silver eagle refining catastrophic pipe rupture woods

24
Cooling Tower Explosion Visakhapatnam, India, 2013 Richa Sarkar MS, Safety Engineering Mary Kay O’Connor Process Safety Center Artie McFerrin Department of Chemical Engineering Texas A&M University Steering Committee Meeting January 19 th , 2017 Case Study

Upload: others

Post on 15-Oct-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Silver Eagle Refining catastrophic pipe rupture Woods

Cooling Tower ExplosionVisakhapatnam, India, 2013

Richa Sarkar

MS, Safety Engineering

Mary Kay O’Connor Process Safety Center

Artie McFerrin Department of Chemical Engineering

Texas A&M University

Steering Committee Meeting January 19th, 2017

Case Study

Page 2: Silver Eagle Refining catastrophic pipe rupture Woods

1

About Myself

• Hometown - Bihar, India

• Bachelors in Chemical Engineering (2005-2009)

National Institute of Technology, Trichy, India

• Process Engineer (2009-2015)

Hindustan Petroleum Corp. Ltd., Visakh Refinery, India

• MS Safety Engineering

Texas A&M University, College Station, USA

Page 3: Silver Eagle Refining catastrophic pipe rupture Woods

2

Outline

• Background

• Incident Description

• Consequences

• Analysis

• Lessons Learned

• Acknowledgement

Page 4: Silver Eagle Refining catastrophic pipe rupture Woods

3

Hindustan Petroleum Corporation Ltd. (HPCL)

•Indian state-owned oil & natural gas company, HQ in Mumbai, India.

• A public sector undertaking of the Govt. of India.

• Formed in 1974 by combining Esso and Lube India

•Two refineries – Mumbai and Visakhapatnam

Page 5: Silver Eagle Refining catastrophic pipe rupture Woods

4

Visakh Refinery• Commissioned as Caltex

Oil Refining India in 1957

• Taken over by government of India and merged with HPCL in 1978

• Visakh Refinery Expansion Projects –

VREPI – 4.5 MMTPA (1985)

VREPII – 7.5 MMTPA (1999)

Effective April 2010 – 8.3 MMTPA

Page 6: Silver Eagle Refining catastrophic pipe rupture Woods

5

Cooling Towers

• The refinery has 3 cooling towers

• Each added during expansion projects

VREPI

VREPII

VRCFP (Visakh Refinery Clean Fuels Project)

• Each provided with 4 cells and induced draft operating mechanism

• 5th cell was to be added to VRCFP cooling tower – to meet the requirements of Diesel Hydrotreater (DHT) Block

Page 7: Silver Eagle Refining catastrophic pipe rupture Woods

6

Sequence of events

VRCFP cooling tower – all cells collapse

Interconnection schemes – to sustain operations

New (5th) cell construction complete

Explosion during commissioning of new cell

Page 8: Silver Eagle Refining catastrophic pipe rupture Woods

7

Cooling tower operation

• Heat rejection to atmosphere

• Inexpensive means for handling low grade heat

• Fills are provided to increase contact area

http://www.svlele.com/piping/cooling_water.htm

Page 9: Silver Eagle Refining catastrophic pipe rupture Woods

8

Cooling tower operation

Fig 2 - Closed loop cooling water system [1]

Page 10: Silver Eagle Refining catastrophic pipe rupture Woods

9

Incident Description

• VRCFP cooling tower commissioned in 2009-10

• All 4 cells collapsed within 2-3 years

• Internal investigation concluded – design issues, improper load distribution

• Design modifications carried out for flow redistribution to individual cells

• Re-construction work of collapsed cells – handled by Maintenance department

• Construction of new 5th cell – handled by Projects department

Page 11: Silver Eagle Refining catastrophic pipe rupture Woods

10

Incident Description

• To sustain operations and reduce flaring –

interconnection provided between old and VRCFP cooling tower return and supply headers

Make-up water quantity was increased

• Decided to take the 5th cell in service – while construction continued on remaining 4 cells

Page 12: Silver Eagle Refining catastrophic pipe rupture Woods

11

Incident Description

Fig 3- sketch of cooling water lines to VRCFP cooling tower [5]

Page 13: Silver Eagle Refining catastrophic pipe rupture Woods

12

Incident Description

• Construction work for 5th cell completed

• Jump over to take 5th cell online, executed in field on 23rd

August

• Decided to go ahead with commissioning at shift change-over time

• Explosion occurred at 1646 hrs on 23rd August 2013, when the isolation valve was opened to commission 5th cell

Page 14: Silver Eagle Refining catastrophic pipe rupture Woods

13

Incident Scene: Before

http://www.process-cooling.com/ext/resources/issues/April2015/Emerson/PC0415_Slideshow_Emerson_1.jpg?1435691229

Page 15: Silver Eagle Refining catastrophic pipe rupture Woods

14

Incident Scene: Damage

http://www.thehindu.com/news/national/andhra-pradesh/one-dead-39-injured-in-vizag-refinery-blast/article5052564.ece

Page 16: Silver Eagle Refining catastrophic pipe rupture Woods

15

Consequences:

• 28 fatalities – 1 employee + 27 contract workers

• Several others with burn injuries

• Further delay in commissioning and limited production

Page 17: Silver Eagle Refining catastrophic pipe rupture Woods

16

Analysis: What went wrong

• Accumulation of hydrocarbon in the jump-over line

• No sample analysis of line content prior to commissioning

• Hot-jobs continued in adjacent cells at the time of commissioning

• Failure to check HC leakage in to cooling water in connected process units

Page 18: Silver Eagle Refining catastrophic pipe rupture Woods

17

Analysis: Management decisions

• Failure to prevent commissioning activities, with plenty of jobs unfinished

HC/H2S detectors were not installed

Fan cabling was incomplete

Improper co-ordination between Operations, Maintenance and Project departments

• Decision to go ahead with commissioning at shift change-over time

• Failure to implement procedures – PSSR, pre-com audit

• Commissioning procedure not followed – 16 jobs were going on, with 9 permits for hot job

• Standard operating procedure was not available

Page 19: Silver Eagle Refining catastrophic pipe rupture Woods

18

Analysis: Technical deficiencies

• Jump-over connection was at elevated location –resulting in accumulation of light hydrocarbons

• Significant distance between the isolation valve and the location where tie-in was made

Page 20: Silver Eagle Refining catastrophic pipe rupture Woods

19

Lessons Learned: Procedural

• Hot works and commissioning activity should not be allowed simultaneously

• PSSR should be done prior to commissioning new facility

• Check points of pre-commissioning audits and internal audits should be completed

• Minimum number of operating crew and nobody should be present at work site

• Provision of HC and other detectors as applicable should be ensured

• Hazard Identification and Risk Assessment should be ensured prior to commissioning of any new system

• Lack of operating procedure

Page 21: Silver Eagle Refining catastrophic pipe rupture Woods

20

Lessons Learned: Technical

• Always check and follow industrial standards

• Wherever possible avoid creation of dead-zones

• Provide high point vents, low point drains and appropriate sample points

• Ensure flow pattern within the line when providing take-off

Page 22: Silver Eagle Refining catastrophic pipe rupture Woods

21

Acknowledgement:

• Dr. M. Sam Mannan

• Dr. Guanlan Liu

• Pritishma Lakhe

• Ankita Taneja

• Valerie Green

• Alanna Scheinerman

• Members of MKOPSC

• Members of SC

Page 23: Silver Eagle Refining catastrophic pipe rupture Woods

22

References:

1. Lj. Matijasevic, A. V., and I. Dejanovic. (2014). Analysis of Cooling water systems in a Petroleum Refinery. Chemical and Biochemical Engineering Quaterly, 8.

2. Analysis of Incidents reported to PNGRB from July, 2013 to December, 2014. (2015). Retrieved 1/10/2017, from Petroleum & Natural Gas Regulatory Board http://pngrb.gov.in/Notices.html

3. http://www.oisd.nic.in/

4. http://oisd.nic.in/PDF/OISDCaseStudies/OISDCaseStudyCoolingTowerFire.pdf?WhatNewId=20&button=Edit

5. https://www.icheme.org/shop/lpb/2015/issue%20245/explosion%20in%20a%20cooling%20tower.aspx

6. http://www.hindustanpetroleum.com/documents/pdf/AnnualReport2013-14.pdf

7. http://www.thehindu.com/news/national/andhra-pradesh/one-dead-39-injured-in-vizag-refinery-blast/article5052564.ece

8. http://www.thehindubusinessline.com/companies/death-toll-in-hpcl-accident-rises-to-28/article5159682.ece

9. http://indiatoday.intoday.in/story/death-toll-in-vizag-hpcl-refinery-fire-rises/1/301164.html

Page 24: Silver Eagle Refining catastrophic pipe rupture Woods

23

Questions/ Comments

Thank you for your attention!

[email protected]