2 X 363.3 Combined Cycle Gas Power Project

Palatana, Tripura

Presentation

atMinistry of Development of

North Eastern Region,Government of India

January 17, 2011 www.otpcindia.inNew Delhi

Page 2: SIMA Presentation

Contents

Background Project Highlight Power Allocation Project Location Gas Supply Network of ONGC Project Status : Clearances & Permits Project Status : Supply and Construction Logistics Status of Inputs Areas of Concern Assistance Required

Page 3: SIMA Presentation

October 29, 2005

LAYING OF FOUNDATION STONE

Page 4: SIMA Presentation

Source of Inspiration

Page 5: SIMA Presentation

SITE VIEW FROM (MAIN GATE ROOF)

Site Activity Photographs 07-JAN-11

Page 6: SIMA Presentation

STACK, HRSG AND GTG FOUNDATION – UNIT-1

07-Jan-11

Site Activity Photographs

Page 7: SIMA Presentation

GTG FOUNDATION – UNIT-1

Site activity photographs

07-Jan-11

Page 8: SIMA Presentation

COOLING TOWER : UNIT-1

07-Jan-11

Site Activity Photographs

Page 9: SIMA Presentation

CW PUMP HOUSE: UNIT-1

Site Activity Photographs

07-Jan-11

Page 10: SIMA Presentation

PRE-TREATMENT PLANT : CLARIFLOCCULATOR -2

07-Jan-11

Site Activity Photographs

Page 11: SIMA Presentation

SWITCHYARD – CONTROL ROOM BUILDING

Site activity photographs

07-Jan-11

Page 12: SIMA Presentation

HRSG-DRUM AT PORT

Project photographs

10-Dec-1008-Jan-11

Page 13: SIMA Presentation

HRSG : HP DRUM-1 ON TRAILER

Project photographs

12-Nov-10

Page 14: SIMA Presentation

HRSG Modules : Transportation

Logistic Photographs

Page 15: SIMA Presentation

GT GENERATORS: UNLOADED NEAR KOLKATA

12-Nov-10

Project photographs

Page 16: SIMA Presentation

Bypass Construction in Bangladesh

Page 17: SIMA Presentation

Bypass Construction in Bangladesh

Page 18: SIMA Presentation

Bypass Construction in Bangladesh

Page 19: SIMA Presentation

Bypass Construction in Bangladesh

Page 20: SIMA Presentation

Bypass Construction in Bangladesh

Page 21: SIMA Presentation

Project Highlight

Capacity: 2 x 363.3 MW

Type: Gas Based Combined Cycle

Location: Palatana, Tripura

Project Cost: Rs 3,429 Crore

Source of Fuel: ONGC’s Gas Field in Tripura

Type of Fuel: Natural Gas

Quantity of Fuel: 2.65 MMSCMD

Source of Water: River Gumti

Quantity of Water: 125 MLD

Promoters: ONGC (50%), IL&FS (26%), GOT (0.5%).

Page 22: SIMA Presentation

Project Highlight …… Contd

EPC Contractor: Bharat Heavy Electricals Limited (BHEL)

Award of Contract: 23-Jun-08

Commissioning: Unit-1: 22-Dec-11,

Unit-2: 22-Mar-12

Evacuation: 650 KM 400 KV D/C Palatana – Bongaigaon Line

Page 23: SIMA Presentation

Power Allocation

Power Allocation by MoP

Beneficiary State Pro-rata allocation in MW based on actual capacity of 726.6 MW

Tripura 196Assam 240Arunachal Pradesh 22Nagaland 27Mizoram 22Manipur 42Meghalaya 79

Power allocated to OTPC 98

Page 24: SIMA Presentation

Project Location

650 kms 400 kV D/C line

Byrnihat S/S

Ajara S/S

Silchar S/S

Page 25: SIMA Presentation

Konaban GGSKunjaban Manifold

Nimbutali

Sonamura GGS

Agartala Dome GGS(ADB)

Palatana

Sundalbari Manifold

16” 12km Pipeline

(Sector–II)

8” 19.5km Pipeline

(Sector-IV)

6” 19.5km Pipeline

(Sector-V)

20” 41km Pipeline (Sector-I)

20” 12km Pipeline

(Sector –I)

8” 12.5km Pipeline

(Sector –VI)6” 12.5km

Pipeline(Sector-VII)

16” 22km Pipeline

(Sector – III)

BagabasaSectionalizing Valve Station

F1A : Facility F1 (Early)F1B : Facility F1 (as per NOA)F 2 : Facility F2

Gas Supply from ONGC – Tripura Asset

Page 26: SIMA Presentation

Project Status: Clearances and Agreements

Clearance received from MOEF, TSPCB, AAI, MOD

State Support Agreement Signed

206 Acres of Land Acquired for the project

Shareholders Agreement, Gas Sale & Purchase Agreement and Power

Purchase Agreement signed.

Long Term Service Agreement signed with OEM (GE) for Gas Turbine

Page 27: SIMA Presentation

Project Status : Supply & Construction

SUPPLIES

Dispatch of ODCs to be transported through Bangladesh started in May-10 and last dispatch from BHEL works for Unit-1 & Unit-2 is expected by end Feb-11.

Supplies of non-ODCs to be transported via Gauhati started in Mar-10 and last dispatch from BHEL works for Unit-1 is expected by Apr-11 and for Unit-2 by Aug-11.

CIVIL CONSTRUCTION

Piling and foundation of major buildings for Unit-1 completed and main plant equipment erection started in Jan-11.

Major structures for Unit-2 are likely to be ready for erection by Apr-11.

Work for Cooling Tower and Water Treatment System has commenced. CT-1 is likely to be commissioned in Sep-11 and Water Treatment System is likely to be commissioned in Jul-11

Construction of River Water Intake Pump house and pipeline has commenced and likely to be commissioned by Jul-11.

Page 28: SIMA Presentation

Project Status : Erection

ERECTION

Main Plant equipment erection started in Jan-11

Milestone Target Date

UNIT-1

Mechanical Completion Aug-11

Hydro test Completion Oct-11

Readiness for commissioning Dec-11

UNIT-2

Mechanical Completion Nov-11

Hydro test Completion Jan-12

Readiness for commissioning Mar-12

Page 29: SIMA Presentation

Routes: Kolkata – Ashuganj – Palatana Kolkata – Karimgunj - Palatana

Page 30: SIMA Presentation

Routes for transportation of ODCs from Kolkata: There are two routes available for transportation of ODCs to Palatana site:

Via Karimganj: 1318 KM (river) + 320 KM (road - India)

Via Ashuganj (Bangladesh): 856 KM (river) + 115 KM (road – India + B’dsh)

Ashuganj route has been selected because river route is navigable through out the year and road route passes through generally plain land leading to less risk in transportation.

Hon’ble Prime Minister of Bangladesh during her visit to India in Jan-10 agreed to allow movement of ODC through Ashuganj in Bangladesh. Since then, Ashuganj has been included in Indo-Bangla Water Transport Proto-call and MOU has been signed with GOB formally allowing movement of ODCs through Bangladesh territory.

96 ODCs shall be transported through Bangladesh for which construction of RO-RO jetty at Ashuganj and bypasses between Ashuganj and Palatana has started.

Construction of bypasses in between Ashuganj (Bangladesh) and Palatana (Tripura) has commenced and movement of ODC from Kolkata to Ashuganj expected to start from 20-Jan-11 and from Ashuganj to Palatana site by 15-Feb-11.

Logistics – Overview

Page 31: SIMA Presentation

PROJECT – STATUS OF INPUTS

Commissioning Gas Start-up Power Evacuation System

Responsible agency ONGC TSECLNETCL / POWERGRID /

NER STATES

Latest required – to meet commissioning schedule

August ’11 May’11 November’11

Current StatusConstruction has

startedContract for line

construction awarded

Construction started but moving at tardy

pace.

OTPC assessment No delay Delay of 3 Months

Delay of 3 months (up to Silchar)

Delay of 6-9 months (up to Bongaigaon)

Impact on unit#1 No impact Delay of 3 monthsLikely delay of 3

months

Impact on Unit#2 No impact No impactLikely delay of 6/9

months

Page 32: SIMA Presentation

SILCHAR – BONGAIGAON TRANSMISSION LINE

Delay in Forest Clearance in Meghalaya (25 KM) and Assam (22 KM) – NETCL

EVACUATION CONSTRAINT: PALATANA – BONGAIGAON

Delay in construction of Azara and Byrnihat sub-station – Assam / Meghalaya

Delay in construction of 400 kV Silchar sub-station – POWERGRID

DOWNSTREAM NETWORK BY BENEFICIARY STATES

Work yet to commence by States i.e. Assam, Tripura, Mizoram etc for absorption of power. Unit-1 commissioning may be delayed on this account. – NER States

States to absorb Unit-1 power:

Assam : 120 MW Meghalaya: 40 MW

Tripura: 98 MW Manipur: 21 MW

Mizoram: 11 MW Nagaland: 14 MW

Arunachal: 11 MW

AREAS OF CONCERN

Page 33: SIMA Presentation

Immediate Forest Clearance in Assam (22 KM) and Meghalaya (25 KM) required.

State governments to expedite development of Azara and Byrnihat sub-station and downstream network to match Unit-1 commissioning in Dec-11

States to advise POWERGRID to install series-compensation facility at Bongaigaon sub-station.

Government of Tripura to expedite construction of 132 KV line and provide startup power by May-11

POWERGRID to expedite construction of 400 kV Silchar substation to match with Unit-1 commissioning in Dec-11.

ASSISTANCE REQUIRED

Page 34: SIMA Presentation

January 17, 2011New Delhi