ISGF Technology Session
Improving System Reliability throughAutomating Rural Feeders and
Substations
Amit Sharma
27thApril 2012
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
2/53
Automatic Circuit Reclosers and Sectionalizers
Amit Sharma24thNov 2011
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
3/53
Schneider Electric 3- EnergyMONTHLY REVIEW
Overhead Faults 60% - 70% of faults are of a transient (temporary) nature:
Conductors clashing in the wind
Tree branches falling on overhead conductors
Animals or birds getting curious
Careless motor vehicle drivers
Lightning strikes
Operating error : leaving earths connected etc
Some are more permanent:
An auto-reclosecycle should clear the fault
lock out of the section
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
4/53
Schneider Electric 4- EnergyMONTHLY REVIEW
What is a Recloser ?
A Recloseris a protection device:
For overhead power lines
It is a circuit breaker with more arduoustest & install conditions
Designed to RECLOSE on to a fault.
Terminology
The auto-reclosecycle
Will detect a fault and open for a pre-programmed time,
before closing again automatically
This cycle can be repeated 3 times
Lockout typically on the fourth trip
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
5/53
Schneider Electric 5- EnergyMONTHLY REVIEW
What is a Sectionaliser ?
A Sectionaliseris a switch: It is used in conjunction with an upstream recloser or circuit breaker
It counts the interruption created by a recloser during a fault sequence.
On a preset count
trips during the dead time of the up stream recloser
Isolates a faulty network section
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
6/53
Schneider Electric 6- EnergyMONTHLY REVIEW
Benefit to the Customer
Improved reliability of power supply Quality of supplyAutomatic recloser function - supply restoration after temporary faults
Reduced outage time
Minimise revenue loss
Event Log and Remote control
Reduce cost of fault finding Better knowledge of the network
Reduction in the number of customer complaints
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
7/53
MV NETWORK
MANAGEMENT
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
8/53Schneider Electric 8- EnergyMONTHLY REVIEW
- why improve MV distribution?
To obtain the best possible power
quality
The main issue is to reduce
outage time and cost to the utility
and its customers
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
9/53Schneider Electric 9- EnergyMONTHLY REVIEW
- how can outage time be reduced?
By improving
MV networks: By improving the MV
networks management:
Large number of short
sectionsRedundant networks
Reliable components
With Fault Passage
Indicators (FPIs)
Or with remote
controlled load break
switches
Or with fully automated
reclosers andsectionalizers
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
10/53Schneider Electric 10- EnergyMONTHLY REVIEW
R
- different types of devices
R2
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
11/53Schneider Electric 11- EnergyMONTHLY REVIEW
- overhead networks: types of faults Temporary
faults
Permanent
faults
80% 20%
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
12/53Schneider Electric 12- EnergyMONTHLY REVIEW
- temporary faults
Temporary faults can be cleared by the
use of Automatic Circuit Reclosers(ACRs)
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
13/53Schneider Electric 13- EnergyMONTHLY REVIEW
R
- temporary fault: one recloser
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
14/53Schneider Electric 14- EnergyMONTHLY REVIEW
R
15
s
C
O
Time
100%
- temporary fault: one recloser
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
15/53Schneider Electric 15- EnergyMONTHLY REVIEW
R
15
s
C
O
15
s
Time
100%
- temporary fault: one recloser
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
16/53
Schneider Electric 16- EnergyMONTHLY REVIEW
R
15
s
C
O
15
s
Time
100%
- temporary fault: one recloser
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
17/53
Schneider Electric 17- EnergyMONTHLY REVIEW
R
15
s
C
O
15
s
15
s
Time
100%
- temporary fault: one recloser
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
18/53
Schneider Electric 18- EnergyMONTHLY REVIEW
R
15
s
C
O
15
s
15
s
Time2
mn
100%
- temporary fault: one recloser
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
19/53
Schneider Electric 19- EnergyMONTHLY REVIEW
R1
- temporary fault: TWOreclosers
R2
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
20/53
Schneider Electric 20- EnergyMONTHLY REVIEW
R1Network A-
50%
Network B-
50%
NetworkB
Time
- temporary fault: TWOreclosers
R2
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
21/53
Schneider Electric 21- EnergyMONTHLY REVIEW
- permanent faults
Permanent faults cannot be cleared by
automatic reclosing
To manage permanent faults, the
best solution is to add some
sectionalizers
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
22/53
Schneider Electric 22- EnergyMONTHLY REVIEW
R
5H6H
100%
- case 1: no network automationPermanent fault
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
23/53
Schneider Electric 23- EnergyMONTHLY REVIEW
R
5H6H
100% 95%
- case 1: no network automationPermanent fault
2 f f
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
24/53
Schneider Electric 24- EnergyMONTHLY REVIEW
R
- case 2: addition of non-communicatingfault
passage indicators (FPI)
An FPI for each branch of the network
Add an FPI around
each majorobstacle
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
25/53
Schneider Electric 25- EnergyMONTHLY REVIEW
- case 3: addition ofcommunicating FPIs
R
Put several
communicating
FPIs in strategic
locations
case 4: addition of communicating FPIs and remote
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
26/53
Schneider Electric 26- EnergyMONTHLY REVIEW
- case 4: addition ofcommunicating FPIs and remote
controlled load break switches
RT
TT
T
T remote controlled load breakswitchesCommunicating FPI
5 l d ti li l d b k
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
27/53
Schneider Electric 27- EnergyMONTHLY REVIEW
- case 5: recloser and sectionalizer load break
switches
R
case 5: recloser and
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
28/53
Schneider Electric 28- EnergyMONTHLY REVIEW
- case 5: recloser andsectionalizer load break switches
S1 = opens after ONE reclosing
operation
S2 = opens after TWO reclosing
operations S3 = opens after THREE reclosing
operations
S4 = opens after FOUR reclosingo erations
Sectionaliser load break switches are
always associated with a recloseror circuit
breaker:
case 5: recloser and
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
29/53
Schneider Electric 29- EnergyMONTHLY REVIEW
S4
S3
S3
S2
S1
S2
- case 5: recloser andsectionalizer load break switches
R
Permanent fault
case 5: recloser and
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
30/53
Schneider Electric 30- EnergyMONTHLY REVIEW
S4
S3
S3
S2
S1
2 2
2
S2
- case 5: recloser and
sectionalizer load break switches
R
Permanent fault
case 5: recloser and
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
31/53
Schneider Electric 31- EnergyMONTHLY REVIEW
S4
S3
S3
S2
S1
2 2
2 S2
- case 5: recloser and
sectionalizer load break switches
R
Permanent fault
2
case : rec oser an
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
32/53
Schneider Electric 32- EnergyMONTHLY REVIEW
S4
S3
S3 S2
S2
S1
- case : rec oser ansectionalizer load break switches
R
Permanent fault
2 60
75
%
95
%
f h d k
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
33/53
Schneider Electric 33- EnergyMONTHLY REVIEW
- summary of overhead networks 1/2Permanent fault
95%
Case 2A recloser
+ FPIs3 h
6 h
95%
Case 1
A recloser
95%Case 3
A recloser
+ FPI with Com1h30
f h d k
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
34/53
Schneider Electric 34- EnergyMONTHLY REVIEW
- summary of overhead networks 2/2
Permanent fault
95%
1h2
75 %Case 5
A recloser
and sectionalizers
95%
1
h
10
70 %Case 4: A recloser,
remote controlled
switches
and FPI with Com
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
35/53
Schneider Electric 35- EnergyMONTHLY REVIEW
SAIDI (System Average Interruption Duration Index) can vary from a
few minutes to several hours,
SAIFI (System Average Interruption Frequency Index) can vary from
1to10and more, depending on :
population density (ruralor urbanarea)
proportion between undergroundand overheaddistribution
maximum accepted costsfor non distributed energy
Excellent Average PoorUrban area < 10 mn 30 mn >2 hrs
Rural area < 30 mn 2 hrs >10 hrs
Permanent Interruptions (>1 mn)
SAIDI/SAIFI variationsQuality Power
33/11 KV U d R t
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
36/53
Schneider Electric 36- EnergyMONTHLY REVIEW
33/11 KV Unmanned Remote
Controlled S/s
C t U d R t t ll d 33/11 KV S/ ith
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
37/53
Schneider Electric 37- EnergyMONTHLY REVIEW
Compact, Unmanned, Remote controlled 33/11 KV S/s with
2 transformers each up to 10 MVA.
Half space than a conventional s/s. Economic as very less civil work.
Saving in execution time and costly land in urban areas app.
Remote regular maintenance.
CB,Current & Voltage sensors are life sealed ,insensitive to the environment.
All types of protection OC,EF,UV,OV,OF,UF,DF, measurementKW,KWH,KVArH, data logging and event recording & self diagnostic facility
helps to analyze the system and energy consumption.
Delivers quality power.
Automatic callout to the remote control station in case of predefined critical
alarms. Communication with the remote central control station using GPRS Network
or other media like GSM, 3G, PSTN, Leased Lines, Radio, VSAT etc. using
established and field proven IEC 60870-5-104. Scalable to SCADA.
Sub-station will have a unique aesthetic view in a crowded city.
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
38/53
Schneider Electric 39- EnergyMONTHLY REVIEW
33/11 KV
unmanned
Remotecontrolled s/s
within
25Mx15M
space
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
39/53
Schneider Electric 40- EnergyMONTHLY REVIEW
33/11 KV s/s at Judges Filed Guwahati with 2 Nos. 5 MVA
Transformers.
33/11 KV S/s at Kamakhya Guwahati
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
40/53
Schneider Electric 41- EnergyMONTHLY REVIEW
33/11 KV S/s at Kamakhya, Guwahati
with 2x5MVA Trfr.
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
41/53
Schneider Electric 42- EnergyMONTHLY REVIEW
Unmanned 33/11 KV , 10 MVA s/s at Nalagarh, HP
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
42/53
Schneider Electric 43- EnergyMONTHLY REVIEW
Pole mounted 11 KV Breakers/AR ( Sub station Application)
Channel Mounted 33 KV Breakers (SS Aplication)
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
43/53
Schneider Electric 44- EnergyMONTHLY REVIEW
Channel Mounted 33 KV Breakers (SS Aplication)
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
44/53
Schneider Electric 45- EnergyMONTHLY REVIEW
Typical layout of 33/11 KV s/s with 2 Nos. 5 MVA Trfr.
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
45/53
Schneider Electric 46- EnergyMONTHLY REVIEW
ArchitectureGPRS
Future Substations (up to 30 nos.)
14 LCD
Remote Accessto maintenance
staff
ADSL Line
Substation # 1
Ethernet Switch
Leased Line
BreakerControlCubicle
BreakerControlCubicle
BreakerControlCubicle
BreakerControlCubicle
BreakerControlCubicle
Rs232 toEthernet
Converters(If required)
RS 232or
Ethernet Port
RS 232Nulec Direct
Protocol
RS 232Nulec Direct
Protocol
RS 232Nulec Direct
Protocol
RS 232Nulec Direct
Protocol
1
SEPAMT-87
EnergyMeters
Twisted Pair Cu
CA
T5
RS 485 (Modbus)
2 3 4 n
GPRS Router
Ethernet Switch
Leased Line
CAT
5
GPRS Router
14 LCD
Control Center
ADSL Line
M2MGateway
GPRS Cloud
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
46/53
Schneider Electric 47- EnergyMONTHLY REVIEW
ArchitectureASEB (Judges Field S/S)
GPRS(DHBVNs Scope)
GPRS M2M GatewayLeased Line with Static IP
VPN Tunnel
Nulec Direct TCP/Modbus
VPN Tunnelusing Remote Moblie VPN
WSOS
SMSor
3rd party SCADA
Judges Field S/S
Judges Field S/S
Protocol GatewayTwo way with Dynamic IPs
Service provider independent VPN
Data encryption
Firewall
Scalable to any third party SCADA
33KV Remote controlled VCB substation application
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
47/53
Schneider Electric 48- EnergyMONTHLY REVIEW
33KV Remote controlled VCB- substation application
33KV substation and feeder breaker
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
48/53
Schneider Electric 49- EnergyMONTHLY REVIEW
33 KV b k i 33/11 KV S/S ith 33/11 KV t f
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
49/53
Schneider Electric 50- EnergyMONTHLY REVIEW
33 KV breaker in 33/11 KV S/S with 33/11 KV transformer
33KV outdoor VCB Breaker in Pandav-Nagar ( Delhi)
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
50/53
Schneider Electric 51- EnergyMONTHLY REVIEW
33KV Pole Mounted Breaker protecting a 10 MVA 33/11 KV
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
51/53
Schneider Electric 52- EnergyMONTHLY REVIEW
33KV Pole Mounted Breaker protecting a 10 MVA 33/11 KV
Transformer
M k th t
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
52/53
Schneider Electric 62- EnergyMONTHLY REVIEW
Make the mostof your energy
-
5/21/2018 Schneider PPT - Autorecloser _ Sectionalizer (1)
53/53