section 14611 monorail hoist and trolley
TRANSCRIPT
MONORAIL HOIST AND
TROLLEY
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14611-1
SECTION 14611
MONORAIL HOIST AND TROLLEY
PART 1 -- GENERAL
1.01 DESCRIPTION
A. SCOPE:
This Section specifies single girder monorail system complete with monorail beam, hoist,
trolley, and associated drive units and controls for installation in the Lift Station.
B. TYPE:
Trolley shall be a four-wheel type and travel on the bottom flange of a monorail beam,
with underhung heavy-duty wire rope hoist. Monorail system shall be equipped for electric lift
and travel, with pendant control. All motor controller drives shall be adjustable speed type.
C. EQUIPMENT LIST:
Equipment numbers are as follows:
Item Equipment No.
Lift Station Monorail & Hoist MME 3110
D. PERFORMANCE AND DESIGN REQUIREMENTS:
Monorail system will be used to lift and maintain the lift pump motors and related
components for occasional maintenance.
Monorail system will be installed inside the Lift Station motor room for the lift pumps.
Environmental conditions are described in Section 01800.
Electrical equipment, supports, and anchorage shall be designed and installed in
accordance with the seismic design requirements specified in Section 01900.
Except as noted, all equipment provided under this Section shall be suitable for Class A,
L2, N1 service as defined by CMAA standards. A heavy-duty hoist shall be suspended from the
trolley.
Operating and dimensional data are specified in Paragraph 14611-1.01E.
MONORAIL HOIST AND
TROLLEY
14611-2 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
A vertical impact allowance shall be included in design calculations for hoist, trolley and
monorail. The impact allowance shall be ½ percent of the rated load for each foot per minute of
hoisting speed with a minimum allowance of 15 percent and a maximum allowance of 50
percent.
The Contractor shall examine the drawings for interferences and obstructions which
might impose additional limitations upon the equipment.
E. OPERATING AND DIMENSIONAL DATA:
Item Value
Rated capacity, tons 2
Runway length, feet-inches 81’-0”
Trolley type underhung
Hoist type wire rope
Elevation of hook in highest position, minimum, feet 46.00 a
Elevations within hook reach, feet:
Operating floor elevation 32.00
Speeds, fpm, infinitely variable: b
Hoist 2.5 to 12.5
Trolley 1.5 to 50
Motors c per CMAA and HMI Duty
Class Notes:
a. Actual hook position shall be the elevation required to lift and move the Lift Pump motors
provided between a flat bed truck and the installed locations.
b. Motors shall be controlled by adjustable frequency drives.
c. See Section 11060.
1.02 QUALITY ASSURANCE
A. REFERENCE STANDARDS:
This Section incorporates by reference the latest revisions of the following documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). They are part of this Section. In case of conflict between the
requirements of this Section and the listed documents, the Contractor shall point out the conflict
to the Construction Manager; lacking a definitive answer otherwise, the requirements of the
Contract Specifications shall prevail.
MONORAIL HOIST AND
TROLLEY
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14611-3
Reference Title
AISC Specifications for the Design, Fabrication, and Erection
of Structural Steel for Buildings
AGMA American Gear Manufacturers Association
ASME B30.10 Hooks
ASME B30.11 Monorails and Underhung Cranes
ASME B30.16 Overhead Hoists (Underhung)
ASME HST-4 Performance Standard for Electric Wire Rope Hoists
ASTM A36 Standard Specification for Carbon Structural Steel
HMI Hoist Manufacturer’s Institute
CMAA 70 Specifications for Top Running Bridge & Gantry Type
Multiple Girder Electric Overhead Traveling Cranes
CMAA 74 Specification for Top Running and Under Running
Single Girder Electric Overhead Travelling Cranes
Utilizing Under Running Trolley Hoist
NFPA 70 National Electric Code
ASME American Society of Mechanical Engineers
CMAA Crane Manufacturers Association of America
NEMA National Electrical Manufacturers Association
OSHA Occupational Safety and Health Administration
UL Underwriters Laboratories
All equipment furnished under this Section shall comply in all respects with the
requirements of OSHA, the standards of the Crane Manufacturer’s Association of America
(CMAA), the Hoist Manufacturer’s Institute (HMI), ASME HST-4 Performance Standards for
Electric Wire Rope Hoists, and the National Electric Code (NFPA 70).
B. MANUFACTURER’S QUALIFICATIONS:
The monorail system manufacturer shall be one who is regularly engaged in the business
of designing, building, and repairing monorails and hoists of the type specified in this section.
All monorail system components furnished for this contract shall be designed, coordinated and
supplied by a single manufacturer.
MONORAIL HOIST AND
TROLLEY
14611-4 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
C. UNIT RESPONSIBILITY:
The Contractor shall assign unit responsibility as specified in paragraph 11000-1.02C to
the monorail system manufacturer for all equipment specified in this Section. The monorail
system manufacturer is the unit responsibility manufacturer and has unit responsibility, as
defined in Section 11000, for the equipment specified in this Section. A completed and signed
certificate of unit responsibility (Form 11000-C, Section 01999) shall be submitted as specified
herein.
D. FACTORY TESTS:
Manufacturer shall test the equipment in accordance with its current Quality Assurance
program, industry standards and federal regulations prior to shipment of the equipment.
Certification of the factory test results shall be provided as specified herein.
1.03 SUBMITTALS
Submittals shall comply with the requirements of Section 01300. Submittals shall
include the following information.
1. A copy of this specification section, with addendum updates included, and
all referenced and applicable sections, with addendum updates included,
with each paragraph check-marked to indicate specification compliance or
marked to indicate requested deviations from specification requirements.
Check marks (�) shall denote full compliance with a paragraph as a
whole. If deviations from the specifications are indicated and, therefore
requested by the Contractor, each deviation shall be underlined and
denoted by a number in the margin to the right of the identified paragraph.
The remaining portions of the paragraph not underlined will signify
compliance on the part of the Contractor with the specifications. The
submittal shall be accompanied by a detailed, written justification for each
deviation. Failure to include a copy of the marked-up specification
sections, along with justification(s) for any requested deviations to the
specification requirements, with the submittal shall be sufficient cause for
rejection of the entire submittal with no further consideration.
2. Completed Certificate of Unit Responsibility attesting that the Contractor
has assigned, and that the manufacturer accepts unit responsibility in
accordance with the requirements of this Section and Paragraph 11000-
1.02C. No other submittal material will be reviewed until the certificate
has been received and found to be in conformance with these
requirements.
3. Manufacturer's catalog data confirming rated capacity, equipment speeds,
motor horsepower, electrical requirements, and component sizes and
dimensions.
MONORAIL HOIST AND
TROLLEY
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14611-5
4. Shop drawings showing physical details, dimensions of the equipment,
details of construction for monorail installation, and all information listed
in Paragraphs 14630-1.01D and -E.
5. Monorail beam and track design calculations. Seismic calculations.
Loads to the building frame structure shall be provided in calculations.
Calculations shall be stamped by a California registered structural or civil
engineer.
6. Anchor bolt calculations in accordance with Section 05501.
7. Motor data.
8. Electrical diagrams and schematics.
PART 2 -- PRODUCTS
2.01 ACCEPTABLE PRODUCTS
Monorail hoist shall be P & H, Yale Lift Tech’s Shaw-Box product series, CraneVeyor
Corp, or equal, modified to provide the specified features. All products specified herein shall be
provided by a single supplier.
2.02 MATERIALS
Component Material
Monorail beam and trolley Steel, ASTM A36
Bottom tees Manganese steel, 225 Brinell hardness
Hoist gearing, trolley wheels, hook
Wire rope
Steel
Steel
2.03 EQUIPMENT FEATURES
A. MONORAIL BEAMS:
Monorail track shall be straight and level and specially designed for this application. The
monorail beam shall be designed for stresses not exceeding 60 percent of material’s yield
strength and a maximum vertical deflection of 1/450 of span. Lower load-carrying flange shall
have a minimum 3-1/4-inch width and a raised running or tread wear. Couplings shall be web
type at rail joints with maximum gap at rail ends of load-carrying flange of 1/16-inch, and 3/16-
inch at free ends. Monorail shall be provided with bolted end stops and impact absorbing
bumpers at rail ends.
MONORAIL HOIST AND
TROLLEY
14611-6 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
B. RAIL SUSPENSION:
Provide anchor bolts, clamps, hanger rods, and fittings to support live, dead, vertical
impact, and lateral load of hoist, trolley, controls, motors, and track. Hanger rods, if provided,
shall be high carbon, cold-rolled alloy steel with unified national fine, Class 2 screw thread ends.
Vertical adjustment shall be 1-inch adjustable. Provide lateral bracing as recommended by
manufacturer.
C. TROLLEY:
Trolley frame shall be welded steel, cast steel, or a combination thereof. The trolley shall
be motorized and driven by an electric motor through a gear reduction unit and drive shaft.
Trolley motor and drive shall be as specified in Paragraph 14611-2.03F. The motor shall be
provided with cushion start and controller for smooth travel and load control. Roller assembly
stabilizers shall be provided to prevent tipping during load pickup. Trolley wheels shall be steel.
The wheel tread shall be accurately machined to assure concentricity of axle and tread, and
hardened to 280 Brinell minimum. Wheels shall be mounted on permanently lubricated anti-
friction bearings. Bearings shall have a minimum B-10 life of 10,000 hours. Trolley brakes
shall be suitable for the service class and rated torque capacities as specified in ASME B30.11.
D. WIRE ROPE HOIST:
The hoist shall be double reeved. The hoisting drum shall be grooved and designed for
one layer of wire rope, with at least two (2) full turns of rope to remain on the drum at the lowest
hook position. Hoist gearing shall be heat-treated hardened steel, running in an oil bath. Gear
bearings shall be the oil-lubricated anti-friction type, and all bearings shall be designed for a
Class M2 (20,000 hour) bearing life.
A gravity type and upper and lower geared limit switch shall be provided to assure safe
operation and positive stopping under all conditions. The limit switch shall automatically stop
the motor and engage the hoist brake when the hook reaches either the upper or lower limit of
travel. The hoist shall be provided with a load limiting device adjusted not to exceed 100 percent
of rated capacity.
The load hook shall be mounted on ball thrust bearings to swivel without twisting the
wire rope. The lifting tackle shall be of the safety type, and the hook shall be of hardened steel
equipped with a safety catch. Sheaves shall be properly guarded and shall be heavy pattern, deep
flanged, and properly grooved. Sheaves shall either be bronze bushed, or fitted with ball
bearings and supported on fixed pins. Wire rope shall be improved plow steel with steel center
complete with swaged fittings. Wire rope shall be grease impregnated. The rated capacity load
divided by the number of parts of hoisting rope shall not exceed 20 percent of the published
breaking strength of the rope.
Hoist motor brake shall be magnetically operated disc type or shoe type, mounted on the
extended pinion shaft, and designed for a torque rating to 150 percent of the motor full load
torque. Brake shall be equally effective in both directions of motor rotation and of sufficient size
MONORAIL HOIST AND
TROLLEY
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14611-7
to stop motor and hold rated capacity load. Brake shall be set automatically when current is not
flowing to the motor. A second “load brake” shall be included and applied automatically on
lowering and require the motor to drive the load down. Brake shall be self-adjusting to allow for
normal wear of the brake lining. Hoist motor shall be as specified in Paragraph 14611-2.03F.
The Contractor shall furnish and install an identification plate on the hoist housing. The
identification plate shall be of clearly legible permanent lettering giving the manufacturer's
name, model number, rated capacity, and other essential information. In addition, the
identification plate shall display the equipment number for the hoist that is identified
hereinbefore.
F. MOTORS:
Motors shall be 1750 rpm, TEFC, 30-minute-duty-cycle, rated for inverter duty, comply
with CMAA No. 70 for AC Motors, and shall be suitable for the class and type of crane service
specified in Paragraphs 14630-1.01D and -E, and also herein. Hoist and trolley motion shall be
through adjustable frequency drive operation. All motors shall be provided with lifetime
lubricated anti-friction bearings. The hoist motor bearings shall be designed for a Class M2
(20,000 hour) bearing life.
Controllers shall be capable of providing the control speed ranges specified in Paragraph
14611-1.01E. Controller shall provide soft start/soft stop (dynamic braking), acceleration
control, phase loss protection, user programming, and ability to store and retrieve fault history.
Trolley motor shall drive the trolley through a gear reducer. Gear reducer shall be
enclosed heavy-duty helical, or spur gear type, of a self-lubricating design, with anti-friction
bearings. Brakes shall be solenoid actuated.
G. ELECTRIFICATION AND CONTROLS:
All electrical and control equipment shall comply with the requirements of Division 16.
The crane manufacturer shall furnish and mount all electrical equipment on the crane
including motors, adjustable frequency drives, controls, conduit, and wiring. Trolley conductors
may be removed for shipment. All wiring on the crane shall be furnished, installed, and
terminated by the crane manufacturer, as far as practical for shipment.
The crane manufacturer shall also provide a NEMA 4X main control panel and a NEMA
4X push-button pendant controller suspended from the trolley and capable of controlling all
crane motions (hoist and trolley). The main control panel shall include: individual disconnects
for hoist and trolley; reversing controller for hoist and trolley; thermal overload relays; control
transformers; control relays; power terminal blocks and control terminal blocks all prewired, as
required for a complete system and fully operational via a single 480V, 3-phase 60 Hz power
feed. The top of the pendant shall be 4 feet above the operating floor. Hoist and trolley motion
control shall be adjustable speed actuated from the pendant push button station suspended from
the movable trolley. Both the main control panel and the pendant controller shall be equipped
MONORAIL HOIST AND
TROLLEY
14611-8 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
with an emergency stop pushbutton to disable all crane motions. All controls shall be clearly
marked with etched or engraved nameplates.
The Contractor shall provide the power feed and a NEMA 4X lockable local main
disconnect switch of suitable rating for the crane system accessible from the operating floor.
Electrification of the trolley and hoist shall be by flat insulated festooned cable supported
in an enclosed track. Conductors shall be complete with all necessary insulation, supports and
appurtenances as required. All other wiring of the crane shall be in rigid or flexible conduit and
in accordance with National Electrical Code and complying with Fire Underwriters
specifications. When a crane is shipped knocked down, the wiring shall terminate in approved
terminal boxes and the wire ends shall be provided with permanent marking tags.
2.04 PAINTING
Contact wheel and rail surfaces shall not be coated. All other metal surfaces shall receive
proper metal preparation and cleaning prior to application of protective coating. Finish color
shall be safety yellow except for trolley, which shall be a different color (e.g., blue) for good
positioning contrast. Coating system shall be E-2 epoxy or EU-1 epoxy polyurethane as
specified in Section 09900, or equal coating system suited for a corrosive environment. All
components shall be factory coated, tested, and defects corrected prior to shipment. Field touch-
up will be permitted for minor scratches but defective coatings shall be corrected in the shop.
Manufacturer’s standard epoxy finish is acceptable for hoist.
2.05 PRODUCT DATA
The following information shall be provided in accordance with Section 01300:
1. Applicable operations and maintenance information as specified in
Section 01730.
2. Factory test certification.
3. Installation Certification Form 11000-A specified in Paragraph
14611-3.05.
4. Training Certification Form 11000-B specified in Paragraph 14611-3.05.
PART 3 -- EXECUTION
3.01 INSTALLATION
The monorail, trolley and hoist shall be installed at the location shown and in accordance
with the manufacturer’s recommendations, to the tolerances recommended by CMAA, and under
the supervision of the manufacturer’s authorized field representative.
MONORAIL HOIST AND
TROLLEY
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14611-9
3.02 INSPECTION AND TESTING
After completion of the installation, the Contractor shall test all hoist and crane
equipment under load in the presence of the manufacturer's field representative, who shall certify
in writing that the equipment meets all applicable standards and specified performance
requirements. Form 11000-A, specified in Section 11000, General Requirements for Mechanical
Equipment, shall be completed and submitted.
As a minimum, testing shall be by operating the equipment through a complete lift and
lowering cycle and through a complete travel of the trolley to determine that the equipment
performs smoothly and safely without failure.
The tests shall be carried out with the hoisting equipment loaded as near to the specified
capacity as possible. Any defects shall be corrected or replaced immediately by the Contractor
and at no expense to the Owner.
3.03 USE BY CONTRACTOR
Any hoist and crane equipment used by the CONTRACTOR shall be repaired, repainted
and otherwise refurbished to like-new condition prior to its acceptance. After equipment
refurbishment, the manufacturer’s field representative shall re-inspect and re-test the crane
unloaded, and certify in writing that the equipment meets all applicable standards and specified
performance requirements. The certification shall be submitted. The CONTRACTOR assumes
all responsibility for operation and maintenance until the equipment has been accepted.
3.04 WARRANTY
A written, one year warranty for equipment shall be provided. Warranty shall include
parts and labor for any repair work.
3.05 TRAINING
Furnish the services of a factory trained representative for one (1) eight hour man-day for
instruction of the Owner’s personnel in the proper operation and maintenance of the equipment.
Training shall be as specified in Section 01664, and shall be certified on Form 11000-B,
specified in Section 01999.
** END OF SECTION **
MONORAIL HOIST AND
TROLLEY
14611-10 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
THIS PAGE INTENTIONALLY LEFT BLANK
BRIDGE CRANE
AND HOISTS
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14630-1
SECTION 14630
BRIDGE CRANES AND HOISTS
PART 1 -- GENERAL
1.01 DESCRIPTION
A. SCOPE:
This Section specifies an electrically operated bridge crane system complete with hoist,
trolley, bridge, end trucks, and associated drive units and controls, for installation in the Lift
Station.
B. TYPE:
Bridge crane shall be single girder top-running type mounted on individual drive end
trucks designed to travel on ASCE runway rails, with underhung heavy-duty wire rope hoist and
four-wheel trolley, equipped for electric lift and travel in both directions, with pendant control.
All motor controller drives shall be adjustable speed type.
C. EQUIPMENT LIST:
Equipment numbers are as follows:
Item Equipment No.
Lift Station Bridge Crane CRN 3120
D. PERFORMANCE AND DESIGN REQUIREMENTS:
Bridge crane will be used to lift and maintain process equipment and related components
for occasional maintenance.
Bridge crane will be installed inside the Lift Station motor room for the force main
pumps.
Environmental conditions are described in Section 01800.
Electrical equipment, supports, and anchorage shall be designed and installed in
accordance with the seismic design requirements specified in Section 01900.
Except as noted, bridge crane shall be CMAA Class A. Bridge drive shall be CMAA
Type A4. A heavy-duty hoist shall be suspended from the trolley.
BRIDGE CRANE
AND HOISTS
14630-2 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
Operating and dimensional data are specified in Paragraph 14630-1.01E.
Runway beams, rails, and bridge beams shall be as specified in this Section. Runway
beams shall be complete with connections to the building structural system, splices, and crane
stops, and shall be furnished by the crane manufacturer. Runway beam minimum size is shown
on the Drawings. All beams shall be designed by a structural engineer registered in the State of
California.
Hook approach distances shall be as shown on the Drawings.
Vertical Impact: An impact allowance shall be included in design calculations for
trolleys, cranes and runways. The impact allowance shall be ½ percent of the rated load for each
foot per minute of hoisting speed with a minimum allowance of 15 percent and a maximum
allowance of 50 percent.
The Contractor shall examine the drawings for interferences and obstructions which
might impose additional limitations upon the equipment.
E. OPERATING AND DIMENSIONAL DATA:
Item Value
Rated capacity, tons 3
Runway span, feet-inches 25’-9”
Runway length, feet-inches 81’-0”
Bridge type single girder, top running
Trolley type underhung
Hoist type wire rope
Elevation of hook in highest position, minimum, feet 46.00 a
Elevations within hook reach, feet:
Operating floor elevation 32.00
Ground floor elevation 12.00
Speeds, fpm, infinitely variable: b
Hoist 2.5 to 12.5
Bridge 2.5 to 75
Trolley 1.5 to 50
Motors c per CMAA and HMI Duty
Class Notes:
a. Actual hook position shall be the elevation required to lift and move pumping equipment provided
between a flat bed truck and the installed locations (Force Main pump motors) or ground floor (all
pumps).
b. Motors shall be controlled by adjustable frequency drives.
c. See Section 11060.
BRIDGE CRANE
AND HOISTS
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14630-3
1.02 QUALITY ASSURANCE
A. REFERENCE STANDARDS:
This Section incorporates by reference the latest revisions of the following documents in
effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the
Agreement if there were no Bids). They are part of this Section. In case of conflict between the
requirements of this Section and the listed documents, the Contractor shall point out the conflict
to the Construction Manager; lacking a definitive answer otherwise, the requirements of the
Contract Specifications shall prevail.
Reference Title
AISC Specifications for the Design, Fabrication, and Erection of
Structural Steel for Buildings
AGMA American Gear Manufacturers Association
ASME B30.10 Hooks
ASME B30.11 Monorails and Underhung Cranes
ASME B30.16 Overhead Hoists (Underhung)
ASME B30.17 Overhead and Gantry Cranes (Top Running Bridge,
Single Girder, Underhung Hoist)
ASME HST-4 Performance Standard for Electric Wire Rope Hoists
ASTM A36 Standard Specification for Carbon Structural Steel
ASTM A992 Standard Specification for Structural Steel Shapes
HMI Hoist Manufacturer’s Institute
CMAA 70 Specifications for Top Running Bridge & Gantry Type
Multiple Girder Electric Overhead Traveling Cranes
CMAA 74 Specification for Top Running and Under Running Single
Girder Electric Overhead Travelling Cranes Utilizing
Under Running Trolley Hoist
NFPA 70 National Electric Code
ASME American Society of Mechanical Engineers
CMAA Crane Manufacturers Association of America
NEMA National Electrical Manufacturers Association
OSHA Occupational Safety and Health Administration
UL Underwriters Laboratories
BRIDGE CRANE
AND HOISTS
14630-4 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
All equipment furnished under this Section shall comply in all respects with the
requirements of OSHA, the standards of the Crane Manufacturer’s Association of America
(CMAA), the Hoist Manufacturer’s Institute (HMI), ANSI/ASME HST-4 Performance
Standards for Electric Wire Rope Hoists, and the National Electric Code (NFPA 70).
B. UNIT RESPONSIBILITY:
The Contractor shall assign unit responsibility as specified in paragraph 11000-1.02C to
the bridge crane manufacturer for all equipment specified in this Section. The crane
manufacturer is the unit responsibility manufacturer and has unit responsibility, as defined in
Section 11000, for the equipment specified in this Section. A completed and signed certificate of
unit responsibility (Form 11000-C, Section 01999) shall be submitted as specified herein.
C. FACTORY TESTS:
Manufacturer shall test the equipment in accordance with industry standards and federal
regulations prior to shipment of the equipment. Crane, trolley and hoist shall be completely
assembled and no load run tested in the factory prior to shipment to the job site. Crane shall be
disassembled to the least amount possible for shipment. Certification of the factory test results
shall be provided as specified herein.
1.03 SUBMITTALS
Submittals shall comply with the requirements of Section 01300. Submittals shall
include the following information.
1. A copy of this specification section, with addendum updates included, and
all referenced and applicable sections, with addendum updates included,
with each paragraph check-marked to indicate specification compliance or
marked to indicate requested deviations from specification requirements.
Check marks (�) shall denote full compliance with a paragraph as a
whole. If deviations from the specifications are indicated and, therefore
requested by the Contractor, each deviation shall be underlined and
denoted by a number in the margin to the right of the identified paragraph.
The remaining portions of the paragraph not underlined will signify
compliance on the part of the Contractor with the specifications. The
submittal shall be accompanied by a detailed, written justification for each
deviation. Failure to include a copy of the marked-up specification
sections, along with justification(s) for any requested deviations to the
specification requirements, with the submittal shall be sufficient cause for
rejection of the entire submittal with no further consideration.
BRIDGE CRANE
AND HOISTS
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14630-5
2. Completed Certificate of Unit Responsibility attesting that the Contractor
has assigned, and that the manufacturer accepts unit responsibility in
accordance with the requirements of this Section and Paragraph 11000-
1.02C. No other submittal material will be reviewed until the certificate
has been received and found to be in conformance with these
requirements.
3. Manufacturer's catalog data confirming rated capacity, equipment speeds,
motor horsepower, electrical requirements, and component sizes and
dimensions.
4. Bridge crane shop drawings showing physical details, dimensions of the
bridge crane and hoist equipment, details of construction for crane
installation, and all information listed in Paragraphs 14630-1.01D and -E.
5. Runway beam design calculations. Loads to the building frame structure
shall be provided in calculations. Calculations shall be stamped by a
California registered structural or civil engineer.
6. Anchor bolt calculations in accordance with Section 05501.
7. Motor data.
8. Electrical diagrams and schematics.
PART 2 -- PRODUCTS
2.01 ACCEPTABLE PRODUCTS
Bridge cranes and hoists shall be P & H, Acco-Wright, Stahl, Demag, CraneVeyor Corp,
or equal, modified to provide the specified features. All products specified herein shall be
provided by a single supplier.
2.02 MATERIALS
Component Material
Runway beams Steel, ASTM A992
Bridge beams and trolley Steel, ASTM A36
Hoist gearing, trolley wheels, end truck wheels, hook
Wire rope
Steel
Steel
BRIDGE CRANE
AND HOISTS
14630-6 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
2.03 EQUIPMENT FEATURES
A. RUNWAY BEAMS AND RAILS:
Runways shall be straight, parallel, and level and specially designed for this application.
At full load, the runway beams shall be designed for a maximum deflection of 1/600 of span.
Runway rails shall be selected for proper loading, and shall be ASCE 30# minimum. Runways
shall be provided with bolted end stops.
B. RUNWAY SUPPORTS:
Anchor bolts and clamps shall be provided to secure runway beams and rails. Provide
lateral bracing to walls for runways as recommended by manufacturer.
C. BRIDGE BEAM:
The crane bridge assembly shall be a top-running, single girder bridge beam, electrically
driven. The bridge beam shall be rigidly attached to end trucks and serve as the hoist runway.
Permanent stops shall be provided to prevent trolley overrun. At full load, the bridge beam shall
be designed for a maximum deflection of 1/800 of span.
D. END TRUCKS:
The bridge crane end trucks shall carry the rated load between the end truck wheels while
the rated load is lifted at one end of the crane bridge. End truck wheel bases shall be 1/8 of the
span. The crane and trucks shall contain diaphragm members welded to truck frames to maintain
alignment and distribute truck loads on the inner and outer truck members.
An impact absorbing rubber bumper shall be mounted on each end of the end trucks.
Rail sweeps shall be provided. Safety lugs shall be provided to limit drop of the end trucks to 1
inch or less in the event of wheel or axle failure.
Wheel bearings shall be roller type with life time lubrication, fitted with seals to exclude
dust and moisture, and provided with a suitable reservoir of lubricant to eliminate the need for
field lubrication.
Crane wheels shall be steel with flat tread surfaces hardened to 280 Brinell minimum.
Wheel treads shall be smooth, true, and uniform within 0.01-inch tread diameter on all wheels.
Wheel mounting shall be designed so that axles and wheels can be removed without disturbing
other truck elements of their alignment.
E. BRIDGE DRIVE:
Bridge drive shall be CMAA Type A4. Bridge motors and drives shall be as specified in
Paragraph 14630-2.03H. The motors shall be provided with cushion start and controller for
smooth travel and load control. The motors shall drive the bridge through gear reducers. Gear
BRIDGE CRANE
AND HOISTS
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14630-7
reducers shall be enclosed heavy-duty helical, or spur gear type, of a self-lubricating design, with
anti-friction bearings. The drive shafts shall provide synchronous drive from the gear reduction
units to both end trucks. Both motorized trolley wheels shall be driven simultaneously. Brakes
shall be solenoid actuated. The crane drive shall include integrally mounted spring set
electrically released ac or dc rectified disc brake.
F. TROLLEY:
The trolley shall be a four-wheel motorized assembly designed for under running hoist
application. The trolley shall be framed by a structural shape welded into a stable assembly for
proper wheel and bearing alignment. Trolley bumpers shall be provided. The trolley assembly
shall be supported by trolley wheels with flat tread surfaces. The wheel tread shall be accurately
machined to assure concentricity of axle and tread, and hardened to 280 Brinell minimum.
Wheels shall be mounted on permanently lubricated anti-friction bearings. Bearings must have a
minimum B-10 life of 10,000 hours. Trolley motor and drive shall be as specified in Paragraph
14630-2.03H. The motor shall be provided with cushion start and controller for smooth travel
and load control. The motor shall drive the trolley through a gear reducer. Gear reducer shall be
enclosed heavy-duty helical, or spur gear type, of a self-lubricating design, with anti-friction
bearings. Brakes shall be solenoid actuated. Trolley drive shall include integrally mounted
spring set electrically released ac or dc rectified disc brake.
G. HOIST:
The hoist shall be double reeved. The hoisting drum shall be grooved and designed for
one layer of wire rope, with at least two (2) full turns of rope to remain on the drum at the lowest
hook position. Hoist gearing shall be heat-treated hardened steel, running in an oil bath. Gear
bearings shall be the oil-lubricated anti-friction type, and all bearings shall be designed for a
Class M2 (20,000 hour) bearing life.
A gravity type and upper and lower geared limit switch shall be provided to assure safe
operation and positive stopping under all conditions. The hoist shall be provided with a geared
limit switch to automatically stop the motor and engage the hoist brake when the hook reaches
either the upper or lower limit of travel. The hoist shall be provided with a load limiting device
adjusted not to exceed 100 percent of rated capacity.
The load hook shall be mounted on ball thrust bearings to swivel without twisting the
wire rope. The load hook shall be of the safety type, and the hook shall be of hardened steel
equipped with a safety latch. Sheaves shall be properly guarded and shall be heavy pattern, deep
flanged, and properly grooved. Sheaves shall be fitted with ball bearings and supported on fixed
pins. Wire rope shall be improved plow steel with steel center complete with swaged fittings.
Wire rope shall be grease impregnated. The rated capacity load divided by the number of parts
of hoisting rope shall not exceed 20 percent of the published breaking strength of the rope.
Hoist motor brake shall be magnetically operated disc type or shoe type, mounted on the
extended pinion shaft, and designed for a torque rating to 150 percent of the motor full load
torque. Brake shall be equally effective in both directions of motor rotation and of sufficient size
BRIDGE CRANE
AND HOISTS
14630-8 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
to stop motor and hold rated capacity load. Brake shall be set automatically when current is not
flowing to the motor. A second “load brake” shall be included and applied automatically on
lowering and require the motor to drive the load down. Brake shall be self-adjusting to allow for
normal wear of the brake lining. Hoist motor shall be as specified in Paragraph 14630-2.03H.
The Contractor shall furnish and install an identification plate on the hoist housing. The
identification plate shall be of clearly legible permanent lettering giving the manufacturer's
name, model number, rated capacity, and other essential information. In addition, the
identification plate shall display the equipment number for the hoist that is identified
hereinbefore.
H. MOTORS AND CONTROLLERS:
Motors shall be 1750 rpm, TEFC, 30-minute-duty-cycle, rated for inverter duty, comply
with CMAA No. 70 for AC Motors, and shall be suitable for the class and type of crane service
specified in Paragraphs 14630-1.01D and -E, and also herein. Hoist, trolley and bridge motion
shall be through adjustable frequency drive operation. All motors shall be provided with lifetime
lubricated anti-friction bearings. The hoist motor bearings shall be designed for a Class M2
(20,000 hour) bearing life.
Controllers shall be capable of providing the control speed ranges specified in Paragraph
14630-1.01E. Controllers shall provide soft start/soft stop (dynamic braking), acceleration
control, phase loss protection, user programming, and ability to store and retrieve fault history.
I. ELECTRIFICATION AND CONTROLS:
All electrical and control equipment shall comply with the requirements of Division 16.
The crane manufacturer shall furnish and mount all electrical equipment on the crane
including motors, adjustable frequency drives, controls, conduit, and wiring. Bridge conductors
may be removed for shipment. All wiring on the crane shall be furnished, installed, and
terminated by the crane manufacturer, as far as practical for shipment.
The crane manufacturer shall also provide a NEMA 4X main control panel and a NEMA
4X push-button pendant controller suspended from the trolley and capable of controlling all
crane motions (hoist, bridge, and trolley). The main control panel shall include: service
disconnect for mainline power feeding the panel; reversing controller for hoist, bridge, and
trolley; thermal overload relays; control transformers; control relays; power terminal blocks and
control terminal blocks all prewired, as required for a complete system and fully operational via
a single 480V, 3-phase, 60 Hz power feed. A torque reel shall be supplied to allow easy
adjustment of the pendant height for hoist use at elevations shown in Paragraph 14630-1.01E.
Hoist, bridge and trolley motion control shall be adjustable speed actuated from the pendant push
button station suspended from the movable trolley. The pendant controller shall be equipped
with an emergency stop pushbutton to disable all crane motions. All controls shall be clearly
marked with etched or engraved nameplates.
BRIDGE CRANE
AND HOISTS
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14630-9
The Contractor shall provide the power feed and a NEMA 4X lockable local main
disconnect switch of suitable rating for the crane system and accessible from the operating floor.
Electrification of the bridge shall be by enclosed bus bar conductors. Conductor bars
shall be stainless steel clad hard copper enclosed in insulation. Conductors shall be complete
with all necessary insulation, supports, and appurtenances, and shall meet the NFPA 70 (NEC)
requirements. Current collectors shall be the sliding noncopper bearing, carbon shoe type, with
adjustable spring tension arms for contact between bus bars and controls. Collector mechanism
components shall be aluminum, stainless steel, or other noncorrosive materials (excluding
plastic). Electrification of the trolley and hoist shall be by flat insulated festooned cable
supported in an enclosed track. Conductors shall be complete with all necessary insulation,
supports and appurtenances as required. All other wiring of the crane shall be in rigid or flexible
conduit and in accordance with National Electrical Code and complying with Fire Underwriters
specifications. When a crane is shipped knocked down, the wiring shall terminate in approved
terminal boxes and the wire ends shall be provided with permanent marking tags.
2.04 PAINTING
Contact wheel and rail surfaces shall not be coated. All other metal surfaces including
the runway beams shall receive proper metal preparation and cleaning prior to application of
protective coating. Finish color shall be safety yellow except for trolley, which shall be a
different color (e.g., blue) for good positioning contrast. Coating system shall be E-2 epoxy or
EU-1 epoxy polyurethane as specified in Section 09900, or equal coating system suited for a
corrosive environment. Runway rails shall be coated after installation. All other components
shall be factory coated, tested, and defects corrected prior to shipment. Field touch-up will be
permitted for minor scratches but defective coatings shall be corrected in the shop.
Manufacturer’s standard epoxy finish is acceptable for the hoist.
2.05 PRODUCT DATA
The following information shall be provided in accordance with Section 01300:
1. Applicable operations and maintenance information as specified in
Section 01730.
2. Factory test certification.
3. Installation Certification Form 11000-A specified in Paragraph
14630-3.02.
4. Training Certification Form 11000-B specified in Paragraph 14630-3.05.
BRIDGE CRANE
AND HOISTS
14630-10 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
PART 3 -- EXECUTION
3.01 INSTALLATION
The runway rails, bridge crane, trolley, and hoist shall be installed at the location shown
and in accordance with the manufacturer’s recommendations, within the tolerances
recommended by CMAA, and under the supervision of the manufacturer’s authorized field
representative.
3.02 INSPECTION AND TESTING
After completion of the installation, the Contractor shall test all hoist and crane
equipment under load in the presence of the manufacturer's field representative, who shall certify
in writing that the equipment meets all applicable standards and specified performance
requirements. Form 11000-A, specified in Section 11000, General Requirements for Mechanical
Equipment, shall be completed and submitted.
As a minimum, testing shall be by operating the equipment through a complete lift and
lowering cycle and through a complete travel of the bridge and trolley to determine that the
equipment performs smoothly and safely without failure.
The tests shall be carried out with the hoisting equipment loaded as near to the specified
capacity as possible. Any defects shall be corrected or replaced immediately by the Contractor
and at no expense to the Owner.
3.03 USE BY CONTRACTOR
Any hoist and crane equipment used by the CONTRACTOR shall be repaired, repainted
and otherwise refurbished to like-new condition prior to its acceptance. After equipment
refurbishment, the manufacturer’s field representative shall re-inspect and re-test the crane
unloaded, and certify in writing that the equipment meets all applicable standards and specified
performance requirements. The certification shall be submitted. The CONTRACTOR assumes
all responsibility for operation and maintenance until the equipment has been accepted.
3.04 WARRANTY
A written, one year warranty for equipment shall be provided. Warranty shall include
parts and labor for any repair work.
BRIDGE CRANE
AND HOISTS
DECEMBER 2014 PWS CONTRACT NO. 13-40UTIL 14630-11
3.05 TRAINING
Furnish the services of a factory trained representative for one (1) eight hour man-day for
instruction of the Owner’s personnel in the proper operation and maintenance of the equipment.
Training shall be as specified in Section 01664, and shall be certified on Form 11000-B,
specified in Section 01999.
** END OF SECTION **
BRIDGE CRANE
AND HOISTS
14630-12 PWS CONTRACT NO. 13-40UTIL DECEMBER 2014
THIS PAGE INTENTIONALLY LEFT BLANK