senior managing director brewer consulting...brewer consulting contractors payment claims obtaining...

16
Geoff Brewer Geoff Brewer Senior Managing Senior Managing Director Director Brewer Consulting Brewer Consulting

Upload: others

Post on 27-Jan-2021

8 views

Category:

Documents


0 download

TRANSCRIPT

  • Geoff BrewerGeoff BrewerSenior Managing Senior Managing

    DirectorDirector

    Brewer ConsultingBrewer Consulting

  • Contractors Payment Contractors Payment

    ClaimsClaims

  • Obtaining payment and how the Obtaining payment and how the

    market has changedmarket has changed

    • Vital importance of payment

    • Payment provisions – Contractual or Statutory

    • Contract price dealt with differently by different

    contracts

  • Contractual Payment Contractual Payment

    ProvisionsProvisions

    • Instalments provided for in most contracts

    • Value of work properly carried out, stated in certificates

    • Employer’s obligation to pay, subject to rights to

    cross claim

    • Contractual procedure to be followed

  • Improving Cash FlowImproving Cash Flow

    • Mobilisation payments

    • Working capital to get the ‘show on the road’

    • Price discount negotiated by payer

    • Surety bond required

    • Less readily available in recession

    • Manufactured goods and materials off site

    • Optional payment provisions

    • Popularity decreases when work becomes scarce

  • Improving Cash FlowImproving Cash Flow• Escrow accounts

    • Assist in financial security for contractor

    • Escrow has ring fenced funds for 2-3 months payments

    • Escrow agent acts as stakeholder for both parties

    • Contractual right to suspend or terminate employment

    • Affected by lack of project funds

    • Retention bonds

    • Provided by Surety in lieu of retention

    • Optional in JCT contracts

    • Some increased administrative burden on contractor

    • Government drive to ban retentions

  • Improving Cash FlowImproving Cash Flow

    • Recovering interest on late payment

    • Payment of interest in some standard forms

    • Statutory ability to claim interest where no contractual

    provision

    • Late Payment of Commercial Debts (Interest) Act 1998

    • Used in dispute resolution proceedings

    • Ownership and title in materials

    • Contractual provisions to reduce exposure in event of third party insolvency

  • The Construction Act andThe Construction Act and

    Sections 110 & 111Sections 110 & 111

    • The Construction Act

    • Applies to every construction contract for purposes of

    construction operations

    • Specific payment provisions required

    • Failure to provide imports the Scheme

    • Interim and stage payment provisions

    • Adequate mechanism - Final date for payment

    • Parties free to agree periods

    • Scheme provides for 28 day intervals, a set valuation method

    and 17 day period between due date and final date for

    payment

  • Statutory Payment Notification Statutory Payment Notification

    (Section 110)(Section 110)• The Act requires payment notice no later than 5 days after

    due date

    • Most standard forms keep to 5 days

    • Effect of failure depends on contract terms

    • Considered to be ‘without-teeth’

    • No sanction for failing to provide notice

    • Receiving party entitled only to be paid what is properly due

  • Withholding Notice (Section Withholding Notice (Section

    111)111)• The Act requires a withholding notice where withholding

    from an otherwise due amount

    • No maximum or minimum period stated in the Act

    • Under the Scheme, period for issue is not later than 7 days

    before the ‘final date for payment’

    • Compliant clause could state not later than 1 day

    • Withholding notice required where set-off is to be withheld

    • May be necessary where abatement is to be taken into

    account

  • Suspension for nonSuspension for non--paymentpayment

    • Statutory right where payment not made by final date for

    payment (Section 112)

    • Default position provided by the Act

    • Procedure must be followed

    • Ensure relevant conditions are satisfied before suspending

    • Extension of time for period of direct delay caused by valid

    suspension

  • Variations and Delay MattersVariations and Delay Matters

    • Variation clauses are standard fare

    • Commonly changes are not permitted which ‘go to the root of the contract’

    • Definition and procedure for issuing of variations varies from contract to contract

    • Recovery without written variation orders

    • Condition precedent clauses

    • Adhere to contract mechanisms

    • Valuation procedure

    • Must obtain maximum value within rules of the contract

  • Delay MattersDelay Matters

    • Project delays and categorisation of events

    • Extension of time provisions

    • Subject to procedures and proof

    • Condition precedent clauses

    • ‘Upfront’ mechanism to allow additional time

    • Time is money

    • Must be able to recognise, claim, demonstrate and fully

    evidence entitlements

    • Delay analysis trends

    • Content and quality of information

    • Vigorous pursuit in economic downturn

  • Payment Regime Payment Regime –– Likely Changes in Likely Changes in

    20092009• Proposed amendments to the Construction Act• Draft Construction Contracts Bill 2008

    • Improve transparency and clarity relating to payments

    • Encourage adjudication by widening Act’s ambit

    • Improve suspension rights

    • Changes to payment regime

    • Replace existing sections 110 &111

    • New S110A payment notice setting out ‘sum due’

    • Can take account of cross claims

    • New S111 notice

    • Clarifying the use of pay when paid clauses

  • Payment Regime Payment Regime –– Likely Changes Likely Changes

    in 2009in 2009

    • Section 110A notice

    • Not later than 5 days after payment due date

    • Payee can issue payment notice in default

    • Section 111 notice

    • Provides second opportunity for payer to consider and apply cross claims

  • Likely Changes in 2009Likely Changes in 2009

    • Adjudication provisions

    • Widen access - adjudication permitted on oral and partly oral/ partly written contracts

    • Prevents agreements that interim payment decisions will be conclusive

    • Parties costs agreement can only be made after adjudicator appointment

    • Improve and reinforce suspension rights

    • Suspending party can claim costs and consequential delay