on the bottom because of weight, making it so invisible from the
surface. As high water, measuring 110 cm set in the sluice gates would be emptied by a system of pumps pressure or compressed air, and then lifted up like a drawbridge to reach
an angle of 45 degrees.
Our solutions
• Calcestruzzi Spa purchased two mobile plants SIMEM
SuperMobyMix 100 currently installed on Pellestrina island near the outlet of Malamocco: each plant can reach a production
capacity of 100 cubic meters/hour;
• Unicalcestruzzi Spa purchased two mobile plants currently installed on Pellestrina island near the outlet of Chioggia: one
SIMEM MobyMix 3000, a plant with a production capacity of 90 cubic meters/hour and one SIMEM Super Moby Mix 130 with production capacity of 130 cubic meters/hour;
• Laguna Calcestruzzi srl purchased two mobile plants SIMEM MobyMix 3000 with production capacity of 90 cubic meters/hour, currently installed in Punta Sabbioni near the
outlet of Lido.
2009 – MAXXI MUSEUM (Rome, Italy)
The MAXXI_National Museum of the XXI Century Arts is a new inst itut ion of the Ministry for Cultural
Heritage. Thus, in the adventure of an inst itution
so projected towards the future, it was dec ided to
seize the opportunity to carry out a grand public work with the innovative and the spectacular
architectural forms of the architect Zaha Hadid.
Integrated manufacturing solut ions, test ing
materials, site-specific applicat ions and optimized
job site management, are some elements that
explain the complexity of this job executed by a consortium of Italian companies. Among them,
Calcestruzzi Spa (Gruppo Italcementi), with a
SIMEM MOBY MIX 1500, supplied the Self-
Compacting Concrete.
Given the dimensions of the concrete pours (more than 200 m3 of concrete) and the quality of the
concrete itself, self-compacting and quick drying, it
was necessary to install the SIMEM concrete mixing
plant on site to mix the self-compacting concrete (SCC). In fact, this material, in order to ensure
quality control, requires the constant monitoring of
the humidity of the aggregates and the overall
granulometric composition of the mixture.