setiawan 2009 renewable-energy

Upload: gururaj-banda

Post on 06-Apr-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    1/10

    Design, economic analysis and environmental considerations of mini-grid hybrid

    power system with reverse osmosis desalination plant for remote areas

    Ahmad Agus Setiawan*, Yu Zhao, Chem. V. Nayar

    Department of Electrical and Computer Engineering, Curtin University of Technology, GPO Box U1987, Perth WA 6845, Australia

    a r t i c l e i n f o

    Article history:

    Available online 21 July 2008

    Keywords:

    Hybrid system

    Reverse osmosis

    Economic analysis

    Emissions

    CO2NOxRemote areas

    HOMER

    Emergency relief

    a b s t r a c t

    This paper discusses the design process of a mini-grid hybrid power system with reverse osmosis de-salination plant for remote areas, together with an economic analysis and environmental considerations

    for the project life cycle. It presents a design scenario for supplying electricity and fulfilling demand for

    clean water in remote areas by utilising renewable energy sources and a diesel generator with a reverse

    osmosis desalination plant as a deferrable load. The economic issues analysed are the initial capital cost

    needed, the fuel consumption and annual cost, the total net present cost (NPC), the cost of electricity

    (COE) generated by the system per kWh and the simple payback time (SPBT) for the project. The en-

    vironmental considerations discussed are the amount of gas emissions, such as CO2 and NOx, as well as

    particulate matter released into the atmosphere. Simulations based on an actual set of conditions in

    a remote area in the Maldives were performed using HOMER for two conditions: before and after the

    Tsunami of 26th December 2004. Experimental results on the prototype 5 kVA mini-grid inverter and

    reverse osmosis desalination plant, rated at 5.5 kWh/day, are also presented here to verify the idea of

    providing power and water supplies to remote areas.

    2008 Elsevier Ltd. All rights reserved.

    1. Introduction

    Providing energy for a community, in a sustainable manner,

    nowadays has become a more and more important issue as we face

    global warming and climate change realities. Power generation

    engineers and designers have a responsibility to improve tech-

    niques of energy conversion in order to reduce emissions of CO2and NOx, which are believed to be a source of environmental deg-

    radation. Harnessing renewable energy sources which are abun-

    dantly available in nature provides an opportunity to produce

    energy in an environmentally friendly way.

    There are many locations, especially in remote areas of de-

    veloping countries, which have no access to a reliable power sup-

    ply. This situation mainly is due to the geographical conditions ofthe areas, which make it uneconomic to build any connection to the

    existing power grid lines. Most of these areas rely on diesel gen-

    erators for their power supply. However, this conventional gener-

    ation depends on the availability of fossil fuel that usually is quite

    expensive. Beside that, the engines usually operate at lowefficiency

    due to the typical loads in remote areas that vary considerably

    during the day and night. Therefore, with an appropriate design,

    combining a reliable diesel generator with a renewable energy

    generator can solve these economic and environmental problems

    to supply the energy demands for those particular areas in a sus-

    tainable way.

    In addition, there are plenty of opportunities for renewable

    energy applications in emergency relief conditions, for example,

    after the tsunami disaster that happened recently, as well as any

    other natural disaster (such as earthquake, volcanic eruption, etc.),

    which usually results in isolating affected areas, especially if it

    happens in a remote location. Most of these areas usually suffer

    from the destruction of their infrastructure such as power and

    water supplies.

    This paper presents a design process, economic analysis and

    environmental considerations of a mini-grid hybrid power system

    with reverse osmosis desalination plant for providing electricityand clean water supplies for remote areas. The design steps are

    presented for supplying electricity and clean water in remote areas

    by utilising renewable energy sources (wind and photovoltaic) and

    a diesel generator with a reverse osmosis desalination plant as

    a deferrable load. The economic analysis considersthe initial capital

    cost needed, the fuel consumption and annual cost, the total net

    present cost and the cost of electricity generated by the system per

    kWh. Furthermore, the simple payback time (SPBT) calculation is

    also presented in order to show the project feasibility from an

    economic point of view. The environmental aspects analysed are

    the amount of gas emissions such as CO2 and NOx as well as par-

    ticulate matter released into the atmosphere.* Corresponding author. Tel.: 61 892 661784; fax: 61 892 662584.

    E-mail address: [email protected] (A.A. Setiawan).

    Contents lists available at ScienceDirect

    Renewable Energy

    j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m / l o c a t e / r e n e n e

    0960-1481/$ see front matter 2008 Elsevier Ltd. All rights reserved.doi:10.1016/j.renene.2008.05.014

    Renewable Energy 34 (2009) 374383

    mailto:[email protected]://www.sciencedirect.com/science/journal/09601481http://www.elsevier.com/locate/renenehttp://www.elsevier.com/locate/renenehttp://www.sciencedirect.com/science/journal/09601481mailto:[email protected]
  • 8/2/2019 Setiawan 2009 Renewable-Energy

    2/10

    Simulations based on the actual conditions in a remote area of

    the Maldives were performed using HOMER, for two conditions:

    before and after the Tsunami of 26th December 2004. Experimental

    works on prototypes of a 5 kVA mini-grid inverter and a reverse

    osmosis desalination plant, rated at 5.5 kWh/day, have been com-

    pleted and the results are also presented here to verify the idea of

    providing power and water supplies to remote areas.

    2. Hybrid power system

    There is a huge potential for utilising renewable energy sources,

    for example solar energy, wind energy or micro hydropower, to

    provide a quality power supply to remote areas. The abundant

    energy available in nature can be harnessed and converted to

    electricity in a sustainable way to supply the necessary power to

    elevate the living standards of people without access to the elec-

    tricity grid.

    The advantages of using renewable energy sources for gener-

    ating power in remote areas are obvious: the cost of transported

    fuel is often prohibitive, and there is increasing concern about fossil

    fuels and the issues of climate change and global warming. The

    disadvantage of stand-alone power systems using renewable en-

    ergy is that the availability of renewable energy sources has daily

    and seasonal patterns which result in difficulties in regulating the

    output power to cope with the load demand. Combining renewable

    energy generation with conventional diesel power generation willenable the power generated from renewable energy sources to be

    more reliable and affordable. This kind of electric power generation

    system, which consists of renewable energy and fossil fuel gener-

    ators together with an energy storage system and power condi-

    tioning system, is known as a hybrid power system [5].

    Fig. 1. Series hybrid power system configuration.

    Fig. 2. Parallel hybrid power system configuration.

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 375

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    3/10

    A hybrid power system has the ability to provide 24-h grid

    quality electricity to the load. This system offers better efficiency,

    flexibility of planning and environmental benefits compared to the

    diesel generator stand-alone system. The usual maintenance costs

    of a diesel generator can be decreased as a consequence of im-

    proving the efficiency of operation and reducing the operational

    time, which also means less fuel usage. Furthermore, the system

    provides an opportunity for expanding its capacity in order to cope

    with increasing demand in the future. This can be done by in-

    creasing either the rated power of the diesel generator, renewable

    generator or both.

    The hybrid power systems which utilize renewable energy

    generators can be classified into two basic configurations: series

    hybrid system and parallel hybrid system.

    2.1. Series hybrid power system

    In a series hybrid system configuration, as shown in Fig. 1,

    power generated by a diesel generator, wind generator and solar

    PV array are used to charge a battery bank. The inverter will

    convert the DC power stored in the battery bank to AC, at

    a standard level of voltage and frequency, and then supply it to

    the load.

    Battery charging can be controlled either by controlling the

    excitation of the alternator or by utilising wind/solar charger reg-

    ulators that can prevent overcharging of the battery bank from the

    wind/PV generators when the renewable power exceeds the load

    demand and when the batteries are fully charged.

    Fig. 3. AC coupling of parallel hybrid power system.

    Fig. 5. Mini-grid hybrid power system with RO plant configuration.

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    Load(kW)

    1 3 5 7 9 11 13 15 17 19 21 23

    Hours

    Fig. 4. Estimated daily load profile for a remote area in the Maldives after the tsunami.

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383376

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    4/10

    This configuration results in relatively simple implementation

    but it has some drawbacks, such as: low overall efficiency, re-

    quirement for a large battery bank to limit the depth-of-discharge,

    and limited control of the diesel alternator since the system isbased on the level of charge in the battery rather than the site load.

    2.2. Parallel hybrid power system

    In a parallel hybrid system configuration, as shown in Fig. 2, the

    diesel generator and renewable energy generator supply a portion

    of the load demand directly. This system utilises a bi-directionalinverter, which is operated in parallel with the diesel generator and

    can act as an inverter and rectifier/battery charger. The design

    principles of this system are relatively complicated but it has su-

    periority compared to the series configuration; for example, the

    system load in this configuration can be met in the most optimal

    way, the diesel efficiency can be maximized and there are possible

    reductions in the capacities of diesel, battery and renewable energy

    generators while meeting the load peaks.

    The parallel hybrid power system, shown in Fig. 2, is a DC

    coupling configuration where the renewable energy generators are

    connected to a battery bank through the DC bus and supply ACload

    through the bi-directional inverter. This configuration can further

    be improved by connecting all of the renewable generators to the

    AC bus to perform an AC coupling configuration, as shown in Fig. 3.Since this parallel topology has advantages regarding the control-

    lability of the system, only this topology is considered for the de-

    sign of a mini-grid hybrid power system in this paper [1].

    3. Design procedures and simulation

    There are a number of issues that should be considered in de-

    signing a mini-grid hybrid power system: power demand topology,

    cost of fuel in the particular area, availability of the renewable

    energy resources, initial cost of the project including cost of each

    component needed, project life time, interest rate, subsidization of

    scheme, etc. Comparison analysis on the diesel-only system (which

    is the common case foran autonomous power generation system in

    remote areas), with the proposed hybrid system can be performedto observe the feasibility of the design project [7].

    For this project, we selected one of the remote islands in the

    Maldives which, after the tsunami disaster, now is populated by

    approximately 300 people. Before tsunami, power supply was

    maintained by operating two diesel generators with capacities of

    40 kW and 32 kW. According to the Island Development Committee

    (IDC),the influential authority in the island that makes decisionson

    island development including electrification, the estimated load

    distribution for the post-tsunami day is shown as in Fig. 4. This

    primary load has an annual average of 298 kWh/day with an annual

    peak of 37.4 kW [8].

    In the simulation, in order to provide a consumable water

    supply, a reverse osmosis desalination plant was chosen as a de-

    ferrable load to the system. The RO plant should be capable ofsupplying 5 m3 of fresh water per day. This system consumes

    Table 1

    Economic analysis results from HOMER simulation

    Parameter Before tsunami After tsunami

    Diesel only PV-diesel Wind-diesel PV/wind-diesel

    Ini ti al c apital c ost $ 57,600 $165,900 $185,900 $209, 900

    Total net present

    cost

    $709,055 $646,359 $632,159 $635,386

    Cost of electricity

    ($/kWh)

    $0.510 $0.447 $0.437 $0.439

    Annual fuel

    consumed (L)

    55,494 40,919 37,247 35,252

    Annual fuel cost $35,516 $26,188 $23,838 $22,561

    Table 2

    Simple payback time calculations

    Paramet er Di esel on ly PV- di esel Wi nd-die sel PV/wi nd-diesel

    Initial cost $57,600 $165,900 $185,900 $209,900

    Annual fuel cost $35,516 $26,188 $23,838 $22,561

    SPBT in years 11.6 11 11.8

    Table 3

    Pollutants emitted from the power systems

    Parameter Diesel only PV-diesel Wind-diesel PV/wind-diesel

    CO2 (kg/yr) 146,135 107,753 107,753 98,829

    CO (kg/yr) 361 266 266 229

    UHC (kg/yr) 40 29.5 29.5 25.4

    PM (kg/yr) 27.2 20.1 20.1 17.3

    SO2 (kg/yr) 293 216 216 186

    NOx (kg/yr) 3,219 2,373 2,373 2,045

    Table 4Percentage of energy production

    Paramet er Di esel on ly P V-die se l Win d-die se l PV/wi nd-diesel

    Diesel 100% 86% 80% 76%

    PV 0 14% 0 4%

    Wind 0 0 20% 20%

    Diesel efficiency 21.9% 30.5% 30.4% 30.4%

    Water supply No Yes Yes Yes

    Fig. 6. Equivalent circuit diagram of hybrid system.

    Fig. 7. Energy management in hybrid system.

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 377

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    5/10

    2.5 kW of power and needs to be operated for 8 h per day. A fresh

    water tank is designed to have storage capacity for two days de-mand. So, there will be a 20 kWh/day average deferrable load with

    40 kWh storage capacities.

    For both analytical and simulation purposes, we need to have

    appropriate data on renewable energy availability for a certain

    period of time. In this preliminary study case, they were obtained

    from the Maldives government and the National Renewable Energy

    Laboratory (NREL), USA [2,6]. With all necessary inputs collected,

    we then carried out the simulation on this particular hybrid power

    system modelling, using HOMER, to find the best configuration

    [4,3]. The resultant system configuration for the mini-grid hybrid

    system is shown in Fig. 5.

    Simulations were performed for two conditions: before and

    after the tsunami. Before the tsunami, the power generator consists

    of two diesel generators, 40 kW and 32 kW. After the tsunami,

    power demands including a reverse osmosis desalination plant are

    supplied by using a mini-grid hybrid power system with several

    topology options: PV/diesel, wind/diesel and PV/wind/diesel. The

    economic analysis results obtained from the simulation for theproject period of 20 years are presented in Table 1.

    We can calculate the simple payback time (SPBT), from Table 1

    above, using the simple formulation below (Eq. (1)), and the results

    are presented in Table 2 [9,10]. As can be seen, the simple payback

    times for the hybrid systems are 11.6 years, 11 years, and 11.8 years

    for PV-Diesel, Wind-Diesel, and PV/Wind-Diesel, respectively.

    SPBT Excess Cost of hybrid system

    Rate of saving(1)

    From the simulation, we can also obtain the levels of emitted

    pollutants to the environment. It shows the total amount of emis-

    sions produced annually by the power systems. These emissions

    are a by-product of the energy conversion processes, mainly oc-

    curring in the diesel generator from fuel combustion. There are sixpollutants as simulation outputs: carbon dioxide (CO2), carbon

    monoxide (CO), unburned hydrocarbons (UHC), particulate matter

    (PM), sulfur dioxide (SO2) and nitrogen oxides (NOx); and they are

    presented in Table 3.

    In addition, the percentages of energy production from each

    system are presented in Table 4, together with diesel operative

    efficiency and supply of water capability.

    From all of the simulation results above (Tables 14), we can

    reveal that even though the diesel-only system has the least initial

    capital cost, it results in the highest total net present cost for the

    whole project, it emits more pollutant into the atmosphere, and the

    diesel system operates at low efficiency (21.9%). The hybrid systems

    utilising renewable energy generators offer a better economic

    feasibility, lower emissions and the component diesel generator

    Fig. 8. Prototype of 5 kVA mini-grid inverter.

    Fig. 9. Experimental setup for mini-grid inverter.

    Fig. 10. Efficiency of the 5 kVA mini-grid inverter.

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383378

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    6/10

    operates at a higher efficiency (above 30%) which ensures a longer

    operation lifetime. Payback time for the hybrid systems is also quite

    attractive with an average of 11.5 years in the 20-year period of the

    project. In addition, the hybrid system topologies also provide

    a fresh water supply as needed by people living in this particularremote area.

    4. Prototype experimental results

    Laboratory experiments on the prototype 5 kVA mini-grid in-

    verter and reverse osmosis desalination plant rated at 5.51 kWh/

    day were performed and the results are presented here to verify theidea of providing power and water supplies to remote areas.

    Fig. 11. (a) Voltage and current waveforms, and (b) power output.

    Fig. 12. THD for (a) voltage output, and (b) current output.

    Fig. 13. Overload handling capability at 150% rated load.

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 379

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    7/10

    4.1. Prototype of mini-grid inverter

    A power conditioning unit is the heart of the hybrid energy

    system mentioned in the previous section. A bi-directional inverter

    that can act both as inverter and charger is based on a voltage

    source inverter (VSI). VSIs have DC input voltage as the source and

    produce sinusoidal output voltage. During the inverting process the

    inverter is operated to supply power with constant voltage, thus it

    is operated in Voltage-Controlled VSI (VCVSI) mode. During the

    charging process the inverter is operated in Current-Controlled VSI

    (CCVSI) mode to ensure constant current to charge the battery

    bank. Fig. 6 shows the equivalent circuit diagram of the hybrid

    system where the inverter is operated in parallel with the diesel

    generator to supply the load.

    As shown in Fig. 7, during a low load period, power demand is

    supplied by inverting energy from the battery bank through VCVSI

    mode to provide a certain level of voltage and frequency output.

    When the load increases and the inverter is not capable of pro-

    viding the supply of power any longer, the diesel generator is op-

    erated to cover the load demand, and the excess of the energy is

    used to charge the battery in CCVSI mode.

    Fig. 8 shows the prototype of a 5 kVA inverter which acts as

    a power conditioner for the mini-grid hybrid system, and Fig. 9

    shows the experimental setup in the control room.

    The results of efficiency testing for various loading on the pro-

    totype 5 kVA mini-grid inverter are presented in Fig. 10, which

    shows the efficiency operation at 90% for a full load condition. The

    inverter produces sinusoidal voltage and current output wave-

    forms, as shown in Fig. 11, with small harmonics distortion

    (1.1% THD) as shown in Fig. 12.

    Additionally, overloading test results are presented in Fig. 13,

    which shows the capability of the prototype inverter in handling

    this situation for various changing loads. Fig. 14 shows the voltage

    regulation by the inverter for a 0150% step load change.

    4.2. Reverse osmosis desalination plant

    The experimental works on the RO system were first performed

    by conducting preliminary testing on the system prototype. Then,

    based on these preliminary data, the system was modelled and the

    mathematical formulation was derived. After that simulation was

    performed using MATLAB-SIMULINK. Finally, the simulation results

    were compared with the experimental results to verify accuracy of

    the system modelling.

    Using the MATLAB data fitting function, a mathematical ex-

    pression was derived from the preliminary test (Fig. 15) that was

    conducted on the RO unit and formulated as:

    Yp0:0002X310:0037X

    210:0824X10:000071X20:98 (2)

    where, Yp

    is the permeate flow rate, l/min; X1

    is the motor fre-

    quency, Hz; X2 is the feed water conductivity, ppm.

    Fig. 14. Voltage regulation at 150% step load.

    30004000

    50006000

    70008000

    900010000

    2025

    3035

    4042

    4446

    4850

    5254

    5658

    60

    0.4

    0.5

    0.6

    0.7

    0.8

    0.9

    1

    1.1

    1.2

    FeedWat

    erCondu

    ctivity(p

    pm)

    SupplyPowerFrequency(Hertz)

    InletFlo

    wRateof

    theProduc

    tTank(L/m)

    Fig. 15. Product water flows corresponding to the motor frequency and feed water conductivity.

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383380

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    8/10

    0 1 2 3 4 5 6 7 8

    x 104

    0.15

    0.16

    0.17

    0.18

    0.19

    0.2

    0.21

    0.22

    0.23

    Time of a day (second)

    PowerConsumption(kW)

    Fig. 17. Transient power consumption over 24 h.

    0 1 2 3 4 5 6 7 8 9

    x 104

    0.48

    0.5

    0.52

    0.54

    0.56

    0.58

    0.6

    0.62

    0.64

    0.66

    Time of a day (second)

    Waterlevelintheproducttank(%)

    Fig. 18. Water level in the product tank over 24 h.

    0

    Total Water Product

    0

    Total Energy Consumed

    kWh

    Water Capacity Motor Frequency

    Toggle Control

    power

    To WorkspaceWater Demands

    Subsystem

    Scope1

    16points

    Conductivity of feed water

    Inlet Flow Rate of the Product Tank

    Reverse Osmosis Unit

    Product flowTotal water amount

    Product Water Totalization

    Input Water Flow Rate

    Water consumption Flow Rate Water Capacity

    Initial Water Capacity

    Product WaterTank

    0

    Power Consumption Display

    Feed Water Conductivity

    Motor Frequency

    Power Consumption

    Power Consumption Calculation

    Water Consumption

    Water Capacity Motor Frequency

    Product Water Flow Rate

    PID Controller

    Mode Switch

    650

    Initial

    Water Capacity

    -K-

    Gain

    Motor Input Frequency 16points

    Frequency Scaling

    4000

    Feed Water

    Conductivity

    Transient Power Total Energy

    Energy Calculation

    Fig. 16. SIMULINK block diagram model for RO system.

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    9/10

    More explicitly, Fig. 15 reveals the water productivity of the RO

    system under different feed stream conditions, such as conductivity

    and pressure. It can be observed that the product water flow is

    higher when the motor frequency is higher and the feed water

    salinity is lower. Furthermore, the output water flow does not

    increase significantly as the motor augments beyond 40 Hz.

    A SIMULINK model of the RO unit was created in accordance

    with the membrane characteristic that was already obtained

    (Eq. (2)). A PID controller was designed and modelled, as presented

    in Fig. 16.

    With an initialwater level settingat 50% of the product tank, the

    simulations were carried out over both a 24-h and a 7-day period of

    time. Simulation results on the RO system are presented in Figs. 17

    20. It was found that the tanks water level stayed at above 60%

    most of the time, as seen in Fig. 20. The RO plant has an additional

    0 1 2 3 4 5 6 7

    x105

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    Time of a week (second)

    Powercon

    sumption(kW)

    Fig. 19. Transient power consumption over 7 days (one week).

    0 1 2 3 4 5 6 7

    x105

    0.45

    0.5

    0.55

    0.6

    0.65

    0.7

    0.75

    0.8

    0.85

    0.9

    Time of a week (second)

    Waterlevelintheproducttank(%)

    Fig. 20. Water level in the product tank over 7 days (one week).

    Table 5

    Simulation results on RO system productivity and energy consumption

    Feed water

    conductivity (ppm)

    Water productivity

    over 24 h (l)

    Energy consumption

    over 24 h (kWh)

    2000 1339 3.939

    3000 1237 3.936

    4000 1135 3.851

    5000 1033 3.959

    6000 930.4 4.078

    7000 828.3 3.886

    8000 726.1 3.824

    9000 623.9 3.75

    10000 521.7 3.818Fig. 21. Schematic diagram of the RO experimental unit.

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383382

  • 8/2/2019 Setiawan 2009 Renewable-Energy

    10/10

    feature of energy saving with a proportional, integral and derivative

    (PID) controller that monitors the demand and regulates the motor

    speed accordingly, as shown in Fig. 19.

    Simulation results on water productivity and energy consump-

    tion for the reverse osmosis desalination plant are presented inTable 5. It is shown that both the system productivity and energy

    needed by the system vary accordingly in respect to the feed water

    conductivity. The most productive performance by the RO system

    occurs at the lowest feed water conductivity.

    A prototype reverse osmosis desalination plant rated at

    5.51 kWh/day was built and tested. The schematic diagram for the

    RO unit experimental system is shown in Fig. 21 and a photograph

    of the measurement systems on the experimental setup is shown in

    Fig. 22.

    Experiments on the RO unit were conducted over 24 h for the

    expected real situation feed water conductivity condition of

    4000 ppm. Experimental data were collected and presented in

    Table 6. It was noticed that the power consumption of the RO unit

    was higher than the one obtained from the simulation result. Thismayhave been caused by the turbulence of the transient conditions

    in the experiment, such as the temperature variations. However, in

    general, the experimental result is still within the range of expected

    power coverage by the mini-grid hybrid power system and thus the

    system modelling can be justified.

    5. Conclusions

    This paper presents a design scenario to provide a reliable

    supply of power and water to meet demands for remote areas and

    emergency relief conditions. A simulation has been performed to

    find the optimum configuration for a hybrid power system by uti-

    lising HOMER software from NREL-USA. It is shown that a hybrid

    power system can provide both power and water supplies withbetter performance, both economically and environmentally viable,

    compared to the stand-alone diesel system. Laboratory experiment

    results on the prototype 5 kVA mini-grid inverter and reverse os-

    mosis desalination plant, rated at 5.51 kWh/day, were also pre-

    sented in this paper to demonstrate the feasibility of providing

    reliable power and water supplies to remote areas.

    Acknowledgements

    The authors would like to thank Curtin University of Technology

    and industry partner Regen Power Pty Ltd, Australia, for providing

    test facilities for this project. The first author would like to ac-

    knowledge the Australian Development Scholarships for providing

    support to pursue a Ph.D. degree in the Department of Electricaland Computer Engineering, Curtin University of Technology (Centre

    for Renewable Energy and Sustainable Technologies Australia,

    CRESTA).

    References

    [1] Dehbonei H, Nayar CV, et al. A multifunctional power processing unit for anoff-grid PV diesel hybrid power system. Power Electronics Specialists Con-ference, 2004. PESC 2004;04. IEEE 35th Annual.

    [2] Elliot D, Schwartz M, et al. Wind energy resource atlas of Sri Lanka and theMaldives. National Renewable Energy Laboratory; 2003.

    [3] Lambert T, Gilman P, et al. Micropower system modeling with HOMER. In:Farret FA, Simoes MG, editors. Integration of alternative sources of energy.

    John Wiley & Sons; 2006.[4] Lilienthal P, Gilman P, et al. HOMER the micropower optimization model.

    National Renewable Energy Laboratory; 2005.[5] Nayar CV, Phillips SJ, et al. Novel wind/diesel/battery hybrid energy system.

    Solar Energy 1993;51(1):6578.[6] Renne D, George R, et al. Solar resource assessment for Sri Lanka and Maldives.

    Colorado: National Renewable Energy Laboratory; 2003.[7] Setiawan AA, Nayar CV. Hybrid power system for Maldives post tsunami.

    USA: National Renewable Energy Laboratory (NREL), http://www.nrel.gov/homer/; 2006. The First HOMER User Group Webcast hosted by National Re-newable Energy Laboratory (NREL) USA.

    [8] Setiawan AA, Zhao Y, et al. Design of hybrid power system with reverseosmosis desalination plant for Maldives, AUPEC 2006. Melbourne, Australia:Victoria University; 2006.

    [9] Short W, Packey DJ, et al. A manual for the economic evaluation of energyefficiency and renewable energy technologies. Department of Energy, NationalRenewable Energy Laboratory; 1995.

    [10] Wies RW, Johnson RA, et al. Simulink model for economic analysis andenvironmental impacts of a PV with diesel-battery system for remote villages.Power Systems, IEEE Transactions 2005;20(2):692700.

    Fig. 22. Photograph of the measurement systems on the experimental beds.

    Table 6

    Experimental results on the RO system productivity and energy consumption

    Feed water

    conductivity (ppm)

    System operation

    time (h)

    Total energy

    consumption (kWh)

    Water

    consumption (l)

    4000 24 5.51 1058

    A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 383

    http://www.nrel.gov/homer/http://www.nrel.gov/homer/http://www.nrel.gov/homer/http://www.nrel.gov/homer/