sierra club of maine climate action conference · cmp rev. req. gs costs gs rev.req. $0 $10,000,000...

20
GridSolar, LLC The GridSolar Pilot Project for Grid Reliability Sierra Club of Maine Climate Action Conference Dr. Richard Silkman, Founding Partner September 16, 2017

Upload: others

Post on 08-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

GridSolar, LLC

The GridSolar Pilot Project for Grid Reliability

Sierra Club of Maine

Climate Action Conference

Dr. Richard Silkman, Founding Partner

September 16, 2017

Page 2: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

2

Electric Grid Reliability:

The Problem

� Grid Reliability is generally a Peak Load Problem

� ME Turnpike Analogy

Maine 2017 Projected Load Duration Curve

and 1,750 MW Critical Load Level

0

500

1000

1500

2000

2500

3000

1 1 9 0 3 7 9 5 6 8 7 5 7 9 4 6 1 1 3 5 1 3 2 4 1 5 1 3 1 7 02 1 8 9 1 2 08 0 2 2 6 9 2 4 5 8 2 6 4 7 2 8 3 6 3 02 5 3 2 1 4 3 4 03 3 5 9 2 3 7 8 1 3 9 7 0 4 1 5 9 4 3 4 8 4 5 3 7 4 7 2 6 4 9 1 5 5 1 04 5 2 9 3 5 4 8 2 5 6 7 1 5 8 6 0 6 04 9 6 2 3 8 6 4 2 7 6 6 1 6 6 8 05 6 9 9 4 7 1 8 3 7 3 7 2 7 5 6 1 7 7 5 0 7 9 3 9 8 1 2 8 8 3 1 7 8 5 06 8 6 9 5

MW

Critical Load Level

1,750 MW

Hours where Load Exceeds

Critical Load Level

Page 3: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

3

Electric Grid Reliability:

Potential Solutions

� Transmission Solution – Build more Transmission to bring power from away into the Region

� Non-Transmission Alternative or “NTA” Solution - Manage Load and develop new Distributed Generation withinthe Region

Page 4: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

4

Yesterday’s Electric Grid

Large Central Generating Stations designed to serve 24 x 7 industrial loads using high voltage transmission lines and centralized dispatch control

Page 5: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

5

Tomorrow’s Electric Grid

Distributed Energy Resources located near commercial loads that are weather sensitive (more peaked) using distributed control technologies

Page 6: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

6

Smart Electric Grids

Page 7: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

7

Contrasting Visions

Utility Vision in which peak load is met by large generating facilities located far from load requiring expensive transmission systems

GridSolar Vision in which peak load is met through a smart electric grid using energy efficiency, DR, small-scale distributed solar generation and other resources located close to load

Page 8: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

8

Boothbay Pilot

Radial nature of electric service and local distribution circuits on the Boothbay peninsula defines the electrical region for the Pilot Project – Total Peak load – Approx. 30 MW.

Page 9: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

9

Boothbay Harbor, Maine

Page 10: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

10

Shock and Sag

� When a Reliability Event Occurs, the electric grid has two responses:

� “SHOCK” – frequency and voltage responds immediately, which can cause power failure.

� “SAG” – power flows on specific lines and circuits exceeds carrying capacity causing them to overheat and sag. If sag exceeds clearance, they will short causing power failure.

Page 11: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

11

Boothbay Pilot

� Hybrid Solution

� CMP – Voltage Support investments to address instantaneous response issues – “SHOCK”

� NTA Options – Manage thermal conditions on conductor feed into the region – “SAG”

� Benefit – Avoid $18 million upgrade to CMP Sub-Transmission Line serving the region.

Page 12: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

12

Pilot Design

� Term – 3 Years, option to 10 Years

� Need – up to 2 MW of NTA Resources

� modular, can scale with load

� NTA Types – Target 250 kW each� Efficiency

� Renewable DG (125 kW Solar)

� Non-renewable DG (preference net zero CO2)

� Demand Response

� Competitive Bids - PUC approves all contracts

� Cost are recoverable in utility rates

Page 13: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

13

NTA ResourceskW RFP I RFP II Totals Pct. $/kW M

Conservation 237.0 111.3 348.3 19% 10.47$

Solar 168.8 106.8 275.6 15% 13.19$

BUGS 500.0 0.0 500.0 27% 20.63$

Demand Response 0.0 250.0 250.0 13% 57.65$

Battery 0.0 500.0 500.0 27% 75.99$

Totals 905.8 968.0 1,873.8 100%

19%

15%

27%

13%

27%

NTA Resources By Category

Conserva on

Solar

BUGS

Demand Response

Ba ery

Page 14: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

GridSolar Ops Center - Portland

� Dispatch (SCADA) System

� Direct/Cellular Link to Active NTAs

� Data loggers at Passive NTAs

� Command Interface

� CMP dispatch: load, location, duration

� GridSolar: define & issue dispatch order

� Automated, failsafe backup

� Real time monitoring & data logging

� CMP collect data at substations

14

Page 15: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

15

Boothbay Pilot – Response

Actual and Reconstituted Loads on August 11, 2016 for CMP’s Boothbay Circuit 209

26000

27000

28000

29000

30000

31000

32000

9:0

0

9:3

0

10

:00

10

:30

11

:00

11

:30

12

:00

12

:30

13

:00

13

:30

14

:00

14

:30

15

:00

15

:30

16

:00

16

:30

17

:00

17

:30

18

:00

18

:30

19

:00

19

:30

20

:00

20

:30

21

:00

21

:30

Kilowatts

Kilowatts

Kilowatts

Kilowatts

Dispatch & Reconstituted Load

Battery

BUG

Demand

Response

Thermal Energy

Storage

Efficiency

PV Solar

209 Load

Page 16: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

16

Boothbay Pilot – Response

Response of Passive and Active Distributed Energy Resources –August 11, 2016

-1600

-1400

-1200

-1000

-800

-600

-400

-200

0

9:0

0

9:3

2

10

:04

10

:36

11

:08

11

:40

12

:12

12

:44

13

:16

13

:48

14

:20

14

:52

15

:24

15

:56

16

:28

17

:00

17

:32

18

:04

18

:36

19

:08

19

:40

20

:12

20

:44

21

:16

21

:48

Kilowatts

Kilowatts

Kilowatts

Kilowatts

PV Solar

Efficiency

Thermal

Energy Storage

Demand

Response

BUG

Battery

Page 17: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

17

Comparative Costs

$0

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

Comparison of the Annual Costs of the

Transmission and NTA Solutions Over 10-

Year Planning Period

CMP Rev. Req.

GS Costs

GS Rev.Req.

$0

$10,000,000

$20,000,000

$30,000,000

$40,000,000

$50,000,000

$60,000,000

$70,000,000

$80,000,000

20

12

20

16

20

20

20

24

20

28

20

32

20

36

20

40

20

44

20

48

20

52

20

56

Comparison of the Cumulative Costs of the

Transmission and NTA Solutions

CMP Rev.Req.

GS Costs

GS Rev.Req.

$5.87

Million$1.75

Million

$75.75

Million

Page 18: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

18

Findings/Conclusions

1. NTAs can provide the same degree of grid reliability at less cost than transmission solutions

2. While Transmission Costs keep going up and up and up – NTA costs are going down and down and down

3. We are currently utilizing only a tiny fraction of the capabilities of CMP’s increasingly smart electric grid

4. Public policies should encourage not discourage customer installation of Distributed Energy Resources

Page 19: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

19

Last Thought …

DO NOT underestimate how difficult it will be to implement the lessons learned from the Boothbay Pilot

The barriers utilities will erect –while not insurmountable - are very formidable ... e.g. NYS REV, CMP – Net Metering

Page 20: Sierra Club of Maine Climate Action Conference · CMP Rev. Req. GS Costs GS Rev.Req. $0 $10,000,000 $20,000,000 $30,000,000 $40,000,000 $50,000,000 $60,000,000 $70,000,000 $80,000,000

GridSolar, LLC

Contact Information

www.gridsolar.com

(207) 772-6190