sced re-runs: before and after non-spin deployment on july 13 & july 18

12
August 8, 2011 Reliability Deployments Task Force Meeting SCED Re-Runs: Before And After Non-Spin Deployment on July 13 & July 18 John Dumas Director Wholesale Market Operations

Upload: mab

Post on 15-Jan-2016

40 views

Category:

Documents


0 download

DESCRIPTION

SCED Re-Runs: Before And After Non-Spin Deployment on July 13 & July 18. John Dumas Director Wholesale Market Operations. Outline of Presentation. Additional Data from July 13 & 18 Non-Spin Deployment. Results of SCED Re-Run for different “floor” scenarios. Limitations of the SCED Re-Run - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

August 8, 2011

Reliability Deployments Task Force Meeting

SCED Re-Runs: Before And After

Non-Spin Deployment on July 13 & July 18

John DumasDirector Wholesale Market Operations

Page 2: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

2

Outline of Presentation

• Additional Data from July 13 & 18 Non-Spin Deployment.

• Results of SCED Re-Run for different “floor” scenarios.• Limitations of the SCED Re-Run

• QSE actions to submit EOC with floor for Non-Spin

• Summary of the SCED Re-Run

• Observations

August 8, 2011

Page 3: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

3

Additional Data from July 13 Non-Spin Deployment.

July 28, 2011

@14:35 LSL Non-Spin Responsibility“ON” Non-QSGR 2247 649

“OFFNS” Non-QSGR 104 251

“ON” QSGR 433 844

“OFFNS” QSGR 219 291

“OFF” Non-QSGR that came online by 14:55

56 0

“OFF” QSGR that came online by 14:55

144 0

•Note 1: All are telemetry values at 14:35 (before Non-Spin Deployment)

•Note 2: Load increase from 14:35 to 14:55 = 540 MW

•Note 3: LSL injection from OFFNS resources from 14:35 to 14:55 =

219 (“OFFNS” QSGR) + 104 (“OFFNS” Non-QSGR) = 323 MW•Note 4: The total HSL from “OFF” Generation Resources that came online = 248 MW

Page 4: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

4

Additional Data from July 18 Non-Spin Deployment.

July 28, 2011

@14:35 LSL Non-Spin Responsibility“ON” Non-QSGR 1636 738

“OFFNS” Non-QSGR 116 358

“ON” QSGR 258 536

“OFFNS” QSGR 288 368

“OFF” Non-QSGR that came online by 14:55

0 0

“OFF” QSGR that came online by 14:55

0 0

•Note 1: All are telemetry values at 15:20 (before Non-Spin Deployment)

•Note 2: Load increase from 15:20 to 15:55 = 507 MW

•Note 3: LSL injection from OFFNS resources from 15:20 to 15:55 =

288 (“OFFNS” QSGR) + 116 (“OFFNS” Non-QSGR) = 404 MW

Page 5: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

5

Scenarios for SCED Re-Run with different “floors”

August 8, 2011

• For “ON” Generation Resources (QSGR and Non-QSGR), change HASL/HDL calculation to give SCED ability to ALWAYS use capacity reserved for Non-Spin.

• Re-Run SCED with modified EOC for Generation Resources having Non-Spin Responsibility as per the following:

Low FLoor Medium-1 Floor

Medium-2 Floor

High Floor

ONLINE Non-QSGR:HASL to HSL

18*FIP

July13=$79.38July 18=$80.01

$500 $1000 $3000

ONLINE QSGR:(HSL-Non-Spin) to HSL

18*FIP

July13=$79.38July 18=$80.01

$500 $1000 $3000

OFFNS (QSGR & Non-QSGR):LSL to HSL

15*FIP+$120

July13=$186.15July 18=$186.675

$500 $1000 $3000

Page 6: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

6

Results of SCED Re-Run for different “floor” scenarios

August 8, 2011

July 13: FIP=4.41 July 18: FIP=4.445

System Lambda@14:35 Before Non-Spin Deployment

System Lambda@14:55 - After Non-Spin Deployment

System Lambda@15:20 Before Non-Spin Deployment

System Lambda@15:55 - After Non-Spin Deployment

Sum(HDL)-GTBD=459 MW (New)= -7 MW (Original)

Sum(HDL)-GTBD=505 MW (New)=505 MW (Original)

Sum(HDL)-GTBD=335 MW (New)=280 MW (Original)

Sum(HDL)-GTBD=1149 MW (New)=1149 MW(Original)

Original – No change

$2999.99 $76.79 $267.75 $63.35

Original – Only online HASL/HDL changed, NO floor

$92.88 $76.79 $62.54 $63.35

Low Floor $81.28 $83.61 $85.08 $80.92

Med Floor-1$500

$500 $500 $475.57 $80.92

Med Floor-2$1000

$1000 $1000 $968.96 $80.92

High Floor$3000

$3000 $3000 $2968.95 $80.93

Page 7: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

7

Results of SCED Re-Run for different “floor” scenarios

• July 13 : 13:00 – 20:00

August 8, 2011

@14:35GTBD=62261 MW

orig=$2999.99HASL=$92.88low=$81.28med-1=$500med-2=$1000high=$3000

@14:55GTBD=62801 MW

orig=$76.79HASL=$76.79low=$83.61med-1=$500med-2=$1000high=$3000

Page 8: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

8

Results of SCED Re-Run for different “floor” scenarios

• July 18 : 13:00 – 20:00

August 8, 2011

@15:55GTBD=61677 MW

orig=$63.35HASL=$63.35low=$80.92med-1=$80.92med-2=$80.92high=$80.93

Page 9: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

9

Limitations of the SCED Re-Run

August 8, 2011

• In Production, the additional EOC available to SCED after Non-spin deployment pushed down the output of other Generation Resources not carrying any Non-Spin Responsibility.

• The SCED re-runs used the Production telemetered MW. The telemetered MW would have been different if the floor were applied ALL of the time.

Page 10: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

10

QSE actions to submit EOC with floor for Non-Spin

• No change to QSE process of submitting EOC and AS offers to DAM

• No change to QSE process of submitting AS offers to SASM

• QSE will update EOC to incorporate floor before the end of the Adjustment Period.

– With the ability provided by NPRR 321 “Allow Change to Energy Offer Curve MW Amounts in the Adjustment Period”,

August 8, 2011

Page 11: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

11

Summary of the SCED Re-Run

• After Non-Spin deployment, if the “floored” EOC segments are marginal, then the LMPs will be at the floor – i.e. LMPs are administered - by the value of the floor.

• After Non-Spin deployment, if none of the “floored” EOC segments are awarded, then the Generation Resources providing Non-Spin will be at risk of being price-takers at their LDL.

• Floors over or under compensate relative to prices without Non-Spin deployment.

August 8, 2011

Page 12: SCED Re-Runs:  Before And After  Non-Spin Deployment on  July 13 & July 18

12

Observations

• ERCOT did not over deploy Non-Spin on July 13 and July 18.– Sum(HDL)-GTBD <200– Load growth exceeded the remaining Non-Spin deployed

• Is the impact to the Day-Ahead and Real-Time energy price convergence because of permanently allowing SCED to use Non-Spin capacity mitigated by the floor on the Non-Spin segment of the EOC?

• ERCOT procedure to deploy Non-Spin will need to be reviewed if the Non-Spin capacity is permanently made available to SCED.

August 8, 2011