scaldis brochure renewables

Upload: pramodtry

Post on 04-Jun-2018

234 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/14/2019 Scaldis Brochure Renewables

    1/20

    Scaldis: lifting at a higherlevel

    RENEWABLES

  • 8/14/2019 Scaldis Brochure Renewables

    2/20

    From the early offshore renewable days Scaldis has been a key player in the rapidly growing

    sector of renewable energy. Whilst Scaldis served in various disciplines of this market, the

    majority of the works concentrated around the installation of jackets and substations.

    Introduction

    Scaldis: lifting at a higherlevel

    Scaldis executes its offshore activities with two heavy lift vessels, the

    Rambiz (lifting capacity 3,300 tonnes) and Norma (400 tonnes). A third

    heavy lift vessel is presently under construction (lifting capacity 4,000

    tonnes) and will be available as from Q2 2014.

    Our activities include: Transport and installation of concrete foundations/structures, jackets

    and transformer units,

    ROV surveys, piling, levelling, grouting and welding,

    Transportation and installation of metmasts and

    wind turbine generators,

    Transportation and installation of current turbines.

    Picture cover: Beatrice Demonstrator project

    02

  • 8/14/2019 Scaldis Brochure Renewables

    3/20

    Gravity based foundations

    2

    Picture 2: Installation of gravity foundations at

    the Karehamn Wind Farm, Sweden

    Picture 1: Transportation and installation of

    the concrete foundations for theThorntonbank I

    03

    11

  • 8/14/2019 Scaldis Brochure Renewables

    4/20

    Picture 3: Lifting and installation of a sleeved pile jacket

    for the Hasdrubal project

    Picture 4: Lifting and installation of the Walney jacket

    3

    Sleeve pile jackets4

    4

  • 8/14/2019 Scaldis Brochure Renewables

    5/20

    05

    Step 1- Barge loaded with jackets and moored in front of the Rambiz.

    - Jacket is positioned under Rambiz crane hook and rigging

    connected to Rambiz hook.

    Step 3- Barge towed away from Rambiz.

    Step 2- Jacket seafastening disconnected.

    - Jacket lifted free from grillages.

    Step 4- Jacket lowered into the water.

    - Set down at position.

    Sleeve pile jackets

  • 8/14/2019 Scaldis Brochure Renewables

    6/20

    Step 5- Pile is placed into jacket sleeve.

    Step 7- Pile in position.

    - Hammer is removed.

    Step 6- Piling operations.

    Step 8- Piling operations repeated for all sleeves.

    - If necessary levelling operations can be started.

    Sleeve pile jackets6

  • 8/14/2019 Scaldis Brochure Renewables

    7/20

    Picture 5: Installation of the Ormonde jacket

    Picture 6: Installation of the Thornton II jacket

    07

    Pre-piled jackets

    5

    6

  • 8/14/2019 Scaldis Brochure Renewables

    8/20

    Pre-piled jackets8

    Step 1- Barge loaded with jackets and moored in front of Rambiz.

    - Jacket is positioned under Rambiz crane hook and rigging connected

    to Rambiz hook.

    Step 3- Barge towed away from Rambiz.

    Step 2- Jacket seafastening disconnected.

    - Jacket lifted free from grillages.

    Step 4- Jacket lowered into the water above pile location.

  • 8/14/2019 Scaldis Brochure Renewables

    9/20

    09

    Step 5- Jacket is above pre-installed piles by Rambiz.

    - Assistance by survey equipment and ROV monitoring during

    installation.

    Step 7- Jacket is lowered further by Rambiz cranes.

    - ROV monitoring.

    Step 6- The leg with the longeststabbing point is now positioned into the pile

    and lowered, monitoring by ROV.

    - The jacket is lowered by the Rambiz cranes until the second stabbing

    point is into its pile.

    - When the two stabbing points are in position, the jacket will be

    further lowered.

    Step 8- Jacket is lowered until contact has been made between the jacket

    shim plates and the piles.

    - Rigging is disconnected.

    - Grout operations can commence.

    Pre-piled jackets

  • 8/14/2019 Scaldis Brochure Renewables

    10/20

    Substations0

    8

    7

    Picture 7: Installation of Rodsand transformator

    Picture 8: Installation of the Ormonde substation

  • 8/14/2019 Scaldis Brochure Renewables

    11/20

    11

    Picture 9: Installation of the Gundfleet Sandstransformator

    Picture 10: Installation of the Lincs topside

    Picture 11: Installation of the London Array topside

    11

    10

    9

    Substations

  • 8/14/2019 Scaldis Brochure Renewables

    12/20

    2

    Deepwater WTG Installation

    12

    12

    11

    Pictures 12: Beatrice Demonstrator project

    Picture 13: Lifting and upending of a jacket

    1312

  • 8/14/2019 Scaldis Brochure Renewables

    13/20

    13

    Transportation

    14

    15

    Picture 14: Transportation of the Ormonde jackets

    Picture 15: Transportation of jacket, topside and piles

  • 8/14/2019 Scaldis Brochure Renewables

    14/20

    Tidal Energy4

    16

    Picture 16: Lifting, transportation over sea and installation of the SeaGen Tidal Current Generator

  • 8/14/2019 Scaldis Brochure Renewables

    15/20

    15

    Others

    Picture 17: Piling

    Picture 18: Monitoring levelling equipment

    Picture 19: Monitoring grouting activities

    1918

    17

    PILING & LEVELLING & GROUTING

  • 8/14/2019 Scaldis Brochure Renewables

    16/20

    Others6

    Picture 20: Levelling and swaging equipment

    20

  • 8/14/2019 Scaldis Brochure Renewables

    17/20

    17

    SCAFFOLDING & WELDING

    Picture 21: Welding Lincs project

    Picture 22: Scaffolding Lincs project

    22

    21

    Others

  • 8/14/2019 Scaldis Brochure Renewables

    18/20

    C H A R A C T E R I S T I C S R A M B I Z

    Length O.A. 85 m

    Breadth moulded 44 m

    Depth moulded 5.6 m

    Minimum operational draft 3.6 m

    Load capacity 3,300 t hookload

    Distance between crane booms at top 34.10 m

    Propulsion 4 units 2,200 kW, 3,000 Hp total

    Class Lloyds Register of Shipping

    Class notations 100 AT

    AT crane pontoon, LA

    LMC

    Accommodation (beddings) 70 pers.

    Technical information8

  • 8/14/2019 Scaldis Brochure Renewables

    19/20

    19

    Technical information

    C H A R A C T E R I S T I C S H E A V Y L I F T V E S S E L R A M B I Z 4 0 0 0GENERAL PARTICULARS

    Type of vessel Self-propelled Heavy Lift DP II

    Vessel

    Year of construction 2012 2014

    Builders STX/Huisman

    Class Lloyds Register of shipping

    Class Notation 100A1, Crane Ship,

    ShipRight(ACS(B)), LA,

    IWS, LMC, UMS, DP(AA), CAC 3

    Operators SCALDIS-SMC NV

    Flag Belgian

    MAIN DIMENSIONS

    Length overall 108 m

    Breadth moulded 49 m

    Depth moulded 8 m

    Min. Operating draft 4.9 m

    Displacement in operation 22,400 t

    LIFTING CAPACITY

    Portside crane Main hoist 2 x 1000 t

    Auxiliary hoist 2 x 15 t

    Starboard crane Main hoist 2 x 1000 t

    Auxiliary hoist 2 x 15 t

    Tandem liftMax. capacity 4,000 t

    Max. Lift Height 75 m above deck

    Skidding System

    PROPULSION

    Type of propulsion 4 x Azimuth thrusters

    Installed propulsion power aft 2 x 1,720 kW

    Installed propulsion power forward 2 x 1,505 kW

    Sailing speed 7 knots

    TANK CAPACITY

    Fuel oil 1,342 m3

    Fresh water 935 m3

    + 2x FW Generator 20 m3/day

    Water ballast 11,316 m3

    COMMUNICATION

    GMSS A3

    V-SAT (Internet and voip phone facilities)

    Immersat fleet broadband

    ACCOMMODATION/HELICOPTER DECK

    78 persons

    Suitable for a helicopter of type S92

    S

    AFETY EQUIPMENT

    According to SOLAS and ISPS Regulations for 78 persons

    DECK LOAD15 tons/m2

  • 8/14/2019 Scaldis Brochure Renewables

    20/20

    Scaldis: lifting at a higherlevel

    &P

    roduction:

    lu'sparagraph

    RENEWABLES