sc project review of ncsx wbs5 - central controls and computing august 15-17, 2007 wbs5 manager:...

20
SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

Upload: veronica-turner

Post on 26-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Project Review of NCSX

WBS5 - Central Controls and Computing

August 15-17, 2007

WBS5 Manager: Paul Sichta

Page 2: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page2

WBS5 Elements

NCSX Central Controls and Computing will provide the equipment and services for: 1) integrated and remote control; 2) data acquisition, analysis, and storage; 3) facility timing and synchronization; 4) central safety and interlocks.

• Network and Fiber Optic Infrastructure (WBS 51)

• Central Instrumentation and Control (WBS 52)

• Data Acquisition and Facility Computing (WBS 53)

• Facility Timing and Synchronization (WBS 54)

• Real Time Plasma and Power Supply Control (WBS 55)

• Central Safety and Interlock System (WBS 56)

• Control Room Facility (WBS 57)

Page 3: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page3

NCSX Computing Overview

OPIsOPIsOPIsOPIs

OPIsOPIs

workstations

Diagnostics VLAN

NCSXMDSplus ServerSAN

Tape Archive

PPPL Network

Timing & SyncSystems

Diagnostics:•Magnetics•Visible Camera•E-Beam

PPPLCore Switch &

Internal Firewalls

HIGH PERFORMANCE FIBER CHANNEL

Offices

Control Systems VLAN

EPICS

EngineeringComputingSystems

NCSXComputing

Pool

4/20/07 PS

PLC VLAN

PLC

ProgrammableLogic

Controllers

wwwoffsite

collaborators

PPPLFirewall

Page 4: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page4

Budget Partition

WBS5 Resources

WBS5 Budget $ 1.1 M WBS54 T&S

WBS53DAS

WBS55 PCS

WBS56CSIS

WBS52CI&C

WBS51Network

Softwr/Elec Engineers: 2.4 yearsElec/Mech/Draft Techs: 1.6 years‘Materials & Services’: $ 211 K

Page 5: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page5

WBS5 Schedule

• Tasks: PDR, FDR, Fabricate, Install, PreOp Test

Page 6: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page6

Basis of Estimate

• Labor:– NSTX first plasma effort.– personal experience.– ~25% for ‘green’, mentored engineering talent.– field estimates (e.g. Eric Perry).

• M&S – recent purchases of similar equipment.– current catalog prices.

• Design Complexity & Maturity – The systems are generally based upon the existing NSTX

design, so complexity is relatively low. However, the current workscope has neither Preliminary or Final design.

Page 7: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page7

WBS 51 – Networking & Fiber Optic Infrastructure

• an infrastructure of fiber optic cables that connect the main experimental areas. All WBS can use these.

• conventional (tcp/ip) networking equipment such as switches and routers and wireless-access-points (WAP).

Page 8: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page8

WBS 51- Cost & Schedule Detail

Labor Engineering: 160 hours

Technician: 770 hours

M&S

Contingency & Risk

Design Maturity: Medium

Design Complexity: Low

Uncertainty Range: -10%/+15%

M&S Details: K$Switches $15.0KNCSX_TC WAP $5.0Kmedia converters 6) $1.8KTerminations, F/O patch panels & cable mgmt., patch cables

$7.0K

Fiber Optic cable $5.0Kmisc. $10.0K

Total M&S $43.8K

Page 9: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page9

WBS 52 – Central Instrumentation and Controls

• Supervisory and integrated control of NCSX engineering subsystems and diagnostics.

• Like NSTX, will use the EPICS software.

• System provides data trending, alarm logging, operator displays, and integrated process control and monitoring functions for NCSX.

• NCSX Test Cell audio and video support.

Page 10: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page10

WBS 52- Cost & Schedule Detail

Labor Engineering: 720 hours

Technician: 460 hours

M&S

Contingency & Risk

Design Maturity: Medium

Design Complexity: Low

Uncertainty Range: -10%/+15%

M&S Details: K$Travel/training $2.0KNTC web cam (4) $3.0KPC - appl. TBD (2) $6.0KLinux soft IOC (2) $3.0KOPC client & server HW/SW/TRNG (for T/C) $10.0KEPICS server $8.0KEPICS gateway (use NSTX) $0.0Kmisc $10.0K

Total M&S $42.0K

Page 11: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page11

WBS 53 – Data Acquisition and Facility Computing

•Automated pre-shot device configuration and post-shot data acquisition.

•Like NSTX, will use the MDSplus software.

•A software infrastructure to catalog and manage experimental data for subsequent retrieval and analysis.

•A pool of computers for data analysis.

•An Applications Program Interface (API) for commonly used software, such as C, IDL, Matlab, LabVIEW, and EPICS.

Page 12: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page12

WBS 53- Cost & Schedule Detail

Labor Engineering: 820 hours

Technician: 80 hours

M&S

Contingency & Risk

Design Maturity: Medium

Design Complexity: Low

Uncertainty Range: -10%/+15%

M&S Details: K$Linux MDSplus Server $3.0KSAN - disk space (500 GB) $6.0Kmisc. $3.0KPC appl. TBD $10.0K

Total M&S $22.0K

Page 13: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page13

WBS 54 – Timing and Synchronization

The Facility Timing and Synchronization System (T&S) will provide the hardware and software that facilitates the synchronization of hardware and equipment to the ‘microsecond’ degree, and computer programs on NCSX computers to the ‘seconds’ degree.

The T&S requirements include:• Local timing resolution of 100 nanoseconds, complex-wide

synchronism < 10 microseconds.• Support 64 hardware events.• Timing signals are low voltage, high speed, and electrically isolated,

equivalent to TFTR and NSTX.

Generation_1 of the event decoder has been in use on NSTX for several years.

Page 14: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page14

WBS 54- Cost & Schedule Detail

Labor Engineering: 760 hours

Technician: 560 hours

M&S

Contingency & Risk

Design Maturity: Medium

Design Complexity: Medium

Uncertainty Range: -15%/+25%

M&S Details: K$Central Clock (PC, timers, SW)Complete prototype UNT (Universal Timer) $3KDesign & fab proto fiber optic xmit $10KUNT Production (10 units) $10K

Clock Distribution modules production (6 units) $6Kmisc $5K

Total M&S $34K

Page 15: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page15

WBS 55 – Real Time Plasma and Power Supply Control

For CD-4/MIE, the control system must provide synchronized control signals for the (approx.) seven NCSX power supplies, and one gas injector.

• The control methodology will be open-loop; no feedback will be used to determine the computer’s outputs.

• WBS4 will specify the detailed requirements and algorithms for power supply control. WBS2 will provide the detailed requirements for gas injection control.

• A standard PC/LabVIEW-based system architecture will be used to fulfill the WBS55 systems.

Page 16: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page16

WBS 55- Cost & Schedule Detail

Labor Engineering: 620 hours

Technician: 104 hours

M&S

Contingency & Risk

Design Maturity: Medium

Design Complexity: Low

Uncertainty Range: -10%/+15%

M&S Details: K$PC/LabVIEW control of C-Site Power Supplies $13.0KPC/LabVIEW control of Gas Injection $10.5Kmisc. $2.0K

Total M&S $25.5K

Page 17: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page17

WBS 56 – Central Safety and Interlock System

The Central Safety Interlock System (CSIS) will provide system wide coordination of personnel and hardware interlocks.

• Each NCSX high-energy (or otherwise hazardous) entity will interface with the CSIS. The high-energy subsystem will be responsible for ensuring that the design of its (local) interlocks and safety features are adequate.

• The CSIS will provide a global E-Stop system, permitting individuals the ability to shutdown all hazardous equipment using E-Stop pushbuttons located throughout the NCSX complex.

• An Access Control System will be incorporated to control access into hazardous areas, such as the Test Cell. Entry into these areas while “unsafe” will cause an automatic E-Stop.

• The CSIS will provide the NCSX Chief Operation Engineer (COE) with a centralized point of control to enable/disable, arm/disarm, and shutdown each NCSX high-energy (or otherwise hazardous) subsystem

• The CSIS M&S costs estimates are based on a cursory review of online pricing. A system configuration, parts list, and price quotes have not been developed.

Page 18: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page18

WBS 56- Cost & Schedule Detail

Basis of Estimate

This estimate is based upon a conceptual design for an off-the-shelf Safety-class Programmable Logic Controller (Safety PLC).

Contingency & Risk

Design Maturity: Low

Design Complexity: Low

Uncertainty Range: -15%/+25%

Labor Engineering: 600 hours

Technician: 840 hours

M&S $44 K for Safety PLC, I/O, communications, software, training, and installation. A price-quote has not been obtained.

Page 19: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page19

WBS 57 – Control Room Facility

• The Control Room will support PPPL physicists, engineers, and collaborators. The former PLT and PBX control rooms are approximately 2200 sq. ft. and will be used as the NCSX main control room.

– For CD-4/MIE, WBS 5 will provide approximately six surplus office-style tables and chairs.

• The Computing Center will hold the bulk of networking equipment, NCSX server computers, and will be a fiber optic cable hub location for the WBS51 fiber optic cable infrastructure. Approximately 1200 sq. ft. of the former PLT DAS computer area will be used as the NCSX Computing Center.

A ‘normal’ Control Room Facility will not be provided for CD-4/MIE. However, facilities such as lighting, power, fire suppression, HVAC, basic network communications, and telephones will be provided (not part of the NCSX workscope). The extent to which the Control Room Facility will be outfitted under GPP (as a general-use area) is unclear at this time. GPP planning is in-process.

Page 20: SC Project Review of NCSX WBS5 - Central Controls and Computing August 15-17, 2007 WBS5 Manager: Paul Sichta

SC Review, WBS5 Central Controls and Computing Page20

SummaryThe similarity to NSTX’s central controls and

computing and the availability of an experienced and technically diverse staff provides confidence

that WBS5 can effectively support the NCSX project.

•The remaining work has generally been identified. The effort that leads to the Final Design Reviews will produce the best estimate.

•Simultaneously supporting two ‘large’ machines (NSTX, NCSX) is ‘new ground’ for the computer engineering staff. This situation presents a potential for impacting WBS5 schedule performance.

•WBS5’s workscope and cost have been substantially reduced since the NCSX CDR (2002) and PDR (2003). Although the M&S costs could be further reduced, doing so would lessen the effectiveness of the staff which would tend to increase the labor costs.