sed duxbury wind feasibility report

Upload: duxbury-clipper

Post on 07-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 SED Duxbury wind feasibility report

    1/144

    TECHNICAL ANALYSIS FOR ON-SITE WIND GENERATION- DRAFT REPORT

    Town of Duxbury, Massachusetts

    October 20, 2011

    Sponsored by:

  • 8/3/2019 SED Duxbury wind feasibility report

    2/144

    2

  • 8/3/2019 SED Duxbury wind feasibility report

    3/144

    iDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Notice

    This report was prepared by Sustainable Energy Developments, Inc. in the course of performing work

    sponsored by the Massachusetts Clean Energy Center (MassCEC) Commonwealth Wind Incentive

    Program: Community Scale Wind, pursuant to task order 10-1 executed November 19, 2010. The

    opinions expressed in this report do not necessarily reflect those of the MassCEC or the Commonwealth

    of Massachusetts, and reference to any specific product, service, process, or method does not constitute

    an implied or expressed recommendation or endorsement of it.

    Further, the MassCEC, the Commonwealth of Massachusetts, and the contractor make no warranties or

    representations, expressed or implied, as to the fitness for particular purpose or merchantability of any

    product, apparatus, or service, or the usefulness, completeness, or accuracy of any processes, methods

    or other information will not infringe privately owned rights and will assume no liability for any loss, injury,

    or damage directly or indirectly resulting from, or occurring in connection with, the use of information

    contained, described, disclosed, or referred to in this report.

    Acknowledgements

    Rich Gross P.E. Inc. contributed to the development of an electrical interconnection plan for a wind

    turbine at this site.

    AWS Truepower, LLCprovided wind resource data that was used to calculate wind turbine output

    estimates.

    Disclaimer

    This report is presented in response to the contract between the Town of Duxbury and Sustainable

    Energy Developments, Inc. executed on 19 November 2010. The information and analyses presented

    herein is based on wind development best practices, commercially available information and a preliminary

    analysis of the Town of Duxbury electrical infrastructure. SED makes no guarantees, expressed or

    implied as to the actual outcome of the processes described in this report.

  • 8/3/2019 SED Duxbury wind feasibility report

    4/144

    3

  • 8/3/2019 SED Duxbury wind feasibility report

    5/144

    iiDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    ABSTRACT

    nalysis for On-Site

    Wind Generation for the Town of Duxbury that occurred between November of 2010 and December of

    2011. The study assessed and quantified the ability to install a wind turbine on Town-owned land

    that would utilize virtual net metering to offset municipal accounts. Key aspects of wind project

    development were examined including: site considerations; wind resource assessment and turbine output

    modeling; wind generated electricity value; electrical system impact assessment; buildability; permitting;

    development budgeting; total capital cost; operations & maintenance; timeline; an economic analysis; and

    financing and ownership options.

    The goal of this feasibility study was to identify and explore a wind energy project that would be

    economically beneficial for the Town of Duxbury to pursue. The Town of Duxbury Wind Bylaw restricts

    the allowable height of a wind turbine to 250 feet, which presents an obstacle to economically beneficialoutcome for the Town. There are currently no wind technologies under this height that would be an

    economical option for the Town to purse. Therefore, SED explored two different wind turbine technology

    options that would provide the best economic opportunity for the Town of Duxbury. One would involve a

    Northwind 450kW, a wind turbine currently under development, but that would be much more economical

    than other similarly sized technologies on the market. The other technology evaluated was a PowerWind

    900kW, which would slightly exceed the height limit, but would provide a proven and readily available

    wind turbine that would generate significant electricity savings for the Town of Duxbury. Proceeding with

    a project utilizing either of these technologies would be the best pathway to forward to a successful wind

    development.

  • 8/3/2019 SED Duxbury wind feasibility report

    6/144

    iiiDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    KEYWORDS

    On-site Wind Power

    Wind Turbine

    Wind Power

    Wind Modeling

    WindPro

    WAsP

    Town of Duxbury

    Sustainable Energy Developments, Inc.

    Northern Power Systems

    Northern Power 450kW

    PowerWindPowerWind 56 900kW

    Virtual Net Metering

  • 8/3/2019 SED Duxbury wind feasibility report

    7/144

    ivDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    ACRONYMS AND ABBREVIATIONS

    agl -above ground level

    amsl -above mean sea level

    AEP -annual energy production

    AEO -annual energy output

    DEP -Department of Environmental Protection

    ENF -Environmental Notification Form

    EPA -Environmental Protection Agency

    FAA -Federal Aviation Administration

    FCC -Federal Communications Commission

    ft -feet

    kW -kilowatt

    kV -kilovolt

    kVA -kilovolt-amp

    MEPA -Massachusetts Environmental Policy Act

    Mass Highway -Massachusetts Highway Department

    MassCEC -Massachusetts Clean Energy Center

    MWh -Megawatt hours

    m -meters

    m/s -meters per second

    MW -Megawatt

    NPDES -National Pollutant Discharge Elimination System

    NHESP -Natural Heritage and Endangered Species Program

    NHGC -North Hills Golf Course

    NOI -Notice of Intent

    O & M -operations and maintenance

    SED -Sustainable Energy Developments, Inc

    USFWS -United States Fish and Wildlife Service

    W/m2

    -Watts per square meter

    WAsP -Wind Atlas and Analysis Application Program

  • 8/3/2019 SED Duxbury wind feasibility report

    8/144

    vDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    TABLE OF CONTENTS

    Section Page

    S EXECUTIVE SUMMARY S-1

    1 WIND TURBINE SITING AND ENERGY YIELD ANALYSIS 1-1

    1.1 BACKGROUND 1-1

    1.2 NORTH HILL SITE DESCRIPTION 1-1

    1.3 PROPERTIES ASSESSMENT 1-2

    1.4 WIND RESOURCE POTENTIAL 1-4

    1.5 SITING CONSIDERATIONS 1-6

    1.6 SELECTED SITE EVALUATIONS 1-10

    1.7 FINAL SCENARIO RECOMMENDATIONS 1-16

    2 WIND RESOURCE ASSESSMENT AND TURBINE OUTPUT MODELING 2-1

    2.1 WIND TURBINE SELECTION AND OUTPUT CALCULATION 2-12.2 VIRTUAL MET MAST INFORMATION 2-2

    2.3 TERRAIN AND ROUGHNESS MAPS 2-3

    2.4 WIND TURBINE POWER CURVES 2-3

    2.5 SUMMARY OF MODEL RESULTS 2-5

    2.6 FINAL TURBINE OUTPUT CALCULATIONS 2-6

    3 INTERCONNECTION INVESTIGATION 3-1

    3.1 RECOMMENDED INTERCONNECTION PLAN 3-1

    3.2 NEXT STEPS 3-2

    4 WIND GENERATED ELECTRICITY VALUE 4-1

    4.1 TOWN OF DUXBURY ELECTRICITY DATA 4-1

    4.2 GREEN COMMUNITIES ACT AND NET METERING 4-2

    4.3 CALCULATING NET METERED CREDITS 4-3

    4.4 IMPLICATIONS OF NET METERING 4-5

    4.5 ELECTRICITY RATE ESCALATION 4-6

    5 BUILDABILITY 5-1

    5.1 TRANSPORTATION 5-1

    5.2 SITE ACCESS AND STAGING 5-1

    5.3 FOUNDATIONS AND GEOTECHNICAL CONSIDERATIONS 5-3

  • 8/3/2019 SED Duxbury wind feasibility report

    9/144

    viDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    6 PERMITTING AND REGULATORY ANALYSIS 6-1

    6.1 FEDERAL REGULATIONS 6-1

    6.2 STATE REGULATIONS 6-9

    6.3 LOCAL REGULATIONS 6-17

    6.4 RECOMMENDATIONS 6-19

    7 PERMITTING TOOLBOX 7-1

    7.1 SOUND PROPAGATION REPORT 7-1

    7.2 SHADOW FLICKER ASSESSMENT 7-3

    7.3 SUMMARY OF FINDINGS 7-7

    8 CAPITAL COSTS 8-1

    8.1 ESTIMATED CAPITAL COSTS 8-1

    8.2 OPERATION AND MAINTENANCE 8-58.3 PROJECT TIMELINE 8-6

    9 ECONOMIC ANALYSIS 9-1

    9.1 BASELINE ECONOMIC ANALYSIS 9-1

    9.2 SENSITIVITY ANALYSIS 9-2

    10 FINANCING, OWNERSHIP AND OPERATIONS

    10.1 MUNICIPAL BOND 10-1

    10.2 LEASE MODEL 10-310.3 THIRD PARTY OWNERSHIP 10-4

    10.4 CONCLUSION 10-9

  • 8/3/2019 SED Duxbury wind feasibility report

    10/144

    viiDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    FIGURES

    FIGURE PAGE

    Figure 1-1 North Hill Area with Property Lines 1-2

    Figure 1-2 Property Designations with Legend 1-3

    Figure 1-3 Municipal Open-Space Properties with Outline 1-4

    Figure 1-4 Wind Resource Grid and Eligible Municipal Properties 1-5

    Figure 1-5 Wind Resource Grid with Areas Identified 1-6

    Figure 1-6 Wind Turbine Technologies 1-10

    Figure 1-7 Site 1 NHGC with Setbacks 1-11

    Figure 1-8 Site 2 Kettle Hole with Setbacks 1-13

    Figure 1-10 Site 3 DPW West with Setbacks 1-15

    Figure 1-7 Recommended Wind Turbine Locations 1-17

    Figure 2-1 VMM Information 2-2

    Figure 2-2 70m VMM Wind Roses and Weibull Distribution 2-3Figure 2-3 PowerWind 56 900kW Manufacturer Supplied Power Curve 2-4

    Figure 2-4 Northern Power 450kW Manufacturer Supplied Power Curve 2-5

    Figure 2-5 Summary of Model Result 2-5

    Figure 2-6 Assumed Losses 2-6

    Figure 2-7 Final Output Calculations 2-7

    Figure 4-1 12-Month Electric Usage Data (kWh) 4-2

    Figure 4-2 Ten Largest Electric Accounts in Town of Duxbury 4-2

    Figure 4-3 NSTAR 33-General Annual (G-1) Delivery Service Charges 4-4

    Figure 4-4 Utility Derived Electricity Value Year 1 4-5Figure 4-5 Projected Electricity Rates ($ per kWh) 4-6

    Figure 6-1 Airports in Proximity of Proposed Development 6-2

    Figure 6-2 Airports within a Ten-mile Vicinity 6-2

    Figure 6-3 FCC Communication Paths Geosearch Results 6-4

    Figure 6-4 Point to Point Communications 6-5

    Figure 6-5 Local Communications 6-6

    Figure 6-6 DOD long Range Radar Tool 6-7

    Figure 6-7 Federal Regulations 6-8

    Figure 6-8 Priority Habitats in Proximity of the Proposed Locations 6-10

    Figure 6-9 Estimated Habitats in Proximity of the Proposed Locations 6-11

    Figure 6-10 Protected or Listed Species for the Town of Duxbury 6-12

    Figure 6-11 National Wetlands Inventory 6-13

    Figure 6-12 Nationally Registered Historic Sites within Five Miles 6-14

    Figure 6-13 Nationally Registered Historic Site Details within Five Miles 6-15

  • 8/3/2019 SED Duxbury wind feasibility report

    11/144

    viiiDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 6-14 State Regulations and Policies 6-16

    Figure 6-15 Publicly Owned Land Overlay (POLO) District 6-17

    Figure 6-16 Comparison of Turbine Variance Needs 6-18

    Figure 6-17 Town Permits and Approvals 6-19

    Figure 7-1 Sound Levels at 8 m/s for One (1) PowerWind 56 900kW

    Wind Turbine at Site 1 7-2

    Figure 7-2 Sound Levels at 8 m/s for One (1) PowerWind 56 900kW

    Wind Turbine at Site 2 7-2

    Figure 7-3 Sound Levels at 8 m/s for One (1) PowerWind 56 900kW

    Wind Turbine at Site 3 7-3

    Figure 7-4 PowerWind 56 Shadow Flicker Map Site 1 7-5

    Figure 7-5 PowerWind 56 Shadow Flicker Map Site 2 7-6

    Figure 7-6 PowerWind 56 Shadow Flicker Map Site 3 7-6

    Figure 8-1 Estimated Total Project Costs 8-1Figure 8-2 Estimated Design Costs 8-2

    Figure 8-3 Estimated Construction Capital Costs for PowerWind 900kW 8-3

    Figure 8-4 Estimated Construction Capital Costs for PowerWind 900kW 8-4

    Figure 8-5 O&M Costs Comparison 8-6

    Figure 8-5 Project Timeline for Wind Turbine Development 8-7

    Figure 9-1 Unleveraged IRR, Payback and Savings at a 3% Energy Escalation 9-2

    Figure 9-2 Scenario 1 900kW Sensitivity Analysis with Variable Energy Escalation Rates 9-2

    Figure 9-3 Scenario 2 450kW Sensitivity Analysis with Variable Energy Escalation Rates 9-3

    Figure 9-4 Scenario 1 900kW Sensitivity Analysis with Variable Annual Energy Production 9-3Figure 9-5 Scenario 2 450kW Sensitivity Analysis with Variable Annual Energy Production 9-3

    Figure 9-6 Scenario 1 900kW Sensitivity Analysis with Capital Costs 9-4

    Figure 9-7 Scenario 2 450kW Sensitivity Analysis with Capital Costs 9-5

    Figure 10-1 IRR, Year 1 and Year 20 Savings for Scenario 1 with Municipal Bond 10-2

    Figure 10-2 Cash Flow of Bond Financed Wind Turbine Project at 3% Escalation 10-2

    Figure 10-3 Town of Duxbury Economic Benefits for Lease Model Scenario 1 10-3

    Figure 10-4 Cash Flow of Lease Model Scenario 1 10-4

    Figure 10-5 20-Year Economic Benefit at Varying Retail Electricity Escalation Rates for $0.125/kWh

    PPA at 3% Escalation with ITC 10-5

    Figure 10-6 Energy Savings with $0.125/kWh PPA Escalating at 3% with ITC 10-6

    Figure 10-7 20-Year Economic Benefit at Varying Retail Electricity Escalation Rates for $0.155/kWh

    PPA at 0% Escalation with ITC 10-6

    Figure 10-8 Energy Savings with $0.155kWh PPA Escalating at 0% with ITC 10-7

  • 8/3/2019 SED Duxbury wind feasibility report

    12/144

    ixDraft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 10-9 20-Year Economic Benefit at Varying Retail Electricity Escalation Rates for $0.195/kWh

    PPA at 3% Escalation without ITC 10-7

    Figure 10-10 Energy Savings with $0.195 PPA Escalation at 3% without ITC 10-8

    Figure 10-11 20-Year Economic Benefit at Varying Retail Electricity Escalation Rates for $0.245/kWh

    PPA at 0% Escalation without ITC 10-8

    Figure 10-12 Energy Savings with $0.245/kWh PPA Escalating at 0% without ITC 10-9

    APPENDICES

    Appendix A WindPRO Model Runs

    Appendix B Electrical One-line Diagram E-2

    Appendix C Utility Rate Description

    Appendix D Preliminary Development Plan D-1

    Appendix E FAA Determination

    Appendix F Town of Duxbury Community Wind Facilities Bylaw

    Appendix G Shadow Flicker Analysis

    Appendix H Output Pages from Cash Flow Models

  • 8/3/2019 SED Duxbury wind feasibility report

    13/144

    S-1Draft Report

    Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    EXECUTIVE SUMMARY

    After completing a thorough technical feasibility study, Sustainable Energy Developments, Inc. (SED) has

    determined that the installation of an economically viable wind power installation in the Town of Duxbury

    is dependent upon: access to appropriately sized wind turbine technology and/or building community

    support necessary to secure a height variance from the 250 foot height restriction established by the

    no currently available wind turbine which would generate significant economic returns for the Town. This

    issue may be overcome by the introduction of new wind turbine technologies, currently being tested for

    rbine project.

    SED therefore identified two wind turbine technologies that would provide favorable economic returns for

    use in this technical assessment. Neither of these technologies is an ideal or immediate fit for the project.

    The Northwind 450kW is currently undergoing testing at the National Renewable Energy Laboratory inGolden, CO and is not expected to be commercially available until the summer of 2012 at the earliest.

    The PowerWind 900kW is problematic because the shortest tower option would excees

    height limit by 26 feet. These technology issues can be navigated efficiently through a transparent

    development process A wind energy

    installation in the Town of Duxbury possesses the technical characteristics necessary for a feasible,

    is to pursue a larger project that would require a variance, because such a project will provide significantly

    greater financial benefits for the Town without imposing significant impacts to the environment or

    neighboring land uses. SED further recommends that this project proceed into the business planningphase in preparation for a public vote on whether to proceed with obtaining a design and construction

    grant from the MassCEC.

    Site Considerations: Only property owned by the Town of Duxbury located in the area of North Hill, not

    designated as conservation land was contemplated for potential wind turbine locations. There were

    numerous development factors considered to identify appropriate locations for a wind turbine installation

    in the North Hill area. SED first identified properties owned by the Town of Duxbury within an area of

    roughly 1000 acres between the North Hill Golf Course, North Hill Marsh Wildlife Sanctuary, the Town

    Hall and DPW Yard and Mayflower Cemetery. Once these properties were identified, SED overlaid a

    wind resource grid to determine those areas with the highest wind speeds that would best support an

    installation and three specific areas were selected: North Hill Golf Course, Kettle Hole and DPW West.

  • 8/3/2019 SED Duxbury wind feasibility report

    14/144

    S-2Draft Report

    Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    SED then applied additional criteria to determine most appropriate location to install a wind turbine within

    each identified area. These included: setbacks from residences; setbacks from sensitive habitats;

    Duxbury Community Scale Wind Facilities Bylawsetbacks; interconnection; accessibility; and wind

    turbine technology.

    The Town of Duxbury Wind FacilitiesBylaw establishes a minimum setback distance equal to 1.1 times

    the overall height of the wind turbine from the nearest property line and private or public way; and a

    minimum setback distance equal to 2 times the overall height of the wind facility from the nearest existing

    residential or commercial structure not owned by the applicant. SED also applied wind industry standard

    setbacks based on the scale of wind turbine being considered.

    The Bylaw also restricts height of a wind turbine to 250 feet (76m) from the base of the wind turbine to the

    tip of the rotor blade at its highest point. This height restriction greatly limits the available wind turbine

    technologies that could be considered for this project that would provide a worthwhile economic benefits

    to the Town. Therefore, SED identified two wind turbine technologies to be considered for installation in

    the Town of Duxbury, a Northwind 450kW and a PowerWind 900kW. The Northwind 450kW wind turbine

    is currently under development and will not be commercially available until late 2012, but on a 50-meter

    (76 feet) tower would not exceed the 250 foot height limited established by the Bylaw and due to its

    advanced design would be more cost effective than other similarly sized technologies. The other wind

    turbine considered, was a PowerWind 900kW on a 59-meter (194 feet) tower, which is a proven and

  • 8/3/2019 SED Duxbury wind feasibility report

    15/144

    S-3Draft Report

    Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    readily available technology. This wind turbine would slightly exceed the 250 foot height limit, but the

    stronger economic returns it would provide may be enough to justify a variance for the additional height.

    Wind Turbine &

    Rated Capacity

    Tower

    Height

    Rotor

    Diameter

    Total Tip

    Height

    Bylaw

    Setback from

    Residential

    Buildings

    Recommended

    Setback from

    Residential

    Buildings

    Northern Power

    450kW50m (164ft) 48m (157ft) 74m (243 ft) 150m (492ft) 244m (800ft)

    PowerWind

    900kW59m (194ft) 56m (184ft) 87m (276 ft) 175m (574ft) 305m (1000ft)

    After evaluating the positive and negative aspects of the potential locations, three final sites wereidentified as the most developable locations for a wind turbine installation. All of the proposed sites meet

    Bylaw and industry standard setback requirements.

  • 8/3/2019 SED Duxbury wind feasibility report

    16/144

    S-4Draft Report

    Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    From these locations, SED developed six potential development scenarios utilizing the two different wind

    turbine technologies detailed to determine the logistical and economic viability of a development at the

    Town of Duxbury.

    Scenario Site Wind Turbine

    1 North Hill Golf Course PowerWind 56 900kW

    2 North Hill Golf Course Northwind 450kW

    3 Kettle Hole PowerWind 56 900kW

    4 Kettle Hole Northwind 450kW

    5 DPW West PowerWind 56 900kW

    6 DPW West Northwind 450kW

    Wind Resource Assessment and Wind Turbine Output Modeling: The two different sized wind turbine

    technologies were analyzed by creating a computer model with the industry standard modeling tool Wind

    Atlas and Application Program (WAsP), created by the Danish National Laboratory, along with WindPRO,

    created by EMD International A/S. A key input to the model was a representative year of wind data

    derived from a Virtual Met Mast. Other key inputs to the model include wind turbine power curves for the

    selected technologies, a roughness map, and a digital elevation model of the region. The following chart

    is a summary comparison of the four scenarios analyzed.

    Scenario Wind Turbine Gross MWh

    Net MWh (AEP

    minus 7.5% in

    losses)

    Mean Wind Speed

    at Hub Height (m/s)

    1 PowerWind 56 900kW 1,830.4 1,693 5.82 m/s (13.0 mph)

    2 Northwind 450kW 1,167.5 1,080 5.48 m/s (12.3 mph)

    3 PowerWind 56 900kW 1,892.1 1,750 5.89 m/s (13.2 mph)

    4 Northwind 450kW 1,234.4 1,1425.61 m/s (12.6 mph)

    5 PowerWind 56 900kW 1,893.3 1,751 5.91 m/s (13.2 mph)

    6 Northwind 450kW 1,243.0 1,150 5.64 m/s (12.6 mph)

  • 8/3/2019 SED Duxbury wind feasibility report

    17/144

    S-5Draft Report

    Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Interconnection Investigation: SED commissioned an electrical interconnection plan for the project. It

    was determined that the recommended interconnection for any of the three facilities would be into existing

    three phase 23kV over-head distribution circuits located at the North Hill Golf Course (Sites 1 and 2) or

    Town of Duxbury DPW Yard (Site 3). The 690V output of the wind turbine will be stepped up by a three

    phase transformer at the base of the wind turbine. From there, the wire will run underground to the

    overhead circuit at the Golf Course or DPW Yard. The wire runs for each site will be: 640m (2100ft) for

    Site 1, 832m (2700ft) for site 2 and 518m (1700ft) for Site 3 respectively.

    Utility Derived Electricity Value: SED evaluated 12+ months of electric bills and other supporting

    i in order to determine the value of wind

    generated electricity. The Town of Duxbury currently uses over 5.2 million kWh per year, most of which is

    attributed to the Duxbury Public Schools. The Town of Duxbury is served by NStar and currently has a

    supply contract with GEXA for $0.104/kWh. The average electricity rate that the Town of Duxbury

    currently pays is valued at $0.18/kWh.

    Based on the interconnection investigation, any of the proposed wind turbines, would not be

    interconnected behind an existing meter and therefore virtual net metering will be employed. Based on

    proceedings in the Mass DPU regarding the implementation of the Green Communities Act, the rate at

    which the electricity produced by a wind turbine at North Hill -

    1 Rate) calculated to be $0.16/kWh. This will be applied to every kWh generated by a wind turbine at

    North Hill and the savings will then be allocated onto the

    The scenarios presented will produce between 20% and 40% of the total electricity usage within the Townof Duxbury and net metering eligibility will provide that 100% of the wind generated electricity will be

    valued at the G-1 Rate.

    Buildability: The transport of equipment, site access, staging needs and foundation considerations were

    explored for both the PowerWind 900kW and Northwind 450kW wind turbines. Site 1 will require an

    access road to be built from the golf course parking lot that follows the edge of the driving range to the

    proposed turbine site. Limited clearing will be necessary at the wind turbine site, with the potential

    utilization of a small area of the golf course. Site 2 and 3 will require significant site work that includes

    grading of the existing slope to provide a flat area for the installation of the foundation and clearing of

    trees at the project site and for a permanent access road.

    Based on the subsurface conditions typical to coastal regions of Massachusetts consisting of sand and

    gravel deposits a spread footing type foundation is anticipated for use at each site.

  • 8/3/2019 SED Duxbury wind feasibility report

    18/144

    S-6Draft Report

    Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Permitting: SED analyzed local, state and federal permitting considerations for the installation of a wind

    turbine in the Town of Duxbury at three identified sites. SED mapped out a permitting pathway for the

    wind project to satisfy required permits and approvals. If the PowerWind 900kW wind turbine is pursued

    a variance would be required to exceed the 25 . There do not

    appear to be any other major permitting obstacles to development, although some additional

    environmental studies will be necessary and public outreach through project specific public forums

    combined with general wind education will be vital to project success.

    Permitting Toolbox: SED performed initial assessments of the sound, shadow and visual implications of

    a wind turbine installation at the sites considered. These studies suggest that any of three sites will have

    limited or no discernible effect to neighboring residences. Site 1 will present some shadow and sound

    effects to the North Hill Golf Course, but this will not affect the safety nor does SED feel it will adversely

    affect recreation or ongoing operations at the golf course.

    Development Budget Timeline and Total Capital Cost: Detailed design and construction budgets were

    created for the different development scenarios. The following chart shows the design and construction

    budgets for each scenario.

    Town of Duxbury Scenario 1900kW

    Scenario 2450kW

    Scenario 3900kW

    Scenario 4450kW

    Scenario 5900kW

    Scenario 6450kW

    Total Design $249,830 $203,800 $268,390 $222,360 $263,390 $217,360

    Wind Turbine Cost $1,664,000 $997,000 $1,664,000 $997,000 $1,664,000 $997,000

    Total Construction $1,106,500 $882,000 $1,372,500 $1,140,000 $1,211,500 $1,001,000

    Total Project Cost $3,020,330 $2,082,800 $3,304,890 $2,359,360 $3,138,890 $2,215,360

    SED has presumed that the design phase could begin as early July of 2012. Depending on how this

    proceeds, construction could begin by the spring of 2013 and be completed later that summer.

    Economic Analysis: The wind turbine output predictions, current wind generated electricity value and

    total capital costs were compiled to produce unlevered pro-formas. The following chart is a comparison

    of the economic returns for the six development scenarios in a baseline economic scenario of 3.0%

    energy escalation rate, including MassCEC Design and Construction funding.

  • 8/3/2019 SED Duxbury wind feasibility report

    19/144

    S-7Draft Report

    Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Scenario Wind Turbine SitePayback(years)

    IRR 20 Year Savings

    1 PowerWind 900kW 1 9.12 9.58% $3,776,304

    2 Northwind 450kW 1 9.73 8.59% $2,194,047

    3 PowerWind 900kW 2 9.65 8.74% $3,734,911

    4 Northwind 450kW 2 10.51 7.56% $2,171,931

    5 PowerWind 900kW 3 9.17 9.51% $3,905,279

    6 Northwind 450kW 3 9.73 8.58% $2,348,763

    Each of the scenarios examined appears to have favorable economics in this baseline scenario.

    Scenarios 1 and 2 at Site 1 demonstrate the strongest economics and additional sensitivity were applied

    to each.

    Financing, Ownership and Operations: SED analyzed three different financing and ownership

    scenarios utilizing the PowerWind 900kW to demonstrate how each would benefit the Town of Duxbury in

    relation to a varying dispersal of risk. The most financially beneficial option to the Town of Duxbury would

    be to self finance the project through issuing a municipal bond. This scenario could generate significant

    energy savings, but the Town would take on the risk of developing and owning the project.

    Alternately, the opportunity for third party ownership structure for this scenario could generate long-term

    savings for the Town of Duxbury and provide very little upfront risk. A lease structure could be the most

    practical solution, as risk would be shared between the Town and a third party. In this model, the ThirdParty would develop and own the project, while the Town makes an annual lease payment, as well as

    maintenance costs in exchange for all of the electricity generated by the wind turbine. These lease and

    maintenance payments would be less than the value of energy savings and could save the Town over

    $2

    Conclusion & Recommendation: This project has many of the aspects necessary for the successful

    development of an on-site wind project. Based on the results of this study SED recommends that the

    Town proceed into the business planning phase to prepare for a decision on whether to proceed with

    design and construction in the spring 2012 Town Meeting. SED recommends that the stronger economicbenefit of installing a PowerWind 900kW justifies obtaining a variance of 26 feet on the Wind Bylaw and

    would be the best path for the Town of Duxbury to pursue.

  • 8/3/2019 SED Duxbury wind feasibility report

    20/144

    1-1Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    WIND TURBINE SITING AND ENERGY YIELD

    SECTION 1

    Appropriate and effective siting of a wind turbine is the most critical aspect of wind energy development.

    This siting assessment is a culmination of the results of numerous investigations performed and

    presented throughout this study in order to determine the optimal location and configuration for a wind

    energy development to be owned by the Town of Duxbury. A technical siting assessment must critically

    examine how a wind turbine will interact with a surrounding community and investigate all reasonable

    actions that may be taken to minimize potential negative effects while maximizing economic and

    environmental benefits for the Community.

    1.1 BACKGROUND

    A preliminary site assessment administered by the MassCEC was performed for the Town of Duxbury

    which evaluated all municipally-owned property for suitability to host a community-scale wind energydevelopment. The assessment identified municipal property near the North Hill Golf Course and Town

    Department of Public Works as the most feasible locations for wind development. The area offers ample

    space for siting a wind turbine and thereby minimizing effects to the surrounding community, and

    environmental and recreational resources on-site and in the neighboring vicinity. This area identified in

    the preliminary site assessment is the basis of further investigations for this technical and economic

    analysis for on-site wind generation.

    SED performed site visits, evaluated available property/satellite maps and applicable GIS data, analyzed

    wind resource data, and participated in discussions with Town officials and the general public in order to

    identify the most appropriate locations for a wind turbine development within this identified area, identified

    for the remainder of this study as North Hill. This siting process accounts for several considerations

    including but not limited to: regulatory and development setbacks; current land uses and classifications;

    and available site wind resource. From these details the most appropriate sites and the scale of preferred

    technology was determined. Only property owned or administered by the Town of Duxbury was

    considered within this analysis.

    1.2 NORTH HILL SITE DESCRIPTION

    The area encompassing North Hill represents the largest contiguous open space in the Town of Duxbury

    with over 1000 acres of land divided between municipal, recreational and conservation classifications.

    North Hill is predominantly wooded, with some wetlands distributed throughout. The signature

    conservation feature in the area is the North Hill Marsh Wildlife Sanctuary, a 117 acre parcel owned

    jointly by the Massachusetts Audubon Society and the Town of Duxbury, managed as part of the North

    River Wildlife Sanctuary. The sanctuary is centrally located in the North Hill area and contains the North

    Hill Pond and numerous recreation trails.

  • 8/3/2019 SED Duxbury wind feasibility report

    21/144

    1-2Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Several conservation and historic areas are designated throughout this portion of the Eastern Greenbelt,

    including the Knapp Town Forest and the Waiting Hill Preserve. In addition to the extensive network of

    recreational trails throughout, this area hosts the North Hill Golf Course (NHGC), a nine-hole municipal

    golf course managed by Pilgrim Golf, LLC. The North Hill area adjoins with the Duxbury Town Hall,

    Department of Public Works (DPW), the Senior Community Center, the Mayflower Cemetery and the

    Town Transfer Station properties. The area evaluated for wind turbine development is bordered by

    Tremont Street to the east, Mayflower Street to the south, Lincoln Street to the west and West Street to

    the north.

    Figure 1-1 North Hill Area with Property Lines

    1.3 PROPERTIES ASSESSMENT

    To determine appropriate wind turbine locations, SED first established a baseline criteria to identify whatsites would be considered:

    1. Property must be owned by the Town of Duxbury;

    2. Property must not be designated Conservation Land or Open Space;

    3. Property must have a high enough wind resource to satisfy the MassCEC funding requirement.

  • 8/3/2019 SED Duxbury wind feasibility report

    22/144

    1-3Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Utilizing maps from the Massachusetts Oliver Program1 and the Town of Duxbury GIS platform, SED

    determined the ownership and usage designation for the numerous lots within the defined North Hill area

    see Figure 1-2. Designations include Municipally Owned, Conservation, Audubon and Historical Property.

    Areas outside of the considered area consist of single family residences and some additional

    conservation and historically designated land. There are roughly 20 parcels owned by the Town of

    Duxbury within this area (see Figure 1-3). Municipal properties were also identified south of Mayflower

    Street between Round and Island Creek Ponds; these properties were not included in the preliminary site

    assessment and therefore will not be considered for this siting assessment.

    Figure 1-2 Property Designations with Legend

    In addition to Conservation Land and Open Space areas, the Knapp Town Forest, the Mayflower

    Cemetery, and the Senior Community Center property have also been excluded from consideration.

    1The MassGIS online data viewer:http://www.mass.gov/mgis/mapping.htm.

    http://www.mass.gov/mgis/mapping.htmhttp://www.mass.gov/mgis/mapping.htmhttp://www.mass.gov/mgis/mapping.htmhttp://www.mass.gov/mgis/mapping.htm
  • 8/3/2019 SED Duxbury wind feasibility report

    23/144

    1-4Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 1-3 Municipal Open-Space Properties under Consideration with Outline

    1.4 WIND RESOURCE POTENTIAL

    In order to be eligible for MassCEC funding a wind energy project requires a wind speed of at least 5.6

    m/s (12.6mph) between hub heights of 50m (164ft) and 59m (194ft) and 5.8 m/s (13mph) between hub

    heights of 60m (195ft) and 69m (226ft). To identify the available wind resource of the North Hill area an

    analysis was performed utilizing data obtained through a Virtual Met Mast (VMM) provided by AWS

    Truepower (See Section 2). This VMM data was used to generate a wind resource grid of the North Hill

    area that provides a visual representation of wind speeds at a height of 60m (195ft). The resource grid

    provides a useful tool for micro-siting wind turbines by identifying areas where electrical generation can

    be maximized based on the available wind resource. The combination of the wind resource grid with the

    identified eligible properties overlay results in several areas where the wind resource would be supportiveof a wind turbine installation.

  • 8/3/2019 SED Duxbury wind feasibility report

    24/144

    1-5Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 1- 4 Wind Resource Grid and Eligible Municipal Properties

    Properties located within the green shading of Figure 1-4 meet the minimum requirement established by

    the MassCEC; and would therefore would be best suited for siting a wind turbine based upon available

    wind resource. Of these areas, three in particular were determined to be a far enough distance from

    residential areas to minimize possible effects that a wind turbine could generate. These will be referred to

    as:

    Area 1) North Hill Golf Course

    Area 2) Kettle Hole

    Area 3) DPW West

  • 8/3/2019 SED Duxbury wind feasibility report

    25/144

    1-6Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 1- 5 Wind Resource Grid with Development Areas Identified

    1.5 SITING CONSIDERATIONSThe three areas identified were then evaluated to determine which location within would provide the most

    ideal wind resource for an economically viable wind energy project. Additional siting criteria were then

    applied to refine specific wind turbine locations and establish development options for the Town of

    Duxbury. Appropriate wind turbine siting assures minimal interference results upon nearby properties,

    existing buildings and/or residences, and allows for ease of access for construction and staging purposes.

    The following is a brief description of these considerations with respect to wind turbine development in the

    North Hill area.

    SetbacksSetbacks are used to avoid or minimize potential disturbances associated with sound and/or any

    resulting shadow flicker effect , as well as to minimize potential disruption to the surrounding area and

    natural habitat. Setbacks for residences, conservation areas and wetlands, historic areas, and recreation

    areas and trails have been considered to determine appropriate locations to site a wind turbine within a

    speicific area.

  • 8/3/2019 SED Duxbury wind feasibility report

    26/144

    1-7Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Residences and Unoccupied Buildings There are numerous residential neighborhoods

    surrounding the North Hill area that were considered throughout siting efforts; these are primarily

    located to the east and south. Industry standard setbacks based upon the scale of a proposed wind

    turbine were used to determine the appropriate setback distance (See Figure 1-6). For non-

    residential, unoccupied buildings, the standard setback employed is 1.1 times the total tip height of

    the wind turbine. Another setback metric is drawn from the MassCEC which requires the performance

    of an ambient sound study during the feasibility phase if a residence falls within 3.5 times the total tip

    height of the proposed wind turbine.

    Environmental and Recreational Resources SED consulted with a variety of resources to

    determine where these critical areas are located within the North Hill area, including but not limited to:

    the National Wetlands Inventory (NWI), MassGIS data and the Town of Duxbury GIS platform.

    The North Hill Marsh Wildlife Sanctuary is the defining feature of this area, and is therefore taken intoconsideration in relation to each of the potential sites. SED recommends consultation be initiated

    with the Mass Audubon Society, however, based upon past experience, and, that this is a single wind

    turbine project it is unlikely that the Sanctuary will experience significant impacts by the envisioned

    development.

    The North Hill area has many recreational uses and numerous trails throughout. The NHGC is a

    prominent recreational facility owned by the Town of Duxbury within proximity to the proposed

    development.

    Typical concerns associated with a wind turbine development include shadow flicker, general

    aesthetic visibility, and ice throw. Shadow flicker and visibility will be discussed in later sections.

    Icing on wind turbine blades is common in Northern areas of North America, but less likely in coastal

    regions such as in Duxbury due to the moderating effects of the ocean. Wind turbines have been

    proven to coexist with recreational and other uses and will pose little risk to the safety of existing land

    uses with proper planning and education.2 It is important however to minimize project encroachment

    on these resources in order to avoid disrupting intended activities.

    Buildabilty and Interconnection - Understanding the logistics of how a wind turbine project is built,

    including the staging area, foundation, access road construction/upgrades and interconnection is vital

    when considering how to site a wind turbine. Any obstacles associated with these could cause major

    delays or cost increases that could impact a SED examined each site

    2Hull Wind I: adjacent to the high school football field. The Massachusetts Maritime Academy: close proximity to the school. IBEW:located in the parking lot.

  • 8/3/2019 SED Duxbury wind feasibility report

    27/144

    1-8Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    host a wind turbine with consideration for the staging and foundation, site accessibility, and distance to

    points of interconnection. All sites would require construction of a 6m (20ft) wide paved access road to

    allow for the transport of components.

    Permitting Implications SED strives to work closely with clients, permitting authorities and

    environmental advocacy groups to support smart community wind development. The many benefits this

    type of development can bring are presented to all interested parties and all efforts are made to address

    reasonable concerns associated with a wind turbine installation, particularly regarding construction near

    sensitive areas. Permitting for a wind turbine at any of the proposed locations would require approvals

    and or review at the federal, state and local levels.

    Local Town of Duxbury local bylaws limit the overall scale and generating capacity for a

    community-scale wind facility, largely due to the existing cap on the height of a wind turbine,

    currently set at 250ft. The bylaw establishes a minimum setback distance equal to 1.1 times theoverall height of the wind turbine from the nearest property line and private or public way; and a

    minimum setback distance equal to 2 times the overall height of the wind facility from the nearest

    existing residential or commercial structure not owned by the applicant. The bylaw does however

    allow the setback zone for Community-Scale Wind Facilities and or Wind Monitoring or

    Meteorological Towers to fall within the limits of a Wetlands Protection Overlay District, and/or a

    Flood Hazard Overlay District.

    State Sites 1 and 2 are located within a Priority Habitat Area, which triggers review by the

    Massachusetts Department of Natural Heritage. Due to the scale of the wind turbine and limitedarea that would be disturbed by construction, and the close proximity of the previously disturbed

    nature of the existing golf course, this is not considered a fatal flaw to development.

    Federal FAA approval will be a limiting factor in the scale of a wind turbine development. A

    Notice of Presumed Hazard (NPH) for Site 1 has been issued and will limit the overall height of a

    wind turbine based upon proximity to the Marshfield Airport and is considered representative of

    the other 2 sites evaluated. The Not-to-Exceed Height is 317 feet (97m). The wind turbines

    examined in this technical assessment would/would not exceed this limit. Appendix D: FAA NPH?

    Wind Turbine Technology

    SED actively performs technical reviews of wind turbine technologies with particular attention to their

    compatibility with the distributed wind energy market. SED works with specific technologies in sizes

    ranging from 10kW to 2MW, constantly reevaluating and updating the systems employed based on

  • 8/3/2019 SED Duxbury wind feasibility report

    28/144

    1-9Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    availability, cost competitiveness, performance and overall reliability. Employing a proven wind turbine

    technology is crucial for the successful planning, development and operation of a wind energy project.

    Much of the advances in wind turbine technology over the past decade have been geared towards

    making larger technologies for utility-scale wind farm development. The big players such as GE, Vestas

    and Gamesa have put their resources towards boosting production and capacity for these technologies

    larger than 1MW. During this time, community wind developers have had to rely on older technologies in

    the 100kW to 1MW range such as the Turbowinds 400kW, the RRB 600kW or Norwin 750kW just to

    name a few. Most of these technologies are manufactured by other firms that have bought the rights to

    these technologies and have made very few improvements. The benefit of these machines is that they

    are proven and reliable, but the technologies have become outdated.

    A shift is taking place though as smaller manufacturers recognize the potential of mid-scale wind turbines

    in the community wind market. These firms are scaling down some of the advancements made in theutility-scale market to improve capacity factors, reliability and cost effectiveness. Examples include

    permanent magnet generators that can cut down on maintenance costs or larger rotor diameters that

    provide greater output in lower wind speeds. SED is working with several manufacturers at the forefront

    of these upgrades to ensure that our clients are provided with most advanced technologies from firms like

    Northern Power Systems and PowerWind that will improve economics and reliability. These will be the

    technologies that take community wind into the future.

    The Northern Power 450kW wind turbine is a mid-scale technology currently installed for testing

    at the National Renewable Energy Laboratory in Colorado. This technology is based on thedesign of the highly successful Northern Power 100kW. This wind turbine is a gearless direct

    drive machine that utilizes permanent magnet technology thus reducing the number of moving

    parts and wear items. The wind turbine has a rotor diameter of 48m and will be available with a

    hub height of 50m or 65m. The first commercial versions of this wind turbine will be available in

    mid-2012. The 50m tower will be the option investigated in this feasibility study that will meet not

    exceed the Town Bylawcurrent height restriction.

    The PowerWind 900kW is the best mid-size wind turbine technology available on the market

    today based on its performance and reliability history. The PowerWind 900kW is a horizontal axis

    wind turbine available on a 59m or 71m steel, tubular tower with a rotor diameter of 56m or 60m.

    The 56m rotor would be employed for the Town of Duxbury, as the Town of Duxbury is an

    International Electrical Commission (IEC) Class II wind regime meaning that the 10-minute

    average maximum 50-year extreme wind speed in this area is at least 95 mph. The 60m rotor is

    designed for a Class III and would not meet the IEC standards for this region. It provides

  • 8/3/2019 SED Duxbury wind feasibility report

    29/144

    1-10Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    significant power production (65% of the 1.5MW class); lower construction costs; and much lower

    long term maintenance and operation costs than utility scale (1 MW or larger) wind turbines.

    Both of these wind turbines also possess the functionality to prevent ice shedding during major icing

    events, while minimizing downtime associated with these events. Ice buildup on each blade is measured

    to determine the conditions that would require the wind turbine to be shutdown, which is done through

    analysis of natural oscillation frequencies of the blades which will change during icing events. The

    system will shut down the wind turbine automatically in these events and also restart whenever the

    conditions improve.

    With consideration for and airspace restrictions from the FAA, SED focused

    investigations on the Northern Power 450kW on a 50m tower and the PowerWind 900kW on a 59m

    tower. While overall, the height of the PowerWind 900kW does Bylaw, the economic

    returns are stronger a a variance for this height restriction.

    Figure 1-6 Wind Turbine Technologies

    Wind Turbine

    & Rated

    Capacity

    Tower

    Height

    Rotor

    Diameter

    Total Tip

    Height

    Bylaw

    Setback

    from

    Residential

    Buildings

    MassCEC

    Ambient

    Sound Study

    Setback

    Industry

    Recommended

    Setback from

    Residential

    Buildings

    Northern

    Power 450kW

    50m

    (164ft)

    48m

    (157ft)

    74m

    (243 ft)150m (492ft) 259m (851ft) 244m (800ft)

    PowerWind

    900kW

    59m

    (194ft)

    56m

    (184ft)

    87m

    (276 ft)175m (574ft) 305m (1000ft) 305m (1000ft)

    1.6 SELECTED SITE EVALUATIONS

    Area 1 - North Hill Golf Course The North Hill Golf Course (NHGC) is located on relatively flat terrain

    above the North Hill Marsh area. SED did not consider siting the wind turbine within the confines of the

    NHGC as a suitable option, so as to minimize disruption to the course during construction. When

    considering the wind resource, the most suitable location appears to be in a thinly forested area south of

    the 8th hole green and 9th hole tee that sits at an elevation of 24m (79ft).

  • 8/3/2019 SED Duxbury wind feasibility report

    30/144

    1-11Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 1-7 Site 1 NHGC with Setbacks

    Residences and Unoccupied Buildings The proposed site is south and east of nearby residential

    areas. The closest residential property line is 396m (1300ft) west, with the closest residential building442m (1450ft) north, both of which are associated with 72 Hounds Ditch Lane. There is also a facility

    owned by the Duxbury Housing Authority north of the Club House at 75 Merry Ave which is 427m

    (1400ft) from the proposed site. The closest non-residential building is the North Hill Club House, 396m

    (1300ft) north of the proposed turbine site.

    Environmental and Recreation Areas - The proposed wind turbine site is 177m (580ft) from the North

    Hill Marsh Wildlife Sanctuary. There are wetland areas 76m (250ft) southwest and 146m (480ft)

    southeast, both classified as Freshwater Forested Wetlands.

    The proposed site would be within 30m (100ft) of the NHGC and 60m (200ft) from the North Hill Marsh

    Pond Loop, a hiking trail that encircles the marsh. SED does not believe that these resources will be

    adversely impacted by the presence of the wind turbine.

    Buildability and Interconnection The proposed site would be accessed along the eastern edge of the

    NHGC driving range. This route will require the construction of a suitable access road from the NHGC

  • 8/3/2019 SED Duxbury wind feasibility report

    31/144

    1-12Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    parking lot. The proposed location is relatively flat and has the necessary room, roughly one acre, to

    support the wind turbine installation and staging area for the crane and other components. The clearing of

    approximately 1/3 acre would be necessary to construct the access road and prepare the site for staging,

    which will require use of the area between the 8th and 9th holes.

    The existing electrical infrastructure at the NHGC and at the DPW is not substantial enough to handle a

    behind the meter interconnection without significant modifications and upgrades. SED therefore

    recommends that the wind turbine be interconnected directly into the existing distribution circuit near the

    Club House as a new service and account.

    Permitting Implications The proposed site meets setback

    Wind Bylaw. The site is located within a Priority Habitat Area, which triggers review by the

    Massachusetts Natural Heritage & Endangered Species Program (NHESP), but due to the scale of the

    wind turbine, the limited area that will be disturbed by construction, and the close proximity to thepreviously disturbed nature of the golf course, this is not considered a fatal flaw. The only identified

    federal implication is FAA approval based upon proximity to the Marshfield Airport four miles away.

    Recommendation the North

    Hill Golf Course Site - Site 1 - is suitable for a wind turbine development. Based on the site characteristics

    and setbacks, a PowerWind 900kW or Northwind 450kW could be appropriately sited here. SED does

    not anticipate a wind turbine will adversely impact recreational activities at the golf course or other trails in

    the North Hill area. The wind turbine could co-exist with the golf course and has potential to become a

    signature feature of the NHGC that would draw golfers from around the region.

    Area 2 Kettle Hole This area is located between the Pond Loop Trail and Kettle Hole Trails. The

    highest elevation within this area is 27m (90ft), and is centrally located within the parcel, which would

    make it an ideal location for a wind turbine.

  • 8/3/2019 SED Duxbury wind feasibility report

    32/144

    1-13Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 1-8 Site 2 Kettle Hole with Setbacks

    Residential and Unoccupied Building Setbacks The proposed site is centrally located within theNorth Hill Area and there are no residences or unoccupied buildings nearby. The closest residences are

    518m (1700ft) to the northeast and south. The closest non-residential building is the NHGC club house

    762m (2500ft) north.

    Conservation Areas and Wetlands - The proposed site sits between an unnamed Conservation Area

    and the Mass Audubon North Hill Marsh Wildlife Sanctuary, at 91m (300ft) and 113m (370ft) respectively.

    The closest wetland is 91m (300ft) east and is a Freshwater Forest Wetland. However, no wetland areas

    would be disturbed during an installation at this site.

    A wind turbine at the proposed site will not encroach upon any major trails within the North Hill area. The

    closest trail is the Pond Loop Trail 137m (450ft) west and Kettle Hole Trail 198m (650ft) east.

    Consultation with the local historic commission is recommended since a section of the Pond Loop Trail on

    the east side of the M

    connected the Towns of Plymouth and Marshfield.

  • 8/3/2019 SED Duxbury wind feasibility report

    33/144

    1-14Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Buildability and Interconnection The site access would be from the NHGC. An entirely new access

    road over 1067m (3500ft) in length would need to be constructed, likely originating at the NHGC parking

    lot and continuing through the Town Dumping Area. This route would require crossing some trails, but

    identified wetlands and Conservation Lands could be avoided. A wetland delineation survey would be

    needed for a development at this location. The project area itself is relatively flat. Clearing of at least one

    acre for the foundation and staging area would be required; the access road would result in an additional

    1.5 acres of cleared land.

    Interconnection would be costly due to a long wire run and would follow the same route as the access

    road with an interconnection scheme similar to that recommended for Site 1.

    Permitting Implications A wind turbine at the proposed site meets the setback requirements

    Wind Bylaw. Based upon the scale of proposed clearing and the disturbance

    of greater than one acre, National Pollutant Discharge Elimination System (NPDES) coverage will berequired. For the State of Massachusetts, the EPA is the permitting authority for the NPDES.3 The federal

    implication of FAA approval remains based upon proximity to the Marshfield Airport four miles away.

    Recommendation Based on the demonstrated characteristics, it Kettle

    Hole Site - Site 2 - is suitable for a wind turbine development utilizing a Northwind 450kW or PowerWind

    900kW. Siting however, will add significant costs to the overall project due to the length of wire run and

    access upgrades to be required. The amount of clearing necessary for the staging area and the

    construction of an access road could pose an obstacle to development.

    Area 3 DPW West This area is located west of the Duxbury Town Hall and DPW yard and is

    predominantly forested and interspersed with some recreational trials. The highest point and prime

    location for siting a wind turbine within the area is approximately 27m (90ft) above sea level.

    3Applicants for National Pollutant Discharge Elimination System (NPDES) permits covering new or expanded industrial project

    construction must submit information on the proposed construction. The information must describe the proposed or expandedprocess and its relationship to the existing facilities. The EPA will use the information to determine if new source performancestandards (NSPS) apply to the new construction. The New Source Determination (NSD) establishes whether or not the proposedconstruction is subject to environmental assessment under the National Environmental Policy Act of 1969, as amended (NEPA).These regulations and definitions are found in Sections 306 and 511(c) of the Clean Water Act and 40 CFR Parts 6, 122.2, and122.29.

  • 8/3/2019 SED Duxbury wind feasibility report

    34/144

    1-15Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 1-9 Site 3 DPW West with Setbacks

    Residential and Unoccupied Building Setbacks The closest residential areas are to the north and

    east of this proposed location. The closest residential property and residential building is at 102 Hounds

    Ditch Lane, 366m (1200ft) and 405m (1330ft) to the northeast, respectively. The DPW Yard and Town

    Hall are over 457m (1500ft) away from this site. The Duxbury First Parish Church is 548m (1800ft) east

    of the proposed site.

    Conservation Areas and Recreational Resources - The proposed site is 213m (700ft) away from two

    unnamed Duxbury conservation areas that contain wetlands; these would not be disturbed at the

    proposed location. The proposed site would pose little threat to recreation areas however trails in the areawould be crossed by the creation of an access road. The closest trail is a connector trail 30m (100ft) to

    the north.

    Buildability and Interconnection The proposed location would require the construction of an access

    road originating at the DPW yard and extending 457m (1500ft). The proposed location is relatively flat

    and has the area needed, roughly one acre, to support the wind turbine installation and staging area for

  • 8/3/2019 SED Duxbury wind feasibility report

    35/144

    1-16Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    the crane and other components. Interconnection costs would be high due to the wire run and would

    follow the same route as the access road. The wind turbine would be interconnected at the DPW yard

    onto the existing 23kV overhead circuit owned by NSTAR.

    Permitting Implications The proposed site would meet the setback requirements established by the

    Wind Bylaw. The site is not located within a Priority Habitat Area. Based upon the scale of

    proposed clearing and the possible disturbance of greater than one acre, National Pollutant Discharge

    Elimination System (NPDES) coverage would likely be required. The federal implication associated with

    FAA approval proximity to the Marshfield Airport four miles away still remains.

    Recommendation Based on the demonstrated characteristics, it is

    would be suitable for wind development. However this site would add significant costs to the overall

    project based upon the length of wire run and access upgrades required. The site could support a wind

    turbine up to the 900kW scale, providing the Town Bylaw allows for a variance regarding the heightrestriction currently in place, as a 900kW would exceed the maximum allowable height.

    1.7 FINAL SCENARIO RECOMMENDATIONS

    SED has identified three possible sites that would be appropriate options for siting a wind turbine within

    the Town of Duxbury. The locations are titled: Site 1-North Hill Golf Course (42.042803, -70.701576);

    Site 2 - Kettle Hole (42.039523, -70.702537); and Site 3 - DPW West (42.037655, -70.698261).

    Each potential site presents its own benefits and obstacles to development that should be carefully

    stands out as the most developable location due to its accessibility and available area for staging both of

    which act to limit total project costs. The proximity of the wind turbine to the golf course will require some

    additional planning and outreach, but SED does not consider that this will be a detriment to the golf

    course but rather a potential opportunity to market the green credentials of the golf course and attract a

    broader base of recreationists.

  • 8/3/2019 SED Duxbury wind feasibility report

    36/144

    1-17Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 1-10 Recommended Wind Turbine Locations

  • 8/3/2019 SED Duxbury wind feasibility report

    37/144

    2-1Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    SECTION 2

    WIND RESOURCE ASSESSMENT AND TURBINE OUTPUT MODELING

    In order to calculate the anticipated Annual Energy Production (AEP) of the wind turbine for the Town of

    Duxbury, SED used the wind industry standard modeling tools Wind Atlas and Application Program

    (WAsP), created by the Danish National Laboratory along with WindPRO, created by EMD International

    A/S. WindPRO is used for creating the model and reports and the WAsP program is used by WindPRO

    for the wind flow calculations. For this analysis, SED input model data from the selected wind turbines

    and potential sites. A single PowerWind 56 900kW wind turbine with a hub height of 59m (193.5ft), and a

    rotor diameter of 56m (183.7ft); along with a single Northwind 450kW wind turbine with a hub height of

    50m (164ft), and a rotor diameter of 54m (177ft) were explored at three potential sites.

    2.1 WIND TURBINE SELECTION AND OUTPUT CALCULATION

    SED selected the PowerWind 900kW wind turbine for this project as they are highly reliable, currently electricity consumption.

    The Northwind 450kW wind turbine offers a smaller alternative option to the PowerWind with the

    . To determine the

    output of the wind turbines at each individual site, SED used the industry standard wind modeling

    software, WAsP. The model was created by licensed and certified user: Scott Abbett, SED, USA using

    WAsP version: 9.00.0153 and certified user Bill Court, SED, USA using WindPRO version 2.7.473.

    In order to accurately calculate the output of the wind turbine at the Town of Duxbury, the WAsP and

    WindPRO models considered:

    A full year Virtual Met Mast (8760 hours) of wind data provided by AWS Truepower4

    The turbine sites located at: (UTM Zone 19, WGS84)

    o Turbine Site 1 NHGC 359186.0 E, 4655940.0 N

    o Turbine Site 2 Kettle Hole 359085.0 E, 4655567.0 N

    o Turbine Site 3 DPW West 359435.0 E, 4655353.0 N

    A terrain map of the USGS 7.5 minute Quadrangle-Duxbury, MA

    A roughness map for the USGS 7.5 minute Quadrangle-Duxbury, MA

    The power curve of the PowerWind 56 900 kW wind turbine with a 56m (183.7ft) rotor diameter

    and a 59m (193.5ft) hub height

    The power curve for the Northwind 450 kW wind turbine with a 54m (177ft) rotor diameter and a

    50m (164ft) hub height.

    4 AWS Truepower LLC based out of Albany, New York is an international leader and innovator in renewable energy technologyapplications, advanced atmospheric modeling and measurement, and engineering services for over 25 years.

  • 8/3/2019 SED Duxbury wind feasibility report

    38/144

    2-2Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    2.2 VIRTUAL MET MAST INFORMATION

    SED contracted AWS Truepower of Albany, NY, to provide a Virtual Met Mast (VMM) data set, comprised

    of a full year (8760 hours) of wind speed and direction data, for a location on the Town of Duxbury

    property. Data from this VMM was then imported into WindPro in order to tabulate average wind speed

    and direction data. AWS Truepower provides the following description of their VMM Product:

    A Virtual Met Mast produces a representative calendar year of hourly wind speed, direction,temperature, atmospheric pressure, air density, and energy output. It is produced by makingmultiple refinements to coupled mesoscale and microscale model output, and then, using anestimated wind profile for the chosen site, scaling this data to a particular height (e.g. 40m). Thus,a complete climatology of typical conditions expected at the selected height above ground iscreated

    mesoscale numerical weather model that resolves atmospheric phenomena at scales down to 1

    3 km, establishes the general patterns of wind and weather in a region. These patterns reflect theinfluence of terrain, vegetation, oceans and lakes, solar heating, radiative cooling, convection,and many other factors. With output from MASS, MesoMap, a microscale wind flow model, isthen used to assess the wind resource at a higher resolution (typically 50 - 200 m, or grid sizes offrom less than 1 acre to about 10 acres). Existing long-term meteorological data is then used toverify output from MesoMap.

    Figure 2-1 VMM Information

    Data Source AWS Truepower

    Height 50m & 70m

    Location 359450.0 Easting (UTM -

    WGS84)

    Location 4655446.0 Northing (UTM

    - WGS84)

    Site Elevation 22m

    Mean Wind Speed at 70m AGL

    Mean Wind Speed at 50m AGL

    6.18 m/s

    5.68 m/s

    Figure 2-1 provides a graphical representation of the WindPRO wind speed and direction in the form of

    Wind Roses and Weibull Distribution for the 70m (229.6ft) VMM wind data. The Wind, Frequency and

    Energy Roses describe wind direction, frequency and quantity of wind and turbine generated power from

    each direction. It should be noted that in Figure 2-2 the energy rose is blank as it needs an associated

    power curve in order to convert wind data to energy production. As depicted, the wind at the met mast

    location is most frequently experienced at the southwest sectors. The Weibull Distribution (top left) is a

    description of the number of hours in a year where certain wind speeds will exist at the meteorological

  • 8/3/2019 SED Duxbury wind feasibility report

    39/144

    2-3Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    tower location. A similar distribution is used in conjunction with the wind turbine manufacturer-supplied

    power curve to determine the gross electrical output from a wind turbine at a particular site.

    Figure 2-2 70m VMM Wind Roses (Bottom) and Weibull Distribution (Top Left)

    2.3 TERRAIN AND ROUGHNESS MAPS

    WAsP and WindPRO use terrain and roughness maps to accurately determine the way the wind flows

    over the identified site. These maps are input into the model in order to calculate the local site effects.

    The terrain map is a topographical representation of the area using 6.096m (20ft) contour lines. The

    roughness map is a representation of the surface roughness and/or ground cover in the surrounding area

    based on the WAsP roughness classification system. The area was modeled using a 23,500m (77,099ft)

    by 23,750m (77,919ft) digital elevation model around the Town of Duxbury sites. The terrain map comes

    directly from the US Geological Survey and the roughness map used in this model was obtained from

    AWS Truepower.

    2.4 WIND TURBINE POWER CURVES

    In order for the WAsP and WindPRO models to work properly it is important to have an accurate power

    curve for the turbine being considered for the project. A power curve indicates how much power the

  • 8/3/2019 SED Duxbury wind feasibility report

    40/144

    2-4Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    turbine will produce at different wind speeds. For this model, SED used the power curve for the

    PowerWind 56 900 kW wind turbine with a 56m (183.7ft) rotor diameter along with the power curve for a

    Northwind 450 kW wind turbine with a 54m (177ft) rotor diameter. The wind turbine manufacturer

    provided the technical specifications needed to input the power curves into WindPRO. Figures 2-3 and 2-

    4 are visual representations of the power curves for the PowerWind 56 900kW and Northwind 450kW

    respectively as shown in WindPRO.

    Figure 2-3 PowerWind 56 900kW Manufacturer Supplied Power Curve

  • 8/3/2019 SED Duxbury wind feasibility report

    41/144

    2-5Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 2-4 Northwind 450kW Manufacturer Supplied Power Curve

    SUMMMARY OF MODEL RESULTS

    Once all of the data inputs were completed, the WindPRO model was run with the PowerWind 900 kW

    turbine and the Northwind 450 kW wind turbine at the identified locations. Figure 2-5 is a summary of the

    results of this model.

    Figure 2-5 Summary of Model Result

    Site Identification Location [UTM, WGS84] TurbineHeight

    [m]Wind Speed at

    Hub (m/s)Net AEP[MWh]

    Site 1 359186.0E, 4655940.0N PowerWind 900 59 5.82 m/s 1,830.4

    Site 1 359186.0E, 4655940.0N Northwind 450 50 5.48 m/s 1,167.5

    Site 2 359085.0E, 4655567.0N PowerWind 900 59 5.89 m/s 1,892.1

    Site 2 359085.0E, 4655567.0N Northwind 450 50 5.61 m/s 1,234.4

    Site 3 359435.0E, 4655353.0N PowerWind 900 59 5.91 m/s 1,893.3Site 3 359435.0E, 4655353.0N Northwind 450 50 5.64 m/s 1,243.0

  • 8/3/2019 SED Duxbury wind feasibility report

    42/144

    2-6Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    2.6 FINAL TURBINE OUTPUT CALCULATIONS

    WAsP calculates turbine output assuming that the wind turbine is available 100% of the time and that

    100% of the power produced by the generator makes it into the grid or is otherwise consumed on-site.

    Realistically, a wind turbine experiences downtime for various reasons and not every single unit of power

    -site. The following are

    considerations used in WindPRO determining how much power a wind turbine will actually supply.

    Assumed Availability: This assumed figure is based on generally accepted performance history for

    wind turbine size classes and is the percentage of time that the wind turbine would be in working

    condition. This figure takes into account the downtime for scheduled maintenance activities and assumes

    that the wind turbine is properly cared for and maintained by professionals.

    Electric Line Losses: The power generated at the turbine needs to run through a certain distance of

    electric lines and two different transformers before it connects to the grid or is consumed at a facility.Through these conversions, a portion of power will be lost.

    General Losses: This category includes downtime due to icing, other weather related events such as

    high wind speed events and unscheduled maintenance.

    Grid Failure: Without the electrical grid operating normally, a wind turbine cannot produce power

    because it is a synchronous/induction generator that initially requires electricity to generate its own

    electricity. Grid failure takes into account the time when the electrical grid is down due to scheduled or

    unforeseen events.

    Figure 2-6 Assumed LossesAssumed Availability (98%) 2.0%

    Electric Line Losses 2.0%

    General Losses 2.5%

    Grid Failure 1.0%

    Total Losses 7.5%

    Therefore the power produced by a turbine as calculated by WindPRO needs to be reduced by 7.5%.

    Figure 2-7 shows the remaining calculations to determine power output of the wind turbines that were

    examined for the Duxbury site. The final values used for turbine output are shown in bold.

  • 8/3/2019 SED Duxbury wind feasibility report

    43/144

    2-7Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 2-7 Final Output Calculations

    Site Turbine Rated PowerGross AEP from

    WindPRO (MWh/yr)

    Final net AEP after

    losses (MWh/yr)

    Site 1 PowerWind 900 kW 1,830.4 1,693

    Site 1 Northwind 450 kW 1,167.5 1,080Site 2 PowerWind 900 kW 1,892.1 1,750

    Site 2 Northwind 450 kW 1,234.4 1,142

    Site 3 PowerWind 900 kW 1,893.3 1,751

    Site 3 Northwind 450 kW 1,243.0 1,150

  • 8/3/2019 SED Duxbury wind feasibility report

    44/144

    3-1Final Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    INTERCONNECTION INVESTIGATION

    SECTION 3

    SED analyzed the existing electrical supply facilities, and the necessity for modifications associated with

    interconnecting one (1) 450kW or one (1) 900kW to the utility grid at the Site 1 - NHGC.

    3.1 RECOMMENDED INTERCONNECTION PLAN

    Based on an analysis of the existing electrical facilities, consultation with Mr. Rich Gross P.E., and SED's

    experience with similar wind turbine projects, an interconnection plan has been developed for proposed

    turbine Site 1. Due to the similarity in approach for interconnecting a 450kW or a 900kW wind turbine, a

    single plan has been developed and the minor differences based on wind turbine size are noted within the

    plan. recommendations will minimize interconnection costs while maintaining the integrity of the

    existing town and utility owned electrical systems.

    Existing Conditions

    The primary electrical feeder for NHGC is a three-phase, 23kV overhead distribution circuit owned by

    NSTAR5. The 23kV overhead circuit extends from West Street, up Merry Avenue, to a riser pole located

    adjacent to the NHGC parking lot entrance and beside a gravel road leading to the NHGC maintenance

    facilities. The circuit continues underground to a 150kVA transformer located adjacent to the maintenance

    building at the west end of the course. The Club House appears to be electrically fed by a single phase

    line originating from the three-phase 23kV overhead circuit. The single-phase circuit follows the northern

    edge of the parking lot and terminates after approximately three spans at a pole north-east of the Club

    House.

    Interconnection Plan

    The recommended interconnection plan includes all of the necessary protective equipment (relays and

    disconnects) and interconnection of the wind turbine into the existing three-phase 23kV overhead circuit

    currently feeding the golf course. The 690 Volt out-23kV by a new,

    1000kVA three-phase transformer for a 900kW, or 500kVA three-phase transformer for a 450kW (located

    at the base of wind turbine); transferred below ground approximately 2100ft via three, 1/0 AWG,

    aluminum cable, under the parking lot and to a new riser pole located off the western side of the Club

    House. The circuit will then be transferred over-head via three, 1/0 AWG, aluminum cable and

    interconnect into the exiting three-phase 23 kV overhead circuit at NSTAR Pole # 459/9 located south-

    west of the golf course parking lot. New poles for transferring the overhead circuit and for locating

    protection and metering equipment will be installed between the new riser pole and existing NSTAR Pole

    5 NSTAR is a Massachusetts based electric and gas utility

  • 8/3/2019 SED Duxbury wind feasibility report

    45/144

    3-2Final Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    #459/9 as needed. Mr. Gross has developed a conceptual one-line for the proposed interconnection

    approach for both the 900kW and 450kW wind turbines.

    Since the generator will not be connected behind an existing service account, new service will be required

    and a new account created with NSTAR for the turbine circuit. In addition, a new four quadrant meter will

    be installed as well as any utility required protection equipment, such as a recloser and/or fused cut-outs,

    deemed necessary by NSTAR.

    Interconnection for Proposed Turbine Sites 2 and 3

    The interconnection of turbines placed at the proposed turbine locations 2 or 3 will be very similar to the

    approach described above. A turbine at Site 2 will interconnect at the same location as described above

    for Site 1 and with identical protection equipment. The wire run, however, will increase from approximately

    1700ft to 2900ft due to the increased distance from the proposed point of interconnection at the golf

    course. A wind turbine at Site 3 will include all the same protection and electrical components asdescribed above but instead would interconnect into the existing three-phase 23kV over-head circuit

    located at the DPW facility. The DPW buildings are fed by the same distribution circuit as the NHGC. As

    with interconnection at the golf course, due to the size of the proposed generators and the capacity of the

    existing electrical infrastructure at the DPW, it is recommended that the wind turbine be directly

    connected into the existing 23kV distribution circuit and considered a new service account with NSTAR.

    3.2 NEXT STEPS

    During project design, an Interconnection Application will be filed with NSTAR for the proposed

    interconnection approach. NSTAR will perform an initial review of the requested interconnection and willdetermine if the request can proceed under the Expedited or Standard Process based on set screening

    criteria. The ability to proceed under the Expedited Process depends on the size of the generator,

    component certifications (IEEE, UL, etc), condition

    associated impact of interconnecting the generator onto the distribution circuit. Costs associated with the

    interconnection process have been included in the Capital Costs in Section 8 of this report. During the

    interconnection application process system modifications, additional reviews or studies may be found to

    be necessary, but these are not reflected in the costs provided as part of this study.

    A detailed description of the interconnection process can be found in

    effective date October 1, 2009 and is available on the NSTAR website.

  • 8/3/2019 SED Duxbury wind feasibility report

    46/144

    4-1Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    WIND GENERATED ELECTRICITY VALUE

    SECTION 4

    The value of electricity generated by a wind turbine will play a significant role in determining the final

    configuration for a wind project owned by the Town of Duxbury. Wind generated electricity values for

    municipalities significantly improved when net metering provisions were enacted and will now allow theTown of Duxbury to aggregate and offset municipal loads with power produced from a single wind turbine

    project, for multiple meters under the same distribution company and located in the same ISO-NE load

    zone (also known as virtual net metering). This legislation will allow the Town of Duxbury to utilize all of

    the electricity produced by a wind turbine installation to offset electricity use of any Town owned

    accounts.

    4.1 TOWN OF DUXBURY ELECTRICITY DATA

    In order to determine the value of a wind energy generating facility for the Town of Duxbury, SED first

    examined cumulative consumption data for all Town-owned accounts. Conservatively, SED has assumed

    that electrical usage for the Town will not change significantly from its current level over the projected

    lifespan of a wind turbine. Figure 4-1 shows the total electricity consumption of approximately 70 Town

    accounts for the 12 months leading to December of 2009 6. Town accounts are billed at several rate

    classes for various meters; the most commonly experienced rate for the largest Town accounts include:

    33-GeneralAnnual and 84-SEMA Medium General TOU. This will prove significant if the wind generated

    electricity is used to offset usage for specific accounts. For 2009, Duxbury utilized in excess of 5 million

    kWh across all facilities. Based on an analysis of the provided electricity bills, SED determined the total

    electricity usage for the Town, as well as the average retail electricity cost per kWh. Figure 4-1 is amonthly break down of electricity usage across all town accounts for the year 2010.

    6 The Town provided copies of electricity bills reflecting annual usage for approximately seventy Town metered electricity accounts;while dates vary slightly from account to account, the overall cumulative data provides an overall representation of the electricityused by the Town for the year 2009.

  • 8/3/2019 SED Duxbury wind feasibility report

    47/144

    4-2Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    Figure 4-1 12-Month Electric Usage Data (kWh)

    Month Consumption (kWh)

    January 468,508

    February 483,166

    March 462,166

    April 425,997

    May 444,978

    June 408,385

    July 347,257

    August 386,505

    September 423,415

    October 441,819

    November 458,698

    December 488,100

    Total 5,238,994

    Of these 70 accounts, there are 10 that represent 80% of the total usage in the Town of Duxbury. These

    include but are not limited to the High School, Intermediate School, Town offices, Senior Center, library,

    fire station, pool, police station, water department, pump stations, town lighting, and traffic signals (Figure

    4-2).

    Figure 4-2 Ten Largest Electric Accounts in Town of Duxbury.

    Account Name2010 Electric Usage

    (kWh)

    Duxbury High School 1,244,320

    Chandler School 618,971

    Duxbury Middle School 616,000

    Alden 515,090

    Duxbury Free Library 322440

    Off Evergreen 236,640

    Tremont St. 168,240

    Percy Walker Pool 150,400

    10 Mayflower 132,400

    Wright 115,760

  • 8/3/2019 SED Duxbury wind feasibility report

    48/144

    4-3Draft Report - Technical Analysis for On-Site Wind Generation for the Town of Duxbury

    4.2 GREEN COMMUNITIES ACT AND NET METERING

    In 2008, the Green Communities Act, which contained legislation to significantly expand net metering in

    Massachusetts, was signed into law. The passage of this legislation and its implications on net metering

    has made Massachusetts a national model for stimulating the expansion of on-site renewable energy

    generation. Under these regulations, customers are classified into tiers based on the size of their

    electricity generator (under 60kW, between 60kW and 1MW, or 1MW to 2MW per unit). Any of the wind

    turbine sizes contemplated in this Study for the Town would be categorized as a Class II Net Metering

    Facility. Net metering allows customers with their own electricity generation capabilities to quantify the

    flow of electricity through the use of a bi-directional meter. Net metering allows th

    generation to be allocated by the utility to other Town-owned facilities or through payment of net metering

    credits and the utility is required to purchase or provide value for this excess energy. The rate that the

    utility is required to purchase the excess electricity does not include the demand side management or

    energy conservation charge (ECC), or the renewable energy charge (REC).

    In late 2010, the Massachusetts Department of Public Utilities (DPU) adopted an amended definition for

    "a net metering facility of a municipality or other governmental entity.

    is eligible for up to a 10 MW net metering, so long as the individual project does not exceed 2MW. Based

    upon this new definition, a net metered wind facility must be owned by the Town, must be either a Class II

    or Class III facility, or the Town must utilize all of the output of the facility. Based upon the annual

    consumption data provided, the Town will easily be able to utilize all of the energy produced by the two

    technologies contemplated in this Study. Based on the anticipated load and newly enacted net metering

    regulations, the Town could pursue a project up to 2MW in size.

    4.3 CALCULATING NET METERED CREDITS

    Interconnecting a net metered wind turbine for the Town of Duxbury will be governed in this case by the

    Metering Credit as determined in Section 1.06 (1) of the M.D.P.U. No. 163. For a Class II municipally

    owned net metered facility credits will be equal to the product of excess kWh, by time-of-use if applicable,

    in a billing period (monthly), that is aggregated over a period of a year. The net excess generation will be

    monetized and Net Metering Credits will be calculated based on the excess kilowatt hours (kWh)

    the Utility distribution charges, which include the default service kWh charge, distribution kWh charge,

    transmission kWh charge and transition kWh charge. Net Metering Cred