Page 1: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 1

Sewer Lateral Sewer Lateral Inspection ProgramInspection Program

Page 2: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 2

SLIP SLIP Presentation OverviewPresentation OverviewIntroduction - System InformationPublic Process - Ordinance Committee Discussion - Direction to Staff

Implementation; CCTV, Data Management, Decision MakingEligibility

Ordinance Inspection Requirements - Standards and Requirements Incentive Program General Information

Financial Impact

Challenges Ahead – Recommend Significant Program UpdatesLessons Learned – Program Summary

Page 3: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 3

City of Santa Barbara City of Santa Barbara Collection SystemCollection System 277 Miles of Mainline (4 – 42 inches)

~ 350 miles of Private Laterals

9 Lift Stations

Active SSMP

System dates to 1870’s - has grown with the City

>50% of pipes installed in 1950’s & 1960’s

Private laterals represent significant portion of system

Approximately 23,910 wastewater user fee accounts

Primary Causes of Spills

I&I

Lateral/Plumbers Roots

Page 4: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 4

Changing Culture –Changing Culture – New Expectations for New Expectations for Collection System ManagementCollection System Management

Changing expectations require changes in the way we do business.

Regulatory Scrutiny - SSMP

• Statewide WDR

• Site specific WDRs/NPDES permits

NGO Scrutiny

Page 5: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 5

Objectives of;Objectives of; Sewer Lateral Inspection ProgramSewer Lateral Inspection Program

Reduce Sewer Spills

Protect Public Health and Safety

Protect the Environment

Promote private infrastructure maintenance

Page 6: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 6

Why Inspect LateralsWhy Inspect Laterals??

City lines routinely CCTV inspected

Laterals comprise more than ½ the sewer system

Privately owned laterals poorly maintained/replaced

Laterals will fail – planned response saves money and aggravation

Page 7: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 7

Public Problems From Private Public Problems From Private LateralsLaterals

Increased spills Private lateral spills

Public spills caused by private discharges

Increased wet weather flows Spills in collection system

Negative impacts to treatment process

Threat to treatment infrastructure

Beach Closures

Program development aimed at efficiently reducing known problems

Page 8: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 8

Municipal CodeMunicipal Code Title 14.34.040Title 14.34.040

House Connection Sewer.

"House connection sewer" means that portion of the horizontal piping which extends from the public sewer to the street property line or right-of-way (part).

Maintenance of Private Systems, Etc.

It shall be the responsibility of each property owner whose property is connected to the City sewer system to maintain continuously and satisfactorily in operation at his own expense, any house connection sewer. Failure to maintain such facilities shall be sufficient for immediate revocation of the person so failing and disconnection of his premises from the public sewer. (part)

Page 9: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 9

Special ConsiderationsSpecial Considerations

Effective Program (sufficient number of inspections)

Incentives

Enforcement

Backwater valve requirement

Certification of no outdoor connections to sewer

Page 10: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 10

Options Reviewed Options Reviewed Pros – ConsPros – Cons

A. All Building Permits

B. All building permits requiring discretionary review

C. All permits with 400 or more feet of altered space

D. All permits with 400 or more feet of new space

E. Any plumbing changes

F. Any new plumbing

G. Addition of 2 or more new fixtures

H. Inspection upon sale

I. Chronic problems

J. Spill from lateral leaving property

J. Failure of Smoke Test

K. Problem identified during routine inspection of City lines

M. Every 10 Years

N. By Area (proximity to creeks)

O. Differing Frequency for Commercial/PUDS

P. Upon reports from plumbers

Q. When working on sewer main

R. Incentive Program

S. Educational Program

T. Combination of “triggers”

Page 11: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 11

Public OutreachPublic Outreach 2004 - 2005 2004 - 2005

Conducted focus group meetings with: Community Development Staff Creeks Committee Water Commission Business Representatives Contractors Environmental Groups Neighborhood Study Groups Plumbers Realtors

Page 12: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 12

Issues of ConcernIssues of Concern

Shared Laterals Require individual laterals

Require joint lateral agreement

Lines in the public right of way

Laterals constructed under structures Associated private infrastructure

upgrades (adding cleanouts & backwater valves)

Street Trees

Page 13: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 13

Recommendations Developed Recommendations Developed from Focus Group Processfrom Focus Group Process

Inspection when: Property sells

400 sq feet or more of new space added

Two or more new plumbing fixtures added

Spill from lateral

Fail smoke test

Problem identified during CCTV of City lines

Every ten years for commercial and condo’s

Reasonable cause to suspect lateral problems

Page 14: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 14

Draft Ordinance Draft Ordinance Inspection RequirementsInspection Requirements

Inspections required when:

400 sq. feet or more of new space added

2 or more new plumbing fixtures added

Spill from private lateral occurs

Private lateral fails smoke test

Problem identified during CCTV of City lines

Every ten years for commercial and condo’s

Reasonable cause to suspect lateral problems

Page 15: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 15

Incentives - Homeowner Incentives - Homeowner AssistanceAssistance

Rebate for inspections – $150 per inspection if lateral in good repair

Rebate for repair/replacement 50% of cost up to $2,000 per lateral

Low interest loans may also be available to qualified owners through the City Affordable Housing Program

Page 16: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 16

Other IssuesOther Issues Shared Laterals

Inspection required only on portion of lateral on owner’s property and in public right-of-way

Septic Tanks Same requirements for inspection as laterals

Exemptions Line installed in past 20 years Line inspected in past 3 yearswith proof of submitted documents

New

Sewer Tap scheduling procedures

Commercial – Condominiums

Page 17: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 17

CCTV Standards and RequirementsCCTV Standards and Requirements for a System for a System

Inspection “Snapshot” Inspection “Snapshot” Proactive Approach Development of Specifications Inspection Planning Process Programmatic Inspection

Planning Scheduling Computerized Data Management Includes:

• Standards

• Defect Codes

• Photos Quality Assurance and Quality Control Program

Enhances implementation of: Scheduled periodic Condition Assessment Seek out and correct deficiencies prior to system failure

Page 18: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 18

Data ManagementData Management POSM – Management Software

NASSCO – • Inspection “Language”

CarteGraph – Work Order System – SEWERview

Sewer Model

GIS – Master Repository for storing and accessing system information; roughly 27% of the laterals populated with information (6,530 out of 23,910) showing general data

Page 19: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 19

Approved MethodsApproved Methods

Conventional method

(open cut dig and replace)

Pipe bursting (HDPE)

Inversion lining (case by case basis) pre-approval and post video required

Page 20: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 20

Public OutreachPublic Outreach Advertise incentives

Inform of requirement to maintain laterals

Provide information on City TV

Outreach to condominium associations

Board of Realtor’s Association

Outreach to business community

Forms available on City website www.SantaBarbaraCA.gov/lateral

Page 21: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 21

PaPamphletsmphlets

Page 22: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 22

Administrative GuidelinesAdministrative Guidelines

4.Private Sewer Lateral Inspection Program – Administrative Guidelines. This section explains when inspection is required; outlines the administrative process used to notify property owner of inspection requirement; and details the timeline for compliance. Ability to ensure proper installation, testing, and inspection of new and rehabilitated service laterals.

Section Section Title

14.46.040.A Health And Safety Inspections

14.46.040.B Events Requiring An Inspection of Residential Sewer Laterals

14.36.040.C Inspection of Commercial Properties, Condominiums And Other Common Interest Developments

14.48.0040.D Exemptions-Sewer Lateral Inspections Will Not Be Required Under the Following Conditions

14.46.050 Qualified Inspection Companies

28.87.220 Zoning Information Report Preparation

Page 23: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 23

SSewer ewer LLateral ateral IInspection nspection PProgramrogramOn November 21, 2006;

City Council passed a resolution to:

Require property owners to proactively maintain sewer lateral

Pay Incentives:

- $150 for inspections

- $2,000 for repairs / replacements

- Permit Fees

Effective January 1, 2007 – Residential

Effective January 1, 2008 – Commercial – Condo’s – Grid system

Page 24: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 24

SSewer ewer LLateral ateral IInspection nspection PProgramrogramInitiated January 2007Initiated January 2007

Targeted Replacement Level: 100 laterals Annually

Estimated Program Cost: - Staff per year (2 FTE): $ 145,000

- Permit fees: $ 145,200

- Rebates, $2,000 per lateral: $ 200,000

Total estimated annual cost: $ 490,000

Page 25: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 25

Page 26: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 26

Completed cases: Residential 158 Commercial 0 Condo 0 Total: 158

City paid incentives: Inspections only $ 1,205.90 Repairs $ 144,654.05 Permits $ 73.173.16 Total Costs of Incentives & permits Fees $ 219,033.11

FY2007 SLIP OverviewFY2007 SLIP Overview(Funding & Costs 6 months - January to June, 2007)(Funding & Costs 6 months - January to June, 2007)Funding:

FY 2007 Allocation $ 200,000

Additional Administrative Allocation $ 19,500

Total FY 2007 Allocations $ 219,500

Page 27: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 27

FY 2008 SLIP OverviewFY 2008 SLIP OverviewFY 2008 FUNDING & COSTSFY 2008 FUNDING & COSTS

Completed cases Residential 433 Commercial 265 Condo 8 Total: 706

City paid incentives: Inspections only $ 2,444.74 Repairs $ 468,876.42 Permits $ 192,249.99

Total Cost of Incentives and Permit fees $ 651.571.15

Funding: FY 2008 Allocation $ 250,000 Additional Administrative Allocation $ 125,000 Additional Funding from WW Fund $ 240,000 Total FY 2008 Allocations $ 615,000

Page 28: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 28

FY2009 SLIP OverviewFY2009 SLIP Overview(July 31, 2008 – June 30, 2009)(July 31, 2008 – June 30, 2009)

Completed cases Residential 436 Commercial 31 Condo 12 Total 479

City paid incentives Inspections only $ 2,400.00 Repairs $ 713,029.47

Permits $ 219,173.12 Total Incentives & permits $ 934,612.59

Page 29: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 29

CostCost to Date (1/1/07 - 6/30/09)to Date (1/1/07 - 6/30/09)

CY2007 CY 2008 CY 2009 )

CCTV videotape only - $ 2,625.64 $ 2,975.00 $ 450.00

Repair/Replace - $ 373,215.47 $ 638,247.47 $ 303,097.00

Permit Costs - $ 157,939.09 $ 199,996.17 $ 126,671.01

Total Cost - $ 533,780.20 $ 841,218.64 $ 430,218.01

Total Cost to Date: $1, 805,216.85

SSewer ewer LLateral ateral IInspection nspection PProgramrogram

Page 30: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 30

Sewer Lateral Inspection ProgramSewer Lateral Inspection Program(SLIP)(SLIP)

Implemented January 2007

Requires Sewer Lateral Inspections & Repair if Necessary

Reimbursement Payments for Inspection & Repair

Jan 2007 – Oct 2009 -1,484 Inspections or Repairs Completed

Possible Cause of Increase Private Related Spills

Page 31: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 31

SLIP Costs Jan 2007 – June 2009SLIP Costs Jan 2007 – June 2009

CY 2007 CY 2008 CY 2009

Inspection $ 2,626 $ 2,975 $ 450

Repair/ Replacement

$373,216 $638,247 $303,097

Permit Costs $157,939 $199,996 $126,671

Total Costs $533,778 $841,218 $430,218

Total $1,805,214

Page 32: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 32

Why Bother With All of This?Why Bother With All of This? Provides snapshot of system needs

Identifies immediate needs Priority Preventative Maintenance

Prioritize Maintenance Program and Staffing needs

Identifies long term needs Repair/Replacement – CIP

Evaluate Funding Needs

Evaluate Projected Fund availability

Page 33: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 33

Wastewater ModelWastewater Model

Page 34: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 34

Performance Measures Performance Measures Measurable ObjectivesMeasurable Objectives

3. Review 90% of all private lateral CCTV inspection tapes within 5 days of receipt. Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

90% 100% 100% 100% 100% 100%

3. Review 90% of all private lateral CCTV inspection tapes within 5 days of receipt. Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

90% 100% 100% 100% 100% 100%

12. Number of private laterals replaced.

Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

100 116 99 99 87 401

12. Number of private laterals replaced.

Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

100 116 99 99 87 401

13. Number of incentives issued for private lateral replacement/repair/inspection.

Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

100 123 105 100 89 417

13. Number of incentives issued for private lateral replacement/repair/inspection.

Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

100 123 105 100 89 417

14. Administrative action requiring private lateral replacement/repair/inspection.

Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

20 2 1 0 0 3

14. Administrative action requiring private lateral replacement/repair/inspection.

Annual Target QTR 1 Jul-Sep QTR 2 Oct-Dec QTR 3 Jan-Mar QTR 4 Apr-Jun YTD

20 2 1 0 0 3

Page 35: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 35

Challenges Ahead!Challenges Ahead!

Predictive Centered SLIP Program optimization outcome

Decision process based on response from CCTV data

GIS integrated with CarteGraph database creates operational effectiveness

Meeting Measurable Goals & Objectives

As program matures, volume of data required to manage increases

Page 36: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 36

Earth Day

Page 37: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 37

Significant Program/Updates – Significant Program/Updates – scheduled for City Council February 2010scheduled for City Council February 2010

City required to; Identify mechanism for disqualification – appeal process Qualified Inspector’s list Sewer Lateral Incentive Payment Request Form modified to include:

Specific plumbing contractor section that needs to be dated and signed Specific property owner section that needs to be dated and signed Mandatory customer survey on back of form Incentive rebate changed; up to 10% upper lateral – up to 20% lower lateral - not

to exceed $2,000.00 Incentive rebate tied to cost of lowest bid

Property owners required to; Obtain mandatory minimum two bids before signing contract

Plumbers required to; Mandatory requirement for plumbers to provide 3 Day Right to Cancel document Itemized invoice that includes a cost breakdown per foot

Page 38: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 38

Disqualification Procedures Disqualification - for minimum period of 60 days. Three or more occurrences WITHIN ONE YEAR PERIOD of the infractions listed

below: Incomplete inspection reports Submissions of poor quality tapes or unreadable CD’s Invoices without appropriate cost breakdown Unprofessional or rude conduct to customers or City staff Inappropriate solicitation while representing the SLIP Program

Disqualification - for minimum period of up to one full year. Three or more occurrences WITHIN ONE YEAR PERIOD of the infractions listed

below: Permits not pulled for work done Permits pulled after work was already begun Lack of proper sign posting Lack of traffic control, MUTCD Not following Best Management Practices Improper shoring for trench holes Stating that work was completed for work never done

Page 39: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 39

Miscellaneous FeesMiscellaneous Fees

CCTV inspection to identify lateral location - $200.00/hr. – 2 staff

Response to private lateral overflow - $300.00/hr. – 2 staff

Damage to public sewer main - $200.00/ft. or $300.00/hr. + 15% markup on parts and material

Request for City assistance - $200.00/ individual request/day

Page 40: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 40

Legal Authority; Case StudyLegal Authority; Case Study

600 Blk. Del Monte Ave.

Original Notification sent - 2007

Mediation; July 20, 2009 – no agreement

Superior Court; July 31, 2009 Judgment; $30,000 fine

Mediation - agree to $7,000 fine and $250/day fine if not completed with 10 working days plus court costs.

Final outcome; new lateral installed August 9, 2009.

Page 41: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 41

Manuel RomeroWastewater System SuperintendentSanta Barbara, CA Ph. (805) 568-1020 [email protected]

santabarbaraca.gov/lateral

Page 42: Sewer Lateral  Inspection Program

City of Santa Barbara • Public Works Department 42

Featured Article – December Featured Article – December 20092009