semi-annual environmental safeguard monitoring report€¦ · (i) the fiscal year (fy) of the...

40
Semi-Annual Environmental Safeguard Monitoring Report Project Number: 39298-013 Semestral Report December 2015 BAN: City Region Development Project (CRDP) Prepared by Local Government Engineering Department (LGED) for the People’s Republic of Bangladesh and the Asian Development Bank.

Upload: others

Post on 15-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

Semi-Annual Environmental Safeguard Monitoring Report Project Number: 39298-013 Semestral Report December 2015

BAN: City Region Development Project (CRDP) Prepared by Local Government Engineering Department (LGED) for the People’s Republic of Bangladesh and the Asian Development Bank.

Page 2: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

CURRENCY EQUIVALENTS

(as of 31 December 2015)

Currency unit – taka (Tk) Tk1.00 = $0.01275 $1.00 = Tk78.430

NOTES

(i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2016 ends on June 2016.

(ii) In this report, "$" refers to US dollars. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

Semi-Annual Environmental Safeguard Monitoring Report

Project Number: 39298

Period: July – December 2015

Bangladesh: City Region Development Project

ADB Loan 2695-BAN

Prepared by Local Government Engineering Department

This report has been submitted to ADB by the Local Government Engineering Department,

Government of Bangladesh, and is made publicly available in accordance with ADB’s public

communications policy (2011).

Page 4: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

1

TABLE OF CONTENTS

TABLE OF CONTENTS 1

LIST OF TABLES 2

I. INTRODUCTION 3

A. Purpose of the Report 3

B. Overall Project Description and Objectives 3

C. Description of Subprojects 4

D. Environmental Category of Subprojects 5

E. Personnel Responsible for Environmental Monitoring 5

F. Overall Project and Subproject Progress and Status 6

II. COMPLIANCE STATUS WITH NATIONAL STATUTORY REQUIREMENTS 6

III. COMPLIANCE STATUS WITH ENVIRONMENTAL LOAN COVENANTS 10

IV. APPROACH FOR SAFEGUARD MANAGEMENT AND MONITORING 13

A. Environmental Safeguard Framework 13

B. Environmental Performance Indicators 16

C. Subproject Environmental Monitoring 16

D. Capacity Building 18

V. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND

MONITORING PLAN 19

A. Status of Recruitment 19

B. Subproject Environmental Safeguard Performance 19

C. Summary Lists 19

VI. CONCLUSIONS AND RECOMMENDATIONS 31

APPENDIX 1: CRDP ENVIRONMENTAL MONITORING CHECKLIST 32

Page 5: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

2

LIST OF TABLES

Table 1: Subprojects Financed under ADB Loan No. 2695-BAN ............................................................. 4

Table 2: Road and Transport Improvements in Khulna Division under KfW Funding ............................ 5

Table 3: Subproject progress and Status ......................................................................................... 6

Table 4: Status of Environment and Related Loan Covenants as of 30 June 2014 ............................... 11

Table 5: Status of IEEs for Batch 2A Subprojects ..................................... Error! Bookmark not defined.

Table 6: Subprojects Monitored during the Reporting Period (January – June, 2015) ....................... 21

Table 7: Subproject Environmental Performance ................................................................................. 26

Page 6: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

3

I. INTRODUCTION

A. Purpose of the Report

1. ADB Loan 2695-BAN, the City Region Development Project, commenced in July 2011 and the

implementation consultants joined the project in the later part of 2012. Safeguard specialist was

hired directly by the PMCU towards the end of 2012.

2. The ADB Public Communications Policy (PCP 2011) references the Safeguard Policy

Statement (SPS 2009) in respect to information disclosure related to project safeguard

documentation, and states that “ADB shall post on its website *among other+ documents submitted

by the borrower and/or client . . . the safeguard and environmental monitoring reports, upon receipt

by ADB.” (PCP 2011) SPS (2009) contains similar wording in reference to posting of “environmental,

involuntary resettlement, and Indigenous Peoples monitoring reports submitted by

borrowers/clients during project implementation upon receipt” and goes on to specify under

“Monitoring and Reporting” that “the borrower/client will submit at least semiannual monitoring

reports during construction for projects likely to have significant adverse environmental and social

and resettlement impacts, . . .”

3. The present report is the fifth Semi-Annual Safeguard Monitoring Report to be prepared

under the loan. This report compiles environmental monitoring results to comply with the spirit of

ADB policy to “enhance stakeholders’ trust in and ability to engage with ADB, and thereby increase

the development impact *of projects+” in which disclosure of safeguard monitoring is a prominent

aspect.

B. Overall Project Description and Objectives

4. CRDP aims at enhancing growth potential and improving environmental sustainability of the

target city regions using an approach based in regional and urban planning. Under the project, a city

region is defined as an organic agglomeration of a large metropolitan city (City Corporation),

surrounding secondary towns (Pourashavas) and adjacent peri-urban areas (urban centers). The

Project targets city regions centered at Dhaka City Corporation (DCC) and Khulna City Corporation

(KCC). The Project supports the development of key urban infrastructure, focusing on projects that

enhance the urban environment and spur local economic development. The Project also supports

the Government to improve regional and urban planning, and to strengthen municipal management

and capacity for effective and sustainable urban development.

5. The infrastructure investments or subprojects being undertaken under the CRDP will

improve the social environment of the target municipalities. Some of the sub-projects are

concerned with reducing human exposure to pollutants. These include improvement of water

supply and sanitation, drainage and solid waste collection. Other sub-projects target transport and

commercial infrastructure, including improvement of roads and bridges, markets and bus terminals.

A further category is urban improvement using an integrated approach that provides for basic urban

services along with community water supply and sanitation. These latter projects take place in

‘urban centers’, which are small agglomerations of population outside the district centers. Urban

center improvements targeted under Phase 2B (see below) have been expanded under SIDA funding

to cover additional localities.

Page 7: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

4

C. Description of Subprojects

6. Proposed subproject investments are shown in Table 1. As can be seen these cover a range

of improvements under Batch 1, developed during the PPTA, then focus primarily on road and

drainage improvement under Batch 2A developed during the loan implementation phase, followed

by urban renewal projects of a multi-sector nature, which focus on the commercial areas of urban

centers at sub-district (Upazila) level.

Table 1: Subprojects Financed under ADB Loan No. 2695-BAN

Batch 1 (PPTA):

1. Water Supply, Sanitation and Drainage in Gazipur

2. Drainage Improvement and Flood Protection in Khulna City Corporation

3. Urban Services in Ashulia, Savar (including Water Supply, Sanitation, Roads)

4. Integrated Traffic Management at Banani, Dhaka

5. Energy Conservation in Tongi, Gazipur City Corporation

6. Shakhari Bazaar Urban Renewal Subproject (Project on hold pending resolution of issues)

7. Solid Waste Management in Narayanganj (Sites being sought for facilities)

Batch 2A: Road and Drainage Subprojects (Pourashava / City Corporation)

1. Tarabo Paurashava (2 Packages/2 Lots) 2. Sonargaon Paurashava(2 Packages/2 Lots)

3. Narsingdi Paurashava(2 Packages/2 Lots) 4. Kanchon Paurashava(2 Packages/2 Lots)

5. Kaliakoir Paurashava(2 Packages/3 Lots) 6. Singair Paurashava(2 Packages/2 Lots)

7. Tongi area(Gazipur C C) (1 Package/2 Lots) 8. Narayangonj C C(2 Packages/2 Lots)

9. Savar Paurashava(2 Packages/3 Lots) 10. Manikgonj Paurashava(2 Packages/3 Lots)

11. Jessore Paurashava(3 Packages/5 Lots) 12. Jhikargacha Paurashava(2Packages/3 Lots)

12. Mongla port Paurashava(3 Packages/6 Lots) 13. Nowapara Paurashava(2 Packages/2 Lots)

Batch 2B: Urban Center (By District/Urban Center (6/35))

1. Bagerhat: Jatrapur, Foylahat, Joymoni Goal, Garfa, Chitalmari, Fakirhat, Morelgonj, Badhal,

Rayenda (9)

2. Khulna: Fultala Hat, Pather Bazar, Kapilmuni, Dumuria, Khutakhali, Kaya, Gharial, Alaipur,

Katinga (9)

3. Jessore: Khajura, Salua, Bakra, Chinatola, Chingra, Navaron (6)

4. Narayangonj: Uchitpur, Sabdibazar, Fatullah, Murapara, Mograpara (5)

5. Gazipur: Mirzapur, Mouchak, Dolon Bazar, Barmi (4)

6. Dhaka: Subhadya, Kalampur (2)

7. Urban Centres under SIDA funding: Gilabari, Rayenda, Uchitpur, Kutakhali, and Bakrahat.

Page 8: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

5

7. KFW also supports subprojects that are prepared by the Management Design and

Supervision Consultants (MDSC) and implemented through PIUs. The list of projects financed by

KfW is shown in Table 2; these projects are all focused on improving transport infrastructure within

the City of Khulna.

Table 2: Road and Transport Improvements in Khulna Division under KfW Funding

Batch 1

1. Jessore Road., Barabazar to Joragate Area Improvement (Packg W-01)

2. Rehabilitation of Embankment/Riverfront Road (Packg W-02)

3. Access Road Improvement in Poor Areas connected to other components (Packg W-03)

4. Enhancement of road for pedestrians/ public transport on outer bypass road (Packg W-04)

5. Improvement of the Link Rd. 7 (Packg W-05)

6. Bus Terminal Improvement (Packg W-06)

7. Road Safety Measures (Packg W-07)

8. Rupsha River Crossing Area Improvement (Packg W-08)

Batch 2

9. Embankment / River Front Road - Part II (Packg W-09)

10. Rupsha River Crossing Area - Part II (Packg W-10)

D. Environmental Category of Subprojects

8. The CRDP is classified as category B with respect to environment; therefore, subprojects are

considered Category B.

9. Requirements of the Government of Bangladesh are set out in the Environmental

Conservation Act and Rules (1995 and 1997), which classifies subprojects as Green, Orange A and B

and Red Categories. The Department of Environment (DOE) has granted an Environmental

Clearance Certificate to the CRDP that applies to all subprojects with the exception of those in the

Red Category (water treatment plants and distribution line laying/relaying/extensions, landfills, and

bus and truck terminals), by means of a letter No. DoE/Clearance/5194/2013/180 dated 21/07/2013.

Under DOE rules, EIAs are required for water supply and sanitation projects (“Water, power and gas

distribution line laying/relaying/extension” – DOE, ECR Schedule 1). A consolidated EIA report

covering the water supply and sanitation subprojects proposed for Gazipur and Ashulia was

prepared according to an approved terms of reference, and was approved by DOE shortly after the

end of the reporting period (DOE Clearance 5194/2013/07, letter dated 9 Jan 2014).

E. Personnel Responsible for Environmental Monitoring

10. Monitoring of mitigation measures during construction are the responsibility of the PIU

Environmental Management Officer, supported by the PMCU Environmental Specialists. The

monitoring system involves a Monitoring Checklist, which reflects the requirements of the EMP and

Special Conditions. The checklist is filled in quarterly by the PIU and PMCU Environmental

Specialists.

Page 9: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

6

F. Overall Project and Subproject Progress and Status

11. The overall project and subproject progress and status is presented in table 03 below.

Table 3: Subproject progress and Status (As of July – December 2015)

No. Sub-Project Name

Status of Sub-Project List of Works/ Programme

Progress of Works(% complete)

Design Pre-Construction

Construction Operational Phase

1 Batch 1 (PPTA)

Gazipur: Water Supply Sanitation and

Drainage

Complete

Complete

In Progress

Yet to start

Water Supply (3 packages and 3 lots) Drainage (9 lots under 2 packages)

W-03: 52.98%; W-04: 85.23%; & W-05: 15.00% Overall progress- Water Supply & Sanitation: 76.34% Drainage works: overall progress W-02: 94.07%

2 Khulna Drainage Improvement and Flood Protection

Complete Complete In Progress

Yet to start 17 lots under 10 packages

Packages 1 to 8 complete 100% Overall progress of 10 pkg/17 lots 87.54%

3 Urban Services in Ashulia, Savar

Complete Complete In Progress

Yet to start Roads & drainage (2 packages);

Water Supply (1 package)

W-01: 100%; W-02: 66.78%,

WS: Tendered (shall be implemented by DPHE)

4 Integrated Traffic Management at Banani, Dhaka

Complete In progress In Progress

Yet to start Roads & drainage (1 packages)

W-01: 21.21%

5 Energy Conservation in Tongi, Gazipur

Complete Complete In Progress

Started 2 packages G-01: 100%; G-02: 100% (Handed over)

6 Shakhari Bazaar Urban Renewal Subproject

Not feasible (time is the constraint)

N/A N/A N/A N/A N/A

7 Solid Waste Management in Narayanganj

Design not applicable

N/A N/A N/A N/A Not Feasible (land not available)

8 Solid Waste Management in Jessore (Jhum Jhumpur)

Design complete-(awaiting approval)

Yet to start Yet to start Yet to start Land-fi l l ing, composting

Yet to start

Page 10: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

7

No. Sub-Project Name

Status of Sub-Project List of Works/ Programme

Progress of Works(% complete)

Design Pre-Construction

Construction Operational Phase

Batch 2A:

29 Packages / subprojects (39 Lots / Contracts)

Complete

Various stages of completion

Work in progress

Yet to start

Road and drainage works in urban/ex-urban areas

Work in progress; overall progresses for pourashavas are as follows: a) Manikganj: 2 Packages-81.2% (W-01+02) b) Mongla Port: 3 Packages-67.9% (W-01+02+03) c) Jessore: 3 Packages-62.5% (W-01+02+03) d) Sonargaon: 2 Packages- ( W-01: 90.98% W-02: 11.39% ) e)NarayanganjCC: 2 Packages- (W-01: 55.8% W-02: 5.48%) f) Tarabo: 2 Packages- ( W-01: 91.7% W-02: 32.1%) g) Jhikorgacha: 2 Packages-87.1% (W-01+02) g) Narasingdi: 2 Packages- ( W-01: 33.5% W-02: 26.9%) h) Kaliakoir: 2 Packages-64.7% (W-01+ 02) i) Kanchon: 2 Packages- ( W-01: 81.55% W-02: 6.03) j) Singair: 2 Packages- 82.00%( W-01) 49.85%( W-02) k) Nowapara : 2 Packages- 73.60%( W-01) 11.31%(W-02) l) Savar: 2 Packages- 39.84%( W-01) 45.1%( W-02/Lot 1) 22.5%( W-02/Lot 2) m) Tongi (Gazipur City Corporation): 1 Package- 2 Lots Overall progress-30.69% (Lots-1+2)

Page 11: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

8

No. Sub-Project Name

Status of Sub-Project List of Works/ Programme

Progress of Works(% complete)

Design Pre-Construction

Construction Operational Phase

Batch 2B: Concept designs complete; detai led design in progress

Yet to start Yet to start Yet to start Small scale water supply, drainage, road and market improvements

Bid documents of 2 urban centres ( Gazipur/UC/W-01 + Gazipur/UC/W-02) have been prepared and submitted to ADB for concurrence

KfW-financed Transport-related Urban Infrastructure Improvement Projects in Khulna

10 subprojects (under 10 Packages)

Batch 1 Packg W-01- W-08

Batch 2 W-09 & W-10

In Progress

In Progress

Work in progress

Yet to start Selected transport improvements (link/feeder roads, pedestrian safety, public access

Work in progress; overall progresses for the packages are as follows:

Batch 1 W-01 to W-08 85.55% ( W-01) 100.0% ( W-02) 58.00% ( W-03) 60.00% ( W-04) 80.53% ( W-05) 10.78% (W-06 ) Bid under review ( W-07) & 12.80% (W-08)

Batch 2 W-09 & W-10 Obtained KfW’s concurrence on submitted Bid Document and tender has been floated.

Page 12: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

9

II. COMPLIANCE STATUS WITH NATIONAL STATUTORY REQUIREMENTS

12. The DOE-issued Environmental Clearance Certificate referred to in Sec. I.D covered all

subprojects with the exception of Red Category subprojects, and attached no special conditions

therewith. A combined EIA has been submitted by the PMCU and approved by DOE for the Gazipur

and Ashulia Water Supply and Sanitation Subprojects, the only two red category subprojects thus far

to reach bidding stage.

13. All requirements of the Department of Environment related to environmental clearance are

being met and DOE does not require monitoring and reporting for CRDP subprojects. There is no

other regulation of the Government of Bangladesh related to environmental management applicable

to CRDP.

Page 13: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

10

III. COMPLIANCE STATUS WITH ENVIRONMENTAL LOAN COVENANTS

14. The covenants to the loan agreement with ADB, to which KfW and SIDA are parties, requires

that “subprojects are designed, constructed, operated, and maintained in accordance with

Borrower’s Environmental Conservation Rule 1997, ADB’s Safeguard Policy Statements (2009) and

EARF prepared for the Project and agreed between the Borrower and ADB and KfW.” Other

covenants written into the loan agreement related to disclosure, grievance redress and

environmental safeguards are listed in Table 4. The status of compliance is described in the table.

Page 14: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

11

Table 4: Status of Environment and Related Loan Covenants as of 30 June 2015

Covenant Safeguard Applicability Status of Compliance

Implementation Arrangements: The Borrower, LGED, and the IAs shall

ensure that the Project is implemented in accordance with the detailed

arrangements set forth in the PAM. Any subsequent change to the PAM

shall become effective only after approval of such change by the Borrower

and ADB. In the event of discrepancy between the PAM and the Loan

Agreement, the provisions of this Loan Agreement shall prevail.

Section VII of the PAM, paras. 33

thru 42, address safeguard

requirements under the loan.

Complied with.

Subproject Selection Criteria: LGED shall ensure that all subprojects are

selected and implemented in accordance with the subproject selection

criteria prepared for the Project and agreed between ADB, KfW and the

Borrower and set out in Appendix A to the ADB Project Administration

Manual (PAM).

Some aspects of the selection

criteria are directly related to

environmental and resettlement

safeguards.

Complied with.

Project Website: Within 12 months after the Effective Date, LGED shall

create a Project website to disclose information about various matters on

the Project, including procurement. With regard to procurement, the

website shall include information on the list of participating bidders, name of

the winning bidder, basic details on bidding procedures adopted amount of

contract awarded, and the list of goods/services procured.

Subproject safeguard

documentation may be posted on

the website.

Complied with.

Grievance Redress Mechanism: Within 12 months after the Effective

Date, LGED shall prepare a Grievance Redress Mechanism, acceptable to

ADB, and KfW and establish a special committee to receive and resolve

complaints/grievances or act upon reports from stakeholders on misuse of

funds and other irregularities, including grievances due to resettlement. The

special committee shall (i) make public of the existence of this Grievance

Redress Mechanism, (ii) review and address grievances of stakeholders of

the Project, in relation to either the Project, any of the service providers, or

any person responsible for carrying out any aspect of the Project; and (iii)

proactively and constructively responding to them.

The GRM provides redress for

grievance arising from resettlement,

compensation and environmental

impact during subproject

implementation.

Grievance Redress Committees have

been formed in local governments

where subprojects are under

construction. Other aspects of the GRM

are being progressively complied with.

Environment: The Borrower, LGED and the IAs shall ensure that:

a. the Subprojects are designed, constructed, operated, and maintained in accordance with Borrower’s environmental Conservation Rule 1997, ADB’s Safeguard Policy Statements (2009) and EARF prepared for the

Directly applicable; approach for

meeting review requirements under

Complied with.

Page 15: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

12

Covenant Safeguard Applicability Status of Compliance

Project and agreed between the Borrower and ADB and KfW; ECR (1997) in development.

b. the EMP and the mitigation measures included therein, as specified in the IEEs, are properly implemented;

Mitigation measures guarantee

performance and provide basis for

monitoring

Progressively complied with

c. the mitigation measures set out in the EMP are incorporated into the bidding documents and Works contracts, and are updated, if necessary, in course of Project implementation with prior clearance from ADB and KfW;

Bid documents provide basis for

contractor performance.

Complied with.

d. all environmental permits, licenses and clearances are obtained in a timely manner prior to commencement of Works in the relevant section of the Project roads;

Required by the EARF. Complied with.

e. any adverse impact on the environment that may arise from the Project implementation is promptly mitigated or minimized in accordance with the EMPs;

Fundamental purpose of

environmental review.

Progressively complied with. See the

monitoring results included in this

report.

f. implementation of the EMPs, including any safety breaches, violation of environmental standards, and corrective measures taken in respect thereof are reported semi-annually to ADB; and

Fundamental purpose of

environmental reporting.

Complied with.

g. implementation of the EMPs, including any safety breaches, violation of environmental standards, and corrective measures taken in respect thereof are reported, in the Project Management and Coordination Unit’s (PMCU) quarterly report to ADB and KfW;

Fundamental purpose of

environmental reporting.

Complied with.

h. reports and information are provided to ADB and KfW on request to enable it to verify that the Goods, Works, and consulting services financed out of the proceeds of the Loan, have been produced in a responsible manner with a view to resource efficiency, waste minimization, and other environmental considerations.

Aim of transparency in project

implementation.

Will be done as and when necessary.

Page 16: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

13

IV. APPROACH FOR SAFEGUARD MANAGEMENT AND MONITORING

A. Environmental Safeguard Framework

15. The Environmental Assessment and Review Framework (EARF) was prepared during the

PPTA, which establishes the basis for environmental review for the CRDP. The EARF also sets out the

organizational structure for environmental management within the Project Management and

Coordination Unit (PMCU), the Management, Design and Supervision Consultant (MDSC), and the

Project Implementation Units (PIUs). Specialist staff to be hired for supporting environmental

management functions of the PMCU is set out in the EARF. Under the PPTA, Draft Environmental

Management Plans (EMPs) were prepared for sample subprojects as part of the IEE reports. EMPs

and supporting criteria inclusive of environmental specifications for inclusion in construction

contract tender documents provide the basis for monitoring compliance with the EARF.

16. IEEs for the original subprojects proposed under the PPTA have been approved by ADB,

including the IEEs for Gazipur and Ashulia Water Supply and Sanitation, Gazipur Drainage, Ashulia

Road and Drainage, and Banani Integrated Traffic Management (final approval still pending). An IEE

was prepared and submitted to ADB for the Khulna Drainage and Flood Protection subproject.

These IEEs have been posted on the ADB and LGED websites. Environmental review for the

remaining Batch 1 subprojects were either addressed through a due diligence report, for which no

update is needed (Tongi Energy Conservation), or are being reassessed due to changes in scope

(Shakhari Bazaar Urban Renewal Subproject) or location of facilities (Narayangonj Solid Waste

Management-alternate site being identified).

17. Initial Environmental Examination (IEE) of sub-projects has to be prepared and concurrence

on the IEEs of the development partners has to be obtained. Status of IEEs up to December 2015 is

shown in Table 5.

Table 5: Status of IEEs for Subprojects of different batches

Sl.

No.

Name of City Corporation / Pourashava with

Components

Status of IEEs as

of December 31,

2015

Remarks

Batch 1 Sub-projects:

Under ADB Financing:

1. Dhaka North City Corporation: Integrated Traffic

Management in Banani, Dhaka

Completed Sent to ADB

2. Gazipur City Corporation: Water Supply and

Sanitation Component of the Water Supply,

Sanitation and Drainage in Gazipur Sub-project

Completed Approved by ADB

and EIA approved

by DoE

3. Gazipur City Corporation: Drainage Improvement

Component of the Water Supply, Sanitation and

Completed Approved by ADB

Page 17: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

14

Sl.

No.

Name of City Corporation / Pourashava with

Components

Status of IEEs as

of December 31,

2015

Remarks

Drainage in Gazipur Sub-project

4. Ashulia Urban Center: Water Supply and

Sanitation Component

Completed Approved by ADB

and EIA approved

by DoE

5. Ashulia Urban Center: Road and Drainage

Improvement Component

Completed Approved by ADB

6. Khulna City Corporation: Khulna Drainage

Improvement and Flood Protection Sub-project

Completed Approved by ADB

7. Solid Waste Management in Narayanganj Sub-

project

Preliminary study is

in process.

8. Urban Renewal in Shakhari Bazar, Old Dhaka Sub-

project

Could not be

undertaken as

found not feasible.

9. Energy Conservation in Tongi Sub-project IEE not applicable

Under KfW Financing:

Khulna City Corporation: Urban Transport

Improvement Sub-project funded by KfW

Completed for 4

Sub-projects.

Batch 2A Sub-projects:

Under ADB Financing:

1. Manikganj Pourashava: Road and Drainage Sub-

project

Completed Approved by ADB

2. Mongla Port Pourashava: Road and Drainage Sub-

project

Completed Approved by ADB

3. Narayanganj City Corporation: Drainage Sub-

project

Completed Sent to ADB

4. Narsingdi Pourashava: Road and Drainage Sub-

project

Completed Sent to ADB

5. Singair Pourashava: Road and Drainage Sub-

project

Completed Sent to ADB

Page 18: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

15

Sl.

No.

Name of City Corporation / Pourashava with

Components

Status of IEEs as

of December 31,

2015

Remarks

6. Sonargaon Pourashava: Road and Drainage Sub-

project

Completed Sent to ADB

7. Kaliakoir Pourashava: Road and Drainage Sub-

project

1 package

Completed;

Another

1 package /

2 lots to be

completed

Sent to ADB

8. Tarabo Pourashava: Road and Drainage Sub-

project

Completed Sent to ADB

9. Kanchan Pourashava: Road and Drainage Sub-

project

1 package

Completed;

Another

1 package /

1 lot to be

completed

Sent to ADB

10. Jessore Pourashava: Road and Drainage Sub-

project

Completed Sent to ADB

11. Jhikorgacha Pourashava: Road and Drainage Sub-

project

1 package

Completed;

Another

1 package /

2 lots to be

completed

Sent to ADB

12. Nowapara Pourashava: Road and Drainage Sub-

project

Completed Sent to ADB

13. Savar Pourashava: Road and Drainage Sub-project Completed Sent to ADB

14. Gazipur City Corporation Tongi Area: Road and

Drainage Sub-project

Completed Sent to ADB

Batch 2B Sub-projects:

Under ADB Financing:

1. Strengthening economic potential of four urban

centres (Mouchak & Mirzapur – W-01, Dolon &

Barmi – W-02) in Gazipur district

Completed Sent to ADB

Page 19: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

16

Sl.

No.

Name of City Corporation / Pourashava with

Components

Status of IEEs as

of December 31,

2015

Remarks

2. Strengthening economic potential of seven urban

centres (Fakirhat, Chitalmari & Garfa - W-01 &

Foylahat, Jatrapur, Joymonir Goal & Badhal – W-

02) in Bagerhat district

Completed Sent to ADB

3. Strengthening economic potential of seven urban

centres (Fultola, Pather Bazar, Katinga & Alapur -

W-01 & Koyerhat, Dumuria & Kapilmuni - W-02) in

Khulna district

Completed Sent to ADB

4. Strengthening economic potential of five urban

centres (Navaran, Khajura, Salua, Chintola &

Chingra - W-01) in Jessore district

Completed Sent to ADB

5. Strengthening economic potential of four urban

centres (Sabdi, Murapara & Mograpara - W-01 &

Fatullah - W-02) in Narayanganj district

Completed Sent to ADB

6.. Strengthening economic potential of one urban

centre (Kalampur UC – W-01) in Dhaka district

Completed Sent to ADB

B. Environmental Performance Indicators 18. Environmental monitoring occurs at the subproject level by observing performance during

the construction phase. Environmental specifications reflect general construction requirements

identified in the subproject environmental management plans (EMPs). A provisional sum to cover

environmental mitigation is included in the bid price where needed; though costs for implementing

the general requirements of the environmental specification are considered the responsibility of the

contractor and are part of the overall bid price.

C. Subproject Environmental Monitoring 19. The system for environmental monitoring consists of observations using a checklist for

comparison with contractor performance that reflects the requirements of the construction

specifications. The standard CRDP checklist is shown in Appendix 1. Performance is expressed as a

percent of requirements being met by the contractor. The checklist allows for omitting any

requirements not seen as applicable to the specific works, while any special requirements set out in

the subproject EMP are also monitored. Performance tracking is used in a manner that provides

consistent semi-annual reporting, with the objective of improving performance of contractors. The

environmental specialist conduct field visits during the reporting period, complete the checklist for

active subproject contracts, and discusses the results with the site supervisor. As a part of the

monitoring program, field visits undertaken in the recent months are summarized here below:

Visit of Savar and Singair Pourashavas in November 2015:

Page 20: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

17

A team headed by the Project Director, CRDP, visited different sites under Savar and Singair

Pourashava on November 11, 2015. The members of the team were: Project Director, CRDP, DPD,

CRDP, representative of ADB, Team Leader of MDSC, Project Management Specialist and others. The

team visited the following sites:

Savar Pourashava:

1. Improvement of road side drain from Savar Thana Bus Stand to Nama Bazar via Savar Model

Thana (Ch: 0- 1200m and 0-1200m,) under Package- W-2, Lot -2

2. Improvement to road from Radio Colony Bus Stand to Savar Nama Bazar (CARE Bridge) Ch:

0-2790m under Package No – W-2. Lot-1

3. Improvement of roadside drain from Pakija Textile Mill to Shahibag chowrasta (Ch: 0-1165m,

Link-1 0- 360m, L-2 0-100m)

Singair Pourashava:

4. Improvement of road from Azimpur mosque to river ghat via Glora more (Ch. 0- 3365m)

under Package No. W-01

5. Improvement of road from Ghona Para more to Singair- Manikgonj road via Hospital (Ch. 0-

2016m) under package No. W-01

6. Improvement of road from Habibur Munshi house to Muslem house (Ch. 0- 2350m) under

Package No. W-02

Based on field visits of subprojects, the Loan Review Mission (10 to 18 November 2015) has

observed, “Overall the mission was satisfied with the quality of construction works of the visited

subprojects.”

Visit of Savar Thana Road in December 2016

Mr. Md. Hamidul Hoque, Deputy Project Director (DPD) of the Project, visited Savar in December

2015 to see the progress of work of Savar Thana road. The road was found to be a busy one;

expediting the improvement work of the road was found to be an imperative. The DPD urged the

contractor to expedite the work and to plan judicious and synchronized mobilization of his work

force so as to optimize time for completion of the work. The DPD underlined that such modus

operandi would reduce suffering of people due to construction activities and save time facilitating

faster completion of the work.

Page 21: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

18

D. Capacity Building

20. Capacity building is aimed at orientation and training of PIU staff in ADB’s safeguards policy

and management. Training is conducted by the Environment Specialists (international and national)

and covers integration of environmental considerations into project implementation and procedures

for monitoring and reporting.

A follow-up training on safeguard issues and monitoring using the standard checklist was undertaken

in Dhaka office for the Municipal Engineers of the project responsible for Singair, Manikganj and

Savar Pourashavas. Training Handouts and necessary Training Documents were distributed to the

participants. This training helps in increasing ability of the participants to improve quality control and

safeguard activities in construction works.

Another a 1-day training on quality control, safeguard and gender activities was conducted on

December 14, 2015 at Narayanganj City Corporation Training Hall with participation of Narayanganj

City Corporation Technical and Non-technical staff members, MDSC Junior Engineers and Contractor

and his Site Engineers/Project Managers.

Very recently, a routine in-house training was organized for few Municipal Engineers of CRDP to

enhance their capacity to undertake the environmental impact monitoring work in an efficient

manner.

Environmental and social issues discussed in training programme

The orientation–cum-training programme conducted for pourashavas covered the following:

Discussed the uniqueness of the CRDP project that has new construction as well as

rehabilitation works belonging to various sectors viz. transport, water supply, drain, street

lighting and city beautification, etc.

Explained the need of safeguard documents and implementation of safeguard measures in the

project in light of the loan covenants, GOB and ADB requirements...

Discussed the safeguard issues related with various stages of the project and also presented

some case study related to the CRDP to explain the relationship of safeguard issues and project

cycles.

Discussed the various social issues in the participating Pourashavas observed/reported by

safeguard team during implementation of the various Sub-projects. Mitigation measures

suggested and implemented in various city corporation/Pourashavas was also discussed.

Specific issues of safeguard measures discussed included issues of the Design Stage and

Construction stage.

Consideration of Climate Change Effects in CRDP

A rapid assessment for the climate change effects in terms of a) Climate Adaptation Assessment (climate proofing) and b) Climate change reduction assessment (Emission Saving) from projects are being addressed in the planning and design of the sub-project interventions and the construction materials used therein are expected to make any substantial contribution to Greenhouse Gas Emissions, rather the measures present the possibility of adaptation of the target groups or eco-systems.

Page 22: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

19

V. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN

A. Status of Recruitment

21. International and national environmental safeguard specialists were engaged in the project

over the period on intermittent basis.

B. Subproject Environmental Safeguard Performance

22. Environmental safeguard activities over the reporting period include the following:

Batch 1 subproject IEEs are complete as described previously; the IEE for the Integrated

Traffic Management at Banani Subproject was revised based on ADB comments, with final

approval pending; IEEs for both Narayanganj Solid Waste Management and Shakari Bazaar

Urban Renewal await final decisions regarding siting and scope, respectively.

Monitoring commenced for Batch 1 subprojects inclusive of Gazipur Water Supply,

Sanitation and Drainage, Ashulia Urban Services, and Khulna Drainage Improvement

Projects.

IEEs were prepared for Batch 2A subprojects as described previously and monitoring

undertaken for subprojects in progress.

IEEs have been prepared for Batch 2B subprojects under ADB financing

Field trips to municipalities, pourashavas and urban centers were undertaken during the

reporting period for monitoring and to provide guidance to contractors.

IEEs for three of the KfW-funded transport improvement subprojects in Khulna are complete

and have been submitted to KfW. Preparation of IEEs of another two Kfw-funded

subprojects is progressing and will be submitted soon.

The EMPs and Environmental Specifications are being included in contract bid documents

and engagement contracts.

The CRDP monitoring system is being used in the field and contractors are responding with

improved performance of mitigation measures.

Three training sessions were conducted for PIU and contractor staff.

A follow-up training on safeguard issues and monitoring using the standard checklist was

undertaken in Dhaka office for Singair, Manikganj and Savar Pourashavas

The Grievance Redress Mechanism (GRM) is in use. Grievance committees have been

formed by local government units where there are active subprojects.

C. Summary Lists

23. Table 6 lists subproject lots (contracts) in progress during the current reporting period.

There are a total of 76 lots. Table 7 shows contractor performance against major indicators. There

are six indicators that are used to compile performance results for monitoring variables found in

Appendix 1 based on observations during site visits. Values ranging from 0 (non-compliant) to 4

(best performance) are assigned and later averaged for the performance indicator. Indicators

include: design and preparation (preconstruction and construction start-up requirements, for which

there are 13 monitoring variables); worker provisions (7 monitoring variables), gender equity (3) and

community based monitoring (public consultation and disclosure—2 variables); community values

and safety (13); hydrology/water pollution (5); and project completion (7 variables).

Page 23: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

20

24. Overall performance of the works of all the contracts under Gazipur City Corporation (GCC)

and Manikganj Pourashava appears to be in the range of fair to good, and most of the indicators of

these contracts have recorded fair to good scores. As regard project completion performance, 15

contracts for drainage improvement and flood protection in Khulna city have been complete with

score of 100% in the project completion indicator. However, it is worth mentioning that in all

contracts of the pourashavas under CRDP most of the performance indicator result fare to good

score. Noticeable improvement pertinent to environmental management and performance has

been noted in almost all the contracts. Environmental training and meetings in the reporting period

could be the reason. It is to be noted that contracted labors are mostly from rural areas; they have

hardly any idea of environmental management, especially issues of health and work safety. In this

context, contractors need to provide their workforce environmental awareness training in order to

avert occupational health risk and accident.

Page 24: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

21

Table 6: Subprojects Monitored during the Reporting Period

(July-December, 2015)

Package No. Lot No. Contract date Contractor Time for completion Physical Progres

s (%)

BATCH 1

Gazipur City Corporation

A. Drainage

CRDP/LGED/GCC/GAZIPUR/NCB/2012

/W-01

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-01

08-07-13 Popular-M.A. Engineering-

Khandokar (JV)

20-08-2014 66.78

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-02

31/07/13 A.S.Construction 13-08-2014 100.00

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012 /DW-03

08-12-13 Pearl Engineering & Construction

25-08-2014 100.00

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-04

08-05-13 MDJ Associates 19-08-2014 100.00

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-05

08-05-13 MDJ Associates 19-08-2015 100.00

CRDP/LGED/GCC/GAZIPUR/NCB/ 2012/W-02

CRDP/LGED/GCC/GAZI-PUR/NCB/2012/ DW-

06 10-01-13

Q.H.Masood & Co.

14-10-2014 100.00

CRDP/LGED/GCC/GAZIPUR/NCB/ 2012/ DW-

07 10-01-13

Q.H.Masood & Co.

14-10-2014 100.00

CRDP/LGED/GCC/GAZIPUR/NCB/ 2012/ DW-08 10-10-13 MDJ Associates 23-10-2014

100.00

CRDP/LGED/GCC/GAZIPUR /NCB/2012/ DW-

09 10-08-13 BI.BB.PB (JV) 21-10-2014

100.00

B. Gazipur CC: Water Supply and Sanitation

CRDP/LGED/GCC/NCB/ 2013/W-03

27/11/2013 M/S Molla Enterprise

09-12-2014

59.99

CRDP/LGED/GCC/ICB/ 2013/W-04

22-01-2014 Purbachal & Associates

05-02-2015 And extension up to

31-12-2015

90.72

CRDP/LGED/GCC/ICB/ 2013/W-05

14-08-2014 BI.BB.PB (JV)

05-02-2015 And extension up to

31-12-2015 30.00

Drainage Improvement and Flood Protection in Khulna City Region

CRDP/LGED/KLN/NCB/2012 /W-01

CRDP/LGED/KLN/NCB/ 2012 /DW-01 28-05-2013

Alliance International

11-06-2014 100

CRDP/LGED/KLN/NCB/2012 /W-02

CRDP/LGED/KLN/NCB/ 2012/DW-02 28-05-2013

F.T & R.E (JV)

11-06-2014

100

CRDP/LGED/KLN/NCB/2012/W-03

CRDP/LGED/KLN/NCB/ 2012/DW-03 28-05-2013 Raka Enterprise 11-06-2014

100

Page 25: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

22

Package No. Lot No. Contract date Contractor Time for completion Physical Progres

s (%)

CRDP/LGED/KLN/NCB/2012 /W-04

CRDP/LGED/KLN/NCB/ 2012/DW-04 28-05-2013 Md. Farid Uddin 11-06-2014

100

CRDP/LGED/KLN/NCB/ 2012/W-05

CRDP/LGED/KLN/NCB/ 2012/DW-05 28-05-2013 M/S F.T & P.T (JV) 11-06-2014

100

CRDP/LGED/KLN/NCB/ 2012/W-06

CRDP/LGED/KCC/ NCB/ 2013/W-06/

DW-06 20-11-2013 BC-TAE-ME(JV) 03-12-2014

100.00

CRDP/LGED/KCC/ NCB/ 2013/W-06/

DW-07 11-11-2013 BC-TAE-ME(JV) 24-11-2014

100.00

CRDP/LGED/KCC/ NCB/ 2013/W-06/

DW-08 11-11-2013 BC-TAE-ME(JV) 24-11-2014

100.00

CRDP/LGED/KCC/NCB/2013/W-07

CRDP/LGED/KCC/ NCB/2013/W-07/

DW-09 11-11-2013 RBL-MBI (JV) 30-11-2014 100.00

CRDP/LGED/KCC/ NCB/2013/W-07/

DW-10 11-11-2013 RBL-MBI (JV) 30-11-2014

100.00

CRDP/LGED/KCC/ NCB/2013/W-07/

DW-11 11-11-2013 RBL-MBI (JV) 30-11-2014

100.00

CRDP/LGED/KCC/ NCB/2013/W-07/

DW-12 19-11-2013

M/S Marina Construction

02-12-2014 100.00

CRDP/LGED/KCC/ NCB/2013/W-07/

DW-13 11-11-2013

Mahabub Brothers Pvt. Ltd

25-11-2014 100.00

CRDP/LGED/KLN/NCB/ 2012/W-08

CRDP/LGED/KCC/ NCB/ 2013/W-08/

DW-14 19-12-2013 Jamil Iqbal JV 02-01-2015

100.00

CRDP/LGED/KCC/ NCB/ 2013/W-08/

DW-15 19-12-2013 Jamil Iqbal JV 02-01-2015

100.00

Strengthening Economic Potential of Urban Center in Ashilia, Savar, Dhaka.

CRDP/LGED/DHK/ ICB/2013/

W-01

16/07/13

Mir Akhtar Hossain Ltd.

15-07-2014 100.00

CRDP/LGED/ DHK/ NCB/2013/

W-02

26/09/2013

Project Builders Ltd. (PBL)

16-09-2014 And extension up to

31-12-2015 56.49

CRDP/LGED/ DHK/ NCB/2013/

WS-01

18-11-2015

Meghna Structural

Engineering Ltd. 18-11-2016

1.00

Dhaka North City Corporation

CRDP/LGED/DNCCI/ ICB/ 2014/ W-01

(Banani)

04-03-2015 MBEL-UDC JV 17-04-2016 29.33

BATCH 2A

Manikganj Pourashava

CRDP/LGED/Manikganj/NCB/2013/

20-02-2014 Spectra Engineers

Ltd. 06-02-2015

And extension up to 82.00

Page 26: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

23

Package No. Lot No. Contract date Contractor Time for completion Physical Progres

s (%)

W-01/RD-01 31-12-2015

CRDP/LGED/Manikganj/NCB/2013/

W-01/RD-02 20-02-2014

Spectra Engineers Ltd.

06-02-2015 And extension up to

31-12-2015 92.91

CRDP/LGED/Manikganj/NCB/2014/

W-02 24-11-2014 SECL-APEX JV 23-11-2015

72.89

Mongla Port Pourashava

CRDP/LGED/Mongla/NCB/2013/ W-01/RD-01

14/5/2014 Mahabub

Brothers (Pvt.) Ltd.

28-05-2015 And extension up to

20-01-2016 99.65

CRDP/LGED/Mongla/NCB/2013/ W-01/RD-02

14/5/2014 Mahabub

Brothers (Pvt.) Ltd.

28-05-2015 And extension up to

18-02-2016 97.94

CRDP/LGED/Mongla/NCB/2013/

W-02 21-06-2014 SECL & MBPL JV 16-06-2016

92.52

CRDP/LGED/ Mongla/NCB/2014

/W-03

Lot-1 15/1/2015

M/S Ataur Rahman Khan

12-01-16 30.82

Lot-2 01-11-15 JE, BBE & AE (JV) 18-01-16

61.95

Lot-3 01-11-15 M/S JI & ZT (JV) 17-01-16

48.59

Narayanganj City Corporation

CRDP/LGED/ NCC/ICB/ 2014/W-

01

25-11-2014 Khan and Sons

(Bangladesh) Ltd. 24-11-2015

57.41

CRDP/LGED/ NCC/ICB/ 2014/W-

02

04-08-2015 M/S Ratna Enterprise

03-08-2016

8.34

Narsingdi Pourashava

CRDP/LGED/ NARSINGDI/ NCB/

2014/ W-01

22-12-14

JI - (JV)

21-12-15 And extension up to

30-04-2016

36.87

CRDP/LGED/

NARSINGDI/ NCB/

2014/ W-02

19-05-15

M/S JK Enterprise

18-05-16

34.00

Jessore Pourashava

CRDP/LGED/ Jessore/ NCB/ 2014/ W-01

18-06-2014 Md. Noor Hossain JV

02-07-2015 100.00

CRDP/LGED/Jessore/NCB/2014/W-02

Lot-1 15-01-15

M/S Kapotakkhi Enterprise

14-01-16 65.03

Lot-2 15-01-15

M/S Shahid Brothers

14-01-16 70.13

Lot-3 15-01-15 KE-MSC (JV) 14-01-16 60.42

Page 27: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

24

Package No. Lot No. Contract date Contractor Time for completion Physical Progres

s (%)

CRDP/LGED/Jessore/NCB/2014/W-03

04-07-2015 NH-SZ (JV) 03-07-2016 40.34

Sonargaon Pourashava

CRDP/LGED/ Sonargaon/ NCB/

2014/ W-01

24-06-2014 M/S Ratna Enterprise

08-07-2015 98.55

CRDP/LGED/ Sonargaon/ NCB/

2014/ W-02

10-05-2015 M/S Ratna Enterprise

14-05-2016 13.87

Tarabo Pourashava

CRDP/LGED/ Tarabo/ NCB/ 2014/ W-01

31-07-2014 M/S MRC-HC JV 14-08-2015 93.02

CRDP/LGED/ Tarabo/ NCB/ 2014/ W-02

01-07-2015 M/S. Raka

Enterprise JV 07-07-2016 30.07

Jhikorgacha Pourashava

CRDP/LGED/Jhikorgacha/ NCB/ 2014/

W-01

08-03-14 Md. Noor Hossain JV

17-08-2015 And Extension up to 30-

12-2015 94.57

CRDP/LGED/Jhikorgacha/ NCB/ 2014/

W-02

Lot-1 15-01-15 Md. Noor Hossain JV

27-01-16 95.07

Lot-2 15-01-15 Md. Noor Hossain JV

27-01-16 83.37

Nowapara Pourashava

CRDP/LGED/ Nowapara/ NCB/

2014/ W-01

11-02-2014 SS Joint Venture 01-11-15 61.02

CRDP/LGED/ Nowapara/ NCB/

2014/ W-02

05-03-2015 M'S Sunflower &

DL (JV) 19-03-2016 13.31

Kaliakoir Pourashava

CRDP/LGED/ Kaliakoir/ NCB/

2014/ W-01 09-08-14 BI-BB JV

07-09-15 And Extension up to 31-

12-2015 81.00

CRDP/LGED/Kaliakoir/NCB/ 2014/

W-02

Lot-1

24-12-14 TI - MHA JV 29-11-15 And

Extension up to 30-04-2016

54.00

Lot-2 01-07-15 NT - KT JV

20-01-1615 And Extension up to 30-

04-2016 60.00

Kanchon Pourashava

CRDP/LGED/ Kanchon/ NCB/

2014/ W-01

20-08-14 Khan & Sons

(Bangladesh) Ltd.

03-09-1515 And Extension up to 31-

01-2016 83.04

CRDP/LGED/ Kanchon/ NCB/

2014/ W-02

30-12-14 Khan & Sons

(Bangladesh) Ltd. 12-01-16 6.19

Page 28: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

25

Package No. Lot No. Contract date Contractor Time for completion Physical Progres

s (%)

Singair Pourashava

CRDP/LGED/ Singair/ NCB/ 2014/ W-01

24-08-2014 Farid Uddin - ATC

(JV)

24-08-15 And Extension up to 31-

12-2015 82.00

CRDP/LGED/

Singair/ NCB/

2014/ W-01

18-05-15 TISB(JV) 24-05-16 49.85

Savar Pourashava

CRDP/LGED/ Savar/NCB/2014/

W-01 26-02-15

M/S. Md. Jamil Iqbal

09-03-16 51.10

CRDP/LGED/

Savar/NCB/2014/

W-01

Lot-1 22-03-15 TISB(JV) 09-03-16 55.19

Lot-1 29-03-15 M/S Jemin

Corporation 26-02-16 30.14

GCC (Tongi Area)

CRDP/LGED/GCC/TONGI/ NCB/2014/

W-06

Lot-1 24-Dec-14

Khan & Sons BD, Ltd.

24-12-15 And Extension up to 30-

04-2016 42.38

Lot-2 1-Jan-15 BI.BB(JV)

01-01-16 And Extension up to 30-

04-2016 15.00

Khulna City Region: KfW Part

CRDP/LGED/KCC/KfW/ NCB/2013/W-

01

13-11-14 TE-ME JV

12-11-2015 And Extension up to 28-

02-2016 90.26

CRDP/LGED/KCC/KfW/ NCB/2013/W-

02

05-08-14 JI-KE JV

22-05-2015 And Extension up to 31-

12-2015 100.00

CRDP/LGED/KCC/KfW/ ICB/2013/W-

03

22-06-2014

Mahabub Brothers (Pvt.)

Ltd.

06-07-2015 And Extension up to 28-

02-2016 62.00

CRDP/LGED/KCC/KfW/ ICB/2014/W-

04

15-09-2014

Mahbub Brothers (Pvt.) Ltd.

29-09-2015 And Extension up to 31-

01-2016 65.00

CRDP/LGED/KCC/KfW/ NCB/2014/W-

05

13-11-14 JI-ZT & KE JV

12-11-2015 And Extension up to 28-

02-2016 58.34

CRDP/LGED/KCC/KfW/ NCB/2014/W-

06

20-09-2015 BC-TAE JV 05-10-2016 15.10

CRDP/LGED/KCC/KfW/ NCB/2014/W-

08

30-09-2015

M/S KE, JI & ZT (JV)

14-10-2016 16.48

Page 29: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

26

Table 7: Subproject Environmental Performance Package No. Lot No. Design and

Preparation

Worker

Provision

Gender

Equity

Community

Based

Monitoring

Community

values and

safety

Hydrology

/ Water

pollution

Project

Completion

BATCH 1

Gazipur City Corporation

A. Drainage

CRDP/LGED/GCC/GAZIPUR/NCB/2012/W-01 CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-01 100 70 85 75 65 70 N/A

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-02 100 85 100 80 75 80 100

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012 /DW-03 100 75 100 60 70 75 100

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-04 100 85 100 70 100 70 100

CRDP/LGED/GCC/GAZI-PUR/NCB/ 2012/ DW-05 100 85 100 85 100 75 100

CRDP/LGED/GCC/GAZIPUR/NCB/ 2012/W-02 CRDP/LGED/GCC/GAZI-PUR/NCB/2012/DW-06 100 70 100 80 80 65 100

CRDP/LGED/GCC/GAZIPUR/NCB/ 2012/ DW-07 100 75 100 70 75 80 100

CRDP/LGED/GCC/GAZIPUR/NCB/ 2012/ DW-08 100 85 100 80 100 100 100

CRDP/LGED/GCC/GAZIPUR /NCB/2012/ DW-09 100 85 100 90 100 100 100

B. Gazipur CC: Water Supply and Sanitation

CRDP/LGED/GCC/NCB/ 2013/W-03

100 60 75 50 50 60 N/A

CRDP/LGED/GCC/ICB/ 2013/W-04

100 70 80 75 75 80 N/A

CRDP/LGED/GCC/ICB/ 2013/W-05

100 50 75 50 60 70 N/A

Drainage Improvement and Flood Protection in Khulna City

Region

CRDP/LGED/KLN/NCB/ 2012 /W-01 CRDP/LGED/KLN/NCB/ 2012 /DW-01 100 100 100 100 100 100 100

CRDP/LGED/KLN/NCB/2012 /W-02 CRDP/LGED/KLN/NCB/ 2012/DW-02 100 100 100 100 100 100 100

CRDP/LGED/KLN/NCB/2012/W-03 CRDP/LGED/KLN/NCB/ 2012/DW-03 100 100 100 100 100 100 100

CRDP/LGED/KLN/NCB/2012 /W-04 CRDP/LGED/KLN/NCB/ 2012/DW-04 100 100 100 100 100 100 100

CRDP/LGED/KLN/NCB/ 2012/W-05 CRDP/LGED/KLN/NCB/ 2012/DW-05 100 100 100 100 100 100 100

CRDP/LGED/KLN/NCB/ 2012/W-06 CRDP/LGED/KCC/ NCB/ 2013/W-06/DW-06 100 75 100 100 85 75 100

Page 30: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

27

Package No. Lot No. Design and

Preparation

Worker

Provision

Gender

Equity

Community

Based

Monitoring

Community

values and

safety

Hydrology

/ Water

pollution

Project

Completion

CRDP/LGED/KCC/NCB/2013/W-06/ DW-07 100 75 100 100 85 75 100

CRDP/LGED/KCC/NCB/2013/W-06/ DW-08 100 100 100 75 90 100 100

CRDP/LGED/KCC/NCB/2013/W-07 CRDP/LGED/KCC/ NCB/2013/W-07/ DW-09 100 80 100 75 80 80 100

CRDP/LGED/KCC/NCB/2013/W-07/DW-10 100 85 100 85 100 100 100

CRDP/LGED/KCC/NCB/2013/W-07/ DW-11 100 85 100 80 85 100 100

CRDP/LGED/KCC/ NCB/2013/W-07/DW-12 100 90 100 80 100 100 100

CRDP/LGED/KCC/NCB/2013/W-07/ DW-13 100 90 100 75 85 85 100

CRDP/LGED/KLN/NCB/ 2012/W-08 CRDP/LGED/KCC/\NCB/\2013/W-08/DW-14 100 95 100 85 100 100 100

CRDP/LGED/KCC/NCB/ 2013/W-08/ DW-15 100 95 100 85 100 100 100

CRDP/LGED/KLN/NCB/ 2012/W-09

100

N/A

CRDP/LGED/KLN/NCB/ 2012/W-10

100

N/A

Strengthening Economic Potential of Urban Center

in Ashilia, Savar, Dhaka.

CRDP/LGED/DHK/ICB/2013/W-01

100 80 100 75 80 80 100

CRDP/LGED/ DHK/ NCB/2013/ W-02

100 50 70 25 50 70 N/A

Dhaka North City Corporation

CRDP/LGED/DNCCI/ ICB/ 2014/ W-01 (Banani)

100 50 75 15 10 20 N/A

BATCH 2A

Manikganj Pourashava

CRDP/LGED/Manikganj/NCB/2013/W-01/RD-01 Lot-1 100 85 100 80 100 100 N/A

CRDP/LGED/Manikganj/NCB/2013/W-01/RD-02 Lot-2 100 85 100 80 100 100 N/A

CRDP/LGED/Manikganj/NCB/2014/W-02

100 85 100 75 100 80 N/A

Mongla Port Pourashava

CRDP/LGED/Mongla/NCB/2013/ W-01/RD-01 Lot-1 100 70 75 25 45 50 N/A

CRDP/LGED/Mongla/NCB/2013/ W-01/RD-02 Lot-2 100 65 100 50 60 45 N/A

Page 31: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

28

Package No. Lot No. Design and

Preparation

Worker

Provision

Gender

Equity

Community

Based

Monitoring

Community

values and

safety

Hydrology

/ Water

pollution

Project

Completion

CRDP/LGED/Mongla/NCB/2013/ W-02

100 50 65 55 65 25 N/A

CRDP/LGED/ Mongla/NCB/2014/W-03 Lot-1 100 70 100 50 75 60 N/A

Lot-2 100 80 100 55 70 80 N/A

Lot-3 100 75 80 75 80 85 N/A

Narayanganj City Corporation

CRDP/LGED/ NCC/ICB/ 2014/W-01

100 60 75 65 75 80 N/A

CRDP/LGED/ NCC/ICB/ 2014/W-02

100

N/A

Narsingdi Pourashava

CRDP/LGED/ NARSINGDI/ NCB/ 2014/ W-01

100 60 80 70 80 75 N/A

CRDP/LGED/ NARSINGDI/ NCB/ 2014/ W-02

100 50 90 8o 70 80 N/A

Jessore Pourashava

CRDP/LGED/ Jessore/ NCB/ 2014/ W-01

100 75 100 60 75 85 N/A

CRDP/LGED/Jessore/NCB/2014/W-02 Lot-1 100 60 50 35 60 50 N/A

Lot-2 100 55 50 50 70 70 N/A

Lot-3 100 65 50 45 65 65 N/A

CRDP/LGED/Jessore/NCB/2014/W-03

100

N/A

Sonargaon Pourashava

CRDP/LGED/ Sonargaon/ NCB/ 2014/ W-01

100 80 75 75 70 65 N/A

CRDP/LGED/ Sonargaon/ NCB/ 2014/ W-02

100

N/A

Tarabo Pourashava

CRDP/LGED/ Tarabo/ NCB/ 2014/ W-01

100 70 80 60 80 90 N/A

CRDP/LGED/ Tarabo/ NCB/ 2014/ W-02

100

N/A

Jhikorgacha Pourashava

CRDP/LGED/Jhikorgacha/ NCB/ 2014/ W-01

100 60 75 40 90 70 N/A

CRDP/LGED/Jhikorgacha/ NCB/ 2014/ W-02 Lot-1 100 75 80 50 70 80 N/A

Page 32: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

29

Package No. Lot No. Design and

Preparation

Worker

Provision

Gender

Equity

Community

Based

Monitoring

Community

values and

safety

Hydrology

/ Water

pollution

Project

Completion

Lot-2 100 80 90 60 80 75 N/A

Nowapara Pourashava

CRDP/LGED/ Nowapara/ NCB/ 2014/ W-01

100 85 100 50 85 80 N/A

CRDP/LGED/ Nowapara/ NCB/ 2014/ W-02

100 50 70 20 30 50 N/A

Kaliakoir Pourashava

CRDP/LGED/ Kaliakoir/ NCB/ 2014/ W-01

100 90 100 60 75 70 N/A

CRDP/LGED/Kaliakoir/NCB/ 2014/ W-02 Lot-1 100 75 100 50 70 60 N/A

Lot-2 100 75 90 50 60 70 N/A

Kanchon Pourashava

CRDP/LGED/ Kanchon/ NCB/ 2014/ W-01

100 60 90 60 80 75 N/A

CRDP/LGED/ Kanchon/ NCB/ 2014/ W-02

100 70 80 50 70 70 N/A

Singair Pourashava

CRDP/LGED/ Singair/ NCB/ 2014/ W-01

100 80 85 75 100 70 N/A

CRDP/LGED/ Singair/ NCB/ 2014/ W-02 Lot-1 100 50 75 60 75 80 N/A

Lot-2 100 50 70 70 80 60 N/A

Savar Pourashava

CRDP/LGED/ Savar/NCB/2014/ W-01

100 40 80 80 90 80 N/A

CRDP/LGED/ Savar/NCB/2014/ W-02 Lot-1 100 60 75 75 80 90 N/A

Lot-2 100 50 80 90 85 85 N/A

CRDP/LGED/ Savar/NCB/2014/ W-03

GCC (Tongi Area)

CRDP/LGED/GCC/TONGI/ NCB/2014/ W-06 Lot-1 100 70 90 100 85 80 N/A

Lot-2 100 75 80 90 80 75 N/A

CRDP/LGED/ Savar/NCB/2014/ W-03

100

N/A

Khulna City Region: KfW Part

Page 33: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

30

Package No. Lot No. Design and

Preparation

Worker

Provision

Gender

Equity

Community

Based

Monitoring

Community

values and

safety

Hydrology

/ Water

pollution

Project

Completion

CRDP/LGED/KCC/KfW/ NCB/2013/W-01

100 85 90 70 90 55 N/A

CRDP/LGED/KCC/KfW/ NCB/2013/W-02

100 100 100 75 100 90 N/A

CRDP/LGED/KCC/KfW/ ICB/2013/W-03

100 80 80 80 75 80 N/A

CRDP/LGED/KCC/KfW/ ICB/2014/W-04

100 75 100 100 80 75 N/A

CRDP/LGED/KCC/KfW/ NCB/2014/W-05

100 90 70 70 60 60 N/A

Page 34: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

31

VI. CONCLUSIONS AND RECOMMENDATIONS

25. Environmental mitigation measures related to subprojects are being implemented in line

with the Environmental Safeguard Framework; performance is generally according to plan.

Environmental review through use of IEEs and EIAs is done in conjunction with subproject design and

is on schedule. Training has been completed for PIU staff on active subprojects. Contractors are

required to mitigate environmental impacts, and monitoring is being conducted by the

environmental specialists and PIU staff. Where mitigation measures are lacking, contractors are

urged to improve their performance. The GRM is in the process of being implemented with

Committees formed at local level.

26. Active areas for improvement for subprojects under implementation include the following:

Overall improvement of environmental performance is needed on most contracts through

preparation of site construction EMPs, designation of an environmental officer by

contractors and closer attention to mitigation measures.

Workers need to be equipped with safety equipment, which is lacking at most jobsites.

Housing and sanitary facilities for workers are also substandard on some of the contracts,

whereas at other locations these facilities are up-to-standard and/or are not necessary

because of hiring of local labor.

Contractors and PIUs do not formally engage communities in consultation; however due to

the small size of subproject formal public consultation is not justified. Affected parties can

and do directly approach site supervisors to remedy a particular problem or inconvenience.

PIUs need to post notices regarding the grievance redress mechanism and the ability of an

affected party to seek redress on an environmental issue.

Some community safety issues are only partially addressed by contractors. At some

locations better barricades need to be erected around open excavations where the public

has access. Temporary access to homes and businesses need to be properly constructed for

subprojects under implementation.

Use of temporary signage and flagmen is deficient on many contracts. These elements

should be used where they could assist traffic flow and pedestrian safety.

Wind-blown dust and mud/gravel on road surfaces is common at many sites. Contractors

need to remove stockpiled materials that are no longer in use from the jobsite; and reduce

material losses from trucks hauling sand and spoil by covering loads and by removing

materials from tires and truck underbodies before transport. Contractors need to be more

willing to dedicate labor time for cleaning roadway surfaces.

27. The PMCU has made significant strides in improving environmental awareness of the need

for mitigation measures among the PIUs and construction contractors. Environmental specialists will

continue to work with PIUs and contractors to realize performance improvements.

Page 35: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

32

APPENDIX 1: CRDP ENVIRONMENTAL MONITORING CHECKLIST

Asian Development Bank – Local Government Engineering Department

Capital Region Development Project

ADB Loan 2695-BAN

Environmental Compliance Monitoring Form

Part A: General Project Information

Subproject Name:_____________________________________________________

Subproject Package No.:_____________________________ Lot No.:____________

Activity Sector:________________________________________________________

Municipality / Upazila / Urban Center:______________________________________

Construction Contractor Name:___________________ Contract Date: ___________

Contract Amount:_____________________ Contract Duration (days)____________

Person Responsible: __________________________ Phone __________________

PIU EMO:_________________________________ Phone ____________________

Form Completed by: Phone ___

Page 36: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

33

Part B: Monitoring checklist

Performance Indicator 1. Design and Preparation

The PMCU Safeguard Management Officer (PSMO) to complete 1-4 at the time the project is

tendered. Date of Monitoring:_________________

Form Completed by: Phone ___

Score Remarks

1. Does the subproject design meet applicable engineering safety and public health standards?

2. Has ADB approved the revised and updated IEE and related EMP for the subproject?

3. Have applicable resettlement provisions been disclosed and compensation made to affected persons or households?

4. Have special conditions and the EMP been included in the procurement documents?

The PSMO to complete 5-13 with the PIU Environmental Management Officer (PEMO) and

construction contractor at the time of start-up. Date of Monitoring:_____

5. Are the special conditions and the EMP from the subproject IEE included in the construction contract?

6. Has the contractor prepared a Construction EMP?

7. Has the Contractor’s supervisory staff obtained environmental management training and orientation?

8. Has the contractor posted a public notice regarding the nature, extent and cost of the project?

9. Are locations for equipment/materials storage sufficiently distant from schools and hospitals?

10. Have worksite and ancillary sites been surveyed and pegged to ensure correct lines and grades?

11. Has final verification of affected persons/assets been undertaken prior to commencement of works?

12. Are owner agreements in place for temporary use of land for worker camps and construction yards?

13. Are quarry sites, borrow pits and spoil disposal sites selected in consultation with local authorities?

Score (1-13; 13 total) (%)

Page 37: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

34

Performance Indicator 2. Worker Provisions

The PEMO to complete 14-20 in conjunction with the construction contractor following

commencement of construction. Date of Monitoring:__________

Score Remarks

14. Is GOB labor law complied with in hiring of workers?

15. Are supervisors or other site personnel trained in basic first aid emergency response measures?

16. Are first aid kits readily available to workers at the job site along with instructions for use?

17. Has the contractor undertaken an awareness program for communicable diseases/HIV-AIDS?

18. Has the contractor provided necessary safety equipment to workers and training in use?

19. Are construction camps adequately equipped with water supply, sanitary toilets, washing facilities and facilities for waste collection and storage?

20. Do workers at construction sites have access to potable water supply and toilet facilities?

Score (14-20; 7 total) (%)

Performance Indicator 3. Gender Equity

The PEMO should complete 21 - 23 in conjunction with the construction contractor following

commencement of construction. Date of Monitoring:__________

Score Remarks

21. Does the contractor engage women laborers and project-affected women in suitable work?

22. Does the contractor provide equal wages for equal value of work to women engaged at the worksite?

23. Has separate sanitation facilities been provided for women at work camps and the construction site?

Score (21 - 23; 3 total) 0 (%)

Page 38: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

35

Performance Indicator 4. Community Based Monitoring

The PEMO should complete 24 and 25 in conjunction with the construction contractor following

commencement of construction. Date of Monitoring:__________

Score Remarks

24. Has the contractor posted a public notice regarding the Grievance Redress Mechanism (GRM)?

25. Has there been a public consultation regarding construction environmental impact, and the community complaints system?

Score (24-25; 2 total) 0 (%)

Outcome of Public Consultation:

Date: ___________ Location: __________________

Topics covered in presentation: __________________________________________

___________________________________________________________________

Comments from Attendees:

Page 39: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

36

Performance Indicator 5. Community Values and Safety

The PEMO should complete Items 26 – 38 quarterly based on visual inspection of the conduct of

work. Date of Monitoring:___________ Percent Complete:

Score Remarks

26. Is temporary access provided to homes and businesses?

27. Is permanent access reinstated on completion of a segment of work?

28. Are construction hours adjusted around houses, hospitals and schools to minimize disturbance?

29. Does the contractor limit the scope of construction in progress to minimize community impacts?

30. Are physical impacts on public infrastructure and service disruption minimized?

31. Are materials transported on approved haul routes?

32. Is construction equipment kept in good condition?

33. Do vehicles operate within legal speed limits?

34. Are trucks hauling bulk materials covered in transit?

35. Is dust suppressed and road surfaces kept clean?

36. Has the contractor installed signs and lighting in vicinity of works on public roads?

37. Are construction activities barricaded and pedestrian pathways maintained?

38. Have complaints arising during the quarter been satisfactorily resolved?

Score (26-38; 13 total) (%)

Page 40: Semi-Annual Environmental Safeguard Monitoring Report€¦ · (i) The fiscal year (FY) of the Government of Bangladesh ends on 30 June. FY before a calendar year denotes the year

37

Performance Indicator 6. Hydrology/Water Pollution

The PEMO should complete Items 39 – 43 quarterly based on visual inspection of the conduct of

work. Date of Monitoring:_____________ Percent Complete:

Score Remarks

39. Are construction camps and equipment/materials stores maintained in clean and hygienic condition?

40. Are oil, fuel and chemicals stored in enclosed areas (dyked or covered)?

41. Is clearing activity suspended during rains?

42. Have existing drainage patterns been maintained during construction?

43. Are sediment controls installed upslope of waterways?

Score (39-43; 5 total) (%)

Performance Indicator 7. Project Completion

The PEMO should complete items 44 – 50 prior to finalizing the construction works. Date of

Monitoring:______________ Percent Complete:

Score Remarks

44. Have drainage fixtures, curbs, road shoulders and ditch slopes been finished out to prevent hazard to the public during use?

45. Are ground surfaces in the project area graded to prevent water from collecting?

46. Have all construction debris, tree cuttings, excess dirt, rubble and scrap been removed from the construction zone?

47. Have all pits been filled in and graded to drain, underground tanks (including septic tanks) removed and holes backfilled?

48. Are all wastes and unused materials removed from the site, equipment yards and worker camps?

49. Have all points of access (drives, walks) and utilities (water supply, power, communications) to public and private property been restored to original condition?

50. Have all complaints by project-affected persons been resolved by the Contractor?

Score (44-50; 7 total) (%)