sectioniifb.pdf
TRANSCRIPT
-
1
TEDER O. MSETCL/CO/TR.PROJECT/TKC-II/EW SUBST/2008-09/0804
SPECIFICATIO O. MSETCL/CO./TR.PROJ/TKC-II/EW SUBST/2008-09/05
IVITATIO FOR BIDDIG (IFB)
(LOCAL COMPETITIVE BIDDIG)
1.0 Sealed offers in TWO bid system ( Technical & Commercial bid and Price bid) are invited from Local bidders meeting the qualifying requirements specified in the Bid
Documents for executing the following works on turnkey basis.
Sr. Name of Name of Sub-
Stn. Scope of work Esti. Cost period of completion No. Package In Rs lacs
PKG 'A'
A'BAD ZONE 220kV-2 Bus
1 220kV Patoda a)220/33kV T/F 2x50 MVA with bays 2042.75
12 months
from
LOA.
Dist: Beed b)220kV line bays - 4 nos.
(2008-09) - 2 nos. at Beed S/S (end bays)
- 2 nos. at Patoda S/S
c)33kV outlets - 12 nos.
2 132kV Badnapur 132kV-2 Bus 1236.14
Dist:Jalna a)132/33kV, 25 MVA - 2 nos with bays
(2008-09) b)132kV line bays - 2 nos
c)33kV outlets - 8 nos
3 220kV Bhokardhan 220KV-2 Bus, 132kV-2 Bus 3598.92
Dist:Jalna a)220/132kV ICTs, 2x100 MVA &
(2008-09) 220/33kV, 2x25MVA with bays
b)220kV line bays - 4 nos
- 2 nos. at Bhokardhan S/S
-2 nos. at 220kV Savangi S/S(end bays)
c)132kV line bays - 6 nos
- 3 nos. at Bokhardhan S/S
- 1 no. at Sillod S/S (end bay)
- 1 no. at Jafrabad S/S (end bay)
- 1 no. at prop. Rajur S/S (end bay)
d)33kV outlets - 8 nos
TOTAL 6877.81
-
2
PKG 'B'
12 months
from
LOA.
A'BAD ZONE
1 220kV Paranda 220kV-2 Bus, 132kV-2 Bus 3779.85
Dist:Osmanabad a)220/33kV, 2x50 MVA and 220/132kV,
(2008-09) 2x100 MVA with bays
b)220kV line bays - 4 nos
- 2 nos. at Jeur S/S (end bays)
- 2 nos. at Paranda S/S
c)132kV line bays - 6 nos
- 3 nos. at Paranda S/S
- 1 no. at 132kV Kharda S/S (end bay)
- 1 no. at 132kV Kurdwadi S/S (end bay)
- 1 no. at 132kV Bhoom S/S (end bay)
d)33kV outlets - 12 nos.
2 220kV Tuljapur 220kv-2 Bus, 132kV-2 Bus 3588.95
Dist:Osmanabad a)220/132kV, 2x100 MVA and
(2008-09) 220/33kV, 2x50MVA with bays
b)220kV line bays - 4 nos
-3 nos. at Tuljapur S/S
-1 no. at PGCIL, Solapur S/S (end bay)
c)132kV line bays - 4 nos.
-3 nos. at Tuljapur S/S
- 1 no. at Omerga S/S (end bay)
d)33kV outlets - 8 nos.
TOTAL 7368.80
12 months
from
LOA.
PKG 'C' WASHI ZONE 220kV - 2 Bus
1 220kV Kudus a)220/22kV, 2x50MVA-2nos at Kudus S/S with bays 1909.42
Dist: Thane b)220kV line bays - 2 nos
(2008-09) c)22kV outlets - 12 nos
PUNE ZONE 220kV - 3 Bus
2 220kV Talegaon a)2x50 MVA, 220/22kV with bays 2584.69
Dist:Pune b)220kV line bays - 6 nos
(2008-09) - 4 nos at Talegaon S/S
- 2 nos. at 400kV PGCIL ( end bay )
c)22kV outlets - 12 nos.
KARAD ZONE 220kV-2 Bus, 132kV - 2 Bus
3 220kV Jath a)2x100MVA, 220/132-110kV ICT with bays 3344.68
Dist: Sangli b)2x25MVA, 220/33kV T/Fs with bays
(2008-09) c)220kV line bays - 4 nos
- 2 nos. at Mhaisal S/S (end bay)
- 2 nos. at Jath S/S
d)132kV line bays - 6 nos.
- 4 nos. at 220kV Jath S/S
- 1 no. at 132kV Sankh S/S (end bay)
- 1 no. at 132kV Kavathe-Mahankal S/S (end bay)
e)33kV outlets - 8 nos
TOTAL 7838.79
-
3
PKG 'D'
12 months
from
LOA.
NASHIK ZONE 220kV-2 Bus, 132kV-2 Bus
1 220/132/33kV a)2x100 MVA, 220/132kV T/Fs with bays 3261.86
Bambhori b)2x25 MVA, 220/33kV T/Fs with bays
(Jalgaon III) c)220kV line bays - 2 nos
(2008-09) - 2 nos. at 220kV Bambhori S/S
d)132kV line bays - 3 nos.
- 3 nos at Babhori S/S
e)33kV outlets - 8 nos.
220kV-2 Bus, 132kV-2 Bus
2 220kV a)220/132kV ICT, 2x200 MVA and 4355.56
Kopergaon 220/33kV, 2x50 MVA with bays
(Dist:Nashik) b)220kV line bays - 4 nos
(2008-09) - 2 nos. at Babhleshwar S/S (end bays)
- 2 nos. at Kopergaon S/S
c)132kV line bays - 10 nos
- 6 nos. at 220kV Kopergaon S/S
- 2 nos. at Vaijapur S/S (end bay)
- 2 nos. at Yeola S/S (end bay)
TOTAL 7617.42
12 months
from
LOA.
PKG 'E'
AMRAVATI ZONE
1 220kV Balapur 220kV-3 Bus, 132kV-2 Bus 4190.76
(MIDC) Akola a)2x25MVA, 220/33kV T/F with bays
(2008-09) b)2x100MVA, 220/132kV ICTs with bays
c)220kV line bays - 8 nos
- 4 nos. at 220kV Paras S/S ( End bays)
- 4 nos. at 220kV Balapur S/S (End bays)
d)132kV line bays - 4 nos at Balapur S/S
e)33kV outlets - 8 nos;
2 132kV Barshi- 132kV - 2 Bus 1365.12
Takali, Akola a)2x25MVA, 132/33kV T/Fs with bays
(2008-09) b)132kV line bays - 4nos
- 4 nos. at Barshi Takali S/S
c)33kV outlets - 8 nos
NAGPUR ZONE 132kV - 2 Bus
3 132kV Lakhandur a)2x25 MVA, 132/33kV Trfr. With bays 1335.02
Dist:Bhandara b)132kV line bays - 4 nos.
(2008-09) - 2 nos. at Asgaon S/S (end bay)
- 2 nos. at Lakhandur S/S
c)33kV outlets - 8 nos.
TOTAL 6890.90
-
4
2.0 General points :
2.1 Bidders may quote for any one or all Package. The evaluation shall
however be carried out Packagewise.
.
2.2 The prices to be quoted against this tender shall be in Indian rupees only.
2.3 A complete set of bidding documents may be obtained by application and upon payment of specified amount towards cost of bid documents either in
cash or by demand draft towards cost of bid documents payable to
MAHATRANSCO Ltd. (MSETCL), Mumbai and drawn on any
Nationalised/ Scheduled Bank, payable at Mumbai. However, issue of the bid
document will not automatically mean that such bidder is qualified.
2.4 Further Interested eligible bidders may obtain additional information, if needed, from the office of the
Chief Engineer (Transmission Project),
MAHATRASCO Ltd., 3rd Floor, Prakashganga, Plot No.C-19,
Bandra-Kurla Complex, Bandra (E), Mumbai-400 051
Telephone no.(022) 26598595, 26595138 Fax no.(022) 26598587.
2.5 Bidders are requested to note the following details :
1.
Date and time for sale of the document 07-10-08 to 22- 10-.08 (On
all working days, from
11.00 hrs. to 15.00 hrs.)
2. Price of bid documents Rs.50,000/-+MVAT Extra.
3. Last date and time for submission of bids 17 -11-2008 up to 11.00
hrs.
4. Date and time for opening of Techno-
commercial bids.
17-11-2008 at 11.30 hrs.
5 Opening of price bid Will be conveyed later on
6. Work completion period 12 months from date of
LOA, including monsoon.
7. Total estimated cost Rs.36593.72 lacs
2.6 In case the due date for sale, receipt and/or opening of bids happens to be a holiday, the next working day shall be the corresponding due date.
2.7 The bidder will have to furnish Bank Guarantee in prescribed format equivalent to 1% of the estimated cost for each package in lieu of Bid Security
Deposit payable at Mumbai at the time of submission of bid documents.
2.8 The bidders who have already carried out / carrying out the construction work of new substation / Augmentation work on turnkey basis in
MSETCL, their work performance will be considered for evaluation of
the tender.
2.9 In Civil Price Schedule Estimate, Civil estimate of other end bays for that particular substation are not included except 220 KV Kopergaon S/S.
That will be paid as per actual for respective S/S DSR.
-
5
2.10 25 MVA TRASFORMER will be supplied by MSETCL where ever available. Appropriate Cost of the transformer will be deducted.
Chief Engineer
(Trans. Projects)
MSETCL, Mumbai