setiawan 2009 renewable-energy
TRANSCRIPT
-
8/2/2019 Setiawan 2009 Renewable-Energy
1/10
Design, economic analysis and environmental considerations of mini-grid hybrid
power system with reverse osmosis desalination plant for remote areas
Ahmad Agus Setiawan*, Yu Zhao, Chem. V. Nayar
Department of Electrical and Computer Engineering, Curtin University of Technology, GPO Box U1987, Perth WA 6845, Australia
a r t i c l e i n f o
Article history:
Available online 21 July 2008
Keywords:
Hybrid system
Reverse osmosis
Economic analysis
Emissions
CO2NOxRemote areas
HOMER
Emergency relief
a b s t r a c t
This paper discusses the design process of a mini-grid hybrid power system with reverse osmosis de-salination plant for remote areas, together with an economic analysis and environmental considerations
for the project life cycle. It presents a design scenario for supplying electricity and fulfilling demand for
clean water in remote areas by utilising renewable energy sources and a diesel generator with a reverse
osmosis desalination plant as a deferrable load. The economic issues analysed are the initial capital cost
needed, the fuel consumption and annual cost, the total net present cost (NPC), the cost of electricity
(COE) generated by the system per kWh and the simple payback time (SPBT) for the project. The en-
vironmental considerations discussed are the amount of gas emissions, such as CO2 and NOx, as well as
particulate matter released into the atmosphere. Simulations based on an actual set of conditions in
a remote area in the Maldives were performed using HOMER for two conditions: before and after the
Tsunami of 26th December 2004. Experimental results on the prototype 5 kVA mini-grid inverter and
reverse osmosis desalination plant, rated at 5.5 kWh/day, are also presented here to verify the idea of
providing power and water supplies to remote areas.
2008 Elsevier Ltd. All rights reserved.
1. Introduction
Providing energy for a community, in a sustainable manner,
nowadays has become a more and more important issue as we face
global warming and climate change realities. Power generation
engineers and designers have a responsibility to improve tech-
niques of energy conversion in order to reduce emissions of CO2and NOx, which are believed to be a source of environmental deg-
radation. Harnessing renewable energy sources which are abun-
dantly available in nature provides an opportunity to produce
energy in an environmentally friendly way.
There are many locations, especially in remote areas of de-
veloping countries, which have no access to a reliable power sup-
ply. This situation mainly is due to the geographical conditions ofthe areas, which make it uneconomic to build any connection to the
existing power grid lines. Most of these areas rely on diesel gen-
erators for their power supply. However, this conventional gener-
ation depends on the availability of fossil fuel that usually is quite
expensive. Beside that, the engines usually operate at lowefficiency
due to the typical loads in remote areas that vary considerably
during the day and night. Therefore, with an appropriate design,
combining a reliable diesel generator with a renewable energy
generator can solve these economic and environmental problems
to supply the energy demands for those particular areas in a sus-
tainable way.
In addition, there are plenty of opportunities for renewable
energy applications in emergency relief conditions, for example,
after the tsunami disaster that happened recently, as well as any
other natural disaster (such as earthquake, volcanic eruption, etc.),
which usually results in isolating affected areas, especially if it
happens in a remote location. Most of these areas usually suffer
from the destruction of their infrastructure such as power and
water supplies.
This paper presents a design process, economic analysis and
environmental considerations of a mini-grid hybrid power system
with reverse osmosis desalination plant for providing electricityand clean water supplies for remote areas. The design steps are
presented for supplying electricity and clean water in remote areas
by utilising renewable energy sources (wind and photovoltaic) and
a diesel generator with a reverse osmosis desalination plant as
a deferrable load. The economic analysis considersthe initial capital
cost needed, the fuel consumption and annual cost, the total net
present cost and the cost of electricity generated by the system per
kWh. Furthermore, the simple payback time (SPBT) calculation is
also presented in order to show the project feasibility from an
economic point of view. The environmental aspects analysed are
the amount of gas emissions such as CO2 and NOx as well as par-
ticulate matter released into the atmosphere.* Corresponding author. Tel.: 61 892 661784; fax: 61 892 662584.
E-mail address: [email protected] (A.A. Setiawan).
Contents lists available at ScienceDirect
Renewable Energy
j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m / l o c a t e / r e n e n e
0960-1481/$ see front matter 2008 Elsevier Ltd. All rights reserved.doi:10.1016/j.renene.2008.05.014
Renewable Energy 34 (2009) 374383
mailto:[email protected]://www.sciencedirect.com/science/journal/09601481http://www.elsevier.com/locate/renenehttp://www.elsevier.com/locate/renenehttp://www.sciencedirect.com/science/journal/09601481mailto:[email protected] -
8/2/2019 Setiawan 2009 Renewable-Energy
2/10
Simulations based on the actual conditions in a remote area of
the Maldives were performed using HOMER, for two conditions:
before and after the Tsunami of 26th December 2004. Experimental
works on prototypes of a 5 kVA mini-grid inverter and a reverse
osmosis desalination plant, rated at 5.5 kWh/day, have been com-
pleted and the results are also presented here to verify the idea of
providing power and water supplies to remote areas.
2. Hybrid power system
There is a huge potential for utilising renewable energy sources,
for example solar energy, wind energy or micro hydropower, to
provide a quality power supply to remote areas. The abundant
energy available in nature can be harnessed and converted to
electricity in a sustainable way to supply the necessary power to
elevate the living standards of people without access to the elec-
tricity grid.
The advantages of using renewable energy sources for gener-
ating power in remote areas are obvious: the cost of transported
fuel is often prohibitive, and there is increasing concern about fossil
fuels and the issues of climate change and global warming. The
disadvantage of stand-alone power systems using renewable en-
ergy is that the availability of renewable energy sources has daily
and seasonal patterns which result in difficulties in regulating the
output power to cope with the load demand. Combining renewable
energy generation with conventional diesel power generation willenable the power generated from renewable energy sources to be
more reliable and affordable. This kind of electric power generation
system, which consists of renewable energy and fossil fuel gener-
ators together with an energy storage system and power condi-
tioning system, is known as a hybrid power system [5].
Fig. 1. Series hybrid power system configuration.
Fig. 2. Parallel hybrid power system configuration.
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 375
-
8/2/2019 Setiawan 2009 Renewable-Energy
3/10
A hybrid power system has the ability to provide 24-h grid
quality electricity to the load. This system offers better efficiency,
flexibility of planning and environmental benefits compared to the
diesel generator stand-alone system. The usual maintenance costs
of a diesel generator can be decreased as a consequence of im-
proving the efficiency of operation and reducing the operational
time, which also means less fuel usage. Furthermore, the system
provides an opportunity for expanding its capacity in order to cope
with increasing demand in the future. This can be done by in-
creasing either the rated power of the diesel generator, renewable
generator or both.
The hybrid power systems which utilize renewable energy
generators can be classified into two basic configurations: series
hybrid system and parallel hybrid system.
2.1. Series hybrid power system
In a series hybrid system configuration, as shown in Fig. 1,
power generated by a diesel generator, wind generator and solar
PV array are used to charge a battery bank. The inverter will
convert the DC power stored in the battery bank to AC, at
a standard level of voltage and frequency, and then supply it to
the load.
Battery charging can be controlled either by controlling the
excitation of the alternator or by utilising wind/solar charger reg-
ulators that can prevent overcharging of the battery bank from the
wind/PV generators when the renewable power exceeds the load
demand and when the batteries are fully charged.
Fig. 3. AC coupling of parallel hybrid power system.
Fig. 5. Mini-grid hybrid power system with RO plant configuration.
0
2
4
6
8
10
12
14
16
18
20
Load(kW)
1 3 5 7 9 11 13 15 17 19 21 23
Hours
Fig. 4. Estimated daily load profile for a remote area in the Maldives after the tsunami.
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383376
-
8/2/2019 Setiawan 2009 Renewable-Energy
4/10
This configuration results in relatively simple implementation
but it has some drawbacks, such as: low overall efficiency, re-
quirement for a large battery bank to limit the depth-of-discharge,
and limited control of the diesel alternator since the system isbased on the level of charge in the battery rather than the site load.
2.2. Parallel hybrid power system
In a parallel hybrid system configuration, as shown in Fig. 2, the
diesel generator and renewable energy generator supply a portion
of the load demand directly. This system utilises a bi-directionalinverter, which is operated in parallel with the diesel generator and
can act as an inverter and rectifier/battery charger. The design
principles of this system are relatively complicated but it has su-
periority compared to the series configuration; for example, the
system load in this configuration can be met in the most optimal
way, the diesel efficiency can be maximized and there are possible
reductions in the capacities of diesel, battery and renewable energy
generators while meeting the load peaks.
The parallel hybrid power system, shown in Fig. 2, is a DC
coupling configuration where the renewable energy generators are
connected to a battery bank through the DC bus and supply ACload
through the bi-directional inverter. This configuration can further
be improved by connecting all of the renewable generators to the
AC bus to perform an AC coupling configuration, as shown in Fig. 3.Since this parallel topology has advantages regarding the control-
lability of the system, only this topology is considered for the de-
sign of a mini-grid hybrid power system in this paper [1].
3. Design procedures and simulation
There are a number of issues that should be considered in de-
signing a mini-grid hybrid power system: power demand topology,
cost of fuel in the particular area, availability of the renewable
energy resources, initial cost of the project including cost of each
component needed, project life time, interest rate, subsidization of
scheme, etc. Comparison analysis on the diesel-only system (which
is the common case foran autonomous power generation system in
remote areas), with the proposed hybrid system can be performedto observe the feasibility of the design project [7].
For this project, we selected one of the remote islands in the
Maldives which, after the tsunami disaster, now is populated by
approximately 300 people. Before tsunami, power supply was
maintained by operating two diesel generators with capacities of
40 kW and 32 kW. According to the Island Development Committee
(IDC),the influential authority in the island that makes decisionson
island development including electrification, the estimated load
distribution for the post-tsunami day is shown as in Fig. 4. This
primary load has an annual average of 298 kWh/day with an annual
peak of 37.4 kW [8].
In the simulation, in order to provide a consumable water
supply, a reverse osmosis desalination plant was chosen as a de-
ferrable load to the system. The RO plant should be capable ofsupplying 5 m3 of fresh water per day. This system consumes
Table 1
Economic analysis results from HOMER simulation
Parameter Before tsunami After tsunami
Diesel only PV-diesel Wind-diesel PV/wind-diesel
Ini ti al c apital c ost $ 57,600 $165,900 $185,900 $209, 900
Total net present
cost
$709,055 $646,359 $632,159 $635,386
Cost of electricity
($/kWh)
$0.510 $0.447 $0.437 $0.439
Annual fuel
consumed (L)
55,494 40,919 37,247 35,252
Annual fuel cost $35,516 $26,188 $23,838 $22,561
Table 2
Simple payback time calculations
Paramet er Di esel on ly PV- di esel Wi nd-die sel PV/wi nd-diesel
Initial cost $57,600 $165,900 $185,900 $209,900
Annual fuel cost $35,516 $26,188 $23,838 $22,561
SPBT in years 11.6 11 11.8
Table 3
Pollutants emitted from the power systems
Parameter Diesel only PV-diesel Wind-diesel PV/wind-diesel
CO2 (kg/yr) 146,135 107,753 107,753 98,829
CO (kg/yr) 361 266 266 229
UHC (kg/yr) 40 29.5 29.5 25.4
PM (kg/yr) 27.2 20.1 20.1 17.3
SO2 (kg/yr) 293 216 216 186
NOx (kg/yr) 3,219 2,373 2,373 2,045
Table 4Percentage of energy production
Paramet er Di esel on ly P V-die se l Win d-die se l PV/wi nd-diesel
Diesel 100% 86% 80% 76%
PV 0 14% 0 4%
Wind 0 0 20% 20%
Diesel efficiency 21.9% 30.5% 30.4% 30.4%
Water supply No Yes Yes Yes
Fig. 6. Equivalent circuit diagram of hybrid system.
Fig. 7. Energy management in hybrid system.
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 377
-
8/2/2019 Setiawan 2009 Renewable-Energy
5/10
2.5 kW of power and needs to be operated for 8 h per day. A fresh
water tank is designed to have storage capacity for two days de-mand. So, there will be a 20 kWh/day average deferrable load with
40 kWh storage capacities.
For both analytical and simulation purposes, we need to have
appropriate data on renewable energy availability for a certain
period of time. In this preliminary study case, they were obtained
from the Maldives government and the National Renewable Energy
Laboratory (NREL), USA [2,6]. With all necessary inputs collected,
we then carried out the simulation on this particular hybrid power
system modelling, using HOMER, to find the best configuration
[4,3]. The resultant system configuration for the mini-grid hybrid
system is shown in Fig. 5.
Simulations were performed for two conditions: before and
after the tsunami. Before the tsunami, the power generator consists
of two diesel generators, 40 kW and 32 kW. After the tsunami,
power demands including a reverse osmosis desalination plant are
supplied by using a mini-grid hybrid power system with several
topology options: PV/diesel, wind/diesel and PV/wind/diesel. The
economic analysis results obtained from the simulation for theproject period of 20 years are presented in Table 1.
We can calculate the simple payback time (SPBT), from Table 1
above, using the simple formulation below (Eq. (1)), and the results
are presented in Table 2 [9,10]. As can be seen, the simple payback
times for the hybrid systems are 11.6 years, 11 years, and 11.8 years
for PV-Diesel, Wind-Diesel, and PV/Wind-Diesel, respectively.
SPBT Excess Cost of hybrid system
Rate of saving(1)
From the simulation, we can also obtain the levels of emitted
pollutants to the environment. It shows the total amount of emis-
sions produced annually by the power systems. These emissions
are a by-product of the energy conversion processes, mainly oc-
curring in the diesel generator from fuel combustion. There are sixpollutants as simulation outputs: carbon dioxide (CO2), carbon
monoxide (CO), unburned hydrocarbons (UHC), particulate matter
(PM), sulfur dioxide (SO2) and nitrogen oxides (NOx); and they are
presented in Table 3.
In addition, the percentages of energy production from each
system are presented in Table 4, together with diesel operative
efficiency and supply of water capability.
From all of the simulation results above (Tables 14), we can
reveal that even though the diesel-only system has the least initial
capital cost, it results in the highest total net present cost for the
whole project, it emits more pollutant into the atmosphere, and the
diesel system operates at low efficiency (21.9%). The hybrid systems
utilising renewable energy generators offer a better economic
feasibility, lower emissions and the component diesel generator
Fig. 8. Prototype of 5 kVA mini-grid inverter.
Fig. 9. Experimental setup for mini-grid inverter.
Fig. 10. Efficiency of the 5 kVA mini-grid inverter.
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383378
-
8/2/2019 Setiawan 2009 Renewable-Energy
6/10
operates at a higher efficiency (above 30%) which ensures a longer
operation lifetime. Payback time for the hybrid systems is also quite
attractive with an average of 11.5 years in the 20-year period of the
project. In addition, the hybrid system topologies also provide
a fresh water supply as needed by people living in this particularremote area.
4. Prototype experimental results
Laboratory experiments on the prototype 5 kVA mini-grid in-
verter and reverse osmosis desalination plant rated at 5.51 kWh/
day were performed and the results are presented here to verify theidea of providing power and water supplies to remote areas.
Fig. 11. (a) Voltage and current waveforms, and (b) power output.
Fig. 12. THD for (a) voltage output, and (b) current output.
Fig. 13. Overload handling capability at 150% rated load.
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 379
-
8/2/2019 Setiawan 2009 Renewable-Energy
7/10
4.1. Prototype of mini-grid inverter
A power conditioning unit is the heart of the hybrid energy
system mentioned in the previous section. A bi-directional inverter
that can act both as inverter and charger is based on a voltage
source inverter (VSI). VSIs have DC input voltage as the source and
produce sinusoidal output voltage. During the inverting process the
inverter is operated to supply power with constant voltage, thus it
is operated in Voltage-Controlled VSI (VCVSI) mode. During the
charging process the inverter is operated in Current-Controlled VSI
(CCVSI) mode to ensure constant current to charge the battery
bank. Fig. 6 shows the equivalent circuit diagram of the hybrid
system where the inverter is operated in parallel with the diesel
generator to supply the load.
As shown in Fig. 7, during a low load period, power demand is
supplied by inverting energy from the battery bank through VCVSI
mode to provide a certain level of voltage and frequency output.
When the load increases and the inverter is not capable of pro-
viding the supply of power any longer, the diesel generator is op-
erated to cover the load demand, and the excess of the energy is
used to charge the battery in CCVSI mode.
Fig. 8 shows the prototype of a 5 kVA inverter which acts as
a power conditioner for the mini-grid hybrid system, and Fig. 9
shows the experimental setup in the control room.
The results of efficiency testing for various loading on the pro-
totype 5 kVA mini-grid inverter are presented in Fig. 10, which
shows the efficiency operation at 90% for a full load condition. The
inverter produces sinusoidal voltage and current output wave-
forms, as shown in Fig. 11, with small harmonics distortion
(1.1% THD) as shown in Fig. 12.
Additionally, overloading test results are presented in Fig. 13,
which shows the capability of the prototype inverter in handling
this situation for various changing loads. Fig. 14 shows the voltage
regulation by the inverter for a 0150% step load change.
4.2. Reverse osmosis desalination plant
The experimental works on the RO system were first performed
by conducting preliminary testing on the system prototype. Then,
based on these preliminary data, the system was modelled and the
mathematical formulation was derived. After that simulation was
performed using MATLAB-SIMULINK. Finally, the simulation results
were compared with the experimental results to verify accuracy of
the system modelling.
Using the MATLAB data fitting function, a mathematical ex-
pression was derived from the preliminary test (Fig. 15) that was
conducted on the RO unit and formulated as:
Yp0:0002X310:0037X
210:0824X10:000071X20:98 (2)
where, Yp
is the permeate flow rate, l/min; X1
is the motor fre-
quency, Hz; X2 is the feed water conductivity, ppm.
Fig. 14. Voltage regulation at 150% step load.
30004000
50006000
70008000
900010000
2025
3035
4042
4446
4850
5254
5658
60
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
FeedWat
erCondu
ctivity(p
pm)
SupplyPowerFrequency(Hertz)
InletFlo
wRateof
theProduc
tTank(L/m)
Fig. 15. Product water flows corresponding to the motor frequency and feed water conductivity.
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383380
-
8/2/2019 Setiawan 2009 Renewable-Energy
8/10
0 1 2 3 4 5 6 7 8
x 104
0.15
0.16
0.17
0.18
0.19
0.2
0.21
0.22
0.23
Time of a day (second)
PowerConsumption(kW)
Fig. 17. Transient power consumption over 24 h.
0 1 2 3 4 5 6 7 8 9
x 104
0.48
0.5
0.52
0.54
0.56
0.58
0.6
0.62
0.64
0.66
Time of a day (second)
Waterlevelintheproducttank(%)
Fig. 18. Water level in the product tank over 24 h.
0
Total Water Product
0
Total Energy Consumed
kWh
Water Capacity Motor Frequency
Toggle Control
power
To WorkspaceWater Demands
Subsystem
Scope1
16points
Conductivity of feed water
Inlet Flow Rate of the Product Tank
Reverse Osmosis Unit
Product flowTotal water amount
Product Water Totalization
Input Water Flow Rate
Water consumption Flow Rate Water Capacity
Initial Water Capacity
Product WaterTank
0
Power Consumption Display
Feed Water Conductivity
Motor Frequency
Power Consumption
Power Consumption Calculation
Water Consumption
Water Capacity Motor Frequency
Product Water Flow Rate
PID Controller
Mode Switch
650
Initial
Water Capacity
-K-
Gain
Motor Input Frequency 16points
Frequency Scaling
4000
Feed Water
Conductivity
Transient Power Total Energy
Energy Calculation
Fig. 16. SIMULINK block diagram model for RO system.
-
8/2/2019 Setiawan 2009 Renewable-Energy
9/10
More explicitly, Fig. 15 reveals the water productivity of the RO
system under different feed stream conditions, such as conductivity
and pressure. It can be observed that the product water flow is
higher when the motor frequency is higher and the feed water
salinity is lower. Furthermore, the output water flow does not
increase significantly as the motor augments beyond 40 Hz.
A SIMULINK model of the RO unit was created in accordance
with the membrane characteristic that was already obtained
(Eq. (2)). A PID controller was designed and modelled, as presented
in Fig. 16.
With an initialwater level settingat 50% of the product tank, the
simulations were carried out over both a 24-h and a 7-day period of
time. Simulation results on the RO system are presented in Figs. 17
20. It was found that the tanks water level stayed at above 60%
most of the time, as seen in Fig. 20. The RO plant has an additional
0 1 2 3 4 5 6 7
x105
0
0.05
0.1
0.15
0.2
0.25
Time of a week (second)
Powercon
sumption(kW)
Fig. 19. Transient power consumption over 7 days (one week).
0 1 2 3 4 5 6 7
x105
0.45
0.5
0.55
0.6
0.65
0.7
0.75
0.8
0.85
0.9
Time of a week (second)
Waterlevelintheproducttank(%)
Fig. 20. Water level in the product tank over 7 days (one week).
Table 5
Simulation results on RO system productivity and energy consumption
Feed water
conductivity (ppm)
Water productivity
over 24 h (l)
Energy consumption
over 24 h (kWh)
2000 1339 3.939
3000 1237 3.936
4000 1135 3.851
5000 1033 3.959
6000 930.4 4.078
7000 828.3 3.886
8000 726.1 3.824
9000 623.9 3.75
10000 521.7 3.818Fig. 21. Schematic diagram of the RO experimental unit.
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383382
-
8/2/2019 Setiawan 2009 Renewable-Energy
10/10
feature of energy saving with a proportional, integral and derivative
(PID) controller that monitors the demand and regulates the motor
speed accordingly, as shown in Fig. 19.
Simulation results on water productivity and energy consump-
tion for the reverse osmosis desalination plant are presented inTable 5. It is shown that both the system productivity and energy
needed by the system vary accordingly in respect to the feed water
conductivity. The most productive performance by the RO system
occurs at the lowest feed water conductivity.
A prototype reverse osmosis desalination plant rated at
5.51 kWh/day was built and tested. The schematic diagram for the
RO unit experimental system is shown in Fig. 21 and a photograph
of the measurement systems on the experimental setup is shown in
Fig. 22.
Experiments on the RO unit were conducted over 24 h for the
expected real situation feed water conductivity condition of
4000 ppm. Experimental data were collected and presented in
Table 6. It was noticed that the power consumption of the RO unit
was higher than the one obtained from the simulation result. Thismayhave been caused by the turbulence of the transient conditions
in the experiment, such as the temperature variations. However, in
general, the experimental result is still within the range of expected
power coverage by the mini-grid hybrid power system and thus the
system modelling can be justified.
5. Conclusions
This paper presents a design scenario to provide a reliable
supply of power and water to meet demands for remote areas and
emergency relief conditions. A simulation has been performed to
find the optimum configuration for a hybrid power system by uti-
lising HOMER software from NREL-USA. It is shown that a hybrid
power system can provide both power and water supplies withbetter performance, both economically and environmentally viable,
compared to the stand-alone diesel system. Laboratory experiment
results on the prototype 5 kVA mini-grid inverter and reverse os-
mosis desalination plant, rated at 5.51 kWh/day, were also pre-
sented in this paper to demonstrate the feasibility of providing
reliable power and water supplies to remote areas.
Acknowledgements
The authors would like to thank Curtin University of Technology
and industry partner Regen Power Pty Ltd, Australia, for providing
test facilities for this project. The first author would like to ac-
knowledge the Australian Development Scholarships for providing
support to pursue a Ph.D. degree in the Department of Electricaland Computer Engineering, Curtin University of Technology (Centre
for Renewable Energy and Sustainable Technologies Australia,
CRESTA).
References
[1] Dehbonei H, Nayar CV, et al. A multifunctional power processing unit for anoff-grid PV diesel hybrid power system. Power Electronics Specialists Con-ference, 2004. PESC 2004;04. IEEE 35th Annual.
[2] Elliot D, Schwartz M, et al. Wind energy resource atlas of Sri Lanka and theMaldives. National Renewable Energy Laboratory; 2003.
[3] Lambert T, Gilman P, et al. Micropower system modeling with HOMER. In:Farret FA, Simoes MG, editors. Integration of alternative sources of energy.
John Wiley & Sons; 2006.[4] Lilienthal P, Gilman P, et al. HOMER the micropower optimization model.
National Renewable Energy Laboratory; 2005.[5] Nayar CV, Phillips SJ, et al. Novel wind/diesel/battery hybrid energy system.
Solar Energy 1993;51(1):6578.[6] Renne D, George R, et al. Solar resource assessment for Sri Lanka and Maldives.
Colorado: National Renewable Energy Laboratory; 2003.[7] Setiawan AA, Nayar CV. Hybrid power system for Maldives post tsunami.
USA: National Renewable Energy Laboratory (NREL), http://www.nrel.gov/homer/; 2006. The First HOMER User Group Webcast hosted by National Re-newable Energy Laboratory (NREL) USA.
[8] Setiawan AA, Zhao Y, et al. Design of hybrid power system with reverseosmosis desalination plant for Maldives, AUPEC 2006. Melbourne, Australia:Victoria University; 2006.
[9] Short W, Packey DJ, et al. A manual for the economic evaluation of energyefficiency and renewable energy technologies. Department of Energy, NationalRenewable Energy Laboratory; 1995.
[10] Wies RW, Johnson RA, et al. Simulink model for economic analysis andenvironmental impacts of a PV with diesel-battery system for remote villages.Power Systems, IEEE Transactions 2005;20(2):692700.
Fig. 22. Photograph of the measurement systems on the experimental beds.
Table 6
Experimental results on the RO system productivity and energy consumption
Feed water
conductivity (ppm)
System operation
time (h)
Total energy
consumption (kWh)
Water
consumption (l)
4000 24 5.51 1058
A.A. Setiawan et al. / Renewable Energy 34 (2009) 374383 383
http://www.nrel.gov/homer/http://www.nrel.gov/homer/http://www.nrel.gov/homer/http://www.nrel.gov/homer/